Comparison of Variation Clauses

Embed Size (px)

DESCRIPTION

variation clauses comparison

Citation preview

  • 1 | P a g e S e n g H a n s e n 2 / 2 0 1 2

    Comparison of Variation Clauses in Traditional Procurement

    (PWD 203A 2010) and Design-Build Procurement (PWD DB 2010)

    Seng Hansen

    Master Student of Construction Contract Management UTM

    Email: [email protected]

    Introduction: What is Variation?

    Almost all construction contracts have included variation clauses as the

    standard provisions in the contract. We can find them in international as well

    as national standard forms of contract. We can also find them in different types

    of procurement such as traditional, design and build, management contracting,

    EPC, etc. Even in bespoke or domestic contracts, there must be variation

    clauses which entitle the employers to impose the contractors an obligation to

    change the scope of the work during construction stage which subsequently

    cause the contract sum to be adjusted either up or down by such variation. As a

    result, the contractors are entitled for the variations in their payment

    certificates.

    Each standard form of contract gives its own definition on variation. However, in

    general variation can be defined as the alteration or modification to the basis

    upon which the contract was let. It is a famous term known to be inevitable in

    any construction project due to the changing nature of construction projects.

    Powell-Smith (1990) mentioned that in the absence of variation clauses, the

    employers or architects would have no power to request to the contractors to

    make any changes in the work that they have agreed to do. In other words,

    without variations clauses, the employers and his representatives do not have

    the power to order variations to the contractors.

    Beside the above main purpose, variation clauses are made to serve the

    contractors right to seek a claim due to variations, to provide a mechanism for

  • 2 | P a g e S e n g H a n s e n 2 / 2 0 1 2

    limiting the variations scope, to provide a procedure for variation process, and

    to provide a mechanism for the valuation of variations.

    Understanding of variation clauses is very important since variations are the

    major cause of many problems and disputes in construction industry. They

    influence the two major aspects in construction projects: time and cost. If the

    variations do not handled carefully, they may end up in delay of construction

    time period and cause cost overrun. The magnitude of variations effects are of

    course influenced by many factors, including the employers characteristics,

    project characteristics, project organization and environmental factors.

    This paper is talking about the comparison of variation clauses between

    traditional and design-build procurement systems with reference to PWD

    standard forms of contract which are published by the Malaysia Public Works

    Department. Before we move on to the comparison issue, it will be better if we

    briefly discuss the nature of traditional and design-build procurement systems.

    The Nature of Traditional and Design-Build Procurement Systems

    Under conventional/traditional procurement system, design should be

    completed before competitive tenders are invited and before the contract is

    executed. Assuming that there will be less changes introduce during the

    construction period, construction costs can be determined with reasonable

    certainty. The responsibility of both parties is determined clearly. The

    contractors responsibility includes all financial and other risks during

    construction period, whilst the employers take the responsibility and risk for the

    design. The employers also have the ability to influence the development of the

    design to meet their requirements. Moreover, they usually will have the ability to

    influence the construction process through their representatives such as S.Os.

    or architects acting as their agents.

    While on another hand, design and build procurement system is a fast-track

    strategy. Construction can start before all the detailed design is completed, but

  • 3 | P a g e S e n g H a n s e n 2 / 2 0 1 2

    at the contractors risk. Under a design and build strategy, a single contractor

    assumes the risk and responsibility for designing and building the project, in

    return for a fixed-price lump sum. It is very important, therefore, that the brief

    and performance or quality specifications for important requirements in the

    project are fully and unambiguously defined before entering into this type of

    contract. If requirements are not specific, the employers should provide

    contractors with a performance specification at tender stage. The contractors

    develop the design from the specification, submitting detailed proposals to the

    employers in order to establish that they are in accordance with the

    requirements of the specification. The employers are, therefore, in a strong

    position to ensure that their interpretation of the specification takes preference

    over the contractors. Specification is a risky area for inexperienced employers.

    Moreover, the contractors have a legal duty to provide the employers with a

    project that is fit for its purpose.

    Variation Clauses in PWD 203A 2010 (Traditional Procurement)

    There are two clauses related directly with Variations; i.e. clause 24 and 25.

