CIVIL ENGINEER’S HAND BOOK FOR CONSTRUCTION SUPERVISION S.K.GUMASTA RAJASTHAN ATOMIC POWER PROJECT – 5&6

Civil Engineers Hand Book for Construction Supervision

Embed Size (px)

Citation preview

Page 1: Civil Engineers Hand Book for Construction Supervision

CIVIL ENGINEER’S

HAND BOOKFOR

CONSTRUCTION SUPERVISION

S.K.GUMASTA

RAJASTHAN ATOMIC POWER PROJECT – 5&6

Page 2: Civil Engineers Hand Book for Construction Supervision

UNVEILED BY PROJECT DIRECTOR, RAPP-5&6

ON 11.02.05 AT RAPP-5&6 SITE.

Page 3: Civil Engineers Hand Book for Construction Supervision

PREFACE In order to sustain within competitive environment, stress is

given to reduce the gestation period with maintaining the

quality standards of Construction & Commissioning of

Nuclear Power Programme. This is up most important to

reduce the construction time and cost of nuclear power

considering the above aspects. For reduction in cost of

construction few of the requirements are listed as below: -

1. Optimum use of skilled manpower.

2. Mechanization in construction.

3. Awareness of quality system to all supervisors / Engineers.

4. Create competitiveness within working group.

5. Continuous training and performance appraisal of

Supervisor / Engineers.

Construction is major part of Civil Engineering which

includes awareness regarding the Quality Control, Material

Selection, Storage & Handling, Mix Design, Managerial skill to

handle the situations in Pre Construction, During

Construction and Post Construction stages. Effective and

desired results with optimum use of departmental manpower

engaged in Supervision of Construction activities is always a

major concern of NPCIL vision and policy.

Based on daily observation & experience that have been

gathered during handling of various site execution activities,

a need was felt to have a document containing brief

description of the work and effort required for various stages

of construction for improvement of effective supervision of

construction.

Page 4: Civil Engineers Hand Book for Construction Supervision

This document has been prepared as handy tool for ready

reference of Site Civil Engineers and Supervisors. It contains

information basically for site related activities/ checklist

being used on day-to-day basis.

Special emphasis have been given on the skill requires for

supervision of the Civil Construction activities for Site

Engineers/ Site Supervisor to handle the situation w.r.t. Pre-

Construction, During Construction & Post Construction

responsibilities.

Following are the areas enlisted in this document: -

How to organize the job for effective and desired out put

at site.

Importance of Survey in Civil Construction.

Excavation and blasting techniques.

Requirement for formwork placement.

Re steel fabrication and placement.

Importance of Concrete cover.

Pour planning.

Pour checks.

Brief description regarding concrete and mix design

development.

Requirement for concrete production transportation and

placement.

Post-concrete inspection.

Various types of finishes in concrete.

Defects in concrete and its repair.

Various types of joints.

Page 5: Civil Engineers Hand Book for Construction Supervision

Assessment of safe working conditions while executing the

job.

Importance of Job hazard analysis.

Awareness of QA requirements.

I am thankful to all my colleagues and senior Civil Engineers,

who have shared their valuable experience which had paved

the way for making this possible.

I would like to extend sincere thanks to Sh. J.K.Jain,

Sh. S.K.Shrivastava, Sh. H.P.Choudhary & Sh. V.K.Trivedi for

their personal support. The inspiring support and

encouragement provided by Sh. N.K.Jain, ACE (E&I) and

Sh. Sanjiv Sharma, PE (C) is also thankfully acknowledged.

The development of this document as reference to the

requirements of Site Supervisors and Site Engineers, who are

directly connected with work was the vision of Sh. D.K.Jain,

Chief Engineer (Civil). This could be made possible due to his

able leadership, and effective guidance, continuous

motivation and appreciation at every stage for development

of this document in presentable form. I am also grateful to

Sh. C.P.Jhamb, Project Director, RAPP-5&6 for giving

Enthusiastic and inspiring support for development of this

document.

S.K. GUMASTA RAPP-5&6

Page 6: Civil Engineers Hand Book for Construction Supervision

INDEX

SR.

