CM_ Bored Pile, MSE Wall, Drainage Structures

Embed Size (px)

Citation preview

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    1/30

    Construction Method

    PART F - BRIDGE CONSTRUCTION

    1. SCOPE OF WORK

    This item shall consist of the construction of three (3) bridges;

    Bridges Name Length (mts.) Type of Span Foundation

    Sta. Cruz Bridge 1 280.0Pre-stressed

    Concrete GirderBored Pile

    Sta. Cruz Bridge 2 15.0Pre-stressed

    Concrete GirderBored Pile

    Matalaba Bridge 15.0Pre-stressed

    Concrete GirderBored Pile

    2. EQUIPMENT

    Bored Piling

    Crawler Crane

    Auger

    Cleaning bucket

    Vibratory Hammer

    Generator

    Concrete Production

    Concrete B/PGenerator

    Wheel Loader

    Water Truck

    Concrete Pouring

    Transit Mixer

    Concrete Pump

    Engine Vibrator

    Water Truck

    R.S Bar/ Steel Cage

    Bar Bender

    Bar Cutter

    Fork LiftCargo Truck

    Generator

    Acetylene

    Welding Machine

    3. MANPOWER

    Field Engineer

    Operator

    Driver

    Skilled Laborer

    Common Laborer

    4. CONSTRUCTION SEQUENCE

    Hanjin Heavy Industries and Const. Co. LTD.

    1

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    2/30

    Construction Method

    4.1 SURVEY WORK

    Carry out initial topographic survey of the project to establish the existing

    levels and record all details as necessary before commencing the works.

    Where necessary these will be supported by photographs of the area.

    Initial survey of existing utilities must be done to check if there are

    obstructions which might interfere with the permanent works. If there are

    obstructions need to relocate Hanjin shall advise the authorities to relocate

    them before commencing the affected areas.

    4.2 TEMPORARY WORKS

    Access Roads

    Road diversion in area where required and various traffic controlfacilities will be installed.

    b. Craneway for Foundation Works

    Craneway will be constructed for bored piling and other crane works.

    The access shall be constructed using the available material at Site. The

    craneway will be removed and disposed to designated areas upon

    completion of Works.

    4.3 PRE-CASTING OF GIRDERS

    Pre-casting of girders shall be made at fabrication yard that will be located

    within the vicinity of the project. The prestressing works shall be executed

    in accordance with the requirements of the Plan and Specification.

    4.4 FOUNDATION WORKS (Concrete Pile Cast-in Placed Drilled Holes)

    Consist of drilling, excavation, caging, concrete pouring, and cut and

    spliced in accordance with this specification and in reasonably close

    conformity with the plan.

    SubmittalHanjin will submit to the Engineer for review and approval the

    installation plan for the construction of bored piles. The submittal shall

    include the following:

    a) List of proposed equipment to be used including cranes, drills,

    augers, bailing buckets, final cleaning equipment, and slurry pumps,

    sampling equipment, tremies or concrete pumps, etc.

    b) Details of overall construction operation sequence and the

    sequence of bored pile construction in bents or groups.

    c) Details of pile excavation methods.

    Hanjin Heavy Industries and Const. Co. LTD.

    2

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    3/30

    Construction Method

    d) When slurry is required, details of the method proposed to mix,

    circulate and desand slurry.

    e) Details of methods to clean the shaft excavation.

    f) Details of reinforcement placement including support and

    centralization methods.

    g) Details of concrete placement, curing and protection.

    h) Other information shown on the Plans or requested by the

    Engineer.

    Materials

    Reinforcing Steel shall conform to the requirements in the

    Specifications. Concrete for Bored Piles shall be Class P with the

    strength requirement of 28 MN/m2 (4000 psi). The use of appropriate

    additives to assure mix consistency shall be allowed provided air

    entraining is not enhanced and with Engineers approval. A retarder of

    proven adequacy and approved by the Engineer shall be used to ensure

    that early hardening of concrete during tremie operation will not occur.

