CONTRACTOR : SINOHYDRO
PROJECT : KAPIRI - MPOSHI WEIGHBRIDGE CONSTRUCTION
ENGINEER : ZULU BURROW CONSULTANTS
LOCATION : KAPIRI - MPOSHI - TURN OFF
B . R D
CHAINAGE (Km)
DRY MASS IN AIR (g)
IN WATER AT 25 c (g)
SATURATED SURFACE (g)
VOLUME (Cm3 )
BULK SPECIFIC GRAVITY ( g/cm³ )
B . R. D CHAINAGE
DRY MASS IN AIR (g)
IN WATER AT 25°c (g)
SATURATED SURFACE (g)
VOLUME (Cm³ )
BULK SPECIFIC GRAVITY ( g/ cm³)
Prepared by : Daniel Mulenga
SIGNATURE :
CONTRACTOR : SINOHYDRO BULK SPECIFIC DENSITY
PROJECT : KAPIRI - MPOSHI WEIGHBRIDGE CONSTRUCTION OF HOTMIX DRILL CORES
ENGINEER : ZULU BURROW CONSULTANTS STANDARD METHOD : AASHTO T 166
LOCATION : KAPIRI - MPOSHI - TURN OFF
B . R D
A 836.9 1165.0
B 510.1 717.2
C 837.6 1165.8
D = C-B 327.5 448.6
A/ D 2.555 2.597
0 + 100 CL
0 + 100 LHS
B . R. D
A
B
C
D = C -B
A/D
Daniel Mulenga
Checked by Engineer Representative : James
BULK SPECIFIC DENSITY DATE TESTED : 15.03.2014
OF HOTMIX DRILL CORES DATE SAMPLED : 14 .03.2014
STANDARD METHOD : AASHTO T 166
B . R D
650.0 1053.2 928.2 718.6
398.6 625.0 561.6 440.3
650.7 1053.7 929.0 718.9
252.1 428.7 367.4 278.6
2.578 2.457 2.526 2.579
0 + 200 CL
0 + 300 RHS
0 + 400 LHS
0 + 500 CL
Checked by Engineer Representative : James
Approved by Engineer :
DATE TESTED : 15.03.2014
DATE SAMPLED : 14 .03.2014
STANDARD METHOD : AASHTO T 166
B . R D
AVERAGE
2.549
AVERAGE
Approved by Engineer :
MAXIMUM SPECIFIC GRAVITY ( MSG ) WORK SHEET
Date : 18.03.2014 Using Flask 2000ML ( PYK )
LAB . NO.
SAMPLE NO. 1
PYCNOMETER NO.
PYK + WATER (g) @ 25C (D ) 3829.7
PYK + MATERIAL (g) X1 2856.6
EMPTY PYK (g) X2 1568.0
MATERIAL DRY @ 25c X1 - X2 = (A) 1288.6
PKY + MATERIAL + WATER @ 25c (E ) 4627.9
STANDARD : AASHTO T 209-90
MAXIMUM SPECIFIC GRAVITY OF DRILLED CORE
M.S.G. g /Cm³ A / ((A+D) - E ) 2.628
Test Performed by : Checked by :
MAXIMUM SPECIFIC GRAVITY ( MSG ) WORK SHEET
Using Flask 2000ML ( PYK ) ENGINEER : ZULU BURROW CONSULTANTS
BINDER CONTENT (%) 5.1
CLIENT : SINOHYDRO
Asphalt Mix Type :
3829.7 g
2856.6 g
1568.0 g
1288.6 g
4627.9 g
MAXIMUM SPECIFIC GRAVITY OF DRILLED CORE
PROJECT LOCATION : KAPIRI - MPOSHI TURN OFF
Medium Continiously Graded 0-16mm
2.628 g/cm³
Checked by : Approved by :
ENGINEER : ZULU BURROW CONSULTANTS
5.1
SINOHYDRO
PROJECT LOCATION : KAPIRI - MPOSHI TURN OFF
Medium Continiously Graded 0-16mm
Approved by :
MARSHALL AND VOLUMETRIC PROPERTIES WORK SHEETProject Location : Kapiri Mposhi Turn Of
Engineer : Zulu Burrow Consultants
Client : SINOHYDRO
MATERIAL : DRILLED CORES
Mix Type : 0- 16mm Medium Wearing Course
MARSHALL PROPERTIES
Specemen No. Details 1
Specemen H eight (mm) 60.01
