Commissioning Procedure for bKAGRA Phase 1 (2017.9 - 2018.3) Yuta Michimura Department of Physics, University of Tokyo see, also, JGW-T1605595 for interferometer design and commissioning schedule December 16, 2016 JGW-T1605692

Commissioning Procedure for bKAGRA Phase 1gwdoc.icrr.u-tokyo.ac.jp/.../bKAGRAPhase1CommissioningProcedure.pdfCommissioning Procedure for bKAGRA Phase 1 ... ETMX alignment EXT BRT installation

  • Upload
    haquynh

  • View
    218

  • Download
    1

Embed Size (px)

Citation preview

Commissioning Procedure for

bKAGRA Phase 1(2017.9-2018.3)

Yuta MichimuraDepartment of Physics, University of Tokyo

see, also, JGW-T1605595

for interferometer design and commissioning schedule

December 16, 2016JGW-T1605692

IFI IMM

• Legend

chamber

duct

bellows

gate valve

optical table

2

EXTEXCEXAPRM PR3 PR2 BS IXC IXA

TR

X

POP

EY

TE

YC

EY

AS

RM

SR

3S

R2

IYC

IYA

TRY

PO

S

Vacuum Layout

IFI

POP

GVbsx

φ150

GVitmx

φ100

GVetmx

φ100

GVbrtx

φ100

GVbsy

φ150

GVitmy

φ100

GVetmy

φ100

GVbrty

φ100

AS

REFL

PO

S

PRMIFI IMM

Expected Situation

3

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

TE

YC

EY

AS

RM

SR

3S

R2

IYC

IYA

TRY

8.31• PSL & IMC ready, beam reached PRM

(by 8.31)

• BS (by 4.13) and PRs (by 7.6) ready

• SR2 also ready (by 7.31)

PR3-2 not connected GV closed

Yarm evacuated

Xarm evacuated

bellows around BS

not connected

AS

REFL

SR3 installation (7.14-12.19)

bellows between SR2 and SR3

not connected

EYT BRT installation

(7.11-10.2)

PO

S

PRMIFI IMM

Connect PR3-2 Duct

4

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

CE

YA

SR

MS

R3

SR

2IY

CIY

A

9.1-9.8• connect PR3-2 duct to start initial

alignment

• connect it after the start of ETMY CRYp

installation

connect PR3-2 duct

EY

T

TRY

ETMY CRYp installation

starts (9.1-10.31)

AS

REFL

SR3 installation (7.14-12.19)

EYT BRT installation

(7.11-10.2)

PO

S

PRMIFI IMM

Alignment from IMMT to PR3

5

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

CE

YA

SR

MS

R3

SR

2IY

CIY

A

9.11-9.15• beam spot on PR3 has to be off the center

by -5 mm in Y, since there’s no ITM wedge

steer IMMT2 to center

the beam on PRM and PR2

EY

T

TRY

ETMY CRYp installation

(9.1-10.31)

steer PR2 to -5 mm off

in Y from the center of PR3

AS

REFL

SR3 installation (7.14-12.19)

EYT BRT installation

(7.11-10.2)

PO

S

PRMIFI IMM

Alignment from PR3 to Xend

6

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

CE

YA

SR

MS

R3

SR

2IY

CIY

A

9.18-9.22• need to calculate the beam position on

GV windows

EY

T

TRY

ETMY CRYp installation

(9.1-10.31)

steer PR3 to center

the beam on BS and

reach EXA AS

?? mm of the center of GVitmx window

Thorlabs PDA100A

(DC PD)

REFL

Thorlabs PDA100A

(DC PD)

SR3 installation (7.14-12.19)

EYT BRT installation

(7.11-10.2)

PO

S

PRMIFI IMM

Alignment from BS to Yend

7

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

CE

YA

SR

MS

R3

SR

2IY

CIY

A

9.25-9.29• need to calculate the beam position on

GV windows

EY

T

TRY

ETMY CRYp installation

(9.1-10.31)

steer BS to reach EYA AS

?? mm of the center of GVitmy window

+5.6 mm off the center in Y of EXT BRT

(although the beam reach EXT, BRT is not ready

yet at this point)

REFL

Thorlabs PDA100A

(DC PD)

SR3 installation (7.14-12.19)

EYT BRT installation

(7.11-10.2)

PO

S

PRMIFI IMM

Beam Collimation

8

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

CE

YA

SR

MS

R3

SR

2IY

CIY

A

10.2-10.27• measure the beam profile at PR3, PR2

and IXA (or IYA)

