Introduction Civil Works component p activities is directly visible to al school building or additional cla pursue their education. With the other special features, the Civil stakeholders. SSA Delhi has entrusted there was no technical manpowe Delhi has also engaged PWD f school building, additional clas provision of drinking water fac existing building etc. The 3 rd Pa the agency (Delhi Technological Achievements 1. Construction of New School Sl. No. District 1 North West Govt. 2 North West Govt. 3 North West Govt. 4 North West MCPS 5 North West MCPS 6 East Govt. 7 North East Govt. 8 West Govt. 9 South West Govt. 10 South West MCD 11 North West MCPS 12 North West MCPS Some of the school buildings co MCPS Sec-22, Rohini Civil Works- SSA plays a predominant role in SSA, as constructio ll the stakeholders and can be evaluated by one assroom can certainly promote a proper ambienc introduction of Child Friendly Element and BA l Works intervention is getting popular day by the execution of Civil Work to Delhi PWD fo er available with UEEM and further the Director for construction of various projects including, ssrooms, toilets for Girls, Boys & CWSN a cility, compound wall, development of play g arty Evaluation of monitoring and supervision h l University) appointed by SSA. Buildings School Building School Savada Ghewra, A-Block School Savada Ghewra, B-Block School Kalyan Vihar S, Savada Ghewra, F-Block S, Savada Ghewra, I-Block Co-Ed SS, J.J. Colony Khichripur Co-Ed School Buland Masjid Shastri Park School Ranhaula S. Co-Ed Vidyalaya Nangli Sakrawati Primary school, Kapashera S, Sec -22, Rohini S, Sec-27, Rohini onstructed under SSA MCPS Sec-27, Rohini on of Civil Works e and all. A good ce for children to ALA Concept and y day among the or the reason that rate of Education, , construction of alongwith ramps, ground, repair of has been done by Year 2006-07 2006-07 2007-08 2007-08 2007-08 2007-08 2008-09 2008-09 2008-09 2008-09 2011-12 2011-12

Civil Works- SSA · activities is directly visible to all the stakeholders and can be evaluated by one and all. A good school building or additional classroom can certainly promote

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Civil Works- SSA · activities is directly visible to all the stakeholders and can be evaluated by one and all. A good school building or additional classroom can certainly promote

Introduction

Civil Works component plays a predominant role in SSA, as construction of Civil Works

activities is directly visible to all the stakeholders and can be evaluated by one and all. A good

school building or additional classroom can certainly promote a proper

pursue their education. With the introduction of Child Friendly Element and BALA Concept and

other special features, the Civil Works intervention is getting popular day by day

stakeholders.

SSA Delhi has entrusted the ex

there was no technical manpower available with UEEM and further the Directorate of Education,

Delhi has also engaged PWD for construction of various project

school building, additional classrooms

provision of drinking water facility, compound wall, development of play ground, repair of

existing building etc. The 3rd

Party Evaluation of monitoring and supervision has been done b

the agency (Delhi Technological University) appointed by SSA.

Achievements

1. Construction of New School Building

Sl. No. District

1 North West Govt. School Savada Ghewra, A

2 North West Govt. School Savada Ghewra,

3 North West Govt. School Kalyan Vihar

4 North West MCPS, Savada Ghewra, F

5 North West MCPS, Savada Ghewra, I

6 East Govt. Co

7 North East Govt. Co

8 West Govt. School Ranhaula

9 South West Govt. S. Co

10 South West MCD Primary school, Kapashera

11 North West MCPS, Sec

12 North West MCPS,

Some of the school buildings constructed under SSA

MCPS Sec-22, Rohini

Civil Works- SSA

Civil Works component plays a predominant role in SSA, as construction of Civil Works

activities is directly visible to all the stakeholders and can be evaluated by one and all. A good

school building or additional classroom can certainly promote a proper ambience for children to

pursue their education. With the introduction of Child Friendly Element and BALA Concept and

other special features, the Civil Works intervention is getting popular day by day

SSA Delhi has entrusted the execution of Civil Work to Delhi PWD for the reason that

there was no technical manpower available with UEEM and further the Directorate of Education,

Delhi has also engaged PWD for construction of various projects including,

additional classrooms, toilets for Girls, Boys & CWSN alongwith ramps,

provision of drinking water facility, compound wall, development of play ground, repair of

Party Evaluation of monitoring and supervision has been done b

the agency (Delhi Technological University) appointed by SSA.