    Casings which are required to be incorporated as part of the permanent

    work shall conform to AASHTO M183 (ASTM A-36).

    Construction Sequence

    All holes for concrete piles cast-in drilled holes shall be drilled dry to

    the tip elevations. Figure A shows the boring for cast in place pile.

    Figure A) Flight auger mounted on a boring

    rig initiates the excavation

    All holes will be examined for straightness and any hole which on

    visual inspection from the top shows less than one-half the diameter of

    Hanjin Heavy Industries and Const. Co. LTD.

    3

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    4/30

    Construction Method

    the hole at the bottom of the hole will be rejected. Suitable casings shall

    be furnished and placed required to prevent caving of the hole before

    concrete is placed.

    Figure B) Installation of permanent casing to prevent soil from

    eroding

    All loose materials existing at the bottom of the hole after drilling

    operations shall be removed before placing concrete.

    Figure C) Cleaning of the base using cleaning bucket

    The use of water for drilling operations or for any other purpose where

    it may enter the hole will not be permitted. All necessary action shall be

    Hanjin Heavy Industries and Const. Co. LTD.

    4

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    5/30

    Construction Method

    taken to prevent water from entering the hole and all water which may

    have infiltrated into the hole shall be removed before placing concrete.

    Figure D) Installation of steel reinforcement

    prior to concrete pouring

    Prior to pouring of concrete, steel cage will be installed to the drilled

    hole as shown in figure D.

    Concrete shall be placed by means of suitable tubes or pumpcrete

    depends on the accessibility of the area. Prior to the initial concrete set,

    the top 3 m of the concrete filled pile or the depth of any reinforcing

    cage, whichever is greater, shall be consolidated by acceptable

    vibratory equipment.

    Hanjin Heavy Industries and Const. Co. LTD.

    5

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    6/30

    Construction Method

    e) Placing of concrete

    The bottom of the casing shall be maintained not more than 1.5m nor

    less than 0.3m below the top of the concrete during withdrawal and

    placing operations unless otherwise permitted by the Engineer.

    Separation of the concrete during withdrawal operations shall be

    avoided by vibrating the casing.

    4.5 TESTING OF PILES

    a. LOW STRAIN PILE INTEGRITY TESTING (PIT)

    ASTM D5882-00

    Low Strain Pile Integrity Testing is a quick and cost effective method to

    evaluate the shaft integrity of concrete piles. The testing is able to

    provide information on:

    a) Pile continuity

    b) Consistency of material

    c) Location of defect

    d) Degree of defect

    The test method is performed with a hand held hammer, a sensitive

    accelerometer and the Pile Integrity Tester.

    The accelerometer is attached to the top of the pile, and then a

    compressive wave is generated by tapping the pile head with a hammer.

    When the downward compression wave encounters a change in cross

    section or in concrete quality, it generates an upward tension wave that

    is later observed at the pile top.

    The velocity recorded along with the subsequent reflections from the

    Hanjin Heavy Industries and Const. Co. LTD.

    6

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    7/30

    Construction Method

    pile toe or pile discontinuities are graphically displayed.

    The effectiveness of the system is limited to a pile length not exceeding

    30 to 60 pile diameters depending on soil condition and concrete

    quality.

    PILE TOP PILE TOE

    PIT Sample Graph

    b. HIGH-STRAIN DYNAMIC TESTING OF PILES (PDA)

    ASTM D4945-00

    This test method covers the procedure for testing vertical or batter piles

    individually to determine the force and velocity response of the pile to

    an impact force applied axially by a pile driving hammer to the top of

    the pile. This test method is applicable to deep foundation units that

    function in a manner similar to foundation piles, regardless of their

    method of installation provided that they are receptive to high strain

    impact testing.

    This standard does not purport to address all of the safety problems

    associated with its use. It is the responsibility of the user of this

    standard to establish appropriate safety and health practices and

    determine the applicability of regulatory limitations prior to use.

