Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
ComEd’s Advanced Distribution System Planning
February 2020
Aleksi Paaso, PhDDirector of Distribution Planning, Smart Grid &
Innovation
ComEd, an Exelon Company 2
Our Company:• One of six utilities owned by Exelon• 6,400 Employees• Service Territory: 11,428 square miles
Our Customers:• More than 4.1 million customers in
northern Illinois including the City of Chicago
Our Grid:• Peak Load: 23,753 MW (7/20/2011)• 553,800 distribution transformers• 66,200 circuit miles of primary
distribution• 53% overhead, 43% underground• 5,800 circuit miles of transmission• 93% overhead, 7% underground
Increasing Interconnection Requests Changing Grid 3
Data as of 1/27/2020
Advanced Planning Tools to Integrate DER
4
DER Hosting Capacity Analysis:• Determine DER per feeder that can be accommodated without impacting power quality or reliability under existing control and infrastructure configurations.• After all feeder models were created, they were analyzed to determine Hosting Capacity amount per feeder.
Visualization:
• ComEd displays results via a dynamicscaling that colors to highest hostingcapacity at township, section, quarter-section, sixteenth-section & feeder
4
4
Valuing DER’s Contributions to the Grid
Value to Distribution Grid
• DER value is realized by various parties.
• Several categories of value are potentially realized from DER.
• Some value streams are associated with value to the distribution grid.
• Distribution grid value streams are much more dependent on DER location, type and time.
Consumer
• Total Energy Costs• Demand Changes• Consumer Green Lifestyle• Consumer Backup Generation
Distribution System
• Distribution Capacity• Voltage• Reliability
Transmission System • Transmission Capacity
Wholesale Energy Markets
• Losses • Congestion Costs• Generation Energy• Ancillary Services• Resource Adequacy• RPS Procurement
Society • Societal Avoided Costs• Public Safety Avoided Costs
Environmental
• Emissions• Waste Products• Water Pollution• Siting
5
New Methodology for Valuing DER
Develop forecast
Identify binding constraints
Traditional project to address constraints
Allocated Cost of Capacity (ACC)
Locational Marginal Value
(LMV)
Cost of grid upgrades required
to mitigate overloads and
voltage violations in network
Value of real power, reactive
power and reserve provided by DER
at any point in time
Traditional distribution planning stops here.
6
6
Feeder Model
Battery Size
• Time-series power flow simulations size the battery system (CYME and Python)
Benefit Cost Analysis
• Cost-benefit analysis (MATLAB and Excel/Visual Basic)
• NPV of BESS vs T&D upgrades
Economics
• Battery cost -Argonne National Labs “BatPac” (Excel/Crystal Ball)
• Optimal BESS charge/discharge
• Valuation foroPeak shavingoTime arbitrageoAncillary market
Energy Storage Tool for Planning and Analysis 7
Using Metrics to Identify Optimal Locations for Microgrids
Critical Infrastructure Metric
Capacity Planning Metric
Reliability Metric
Substation MetricResilience Metric
8ComEd developed a resilience metric approach to produce a robust screening for prime locations for microgrid deployment, based on inputs impacting resilience and need for resilient power infrastructure
𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅 𝑀𝑀𝑅𝑅𝑀𝑀𝑀𝑀𝑅𝑅𝑅𝑅 = 𝑎𝑎1 ∗ 𝐶𝐶𝑀𝑀𝑅𝑅𝑀𝑀𝑅𝑅𝑅𝑅𝑎𝑎𝑅𝑅 𝐼𝐼𝑅𝑅𝐼𝐼𝑀𝑀𝑎𝑎𝑅𝑅𝑀𝑀𝑀𝑀𝐼𝐼𝑅𝑅𝐼𝐼𝑀𝑀𝐼𝐼𝑀𝑀𝑅𝑅 𝑀𝑀𝑅𝑅𝑀𝑀𝑀𝑀𝑅𝑅𝑅𝑅 + 𝑎𝑎2 ∗𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑎𝑎𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑀𝑀𝑅𝑅 𝑀𝑀𝑅𝑅𝑀𝑀𝑀𝑀𝑅𝑅𝑅𝑅+ 𝑎𝑎3 ∗ 𝐶𝐶𝑎𝑎𝐶𝐶𝑎𝑎𝑅𝑅𝑅𝑅𝑀𝑀𝑅𝑅 𝑃𝑃𝑅𝑅𝑎𝑎𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑃𝑃 𝑀𝑀𝑅𝑅𝑀𝑀𝑀𝑀𝑅𝑅𝑅𝑅 + 𝑎𝑎4 ∗