Construction of New School Buildings

School Building

Govt. School Savada Ghewra, A-Block

Govt. School Savada Ghewra, B-Block

Govt. School Kalyan Vihar

MCPS, Savada Ghewra, F-Block

MCPS, Savada Ghewra, I-Block

Govt. Co-Ed SS, J.J. Colony Khichripur

Govt. Co-Ed School Buland Masjid Shastri Park

Govt. School Ranhaula

Govt. S. Co-Ed Vidyalaya Nangli Sakrawati

MCD Primary school, Kapashera

MCPS, Sec -22, Rohini

MCPS, Sec-27, Rohini

Some of the school buildings constructed under SSA

MCPS Sec-27, Rohini

Civil Works component plays a predominant role in SSA, as construction of Civil Works

activities is directly visible to all the stakeholders and can be evaluated by one and all. A good

ambience for children to

pursue their education. With the introduction of Child Friendly Element and BALA Concept and

other special features, the Civil Works intervention is getting popular day by day among the

ecution of Civil Work to Delhi PWD for the reason that

there was no technical manpower available with UEEM and further the Directorate of Education,

including, construction of

for Girls, Boys & CWSN alongwith ramps,

provision of drinking water facility, compound wall, development of play ground, repair of

Party Evaluation of monitoring and supervision has been done by

Year

2006-07

2006-07

2007-08

2007-08

2007-08

2007-08

2008-09

2008-09

2008-09

2008-09

2011-12

2011-12

Page 2: Civil Works- SSA · activities is directly visible to all the stakeholders and can be evaluated by one and all. A good school building or additional classroom can certainly promote

Block Urban Resource Coordinator Centre Building

Sr.

No.

DISTRICT 2007-08

BURCC

1 East 1

2 North East 1

3 North 1

4 North West 1

5 West 1

6 South West 1

7 South 1

8 New Delhi 1

9 Central 1

Total 9

2. Construction of Additional Classrooms :-

Sr. District 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2010-11 2011-12 Total Porta

Cabins

Additional

Classroom

Additional

Classroom

Additional

Classroom

Additional

Classroom

Additional

Classroom

Additional

Classroom

Additional

Classroom

Completed

1 East 43 0 20 36 0 20 21 20 160

2 North East 48 82 29 30 0 15 46 10 260

3 North 40 22 10 6 0 20 12 10 120

4 North West 148 118 91 30 70 49 18 40 564

5 West 95 0 0 32 25 40 17 30 239

6 South West 87 24 0 27 41 44 10 25 258

7 South 74 104 10 10 25 30 26 20 299

8 New Delhi 8 0 0 0 0 0 0 0 8

9 Central 10 0 0 4 0 5 15 0 34

Total 553 350 160 175 161 223 165 155 1942

Sr. District 2012-13 2013-14 2014-15

Approved Comp In prog. Approved Comp In prog. Approved Comp In prog.

1 East 26 20 6 25 10 15 48 0 48

2 North East 30 6 24 20 0 20 40 0 40

3 North 26 6 20 0 0 0 21 0 21

4 North West 50 18 32 0 0 0 75 0 75

5 West 44 38 6 5 0 5 44 0 44

6 South West 44 37 7 5 0 5 77 0 77

7 South 56 42 14 5 5 0 59 0 59

8 New Delhi 10 5 5 0 0 0 0 0 0

9 Central 14 0 14 0 0 0 0 0 0

Total 300 172 128 60 15 45 364 0 364

Page 3: Civil Works- SSA · activities is directly visible to all the stakeholders and can be evaluated by one and all. A good school building or additional classroom can certainly promote

3. Construction of Additional Toilets

Sr.

No.

DISTRICT 2007-08 2010-11 2010-11 2011-12 Total

Toilets Toilets Toilets Toilets Completed

1 East 98 15 1 10 124

2 North East 132 15 8 10 165

3 North 34 10 5 10 59

4 North West 122 20 10 20 172

5 West 111 10 12 15 148

6 South West 70 15 5 15 105

7 South 8 10 19 10 47

8 New Delhi 0 0 0 0 0

9 Central 35 5 1 5 46

Total 610 100 61 95 866

GBSSS Jharoda Kalan GBSSS Pochan Pur

GSKV, East Vinod Nagar

Page 4: Civil Works- SSA · activities is directly visible to all the stakeholders and can be evaluated by one and all. A good school building or additional classroom can certainly promote

