CMT3212 Chapter 4

Embed Size (px)

Citation preview

  • 7/29/2019 CMT3212 Chapter 4

    1/4

    CMT3212 Measurement of Construction Works I KIST Level 2/1

    | P a g e

    4.0 Measurement of Substructure

    4.1 Introduction

    Substructure is a term used to indicate all

    supporting building work in the groundbelow a specific demarcation line, usually the

    damp proof course.

    The substructure therefore includes the

    following trades or work sections.

    1. SITE PREPARATION.2. EXCAVATION.3. DISPOSAL OF WATER.4. PLANKING AND STRUTTING.5. HARDCORE FILLING.6. PLAIN CONCRETE AND

    REINFORCED CONCRETE.

    7. REINFORCEMENT.8. FORMWORK.9. PRECAST CONCRETE UNITS.10.WALLING.11.DPC.

    The above follow the order in which the

    items of work appear in the SMM.

    4.2 Site Preparation

    Site preparation is one of the first operations

    carried out on a site. SMM clauses D2, D3

    and D4 provide the rules for measurement of

    anti-termite treatment, preservation of

    vegetable soil and removal of trees, hedges,

    bushes and scrub and tree stumps.

    (1)Anti-termite treatment to sub-soil orfilling is measured in square metres

    (SMM D2 (a)). The removal of termite

    nests shall be given as an item and the

    method of destruction of the termites

    stated.

    (2)Oversite excavation is measured tothe extreme dimensions of the

    building including the splash apron.

    Excavating vegetable soil which is to

    be preserved shall be measured insquare metres stating the average

    thickness (SMM D3). If there is no top

    soil (vegetable soil) or if the vegetable

    soil is not preserved then the

    resultant excavation is measured as

    reduce level excavation either in m2

    or m3 as per SMM D6.

    The oversite excavation must be

    completed before the measurement

    of excavation of trenches or pits of

    which the depth is calculated from

    this reduced level (also known as the

    commencing level of excavation).

    (3)Clearing the site of vegetation such astrees, bushes and scrub or hedges is

    measured in either square meters,

    enumerated or in linear metresdepending on the convenient unit of

    measurement. Trees over 600 mm

    girth, and tree stumps (stating thegirth) shall be enumerated. The girth

    is measured at a height of 1m from

    the ground (SMM D4 (a), (c), (d) and

    (e). Cutting down hedges is measured

    in linear metres (SMM D4 (b) while

    clearing the site of bushes is measured

    in square metres (SMM D4 (c).

    4.3 Excavation

    In the measurement of excavations, it should

    be noted that the quantities are measured

    nett without addition or allowance for

    bulking and shrinking (SMM D5 (a)), and

    working space (SMM D5 (g)).

    Excavation is therefore measured to the

    shape shown on the drawings. Any working

    space required and any bulking of the soil will

    be included in the unit rate of theexcavations by the estimators.

  • 7/29/2019 CMT3212 Chapter 4

    2/4

    CMT3212 Measurement of Construction Works I KIST Level 2/1

    | P a g e

    Picture showing an excavated trench for

    foundation.

    Excavating trenches to receive foundations is

    measured in cubic metres (SMM D9) stating

    the starting level and the depth in 1.5 mstages (SMM D5 (f).

    Excavating pits to receive bases shall be

    measured in cubic metres (SMM D10) stating

    the starting level and the depth as

    aforementioned.

    Earth backfilling and Surplus spoil shall each

    be given in cubic metres (SMM D15 (c) and

    (f) respectively.

    4.4 Disposal of Water

    Keeping excavations free from water (i.e all

    water except spring or running water) shall

    be given as an item (SMM D18 (a).

    4.5 Planking and Strutting

    Picture showing upholding the surfaces ofexcavations.

    Planking and strutting to uphold the sides of

    excavations shall be measured as an item(SMM D19).

    4.5 Hardcore Filling

    Hardcore is either measured in m2 or m3

    depending on whether or not it is more than

    300 mm thick. Hardcore is measured as

    equal to the void to be filled (i.e between the

    walls).

    Picture showing hardcore filling. Notice thehardcore is placed between the walls.

    Hardcore less 300 mm thick is measured in

    m2 stating the thickness (SMM D20).

