Upload
jayson-rebuldela
View
254
Download
0
Embed Size (px)
Citation preview
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
1/30
Construction Method
PART F - BRIDGE CONSTRUCTION
1. SCOPE OF WORK
This item shall consist of the construction of three (3) bridges;
Bridges Name Length (mts.) Type of Span Foundation
Sta. Cruz Bridge 1 280.0Pre-stressed
Concrete GirderBored Pile
Sta. Cruz Bridge 2 15.0Pre-stressed
Concrete GirderBored Pile
Matalaba Bridge 15.0Pre-stressed
Concrete GirderBored Pile
2. EQUIPMENT
Bored Piling
Crawler Crane
Auger
Cleaning bucket
Vibratory Hammer
Generator
Concrete Production
Concrete B/PGenerator
Wheel Loader
Water Truck
Concrete Pouring
Transit Mixer
Concrete Pump
Engine Vibrator
Water Truck
R.S Bar/ Steel Cage
Bar Bender
Bar Cutter
Fork LiftCargo Truck
Generator
Acetylene
Welding Machine
3. MANPOWER
Field Engineer
Operator
Driver
Skilled Laborer
Common Laborer
4. CONSTRUCTION SEQUENCE
Hanjin Heavy Industries and Const. Co. LTD.
1
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
2/30
Construction Method
4.1 SURVEY WORK
Carry out initial topographic survey of the project to establish the existing
levels and record all details as necessary before commencing the works.
Where necessary these will be supported by photographs of the area.
Initial survey of existing utilities must be done to check if there are
obstructions which might interfere with the permanent works. If there are
obstructions need to relocate Hanjin shall advise the authorities to relocate
them before commencing the affected areas.
4.2 TEMPORARY WORKS
Access Roads
Road diversion in area where required and various traffic controlfacilities will be installed.
b. Craneway for Foundation Works
Craneway will be constructed for bored piling and other crane works.
The access shall be constructed using the available material at Site. The
craneway will be removed and disposed to designated areas upon
completion of Works.
4.3 PRE-CASTING OF GIRDERS
Pre-casting of girders shall be made at fabrication yard that will be located
within the vicinity of the project. The prestressing works shall be executed
in accordance with the requirements of the Plan and Specification.
4.4 FOUNDATION WORKS (Concrete Pile Cast-in Placed Drilled Holes)
Consist of drilling, excavation, caging, concrete pouring, and cut and
spliced in accordance with this specification and in reasonably close
conformity with the plan.
SubmittalHanjin will submit to the Engineer for review and approval the
installation plan for the construction of bored piles. The submittal shall
include the following:
a) List of proposed equipment to be used including cranes, drills,
augers, bailing buckets, final cleaning equipment, and slurry pumps,
sampling equipment, tremies or concrete pumps, etc.
b) Details of overall construction operation sequence and the
sequence of bored pile construction in bents or groups.
c) Details of pile excavation methods.
Hanjin Heavy Industries and Const. Co. LTD.
2
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
3/30
Construction Method
d) When slurry is required, details of the method proposed to mix,
circulate and desand slurry.
e) Details of methods to clean the shaft excavation.
f) Details of reinforcement placement including support and
centralization methods.
g) Details of concrete placement, curing and protection.
h) Other information shown on the Plans or requested by the
Engineer.
Materials
Reinforcing Steel shall conform to the requirements in the
Specifications. Concrete for Bored Piles shall be Class P with the
strength requirement of 28 MN/m2 (4000 psi). The use of appropriate
additives to assure mix consistency shall be allowed provided air
entraining is not enhanced and with Engineers approval. A retarder of
proven adequacy and approved by the Engineer shall be used to ensure
that early hardening of concrete during tremie operation will not occur.
Casings which are required to be incorporated as part of the permanent
work shall conform to AASHTO M183 (ASTM A-36).
Construction Sequence
All holes for concrete piles cast-in drilled holes shall be drilled dry to
the tip elevations. Figure A shows the boring for cast in place pile.
Figure A) Flight auger mounted on a boring
rig initiates the excavation
All holes will be examined for straightness and any hole which on
visual inspection from the top shows less than one-half the diameter of
Hanjin Heavy Industries and Const. Co. LTD.
