Clarifying the Scope of Preliminary Design Presentation

Embed Size (px)

Citation preview

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    1/44

    SHORTENING PROJECT DELIVERYINITIATIVE

    CLARIFYING THE SCOPE OF PRELIMINARY

    DESIGNDate Prepared: 9/28/2010 1

    EDC Training Regional SummitTysons Corner, VA October 4th, 2010

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    2/44

    Preliminary Design Initiative

    Planning NEPA ROW Design / Construction

    Description:

    Highlight the existing flexibilities in statute andregulation related to advancing project specificdesign activities.

    These flexibilities are available regardless ofproject delivery mechanism prior to NEPA

    approval.

    Leaning ForwardApproach to Preliminary Design2

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    3/44

    Preliminary Design Overview:

    .

    3

    Benefits: slide 1 of 2

    Reduces overall project delivery times;

    Streamlined project delivery. Provides guidance on the design activities that can be

    conducted during the NEPA process;Clarifies existing flexibilities in regulations.

    Improves project decision-making;More information to the public and agencies.

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    4/44

    Preliminary Design Overview:

    Benefits: slide 2 of 2

    Reduces costs in developing and delivering projects;

    Faster delivery to the public.

    Enhances consistency among FHWA Division offices &State DOTs;

    Consistent interpretation of statutes & regulations.

    Improves agency & staff capacity to make risk-baseddecisions; and

    Ensures the integrity of the NEPA process.

    4

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    5/44

    What Can We Do Under Existing

    Statutes / Regulations ?The activities that are presumed to be preliminary designand can be carried out prior to final NEPA decision

    include:

    Activities listed in the definition ofpreliminary design at 23CFR 636.103:

    Environmental assessments, topographic surveys, metes and

    bounds surveys, geotechnical investigations, hydrologicanalysis, hydraulic analysis, utility engineering, traffic studies,financial plans, revenue estimates, hazardous materialsassessments, general estimates of the types and quantities ofmaterials.

    5

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    6/44

    What We Want You To

    Advocate To Your Staff.Slide 1 of 2:

    Take advantage of existing flexibilities that help allow

    your State to expedite project delivery.

    Where feasible, your State should move forward withpreliminary design work.

    As long as no commitments are made to any alternative

    being evaluated in the NEPA process and the design work

    does not prejudice the objective comparison of all

    alternatives.

    6

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    7/44

    What We Want You To

    Advocate To Your Staff.Slide 2 of 2: Perform preliminary design activities

    concurrently with the NEPA process in

    compliance with NEPA regulations at 23 CFR Part771 and 40 CFR Parts 1500-1508 and

    These activities typically do not limit the choice ofreasonable alternatives as required by 40 CFR

    1506.1(a)-(b).

    7

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    8/44

    Preliminary Design:

    What We Cannot Do!

    Final Design Activities that can NOT be advanced prior

    to NEPA completion:

    Any design activities that are not preliminary design. Thisincludes the preparation of final construction plans and

    detailed specifications for the performance of construction

    work.

    The activities in the definition offinal design at 23 CFR636.103 are considered to be final design. They include

    final plans, project site plan, final quantities, and final

    engineers estimate for construction.8

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    9/44

    KeySteps

    National EnvironmentalPolicy Act (NEPA)Process FHWA

    decision on

    alternatives

    Consult with resourceand other agencies

    Identify necessaryenvironmental permits

    for construction

    KeyStepsAdoption in local/

    regional plans TransportationImprovement

    Program

    Air Quality planapproval

    StatewideTransportationImprovement

    Program

    Federal certification

    of planning process

    Comply with UniformAct for right-of-way

    acquisition

    Obtain permits

    Environmentalcommitment

    compliance duringconstruction

    Planning Process

    Systems Planning:

    Identifies projects

    and funding

    Project Development

    Environmental process,Project Planning and

    Preliminary Design

    Project Implementation

    Final Design, Rightof Way and

    Construction

    What We Need States to Do.

    Interdisciplinary Decision-Making:

    9Preliminary Design

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    10/44

    Post NEPA

    Project Development

    Activities

    Transportation Project

    Development Process:Planning

    Right-of-Way

    NEPA

    Construction

    Need, alternatives and impact analysis, public

    / agency coordination, documentation (CE,

    EA/FONSI, EIS/ROD) Preliminary Design

    Final Design

    NEPA Approval: Location, design concept acceptance

    System considerations, coordination,

    conformity, project need

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    11/44

    NEPA Processing Options:(Classes of Action)

    NO

    Proposed Action

    Coordination andAnalysis

    Significant Impact ?