NO. DESCRIPTION

1 How to organize the job for effective and desired out put at site. 2 Importance and requirement of survey.

3 Excavation and blasting techniques.

4 Requirement for formwork placement.

5 Re steel fabrication and placement.

6 Importance of Concrete cover.

7 Pour Planning.

8 Pour Checking.

9 Brief descriptions regarding concrete and mix design development.

10 Requirement for concrete production transportation and placement.

11 Post-concrete inspection.

12 Various types of finishes in concrete.

13 Defects in concrete and its repair.

14 Various types of joints.

15 Assessment of safe working conditions while executing the job.

16 Importance of Job hazard analysis.

17 Awareness of QA requirements.

Page 7: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 1

HOW TO ORGANIZE THE JOB FOR EFFECTIVE AND DESIRED

OUT PUT AT SITE

Page 8: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 1 How to organize the job for

effective and desired out put at site

Learning is a continuous process for individual improvement & is important and essential for completion of jobs with required quality standard and maintaining the time schedule for achieving the targets. Optimum use of availability of skilled manpower is always a matter of concern to all of us in a present competitive world. Further it is needless to say that “ABILITY IS USELESS UNLESS IT IS USED” Hence it is a big challenge for us that “How to organize the job for effective and desired out put at site”.

Following are the few points, which shall be helpful to achieve the above

objectives: -

1) Develop confidence within our self and our team for having

capability to deliver the task.

2) Understand the work in totality before actually proceeding it.

3) Identify the requirement of material, equipments, availability of

drawings / specification, qualified manpower and their availability.

4) Identify the possible hindrances, constraints well in advance and

proactive approach to arrange the solution.

5) Prior requirement i.e. proper pour planning and checking before

execution.

6) Identification of Pre construction / During construction /Post

construction requirement of various sub activities.

Page 9: Civil Engineers Hand Book for Construction Supervision

7) Proper access to site, good illumination, logical and proactive

approach and quality consciousness.

8) Understanding of job and analysis of job hazards prior to start of

the work.

9) Always believe “Ability Has Nothing To Do With Opportunity”

hence deliver the results rather than discussing the excuses.

10) Communication to immediate superior for appraisal of work done.

Such appraisal is appreciated, if it is done before it is asked for.

Remembers - One should not require any reminder for complying

the instruction of superiors.

11) Practice to be a good leader and not the boss for effective team

sprit and desired output.

12) Motivate the team and set an inspiring example for others.

13) Always believe that ”Sincerity has no substitute”.

Page 10: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 2

IMPORTANCE AND REQUIREMENT OF SURVEY

Page 11: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 2

IMPORTANCE AND REQUIREMENT OF SURVEY

Survey plays an important role in Construction activities. It is basic requirement

to ensure the correct location and alignment including required elevation slop etc

for structure or total layout of a plant. Survey is done for the maintaining above

requirement. Brief of survey terms used is indicated below: -

SURVEYING: - Surveying is the art of making such measurements as will

determine the relative positions of points on the surface of

the earth or on structure in order that the shape and extent

of any portions of the earth/structure may be ascertained

and shown on the map or plan.

LEVELING: - Leveling is the art of determining and representing the

relative heights or elevations of different points on the

surface of the earth/structure.

1 SEQUENCE TO BE FOLLOWED FOR SURVEY W.R.T. START OF THE

WORK: -

Following are the salient points/ sequence of survey to be followed for

start of the project activates/ pour: -

WORK IS DIVIDED IN TWO PARTS.

A. To start a new project: - Establishing of Main grid lines and Benchmark

with reference to known datum / reference to start in new work.

B. For a pour in existing structure: - Use of existing reference/bench mark

in existing structure to define the location, alignment and elevation of a

pour.

Page 12: Civil Engineers Hand Book for Construction Supervision

2 USE OF SURVEY IN VARIOUS DAY-TO-DAY ACTIVITIES OF

CONSTRUCTION.

Before we deal with uses of survey for various activities, following steps

are necessary to carryout.

A. Transfer of reference line at each Building/floor to carryout checking of

various activities.

B. Transferring of Bench Mark at each Building/floor.

C. Above two activities should be performed with great care and without

any error, as the effectiveness of total checking depends on theses

reference points.

D. Establishing layout of the building.

E. Establishing bench mark to check elevations of different floor etc.

F. Use for checking of form works: -

i) Alignment checking

ii) Checking of verticality.

G. Tolerance for formwork

i) Section dimension - ± 5 mm

ii) Plumb/ verticality - 5mm in 5 mtr. But should not cumulative.

H. Use in checking of critical EPs.

Checking of location

Checking of elevation

Tolerance –

Before concreting ± 2 mm.

After concreting ± 6mm.

Tolerance on angle± 0.500.