    24.0 VARIATIONS

    Employer Contractor

    Traditional Procurement

    Design and Build Procurement

    Risk Allocation

    Financing Approvals Design Procurement Construction Maintenance Fit Out

    PWD 203A

    PWD DB

    Scope of Contractors Activities

  • 4 | P a g e S e n g H a n s e n 2 / 2 0 1 2

    24.1 The S.O. may issue instructions requiring a Variation in a form of a

    Variation Order. No variation required by the S.O. shall vitiate this

    Contract. Upon the issuance of such Variation Order, the Contractor shall

    forthwith comply with the Variation Order issued by the S.O.

    24.2 The term Variation means a change in the Contract Document which

    necessitates the alteration or modification of the design, quality or

    quantity of the Works as described by or referred to therein and affects

    the Contract Sum, including:

    (a) the addition, omission or substitution of any work;

    (b) the alteration of the kind or standard of any of the materials, goods

    to be used in the Works; or

    (c) the removal from the Site of any work executed or materials or

    goods brought thereon by the Contractor for the purposes of the

    Works other than work, materials or goods which are not in

    accordance with this Contract.

    25.0 VALUATION OF VARIATION

    25.1 All variations instructed in writing by the S.O. in accordance with clause

    24 hereof shall be measured and valued by the S.O. The valuation of

    Variations, unless previously or otherwise agreed, shall be made in

    accordance with the following rules:

    (a) the rates in the Bills of Quantities after adjustment if necessary as

    provided in clauses 26.6 and 26.7 hereof, shall determine the

    valuation of work of similar character and executed under similar

    conditions as work priced therein;

    (b) the said rates, where work is not of similar character or executed

    under similar conditions as aforesaid, shall be the basis of rates for

    the same, so far as may be reasonable, failing which a fair valuation

    thereof shall be made by the S.O.;

    (c) the rates in the Bills of Quantities shall determine the valuation of

    items omitted, PROVIDED THAT if the omission substantially vary

    the conditions under which any remaining items of work are carried

    out, the rates of such remaining items shall be valued under rule

    (b);

  • 5 | P a g e S e n g H a n s e n 2 / 2 0 1 2

    25.2 Where work cannot properly be measured or valued, the S.O. may allow

    daywork price as specified in Appendix. Unless otherwise provided in the

    Bills of Quantities, the daywork prices for the purpose of this Contract

    shall be taken to mean the actual net cost to the Contractor of his

    materials, plant and labour for the work concerned. The Contractor shall

    be paid daywork prices, plus fifteen percent (15%), which shall include for

    the cost of all ordinary plant, tools, scaffolding, supervision and profit.

    PROVIDED ALWAYS that as a condition precedent to any right to any

    payment the Contractor shall produce vouchers, receipts and wage books

    specifying the time for labour and plant employed and materials used to

    the S.O. not exceeding seven (7) days after the work shall have been done.

    25.3 The amount of variations shall be certified by the S.O. and added to or

    deducted from the Contract Sum as the case may be and the amount

    shall be adjusted accordingly.

    Variation Clauses in PWD DB 2010 (Design and Build Procurement)

    There are two clauses related directly with Variations; i.e. clause 23 and 24.

    23.0 VARIATIONS

    23.1 The term variation means a change in the Governments Requirements

    which makes necessary the alteration or modification of the design,

    quality or quantity of the Works as described by or referred to therein and

    affects the Contract Sum, including:

    (a) the addition, omission or substitution of any work,

    (b) the alteration of the kind or standard of any of the materials, goods

    to be used in the Works; and

    (c) the removal from the Site of any work executed or materials or

    goods brought thereon by the Contractor for the purposes of the

    Works other than work, materials or goods which are not in

    accordance with this Contract.