    Note 1--High-strain dynamic testing requires a strain at impact which is

    representative of a force in the pile having the same order of magnitude,

    or greater, than the ultimate capacity of the pile.

    Note 2--This standard method may be applied for high-strain dynamic

    testing of piles with the use of only force or strain transducers and/or

    acceleration, velocity or displacement transducers as long as the test

    results clearly state how the testing deviates from the standard.

    Note 3--A suitable follower may be required for testing cast-in-place

    concrete piles. This follower should have impedance within 80 and

    150% of that of the pile. However, additional caution and analysis may

    be required if the impedance is not within 10%. For mandrel driven

    piles, the mandrel may be instrumented in a similar way to a driven pile

    Hanjin Heavy Industries and Const. Co. LTD.

    7

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    8/30

    Construction Method

    provided that the mandrel is constructed of a single member with no

    joints

    4.6 ABUTMENT AND PIER CONSTRUCTION

    Backfilling of excavated area

    In this phase of work, excavated area will be backfilled layer by layer.

    But prior to backfilling works, temporary facilities will be removed at

    the area from possible subsidence due to the use of wrong selected

    materials.

    Construction of Piers

    After backfilling is completed and the area is reinstated to the existing

    ground level, temporary scaffolding works for the construction of piers

    will follow.

    Construction of Pier Heads

    Schedule the utilization of appropriate system forms to cover the

    standard width type, variable width type and special width type of

    various sizes of pier heads. Falsework and formworks for the work shall

    be steel construction design and detailing of the formworks will be

    submitted to the Engineer for approval.

    Appropriate safety handrail and safety net as well as foot ramp and

    ladder will be installed for this pier head and coping works. Special

    scaffolding (falsework) will be installed for concreting of pier heads.

    Concreting works shall be in accordance with the requirements of the

    drawings and specifications. Pouring of concrete shall be done by

    concrete pump of adequate reach and capacity.

    4.7 INSTALLATION OF PRE-STRESSED CONCRETE GIRDER

    Steel forms shall be used for the casting of concrete for pre-stressed

    concrete girders. These forms shall conform to the girder type and

    length shown on the drawing plans. Steel forms shall be of the required

    gauge thickness, design and rigidity to prevent bulging and produce afinished product with the correct dimension, shapes and details.

    Pre-stressed concrete girders shall be fabricated in the pre-cast yard and

    transported to the required location for launching by using appropriate

    cranes.

    General sequence for the erection of pre-stressed concrete girders will

    be as follows:

    Phase 1: Launching of girders as shown in the figure below.

    Hanjin Heavy Industries and Const. Co. LTD.

    8

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    9/30

    Construction Method

    PIERABUTMENT

    P.S CONCRETE GIRDER

    Phase 2: Concreting of intermediate and end diaphragms

    Pre-stressing of cables

    Phase 3: Concreting of deck slab except interior support.

    Phase 4: Concreting of connection diaphragm pre-stressing of cables

    Concreting of remaining deck slab

    Phase 5: Concreting of sidewalk railing.

    All pre-stressing works shall be carried out safely by using appropriatepre-stressing equipment.

    4.8 CONCRETING OF SLAB AND RAILING

    Immediately after setting of girders, concreting of slab will follow.

    Bracket forms shall be used. The hanging forms will be fixed on the

    girders and removed after the curing of concrete.

    Hanjin Heavy Industries and Const. Co. LTD.

    9

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    10/30

    Construction Method

    4.9 MECHANICALLY STABILIZED EARTH (MSE) WALLS

    4.9.1General

    The wall system consists of the original ground, concrete leveling pad,

    wall facing panels, coping, soil reinforcement, select backfill and any

    loads and surcharges. All of these items have an affect on the

    performance of the MSE wall and are taken into account in the stability

    analysis. The general concept of the MSE wall system is that the

    weight of the select backfill grabs the soil reinforcement by friction

    and by directly binding with the granular backfill. The backfill wants

    to push the facing panels out, but the connection between the facing and

    the reinforcement prevents this.