Sr. District 2012

Approved Comp

1 East 22

2 North East 32

3 North 20

4 North West 48

5 West 30

6 South West 33

7 South 37

8 New Delhi 5

9 Central 0

Total 227

GBSSS Sec-7, Rohini, Delhi

GSKV Sec-6, Dwarka

2012-13 2013-14

Comp In prog. Approved Comp In prog. Approved

10 12 5 0 5

20 12 4 0 4

8 12 0 0 0

32 16 0 0 0

26 4 6 5 1

29 4 6 5 1

33 4 6 6 0

2 3 0 0 0

0 0 0 0 0

160 67 27 16 11

GSKV Mangolpuri

SKV No.2 Sagar Pur, Delhi

2014-15

Approved Comp In prog.

15 0 15

20 0 20

8 0 8

30 0 30

32 0 32

54 0 54

65 0 65

0 0 0

2 0 2

226 0 226

Page 5: Civil Works- SSA · activities is directly visible to all the stakeholders and can be evaluated by one and all. A good school building or additional classroom can certainly promote

4. Providing of Drinking Water Facilities

Sr. District Physical Unit

1 East 6

2 North East 8

3 North 2

4 North West 11

5 West 9

6 South West 14

7 South 11

8 New Delhi 0

9 Central 7

Total 68

Budget Year Wise

Sr. No Name of the Project Amount

Sanctioned

in Year

Amount

Sanctioned

(In lakh)

Expenditure

incurred

(In lakh)

Balance

(In lakh)

BUDGET 2005-06

1 Construction of 553 Porta Cabins (2005-06) 2005-06 2101.40 2036.67 64.73

2 Provision of Drinking water facilities to 68 schools

(2005-06) 2005-06 10.20 10.20 0.00

BUDGET 2006-07

3 350 Additional Class Room (2006-07) 2006-07 1050.00 1050.00 0.00

4 School Building (Savada Ghewra (2006-07) 2006-07 80.00 80.00 0.00

5 Construction of 610 Toilet (2006-07) 2006-07 122.00 122.00 0.00

BUDGET 2007-08

6 160 Additional Class Room (2007-08) 2007-08 480.00 480.00 0.00

7 a) School Building (Khichri Pur & Kalyan Pur 2007-08 80.00 80.00 0.00

b) School building (savada Ghewra) I & F-block 2007-08 80.00 80.00 0.00

8

DURC (1. Pitam Pura, 2. Moti Bagh, 3. Daryaganj,

4.Keshavpuram, 5. Rajinder Nagar, 6.Najafgarh, 7.

Dilshad Garden, 8. Anand Vihar, 9. Kitchner Road

2007-08 54.00 54.00 0.00

BUDGET 2008-09

9 Construction of 175 ACR (2008-09) 2008-09 875.00 875.00 0.00

10 4 New School Building (2008-09) (Buland Masjid,

Ranhaula, Nangli Sakrawati & Kapashera)

2008-09 200.00 200.00 0.00

BUDGET 2009-10

11 Construction of 161 ACR (2009-10) 2009-10 966.00 966.00 0.00

BUDGET 2010-11

12 C/o of 223 ACRs (2010-11) 2010-11 1338.00 1840.15

41.970

C/o of 223 ACRs (Revised Budget) 2010-11 544.12

13 C/o of 2 New School Building (2010-11) 2010-11 156.00 223.68

14.000

C/o of 2 New School Building (Revised Budget) 2010-11 81.68

14 C/o of 100 Toilets (2010-11) 2010-11 220.00 510.00 0.000

C/o of 100 Toilets (Revised Budget) 2010-11 290.00

15 Library (Primary) 2010-11 45.75 45.75 0.000

16 Library (Upper Primary) 80.10 80.10 0.000

Supplementary Budget 2010-11

17 Additional Class Room -165 (2010-11) 2010-11 990.00 965.970 24.030

Additional Class Room -165 (Revised Budget) 2010-11 402.60 386.950 15.650

18 Separate Girl Total-61 (2010-11) 2010-11 134.20 132.35 1.850

Page 6: Civil Works- SSA · activities is directly visible to all the stakeholders and can be evaluated by one and all. A good school building or additional classroom can certainly promote