    23.2 The P.D may issue instructions effecting a variation by way of a Variation

    Order. The Contractor shall forthwith comply with the Variation Order. No

    variation instructed by the P.D under this clause shall in any way vitiate

  • 6 | P a g e S e n g H a n s e n 2 / 2 0 1 2

    or invalidate the Contract but the fair and reasonable value (if any) of all

    such variations shall be taken into account in ascertaining the amount of

    the Contract Sum, unless such variation is necessitated by the

    Contractors default. PROVIDED THAT any variation which alters or

    modifies the design of the Works shall be with the consent of the

    Contractor, whose consent shall not be unreasonably delayed or withheld.

    23.3 Notwithstanding clause 23.2, if in the opinion of the P.D the variation is

    necessary for the purpose of suitability, functionality and safety of the

    Works, the Contractor shall effect the variations. For the purpose of this

    clause, what constitutes suitability, functionality and safety of the

    Works shall be solely determined by the P.D and such determination

    shall for all intents and purposes be final and conclusive. Notwithstanding

    thereto the Contractor shall remain responsible for the design of the

    works as provided under clause 14.

    23.4 Where a variation under clause 23.3 results in extra cost, the said extra

    cost shall be borne by the Contractor. However, if the variation results in

    a reduction in cost, the Contract Sum shall be accordingly reduced.

    23.5 Any variations made under this clause shall not relieve the Contractor of

    his obligations under clause 14.1(a).

    24.0 VALUATION OF VARIATIONS

    24.1 The valuation of additional or substituted work shall be consistent with

    the value of works of similar character set out in the Contract Sum

    Analysis or Contract Schedule of Rates, making due allowance for any

    change in the conditions under which the work is carried out or any

    significant change in the quantity of the work so set out. Where there is

    no work of a similar character set out in the Contract Sum Analysis or

    Contract Schedule of Rates a valuation shall be made by the P.D.

    24.2 The valuation of the omission of work shall be in accordance with the

    values in the Contract Sum Analysis or Contract Schedule of Rates.

    24.3 Any valuation of work under clause 24.1 and 24.2 shall include allowance

    for any necessary addition to or reduction of the Site administration, Site

    facilities and temporary works.

  • 7 | P a g e S e n g H a n s e n 2 / 2 0 1 2

    24.4 Where an appropriate basis of a valuation of additional or substitutes

    work is Day work, the valuation shall comprise the prime cost of such

    work plus 15% which shall include the provision of Site administration,

    Site facilities and temporary works and for profit. PROVIDED THAT as a

    condition precedent to any right to any payment the Contractor shall

    produce vouchers specifying the time daily spent upon the work, the

    workmens names, the plant and the materials employed to the P.D for

    verification not exceeding seven (7) days after the work has been executed.

    24.5 The valuation made under this clause shall not include any claims for

    direct loss or expense notwithstanding that such variation affects the

    regular progress of the Works.

    24.6 Upon determination of the valuation of the variation, the Contract Sum

    shall be revised accordingly by way of addition or deduction.

    Comparison of Variation Clauses in PWD 203A and PWD DB 2010

  • 8 | P a g e S e n g H a n s e n 2 / 2 0 1 2

    Scope of Variation Item/ClausePWD 203A

    2010PWD DB 2010

    S.O. (P.D) issuing the instructions 24.1 23.2

    No variation shall vitiate the contract 24.1 23.2

    The contractor shall comply with the VO 24.1 23.2

    Alteration of modification of the design, quality or quantity of the works 24.2 23.1

    Addition, omission or substitution of any work 24.2(a) 23.1(a)

    Alteration of the kind or standard of any of the materials, goods to be

    used in the Works24.2(b) 23.1(b)

    Removal from the Site of any work executed or materials or goods

    brought thereon by the Contractor for the purposes of the Works other

    than work, materials or goods which are not in accordance with this

    Contract

    24.2(c) 23.1(c)

    A change in the employer's or government's requirements - 23.1

    Fair and reasonable value (if any) of all such variations shall be taken into

    account in ascertaining the amount of the contract sum, unless such

    variation is necessitate by the contractor's default

    - 23.2

    Any variation which alters or modifies the design of the Works shall be

    with the consent of the Contractor, whose consent shall not be

    unreasonably delayed or withheld.