3
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
4/30
Construction Method
the hole at the bottom of the hole will be rejected. Suitable casings shall
be furnished and placed required to prevent caving of the hole before
concrete is placed.
Figure B) Installation of permanent casing to prevent soil from
eroding
All loose materials existing at the bottom of the hole after drilling
operations shall be removed before placing concrete.
Figure C) Cleaning of the base using cleaning bucket
The use of water for drilling operations or for any other purpose where
it may enter the hole will not be permitted. All necessary action shall be
Hanjin Heavy Industries and Const. Co. LTD.
4
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
5/30
Construction Method
taken to prevent water from entering the hole and all water which may
have infiltrated into the hole shall be removed before placing concrete.
Figure D) Installation of steel reinforcement
prior to concrete pouring
Prior to pouring of concrete, steel cage will be installed to the drilled
hole as shown in figure D.
Concrete shall be placed by means of suitable tubes or pumpcrete
depends on the accessibility of the area. Prior to the initial concrete set,
the top 3 m of the concrete filled pile or the depth of any reinforcing
cage, whichever is greater, shall be consolidated by acceptable
vibratory equipment.
Hanjin Heavy Industries and Const. Co. LTD.
5
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
6/30
Construction Method
e) Placing of concrete
The bottom of the casing shall be maintained not more than 1.5m nor
less than 0.3m below the top of the concrete during withdrawal and
placing operations unless otherwise permitted by the Engineer.
Separation of the concrete during withdrawal operations shall be
avoided by vibrating the casing.
4.5 TESTING OF PILES
a. LOW STRAIN PILE INTEGRITY TESTING (PIT)
ASTM D5882-00
Low Strain Pile Integrity Testing is a quick and cost effective method to
evaluate the shaft integrity of concrete piles. The testing is able to
provide information on:
a) Pile continuity
b) Consistency of material
c) Location of defect
d) Degree of defect
The test method is performed with a hand held hammer, a sensitive
accelerometer and the Pile Integrity Tester.
The accelerometer is attached to the top of the pile, and then a
compressive wave is generated by tapping the pile head with a hammer.
When the downward compression wave encounters a change in cross
section or in concrete quality, it generates an upward tension wave that
is later observed at the pile top.
The velocity recorded along with the subsequent reflections from the
Hanjin Heavy Industries and Const. Co. LTD.
6
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
7/30
Construction Method
pile toe or pile discontinuities are graphically displayed.
The effectiveness of the system is limited to a pile length not exceeding
30 to 60 pile diameters depending on soil condition and concrete
quality.
PILE TOP PILE TOE
PIT Sample Graph
b. HIGH-STRAIN DYNAMIC TESTING OF PILES (PDA)
ASTM D4945-00
This test method covers the procedure for testing vertical or batter piles
individually to determine the force and velocity response of the pile to
an impact force applied axially by a pile driving hammer to the top of
the pile. This test method is applicable to deep foundation units that
function in a manner similar to foundation piles, regardless of their
method of installation provided that they are receptive to high strain
impact testing.
This standard does not purport to address all of the safety problems
associated with its use. It is the responsibility of the user of this
standard to establish appropriate safety and health practices and
determine the applicability of regulatory limitations prior to use.
Note 1--High-strain dynamic testing requires a strain at impact which is
representative of a force in the pile having the same order of magnitude,
or greater, than the ultimate capacity of the pile.
Note 2--This standard method may be applied for high-strain dynamic
testing of piles with the use of only force or strain transducers and/or
acceleration, velocity or displacement transducers as long as the test
results clearly state how the testing deviates from the standard.
Note 3--A suitable follower may be required for testing cast-in-place
concrete piles. This follower should have impedance within 80 and
150% of that of the pile. However, additional caution and analysis may
be required if the impedance is not within 10%. For mandrel driven
piles, the mandrel may be instrumented in a similar way to a driven pile
Hanjin Heavy Industries and Const. Co. LTD.
7
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
8/30
Construction Method
provided that the mandrel is constructed of a single member with no
joints
4.6 ABUTMENT AND PIER CONSTRUCTION
Backfilling of excavated area
In this phase of work, excavated area will be backfilled layer by layer.
But prior to backfilling works, temporary facilities will be removed at
the area from possible subsidence due to the use of wrong selected
materials.