Separate Girl Total-61 (Revised Budget) 2010-11 176.90 175.0445 1.8555

19 Augmentation of Training Facilities-9 (2010-11) 45.00 0.00 45.000

BUDGET 2011-12

20 Additional Class Room -155 2011-12 1317.50 1286.85 30.650

21 Separate Girl Total-95 2011-12 522.50 485.578 36.922

22 BURC Centre-19 2011-12 323.00 0.00 323.000

23 Augmentation of Training Facilities-19 2011-12 95.00 0.00 95.000

24a Library (Primary) 2011-12 23.01 23.01 0.000

24b Library (Upper Primary) 2011-12 47.50 47.50 0.000

BUDGET 2012-13

25 New School Building 2012-13 101.84 76.38 25.460

26 Construction of ACR (300) 2012-13 2550.00 1917.600 632.400

27 Construction of Toilets (Boys) 27 2012-13 143.10 108.100 35.000

28 Construction of Toilets (Girls) 200 2012-13 1060.00 780.960 279.040

29 Construction of Ramps (100) 2012-13 70.00 50.170 19.830

BUDGET 2013-14

30 Additional Class Room -60 2013-14 582.00 436.500 145.500

31 Construction of Toilets-27 2013-14 159.30 119.475 39.825

BUDGET 2014-15

32 Additional Class Room -364 2014-15 4113.20 1888.225 2224.975

33 Construction of Toilets-226 2014-15 1371.82 573.460 798.360

GRAND TOTAL 23082.72 18272.266 4810.454

Salient Features in the construction of School buildings, Additional Classrooms:

i. Proper soil testing is done on each site to assess the suitability of the foundation and

design of the building.

ii. Earthquake Resistance:- Proper earthquake provisions as per National Building Code are

being adopted for construction (Bands at Plinth level, lintel level, roof level etc.)

iii. RCC Roof is being considered as per design for the roofing.

iv. Water proofing mud phaska/coba work on the roof.

v. The width of the Stair Case have been kept as 1.5 mtr with Handrail have been provided

keeping in view of fire protection norms, Stair Case with mumty lead up to the top of

the roof, parapet wall on the roof and proper door fixed in the entry to the roof.

vi. One cupboard have been provided for storage of books and teaching material in each

ACR

vii. One ventilator, three window, two doors are being provided for each classroom for

sufficient air ventilation and to meet out fire safety.

viii. One green board for writing surface, one pinup board is being provided in each ACR

and multiple Colours used in Walls/Doors

Page 7: Civil Works- SSA · activities is directly visible to all the stakeholders and can be evaluated by one and all. A good school building or additional classroom can certainly promote

ix. Suitable size Ramp with Railing in 1:10 or 1:12 slope is being provided for each

building block..

x. Kota Stone flooring/suitable tiles flooring

xi. Verandah – 1.8 mtr – 2 mtr width- covered with tiles upto 2 mtr.

xii. Room size: 42-44 Sq. mtr. (approx.) with Double door (1 door-3ft., 1 door-4ft., with 2

panels of 1 ft. & 3ft.)

xiii. Four ceiling fans & 5 tube lights, 1 power point, 2 switch boards with power points one

near the door and one near the black board.

xiv. Specification and estimate to be based on CPWD norms & DSR

xv. Drinking water facility, developmental work as per requirement (for school building).

xvi. Provision of BaLA concepts as per requirement (like Geometrical shape grills, Green

black board, dot board, pinup board & Pictograph, Paintings on walls with different

colors, Protractor near the door etc.)

xvii. Entire building from one end to other end be covered with steps

xviii. Writable surface be constructed on walls of the verandah.

xix. Rain Water harvesting in newly constructed schools are also provided

xx. Fire Safety measures are also provided in various schools.

Provision in the construction of Toilets

1. One W.C & one for Handicapped unit & three Urinal closet

2. Hand wash provision

3. Incinerator for disposal of Sanitary pads preferably electrical operation

4. PVC storage tank of 1000 litre.

5. Tiles flooring, cistern etc.

6. Tiles in the wall upto 2-1 mtr.

7. Drainage to the existing available disposable system.

8. Electrical- one exhaust Fan & Two or three energy efficient lights

9. Covered area – approx 25 sq. mtr.

Ramps:

1. Gradient 1:12

2. Railing on either side with mixed colours

3. Anti skid tiles with smooth finishing

4. Hand railing with some BaLA concepts

5. Width 1.6 -1.8 mtr.