Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
WASH Emergency Response Project
Building Foundation for Development
1
Integrated WASH and C4D Intervention in
Al Jawf and Sa’ada Governorates (2018-2019)
، مديرية المراشي، محافظة الجوفقرية الضلعةمشروع
CO
MP
AN
Y
775999151 / 8006565
- Mohammad Al-Sanabani
- Ahmed Yahya
- Abdulsalam Al-Asad
Reported by: Akram Al-Thari
FINAL REPORT
Reviewed by:
WASH Emergency Response Project
Building Foundation for Development
2
Table of Contents
1 Executive Summary .............................................................................................................. 3
2 Water and Solar Energy System Indicators ....................................................................... 4
3 Background and Coordinates .............................................................................................. 5
4 Target Group and # of Beneficiaries ................................................................................... 5
5 Project Phases ....................................................................................................................... 5
5.1 Field Visits ........................................................................................................................... 6
5.2 The technical studies and designs of the project ................................................................... 6
5.3 Cleaning the borehole ........................................................................................................... 8
5.4 Pumping test ......................................................................................................................... 9
5.5 implementation ................................................................................................................... 11
5.6 hand over the project site .................................................................................................... 12
6 Challenges / Issues and Solutions Taken ........................................................................... 12
7 Lessons Learned ................................................................................................................. 13
8 Recommendations............................................................................................................... 13
9 Success Story ....................................................................................................................... 14
10 Annexes ........................................................................................................................... 15
WASH Emergency Response Project
Building Foundation for Development
3
1 Executive Summary
BFD funded by UNICEF implemented Water and Solar Energy Projects in Al Marashi
District, Al Jawf Gov. In which water networks were installed with a length of 23,883 m,
and an elevated reservoir 100 M 3 as well as control room were constructed. Moreover,
solar panels 40,960 Watt were installed in order to help to operate the process of
transforming water from the borehole to the elevated reservoir. All in all, these
implemented components relieved Al Marashi householders from the suffering, family
hardship, and strife of walking far distances to provide daily water sustenance in small
buckets, pans, and plastic jerry cans.
Google Map of Al Dhalah Village Project
WASH Emergency Response Project
Building Foundation for Development
4
2 Water and Solar Energy System Indicators
100%
0%
Figure 2: Achievement
of Al Dhalah Solar Energy Project
Achievement
Remaining Work
99.84 99.86 99.88 99.9 99.92 99.94 99.96 99.98 100
Build an Elevated Reservoir
Build a Control Room
Water Networks
Build a Wall for the Solar Panels
Total Achievement
99.9
100
101
100
105.7
Figure1: The Achievement of Al Dhalah Water Project
WASH Emergency Response Project
Building Foundation for Development
5
3 Background and Coordinates
The Project is located in Al Dhalah Village –Kharab Almarashi District –Al Jawf Gov. The
area of the project is situated in a mountain, 50-meter-high above the ground level.
Latitude 16°35'35.16"N
Longitude 44°15'2.89"E
4 Target Group and # of Beneficiaries
Inhabitants of Al Dhalah Village are the target group.
# of Beneficiaries, Al Dhalah Village
Men Women Boys Girls Total
871 906 814 857 3448
5 Project Phases
project Phases
Field Visits
A study and design of the
project
1st Preparing as well as announcing tenders, and
then choosing a perfect fit contractor.
Cleaning the Borehole + Pumping
Test
2nd Preparing as well as announcing tenders, and
then choosing a perfect fit contractor.
Implementation
Hand over the site
WASH Emergency Response Project
Building Foundation for Development
6
5.1 FIELD VISITS
On Sep 5th, 2018, BFD's engineers descended to the project site in order to figure out all
the details of the borehole status, surrounding boreholes and any other obstacles that may
happen during the implementation. They found that the borehole is with no infrastructure,
and no consumption; moreover, it was closed by a tree trunk for a very long while.
5.2 THE TECHNICAL STUDIES AND DESIGNS OF THE PROJECT
1st: The Technical Studies: -
Al Marashi District, Al Jawf Gov.
260 m Total depth of the borehole
96.38 m Static Water level
103 m Dynamic Water Level
12 l / s Safe productivity of the borehole
8 inches Casing diameters
16°35'35.16"N 44°15'2.89"E
Coordinates
23883 m The length of the networks
100 m 3 Elevated Reservoir capacity
30000 Watt Water pump Watt
128 Total number of solar panels
320 W Power of each panel
"AE Solar AE P6-72 Series 320"
Type of solar panel
45 KW Capacity of inverter
"INVT GD100-045G-4-PV china"
Type of inverter
26 KW Pump power
"F. B & GP FB6SX47/20
F.B & GP Italy" Type of pump and Engine
40960 W Solar panels Watt
175488.036 $ Cost of the water project
89810.05 $ Cost of the solar energy system
UNICEF Donor
WASH Emergency Response Project
Building Foundation for Development
7
2nd: BFD’s Designs and drawings:
BFD conducted a study as well as a design of Al Dhalah Project to construct an elevated
reservoir, and a control room. Moreover, install water network lines, and solar energy
system, as well build a wall for the solar panels.
