18
2002-2003 AE Senior Thesis Allison M Clarke Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Comparison of Air Distribution Comparison of Air Distribution Systems Systems Underfloor Air vs. Ceiling-Based Systems 2002-2003 AE Senior Thesis Allison M Clarke Capital One Northern Virginia Campus Consolidation Capital One Northern Virginia Campus Consolidation McLean, VA McLean, VA Presentation Outline Existing Building & Systems Underfloor Air Distribution Ceiling-Based System Comparison Conclusion & Recommendations Introduction Existing Building & Systems Underfloor Air System Ceiling-Based System Comparison Recommendation Conclusions

Comparison of Air Distribution Systems

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Comparison of Air Distribution Systems

1

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Comparison of Air Distribution Comparison of Air Distribution SystemsSystemsUnderfloor Air

vs.Ceiling-Based Systems

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Presentation OutlineExisting Building & SystemsUnderfloor Air DistributionCeiling-Based SystemComparisonConclusion & Recommendations

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Page 2: Comparison of Air Distribution Systems

2

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Project TeamOwner - Capital One Financial Corporation

Owner’s Rep - Jones Lang LaSalle

Architect - Ai Architecture

GC - James G. DAVIS Construction

Structural Engr - Rathgeber/Goss Associates

MEP Engr - Ai Engineering

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

ArchitectureIntroduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Page 3: Comparison of Air Distribution Systems

3

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Location & Site1600 Scotts Crossing Road McLean, VA26 AcresBorders I-495 Capital Beltway

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

StructureBase Building – Floors 1 & 2

Cast-in-Place Concrete with Post Tension BeamsTower – Floors 3 – 14

Steel StructureConcrete Slab on Metal Deck18” Raised Concrete CoreTypical Floor Space

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

MechanicalUnderfloor Air Distribution System in TowerFour 600 ton Chillers4-Cell Cooling TowerTwo 22,000 cfm AHU’s per Typical Floor

Page 4: Comparison of Air Distribution Systems

4

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Underfloor Air DistributionBackground InformationSystem ComponentsConstruction Methods/ScheduleEnergy UseCostsLessons Learned

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Background InformationAlternative to conventional ceiling-based air distribution systemsPreviously used for spaces with high heat loadsIntroduces air at floor level

Occupied Zone – floor to head levelUnoccupied Zone – head level to ceiling

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

ConclusionsOccupied Zone

Unoccupied Zone

Page 5: Comparison of Air Distribution Systems

5

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Background InformationBenefits

Improved thermal comfort for occupantsImproved ventilation efficiency & indoor air qualityReduced energy use from mechanical systemsReduced life cycle building costsReduced floor-to-floor height in new constructionImproved occupant satisfaction and productivity

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Background InformationBarriers

New & unfamiliar technologyPerceived higher costsLack of information & design guidelinesLimited applicability to retrofit constructionProblems with applicable standards & codesProblems with spillage and dirt entering underfloor plenumConcerns of condensation and dehumidification problems

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Page 6: Comparison of Air Distribution Systems

6

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

System ComponentsTypical Floor

Two 22,000 cfm AHU’s28 fan powered terminal boxes supply perimeterStatic pressure sensors22,500 sf Access floor panelsPassive & VAV floor diffusers

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Source: Tate Access Floors

Typical Mechanical Room Section

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Construction Methods/ScheduleLocal Jurisdiction Code Requirements

Underfloor is a plenum

Supply Air DiffusersRedundant installation

Underfloor Air SpaceMoisture concerns

Above Ceiling Air SpaceSuspended ceiling not absolutely necessary

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Page 7: Comparison of Air Distribution Systems

7

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Construction Methods/ScheduleTypical Floor Schedule

219 Work Days

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Construction Methods/ScheduleTower Schedule

289 Work Days

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Page 8: Comparison of Air Distribution Systems

8

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Energy UseTypical Floor Design Loads

72060

Total Tower Load(tons)

Typical Floor Load(tons)

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Design Load Distribution

39%

29%

14%

10%

8% OA Load (tons)

Lighting Load(tons)Equipment Load(tons)Envelope Load(tons)Occupant Load(tons)

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Energy UseAnnual Energy Consumption

Binmaker Weather Data3,120 hours

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

701,35258,446Total Ton-hours

Total TowerTypical Floor

Page 9: Comparison of Air Distribution Systems

9

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

CostConstruction Costs

$ 13.66 per square foot $ 5,136,160 Tower Cost

Operating CostsEnergy Consumption 2,912,721 kWhAnnual Cost $ 206,803

Lifecycle Cost30 years $ 9,084,118

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Lessons LearnedMoisture detection in underfloor plenum