60.31
60.52
60.00
Average Height (mm) 60.21
Stability (mm) S 13.09
Flow (mm) F 3.93
Volumetric PropertiesSpecemen No. 1
Mass of dry Specemen in Air (g) a 1194.6
Mass of Specemen in Water (g) b 721.8
Mass of saturated Surface (g ) c 1195.4
Mass of displaced Water (g) d =(c-b) 473.6
Temperature of Water (C ) 27°C
Bulk Relative Density ( Kg / m³ ) a/d 2.522
Maximum Theoretical Density (Kg/ m³) Gmm 2.628
Air Voids ( %) Va 4.0
Voids in mineral Aggregates (%) Vma 15.31
voids Filed with Bitumen ( % ) VFA 73.87
Name Signature
Prepared by :
APPROVED BY :
MARSHALL AND VOLUMETRIC PROPERTIES WORK SHEETProject Location : Kapiri Mposhi Turn Of Lab No. 001
Engineer : Zulu Burrow Consultants Location : Asphalt plant
Client : SINOHYDRO Date Sampled : 14. 03.2014
MATERIAL : DRILLED CORES Date Tested : 18.03.2014
Mix Type : 0- 16mm Medium Wearing Course Bitumen Content : 5.10 %
MARSHALL PROPERTIES
2 3 Average
59.00 58.91
58.85 58.94
59.00 58.61
59.80 59.00
59.16 58.87 59.40
14.44 13.07 13.53
3.92 3.95 3.93
Volumetric Properties2 3
1191.9 1204.3
719.4 728.5
1192.7 1205.0
473.3 476.5
27°C 27°C
2.518 2.527 2.522
2.628 2.628 2.628
4.0 4.0 4.0
15.31 15.31 15.31
73.87 73.87 73.87
Signature Date
DETERMINATION OF BITUMEN CONTENT (EXTRACTION ) WORK SHEETPROJECT LOCATION : KAPIRI - MPOSHI TURNOFF
ENGINEER : ZULU BURROW
CLIENT : SINOHYDRO
DATE SAMPLED: 17 03 .2014
TIME OF SAMPLING : MIXING TEMPERATURE : 165°CEXTRACTION OF BITUMEN LOCATION : ASPHALT PLANT
TEST METHOD ASTM D2172
BINDER CONTENT
Mass of Sample before extraction
Mass of Sample after extraction
Mass of CUP
Mass of Cup + fines
Mass of fines
Mass of sample after extraction + fines
Mass of bitumen
binder content by weight of total mixture
SIEVE ANALYSIS
Mass 949.0 g
Sieve Size Mass of Retained Cumulative
(mm)
19.0 0 0 0
13.2 13 1.4 1.4
9.5 92.0 9.7 11.1
4.75 270.0 28.5 39.6
2.36 167.0 17.6 57.2
1.18 89.0 9.4 66.6
0.6 48.0 5.1 71.7
0.3 32.0 3.4 75.1
0.15 78.0 8.2 83.3
0.075 87.0 9.2 92.5
<0.075 73.0 7.6 100.1
Retained (g)
Percentage
(%)Retained
(%)
DETERMINATION OF BITUMEN CONTENT (EXTRACTION ) WORK SHEETPROJECT LOCATION : KAPIRI - MPOSHI TURNOFF
ENGINEER : ZULU BURROW SAMPLING LOCATION : ASPHALT PLANT
CLIENT : SINOHYDRO TYPE OF ASPHALT : 0 -16mm MEDIUM
DATE SAMPLED: 17 03 .2014 TEST NO. 0
LAB TEST
5.10%
a 1000.0 g
b 910.0 g
c 256.0 g
d 295.0 g
(d-c) e 39.0 g
(b+ e) f 949.0 g
(a-b-e) g 51.0 g
(g/a*100) h 5.10 %
Passing Lower Intermediate UPPER
Limit value Limit
100 100 100 100
98.7 100 100 100
89.0 82 91 100
60.5 54 64.5 75
42.9 35 42.5 50
33.5 27 34.5 42
28.4 18 25 32
25.0 11 17 23
16.8 7 11.5 16
7.6 4 7 10
Percentage
(%)