Figure 3 Figure 4
Figure 5 Figure 6
WASH Emergency Response Project
Building Foundation for Development
8
5.3 CLEANING THE BOREHOLE
On Jan 7th, 2019, a rotary digger (T4W), as well as a Volvo truck were sent scarcely to Al-
Marashi District in order to clean and save the borehole. 13 pipes were lowered into the
borehole, each pipe has a length of 7.6 m, which means the whole 13 pipes have a length
of 99 m, where the obstacle is located. The pressure of the rig was placed at 150 rpm,
followed by the pressure of the air on the waste from the cleaning work to the outside of
the borehole. The excavator continued to reach a distance of 170 m; yet, it was stopped
at this distance and the cleaning was continued at 150 rpm for 3 hours. The foam helped
to facilitate the process of removing the sediments.
Figure 7: An illustration that shows the dimensions of the borehole and the details of the places which have been cleaned
Tota
l De
pth
of
the
Bo
reh
ole
The
leve
l of
Exis
tin
g th
e O
bst
acle
Stat
ic W
ate
r Le
vel
WASH Emergency Response Project
Building Foundation for Development
9
5.4 PUMPING TEST
On Jan 10th, 2019, BFD handed over the site of the project to the contractor in order to
commence conducting the pumping test. The pumping test was carried out in two stages,
the first step was a step-drawdown test; whereas, the other one was a constant pumping
test. The pumping test lasted for 5 days in a row, and according to it, the borehole yield
was determined to be 12 liters / s.
1) The step-drawdown test
The step-drawdown test consisted of three steps, with each consecutive step being
pumped at a higher rate than the previous step. The total pumping of the three steps lasted
270 min, with each step lasting for 90 min. The 270-minute stress test commenced
immediately after the conclusion of the step-drawdown test.
D S ( m) D. W.L (m) Q( L/S) Time Step 0.50 96.88 4.5 90 1
1.16 97.54 8 90 2
1.60 97.98 15 90 3
Photo 1: While cleaning the borehole Photo 2: While cleaning the borehole
WASH Emergency Response Project
Building Foundation for Development
10
2) The constant pumping test
The static water level was measured at (51.6m), and then the constant pumping test was
carried out. The final step approached the estimated maximum yield of the borehole which
is 12 l / s. As the pumping process continued, there was a gradual decrease in both water
and productivity levels. The water dropped to 100 m after 10 hours with the drop-in
productivity to 12.50 l / s after 16 hours of pumping. Both the level and yield were
sustainable at 103 m; in addition, the yield was 11.80 l / s until the end of the 30-hour
continuous pumping process.
Recovery Test
The constant pumping test was stopped, and a recovery test was conducted. It was
observed that the water returned to the static level (51.6 m) after 11 hours of stopped
pumping.
Photo 3: While conducting the pumping test Photo 4: While measuring the water pumping
WASH Emergency Response Project
Building Foundation for Development
11
5.5 IMPLEMENTATION
1- On Mar 31st, 2019, BFD handed over the project site to the contractor in order to commence
implementing the work of the water project, in which an elevated reservoir and a control
room were constructed. Moreover, water network lines have been installed, and a wall for
the solar panels was built.
2- On Jun 24th, 2019, BFD handed over the project site to the contractor in order to commence
implementing the work of the Pumping Solar Energy Project, in which a complete pumping
solar energy was installed.
Photo 5: The elevated reservoir Photo 6: The wall
Photo 7: The solar panelsPhoto 8: The solar panels and the control
room
WASH Emergency Response Project
Building Foundation for Development
12
5.6 HAND OVER THE PROJECT SITE
On Oct 1st, 2019, BFD handed over the project site to the committee of bens of Al Dhalah
Project in order to look after it and make sure that the water is pumping to each HH in the
district. The site was handed over to the committee of bens in the presence of the Director
of GARWP, Director of the District, and engineers from Al Jawf governorate Office.
6 Challenges / Issues and Solutions Taken
Challenges / Issues Solutions Taken
Demanding the Chairman of the Beneficiary Committee to increase the productivity of the pump as well as increase the number of panels.
A committee was set up to investigate this problem, and it was proven that the yield of water is 11 liters per day to each HH in the district, which means that the pump covers triple the daily production of water.
The borehole casings are corroded, making the water pretty much salty; besides, the ruined casings let the dust fall and fill the borehole.
Using Borehole's camera to check up the borehole and evaluate the damage in the casing after extracting all the pipes from the borehole; furthermore, renting a drilling rig to dig the borehole for almost 150 meters depth, then replacing all the damaged casings, and the final step would be the pumping test.
