Definition of HTLQ.1 What is High Tide Line ?
Line up to which the highest water line reaches during the spring tide.
Q.2 What is Coastal Regulation zone ?
Coastal stretches of Sea, Bays, Estuaries, Creeks, Rivers and Backwaters which are influenced by the tidal action.
Area between LTL & HTL.
Area upto 500m from HTL
2
Landward limit of CRZ in creeksC.R.Z is extended up to what point inside landward direction,in cases of Rivers, Creeks and Backwaters?
Distance upto which tidal effects are experienced
Concentration levels of five parts per 1000.
3
Width of CRZ belt in creeksWhat is the width of Coastal Regulation zone in case of sea and in case of creeks and rivers and backwaters ?
for sea is 500mt. from the High Tide Line.
for Creeks and backwaters
4
Width of creek Width of CRZ belt
100m or less Up to 100m or less
100-350m 100m
>350m 150m
Prohibited activities in CRZ Prohibited activities in CRZ areas.
Setting up and expansion of existing industries,
Discharging of untreated waste,
Dumping of waste by land filling,
Land reclamation or bunding,
Construction activity in CRZ - I in between Low Tide Line & High Tide Line,
Alteration of sand dunes etc.
5
CRZ - I What are the different zone in Coastal Regulation
zone?
Coastal Regulation zone-I(i)
Areas that are ecological sensitive such as Marine Park, Mangroves, Coral Riffs, etc.
Coastal Regulation zone-I(ii)
Area between the Low Tide Line & High Tide Line.
6
Development in CRZ - I No new construction in Coastal Regulation zone-I
Projects of Department of atomic Energy, Pipelines, Transmission Lines are permitted
In CRZ- I (ii)
which are not ecological sensitive exploration and extraction of natural gas, salt harvesting permitted.
7
CRZ - II Coastal Regulation Zone - II
Developed areas close to the shore line,
Substantially built up areas within legally designated urban areas.
Infrastructure facilities provided.
8
Development in CRZ - II Development permissibility in CRZ - II
Buildings permitted only on
land ward side of existing road or
landward side of existing authorized structure or on
landward side of proposed roads in approved CZMP.
Such bldgs as per existing FSI/FAR norms
9
Development in CRZ - II Reconstruction permitted subject to existing FSI
*(Floor Space Index)/FAR (Floor Area Ratio)norms without change in use
Bldgs. Consistent with surrounding urban landscape & architecture.
Certain relaxations given in latest amendment to Redevelopment of Cessed Structures / MHADA Projects.
12
CRZ - III Coastal Regulation zone - III
Relatively undisturbed & undeveloped areas
Rural areas within municipal limit which are not substantially built up
13
Development in CRZ - III Development permissibility in CRZ - III
0-200m No construction except repairs of authorized structures public utility facilities allowed with permission of state CZMP.
200-500m Development of vacant plots for Hotels /beach resorts with prior approval from MoEF.
Construction / reconstruction of dwelling units within ambit of tradition of rights and customary use such as fishing, villages and gaothans etc.
14
C.Z.M.P.What is Costal Zone Management Plan?
Identifying coastal stretches & classifying them in different CRZ areas.
Integrated development of these areas.
State level coastal management authority responsible for monitoring
17
Coastal Zone Management Plan for Greater Mumbai
18
N
Combined CZMP for Greater Mumbai
submitted to MoEF by GoM Wide letter
No. CS/TPB. 4396/12/CR-
263/96/UD-11 Dated 25th Nov. 1998
& approved by MoEF letter No. J-
17011/8/95-1A .III Dated 19th Jan 2000.
CRZ - I
CRZ - II
CRZ -III
Existing Roads shown as CZMP Roads
Proposed Roads on Land (Not Passing Trough
CRZ) shown as proposed CZMP Roads
Extent of CRZ in Mumbai The approximate areas of CRZ
CRZ – I 146 sq. kms
CRZ - II 42.7 sq. kms
CRZ - III 13.82 sq. kms.