    Figure 1, Wall Components

    4.9.2 PREPARATION OF THE SITE:

    The MSE wall footprint area needs to be prepared. The footprint area is the

    zone of the wall facing, soil reinforcement and select backfill. The

    foundation for the structure shall be graded level for a width equal to orexceeding the length of soil reinforcement or as shown on the plans. Any

    soft or loose material that is encountered should be compacted or removed

    and replaced. The foundation soils for the retaining system must be proof

    rolled before wall construction begins and after the required excavation is

    completed. If soils are encountered that do not match the borings

    performed for the wall they should be brought to the attention of the

    geotechnical engineers for analysis.

    4.9.3 LEVELING PAD:

    Once the area has been properly prepared, an unreinforced concrete

    leveling pad is poured in place. The leveling pad concrete must cure for a

    Hanjin Heavy Industries and Const. Co. LTD.

    10

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    11/30

    Construction Method

    minimum of 12 hours before placement of the wall panels can begin. Even

    though the leveling pad is not "structurally" important, it is important to the

    construction of the wall. The leveling pad sets the horizontal and vertical

    alignment of the wall. It must be in the correct horizontal position, level

    and at correct grade.

    4.9.4 WALL FACING PANELS:

    Before the panels are placed, the wall and shop drawings must be checked

    to ensure that the proper panels are being used. Depending on the wall

    height, the number of reinforcement connections on the back of the panel

    may vary. The panels with the most connections will be typically the lower

    panels of the wall. In the upper portions of the wall, the number of

    connections may be less. It is important that the panels are used in their

    proper position. The panels need to be inspected to ensure they meet the

    plans, specifications, and shop drawings. They also need to be inspected

    for damage (bent connectors, damaged panels, etc.).

    The correct placement of the first row or two of panels is very important

    (see Figure 2, Placing Panels ). A spacer bar should be used to get the

    correct placement. They need to be on the proper alignment and grade and

    be level. The correct spacing is also very important. Without the correct

    spacing, panel corners will crack and spall as they settle. Spacing blocks

    must be used. Wooden wedges are also used to help hold the vertical

    alignment of the panels. The drainage system for the wall must be installed

    at this early stage of wall construction to prevent ponding of water in the

    excavation and the subsequent loss of strength of the foundation soils.

    Hanjin Heavy Industries and Const. Co. LTD.

    11

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    12/30

    Construction Method

    Figure 2, Placing of Panels

    The vertical and horizontal alignments need to be checked periodically to

    ensure proper alignment. This will also uncover problems early so

    corrections can be made before the panels get too far out of alignment.

    4.9.5 PANEL STORAGE:

    Panels should be stored flat and on dunged (see Figure 3, Proper Panel

    Storage and Figure 4, Improper Panel Storage). Properly storing panels

    protects the connections from being bent and damaging the galvanization

    (see Figure 5, Damaged Tabs). Panels with bent connections will not be

    used. Panels should be stored out of the mud to avoid staining the panel

    face.

    Figure 5, Damaged Tabs

    4.9.6 SOIL REINFORCEMENT:

    The soil reinforcement is used to make a unified gravity mass consisting of

    select structural backfill, facing, and the reinforcement and acting like a

    gravity wall for exterior analysis purposes. Metallic reinforcement should

    not be bent or torn, and the galvanization should not be damaged. Polymer

    reinforcement should not be torn, cut, left in the sun or otherwise damaged.

    Typically, the reinforcement is placed perpendicular to the wall face. Slack

    Hanjin Heavy Industries and Const. Co. LTD.

    12

    Figure 3, Proper

    Panel Storage

    Figure 4, Improper

    Panel Storage

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    13/30

    Construction Method

    in the reinforcement should be removed prior to placing the backfill over it,

    and polymer reinforcement should have some tension placed in the

    reinforcement. The reinforcement should not be connected to the wall until

    the compacted fill is at or slightly higher than the facing panel connector.