    - 23.2

  • 9 | P a g e S e n g H a n s e n 2 / 2 0 1 2

    Scope of Variation Item/ClausePWD 203A

    2010PWD DB 2010

    The Contractor shall effect the variations if in the opinion of the P.D the

    variation is necessary for the purpose of suitability, functionality and

    safety of the Works

    - 23.3

    Where a variation under clause 23.3 results in extra cost, the said extra

    cost shall be borne by the Contractor. However, if the variation results in

    a reduction in cost, the Contract Sum shall be accordingly reduced

    - 23.4

    Any variations made under this clause shall not relieve the Contractor of

    his obligations under clause 14.1(a): contractor's responsibility for design,

    execution and maintenance of the Works

    - 23.5

    The valuation shall be made by the S.O. (P.D) 25.1 24.1

    The valuation of work of similar character and executed under similar

    conditions as work priced therein25.1(a) 24.1

    The valuation of work of not of similar character or executed under

    similar conditions as aforesaid25.1(b) 24.1

    The valuation of items omitted 25.1(c) 24.2

    Any valuation of work shall include allowance for any necessary addition

    to or reduction of the Site administration, Site facilities and temporary

    works

    - 24.3

    The Contractor shall be paid daywork prices, plus fifteen percent (15%) 25.2 24.4

    The Contractor shall produce vouchers, receipts and wage books

    specifying the time for labour and plant employed and materials used to

    the S.O. not exceeding seven (7) days after the work shall have been done

    25.2 24.2

    The valuation shall not include any claims for direct loss or expense

    notwithstanding that such variation affects the regular progress of the

    Works

    - 24.5

    The amount of variations shall be certified and added to or deducted

    from the Contract Sum as the case may be and the amount shall be

    adjusted accordingly

    25.3 24.6

  • 10 | P a g e S e n g H a n s e n 2 / 2 0 1 2

    Conclusion

    Almost all standard forms of construction contract provide for variation or

    change orders clauses. They include the definitions as well as the rules for the

    valuation of variations. Although PWD 203A 2010 (traditional procurement

    system) and PWD DB 2010 (design and build procurement system) are different

    in their nature of project delivery system and risk allocation, both still have

    similar provisions of variations in many aspects.

    From the above comparison, we may conclude that the items of variation

    clauses in PWD DB is more than those in PWD 203A. In my opinion, this may

    happen since the nature of design and build procurement which tends to give

    all responsibility to the contractors. Unlike in traditional procurement where the

    employers may issue any variation instruction easily, in design and build, by

    nature the design is in the contractors responsibility. Therefore, the employer

    does not have flexibility in changing design as much as in the traditional

    procurement system.

    Despites this, both standard forms of contract have many similarities rather

    than differences. The differences are more on the procedural aspects, while the

    main concept is still the same.

    We also may conclude that in order to be valid, variations should be in writing

    and fulfill the principle of variations. The case of Thorn v Mayor and

    Commonalty of London and [1876] 1 App Cas 120 and Blue Circle

    Industries v Holland Dredging Co [1987] 37 BLR 40, are both discussed

    about the invalid additional work of variation. Harban Singh (2003) also

    explains that if the variation order be substantially different, either materially in

    excess of the agreed sum or fundamentally changes the nature of the works,

    such a variation work would be contractually invalid. This statement can be

    seen in the case of Sir Lindsay Parkinson and co Ltd v Commissioners of

    His Majestys Works and Public Buildings [1949] 2 K.B. 623 and Wegan

    Construction Pty Ltd v Wodonga Sewerage Authority [1978] VR 67.

  • 11 | P a g e S e n g H a n s e n 2 / 2 0 1 2

    All variation works also must exclude any changes which are intended to rectify

    any negligence or default by the contractor. If there are such changes, then the

    contractor should entirely bear the cost at his own expenditure.

    References

    Entrusty Group. What Constitute Variations and How to Evaluate Them?. Master

    Builder 4th Quarterly 2008. Page 82-92.

    Heng Wei Kiong, R. 2009. Variation Orders in Design and Build Contracts. M.Sc.

    Universiti Teknologi Malaysia.

    PWD FORM 203A (Rev. 1/2010)

    PWD FORM DB (Rev. 1/2010)