25
C.Limborg-Deprey LCLS FAC , Oct 2005 [email protected]. edu Oct 27th 2005 1 Injector Physics C.Limborg-Deprey GTL final design Wakefield budget Final Modifications Commissioning Readiness Schedule Feedback systems An example of tuning procedure Steering in L0a

C.Limborg-Deprey LCLS FAC, Oct [email protected] Oct 27th 2005 1 Injector Physics C.Limborg-Deprey GTL final design Wakefield budget Final

  • View
    216

  • Download
    1

Embed Size (px)

Citation preview

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 20051

Injector PhysicsC.Limborg-Deprey

GTL final designWakefield budgetFinal Modifications Commissioning Readiness

ScheduleFeedback systems

An example of tuning procedureSteering in L0a

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 20052

Injector

PORCU

PINE CATHODE

HOLDE

R

UHV A

LL METAL

GATE VALVES

SPOOLS FRO

M VALVE

SEAL

LONG B

ELLOWS

ASSEM

BLY

TREATMEN

T CHAM

BER

VACUU

M PUMPS

Gun installation Nov. 2006

Gun Region July 2006

Accel Region June 2006

Heater Region June 2006

Wall Region October 2005

Waveguide October 2005

Injection Region Aug-Nov 2006

Spect Region Aug-Nov 2006

Injector Commissioning Start December 2006

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 20053

Gun to Linac Region

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 20054

GTL Design

Normal incidenceMirror size (14mm x 10 mm)

No second Valve in GTL All wakefield computed

(see next slides)Diagnostics units finalized

accommodate 20 mm screens wakefield mitigation

Gun Solenoid moved as close as possible to cathode

Bucking Coil added (PRD written)cancels the 55 Gauss Bz field on cathode

Compatibility with gun bake + cathode removal

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 20055

GTL Design

Pending issues<1.05 permeability of VV01

Impact on Bsolenoid falling edge to be measured

Choice of material for injector mirrorOptical path for CRG1 lightFinalization of GTL BPMs to meet 20 m resolutionAlignment laser specificationsFinal GTL design review next week Courtesy J.Langton

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 20056

Wakefield Budget

projected <1.2 mm-mradwith no error simulations show 1.0 mm-mradStability of electro- magnetic components to meet less than 10% increase<10 % increased from total wakefield effects over the whole beamline

GTL area is critical region

Injection mirror with 1mm beam offset

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 20057

Case d L Wake

(1) 6 mm 10 mm 0.247 V/pC on axis

(2) 6 mm 10 mm 146 V/pC/m

(3) 6mm 15 mm 171 V/pC/m

(1) (2) (3)

MAFIA Simulations, Courtesy Cho-Kuen Ng

Wakefield from Injection Mirror

d

L

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 20058

Wakefield Mitigation in GTL

Pumping slots 0.24 V/pC/m per unit 3 units at 0.6 m3 units at 1.2 m Negligible emittance growth

Combined Diagnostics chambers Wakefield Mitigated ~small gaps

Courtesy J.Langton

Courtesy Cho-Kuen Ng

Pumping slot

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 20059

Wakefield Mitigation in GTL

Spectrometer bend chamberWakefield mitigation movable plug

Eliminates any wakefield Small gap

BellowsSleeve on each 7Small step transition instead of 25V/pC/m

]//[34.433

mCVga

cZk z

oloss

Gaps1mm gap ~ 3V/pC/m Beam to

Spectrometer

Straight beam

Courtesy J.Langton

Plug out

Sleeve

Bellows

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200510

oo

2

2

1~

Wakefield in Radiation Stopper

Radiation Stopper not an issueLCLS-TN-05-15

"Wakefield Calculations for Radiation Stopper 1  (RST1)“

Wrms < 0.077V/pC on axis

/ < 0.1% due to small =1.5 m

MAFIA computations

Courtesy Cho-Kuen Ng

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200511

Final changes in Accelerator Region

Courtesy P.Stephens

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200512

Beamline Modifications

L0a moved downstream by 8 cmOk with emittance compensation

Solenoid 2 reduced to 20 cm effective length magnet (Req. sent out)

higher Bfield for same focal length

higher Bfield is not an issue

Suppressed one out of 2 BPMs in L0a-L0b drift4 inch Phase monitor fits inValve moved from L0a entrance to L0a-L0b drift

Mu-shield metal wrapped around all possible locationPRD 1.1-009Unfortunately not possible in GTL

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200513

Diagnostics

Critical decisionsSpecifications for screens and resolution finalized (PRD out)CR material: 1mm thick, quartz, to be replaced with aerogel laterOTR cameras orientation to increase depth of fieldStreak camera orderedChoice of CCD cameras finalized