    4.9.7 SELECT BACKFILL:

    The select backfill must meet the specification requirements for gradation,

    electro-chemical properties, soil properties and organic content.

    Placing Backfill

    The select backfill lift should be placed parallel to the wall and starting

    approximately 900 mm from the back of the wall panels. The backfill

    should be placed in 10 inch (250 mm) loose lifts. The fill is then leveled by

    machinery moving parallel to the wall, windrowing the material toward the

    reinforcement ends. This action works out any slack in the reinforcementthen locking the reinforcement and the panels in position. Once this has

    been accomplished, fill is then placed within 900 mm behind the wall by

    windrowing the material.

    Except for the initial layer, the fill must be brought up uniformly for the

    whole layer.

    4.1.8 COMPACTION:

    Compaction equipment used within 3 feet (900 mm) of the wall should be a

    vibratory roller or plate weighing less than 1,000 pounds (450 kg). From

    beyond 3 feet (900 mm) of the wall facing panels, a roller up to 8 tons (7.25

    Mg) may be used, subject to satisfactory performance. A rubber-tired roller

    may also be acceptable. Compactors which employ a foot such as a

    sheepsfoot (see Figure 21, Sheepsfoot Rollers Not Allowed ) or grid

    rollers, are not acceptable for compacting select structural backfill.

    Backfill compaction shall be performed in such a way that the compactorshall move in a direction parallel to the wall facing panels and proceed

    from a distance not less than three feet behind the wall facing panels and

    work toward the end of the soil reinforcement away from the wall facing.

    The moisture content of the backfill material prior to and during

    compaction shall be muted throughout each layer of material. Backfill

    material shall have placement moisture content within 3 percent of the

    optimum moisture content.

    If additional water is required for the material, the water must meet the

    specification requirements.

    Hanjin Heavy Industries and Const. Co. LTD.

    13

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    14/30

    Construction Method

    4.9 SLOPE PROTECTION WORKS

    Right after the completion of the superstructure, abutment slope protection

    works will follow. On this item it will consist of grouted riprap at side drain,

    stone masonry, rubble concrete and mattress.

    This work will avoid erosion from the embankment area.

    COMPACT

    FILL BEFORE

    PLACING

    GROUTED

    RIPRAP

    MATRESSES

    FILTER CLOTH

    GROUTED RIP RAP

    TOP OF COPPING

    ABUTMENT

    BORED PILE

    S=1.5:1

    TYPICAL DETAIL OF ABUTMENT SLOPE PROTECTION

    Hanjin Heavy Industries and Const. Co. LTD.

    14

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    15/30

    Construction Method

    PART G - DRAINAGE & SLOPE PROTECTION STRUCTURES

    BOX CULVERT

    1. SCOPE OF WORK

    This item consists of construction of Box Culverts including the associated

    excavation, backfilling and bedding works in accordance with requirements

    specified or referred to herein, all to the Engineers satisfaction.

    Description Unit Quantity

    Reinforcing Steel, Grade 60 (For RCBC,

    Headwalls)Kg. 175,865.0

    Structural Concrete Class AA (for RCBC) Cu.m 1,630.0

    Lean Concrete (fc=10MPA) Cu.m 100.0

    2. EQUIPMENT

    General

    Generator

    Wheel Loader

    Water Truck

    Excavator

    Plate Compactor

    Pouring & Curing

    Transit Mixer

    Concrete Pump

    Engine Vibrator

    Concrete B/P

    Water Truck

    R. S. Bar

    Cargo Truck

    Fork Lift

    Bar Bender

    Machine

    Bar Cutter

    Machine

    Generator

    3. MANPOWER

    Surveyor

    Survey Aide

    Operator

    Driver

    Skilled Laborer

    Common Laborer

    Hanjin Heavy Industries and Const. Co. LTD.