Survey is very important at pre-construction, during

construction and post construction stages. Site Engineers must

be aware regarding requirement and importance of survey at

pre-construction, during construction and post construction

stages. Few of the requirements are summarized below: -

Page 13: Civil Engineers Hand Book for Construction Supervision

3 Pre construction survey is required for the following: -

i. Defining the plant area in 20m X 20m plant grid pattern with

existing permanent reference.

ii. Location of various plant structures within defined grid established

as above.

iii. Making specific benchmark to take up the work within building /

structure.

iv. Marking and identification of a part of the structure in various

pours at various elevation w.r.t defined Benchmark / reference.

v. These marking are possible by: -

Theodolite.

Measuring tapes.

Dumpy level.

Total station.

vi. At the start of construction- usually reference point is marked on

reference pillars 2-3 meters away from the edge of structure.

vii. After construction, it is transferred to permanent structure and

subsequently all reference to be taken from common reference to

avoid any cumulative error.

4 During construction is required for the following: -

i. During construction survey is very important. Following are the

areas where survey during construction requires by supervisor /

site engineers.

ii. Maintaining alignment of wall and position of embedded part, pipe

support/ piping sleeves etc.

iii. Maintaining the location of EP’s / specifically critical EP’s.

iv. Maintaining the concrete top elevation of plate EP’s / Critical EP’s.

v. Maintaining the concrete top elevation during finishing of green

cutting.

vi. Maintaining the slopes of floors.

vii. Maintaining the levels of sumps.

Page 14: Civil Engineers Hand Book for Construction Supervision

viii. During concreting survey is made to ensure the location of PVC

water stop.

5 Post concrete survey: -

i. Post concrete survey is done for all critical pours to ensure the final

position of EP’s / Levels of concrete.

ii. It is required to done to assess the tolerance in alignment / level

/pockets / bolts etc. in concrete structure.

iii. Post concrete survey is done to examine the spot of honey combed

portion / visual observation of bulging and type of surface finish in

concrete.

Page 15: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 3

EXCAVATION AND BLASTING TECHNIQUES

Page 16: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 3 EXCAVATION AND BLASTING

TECHNIQUES

At NPCIL, Rajasthan Site, we face the greatest challenge of getting the

excavation done at hard rock available here.

Excavation at this site is a critical activity since blasting is the only

economic solution available for excavation in hard rock here.

Following is the salient point generally we refer before proceed for the

work.

1. PLANNING OF WORK. – In order to asses the requirement of

various machineries / explosives required to complete the blasting work

with in schedule time considering hindrances / constraints etc., planning

of the work including resource planning is very important for site

engineers before starting the job. A brief for activities required for

planning of the work is summarized below.

Sr.

no. Description Desired output

i. Total quantity of excavation to be done In Cu.m.

ii. Total time available. No. of Days.

iii. Target excavation to be done per day. Total Qty/No. of days.

iv. Increase target excavation by 15% to

20% due to uncontrolled conditions like

break down of machineries/non

availability of explosive materials /

restriction in blasting due to nearness of

on going works / critical structure.

(Assuming blasting is permitted once in a

day)

Row no. iii X 1.5 cu.m /

per day.

Page 17: Civil Engineers Hand Book for Construction Supervision

2 RESOURCE PLANNING

i. Considering capacity of a poclain to handle

excavated muck/day and using target

excavation/day, we can calculate - No. of

required poclain.

No. of required

poclain can be

calculated based on

this data.

ii. Considering the capacity of dumpers to

handle the excavated muck to disposal

yard / day and using the target excavation

rate per day, we can calculate - No. of

required dumpers.

No. of required

dumpers per day can

be calculate based on

this data.

iii. Based on the experience at this site

approx. depth of borehole in RM required

to achieve one Cu.m. of excavation and

the total excavation is to be done, we can

calculate total RM of drilling required.

(Approximate assumption as 0.8 to 1.0 RM

drilling as an average to achieve one Cum

excavation at this site may be assumed

for planning purpose. This data may

vary for various types of work and their

location.)

This will help to

calculate total Drilling

required in RM.

iv. Considering the capacity of borehole drill

machine to drill-RM/day and using the

target excavation rate per day, we can

calculate total no. of borehole drilling

machine requirement. (Approx. 70 to 80

RM drilling is done per day by a borehole

drill machine can be safely assumed for

planning purpose)

No. of borehole

drilling machine

required can be

calculate with this

data.

v. Considering the capacity of jackhammer

capability to drill RM/day and using the

target excavation rate per day, we can

No. of jack hammer

required can be

calculated with this

Page 18: Civil Engineers Hand Book for Construction Supervision

calculate total no. of jackhammers

requirement. (Approx. 50 to 80 RM

drilling per shift can be safely assumed for

planning purpose)

data.

vi. Based on the experience at this site

amount of explosive required in Kg to

achieve one Cu.m. of excavation and the

total excavation is to be done, we can

calculate total explosive requirement.

