STORAGE
QtreeCreation
This document contains proprietary information of Wipro Infotech – MIT. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means, whether electronic, mechanical, photocopying, recording or otherwise, without the prior written permission of Wipro Infotech – MIT. The information contained herein is confidential to Wipro Infotech – MIT and <Customer Name> and shall not be distributed to any persons other than those involved in the assessment and delivery of services. Wipro Infotech – MIT reserves the right to revise and update this document as and when required. Wipro Infotech – MIT reserves the right to withdraw the document excluding customer specific information at the time of termination of services.
All product names referenced herein are trademarks of their respective companies.
Document Management Information
Document Title : QTreeCreation
Document Status : Draft / Review / Approval / Final
Document Publication History
(All revisions made to this document must be listed in chronological order)
Version
Date Author(s) Remarks
1.0 Praveen Motupalle Draft Document
Document Review and Approval History
(All revisions must be approved. Review and Approval can be done by an internal source or by the customer)
Version
Date Reviewer & Approver Remarks
Document Distribution List
S.No Name and Company Purpose
1
2
TABLE OF CONTENT
1. Purpose.................................................................................................................12. Scope....................................................................................................................13. Definition..............................................................................................................14. Procedure\ Process................................................................................................15. Metric / Acceptable Limits.....................................................................................86. Defect Definition...................................................................................................87. Incident Handing Process......................................................................................88. Escalation Matrix...................................................................................................89. Exceptions............................................................................................................810. Ownership and Responsibilities.............................................................................811. Compliance...........................................................................................................812. Enforcement.........................................................................................................813. Changes to Policy..................................................................................................914. Frequency of Review.............................................................................................915. Reference..............................................................................................................9
Qtree Creation DOCUMENT ID CN.STR_NETAPP.7.15
STORAGEVERSION NO. 1.0
EFFECTIVE DATE
1. Purpose
This SOP would give clear and complete steps required for Creation of Qtree on gefilers on INDGE Domain
2. Scope
All filer of Genpact on INDGE Domain
3. Definition
None
4. Procedure\ Process
Approvals:
ActivityFirst Level Approval
Second Level Approval
Third Level Approval
Share folder creation IT CoE FP&A N/AShare folder creation more than 50GB
Vivek GuptaFP&A ITCOE
CN Confidential Page 1 of 9
Qtree Creation DOCUMENT ID CN.STR_NETAPP.7.15
STORAGEVERSION NO. 1.0
EFFECTIVE DATE
Step 1: Go to Filerview click on Volume Qtree Add
Step 2: Select the volume name form the drop down list on which you want to create the qtreeStep 3: Give the qtree name (check for the naming convention)Step 4: Security style should be NTFS as we only have CIFS (windows) shares in GenpactStep 5: Click Add button to finish creating the qtree
Note on Oplocks:
Oplocks (opportunistic locks) enable the redirector on a CIFS client in certain file-sharing scenarios to perform client-side caching of read-ahead, write-behind, and lock information. A client can then work with a file-read or write it) without regularly reminding the server that it needs access to the file in question, which improves performance by reducing network traffic.
CN Confidential Page 2 of 9
Qtree Creation DOCUMENT ID CN.STR_NETAPP.7.15
STORAGEVERSION NO. 1.0
EFFECTIVE DATE
By default, oplocks are enabled for each qtree. If you disable oplocks for the entire filer, oplocks are not sent even if you enable oplocks on a per-qtree basis
After creating the qtree we need to assign the quota to that qtree to restrict the space usage on the quota tree/volume.
Go to Quota Add and you see the following screen.
We are going to assign the quota to qtree. Select the quota type as tree. Select quota volume and click next:
On the following screen provide the soft limit and the hard limit for the quota and threshold as well.
CN Confidential Page 3 of 9
Qtree Creation DOCUMENT ID CN.STR_NETAPP.7.15
STORAGEVERSION NO. 1.0
EFFECTIVE DATE
Once done just click on the commit button and the quota is applied. We need to restart the quota to enable the quota limit on the following screen. (Quota Manage)
CN Confidential Page 4 of 9
Qtree Creation DOCUMENT ID CN.STR_NETAPP.7.15
STORAGEVERSION NO. 1.0
EFFECTIVE DATE
CN Confidential Page 5 of 9
Qtree Creation DOCUMENT ID CN.STR_NETAPP.7.15
STORAGEVERSION NO. 1.0
EFFECTIVE DATE
CN Confidential Page 6 of 9
Qtree Creation DOCUMENT ID CN.STR_NETAPP.7.15
STORAGEVERSION NO. 1.0
EFFECTIVE DATE
It is mandatory to update the share Description here. Update the Description with the SR Ticket Number.
CN Confidential Page 7 of 9
Qtree Creation DOCUMENT ID CN.STR_NETAPP.7.15
STORAGEVERSION NO. 1.0
EFFECTIVE DATE
5. Metric / Acceptable Limits
Adherence to the process will be considered as acceptable limits.
6. Defect Definition
Non adherence to the process will be considered as defect definition.
7. Incident Handing Process
For all incidents, team will follow the incident handling process (Clarify System) (Wherever Applicable)
8. Escalation Matrix
All escalation will follow-up the laid down ITIL escalation matrix.
9. Exceptions
None.
10. Ownership and Responsibilities
It is the responsibility of the CST SR team to keep the document updated at all times.
11. Compliance
It is the responsibility of the CST SR team to adhere to this policy and ensure compliance with the standards setup in this policy.
12. Enforcement
Any employee found to have violated this policy may be subject to disciplinary action, up-to and including termination of employment
13. Changes to Policy
CN Confidential Page 8 of 9
Qtree Creation DOCUMENT ID CN.STR_NETAPP.7.15
STORAGEVERSION NO. 1.0
EFFECTIVE DATE
Any change in the above policy should be approved by Change Control Board of Genpact as they are the final authority for making changes in the policy document.
14. Frequency of Review
The policy documents needs to be reviewed by the functional leader at least once in a year.