    15

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    16/30

    Construction Method

    4. WORK OF FLOW

    Materials Activity Equipment Manpower

    5. WORK METHODOLOGY

    Excavation

    Survey for layout shall be conducted first before excavation shall be started. The

    trench shall be excavated to the line, depth and grade necessary for the placement

    of Box culvert.

    Bedding

    After the trench has been excavated to the required depth and width, bedding shall

    be compacted. Bedding for box culvert shall be on two layers, first layer shall be

    Hanjin Heavy Industries and Const. Co. LTD.

    16

    Layout of theBox Culvert

    Excavation

    - Excavator

    - Operator

    - Surveyor

    - Foreman

    - Laborers- Driver

    Installation of

    rebar andforms

    Concrete

    Pouring

    Bedding

    - Plate

    Compactor

    - Excavator

    - Cargo Truck

    - Bar Cutter

    - Bar Bender

    - Tr

    ansit Mixer

    - ConcretePump

    - ConcreteVibrator

    -ReinforcingBars

    -Forms

    - Concrete

    - Gravel

    Backfilling

    - Pl

    ate

    Compactor

    - Selected Fill

    - Operator

    - Surveyor

    - Foreman

    - Laborers- Driver

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    17/30

    Construction Method

    100 mm compacted gravel bedding and final bedding shall be 100 mm THK Lean

    concrete. In case where the water level is higher than the elevation of the bedding

    and compaction is not possible, water pump will be used to drain the water.

    Survey checking of elevation of the bedding shall be done before the installation of

    rebar and forms.

    Installation of Rebar and Forms

    Installation of reinforcing bars will take place after the bedding and compaction

    operation is done. All reinforcement shall be fabricated at the yard and shall be

    transported at the site area so as to have an orderly working place. Reinforcing bars

    shall be cut and bend according to the specification and plans.

    Forms shall be installed after the installation of rebar. Plywood shall be used for

    sheathing and shall be framed with a combination of G.I pipe and lumber. Shoring

    on forms shall be tightly installed so as to avoid movement of forms when pouringof concrete take place.

    Concreting Works

    Concrete construction shall conform to the requirements of Specifications.

    Backfilling & Compaction

    Backfilling and compaction shall be done with the used of loader and plate

    compactor. It shall be continued until the fill has reached the required elevation

    density.

    Hanjin Heavy Industries and Const. Co. LTD.

    17

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    18/30

    Construction Method

    RC PIPE CULVERTS

    1. SCOPE OF WORK

    The work include furnishing of all labor, materials and equipment required in

    accordance with the specification and as shown on the drawing for the execution of

    the following activities:

    Description Unit Quantity

    RCPC 910mm dia. (Regular Strengths) l.m 2240

    2. EQUIPMENT

    Excavator

    Dump Truck

    Plate Compactor

    Cargo Truck

    Survey Instruments

    Truck Crane

    3. MANPOWER

    Field Engineer / Foreman

    Surveyor

    Survey Aides

    Common Laborers Operators

    Hanjin Heavy Industries and Const. Co. LTD.

    18

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    19/30

    Construction Method

    4. WORK OF FLOW

    Materials Activity Equipment Manpower

    5. WORK METHODOLOGY

    Excavation

    Survey for layout of the drainage line shall be conducted first before excavation

    shall start.

    Excavation for pipe laying shall be done with the used of excavator.

    The trench shall be excavated to the line, depth and grade necessary for the pipes

    to be laid. It shall have a maximum width of 2 times the diameter of the pipe.

    Bedding

    Bedding for the RC pipes shall be compacted with the used of plate compactor,

    after the trench has been excavated to the required depth and width. FDT testing

    shall be conducted and the bedding shall pass to the requirement of the

    specification.

    Hanjin Heavy Industries and Const. Co. LTD.

    19

    Layout of thedrainage line

    Excavation

    - Excavator

    - Operator- Surveyor

    - Foreman

    - Laborers- Driver

    Placing of RC

    Pipes

    Backfilling

    Bedding

    - Plate

    Compactor

    - Excavator

    - Cargo Truck

    - Pl

    ate

    Compactor

    RC Pipes:

    - 910mm dia.