Remaining issuesOptical path for CRG1 light2nd pick-up on toroid for BCS Alignment laser spec. to be finalized Finalization (Resolution) of BPM design for large aperture pipe

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200514

Commissioning Schedule Discussed every 5th week with LCLS physicists/operators group

To be incorporated into large *.mpp document for linksDiscussed weekly inside Injector group

(Bong, Dowell, Limborg, Loos, Schmerge …)Based on 2 shifts per dayResource loading to be refined

2 physicists per shift + 1 control person + 1 operator guests

Meeting will evolve in high level application discussionSchedule Outline

Starts with RF Gun cold and hot test (summer 06)First beam at 135MeV dump (Nov.22-06 Dec.06)8 months of characterization and optimization

Deliver most stable beam for acceptable charge for BC1 commissioning at end of June07

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200515

Schedule December 06

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200516

Commissioning Readiness

Pending issuesHot test schedule

Finalize start date, detailed schedule

Feedback Systems

Calibrations procedure Magnetic calibration procedure drafted

Screen calibration procedure

High Level Applications

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200517

High Level Applications

Cathode characterization (QE, uniformity, Thermal emittance)Steering in L0aLongitudinal phase space measurements at BXG Bunch length measurement with transverse RF deflector(s)Emittance meas. (multi-wire, multi-OTR, quad-scan, slice)Power-steering through beamlines, with corrector weightsDifference orbit fitting, including internal kickLongitudinal phase space measurement at BXS Tomography (Longitudinal and Transverse)…

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200518

Feedback SystemsPointing Stability (see Laser)

ToleranceSlow (f<1Hz) : <200 m (or slice emittance degraded)Fast (1Hz<f<120 Hz): <10 m (1% of “10% x,undulator budget”)

Slow feedback : Sensor/ actuatorVirtual cathode / mirrorsStatus : preliminary tests at bldg 407

Fast stability Design constraint (Gun + injection mirror + vacuum chamber “rigidly” linked to optical launch table ,i.e. less than 10m fast motion )

Charge Stability (see Laser)Tolerance

Fast (shot-to shot) < 2%rmsSensor/Actuator

first toroid IM01/ polarizer

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200519

Feedback Systems

Timing StabilityTolerance

Fast stability (120Hz),laser phase w.r.t master clock < 0.5 ps rms

feedback system sensor : phase monitor signal actuator: locking electronics from Thales system

Slow stability (<1Hz), laser phase w.r.t gun phase < +/-3 ps to maintain emittance within 5% of optimal

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200520

Steering in L0a

SolenoidSC0 SC1 SC2

BPM2 BPM3 BPM5Gun L0a

Solenoid mispositioning 250 m, 250 rad

Earth Magnetic field 2mrad/m vert.

No space for mu-metal shielding in GTLBy ~ 0.35 GBx ~ 0.12 G

Offset as large as 3mm without steering

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200521

Simulations of steering

SolenoidSC0 SC1 SC2

BPM2 BPM3 BPM5Gun L0a

Procedure

L0a solenoid offOrthogonal knobs at SC0 SC0 and SC1 adjusted to steer in L0a

Scaling of SC0 orthogonal knobs with solenoid to be implemented in software when

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200522

Conclusions

GTL Design finalized

L0a-L0b space issue solved

“Laser Heater” region to be detailed

Commissioning schedule under completion

Feedback systems under completion

High Level Applications to be written

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200523

Response to the April FAC Recommendations

Wakefield in Gun Large Energy spread in gun identified to be related to 0-mode

ACD group will perform more simulations

3D-ellipsoidal laser pulses Presented at major conferences, in particular at FEL05 with good interest shown from many laser experts

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200524

BACK-UP

C.Limborg-Deprey

LCLS FAC , Oct 2005 [email protected]

Oct 27th 200525

Hot test scheduleObjectives

Task1 : RF ConditioningTask2 : Verification of thermal design (f vs Power, f vs T)Task3 : Close LLRF feedback loop

LLRF feedback loop can only be closed if availability of Chiller, Instrumentation of detection of phase from reflected power signal, Drive Amplifier

Four scenarios discussed

Klystron lab. (PEP bunker)

Aug. 06

S20

July 06

S20

Sep 06

S20

Dec06

+ Early start, possible retrofit

No impact on S20 work

Early start

No special PPS

Single installation

No (-) from previous 2

All (+) from previous 2

“Special PPS” forced in (*)

Early commissioning

All systems ready

No special PPS

No impact on S20 work

- Dvt Local Control

Shielding work , add parts

Long WG to be found

Task 3 cannot be completed

PPS finished unlikely

Access Timing cables

Impact laser work

Task 3 cannot be completed

“Special PPS” difficult to obtain

High Technical risk

Delays Commissioning with beam

(*) “Special PPS” == run klystron + e beam to spectrometer during linac downtime