(Approx. 0.5 to 0.7 Kg explosive

requirement can be assumed to achieve

one Cum excavation at this site for

planning purpose.)

This will help up to

calculate total

quantity of explosive

required in kgs. This

will help us to assess

the requirement of

storage of explosive /

magazine.

3 BLASTING & BLASTING TECHNIQUES: - A. BLASTING:- The fragmentation of rock by means of explosives is

called ‘blasting’. There are two type of explosion: -

I. Deflagration: - Explosion by rapid burning

II. Detonation: - Explosion by instantaneous decomposition

B. MUFFLED

BLASTING

Muffled blasting refers – blasting with control of fly

rock. It is defined as preventive action for flying stones

by covering blasting area by steel plates / sand bags

etc.

Control of fly rock: - Blast hole shall be covered with 6

mm thick (min) MS plate 0.6 to 1.0 sq.m – scrap steel

plates/ sand full of gunny bags are used during muffled

blasting for covering the area.

C. CONTROL

BLASTING

In control blasting muffling is not only the requirement

but also controlling the generation of peak particle

velocity due to vibration in nearby Civil structure/

critical and sensitive installation without affecting their

Page 19: Civil Engineers Hand Book for Construction Supervision

performance of structures is main concern for control

blasting.

Control of vibrations- Short delay blasting with light

charges: - Rapid sequence of shot firing with delay of

25 -100-mili seconds.

D. LIMITED

BLASTING: -

To safeguard existing structures and nearby operating

station, permissible PPV is defined as below: -

1. Peak particle velocity 10 mm/sec for near by civil

structures.

2. Peak particle velocity 3 mm/sec. –Safe vibration

level for buildings.

??With electric & electronic equipment installed at

basements.

??Safe charges per delay have also been

specified by CWPRS for various distances and

age of the concrete.

E. LINE DRILLING: - ??By drilling a series of hole at closely spaced

intervals around the perimeter of the excavation

the blast may be trimmed to the finished

dimensions with a minimum over break.

F. PRE-SHEARING: - ??Is a development of line drilling method by

instantaneously firing a closely spaced series of

holes, lightly charged around the desired

perimeter before the nearby main rounds are

blasted.

??Firing of light charges produces tension cracks.

??These cracks de-couple the main blast from the

perimeter rock walls, which are thereby left

intact and unbroken.

??Dia of holes –110 mm Ø

Page 20: Civil Engineers Hand Book for Construction Supervision

??Spacing –800 to 1000 mm c/c

??Charged –300 to 400 gm /m

G. EXPLOSIVES: - Explosives are chemical compounds. They decompose

quickly and violently and change into gases. Such

gases have larger volume. The heat generated serves

to expand gases greatly.

EXPLOSIVES

LOW EXPLOSIVES HIGH EXPLOSIVES

(Deflagrates) (Detonates)

H. LOW EXPOLOSIVES:

-

‘Gunpowder’ is the example of ‘low explosives”

Features of ‘Gun Powder’

i. Gun powder 75% Potassium Nitrate - oxygen supplier

ii.Composition: - 15% charcoal powder - inflammable

10% sulphar.

iii.

Rate of burning; - The speed of burning of gunpowder is of all order of

450 m/sec. The volume of gases produced is as large

as 2000 times the volume of gunpowder used.

iv.

Other properties:- ??Made to explode by ‘Safety fuse’

??Because of its low strength, it is not used in large

scale blasting.

??Can easily absorb moisture.

??Its transport is risky – being inflammable.

??While Stemming –explosion may take place needs

proper care during handling.

Page 21: Civil Engineers Hand Book for Construction Supervision

I. HIGH

EXPOLOSIVES: -

Open cast gelignite, special gelatin, blasting gelatin

super dyne is examples of ‘high explosives’.

i. Main constituents: -

1) TNT (Tri-Nitro –Toluene)

2) Nitro-glycerin

3) Ammonium Nitrate

4) Collodion cotton

ii. Features: -

??Should not be exploded by ignition

??Detonators create ‘shock waves’ of velocity

ranges from 2000 m/sec to 7000-m/ sec.

depending upon quality, nature and strength of

explosive used.

??The mechanical energy of the shock waves does

the work of fragmentation of work.