• adjust PR2-PR3 lengths if beam looks

bad (we won’t try PRMI at first, so we

don’t have to move PR2/3 if the beam is

not terrible)

EY

T

TRY

ETMY CRYp installation

(9.1-10.31)

beam profiling

(adjust PR2-3 length)

AS

REFL

block so that beam

don’t reach Yend

beam profiling

SR3 installation (7.14-12.19)

EYT BRT installation

done

EYA NAB installation

starts (10.3-11.27)

PO

S

PRMIFI IMM

Align ETMY

9

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

CE

YA

SR

MS

R3

SR

2IY

CIY

A

11.1-11.7• align ETMY right after ETMY CRYp

installation completion

• also align TMSY

EY

T

TRY

ETMY CRYp installation

done

align ETMY so that

the beam reach REFL

AS

REFL

Thorlabs PDA100A

(DC PD)

align TMSY BRT in-vac

(ETMY transmission 5-10ppm;

maybe too dim to align BRT; use green??)

SR3 installation (7.14-12.19)

block so that beam don’t reach SR3SRM installation

starts (10.31-3.2)

slit at EYA for ETMY

alignment

block so that beam

don’t reach Xend

EYA NAB installation

(10.3-11.27)

PO

S

PRMIFI IMM

Align Aux Optics

10

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

CE

YA

SR

MS

R3

SR

2IY

CIY

A

11.8-11.14• align REFL, POP, TRY

EY

T

TRY

AS

REFL

align TRY table optics (maybe too dim)

SR3 installation (7.14-12.19)

block so that beam don’t reach SR3SRM installation

(10.31-3.2)

align REFL table optics

align POP in-vac optics

block so that beam

don’t reach Xend

EYA NAB installation

(10.3-11.27)

PO

S

PRMIFI IMM

Prepare for EY Evacuation

11

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

CE

YA

SR

MS

R3

SR

2IY

CIY

A

11.15-11.21• preparation works before evacuation

• EYA NAB won’t be suspended if no time;

EY evacuation is first priority

EY

T

TRY

AS

REFL

SR3 installation (7.14-12.19)

block so that beam don’t reach SR3SRM installation

(10.31-3.2)

align POP table optics

prepare for EY evacuation

block so that beam

don’t reach Xend

EYA NAB installation

(10.3-11.27)

EY evacuation is priority

PO

S

EY

C

PRMIFI IMM

EY Evacuation

12

EXTEXCEXAPR3 PR2 BS IXC IXA

POP

EY

AS

RM

SR

3S

R2

IYC

IYA

11.22-12.8• monitor beam at REFL, POP, TRY during

evacuation

• (EXT BRT alignment without ETMX; +5.6

mm off the center in Y at EXT)

EY

T

TRY

AS

REFL

SR3 installation (7.14-12.19)

block so that beam don’t reach SR3SRM installation

(10.31-3.2)

evacuate EYA+EYC

TR

X

block so that beam

don’t reach Xend

EXT BRT installation

starts (11.28-2.19)

EYA NAB installation

done (10.3-11.27)

PO

S

EY

C

PRMIFI IMM

EY Cooling Starts

13

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

AS

RM

SR

3S

R2

IYC

IYA

12.8• monitor beam at REFL, POP, TRY, TRX

during cool down

EY

T

TRY

AS

REFL

SR3 installation (7.14-12.19)

block so that beam don’t reach SR3SRM installation

(10.31-3.2)

cool down ETMY

keep GVetmy closed

(we can open this if

we have spare time)

block so that beam

don’t reach Xend

EXT BRT installation

(11.28-2.19)

PO

S

EY

C

PRMIFI IMM

Alignment from BS to AS

14

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

AS

RM

SR

3S

R2

IYC

IYA

12.20-26• align SR3 to center the beam on SR3

(CHECK: how much offset?)