Construction of Piers
After backfilling is completed and the area is reinstated to the existing
ground level, temporary scaffolding works for the construction of piers
will follow.
Construction of Pier Heads
Schedule the utilization of appropriate system forms to cover the
standard width type, variable width type and special width type of
various sizes of pier heads. Falsework and formworks for the work shall
be steel construction design and detailing of the formworks will be
submitted to the Engineer for approval.
Appropriate safety handrail and safety net as well as foot ramp and
ladder will be installed for this pier head and coping works. Special
scaffolding (falsework) will be installed for concreting of pier heads.
Concreting works shall be in accordance with the requirements of the
drawings and specifications. Pouring of concrete shall be done by
concrete pump of adequate reach and capacity.
4.7 INSTALLATION OF PRE-STRESSED CONCRETE GIRDER
Steel forms shall be used for the casting of concrete for pre-stressed
concrete girders. These forms shall conform to the girder type and
length shown on the drawing plans. Steel forms shall be of the required
gauge thickness, design and rigidity to prevent bulging and produce afinished product with the correct dimension, shapes and details.
Pre-stressed concrete girders shall be fabricated in the pre-cast yard and
transported to the required location for launching by using appropriate
cranes.
General sequence for the erection of pre-stressed concrete girders will
be as follows:
Phase 1: Launching of girders as shown in the figure below.
Hanjin Heavy Industries and Const. Co. LTD.
8
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
9/30
Construction Method
PIERABUTMENT
P.S CONCRETE GIRDER
Phase 2: Concreting of intermediate and end diaphragms
Pre-stressing of cables
Phase 3: Concreting of deck slab except interior support.
Phase 4: Concreting of connection diaphragm pre-stressing of cables
Concreting of remaining deck slab
Phase 5: Concreting of sidewalk railing.
All pre-stressing works shall be carried out safely by using appropriatepre-stressing equipment.
4.8 CONCRETING OF SLAB AND RAILING
Immediately after setting of girders, concreting of slab will follow.
Bracket forms shall be used. The hanging forms will be fixed on the
girders and removed after the curing of concrete.
Hanjin Heavy Industries and Const. Co. LTD.
9
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
10/30
Construction Method
4.9 MECHANICALLY STABILIZED EARTH (MSE) WALLS
4.9.1General
The wall system consists of the original ground, concrete leveling pad,
wall facing panels, coping, soil reinforcement, select backfill and any
loads and surcharges. All of these items have an affect on the
performance of the MSE wall and are taken into account in the stability
analysis. The general concept of the MSE wall system is that the
weight of the select backfill grabs the soil reinforcement by friction
and by directly binding with the granular backfill. The backfill wants
to push the facing panels out, but the connection between the facing and
the reinforcement prevents this.
Figure 1, Wall Components
4.9.2 PREPARATION OF THE SITE:
The MSE wall footprint area needs to be prepared. The footprint area is the
zone of the wall facing, soil reinforcement and select backfill. The
foundation for the structure shall be graded level for a width equal to orexceeding the length of soil reinforcement or as shown on the plans. Any
soft or loose material that is encountered should be compacted or removed
and replaced. The foundation soils for the retaining system must be proof
rolled before wall construction begins and after the required excavation is
completed. If soils are encountered that do not match the borings
performed for the wall they should be brought to the attention of the
geotechnical engineers for analysis.
4.9.3 LEVELING PAD:
Once the area has been properly prepared, an unreinforced concrete
leveling pad is poured in place. The leveling pad concrete must cure for a
Hanjin Heavy Industries and Const. Co. LTD.
10
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
11/30
Construction Method
minimum of 12 hours before placement of the wall panels can begin. Even
though the leveling pad is not "structurally" important, it is important to the
construction of the wall. The leveling pad sets the horizontal and vertical
alignment of the wall. It must be in the correct horizontal position, level
and at correct grade.
4.9.4 WALL FACING PANELS:
Before the panels are placed, the wall and shop drawings must be checked
to ensure that the proper panels are being used. Depending on the wall
height, the number of reinforcement connections on the back of the panel
may vary. The panels with the most connections will be typically the lower
panels of the wall. In the upper portions of the wall, the number of
connections may be less. It is important that the panels are used in their
proper position. The panels need to be inspected to ensure they meet the
plans, specifications, and shop drawings. They also need to be inspected
for damage (bent connectors, damaged panels, etc.).