Outdoor air load oversized20 cfm/occupant needed43 cfm/occupant used

“Green” technologyRecognized by USGBC

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Page 10: Comparison of Air Distribution Systems

10

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Ceiling-Based System• Background Information• System Components• Construction Methods/Schedule• Energy Use• Costs• Lessons Learned

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Background InformationTraditional approach to HVAC designAir supplied & returned at ceiling

Conditions entire space

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

ConclusionsConditioned Space

Page 11: Comparison of Air Distribution Systems

11

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Background InformationBenefits

Designers & contractors more familiarCheaper to buildAvailable standards & codesSuspended ceiling systems made access easierCurrently found in most U.S. buildings

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Background InformationBarriers

No individual controlExpensive to modify or reconfigureCan be noisyUsually cramped into ceiling plenum with other systems

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Page 12: Comparison of Air Distribution Systems

12

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

System ComponentsTypical Floor

Two 22,000 cfm AHU’sVAV box & thermostat controlled zones

Perimeter zonesInterior zones

Ducted supply, return air plenum

Source: Trane

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Construction Methods/ScheduleTypical Floor Schedule

181 Work Days

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Page 13: Comparison of Air Distribution Systems

13

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Construction Methods/ScheduleTower Schedule

290 Work Days

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Energy UseTypical Floor Design Loads

72060

Total Tower Load(tons)

Typical Floor Load(tons)

Design Load Distribution

39%

29%

14%

10%

8% OA Load (tons)

Lighting Load(tons)Equipment Load(tons)Envelope Load(tons)Occupant Load(tons)

Page 14: Comparison of Air Distribution Systems

14

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Energy UseAnnual Energy Consumption

Binmaker Weather Data3,120 hours

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

701,35258,446Total Ton-hours

Total TowerTypical Floor

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

CostConstruction Costs

$ 10.18 per square foot $ 3,827,680 Tower Cost

Operating CostsEnergy Consumption 3,470,577 kWhAnnual Cost $ 246,410

Lifecycle Cost30 years $ 8,531,753

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Page 15: Comparison of Air Distribution Systems

15

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Lessons LearnedMajor mechanical equipment are correct sizes

Due to underfloor system being oversized

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

ComparisonIntroduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions$ 3,827,680$ 246,410$ 8,531,753

$ 5,136,160$ 206,803$ 9,084,118

Costs:ConstructionOperatingLifecycle

3,470,577 kWh2,912,721 kWhEnergy Use

181 work days290 work days

219 work days289 work days

Construction Schedule:Typical Floor12 Floors

Two AHU’s/floorSupply ductControl zones

Two AHU’s/floorAccess floor panelsSwirl diffusers

System Components

Ceiling-Based System

Underfloor System

Page 16: Comparison of Air Distribution Systems

16

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

RecommendationDedicate chiller plant equipment to areas utilizing underfloor air

distribution

Two systems:Base building – Floors 1 & 2

Supply air temperature at 58˚FTower – Floors 3 – 14

Supply air temperature at 65˚F

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

RecommendationReduction in Cooling Coil Load

Underfloor system requires almost ½ the load

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Underfloor System:

Load = (1.08) x (44,000cfm) x (77-65F) / (12,000 Btu/hr/ton)

Load = 48 tons

Ceiling-Based System:

Load = (1.08) x (44,000cfm) x (77-55F) / (12,000 Btu/hr/ton)

Load = 87 tons

Page 17: Comparison of Air Distribution Systems

17

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Recommendation“Snowball Effect”

Cooling Coil Load Decreases

Air Handling Unit Size Decreases

Chiller Size Decreases

Less Cooling Water Needed / Lower GPM

Smaller Pumps

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Conclusions

Underfloor air distribution system

Easy to reconfigure office spaceMore productive workersPotential for energy savings

Future phases of project use design changes

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

Page 18: Comparison of Air Distribution Systems

18

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

Acknowledgements

DAVIS ConstructionRon Juban, Bill Moyer, Josh Peters, Mike Pittsman

AE FacultyDr. Messner, Prof. Freihaut, Jonathan Dougherty

My ClassmatesEspecially Becky & Joe

Introduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions

2002-2003 AE Senior Thesis Allison M Clarke

Capital One Northern Virginia Campus ConsolidationCapital One Northern Virginia Campus ConsolidationMcLean, VAMcLean, VA

QuestionsIntroduction

Existing Building & Systems

Underfloor Air System

Ceiling-Based System

Comparison

Recommendation

Conclusions