• steer SR3 to center the beam on SR2

• measure beam profile at SR2 and SR3

• AS for Phase 1 is a reflected beam from

SR2, extracted at SR3 chamber

EY

T

TRY

AS

REFL

SR3 installation done

SRM installation

(10.31-3.2)

cool down ETMY

SR3, SR2 alignment

beam profiling

EXT BRT installation

(11.28-2.19)

block so that beam

don’t reach Xend

PO

S

EY

C

PRMIFI IMM

ETMX Installation

15

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

AS

RM

SR

3S

R2

IYC

IYA

1.8-2.2• during ETMX CRYp installation, initial

alignment team have spare time

• we can open GVetmy if we have time

• we can also connect bellows in central

area (but we might have to remove again

for PR2-3 length adjustment for PRMI

mode stabilization, after March)

• note that central area cannot be

evacuated before SRM completion (3.2)

since no GV between BS and SRM

EY

T

TRY

AS

REFL

SRM installation

(10.31-3.2)

cool down ETMY

ETMX CRYp

installation starts

(1.8-2.2)

align AS table optics

(1.15-1.19)

align AS in-vac optics

(1.8-1.12)

connect bellows?

open GVetmy?

block so that beam

don’t reach Xend

EXT BRT installation

(11.28-2.19)

EY

C

PRMIFI IMM

Align ETMX

16

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

AS

RM

SR

3S

R2

IYC

IYA

2.5-2.9• align ETMX right after ETMX CRYp

installation completion

• also, fine align TMSX and TRX

EY

T

TRY

AS

REFL

SRM installation

(10.31-3.2)

cool down ETMY

ETMX CRYp installation

done

align ETMX so that

the beam reach REFL

slit at EXA for

ETMX alignment

EXT BRT installation

(11.28-2.19)

PO

S

EY

C

PRMIFI IMM

Michelson LSC

17

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

AS

RM

SR

3S

R2

IYC

IYA

2.12-2.16• lock Michelson with AS_Q

EY

T

TRY

AS

REFL

SRM installation

(10.31-3.2)

cool down ETMY

lock Michelson

PRM misaligned EXT BRT installation

(11.28-2.19)

PO

S

EY

C

PRMIFI IMM

Prepare for EX Evacuation

18

EXTEXCEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

AS

RM

SR

3S

R2

IYC

IYA

2.19-2.23• preparation works before vacuation

• EXA NAB won’t be suspended if no time;

EX evacuation is first priority

EY

T

TRY

AS

REFL

SRM installation

(10.31-3.2)

cool down ETMY

prepare for EX evacuation

align TMSX BRT in-vac

(2.20-2.26)

EXT BRT installation

done

EXA NAB installation

starts (2.20-2.22)

EX evacuation is priority

PO

S

EXC

EY

C

PRMIFI IMM

EX Evacuation

19

EXTEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

AS

RM

SR

3S

R2

IYC

IYA

2.23-3.2• monitor beam at REFL, POP, TRY, AS

during evacuation

• TRX will be available afterwards

EY

T

TRY

AS

REFL

SRM installation

done (3.2)

cool down ETMY

alignment of TMSX BRT and

TRX table optics (maybe too dim)

evacuate EXA+EXC

keep GVetmx closed

(we can open this if

we have spare time)

align TRX table optics

(2.27-3.5)

PO

S

EXC

EY

C

PRMIFI IMM

EX Cooling, Test Run

20

EXTEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

AS

RM

SR

3S

R2

IYC

IYA

3.2-3.31• monitor beam at REFL, POP, TRY, TRX,

AS during cool down

• keep Michelson locked during cool down

until 3.31

→ Cryogenic Michelson Test Run

(bKAGRA Phase 1 complete)

EY

T

TRY

AS

REFL

cool down ETMY

cool down ETMX

keep Michelson lockedalign TRX table optics

(2.27-3.5)

PO

S

EXC

EY

C

PRMIFI IMM

PRMI

21

EXTEXAPR3 PR2 BS IXC IXA

TR

X

POP

EY

AS

RM

SR

3S

R2

IYC

IYA

Apr-Jun• PR2-PR3 length adjust

• PRMI alignment, locking

• connect remaining bellows/ducts

• evacuate central area

• open GVs (GVsrm should be closed)

EY

T

TRY

AS

REFL

cool down ETMY

cool down ETMX

PR2-PR3 length adjust

(Michelson re-alignment

needed)

lock PRMI

with ASC

PRM alignment

to make PRC

GVsrm: closed

central area evacuation

PO

S

To Be Discussed

22

• TMS BRT installation schedule and other AOS related

issues [Akutsu, Uchiyama, Michimura]

- considering wedge, ETMs should be installed before BRT

alignment, but transmitted beam from ETM is too dim (~ 0.1

uW); use green?

- when to install narrow-angle baffles?

• Wide-angle baffles (for Pcal and main beam) compatible

with ETM HR camera? [Akutsu, Kokeyama, Inoue]

• Confirm beam spot positions at GVs [Michimura, Aso]