The coverage of the internet is very weak in Al Jawf; as a result, BFD team encounter difficulties in sending daily, weekly and monthly reports.
BFD team travel from Al Jawf to Sana'a to submit reports, and sometimes they send them to Sana'a by cars that belong to the foundation.
During the excavation of the water network lines, BFD team did not know that there was a telephone network underground, which destroyed the telephone network during the excavation.
BFD repaired the telephone network, which cost $ 3500.
The difficult terrain of the district as well as overlap and high density of HHs, which made it difficult to identify the paths.
Divided the district into squares and made a sketch for each square which shows all the HHs.
WASH Emergency Response Project
Building Foundation for Development
13
7 Lessons Learned
• Before excavating the ground, asking the residents whether there is a telephone network
or not. In case there is, asking about the places of them is a must.
• Avoid engaging with contractors who have limited resources.
Without complementary components, the project will not be sustainable. For example,
rehabilitating boreholes will make no difference to health if community members are not
educated on the benefits of using clean water and maintaining the water systems.
• It is necessary to count all the houses in the target district accurately.
8 Recommendations
It is recommended that:
• When conducting the population census, never ever forget taking with you the chairman of
bens to make sure that all the houses and residents in the district have been counted.
• Carrying out regular field visits to the project site after finishing the implementation and
handing over the project site to the bens.
• An inspection of the borehole should be carried out every 2 years to confirm that its
condition has not altered in the preceding years.
• Further to the elevated reservoirs, it is recommended to distribute small tanks to each HH
in the target area.
WASH Emergency Response Project
Building Foundation for Development
14
Cleaning and Rehabilitating a Borehole Save Thousands of Lives
“Is it possible to conduct a project on a mountain, and how would you rehabilitate that closed borehole by a tree
trunk?” Ahmed Salah said, a fifty-seven-year-old man who resides in Al Dhalah Village. When it comes to humanity,
everything becomes possible, period. Human lives are more important than anything else. For vulnerable and
conflict-affected populations residing in Al Dhalah Village, Al Marashi District, Al Jawf Governorate, access to safe
drinking water often requires long, arduous hours of walking to the nearest borehole; and what is more, the village is
situated in a mountain, 50-meter-high above the ground level. The worst part of this, is the world’s largest acute
watery diarrhea/ suspected cholera outbreaks caused by contaminated water, especially in Yemen including Al Jawf
Gov. “There are 56 cholera cases, and what makes me happy now is that the residents of Al Marashi District are
aware of the danger of cholera which caused by unclean water.” Dr. Amar Ali said, one of the doctors at Al Marashi
Health Center.
BFD (Building Foundation for Development) funded by UNICEF knew that implementing the project will take a
supreme effort. “We found that the borehole is with no infrastructure; moreover, it was closed by a tree trunk for a
very long while.” Abdusalam Al-Asad said, one of BFD’s engineers (WaSH Officer). He also added saying, “The
issue is not how to clean and carry out the pumping test on that borehole, but how can a rotary digger (T4W), as well
as a Volvo Truck reach the project site, especially the borehole?” Therefore, many meetings were held to come up
with solutions, and hopefully, all WaSH staff were determined to implement that project. “No matter how much does
it cost, and no matter how long time does it take, the project must be implemented to help the residents of Al Dhalah
Village.” Ahmed Al-Theeb said, the program manager of BFD. He added saying, “If a Pressure Digger cannot reach
that site, I myself and all BFD staff will travel to Al Dhalah Village and clean the borehole ourselves to help those
in a dire need for clean water and to end the outbreak of cholera.”
“Yes, BFD faced difficulties in taking permissions to let the Rotary Pressure Digger enters to the project site since
the project is situated in a conflict-affected area and the Saudi-led coalition aircrafts might carry out raids on that the
Rotary Pressure Digger, thinking that it is a launching pad of missiles.” Mohammed Al-Sanabani said, the project
manager of WaSH Sector. He added saying, “Despite the challenges that BFD encountered, the project was
implemented fruitfully, in which an elevated reservoir 100 m was constructed, water networks with a length of 23883
m were installed, solar energy system 40960 W was installed. Moreover, a control room, as well as a wall for the
solar panels, were built.” Currently, 3448 the populations of Al Dhalah Village do not need to walk long distances
to collect water since they have easy access to clean water for drinking, cooking, and cleaning. On the whole, the
intervention of BFD ensured clean water provision to host communities and IDPs with quantities no less than 15L
per person, which rest assured them that the outbreak of cholera has been reduced due to the clean water.
9 Success Story
WASH Emergency Response Project
Building Foundation for Development
15
10 Annexes
Waiver of land for the Solar Energy Panels
WASH Emergency Response Project
Building Foundation for Development
16
Handover Minutes of Al Dhalah Water Project Site to the contrctor
WASH Emergency Response Project
Building Foundation for Development
17
Contract of Implementation, Water Project