The correct placement of the first row or two of panels is very important
(see Figure 2, Placing Panels ). A spacer bar should be used to get the
correct placement. They need to be on the proper alignment and grade and
be level. The correct spacing is also very important. Without the correct
spacing, panel corners will crack and spall as they settle. Spacing blocks
must be used. Wooden wedges are also used to help hold the vertical
alignment of the panels. The drainage system for the wall must be installed
at this early stage of wall construction to prevent ponding of water in the
excavation and the subsequent loss of strength of the foundation soils.
Hanjin Heavy Industries and Const. Co. LTD.
11
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
12/30
Construction Method
Figure 2, Placing of Panels
The vertical and horizontal alignments need to be checked periodically to
ensure proper alignment. This will also uncover problems early so
corrections can be made before the panels get too far out of alignment.
4.9.5 PANEL STORAGE:
Panels should be stored flat and on dunged (see Figure 3, Proper Panel
Storage and Figure 4, Improper Panel Storage). Properly storing panels
protects the connections from being bent and damaging the galvanization
(see Figure 5, Damaged Tabs). Panels with bent connections will not be
used. Panels should be stored out of the mud to avoid staining the panel
face.
Figure 5, Damaged Tabs
4.9.6 SOIL REINFORCEMENT:
The soil reinforcement is used to make a unified gravity mass consisting of
select structural backfill, facing, and the reinforcement and acting like a
gravity wall for exterior analysis purposes. Metallic reinforcement should
not be bent or torn, and the galvanization should not be damaged. Polymer
reinforcement should not be torn, cut, left in the sun or otherwise damaged.
Typically, the reinforcement is placed perpendicular to the wall face. Slack
Hanjin Heavy Industries and Const. Co. LTD.
12
Figure 3, Proper
Panel Storage
Figure 4, Improper
Panel Storage
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
13/30
Construction Method
in the reinforcement should be removed prior to placing the backfill over it,
and polymer reinforcement should have some tension placed in the
reinforcement. The reinforcement should not be connected to the wall until
the compacted fill is at or slightly higher than the facing panel connector.
4.9.7 SELECT BACKFILL:
The select backfill must meet the specification requirements for gradation,
electro-chemical properties, soil properties and organic content.
Placing Backfill
The select backfill lift should be placed parallel to the wall and starting
approximately 900 mm from the back of the wall panels. The backfill
should be placed in 10 inch (250 mm) loose lifts. The fill is then leveled by
machinery moving parallel to the wall, windrowing the material toward the
reinforcement ends. This action works out any slack in the reinforcementthen locking the reinforcement and the panels in position. Once this has
been accomplished, fill is then placed within 900 mm behind the wall by
windrowing the material.
Except for the initial layer, the fill must be brought up uniformly for the
whole layer.
4.1.8 COMPACTION:
Compaction equipment used within 3 feet (900 mm) of the wall should be a
vibratory roller or plate weighing less than 1,000 pounds (450 kg). From
beyond 3 feet (900 mm) of the wall facing panels, a roller up to 8 tons (7.25
Mg) may be used, subject to satisfactory performance. A rubber-tired roller
may also be acceptable. Compactors which employ a foot such as a
sheepsfoot (see Figure 21, Sheepsfoot Rollers Not Allowed ) or grid
rollers, are not acceptable for compacting select structural backfill.
Backfill compaction shall be performed in such a way that the compactorshall move in a direction parallel to the wall facing panels and proceed
from a distance not less than three feet behind the wall facing panels and
work toward the end of the soil reinforcement away from the wall facing.
The moisture content of the backfill material prior to and during
compaction shall be muted throughout each layer of material. Backfill
material shall have placement moisture content within 3 percent of the
optimum moisture content.
If additional water is required for the material, the water must meet the
specification requirements.
Hanjin Heavy Industries and Const. Co. LTD.
13
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
14/30
Construction Method
4.9 SLOPE PROTECTION WORKS
Right after the completion of the superstructure, abutment slope protection
works will follow. On this item it will consist of grouted riprap at side drain,
stone masonry, rubble concrete and mattress.