    ListedCategorical

    Exclusion (CE)

    Public Comment

    DocumentedCategorical

    Exclusion (CE)

    EnvironmentalAssessment

    (EA)

    Significantimpact

    Notice of Intent & ScopingProcess

    Draft Environmental ImpactStatement (EIS)

    Record of Decision (ROD)

    Final Environmental ImpactStatement (EIS)

    Agency ActionAgency Action

    Finding of NoSignificant Impact (FONSI)

    Agency Action

    Coordination and

    analysis as needed

    No significantimpacts

    Unknown

    YES

    Documentappropriately

    Major ProjectMinor Project

    Preliminary

    Design

    Preliminary

    Design

    Final Design

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    12/44

    Preliminary Design Questions

    to Ask & Consider.

    1) Is the design activity in compliance with applicableCEQ regulations?

    Under CEQ Regulations for Implementing NEPA (40CFR Part 1506.1), until an agency issues a Record ofDecision no action concerning the proposal shall betaken which would limit the choice of reasonablealternatives.In addition, while work on NEPA is ongoing, agencies shall

    not undertake in the interim any major Federal actioncovered by the program unless that action would notprejudice the ultimate decision on the program and wouldnot limit alternatives.

    12

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    13/44

    Preliminary Design Questions

    to Ask & Consider.2) Is the design activity in compliance with FHWA

    NEPA regulations (23 CFR 771)?

    FHWA will perform the work necessary to completea FONSI or an EIS. This work includes environmentalstudies, related engineering studies, agencycoordination and public involvement.

    Until a project is classified as a CE, or a FONSI orROD is signed, no work related to final designactivities is allowed to proceed.

    13

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    14/44

    Preliminary Design

    Questions to Ask & Consider.

    3) Is the design activity in compliance with FHWAsDesign-Build regulations?

    In 2007 FHWA adopted definitions of preliminarydesign and final design in its Design-Build Regulationat 23 CFR 636.103. The definitions apply across the Federal-aid Highway

    program, without regard to contracting mechanism.

    Those definitions, when read together with the FHWA andCEQ NEPA regulations, define design activities that may beallowable prior to completion of the NEPA process (CE,FONSI, or ROD).

    14

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    15/44

    What Can We Do Under Existing

    Statutes / Regulations ?

    Currently, the majority of State DOTs advanceFederal-Aid projects through a Design-Bid-Build

    (DBB) and Design-Build (DB) contracting mechanism.

    It is important to note that for the purposes of NEPA,

    it does not matter under which contract mechanism a

    Federal- Aid project is advanced.

    The same flexibilities related to preliminary design

    that can be carried forward prior to completion of the

    NEPA process apply to both contract mechanisms.

    15

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    16/44

    What Can We Do Under Existing

    Statutes / Regulations ?

    Preliminary design activities can be conductedprior to completion of the NEPA process if

    carried out in a manner that would notmaterially affect the objective consideration of

    alternatives being considered in the NEPA

    review process.

    What do we mean by this? See next slide

    16

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    17/44

    What Can We Do Under Existing

    Statutes / Regulations ?

    The limitation on agency actions during NEPA doesnot preclude development by applicants of plans ordesigns or performance of other work necessary to

    support an application for Federal, State or localpermits or assistance. CEQ regulation 40 CFR1506.1(d)

    Higher levels of design work are allowed on thepreferred alternative to facilitate the developmentof mitigation measures and concurrent compliancewith other applicable laws. 23 USC 139(f)(4)(D)

    17

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    18/44

    What Can We Do Under Existing

    Statutes / Regulations ?

    The amount of engineering design work that canbe carried forward and completed throughpreliminary design, either with or without Federal

    financial assistance prior to the completion of theNEPA process, will vary from project to project.

    Determinations of what level of design permittingagencies need, and whether an activity is likely tobias the selection of alternatives or cause adverseenvironmental effects all are very fact-specific.

    18

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    19/44

    What Can We Do Under Existing

    Statutes / Regulations ?

    Activities presumed to be preliminary design include, butare not limited to:

    Activities listed in the definition ofpreliminary design at 23 CFR636.103:

    Environmental assessments, topographic surveys, metes andbounds surveys, geotechnical investigations, hydrologic analysis,hydraulic analysis, utility engineering, traffic studies, financial

    plans, revenue estimates, hazardous materials assessments,general estimates of the types and quantities of materials.

    19

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    20/44

    What Can We Do Under

    Existing Statutes / Regulations ?

    Other activities: slide 1 of 2

    Design and engineering activities to be undertaken forthe purposes of defining project alternatives; completing

    the NEPA alternatives analysis and review process;complying with other related environmental laws andregulations; environmental justice analyses; supportingagency coordination, public involvement, and permitapplications; development of environmental mitigationplans; development of typical sections, grading plans,geometric alignment (horizontal alignment, verticalalignment and any clearances necessary to meetapproved design criteria), noise wall justifications,

    20

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    21/44

    What Can We Do Under Existing

    Statutes / Regulations ?