J. Safety Fuse: - 1. Safety fuse consists of core of fine gunpowder

wrapped with layers of tape, jute and is given

a coat of ‘water proofing’.

2. It will burn without the help of oxygen, inside

water and inside the blast hole.

3. Rate of burning = 2 feet /minutes.

4. Some brand names “Bull brand” “Blue sump”

and “Colite fuse”.

5. High explosives can be detonated with the

help of safety fuse, provided it is capped with

an ordinary detonator.

How to determine

length of a fuse: -

??The blaster should take into consideration the time he

will need to light the fuses and to reach the shelter

safely shall determine the length of a safety fuse.

??Suppose time for lighting 10 fuses requires = 2 min.

??Time to reach the shelter = 5 min. ------- Total time = 07 min So he will need to have 14 feet fuse since the rate of

burning of fuse is 2 ft/min.

Page 22: Civil Engineers Hand Book for Construction Supervision

K DELAY Delays are used to have small time gap between

successive blasting to avoid strong vibration generation

at a time.

At our site as specified in tender document delay per Kg

of blast to be used w.r.t. distance of sensitive or

permanent installation while blasting

L STEMMING: - Too little stemming results - Allow explosion gases to

vent out and fly rock problem.

Too much stemming results - Poor fragmentation.

M ORDINARY ELECTRIC

AND DELAY

DETONATORS

??These are initiated by pressing an electric current

with an apparatus called “EXPLODER”.

??When electric current of about 0.5 amp is passed

the fused head get heated ignite primary charge

which in turn will initiate IInd charge and the

detonation takes place.

The difference between ordinary electric

detonator and delay detonator is due to of

insertion of a “delay element, which has property

of burning at specific rates.

The heart of a detonator is “fuse head “.

Any mal-functioning of this will lead to misfire.

N INITIATION

SEQUENCE OF

DETONATION OF

EXPLOSIVES

To be strictly followed for effective results.

O USING DELAYS: - When the explosive charges in two or more rows of

holes parallel to a face are fired at the same time it is

desirable to fire the charges in the holes nearest the nd

Page 23: Civil Engineers Hand Book for Construction Supervision

face a short time ahead of those in IInd row. This will

reduce the burden on the holes in IInd row and thereby

permit the explosive in IInd row to break the row more

effectively.

The use of delays in the blast is one of the most

powerful weapons in the fight against excessive blast

damage and larger peak particle velocity and in-turn

instability of surrounding area.

MISFIRES: - While shooting explosives charges by blasting, it may be

possible that one or more charges will fail to explode.

This is referred to a misfire. It is necessary to dispose of

this explosive before excavating loosened rock.

P

HOW TO HANDLE

MISFIRES: -

??The most satisfactory method is to shoot it, if

possible.

??If electrical detonator is used, leg wires are available

and circuit is satisfactory, try again to set of charge.

??Stemming should be removed with a wooden tool

instead of metal.

??Water and compressed air should be used to remove

stemming.

??A new charge on top of missed one may also be

blasted to fire the charge.

4. ECONOMICS OF BLASTING

i. To achieve

optimum results:

Following parameters are required to be taken into

consideration –

1) Type of explosive, weight of explosive and

distribution of explosive in holes.

2) Blast hole diameter – If large – flying of rock in air

will be less but secondary blasting may be required to

Page 24: Civil Engineers Hand Book for Construction Supervision

will be less but secondary blasting may be required to

handle large boulders generated.

3) Effective burden: - The distance between the row of

holes under consideration and the nearest free face is

know as effective burden.

If burden is small - Generation of fly rock in -air and

lesser efficiency of blasting will be resulted.

If burden is too large - Check the blast due to -Poor

fragmentation.

ii. Effective spacing: - For good results – effective spacing of holes = 1.25 x

effective burden.

iii. Sub drill depth: - To avoid excessive shovel operation at floor level depth

of hole is kept little less than required.

5 MONITORING OF ACTUAL PROGRESS AGAINST PLANNED PROGRESS

OF BLASTING: -

1) Compare for no. of holes blasted against no. of holes planned to blast

per week.

2) Target excavation rate against achieved excavation rate per week / per

month.

3) Reorganize the deployed resources in case large variations are noticed.

6 REQUIREMENT OF THE PRE BLASTING ACTIVITY: - i. Proper resource planning w.r.t requirement of machineries / availability of

explosives / requirement of storage of explosives/ availability of qualified and

licensed blaster to be ensured.

ii. Blasting notice to all concern and near by all agencies working in the area

/CISF/safety group and to nearby working stations must be circulated. Blasting

notice must indicate blasting timings for specific duration for which it is issued.