This work will avoid erosion from the embankment area.
COMPACT
FILL BEFORE
PLACING
GROUTED
RIPRAP
MATRESSES
FILTER CLOTH
GROUTED RIP RAP
TOP OF COPPING
ABUTMENT
BORED PILE
S=1.5:1
TYPICAL DETAIL OF ABUTMENT SLOPE PROTECTION
Hanjin Heavy Industries and Const. Co. LTD.
14
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
15/30
Construction Method
PART G - DRAINAGE & SLOPE PROTECTION STRUCTURES
BOX CULVERT
1. SCOPE OF WORK
This item consists of construction of Box Culverts including the associated
excavation, backfilling and bedding works in accordance with requirements
specified or referred to herein, all to the Engineers satisfaction.
Description Unit Quantity
Reinforcing Steel, Grade 60 (For RCBC,
Headwalls)Kg. 175,865.0
Structural Concrete Class AA (for RCBC) Cu.m 1,630.0
Lean Concrete (fc=10MPA) Cu.m 100.0
2. EQUIPMENT
General
Generator
Wheel Loader
Water Truck
Excavator
Plate Compactor
Pouring & Curing
Transit Mixer
Concrete Pump
Engine Vibrator
Concrete B/P
Water Truck
R. S. Bar
Cargo Truck
Fork Lift
Bar Bender
Machine
Bar Cutter
Machine
Generator
3. MANPOWER
Surveyor
Survey Aide
Operator
Driver
Skilled Laborer
Common Laborer
Hanjin Heavy Industries and Const. Co. LTD.
15
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
16/30
Construction Method
4. WORK OF FLOW
Materials Activity Equipment Manpower
5. WORK METHODOLOGY
Excavation
Survey for layout shall be conducted first before excavation shall be started. The
trench shall be excavated to the line, depth and grade necessary for the placement
of Box culvert.
Bedding
After the trench has been excavated to the required depth and width, bedding shall
be compacted. Bedding for box culvert shall be on two layers, first layer shall be
Hanjin Heavy Industries and Const. Co. LTD.
16
Layout of theBox Culvert
Excavation
- Excavator
- Operator
- Surveyor
- Foreman
- Laborers- Driver
Installation of
rebar andforms
Concrete
Pouring
Bedding
- Plate
Compactor
- Excavator
- Cargo Truck
- Bar Cutter
- Bar Bender
- Tr
ansit Mixer
- ConcretePump
- ConcreteVibrator
-ReinforcingBars
-Forms
- Concrete
- Gravel
Backfilling
- Pl
ate
Compactor
- Selected Fill
- Operator
- Surveyor
- Foreman
- Laborers- Driver
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
17/30
Construction Method
100 mm compacted gravel bedding and final bedding shall be 100 mm THK Lean
concrete. In case where the water level is higher than the elevation of the bedding
and compaction is not possible, water pump will be used to drain the water.
Survey checking of elevation of the bedding shall be done before the installation of
rebar and forms.
Installation of Rebar and Forms
Installation of reinforcing bars will take place after the bedding and compaction
operation is done. All reinforcement shall be fabricated at the yard and shall be
transported at the site area so as to have an orderly working place. Reinforcing bars
shall be cut and bend according to the specification and plans.
Forms shall be installed after the installation of rebar. Plywood shall be used for
sheathing and shall be framed with a combination of G.I pipe and lumber. Shoring
on forms shall be tightly installed so as to avoid movement of forms when pouringof concrete take place.
Concreting Works
Concrete construction shall conform to the requirements of Specifications.
Backfilling & Compaction
Backfilling and compaction shall be done with the used of loader and plate
compactor. It shall be continued until the fill has reached the required elevation
density.
Hanjin Heavy Industries and Const. Co. LTD.
17
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
18/30
Construction Method
RC PIPE CULVERTS
1. SCOPE OF WORK
The work include furnishing of all labor, materials and equipment required in
accordance with the specification and as shown on the drawing for the execution of
the following activities:
Description Unit Quantity
RCPC 910mm dia. (Regular Strengths) l.m 2240
2. EQUIPMENT
Excavator
Dump Truck
Plate Compactor
Cargo Truck
Survey Instruments
Truck Crane
3. MANPOWER
Field Engineer / Foreman
Surveyor
Survey Aides
Common Laborers Operators
Hanjin Heavy Industries and Const. Co. LTD.