    Other activities cont. slide 2 of 2

    bridge type/size/location studies, temporary structure

    requirements, staged bridge construction requirements,

    structural design (substructure and superstructure), retaining

    wall design, noise wall design, design exceptions, guardrail

    length/layout, existing property lines, title and deed research,

    soil borings, cross sections with flow line elevations, ditch

    designs, intersection design/configuration, interchange

    design/configuration, pavement design, storm/sanitary sewerdesign(plan/profile), culvert design, identification of removal

    items, quantity estimates, pavement details/elevation tables,

    and preliminary traffic control plans to be maintained during

    construction. 21

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    22/44

    What Can We Do Under Existing

    Statutes / Regulations ?

    Costs associated with preliminary designactivities are eligible for Federal-Aid

    reimbursement.

    FHWA is approving the advancement of theseadditional preliminary design activities earlier

    in the project development process and will

    authorize reimbursement for these activities.

    22

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    23/44

    Preliminary Design Project

    Examples:

    Drainage and storm water management.

    Dredged material quantities.

    Flexibly adjust amount of preliminary design to

    meet regulatory requirements, such as bridgesaffecting regulated wetlands.

    More detailed design of light rail projectelements to reduce cost risk.

    Core drilling to characterize soils for trenchexcavation in densely developed urban area.

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    24/44

    Drainage and Storm Water

    Management:I-95: Florida

    FL DOT tailored the storm water pond

    specifications to meet Water ManagementDistrict requirements.

    Drainage plans were completed at 60% design

    versus 30% for remainder of project. Design-build contractor still given opportunity

    for efficiency while minimizing risks.

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    25/44

    Dredged Material Quantities:

    Woodrow Wilson Bridge: DC, MD, VA

    Project sponsors held design competition duringthe NEPA process for a major design-bid-buildbridge project.

    Resulted in higher level of design informationthan previously available.

    Dredged material estimate revised from 40,000to 550,000 cubic yards.

    Separate contract was awarded for dredging; finaldredged quantity was 330,600 cu yd.

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    26/44

    Flexibly Adjust Amount of

    Preliminary Design:

    US 64 Knightdale Bypass: North Carolina

    Increase level of design to 60% at multiple

    bridges affecting regulated wetlands. Remainder of project designed to 25-30%

    where fewer sensitive resources present.

    Perform more design work to addressregulatory and permit requirements to reduce

    delay.

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    27/44

    Tailor Design Work to

    Reduce Cost Risk:

    T-Rex Project: Colorado

    CO DOT and Regional Transit District tailoredpreliminary design for different elements.

    Highway portion: 30% design

    Light rail system and drainage: 30 to 50%

    Light rail stations: 70% Result: reduced cost risk during construction

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    28/44

    Core Drilling to Characterize

    Subsurface Soils:

    ReTRAC project: Nevada

    Core drilling on 100 foot centers along railroadtracks for major railroad grade separation project.

    Improved characterization of soils for trenchesand retaining walls.

    Addressed constructability of alternatives duringNEPA process.

    Allowed project to proceed on schedule in busydowntown urban environment.

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    29/44

    Preliminary Design Interactive

    Example:

    Alternatives & Preliminary Design

    FloodplainsIndustrial Site

    Historic Site

    Neighborhood

    Route 201

    Route 101

    Project Limit Project Limit

    CommonAlignment

    CommonAlignment

    29

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    30/44

    Preliminary Design:

    What We Cannot Do!Final Design Activities that can NOT be advanced prior

    to NEPA completion:

    Any design activities that are not preliminary design. Thisincludes the preparation of final construction plans anddetailed specifications for the performance of constructionwork.

    The activities in the definition offinal design at 23 CFR636.103 are considered to be final design. They includefinal plans, project site plan, final quantities, and finalengineers estimate for construction.

    30

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    31/44

    How Do We Determine What

    Activities are Allowed ?

    What will guide me on implementing this Initiative?

    Preliminary Design Directive:

    On October 1, 2010, the FHWA issued FHWA Order

    6640.1A.

    This Directive establishes FHWAs policy regarding thepermissible project related activities that may beadvanced prior to the conclusion of the NEPA process

    regardless whether the activity is necessary to completethe NEPA process or to obtain other environmentalpermits or approvals.

    Directive relies on, and clarifies, existing definitions at 23

    CFR 636.103 31

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    32/44

    How Do We Determine What

    Activities are Allowed ?

    What will be FHWAs policy regarding which projectactivities may be advanced prior to a NEPA decision?

    State DOTs and other contracting agencies may perform

    preliminary design activities prior to a NEPA decisionregardless of the project delivery mechanism that isused.

    The definitions ofpreliminary design andfinal design

    found at 23 CFR 636.103, and clarified in the Directive,shall be relied upon by the FHWA regardless of theproject delivery mechanism used.