Page 25: Civil Engineers Hand Book for Construction Supervision

iii. Daily blasting permits indicating no. of holes/app. Blast charge requires /

departmental representative to attend / witness the blasting to be taken

iv. This daily permit needs clearance from department safety head and the CISF

authorities well in advance preferable one day in advance

v. Drilling of required no. of holes of desired dia and inclination to be ensured in

one day advance

vi. Availability of muffling plates / sand bags to be ensured at site in one day in

advance

vii. Availability of PPV meter at site for monitoring the vibration to be ensured at

site.

7 REQUIREMENT OF DURING BLASTINGS ACTIVITY: -

i. Loading of required explosive in blast holes to be ensured by licensed blaster

only.

ii. Connecting the blast charge with desired delays in specific circuits to be

ensured by licensed blaster only.

iii. Ensuring the cordon-off the area for entry of vehicle / explosive / Labour.

Using whistle / red flag / siren.

iv. Blasting to be done and measurement of PPV should be recorded.

8 REQUIREMENT OF AFTER BLASTING ACTIVITY: -

i. Blaster must checks for misfire if any and accordingly arrange for reblast if

necessary as per procedure.

ii. Give clearance if no misfire noticed for entry of vehicles / movement of

workers etc..

iii. Check for any damage occurred in near by area. It is requires to be reported

in the blasting report, if any.

iv. Generation of blasting reports including statement of reconciliation for the

explosive materials brought to site, consumed at site and balance taken away

from the premises of the project in presence of CISF.

v. Compare the PPV observed against permissible Peak Particle Velocity for the

area.

Page 26: Civil Engineers Hand Book for Construction Supervision

9 Following details also must be known for effective monitoring of

blasting operation.

BLASTING AREAS: -

Blasting areas where concreting is being done i.e. w.r.t. green age of the

concrete. This data is obtained from the conclusion drawn by CWPRS at site in

their survey.

In nutshell it refer that blasting in the nearby area where green age of the

concrete is 0-4 hrs. is not harmful. But for the concrete having age between 4-

12 hrs. - No Blasting to be permitted in near by area.

Page 27: Civil Engineers Hand Book for Construction Supervision

CHAPTER – 4

FORM WORK PLACEMENT

Page 28: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 4 FORM WORK PLACEMENT

1. Formwork is defined as total system of support of fresh

concrete to be placed it includes: -

??Total frame / mould of various shape in which concrete remain

in contact.

??Total system of supporting arrangement i.e. by frame, pipes,

acro-span, trusses etc.

??Nuts, bolts tie rods, bracing including other supporting system

for satisfactory sustaining the load of concrete + live loads

until the concrete attain the strength to with stand the same.

2. Various type of formwork are used in construction: -

a) CONVENTIONAL FORMWORK: - Includes – formwork i.e.

shuttering made up by steel plates and industrial plywood includes

pipe support’s / wooden ball support.

b) DOCA FORM WORK: - Specially designed form work with simple

methods for fixing in position and removing from the position. This

tread name of formwork had proved confidence in various

complicated structure for their satisfactory completion. This can be

used for large slabs, big columns, deep beams, large size retaining

walls, and hyperbolic cooling towers etc.

c) SLIP FORM WORK: - In structure where shapes are regular of

having a uniform variation like shaft of water tank, chimney,

towers etc. and not having penetrations. This type of form work

can effectively used for rapid construction in this case form work is

design in such a way that it moves continuously ahead to receive

the fresh concrete in such a way that when it leaves the concrete

already placed should attain the sufficient strength to withstand

the load of concrete + live load, while concreting is done. In this

case concreting is done continuously till the work is over for the

shape

Page 29: Civil Engineers Hand Book for Construction Supervision

Example: - Shaft of water tank for 15-20 Mtr. can be completed in

4 to 5 days.

d) JUMP FORM; - Where Shape / Geometry of the structure is not

uniform and height of the structure is more. Jump formwork can

be used. For example about 100 to 110 m high and 90m to 55 m

dia of cooling tower shell varying hyperbolically being constructed

with the jump form at RAPP-5&6 site.

3. Site Engineer / Supervisor must give attention to following

areas while checking the formwork / scaffolding.

PRE CONSTRUCTION REQUIREMENT: -

Alignment level position of formwork w.r.t permanent

reinforcement.

??Type of finish requirement decides the type of formwork.

