Clean TeQ Sunrise
CCC Meeting – 29 November 2019
Clean TeQ Sunrise
Project Update
Community Engagement Update
Environmental Management Update
CCC Member Questions
Summary
CCC Meeting Presentation – 29 November 2019 Page 2
Project Update
Page 3
Clean TeQ Sunrise
Project Update
CCC Meeting Presentation – 29 November 2019 Page 4
• Sunrise Project Team working to prepare Project Execution Plan.
• This work covers updating Sunrise project schedule and cost based on project development since the DFS.
• Continue to work with the Shires of Lachlan and Forbes on the water pipeline agreement, with good progress made.
• Positioning Sunrise to be ready for a final investment decision in mid-2020, subject to the completion of a financing package by that time.
• Various parties remain engaged in the Sunrise partnering process.
Clean TeQ Sunrise
Project Update
CCC Meeting Presentation – 29 November 2019 Page 5
• Completed drilling program
• Completed bypass fencing
• Particulate monitoring installation progressing
• Ongoing site maintenance activities
Clean TeQ Sunrise
Emergency Management Plan• Emergency Maps• Assembly Points• Liaising Emergency ServicesProperty Clean Up• Scrap metal recycled • Sump oils recycledWeed Spraying• Training for spot spraying• Contract for wide area sprayingKangaroo Culling• Contractor commissioned • Commercial harvesting • Licence approved
Land Management
CCC Meeting Presentation – 29 November 2019 Page 6
Before. After.
Community Engagement Update
Page 7
Clean TeQ Sunrise
What we’ve been up to
CCC Meeting Presentation – 29 November 2019 Page 8
Building relationships across the community through engagement and active participation
– Participated in and sponsored the Trundle Bush Tucker day
– Hosted the Northern Panel of the Grains Research and
Development Corporation (GRDC) for two days in the Parkes
office
– Provided in-kind support in planning the 2019 Condo SkyFest
– Rolled out the Happy Daze coffee cart at the Western Business
Forum
Clean TeQ Sunrise
What we’ve been up to
CCC Meeting Presentation – 29 November 2019 Page 9
• Education and Investment
– Hosted a school holidays BBQ in Forbes with the Lake Cowal
Conservation Centre – providing a sausage sizzle lunch and a range of
fun environmental activities
– Supported Parkes Public School through our matched funding program
to assist with playground upgrades
– Provided matched funding to the Bedgerabong Public School to assist
with the installation of sunshades over play areas
– Purchased two x 50,000 Ltr water tanks for the Warroo Community Hall
Clean TeQ Sunrise
VPA investment at work
CCC Meeting Presentation – 29 November 2019 Page 10
• New shade sail in the Hannah Mahon Park was the first
project completed under the VPA funds with many more
to come. Lachlan Children Services also received a
new sun sail on Wednesday this week.
• Parkes Shire Council has recently placed the Trundle
Mainstreet paper on public exhibition and is calling for
community feedback
Clean TeQ Sunrise
Keeping people informed
CCC Meeting Presentation – 29 November 2019 Page 11
• Community newsletter– Published in September, next edition late December
– Distributed through newspapers, mailbox and e-delivery
– Dennis Brady profiled in the September edition– Steve Karaitiana is up next
• Fact Sheets – available on the webpage as completed • Facebook – continue to share short articles on Facebook • Website
– Complaints register published, zero complaints received YTD
• Shop fronts– Continue to operate in Condobolin, occasionally in Trundle
Environmental Management Update
Page 12
Clean TeQ Sunrise
• Environmental Management Strategy has been approved
• The following EMPs (incorporating Modification 4 changes) have been approved for the initial construction activities by the DPIE:– Environmental Management Strategy– Blast Management Plan– Road Upgrade and Maintenance Strategy– Noise Management Plan– Heritage Management Plan– Rehabilitation Management Plan – Biodiversity Management Plan and Revegetation Strategy– Traffic Management Plan
• EMPs approved for the “initial construction activities” will need to be revised and re-approved by DPIE before commencement of any works after this stage
Environmental Management Plans (EMPs)
CCC Meeting Presentation – 29 November 2019 Page 13
Clean TeQ Sunrise
Environmental Monitoring – Air, Noise, Groundwater
CCC Meeting Presentation – 29 August 2019 Page 14
AIR
• Real time particulate matter monitors
– EPA approved - Teledyne API T640x
– Installed this week
NOISE
• Quarterly noise monitoring
– Completed 11 September 2019
– Scheduled 2/3 December 2019
GROUNDWATER
• Monitoring undertaken 11-15 November 2019
• Standing water levels and water quality from minesite and borefield
CCC Member Questions
Page 15
Clean TeQ Sunrise
• No questions received
CCC Member Questions
CCC Meeting Presentation – 29 November 2019 Page 16