    32

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    33/44

    How Do We Determine What

    Activities are Allowed ?Slide 1 of 2:

    Division Administrators and State Chief Engineers mustfocus on whether the level of activities advanced priorto the NEPA decision goes too far in focusing on a

    particular alternative. In making this determination,consider and balance any relevant factors, including;

    The actual bias on the part of the decision maker thatthe proposed preliminary design activity to be advancedwill create with respect to any alternative under

    consideration;The perception of bias on the part of the community atlarge with respect to the advancement of the proposedpreliminary design activity;

    33

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    34/44

    How Do We Determine What

    Activities are Allowed ?

    Slide 2 of 2:

    The extent to which the proposed preliminary designactivity is specific to only one alternative underconsideration;

    The degree of preliminary design activities advancedfor any given alternative relative to other alternativesunder consideration;

    The estimated cost of the proposed preliminarydesign activity standing alone is substantial; and

    The degree to which the proposed preliminary designactivity relates to any specific point of controversyregarding an alternative under consideration.

    34

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    35/44

    How Do We Determine What

    Activities are Allowed ?

    In all cases, regardless of what activities areadvanced prior to a NEPA decision, FHWA

    must exercise independent judgment andretain the discretion to approve any

    reasonable alternative under consideration.

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    36/44

    How Do We Determine What

    Activities are Allowed ?

    What safeguards should be taken to ensure the FHWA

    does not authorize final design activities? Slide 1 of 2

    In project agreements in which Federal funds areauthorized for preliminary engineering, a notation

    should be made that Federal funds are authorized only

    for preliminary design.

    The execution or modification of a project agreement toauthorize final design for design-bid-build projects shall

    not occur until after the NEPA decision.

    36

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    37/44

    How Do We Determine What

    Activities are Allowed ?

    Slide 2 of 2:

    For design-build contracting, a separate notice toproceed is required for final design and construction

    by 23 CFR 636.109 and 636.302.

    37

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    38/44

    What Do States Need to Do Now

    to Implement the Initiative?

    Upon issuance of the Preliminary Design Directive,

    Division Administrators and State Chief Engineers shall

    work together to develop State specific preliminary

    design policies for:Direct oversight projects;

    State administered projects;

    Local public agency projects; and

    Design-bid-build, design-build, and other project delivery

    methods that may be used in that State.

    38

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    39/44

    What Do States Need to Do Now

    to Implement the Initiative?

    Division offices & State DOTs should begin consideringhow they will take advantage of the flexibility to pursue

    further preliminary design activities prior to the

    completion of the NEPA process.

    Our Goal:

    50% of State DOTs will have adopted the definition of

    Preliminary Design in project development policies,

    procedures or recommended practices for Federal-Aid

    projects. For States which have adopted and implemented

    the Directive, 50% of the Federal-Aid projects initiated after

    adoption will have utilized flexibility by December 30, 2011.39

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    40/44

    Preliminary Design: Resources

    FHWA Order 6640.1A.

    One Page Briefing

    Successful Practices (Case Studies) Pending References :23 CFR 636.103 (Preliminary & Final Design definitions)

    23 CFR Part 771

    40 CFR Parts 1500-1508

    40 CFR 1506.1(a)-(b)

    40

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    41/44

    Preliminary Design - Contacts

    Primary contact is your local Division Office and their EDC

    Coordinator. After coordinating with your Division office, HQ

    and Resource Center contacts include:

    Preliminary Design Team Leads:

    Harold Peaks: Team Leader Project Development Team (HEP) (202) 366-1598

    [email protected]

    Jon Obenberger: Team Leader Preconstruction Group (HIF) (202) 366-2221

    [email protected] Smith: Manager of the Env. Technical Services Team (RC) (720) 963-3210

    [email protected]

    Michael Harkins: Attorney (HCC) (202) 366-4928

    [email protected]

    41

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    42/44

    Preliminary Design - Contacts

    Neel Vanikar HEPE David Gamble - RC

    (202) 366-2068 (410) 962-0982

    [email protected] [email protected]

    Kreig Chip Larson HEPE Mary Ann Rondinella - RC

    (202) 366-2056 (720) 963-3207

    [email protected] [email protected]

    Michael Matzke HIF R. Keith Moore - HEPE

    (202) 366-4658 (202) 366-0524

    [email protected] [email protected]

    Preliminary Design Team Members:

    42

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    43/44

    Preliminary Design - Questions

    43

  • 8/6/2019 Clarifying the Scope of Preliminary Design Presentation

    44/44

    Questions on the Preliminary

    Design Initiative:

    What are your reactions to this initiative proposal? What are the pros and cons? What would you change or modify in the approach?

    Can you foresee how this initiative might improve the process?

    Are there particular barriers to this initiative being successful?

    What additional information do you need to help you make this

    initiative a success?

    How should all of us best go about getting our staff to participate?