??Spacing of the support system Tightening of bolt, tie rods

etc.

??Accuracy of dimensions.

??Gap in the successive shutters to avoid the slurry leakage.

??Where penetration / EP’s are to be made, the supports are

to be re-ensured to maintain dimension, alignment and

level of the same.

??Bracing and adequate support for projections/ cantilever

must be checked.

??Wherever construction joints are to be left, the position of

shear keys, and support arrangement to be ensured.

??Safety aspects to be taken care while checking the

formwork the proper access to reach other portion of form

work to be ensure, an case needs attention during the

concreting.

??Form fixing to be checked w.r.t removal of form work point

of view. It should be easily removable without damaging the

final concrete.

Page 30: Civil Engineers Hand Book for Construction Supervision

REQUIREMENT DURING CONSTRUCTION

??A set of skilled carpenter to be ensured to attend the area

immediately in case, support’s / forms gets displaced while

concreting / vibration of concrete.

??Proper illumination in internal and external location of pours

to be ensured.

??Application of surface retarder immediately before the

concreting where green cutting is required.

POST CONSTRUCTION REQUIREMENT: - In general the codal

practice for removing the formwork to be strictly followed for

removal of form.

??For special structures like dome of reactor and shell of

Cooling Towers: -Specified procedure to be followed for

removal of form.

??Specific care to be observed for safety during disturbing.

??Specific care to be observed while removing formwork at

high structure should not damage the structure at floor.

Removal of the formwork at various constructions needs

attention as summarized below

Forms should not be removed until the concrete has achieved strength

that is at least twice the stress to which the concrete may be subjected

at the time of removal of formwork. However, under normal

circumstances, where no significant variation temperature is seen the

following striking period should be followed: -

Removal of forms and supports (As per IS456-2000)

Sr. no.

Position of formwork Min. period before striking formwork.

1. Vertical formwork to columns, walls, beams.

16-24 hours.

2. Soffit formwork to slabs (props left under after removal of formwork)

3 days.

3. Soffit formwork of beams (props left under after removal of formwork)

7 days.

Page 31: Civil Engineers Hand Book for Construction Supervision

4. Props of slabs (spanning up to 4.5 m) 7 days. 5. Props to slabs (span over 4.5 m) 14 days. 6. Props to beams & arches (spanning up to

6) 14 days.

7. Props to beams & arches (spanning over 6m)

21 days. ??Striking should be done slowly to avoid damage to projections and

without shocks or vibration.

??When forms are stripped, there should be no excessive deflection

or distortion and no evidence of damage to the concrete due to

removal of support.

??When forms are removed before the specified curing is

completed, curing should be continued up to the specified time.

??The concrete supporting forms and shores not be removed from

beams, floors and walls until these structural units are strong

enough to carry their own weight or any approved superimposed

load. In no case should supporting forms and shores be removed

from horizontal members before concrete strength has achieved

this specific concrete strength.

??It is always recommended to remove forms for columns and piers

before forms for beams and slabs.

Page 32: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 5

RE-STEEL FABRICATION & PLACEMENT

Page 33: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 5

RE-STEEL FABRICATION & PLACEMENT

Steel reinforcement is a major and most important constituent of

concrete. The correct shape and its position and cutting length is the

main area required to be seen by Site Engineer. Silent feature for

Fabrication & Placement of concrete reinforcement is briefly described

below.

TYPE OF REINFORCEMENT: - 1) High strength deformed bars – (Conforming to IS: 1786)

(a) Cold worked deformed bars.

(b) TMT bars

2) Mild Steel Bars – (Conforming to IS: 432)

3) (A) MATERIAL PROPERTIES FOR HSDB i. CHEMICAL PROPERTIES

Constituents Fe415 Fe500 Fe550 Carbon 0.30 0.30 0.30 Sulphur 0.060 0.055 0.055 Phosphorus 0.060 0.055 0.050 Sulphur & Phosphorus 0.11 0.105 0.10 For weldebility % of C > 0.25

ii. PHYSICAL PROPERTIES Mechanical properties of high strength deformed bars:

S. No.

Property Fe415 Fe500 Fe550

0.2% proof stress

415

500

550

% Elongation on gauge with 5.65 A

14.5

12.0

8.0

Page 34: Civil Engineers Hand Book for Construction Supervision

Tensile Strength

10% more than actual 0.2% proof stress or not less than 485 N/mm2

8% more than actual 0.2% proof stress or not less than 554 N/mm2.

6% more than actual 0.2% proof stress or not less than 585 N/mm2.

