Upload
siva-p
View
224
Download
1
Embed Size (px)
Citation preview
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
1/36
Co-ordination of over current
relays in distribution system
(Prepared by: N.Shahul HameedB.E, EE/P&C,TNEB)
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
2/36
110KV
2600MVA
D
8
7
110/33KV
10MVAZ% = 10.8
5 6
C
B
A
4
3
2 1
2.5MVA 2.5MVA
33/11KV
5MVA
Z% = 6.5Dy1
15.7KM
J0.625 /km
Yy0
33KV
33KV
11KV
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
3/36
The fault MVA of each component For the system (1) MVA = 2600 = 2600 MVA
1 For the 10MVA transformer (2), MVA = 10 = 92.57 MVA 0.108 For theline (3) MVA = 332 = 111 MVA 15.7 x 0.625 For the 5MVA transformer (4), MVA = 5 = 77 MVA
0 .065 Fault level of Bus D = 2600 MVA Fault level of Bus C = 1 = 89.28 MVA 1 + 1 . 2600 92.59 Fault level of Bus B = 1 = 49.48 MVA
1 + 1 + 1 . 2600 92.59 111 Fault level of Bus A = 1 = 49.48 MVA 1 + 1 + 1 + 1 . 2600 92.59 111 77
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
4/36
1
2
3
4
2600MVA (Source)
92.59MVA
111MVA
77MVA
30.12 MVA
49.48 MVA
89.28 MVA
2600 MVAD
C
B
A
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
5/36
ISCA = 30.12 = 1.581 KA
3 x 11 ISCB = 49.48 = 0.8657 KA 3 x 33 ISCC = 89.28 = 1.564 KA 3 x 33
ISCD = 2600 = 13.647 KA 3 x 110
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
6/36
SELECTION FOR CT RATIO :- The CT ratio is selected using the higher of the
following two currents.
the nominal current the maximum short circuit current for which no
saturation is occurred (0.05 x Isc)
Relay 1 &2 : Inom 1 = Inom 2 = Pnom 1 3 x V1 = 2.5 x106 . 3 x 11 x 103
= 131.22 A (referred to 11KV)
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
7/36
Relay No Pnom Isc 0.05 x Isc Inom CT Ratio MVA A A A
1 & 2 2.5 1581.21 79.06 131.22 150/5
3 5 1581.21 79.06 262.44 300/5
4 5 866.37 43.32 87.48 100/5
5 5 1564.42 78.22 87.48 100/5
6 5 1564.42 78.22 87.48 100/5
7 10 1564.42 78.22 174.96 200/5
8 10 13646.41 682.32 52.49 700/5
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
8/36
SETTING OF INSTANTANEOUS UNITS OF OVERCURRENT RELAYS :-.
Lines and sub-stations :- The setting of instantaneous units is carried out by
taking at least 125% of the maximum fault level at thenext sub-station. The procedure must be started from the
farthest sub-station, and continued by moving backtowards the source. When the characteristic of tworelays cross at a particular system fault level, thusmaking it difficult to obtain correct co-ordination, it isnecessary to set the instantaneous unit at the sub-
station that is farthest away from the source to such avalue that the relay operates for slightly lower level ofcurrent. 25% margin avoids overlapping the downstreaminstantaneous unit.
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
9/36
Distribution lines:-
Since the distribution lines are the end of the system anyone of the following criteria may be adopted.
i) 50% of the maximum fault current at the point of
connection of the CT supplying relay.
ii) Between six and ten times of the maximum loadcurrent.
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
10/36
Transformer units:- The instantaneous units of over current relays on the
primary side of the transformer should be set between125 and 150% of the short circuit current at the bus bar
on the secondary side, referred to the primary side. If the
instantaneous units of the transformer secondary and
feeder relays are subjected to same short circuit levelthen the transformer secondary instantaneous over
current unit needs to be overridden to avoid loss of co-
ordination.
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
11/36
CALCULATION OF INSTANTANEOUS SETTING:
Relays 1 & 2
Iinst = 0.5 x Isc = 0.5 x1581.21 = 790.6 A (Primary)
ie = 790.6 x 5/150 = 26.35A (Secondary)
Set the relay at 27A secondary amps equivalent to 810Aprimary amps.
Relay 3 The instantaneous unit is overridden to avoid thepossibility of loss of co-ordination.
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
12/36
Relay 4
The setting is based on 125% of the short circuitcurrent that exists at the busbar on the low voltage sideof the transformer, referred to the high voltage side.
Iinst = 1.25 x1581.21 x (11/33) = 658.84 A
primary ampsie =658.84 x(5/100) = 32.94A
secondary amps
Set 33 amps equivalent to 660 primary amps
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
13/36
Relay 5 The setting is calculated on the basis of 125% of the
current for the maximum fault level that exists at the nextdownstream substation.
