Upload
emmanuel-wamalwa-mumu
View
215
Download
0
Embed Size (px)
Citation preview
7/29/2019 CMT3212 Chapter 4
1/4
CMT3212 Measurement of Construction Works I KIST Level 2/1
| P a g e
4.0 Measurement of Substructure
4.1 Introduction
Substructure is a term used to indicate all
supporting building work in the groundbelow a specific demarcation line, usually the
damp proof course.
The substructure therefore includes the
following trades or work sections.
1. SITE PREPARATION.2. EXCAVATION.3. DISPOSAL OF WATER.4. PLANKING AND STRUTTING.5. HARDCORE FILLING.6. PLAIN CONCRETE AND
REINFORCED CONCRETE.
7. REINFORCEMENT.8. FORMWORK.9. PRECAST CONCRETE UNITS.10.WALLING.11.DPC.
The above follow the order in which the
items of work appear in the SMM.
4.2 Site Preparation
Site preparation is one of the first operations
carried out on a site. SMM clauses D2, D3
and D4 provide the rules for measurement of
anti-termite treatment, preservation of
vegetable soil and removal of trees, hedges,
bushes and scrub and tree stumps.
(1)Anti-termite treatment to sub-soil orfilling is measured in square metres
(SMM D2 (a)). The removal of termite
nests shall be given as an item and the
method of destruction of the termites
stated.
(2)Oversite excavation is measured tothe extreme dimensions of the
building including the splash apron.
Excavating vegetable soil which is to
be preserved shall be measured insquare metres stating the average
thickness (SMM D3). If there is no top
soil (vegetable soil) or if the vegetable
soil is not preserved then the
resultant excavation is measured as
reduce level excavation either in m2
or m3 as per SMM D6.
The oversite excavation must be
completed before the measurement
of excavation of trenches or pits of
which the depth is calculated from
this reduced level (also known as the
commencing level of excavation).
(3)Clearing the site of vegetation such astrees, bushes and scrub or hedges is
measured in either square meters,
enumerated or in linear metresdepending on the convenient unit of
measurement. Trees over 600 mm
girth, and tree stumps (stating thegirth) shall be enumerated. The girth
is measured at a height of 1m from
the ground (SMM D4 (a), (c), (d) and
(e). Cutting down hedges is measured
in linear metres (SMM D4 (b) while
clearing the site of bushes is measured
in square metres (SMM D4 (c).
4.3 Excavation
In the measurement of excavations, it should
be noted that the quantities are measured
nett without addition or allowance for
bulking and shrinking (SMM D5 (a)), and
working space (SMM D5 (g)).
Excavation is therefore measured to the
shape shown on the drawings. Any working
space required and any bulking of the soil will
be included in the unit rate of theexcavations by the estimators.
7/29/2019 CMT3212 Chapter 4
2/4
CMT3212 Measurement of Construction Works I KIST Level 2/1
| P a g e
Picture showing an excavated trench for
foundation.
Excavating trenches to receive foundations is
measured in cubic metres (SMM D9) stating
the starting level and the depth in 1.5 mstages (SMM D5 (f).
Excavating pits to receive bases shall be
measured in cubic metres (SMM D10) stating
the starting level and the depth as
aforementioned.
Earth backfilling and Surplus spoil shall each
be given in cubic metres (SMM D15 (c) and
(f) respectively.
4.4 Disposal of Water
Keeping excavations free from water (i.e all
water except spring or running water) shall
be given as an item (SMM D18 (a).
4.5 Planking and Strutting
Picture showing upholding the surfaces ofexcavations.
Planking and strutting to uphold the sides of
excavations shall be measured as an item(SMM D19).
4.5 Hardcore Filling
Hardcore is either measured in m2 or m3
depending on whether or not it is more than
300 mm thick. Hardcore is measured as
equal to the void to be filled (i.e between the
walls).
Picture showing hardcore filling. Notice thehardcore is placed between the walls.
Hardcore less 300 mm thick is measured in
m2 stating the thickness (SMM D20).
