1[12-Feb-2014] «BE-RF-PM»
CLIC TBM Prototype T0@CLEX
Status update
EDMS №[Number]
Dmitry Gudkov
1
2[12-Feb-2014] [CMWG Meeting] «BE-RF-PM» 2
CONTENTS
• TBM integration in CLEX
• Supporting system
• CLEX room in LAB-169. Status of the room preparation
• Preliminary planning for the TBM installation in CLEX
3[12-Feb-2014] [CMWG Meeting] «BE-RF-PM» 3
TBM Integration of the in CLEX
• The integration is under way, but..• DB optics configuration has been changed (new input received from Jakob)
Position of center [m]Electromagnetic length of element []Type of element Name of element0.3475 0.295 '"QUADRUPOLE"' '"TL2.QDD01"'1.0425 0.295 '"QUADRUPOLE"' '"TL2.QFD02"'
3.265786468 0.451572936 '"RBEND"' '"TL2.BHC01"'6.233502936 0.325 '"QUADRUPOLE"' '"TL2.QFD04"'8.592002936 0.38 '"QUADRUPOLE"' '"TL2.QDD05"'10.95050294 0.325 '"QUADRUPOLE"' '"TL2.QFD06"'13.9177894 0.451572936 '"RBEND"' '"TL2.BHC02"'
15.06096587 0.325 '"QUADRUPOLE"' '"TL2.QDD07"'15.63596587 0.325 '"QUADRUPOLE"' '"TL2.QFD08"'20.76096587 0.325 '"QUADRUPOLE"' '"TL2.QDD09"'21.33596587 0.325 '"QUADRUPOLE"' '"TL2.QDD10"'23.29201587 0.22 '"QUADRUPOLE"' '"CM.QFD0310"'23.79201587 0.22 '"QUADRUPOLE"' '"CM.QDD0315"'24.29201587 0.22 '"QUADRUPOLE"' '"CM.QFD0320"'25.90225587 1.00048 '"RFCAVITY"' '"P1"'27.46643287 0.22 '"QUADRUPOLE"' '"CM.QFD0565A"'28.09777587 0.22 '"QUADRUPOLE"' '"CM.QFD0565B"'
29.05925 0.5235 '"RFCAVITY"' '"P2"'29.5625 0.27 '"QUADRUPOLE"' '"QTB1"'
30.05175 0.5235 '"RFCAVITY"' '"P3"'30.555 0.27 '"QUADRUPOLE"' '"QTB2"'
33.19201587 0.22 '"QUADRUPOLE"' '"CM.QFD0560"'34.19201587 0.22 '"QUADRUPOLE"' '"CM.QFD0570"'37.19399775 0.482161132 '"RBEND"' '"CM.BHB0600"'
Jakob Esberg
• The new study is needed in order to check:• If new positions of the components in CLEX can be applied• Components supporting girder, study is needed.
4[12-Feb-2014] [CMWG Meeting] «BE-RF-PM» 4
Supporting system status
• All 4 girders have been controlled by metrology
• The cradles have been controlled by metrology
Results (axis straightness)MBO-2 :0.010 mmMBO-1 :0.014 mmDBO-1 :0.012 mmDBO-2 :0.012 mm
• ZTS visit for installation of the equipment is confirmed: 24.02 – 28.02
report is under preparation
We are waiting for the detailed visit program from ZTS.
• CLEX room in the LAB-169 is under preparationSee next slides
5[12-Feb-2014] [CMWG Meeting] «BE-RF-PM»
CLEX room in LAB-169. Status of the room preparation
• The floor drilling is finished• Threaded inserts are installed• The location of the racks is defined
OPEN POINTS:• Acquisition and control needs?
• Electricity• Internet• Temperature in the LAB (18-28 deg.)
• Is everything ready? (SU)
RACKS
6[12-Feb-2014] [CMWG Meeting] «BE-RF-PM» 6
Lab 169/S-039: Implantation drawing
Espace réservé pour manutention
Perçage et installation des chevilles diamètre 20 et 16mm après le tracé du positionnement des supports par les géomètres
40 trous OK
Le lab. CLEX est prêt pour l’installation des supportsP. de Souza, S. Lebet
Planéité des supports métrologique ???Rectitude environ 15mm
P. de Souza, S. Lebet
9[12-Feb-2014] [CMWG Meeting] «BE-RF-PM» 9
Preliminary planning for the TBM installation in CLEX