    COMMON MISTAKES IN HOTEL

    PLANNING, DEVELOPMENT

    AND OPERATION

    HOTEL DESIGN

    August 2014

    By Kai Schröter, General Director

    © HTM Management Consultancy

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    2/44

    Common Mistakes in Hotel Planning, Development and Operation

    HTM is pleased to introduce a new series

    of  Common Mistakes in Hotel Planning,

    Development and Operation. This serieshas been prepared in support of owners,

    developers, architects, designers and

    project managers of hotels.

    The following presents the most commonmistakes in Hotel Design. It outlines

    frequent errors and omissions occurring

    during the design process, which can have

    long lasting negative impacts on the

    property’s   management, operation andreturn on investment.

    Please subscribe to our regular updates at

    [email protected].

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    3/44

    Common Mistakes in Hotel Planning, Development and Operation

    Hotel developments are different   –   they are very diverse and quite

    complicated when compared to any other type of real estate investment

    and property development. They involve complex and overlapping end-to-end processes, multiple stakeholders, considerable strategic planning

    and decision making, extensive technical know how and specialist

    experience in project management, operational equipment, technical

    services, pre-openings, management and operation of hotels.

    Hotel developments are risky   –   they are more time-consuming and

    costly. By floor space, an average hotel can cost 3 times as much and

    take 3 times as long to build. 6,500 different items go into a hotel   –

    about 20 into an office block. An average 5 star hotel requires 27

    different consultants and around 10‐15% of the budget, the  pre‐openingover 10%. Few owners have experience with hotels, few architects

    specialize in hotel design and few project management firms know how

    to manage hotel development processes.

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    4/44

    Common Mistakes in Hotel Planning, Development and Operation

    Hotel developments require specific know how   –   they frequently

    attract financially potent owners with a background in various sectors  –

    real estate, banking, law, tourism and others, and with a great deal of vanity, but little experience in hotel development. This often leads to

    wrong decision making in conceptualization, branding, design,

    construction, management, operation…and the failure of the hotel.

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    5/44

    Common Mistakes in Hotel Planning, Development and Operation

    Hotel Planning

    Common Mistakes in Hotel Market StudiesCommon Mistakes in Hotel Finance Studies

    Common Mistakes in Hotel Property Evaluation

    Common Mistakes in Hotel Property Site Selection

    Common Mistakes in Hotel Investment Planning and Financing

    Common Mistakes in Hotel Investment and Business LicensingCommon Mistakes in Hotel Conceptualization

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    6/44

    Common Mistakes in Hotel Planning, Development and Operation

    Common Mistakes in Hotel Branding

    Common Mistakes in Hotel Architect Search and Selection

    Common Mistakes in Hospitality Consultant Search and SelectionCommon Mistakes in Hotel Master Planning

    Common Mistakes in Hotel Business and Operation Models

    Common Mistakes in Hotel Operator Search and Selection

    Common Mistakes in Hotel Management Agreement Negotiation

    Common Mistakes in Hotel Technical Services Contract NegotiationCommon Mistakes in Hotel Project Planning

    Common Mistakes in Hotel Capital Expenditures Budgeting

    Common Mistakes in Hotel Furniture, Fixtures and Equipment Reserves

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    7/44

    Common Mistakes in Hotel Planning, Development and Operation

    Hotel Design

    Common Mistakes in Hotel DesignCommon Mistakes in Hotel Access Design

    Common Mistakes in Hotel Exterior Design

    Common Mistakes in Hotel Interior Design

    Common Mistakes in Hotel Operation and Work Flow Design

    Common Mistakes in Hotel Public Area and Front-of-House DesignCommon Mistakes in Hotel Back-of-House and Staff Areas Design

    Common Mistakes in Hotel Guest Room Design

    Common Mistakes in Hotel Engineering and Technical Design

    Common Mistakes in Hotel Food and Beverage Conceptualization

    Common Mistakes in Hotel Food and Beverage Outlet Branding

    Common Mistakes in Hotel Food and Beverage Outlet Design

    Common Mistakes in Hotel Kitchen and Laundry Design

    Common Mistakes in Hotel Landscape Design

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    8/44

    Common Mistakes in Hotel Planning, Development and Operation

    Hotel Development

    Common Mistakes in Hotel Project Manager SelectionCommon Mistakes in Hotel Contractor Negotiations and Selection

