SPOOLABLE INSTALLATION SEQUENC
CONFIDENTIALITY
This manual section is a confidential document which must not be copied in whole or in part or
discussed with anyone outside the Schlumberger organisation.
COILED TUBING COMPLETION
8/12/2019 Coiled Tbg Cmpln
2/9
CONFIDENTIALITY
This manual section is a confidential document which must not be copied in whole or in part ordiscussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion Surface Equipment
Surface equipment rig-up comprises coiled tubing and
pressure control equipment generally used forconventional coiled tubing service operations
Fig. 1. Surface equipment rig-up.
Injector head
Lubricator
Coiled tubing BOP
Gate valve
Coiled tubing hanger
Casing hanger
8/12/2019 Coiled Tbg Cmpln
3/9
CONFIDENTIALITY
This manual section is a confidential document which must not be copied in whole or in part ordiscussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion Well Preparation
Set bottom-hole seal assembly in existing tubing nipple
Flapper valve (closed) provides a pressure barrier
opens when locator seal is stung-in
Back-pressure valve installed in tubing hanger
Nipple down tree
Fig. 2. Well preparation.
Coiled tubing hanger
Casing hanger
Flapper valve (closed)
Seal bore
Sub-surface safety valve (closed)
Production packer
Nipple in production tubing
8/12/2019 Coiled Tbg Cmpln
4/9
CONFIDENTIALITY
This manual section is a confidential document which must not be copied in whole or in part ordiscussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion BHA Preparation
Locator seal assembly (LSA) made-up to coiled tubing
with an external connector
Pump-through pump-off check valve installed on LSA
LSA is long enough to allow required tubing movement
Fig. 3. BHA preparation.
Coiled tubing hanger
Casing hanger
Locator/external connector
Sub-surface safety valve (open)
Locator seal assembly with pump-out plug
Coiled tubing inside production tubing
Flapper valve (closed)
Lock with PBR
8/12/2019 Coiled Tbg Cmpln
5/9
CONFIDENTIALITY
This manual section is a confidential document which must not be copied in whole or in part ordiscussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion Testing Components
Run required length of coiled tubing until the first GLM
and valve are about to leave the spool
Make up a test pump and gauge to the valve port and testthe valve opening pressure
Repeat as required by completion design
Fig. 4. Testing a gas lift valve.
Testing GLV
8/12/2019 Coiled Tbg Cmpln
6/9
CONFIDENTIALITY
This manual section is a confidential document which must not be copied in whole or in part ordiscussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion Spacing Out
With locator engaged in the seal assembly the flapper
valve will be held open
Find neutral point and test downhole seals
Prepare to set coiled tubing hanger
Coiled tubing hanger
Casing hanger
Valve
SPOOLABLE safety valve
Sub-surface safety valve (open)
SPOOLABLE gas lift valve
SPOOLABLE gas lift valve
Locator in place
Flapper valve (open)
Fig. 5. Sting-in space out.
8/12/2019 Coiled Tbg Cmpln
7/9
CONFIDENTIALITY
This manual section is a confidential document which must not be copied in whole or in part ordiscussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion Setting the CT Hanger
Tighten the coiled tubing hanger slips and pack-off to the
set position
Function and pressure test the hanger
Cut the coiled tubing and control line and rig down thecoiled tubing equipment
Fig. 6. Setting the coiled tubing hanger.
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,
,Control line hanger
Slip actuators
Pack-off
Production tubing hanger
Side-port
8/12/2019 Coiled Tbg Cmpln
8/9
CONFIDENTIALITY
This manual section is a confidential document which must not be copied in whole or in part ordiscussed with anyone outside the Schlumberger organisation.
SPOOLABLE Completion Control Line Hanger
Control line cut above CT
Control line is fed through the hanger and hanger is
placed on the CT
Hanger housing is placed over the hanger and made-upto the coiled tubing hanger
Top of assembly is plugged and tested
Fig. 7. Setting the control line hanger.
, ,
, ,
, ,
, ,
, ,
, ,
, ,
, ,
, ,
, ,
, ,
, ,
, ,
, ,
, ,
, ,
,
,
,
,
,
,
,
,
Guides
Coiled tubing
Plug profile
Control line shear ram
Control line port
8/12/2019 Coiled Tbg Cmpln
9/9
CONFIDENTIALITY
This manual section is a confidential document which must not be copied in whole or in part ordiscussed with anyone outside the Schlumberger organisation
SPOOLABLE Completion Completion Configuration
With the test plug in place rig down the CT equipment and
nipple up the tree
Retrieve the test plug with slick-line and prepare to turnwell to production
Coiled tubing hanger
Casing hanger
SPOOLABLE safety valve
Sub-surface safety valve (open)
SPOOLABLE gas lift valve
SPOOLABLE gas lift valve
Locator in place
Flapper valve (open)
Fig. 8. Completion in place.
Valve
Control line hanger