    4.6 Plain and Reinforced Concrete

    Picture showing pouring of concrete infoundations in trenches.

    Plain in-situ concrete shall be given under an

    appropriate heading (SMM F2 (a)). Reinforcedconcrete shall be given under an appropriate

    heading (SMM F2 (b)).

  • 7/29/2019 CMT3212 Chapter 4

    3/4

    CMT3212 Measurement of Construction Works I KIST Level 2/1

    | P a g e

    Generally for Concrete the following shall be

    included in the description SMM F1.

    (i) Kind and quality of materials forconcrete.

    (ii) Any tests of the material.(iii) Any tests of the finished work.(iv) Composition and mix (or strength

    requirements) of the concrete.

    (v) Any additives e.g. accelerators,retarders, waterproofing agents

    and the like.

    Concrete works are measured as follows:-

    Item Unit

    Foundations to columns,piers etc m3 Ground beams m3 Machine bases m3 Beds over 300 mm thick m3 Beds less than 300 mm thick m2 Walls over 300 mm thick m3 Walls less than 300 mm

    thickm2

    Suspended floors and roofs m2 Beams and columns m3 Steps and staircases m3

    Concrete required to be consolidated by aparticular method (e.g. mechanically tamped,

    vibrated) shall be so described.

    Picture showing formwork to columns andedges of slab and a complete surface bed.

    Concrete in foundations is measured to the

    exact dimensions shown on the drawings.

    4.7 Reinforcement

    Bar reinforcement (measured as executed)

    including links, stirrups, binders, special

    spacers shall be measured in kg. Bends,

    hooks, tying wire, distance blocks and

    ordinary spacers shall be given in the

    description. In addition twisted bars or high-

    tensile steel bars shall be so described (SMM

    F16).

    Picture showing mesh fabric reinforcement and damp

    proof membrane before poring of surface concrete.

    Fabric reinforced shall be measured as to the

    area covered without giving allowance for

    laps. For fabric reinforcement, the mesh, the

    weight per 1 square metres and the minimum

    extent of side and end laps shall be described(SMM F17).

    4.8 Formwork

    Formwork shall be measured as the actual

    surfaces of the finished structure which

    require to be supported during thedisposition of the concrete.

    Generally, formwork is measured in square

    metres except to the following surfaces:-

  • 7/29/2019 CMT3212 Chapter 4

    4/4

    CMT3212 Measurement of Construction Works I KIST Level 2/1

    | P a g e

    Edges and risers Edges of beds,roads, footpaths, suspended floors,

    landings, roof, risers of staircases etc

    shall be measured in linear metres in

    stages of 75 mm.

    Formwork to bands and cornices ismeasured in linear metres (SMM F22). Formwork to chases, mouldings etc

    ((SMM F23).

    4.9 Precast Concrete Units.

    Generally, the following shall be given in the

    description (SMM F25).

    (i) Kind, quality and size ofreinforcement.

    (ii) Shape of cross-section of unit.(iii) Nature and extent of surface

    finish.

    (iv) Composition and mix of joiningand bedding materials.

    (v) Method of fixing.4.10 Walling

    Walling shall consist of bricks/blocks/stone

    laid in mortar e.g.

    Solid concrete blockwork. Hollow concrete blockwork. Natural stone. Brickwork

    Walling shall be measured in square metres

    stating the thickness (SMM G4).

    Particulars of the following shall be given:-

    Material, kind, type, finish and size ofthe blocks or blocks.

    Any requirements as to the stone andthe quarry.

    Type of bond of the brickwork:-o English bond,o Stretcher bond,o English Garden bondo Header bondo Flemish bond etc.

    Composition and mix of mortar forbedding and joining:-

    1:3 Cement: sand

    1:4 Cement: sand

    1:5 Cement: sand

    1:6 Cement: sand

    1:1:6 Cement: lime: sand1:2:9 Cement: lime: sand

    4.11 DPC.

    Particulars of the following shall be given

    (SMM G96):

    (i) Kind and quality of the damp-proof materials.

    (ii) Gauge, thickness or substance(e.g. weight per square metre) ofsheet material.

    (iii) Number of layers.(iv) Composition and mix of bedding

    material.

    Examples of Descriptions are shown on

    Plate 3