    Common Mistakes in Hotel Project Coordination and Implementation

    Common Mistakes in Hotel Bill of Quantities

    Common Mistakes in Hotel Quantity and Quality Surveillance

    Common Mistakes in Hotel Construction and Site SupervisionCommon Mistakes in Hotel Site Safety and Security

    Common Mistakes in Hotel Mechanical and Electrical Engineering

    Common Mistakes in Hotel Utility Conservation and Environmental Protection

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    9/44

    Common Mistakes in Hotel Planning, Development and Operation

    Common Mistakes in Hotel Technical Services Coordination

    Common Mistakes in Hotel Pre-Opening

    Common Mistakes in Hotel Standard Operating Equipment BudgetingCommon Mistakes in Hotel Brand Development

    Common Mistakes in Hotel Marketing, Sales and Public Relations

    Common Mistakes in Hotel Human Resources Planning

    Common Mistakes in Hotel Recruitment, Selection and Training

    Common Mistakes in Hotel Testing, Commissioning and Handover

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    10/44

    Common Mistakes in Hotel Planning, Development and Operation

    Hotel Operation

    Common Mistakes in Hotel Soft-OpeningsCommon Mistakes in Hotel General Management

    Common Mistakes in Hotel Strategic Positioning and Pricing Policies

    Common Mistakes in Hotel Brand Development

    Common Mistakes in Hotel Marketing and Sales

    Common Mistakes in Hotel Strategic Communication and Public RelationsCommon Mistakes in Hotel Promotion and Advertising

    Common Mistakes in Hotel Sales and Marketing

    Common Mistakes in Hotel Digital Marketing and Online Sales

    Common Mistakes in Hotel Distribution Management

    Common Mistakes in Hotel Customer Relationship ManagementCommon Mistakes in Hotel Revenue and Yield Management

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    11/44

    Common Mistakes in Hotel Planning, Development and Operation

    Common Mistakes in Hotel Human Resources Planning

    Common Mistakes in Hotel Human Resources Management

    Common Mistakes in Hotel Recruitment and SelectionCommon Mistakes in Hotel Training and Staff Development

    Common Mistakes in Hotel Rooms Division Management

    Common Mistakes in Hotel Food and Beverage Management

    Common Mistakes in Hotel Operations

    Common Mistakes in Hotel Customer Service and Guest RelationsCommon Mistakes in Hotel Finance and Accounting

    Common Mistakes in Hotel Procurement and Purchasing

    Common Mistakes in Hotel Revenue and Expense Forecasting

    Common Mistakes in Hotel Operational Budgeting

    Common Mistakes in Hotel Profit and Loss Analysis

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    12/44

    Common Mistakes in Hotel Planning, Development and Operation

    Critical Areas with Typical Design Errors

    Hotel Access and EntranceHotel Exterior and Signage

    Lobby and Public Areas

    Front Office and Reception

    Porter and Luggage Room

    Elevators, Corridors and PantriesGuest Rooms and Bathrooms

    Connecting Rooms

    Disabled Guest Rooms

    Restaurants and Bars

    Room Service

    Meeting Rooms and Banqueting Areas

    Spa, Gym and Swimming Pool

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    13/44

    Common Mistakes in Hotel Planning, Development and Operation

    Receiving and Purchasing Areas

    Cooling and Storage Facilities

    Kitchens and LaundryManagement Offices and Staff Areas

    Staff Entrance and Locker Rooms

    Staff Restaurants and Canteens

    Guest and Staff Nursery

    Closed-Circuit Television SystemPrivate Automated Branch Exchange System

    Heating, Ventilation and Air-Conditioning System

    Water Supply, Treatment and Discharge System

    Fire Safety and Sprinkler System

    Main Frame Server and Computer System

    Property Management System

    Point-of-Sales System

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    14/44

    Common Mistakes in Hotel Planning, Development and Operation

    Top 10 Areaswith Most Design Errors in Hotels

    1 Guest Rooms

    2 Back-of-House

    3 Guest Bathrooms4 Fabric and Finishes

    5 Food and Beverage Facilities

    6 Elevators

    7 Function Rooms

    8 Lobby

    9 Entrance

    10 Kitchen

    Source: http://www.wgdarchitects.com/survey/results/results.html

    The following pages present

    only a few of the myriad of considerations which shall

    be made in professional

    hotel design. Most of them

    seem like common sense,

    but one would not believe

    how frequent they are

    disregarded.