𝑆𝑆𝐼𝐼𝑅𝑅𝑅𝑅𝑀𝑀𝑎𝑎𝑀𝑀𝑅𝑅𝑆𝑆𝑅𝑅 𝑀𝑀𝑅𝑅𝑀𝑀𝑀𝑀𝑅𝑅𝑅𝑅where 𝑎𝑎1, 𝑎𝑎2, 𝑎𝑎3, 𝑎𝑎4 are weighing factors for individual metrics
8
8
Bronzeville Community Microgrid (BCM)
•The Bronzeville Community Microgrid enables a green, resilient, sustainable neighborhood for consumers.•7 MW aggregate load, serving approximately 1,000 residences, businesses and public institutions•Installation of first utility-operated microgrid cluster powered by DER including solar PV and energy storage•Demonstration of advanced technologies supported by six grants from the Department of Energy•These technologies have been developed with partnerships with universities, vendors, and national labs
9
9
Advanced Model for Testing Emerging Technology
•Advance modeling capability for hardware in the loop (HIL) test on emerging technology 10
10
GTNET MODBUS 1
GTAO
SEL-3530SEL
GTFPI
3V
CAP Open/Close Status &
Command
MGMS MMC
GTAO GTFPI
CAP Control
Beckwith M6283A
6V+3
I
Intellirupter (IR) Control
Omicron RIR1 Test Interface
S&C IR Control Module (SDA-45405)
GTAO GTDI/DO
Vista Switch (SW.) Control
3V, each 751 (4
relays in total)
AMP
Voltage sensor inputs (low-
voltage)4
4X SEL 751
BESS RTAC
S&C 6802
Digital I/O’s4
SW. Open/Close
Status & Command
SEL-3530SEL
PV RTAC
GTNET DNP
4I, each 751 (4 relays in total)
GTAO GTFPI
GTNET MODBUS 2 GTNET MODBUS 3
DNPDNPDNP
Modbus6
DNP
DNP
DNP
DNP3
Communication with simulated assets
Intellirupter (IR) Control
6V+3
I
Intellirupter (IR) Control
6V+3
I
Intellirupter (IR) Control
6V+3
I
DNP3
TO MGMS
DNP
SEL-3530SEL
DER #1 RTAC
DNP
GTNET DNP
TO MGMS
Modbus6Modbus6
TO MGMS
DNP3
TO SCADA
DNP3
DNP3
TO SCADA
DNP3
TO MGMS
DNP3
TO SCADA
DNP3
TO MGMS
DNP3
TO SCADA
TO SCADA
DNP3
DNPTO SCADA
TO SCADADNP
SCADA Emulator (OCC) and
Reverse Gateway RTAC
AMP
Current sensor inputs (low-voltage)
NOTES:1. The vendor and the model number is TBD.2 3V represents 3 voltage channels.3. Comm. interface may need to be adapted.4. Further details are needed from the vendor.5. The device model number should be confirmed with the vendor.6. The MODBUS connection from the DER RTACs to the RTDS is tentative.7. Each SEL-751 has a separate connection to the RTDS through separate amplifiers.
DNP EthernetModbus Ethernet
LEGEND:
Voltage/Current Amplifier
Analog output (Low-voltage)
Secondary voltage/current (out of amplifier)
AMP
Digital I/O
DNPSEL-3555
Status points
Modbus
RTDSBCM Model
IIT MMC
Datalogger
Siemens MGMS API
RTDS Script
GTAI
Command points
GTAO GTFPIGTAI
Status points
Command points
GTAO GTFPIGTAI GTAO GTFPIGTAI
Status points
Command points
Status points
Command points
DNP
What Advanced Planning Models Enable
Customer Value by Stage
Affordability Reputation Social
Improving reliability for customers by creating a smarter grid that can “self-heal” and minimize disruptions
Ensuring resiliency and security against threats -cybersecurity attacks and extreme weather events
Enabling customers to adopt DER, e.g. solar, storage, and ultimately transact as prosumers in an open marketplace
Achieving climate change objectives, through electrification – transport, business and residential
Providing better city services for citizens – broader infrastructure role, e.g., water, leveraging data and technology
Resiliency and Security
Customer Choice – DER Acceleration
Decarbonization / ElectrificationModernize for Reliability “Connected
Communities”
Resiliency and Security
Customer Choice –DER Acceleration
Decarbonization / Electrification
Modernize for Reliability
“Connected Communities”
11
11