Iinst = 1.25 x 866.37 =1082.96 A primary amps
ie = 1082.96 x (5/100) = 54.15A secondary amps Set 55 amps equivalent to 1100 primary
amps.
Relay 6 Iinst = 1000 A primary amps ie = 50A secondary amps
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
14/36
Relay7 The instantaneous unit is overridden to avoid
the possibility of loss of co-ordination.
Relay 8 The setting is calculated on the basis of 125% of the
current for the maximum fault level that exists at the nextdownstream substation referred to the high voltage side
Iinst = 1.25 x 1564.42 x (33/110)
= 586.66 A primary amps
ie = 586.66 x (5/700)
= 4.19A secondary amps
Set at 6 secondary amps (the minimum setting)equivalent to 840 primary amps.
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
15/36
PICK-UP SETTING:
The pick-up setting or plug setting is determined by thefollowing expression.
Pickup setting = OLF x Inom
CTR
OLF = over load factor, CTR = CT ratio
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
16/36
The overload factor(OLF) recommended for variouscircuits are given below.
For phase fault relays: For motor 1.05 For lines, generator, and transformers 1.25 to 1.5
For distribution feeders under emergency condition 2
For earth fault relays: For lines, generator, and transformers 0.2
For transmission lines 0.1 For distribution feeders 0.3
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
17/36
Calculation of pick-up settings: PU = OLF x Inom
CTR Relay 1 &2 PU 1,2 =1.5 x 131.22 x (5/150) =6.56;
set at 7
Relay 3 PU 3 =1.5 x 262.44 x (5/300) =6.56;set at 7
Relay 4 PU 4 =1.5 x 87.48 x (5/100) =6.56;set at 7
Relay 5 PU 5 =1.5 x 87.48 x (5/100) =6.56;set at 7
Relay 6 PU 6 =1.5 x 87.48 x (5/100) =6.56;set at 7
Relay 7 PU 7 =1.5 x 174.96 x (5/200) =6.56;set at 7
Relay 8 PU 8 =1.5 x152.49 x (5/700) =0.56;set at 1
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
18/36
TIME MULTIPLIER SETTING :
The criteria procedure for calculating the timemultiplier setting (TMS) to obtain appropriate protectionand co-ordination for the system are given below.
determine the required operating time t1 of the relay
farthest away from the source by choosing the lowertime multiplier setting and considering the fault level forwhich the instantaneous unit of this relay picks up. Thismay be higher if it is necessary to co-ordinate withdevices installed downstream. eg. Fuses or reclosersand condition like cold load pick-up.
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
19/36
determine the required operating time of the relayassociated with the next upstream breaker t2a = t1 +tmargin. Use the same fault level that used to
determine t1 of the relay associated with the previousbreaker for this calculation also.
For the same fault current as in 1 above and knowingt2a and pick-up value for relay 2, calculate time
multiplier setting of the relay 2.
Determine the operating time t2b of relay 2, but nowusing the fault level just before the operation of itsinstantaneous unit.
Continue with the sequence, starting from the secondstage.
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
20/36
Time discrimination margin :
A discrimination margin between twosuccessive time characteristic of the order of 0.2to 0.4s should be typically used.
The operating time of the relay can beobtained from the operating characteristic onlog-log paper or from the mathematical formulagiven below.
t = k + L (I/Is) - 1
Where I = fault current, Is = pick-up setting. K = time multiplier setting, L a constant t = relay operating time in sec
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
21/36
By knowing the PSM and operating time theequation can be solved for TMS
Curve description standard LModerately inverse IEEE 0.02 0.0515 0.114Very inverse IEEE 2 19.16 0.491Extremely inverse IEEE 2 28.2 0.1217inverse CO8 2 5.95 0.18
Short time inverse CO2 0.02 0.0239 0.0169Standard inverse IEC 0.02 0.14 0Very inverse IEC 1 13.5 0Extremely inverse IEC 2 80 0Long time inverse IEC 1 120 0
By knowing the PSM and operating time theequation can be solved for TMS
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
22/36
CALCULATION OF TIME MULTIPLIER SETTIG
Characteristic used - IEC very inverse time Constants used for operating time of inversecharacteristic is
= 13.5, = 1, and L = 0
Substituting the constants in the characteristic reducesto
t = k x 13.5 + 0
(I/Is)1 - 1
k x 13.5
PSM - 1
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
23/36
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
24/36
Relay 3 The relay backs up relay 1 and 2
Use a grading margin of 0.4sec There fore the required operating time is t3a =0.24+0.4 = 0.64
PSM is based on 810 primary amps associated theinstantaneous setting of relays 1 & 2
So PSM3a = 810 x(1/CTR3) x (1/PU3)= 810 x (5/300) x(1/7) = 1.928 times
k = (PSM 1) x t3a
13.5= (1.928 1) x 0.64 = 0.04 say0.0513.5 (minimum setting)
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
25/36
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
26/36
Relay 4
The relay 4 backs up relay 3 Use a grading margin of 0.4sec Hence the required operating time is t4a = 0.3+0.4 =0.7 PSM4a is based on 1581.21 primary amps of the CT
associated with relay 3
So PSM4a = 1581.21 x (11/33) x (5/100) x (1/7)= 3.764 times
With PSM4a = 3.764 and backup time of 0.7k = (3.764 1) x 0.7 = 0.1413.5
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
27/36
It is now necessary to calculate the operating time ofrelay 4 just before the operation of the instantaneous
unit.