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    15/44

    Common Mistakes in Guest Room Design

    We can’t expect architects to know the nuances of operating hotels. So

    why do we expect them to know how to best design a hotel room in allfacets and details?

    Seems like ‘common sense’, but still happens all too often.

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    16/44

    Too Many Rooms Types and Categories

    A common misperception is that having many types of rooms increases the

    choice for guests, thereby widening the target market. The reality is, havingmany different types of rooms creates confusion and pricing issues, affects

    marketing and sales, and limits the ability to accommodate large groups. At

    the same time, it increases room cleaning, fit-out and maintenance costs,

    eating up   owner’s  profits.

    Unsuitable Ratio between Room Types and Categories

    The ratio between the number of different room types and categories  – e.g.

    single, double, twin or triple room, standard, superior or deluxe room,

     junior, family or executive suite, connecting rooms, disabled rooms, smoker-

    and non-smoking rooms…depends on many factors, which the developer or

    architect do not necessarily know. This can lead to the difficult situation,

    where the owner is forced to choose between low occupancy or decrease of 

    room rates. A ‘Make or Break’ scenario.

    Room Design | Some Examples of What Could Go Wrong

    |

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    17/44

    Same Room Types and Categories with Different Configurations

    The layout, configuration and fitting out of guest rooms depends on hotel

    property dimensions, brand and operator standards, building design andbudgets, construction ratios etc. Without professional hotel advice,

    mistakes are programmed and will lead to similar issues as before

    mentioned – except that often the architect or hotel operator are blamed,

    instead of the owner…

    Room Design | Some Examples of What Could Go Wrong

    i | l f h h ld d

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    18/44

    The hotel investor, developer or owner should provide the architect or

    interior designer   a detailed design brief , including the guest room

    design standards to apply across all rooms, and tailored to each size andtype of room. The design must be driven by maximizing the guest

    experience and comfort during their stay. The interior designer must also

    keep in mind the efficiency of daily hotel operation, including the

    streamlining of guest check in, housekeeping and minimizing of 

    maintenance due to wear and tear.

    The owner should appoint a hospitality management consultant, who

    will work hand in hand with the architect and interior designer during

    the design phase, in order to minimize costly mistakes that would

    negatively impact operations, create poor guest experiences and effect

    profitability and return on investment.

    Room Design | Some Examples of What Should Have Occurred

    C Mi k i G B h D i

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    19/44

    The  guest’s room experience is highly influenced by the quality of the

    bathroom design. The configuration and fitting out very much depends

    on factors such as hotel property, brand standards, target market,

    guest preferences,  owner’s budget and others.

    The hospitality management consultant   will support owner and

    architects to make the right decisions.

    Common Mistakes in Guest Bathroom Design

    B h D i | S E l f Wh C ld G W

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    20/44

    Bathroom is Too Large

    Inefficient room configuration creates a waste of space and money to

    build and clean. Visually not attractive.Bathroom is Too Small

    Even more important than the size of the bathroom is the efficiency and

    practicality of design.

    Shower or Bathtub?

    Where are your guests from? France, Russia, Japan, Vietnam? Do theytravel for business or leisure? Do they stay for the long-term or short-

    term? Choosing between a shower or bathtub depends on the answer to

    these questions, and many more...

    Towel Rack in the Wrong Location

    Guests need to search or reach for the towel while dripping water all

    over the floor creating a slippage hazard. Is your insurance policy up to

    date?

    Bathroom Design | Some Examples of What Could Go Wrong

    B th D i | S E l f Wh t C ld G W

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    21/44

    No Electricity Socket for the Hairdryer

    It   wouldn’t   be a problem if all your

    guests were bald and  didn’t need a hairdryer.

    Bathroom Window without Blinds

    Some people like privacy.

    Insufficient Hot Water Capacity

    This is a very common mistake and it isvery annoying for the guest. It also

    solicits very expensive negative reviews.

    Mini Bar in the Bathroom

    This is never a good idea.

    Bathroom Design | Some Examples of What Could Go Wrong

    B th D i | S E l f Wh t Sh ld H O d

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    22/44

    Bathrooms need to be carefully planned and well designed. They need to

    be a source of comfort, yet easy to clean and maintain. Lights, mirrors

    and electrical outlets need to be carefully located so that they are alwayswithin reach and in the exact place that the guest would expect.

    The interior designer   must work closely with the hospitality

    management consultant during the design stage in order to avoid costly

    mistakes that will lead to difficulties in operation or a poor experience for

    the guests.