18
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
19/30
Construction Method
4. WORK OF FLOW
Materials Activity Equipment Manpower
5. WORK METHODOLOGY
Excavation
Survey for layout of the drainage line shall be conducted first before excavation
shall start.
Excavation for pipe laying shall be done with the used of excavator.
The trench shall be excavated to the line, depth and grade necessary for the pipes
to be laid. It shall have a maximum width of 2 times the diameter of the pipe.
Bedding
Bedding for the RC pipes shall be compacted with the used of plate compactor,
after the trench has been excavated to the required depth and width. FDT testing
shall be conducted and the bedding shall pass to the requirement of the
specification.
Hanjin Heavy Industries and Const. Co. LTD.
19
Layout of thedrainage line
Excavation
- Excavator
- Operator- Surveyor
- Foreman
- Laborers- Driver
Placing of RC
Pipes
Backfilling
Bedding
- Plate
Compactor
- Excavator
- Cargo Truck
- Pl
ate
Compactor
RC Pipes:
- 910mm dia.
- Selected Fill
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
20/30
Construction Method
In case where the water level is higher than the elevation of the bedding and
compaction is not possible, water pump will be used to drain the water.
Survey checking of elevation of the bedding shall be done before pipe laying,
installation of manhole and catch basin shall start.
Placing of Pipes
The pipe shall be laid carefully. It shall be lifted and placed to the trench with the
used of excavator.
The joints of RC pipe shall be provided with collar filled with mortar.
The inner ends of the RC pipes shall be flushed with the inner face of the wall in
manhole and catch basin outside face of the wall in case of outlet structure.
Backfilling
After the pipe has been installed and the mortar joints sufficiently set, backfilling
shall be started.
The backfilling materials shall be place along side of the pipes in layer of 150mm
in depth and compacted so that on each side of the pipe there shall be thoroughly
compacted material of the same height.
Backfilling and compaction shall be done with the used of loader and plate
compactor. It shall be continued until the fill has reached the required elevation.
Hanjin Heavy Industries and Const. Co. LTD.
20
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
21/30
Construction Method
GROUTED RIPRAP
1. SCOPE OF WORK
This item shall consist of the construction of Grouted Riprap in minor structures,toes of slopes and other locations called on the Plans, and in conformity with the
plan and specification and shall conform to the lines, grades and dimensions as
shown on the plans.
The activities to be done are as follows:
Description Unit Quantity
Grouted Riprap Class A cu.m. 17,350.0
2. EQUIPMENT
Excavator
Dump Truck
Plate Compactor
Concrete Mixer
3. MANPOWER
Operator
Driver
Skilled Laborer
Common Laborer
Hanjin Heavy Industries and Const. Co. LTD.
21
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
22/30
Construction Method
Hanjin Heavy Industries and Const. Co. LTD.
22
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
23/30
Construction Method
4. WORK FLOW
Materials Activity Equipment Manpower
5. WORK METHODOLOGY
Excavation
The bed for riprap shall be excavated to the required depths and properly
compacted, trimmed and shaped. The riprap shall be founded in toe trench dug
below the depth of the scour as shown on the drawings or as directed by the
Engineer. The Toe trench shall be filled with stone of the same class as that
specified for the riprap unless otherwise specified.
Placing
Stone placed below the water line shall be distributed so that the minimum
thickness of the riprap is not less than that specified.
Stones above the water line shall be placed by hand or individually by machines.
They shall be laid with close, broken joints and shall be firmly bedded into the
slope and against the adjoining stones. Each stone shall be laid with its longest axis
perpendicular to the slope in close contact with each adjacent stone. The riprap
shall be thoroughly rammed into a place as construction progresses and thefinished surface shall present an even, tight surface. Interstices between stones
shall be filled with small broken fragments firmly rammed into place.
Grouting
When specified, stones shall be placed by hand, or individually by machine as
specified for riprap placed above the water line. The spaces between the stones
shall then be filled with cement mortar as required in the specification. Sufficient
mortar shall be used to completely fill all voids, except that the face surface of the
stones shall be left exposed.
Hanjin Heavy Industries and Const. Co. LTD.