    - Selected Fill

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    20/30

    Construction Method

    In case where the water level is higher than the elevation of the bedding and

    compaction is not possible, water pump will be used to drain the water.

    Survey checking of elevation of the bedding shall be done before pipe laying,

    installation of manhole and catch basin shall start.

    Placing of Pipes

    The pipe shall be laid carefully. It shall be lifted and placed to the trench with the

    used of excavator.

    The joints of RC pipe shall be provided with collar filled with mortar.

    The inner ends of the RC pipes shall be flushed with the inner face of the wall in

    manhole and catch basin outside face of the wall in case of outlet structure.

    Backfilling

    After the pipe has been installed and the mortar joints sufficiently set, backfilling

    shall be started.

    The backfilling materials shall be place along side of the pipes in layer of 150mm

    in depth and compacted so that on each side of the pipe there shall be thoroughly

    compacted material of the same height.

    Backfilling and compaction shall be done with the used of loader and plate

    compactor. It shall be continued until the fill has reached the required elevation.

    Hanjin Heavy Industries and Const. Co. LTD.

    20

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    21/30

    Construction Method

    GROUTED RIPRAP

    1. SCOPE OF WORK

    This item shall consist of the construction of Grouted Riprap in minor structures,toes of slopes and other locations called on the Plans, and in conformity with the

    plan and specification and shall conform to the lines, grades and dimensions as

    shown on the plans.

    The activities to be done are as follows:

    Description Unit Quantity

    Grouted Riprap Class A cu.m. 17,350.0

    2. EQUIPMENT

    Excavator

    Dump Truck

    Plate Compactor

    Concrete Mixer

    3. MANPOWER

    Operator

    Driver

    Skilled Laborer

    Common Laborer

    Hanjin Heavy Industries and Const. Co. LTD.

    21

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    22/30

    Construction Method

    Hanjin Heavy Industries and Const. Co. LTD.

    22

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    23/30

    Construction Method

    4. WORK FLOW

    Materials Activity Equipment Manpower

    5. WORK METHODOLOGY

    Excavation

    The bed for riprap shall be excavated to the required depths and properly

    compacted, trimmed and shaped. The riprap shall be founded in toe trench dug

    below the depth of the scour as shown on the drawings or as directed by the

    Engineer. The Toe trench shall be filled with stone of the same class as that

    specified for the riprap unless otherwise specified.

    Placing

    Stone placed below the water line shall be distributed so that the minimum

    thickness of the riprap is not less than that specified.

    Stones above the water line shall be placed by hand or individually by machines.

    They shall be laid with close, broken joints and shall be firmly bedded into the

    slope and against the adjoining stones. Each stone shall be laid with its longest axis

    perpendicular to the slope in close contact with each adjacent stone. The riprap

    shall be thoroughly rammed into a place as construction progresses and thefinished surface shall present an even, tight surface. Interstices between stones

    shall be filled with small broken fragments firmly rammed into place.

    Grouting

    When specified, stones shall be placed by hand, or individually by machine as

    specified for riprap placed above the water line. The spaces between the stones

    shall then be filled with cement mortar as required in the specification. Sufficient

    mortar shall be used to completely fill all voids, except that the face surface of the

    stones shall be left exposed.

    Hanjin Heavy Industries and Const. Co. LTD.

    23

    Excavation- Excavator

    - Dump truck

    Hauling/Placing

    Grouting

    - Operator

    - Driver

    - Skilled Labor

    - Common

    Labor

    -Stone,

    -Cement

    -Sand -Skilled

    Laborer

    -Common

    Labor

    - Concrete

    Mixer

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    24/30

    Construction Method

    Hanjin Heavy Industries and Const. Co. LTD.

    24

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    25/30

    Construction Method

    REINFORCED CONCRETE DITCH

    1. SCOPE OF WORK

    This item consists of constructing ditches composed of reinforced concrete,

    grouted riprap, and earth materials. These structures will serve as waterway toavoid flooding on roads.