    Bathroom Design | Some Examples of What Should Have Occurred

    C Mi t k i F d d B O tl t D i

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    23/44

    The profitability of the hotel’s food and beverage department depends very

    much on functionality of operations, whereas owners and architects mostly

    focus on form and design. Successful F&B businesses combine operational

    functionality with aesthetic design. Factors must be considered such as

    room numbers, house guests, walk-in guests, restaurant-, food and service

    concept, menu, meal turnover, average covers, kitchen organization,

    staffing….The hospitality management consultant  will support owner and

    architects to make the right decisions.

    Common Mistakes in Food and Beverage Outlet Design

    F&B O tl t D i | S E l f Wh t C ld G W

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    24/44

    Mismatch between F&B Concept and Design

    To be successful and attract guest, F&B concepts need to be attractive

    and unique. Design must represent this and be consistent. The architectand interior designer follow the hospitality concept, not the other way

    round.

    Poor Restaurant Layout and Work Flow Design

    Inadequate design of F&B outlets by non-hospitality professionals with

    severe results, such as poor food and service quality, low customersatisfaction, food and beverage hygiene problems, high F&B and

    breakage costs, occupational hazards and work accidents, low staff 

    morale and high turnover etc.

    Wrong Restaurant Layout versus Number of Rooms

    Difficulties to render efficient service with long cues for breakfast, lunch

    and dinner.

    F&B Outlet Design | Some Examples of What Could Go Wrong

    F&B Outlet Design | Some Examples of What Could Go Wrong

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    25/44

    Bad Buffet Design

    Wrong location of lighting, selection of heights to display food offerings

    and wrong location of electrical sockets, wrong buffet dimensions andcustomer flow, confused design of cold, hot and dessert stations.

    Bad Bar Design

    Inadequate allocation of space, cooling units, water and electricity

    supply, equipment etc., resulting in decreased effectiveness, higher costs

    Kitchen Design does not match F&B ConceptKitchen is designed too large or too small, layout and equipment are not

    suitable with operational requirements, work efficiency is low. This

    results in similar as before mentioned, problems with quality, consistency

    and volume.

    Inappropriate Kitchen Design and Installation

    Kitchen design does not comply with international safety and hygiene

    standards, leading to work flow problems, occupational hazards,

    sanitation and pest problems…and ultimately to big headaches for

    owners.

    F&B Outlet Design | Some Examples of What Could Go Wrong

    F&B Outlet Design | Some Examples of What Could Go Wrong

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    26/44

    Presence of Hazardous Areas

    Kitchen staff facing risks on a daily basis. Better ensure that the

    insurance policies are up to date.Inadequate Construction, Workmanship and Supervision

    This needs to be aided by experienced hospitality project

    professionals. Poor choice of materials and inadequate

    installation will result in high safety and hygiene risks and non-

    compliance with legal obligations.Wrong Installation of Electrical Sockets in Kitchen

    Difficulties to properly use equipment or to follow cleaning

    procedures.

    Bad Design of Exhaust, Ventilation, Air-conditioning, Exhaust

    and Grease Trap Systems

    Incorrect temperature, unwanted odors, hygiene and pest

    problems, low staff motivation.

    F&B Outlet Design | Some Examples of What Could Go Wrong

    F&B Outlet Design | Some Examples of What Could Go Wrong

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    27/44

    Lack of Emergency Light and Fire Systems

    The fire safety license will not be granted, insurance policy will

    be void and most importantly, the safety of guests and staff willbe compromised.

    Clean Areas not Separated from Dirty Areas

    Violation of forward flow principle and HACCP standards.

    Wet Garbage Area not Separated from Dry Garbage Area

    May be in breach of local regulations and pose fire safety andhygiene risks.

    F&B Outlet Design | Some Examples of What Could Go Wrong

    F&B Outlet Design | Some Examples of What Should Have Occurred

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    28/44

    The hotel owner   should provide the architect, interior designer and

    other contractors (kitchen) a detailed design brief , including the food

    and beverage concept and design standards per outlet. Architect,interior designer and contractors should have prior hospitality project

    and F&B design experience. The design must be driven by maximizing

    guest experience and comfort, and at the same time maximizing

    operational efficiency for employees and revenue generation.

    The architect and interior designer  must work hand in hand with the

    hospitality management consultant during the design phase, in order to

    minimize costly mistakes that would negatively impact operations and

    create a poor guest experience.