23
Excavation- Excavator
- Dump truck
Hauling/Placing
Grouting
- Operator
- Driver
- Skilled Labor
- Common
Labor
-Stone,
-Cement
-Sand -Skilled
Laborer
-Common
Labor
- Concrete
Mixer
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
24/30
Construction Method
Hanjin Heavy Industries and Const. Co. LTD.
24
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
25/30
Construction Method
REINFORCED CONCRETE DITCH
1. SCOPE OF WORK
This item consists of constructing ditches composed of reinforced concrete,
grouted riprap, and earth materials. These structures will serve as waterway toavoid flooding on roads.
The activities to be done are as follows:
Description Unit Quantity
Reinforced Concrete Ditch with Cover, Type A L.m. 7,975.0
2. EQUIPMENT
Excavator
Dump Truck
Plate Compactor
Concrete Mixer
3. MANPOWER
Operator
Driver
Skilled Laborer
Common Laborer
Hanjin Heavy Industries and Const. Co. LTD.
25
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
26/30
Construction Method
2. WORK FLOW
Materials Activity Equipment Manpower
5. WORK METHOLOGY
Excavation
Excavation shall be done by the use of excavator. The bed where the ditch will be
constructed shall be cleared and cleaned to the satisfaction of the Engineer.
Compaction
The bed of ditch shall be compacted by the use of plate compactor. It shall be
compacted to a degree so as to present a relatively even surface and have a state of
bonding to some extent.
Installation of Forms and Rebars
After the compaction of bed, installation of forms and reinforcement bars will take
place. Reinforcing bars shall be according to specifications and forms must be
properly installed to avoid buckling when concrete pouring take place. Dimension
of the ditch shall properly be observed so as to meet the Drawing shown in the
plans.
Concreting Works
Concrete construction shall conform to the requirements of Specifications.
Hanjin Heavy Industries and Const. Co. LTD.
26
Excavation- Excavator
- Plate
Compactor
Installation of
forms and
Rebar
- Operator
- Skilled Labor
- Common
Labor
-Driver
-Skilled
Laborer
-Common
Labor
- Cargo Truck
- Bar Cutter
Fabrication of
Ditch Cover
Concreting
Compaction
- Concrete
Mixer
-Skilled
Laborer
-Common
Labor
-Sheathing
Form
-Rebar
-Sand
-Gravel
-Cement
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
27/30
Construction Method
STONE MASONRY
1. SCOPE OF WORK
This item of work consist of stone masonry in minor structures, in retainingwalls at the toes of slopes and at other locations called for on the Plans, in
accordance with the Specification and in conformity with the lines, grades,
sections and dimensions shown on the Plans.
The activities to be done are as follows:
Description Unit Quantity
Stone Masonry (Retaining Wall) cu.m. 6,580.0
Stone Masonry (Dwarf Wall) cu.m. 1,876.0
2. EQUIPMENT
Dump Truck
Excavator
Plate Compactor
3. MANPOWER Operator
Driver
Skilled Laborer
Common Laborer
4. WORK METHODOLOGY
Selection and Placing
The foundation bed shall be firm and normal to the face of the wall and shall be
approved by the Engineer before placing any stones. Stones to be set shall be
cleaned and the bed is to receive them shall be cleaned and moistened before the
mortar is spread. Setting and laying of stones shall be in accordance with the
specifications.
Beds and Joints
Beds and joints shall not extend in an unbroken line through more than five and
two stones respectively. Cross beds for vertical walls shall be level, and for
Hanjin Heavy Industries and Const. Co. LTD.
27
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
28/30
Construction Method
battered walls may vary from level to normal to the batter line of the face of the
wall.
Hanjin Heavy Industries and Const. Co. LTD.
28
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
29/30
Construction Method
Cleaning Exposed Faces
Immediately after being laid, and while the mortar is fresh, all face stones shall be
thoroughly cleaned of mortar stains and shall be kept clean until the work is
completed.
Curing
In hot or dry weather, the masonry shall be protected from the sun and shall be
kept wet for a period of at least three days after completion.
Hanjin Heavy Industries and Const. Co. LTD.
29
8/3/2019 CM_ Bored Pile, MSE Wall, Drainage Structures
30/30
Construction Method