    The activities to be done are as follows:

    Description Unit Quantity

    Reinforced Concrete Ditch with Cover, Type A L.m. 7,975.0

    2. EQUIPMENT

    Excavator

    Dump Truck

    Plate Compactor

    Concrete Mixer

    3. MANPOWER

    Operator

    Driver

    Skilled Laborer

    Common Laborer

    Hanjin Heavy Industries and Const. Co. LTD.

    25

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    26/30

    Construction Method

    2. WORK FLOW

    Materials Activity Equipment Manpower

    5. WORK METHOLOGY

    Excavation

    Excavation shall be done by the use of excavator. The bed where the ditch will be

    constructed shall be cleared and cleaned to the satisfaction of the Engineer.

    Compaction

    The bed of ditch shall be compacted by the use of plate compactor. It shall be

    compacted to a degree so as to present a relatively even surface and have a state of

    bonding to some extent.

    Installation of Forms and Rebars

    After the compaction of bed, installation of forms and reinforcement bars will take

    place. Reinforcing bars shall be according to specifications and forms must be

    properly installed to avoid buckling when concrete pouring take place. Dimension

    of the ditch shall properly be observed so as to meet the Drawing shown in the

    plans.

    Concreting Works

    Concrete construction shall conform to the requirements of Specifications.

    Hanjin Heavy Industries and Const. Co. LTD.

    26

    Excavation- Excavator

    - Plate

    Compactor

    Installation of

    forms and

    Rebar

    - Operator

    - Skilled Labor

    - Common

    Labor

    -Driver

    -Skilled

    Laborer

    -Common

    Labor

    - Cargo Truck

    - Bar Cutter

    Fabrication of

    Ditch Cover

    Concreting

    Compaction

    - Concrete

    Mixer

    -Skilled

    Laborer

    -Common

    Labor

    -Sheathing

    Form

    -Rebar

    -Sand

    -Gravel

    -Cement

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    27/30

    Construction Method

    STONE MASONRY

    1. SCOPE OF WORK

    This item of work consist of stone masonry in minor structures, in retainingwalls at the toes of slopes and at other locations called for on the Plans, in

    accordance with the Specification and in conformity with the lines, grades,

    sections and dimensions shown on the Plans.

    The activities to be done are as follows:

    Description Unit Quantity

    Stone Masonry (Retaining Wall) cu.m. 6,580.0

    Stone Masonry (Dwarf Wall) cu.m. 1,876.0

    2. EQUIPMENT

    Dump Truck

    Excavator

    Plate Compactor

    3. MANPOWER Operator

    Driver

    Skilled Laborer

    Common Laborer

    4. WORK METHODOLOGY

    Selection and Placing

    The foundation bed shall be firm and normal to the face of the wall and shall be

    approved by the Engineer before placing any stones. Stones to be set shall be

    cleaned and the bed is to receive them shall be cleaned and moistened before the

    mortar is spread. Setting and laying of stones shall be in accordance with the

    specifications.

    Beds and Joints

    Beds and joints shall not extend in an unbroken line through more than five and

    two stones respectively. Cross beds for vertical walls shall be level, and for

    Hanjin Heavy Industries and Const. Co. LTD.

    27

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    28/30

    Construction Method

    battered walls may vary from level to normal to the batter line of the face of the

    wall.

    Hanjin Heavy Industries and Const. Co. LTD.

    28

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    29/30

    Construction Method

    Cleaning Exposed Faces

    Immediately after being laid, and while the mortar is fresh, all face stones shall be

    thoroughly cleaned of mortar stains and shall be kept clean until the work is

    completed.

    Curing

    In hot or dry weather, the masonry shall be protected from the sun and shall be

    kept wet for a period of at least three days after completion.

    Hanjin Heavy Industries and Const. Co. LTD.

    29

  • 8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures

    30/30

    Construction Method