    F&B Outlet Design | Some Examples of What Should Have Occurred

    Common Mistakes in Lobby and Public Area Design

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    29/44

    Common Mistakes in Lobby and Public Area Design

    The hotel entrance and lobby are the face of the hotel, and owners and

    architects pay rightly so much attention to it. However, layout and design of 

    this highly functional requires managerial and operational understanding of 

    hotels. A ‘chic’ and luxury lobby are a waste of money, if inadequate designof reception and other crucial areas cause long queues and waiting of hotel

    guests…

    The hospitality management consultant will support owner and architects

    to make the right decisions.

    Lobby & Public Area Design | Some Examples of What Could Go Wrong

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    30/44

    Size of Seating Area not in Proportion to Room Inventory

    Crowded lobbies with long cues and lack of seating result in poor guest

    perception.Inadequate Available Parking Bays

    Need to ensure that local regulations are followed by the architect.

    Parking not Available for Physically Challenged Guests

    This is very important to be able to offer as well as ramps to access

    buildings.Poor Lighting in Parking Areas

    Safety and security risks.

    Insufficient and Poorly Illuminated Signage

    Guests will have trouble finding their way around the property. Poorly

    lit signage is a common mistake.

    Lobby & Public Area Design | Some Examples of What Could Go Wrong

    Lobby & Public Area Design | Some Examples of What Could Go Wrong

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    31/44

    Insufficient Electrical Sockets and in the Wrong Location

    Operational difficulties especially for cleaning procedures.

    Under- or Over-building Rather than Utilizing Space ProductivelyWide and under-built spaces are unproductive and do not generate

    revenue, but can make all the difference between a profitable or

    unsuccessful hotel. Crammed and over-built spaces look tight and

    messy, can effect guest experience and revenue. The hospitality

    consultant possesses the specialist knowledge and operationalexperience to develop the right concepts for maximizing use of space

    and revenue, the owners or architects do not.

    Lobby & Public Area Design | Some Examples of What Could Go Wrong

    Lobby & Public Area | Some Examples of What Should Have Occurred

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    32/44

    The Lobby and Public Areas need to be

    carefully planned and well designed. These

    areas will not only increase revenue, butalso improve the quality of work for all

    staff.

    The architect  must work closely with the

    hospitality management consultant duringthe design phase, in order to avoid costly

    mistakes that will lead to difficulties in

    operation or a poor experience for the

    guests.

    Lobby & Public Area | Some Examples of What Should Have Occurred

    Common Mistakes in Elevators and Corridors Design

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    33/44

    Common Mistakes in Elevators and Corridors Design

    The correct design and location of elevators and corridors will considerably

    improve the mobility of guests and staff.

    Elevator & Corridor Design | Some Examples of What Could Go Wrong

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    34/44

    Elevator & Corridor Design | Some Examples of What Could Go Wrong

    Lack of Guest Elevators

    Long wait times will negatively affect the experience of guests.

    Wrong Location of Elevators and Goods LiftsSlows down operations and causes decline in service standards.

    Elevators too Close to Guest Rooms

    Guests will complain about noise, especially early in the morning when

    housekeeping staff move around their trolleys.

    Poor Lighting in Corridors and PathwaysSafety and security risks.

    Inadequate Room Signage

    Proper allocated and visible room signage is appreciated by guests.

    Lack of Elevators near Key Outlets

    Guest facing difficulties to access areas especially at peak times.

    Elevator & Corridor | Some Examples of What Should Have Occurred

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    35/44

    Mobility flows will be affecting daily operations of staff and the

    experience for guests. The architect should be warned about the

    potential pitfalls and have a thorough understanding of the function andlocation of each area.

    Elevator & Corridor | Some Examples of What Should Have Occurred

    Common Mistakes in Back-of-House Design

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    36/44

    The Back-of-House Areas are the heart and muscles of the hotel. Bad

    design without support from hospitality professionals will seriously

    affect daily operation.

    Common Mistakes in Back of House Design

    Back-of-House Design | Some Examples of What Could Go Wrong

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    37/44

    Inadequate Supplier Entrance and Receiving Area

    Either no existing separate back-of-house access for daily hotel supply

    or an access to close to public and guest areas will seriously effect hoteloperation and guest experience.

    Inadequate Staff Entrance and Lack of Staff Facilities

    No suitable staff entrance, access control, staff changing areas and

    facilities, staff canteens will result in problems with grooming standards

    and staff motivation.Inadequate Storage Space

    Maintaining minimum stocks will forever be a challenge.