ZULU BURROW CONSULTANTS PROJECT LOCATION : KAPIRI- MPOSHI TURN OFF
ASPHALT TYPE : 0- 16mm Continously Grade - Medium
LOCATION : KAPIRI TURN OFF
Lane : RHS / LHS
KAPIRI MPOSHI - WEIGHBRIDGE CHECK POINT
Core DATE Chanage Of Set
No. TESTED (Km) Lane m
1 18.03.2014 Km 0 + 100 CL 0.0
2 18.03.2014 Km 0 + 100 LHS 1.2
3 18.03.2014 Km 0 + 200 CL 0
4 18.03.2014 Km 0 + 300 RHS 0.0
5 18.03.2014 Km 0 + 400 LHS 1.2
6 18.03.2014 Km 0 + 500 CL 0.0
Average
Marshall Data Bitumen analysis (%) Gmm
Road Initial site (%)
Note : The compaction control was done with the theoretical maximum density .materials was tested as per SATCC Standard Specification for roads and bridges , september,1998 (Reprinted 2001)as per section 4200 cluse 4209.
5.0 5.1 2.628
PROJECT LOCATION : KAPIRI- MPOSHI TURN OFF ASPHALT COMPACTION TEST SUMMARY SHEET
KAPIRI MPOSHI - WEIGHBRIDGE CHECK POINT
Thickness Core Density Compaction voids
mm g/ cm3 % %
41 2.555 97.2 2.8
52 2.597 98.8 1.8
27 2.578 98.1 1.9
53 2.457 93.5 6.5
46 2.526 96.1 3.9
34 2.579 98.1 1.9
42.2 2.549 97.0 3.1
Note : The compaction control was done with the theoretical maximum density .materials was tested as per SATCC Standard Specification for roads and bridges , september,1998 (Reprinted 2001)as per section 4200 cluse 4209.
Minimum on value Compaction %
Maximum value on Compaction %
ASPHALT COMPACTION TEST SUMMARY SHEET
Paving Length : 500 m
Date Sampled : 14 .03.2014
Date Sampled : 1803.2014
Minimum on value Compaction % 93.5 No . Of observation 6
Maximum value on Compaction % 98.8
CONTRACTOR : SINOHYDRO
PROJECT : KAPIRI - MPOSHI WEIGHBRIDGE CONSTRUCTION
ENGINEER : ZULU BURROW CONSULTANTS
LOCATION : KAPIRI - MPOSHI - TURN OFF
B . R D
CHAINAGE (Km)
DRY MASS IN AIR (g)
IN WATER AT 25 c (g)
SATURATED SURFACE (g)
VOLUME (Cm3 )
BULK SPECIFIC GRAVITY ( g/cm³ )
B . R. D CHAINAGE
DRY MASS IN AIR (g)
IN WATER AT 25°c (g)
SATURATED SURFACE (g)
VOLUME (Cm³ )
BULK SPECIFIC GRAVITY ( g/ cm³)
Prepared by :
SIGNATURE :
CONTRACTOR : SINOHYDRO BULK SPECIFIC DENSITY
PROJECT : KAPIRI - MPOSHI WEIGHBRIDGE CONSTRUCTION OF HOTMIX DRILL CORES
ENGINEER : ZULU BURROW CONSULTANTS STANDARD METHOD : AASHTO T 166
LOCATION : KAPIRI - MPOSHI - TURN OFF
B . R D
A
B
C
D = C-B
A/ D
B . R. D
A
B
C
D = C -B
A/D
Checked by Engineer Representative :
BULK SPECIFIC DENSITY DATE TESTED : 15.03.201
OF HOTMIX DRILL CORES DATE SAMPLED : 14 .03.2014
STANDARD METHOD : AASHTO T 166
B . R D
Checked by Engineer Representative : Approved by Engineer :
DATE TESTED : 15.03.201
DATE SAMPLED : 14 .03.2014
STANDARD METHOD : AASHTO T 166
B . R D
AVERAGE
AVERAGE
Approved by Engineer :