4.6 Plain and Reinforced Concrete
Picture showing pouring of concrete infoundations in trenches.
Plain in-situ concrete shall be given under an
appropriate heading (SMM F2 (a)). Reinforcedconcrete shall be given under an appropriate
heading (SMM F2 (b)).
7/29/2019 CMT3212 Chapter 4
3/4
CMT3212 Measurement of Construction Works I KIST Level 2/1
| P a g e
Generally for Concrete the following shall be
included in the description SMM F1.
(i) Kind and quality of materials forconcrete.
(ii) Any tests of the material.(iii) Any tests of the finished work.(iv) Composition and mix (or strength
requirements) of the concrete.
(v) Any additives e.g. accelerators,retarders, waterproofing agents
and the like.
Concrete works are measured as follows:-
Item Unit
Foundations to columns,piers etc m3 Ground beams m3 Machine bases m3 Beds over 300 mm thick m3 Beds less than 300 mm thick m2 Walls over 300 mm thick m3 Walls less than 300 mm
thickm2
Suspended floors and roofs m2 Beams and columns m3 Steps and staircases m3
Concrete required to be consolidated by aparticular method (e.g. mechanically tamped,
vibrated) shall be so described.
Picture showing formwork to columns andedges of slab and a complete surface bed.
Concrete in foundations is measured to the
exact dimensions shown on the drawings.
4.7 Reinforcement
Bar reinforcement (measured as executed)
including links, stirrups, binders, special
spacers shall be measured in kg. Bends,
hooks, tying wire, distance blocks and
ordinary spacers shall be given in the
description. In addition twisted bars or high-
tensile steel bars shall be so described (SMM
F16).
Picture showing mesh fabric reinforcement and damp
proof membrane before poring of surface concrete.
Fabric reinforced shall be measured as to the
area covered without giving allowance for
laps. For fabric reinforcement, the mesh, the
weight per 1 square metres and the minimum
extent of side and end laps shall be described(SMM F17).
4.8 Formwork
Formwork shall be measured as the actual
surfaces of the finished structure which
require to be supported during thedisposition of the concrete.
Generally, formwork is measured in square
metres except to the following surfaces:-
7/29/2019 CMT3212 Chapter 4
4/4
CMT3212 Measurement of Construction Works I KIST Level 2/1
| P a g e
Edges and risers Edges of beds,roads, footpaths, suspended floors,
landings, roof, risers of staircases etc
shall be measured in linear metres in
stages of 75 mm.
Formwork to bands and cornices ismeasured in linear metres (SMM F22). Formwork to chases, mouldings etc
((SMM F23).
4.9 Precast Concrete Units.
Generally, the following shall be given in the
description (SMM F25).
(i) Kind, quality and size ofreinforcement.
(ii) Shape of cross-section of unit.(iii) Nature and extent of surface
finish.
(iv) Composition and mix of joiningand bedding materials.
(v) Method of fixing.4.10 Walling
Walling shall consist of bricks/blocks/stone
laid in mortar e.g.
Solid concrete blockwork. Hollow concrete blockwork. Natural stone. Brickwork
Walling shall be measured in square metres
stating the thickness (SMM G4).
Particulars of the following shall be given:-
Material, kind, type, finish and size ofthe blocks or blocks.
Any requirements as to the stone andthe quarry.
Type of bond of the brickwork:-o English bond,o Stretcher bond,o English Garden bondo Header bondo Flemish bond etc.
Composition and mix of mortar forbedding and joining:-
1:3 Cement: sand
1:4 Cement: sand
1:5 Cement: sand
1:6 Cement: sand
1:1:6 Cement: lime: sand1:2:9 Cement: lime: sand
4.11 DPC.
Particulars of the following shall be given
(SMM G96):
(i) Kind and quality of the damp-proof materials.
(ii) Gauge, thickness or substance(e.g. weight per square metre) ofsheet material.
(iii) Number of layers.(iv) Composition and mix of bedding
material.
Examples of Descriptions are shown on
Plate 3