    Wrong selection of Materials for Walls, Floors, Windows and Ceilings

    Permanent problems of humidity, ventilation, cracks in the masonry

    and slippery floors.

    Lack of Water Points and Drainage in Storage Areas

    Staff will not work efficiently and will fail to follow cleaning, health and

    hygiene procedures.

    Back of House Design | Some Examples of What Could Go Wrong

    Back-of-House Design | Some Examples of What Could Go Wrong

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    38/44

    Insufficient Garbage Collection Space or in Wrong Location

    Too small, too far, too close, not safe or not clean  – all recipes to invite

    pest, hinder effective operation or receive guest complaints.Missing Linen, Uniform and Laundry Room

    The housekeeping manager will have trouble to keep linen standards

    and organize staff to meet operational needs.

    Insufficient Working Space for Housekeeping Department

    Problems to store linen, baby cots, extra beds and trolleys in closeproximity to the rooms.

    Insufficient Departmental Office Space

    The head’s of department will be obliged to work in improvised offices

    far from the workflow and with inadequate loose furniture.

    No Separate Staff Elevators

    Hotel employees will use guest elevators or have to walk stairs. Not only

    unsuitable for international standard hotel, but also detrimental to

    operational costs and guest experience.

    Back of House Design | Some Examples of What Could Go Wrong

    Back-of-House Design | Some Examples of What Could Go Wrong

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    39/44

    Inadequate Hotel Technical Systems

    Design not in line with professional hotel standards in terms of sewage

    treatment, fire, air conditioning, grounding, lighting, rain waterharvesting, generator and gas. Will not only cause trouble with local

    authorities, but even bigger troubles in operation.

    Hot and Cold Water Capacity Issues

    Guests experience an unpleasant surprise during their morning shower.

    Inadequate TV, Camera, Background Music, Telephone, Computer andAudio Visual Systems

    Bland experience for guests.

    Back of House Design | Some Examples of What Could Go Wrong

    Back-of-House | Some Examples of What Should Have Occurred

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    40/44

    The owner, architect, engineering consultant and project manager shall

    work and cooperate closely with the hospitality management

    consultant from an early stage on to avoid costly errors

    Back of House | Some Examples of What Should Have Occurred

    Common Mistakes in Spa, Gym and Pool Design

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    41/44

    These areas are especially important for guests who are looking for

    getaway and leisure trips.

    Common Mistakes in Spa, Gym and Pool Design

    Recreation Areas Design | Some Examples of What Could Go Wrong

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    42/44

    Inadequate Gym Design

    Many hotel gym designs resemble fitness studios without warmth or

    charm.Inferior Spa and Gym Equipment

    Equipment fails to meet expectations of guests and standards of the

    brand.

    Missing Light Dimmers and Sound System in Treatment Rooms

    Negatively impact the experience of guests.Insufficient Space for Lockers

    Complaints from guests.

    Insufficient Furniture in the Pool Area

    The purpose of these areas are rest, relaxation and leisure for guests so

    overcrowding should be avoided.

    g | p g

    Recreation Areas | Some Examples of What Should Have Occurred

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    43/44

    The interior designer should be provided with a detailed design brief,

    including the concept for the spa and sports/recreation areas, as well as

    the design standards for each area. The design must be driven bymaximizing guest experience and comfort during their stay as well as

    streamlining the operation for all employees.

    The architect   must work closely with the hospitality management

    consultant  during the design phase, in order to avoid costly mistakesthat will lead to difficulties in operation or a poor experience for the

    guest.

    | p

    Contact

  • 8/16/2019 Common Mistakes in Hotel Planning Develo

    44/44

    HTM Management Consultancy

    Head Office Hanoi

    No. 2, Alley 236/ 7, Au Co Street

    Tay Ho District, Hanoi, VietnamE-mail: [email protected]

    Website: www.ht-management.com

    Telephone: +84-4-3719 1850/1

    Facsimile: +84-4-3719 1849

    Branch Office Ho Chi Minh City

    SITC Building, 2nd Floor, Room 209-210

    311-319 Gia Phu Street, Ward 1

    District 6, Ho Chi Minh City, Vietnam

    E-mail: [email protected]

    Website: www.ht-management.com

    Branch Office Danang (October 2015)Branch Office Phnom Penh (June 2016)

    Branch Office Vientiane (June 2017)

    Branch Office Yangon (October 2017)