PSM4b = Iinst.prim4 x (1/CTR4) x (1/PU4)
= 660 x (5/100) x (1/7) = 4.714 times
With time multiplier setting 0.14 and PSM4b 4.714
t4b = 0.14 x 13.5 = 0.51sec
4.714 - 1
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
28/36
Relay 5
The relay 5 backs up relay 4 Use a grading margin of 0.4sec
Hence the required operating time is t5a=0.51+0.4=0.91
PSM5a is based on 660 primary amps of the CTassociated with relay 4
So PSM5a = 660 x (5/100) x (1/7)
= 4.714 times
With PSM5a = 4.714 and backup time of 0.91k = (4.714 1) x 0.91 = 0.25
13.5
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
29/36
It is now necessary to calculate the operating time ofrelay 5 just before the operation of the instantaneous
unit.
PSM5b = Iinst.prim5 x (1/CTR5) x (1/PU5)
= 1100 x (5/100) x (1/7) = 7.857 times
With time multiplier setting 0.25 and PSM5b 7.857
t5b = 0.25 x 13.5 = 0.492sec
7.857 - 1
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
30/36
Relay 6
Time multiplier setting = 0.3 (assume slightlyhigher setting than relay 5 for clarity of problem
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
31/36
Relay 7
Relay 7 backs up relay 5 & 6 and should becoordinated with the slower of these two relays.
Relay 5 has an instantaneous setting of 1100primaryamps and relay 6 has an instantaneous setting of 1000primary amps. Therefore the operating of both the relays
should be calculated for 1000 primary amps current.
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
32/36
Relay 5; PSM5 = 1000 x (5/100) x 1/7) = 7.14 times With PSM = 7.14 and time dial setting 0.25
t5 = 0.25 x 13.5 = 0.55sec
7.14 - 1
Relay 6; PSM6 = 1000 x (5/100) x 1/7) = 7.14 times
With PSM = 7.14 and time dial setting 0.3
t6 = 0.3 x 13.5 = 0.66sec
7.14 - 1
The slower relay is relay 6
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
33/36
Therefore, in order to be slower than relay 6, the back uptime of relay 7 should be
t7a = 0.66+0.4 = 1.06 sec
PSM7a is based on the 1000 primary amps of the CTassociated with relay 6
So, PSM7a = Iinst.prim7 x (1/CTR7) x (1/PU7)= 1000 x (5/200) x (1/7)
= 3.57 times
With PSM7a = 3.57 and backup time of 1.06 seck = (3.57 1) x 10.6 = 0.2
13.5
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
34/36
As the instantaneous unit is overridden, themultiplier PSM7b is calculated using the current for a
short circuit on busbar C
So, PSM7b = Isc x (1/CTR7) x (1/PU7)
= 1564.42 x (5/200) x (1/7)
= 5.5 times
With time multiplier setting 0.2 and PSM7b 5.5
T7b = 0.2 x 13.5 = 0.6sec5.5 - 1
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
35/36
Relay 8
The relay 8 backs up relay 7 Use a grading margin of 0.4sec Hence the required operating time is t8a = 0.6+0.4
= 1.0 sec
PSM8a is based on 1564.42, the short circuit current ofbusbar C referred to 110 KV bus, since theinstantaneous unit of relay 7 is overridden.
So PSM8a = 1564.42 x (33/110) x (5/700) x (1/1)= 3.35 times
With PSM8a = 3.35 and backup time t8a = 1k = (3.35 1) x 1 = 0.17
13.5
7/27/2019 Co-Ordination of Over Current Relays in Distribution System
36/36
Table 2 Summery of setting
Rno CT R pickup Tms Instpri sec
1&2 130/5 7 0.05 810 27
3 300/5 7 0.05 overridden
4 100/5 7 0.14 600 335 100/5 7 0.25 1100 55
6 100/5 7 0.3 1000 50
7 200/5 7 0.2 overridden
8 700/5 1 0.17 840 6