3 (B) MATERIAL PROPERTIES FOR MILD STEEL: - i) CHEMICAL PROPERTIES Constituents Upto 20 mm Above 20 mm

Carbon 0.23 0.25 Sulphur 0.055 0.055

Phosphorus 0.055 0.055 ii) PHYSICAL PROPERTIES MECHANICAL PROPERTIES OF MS BARS: - S. No.

Property Grade-1 (less than 20 mm)

Grade-1 (Above 20 mm)

0.2% proof stress 250 240 % Elongation on gauge

with 5.65 A 23% 23%

Tensile Strength 410 mpa 410 mpa

Material Sampling and Acceptance to be ensured as per requirement.

(4) CUTTING & BENDING OF RE-STEEL BARS: -

Cutting & Bending shall be done in accordance of requirements laid

down in IS: 2502 as per the Bar Bending schedule. The

reinforcement bars shall be cold bended. Fabricated bars should be

tagged indicating the following information: -

(a) BBS (b) Structure (c) Bar mark (d) No. of Bars.

(5) PLACEMENT OF BARS: -

Placement of re-steel bars shall be done as per arrangement shown

in approved reinforcement drawings.

(6) Reinforcement work shall be checked for the following: -

FABRICATION: -

(i) Diameter of the bar

Page 35: Civil Engineers Hand Book for Construction Supervision

(ii) Shape of the bar

(iii) Finished length of the bar

(iv) Bending radius

(v) Visual inspection for crack during fabrication

LAYING

(i) Location

(ii) Alignment and array

(iii) Spacing / numbers

(iv) Binding / tying

(v) Cover

(vi) Staggering if any

(vii) Splicing – numbers and location

Inspection status shall be mentioned in the form of Pour Card.

(7) PLACING OF REINFORCEMENT

Rough handling, shock loading prior to embedment and the

dropping of reinforcement for a height should be avoided.

Reinforcement should be secured against displacement outside the

specified limits.

(8) TOLERANCES ON PLACING OF REINFORCEMENT

Unless otherwise specified by Engineer-In-Charge, the

reinforcement shall be placed within the following tolerances:

a) For effective depth 200 mm or less ± 10 mm

b) For effective depth more than 200 mm ± 15 mm

(9) TOLERANCE FOR COVER

Unless specified otherwise, actual concrete cover should not deviate

from the required nominal cover by 0, +10 mm.

Sl. No.

Diameter of Rod Weight in kg/RM

1 6mm 0.222 2 8mm 0.395 3 10mm 0.617 4 12mm 0.888

Page 36: Civil Engineers Hand Book for Construction Supervision

5 16mm 1.578 6 20mm 2.466 7 22mm 2.984 8 25mm 3.853 9 28mm 4.834 10 32mm 6.313 11 36mm 7.990 12 45mm 12.485

Page 37: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 6

IMPORTANCE OF CONCRETE COVER

Page 38: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 6 IMPORTANCE OF CONCRETE COVER

In addition to integrity, strength and other design requirement, durability

of structure during its design life is extremely important. No matter care

have been exercised while designing the concrete mix, formwork and

effective methods have been used for placing, consolidating and curing

of concrete. But if care towards required concrete cover is not made

than the efforts made towards all the above could loose their

significance, which result, pour durability of structure. The importance of

concrete cover is more significant in structures located in aggressive

environment. The cover also protects the reinforcement to get it exposed

in environment and prevent formation of oxygen concentration cell,

which is the major reason for starting the corrosion of reinforcement.

Site engineer must understand the importance of the concrete cover and

necessary care must be exercised to ensure it as per drawing

requirement.

Following care shall help in achieving the above objectives: -

1. Proper alignment of formwork and re steel at location, to be

ensured.

2. Concrete cover block should be of similar mix design.

3. Proper cover blocks in columns, beam bottom, beam side and slab

as per drawing requirement.

4. Additional cover requirement for the structure where it is exposed

to sea, aggressive environment or alternate drying and wetting,

should be given due care as per drawings requirement.

5. Specific care to be ensure during vibration of concrete, so that

concrete cover block remains intact as placed.

6. Cover blocks must be properly tied to the reinforcement.

7. Properly cured cover blocks only to be used at site. There fore, as

per requirement of cover block site engineer must ensured that

they have to be casted well in advance.

Page 39: Civil Engineers Hand Book for Construction Supervision

CHAPTER – 7

POUR PLANNING

Page 40: Civil Engineers Hand Book for Construction Supervision

CHAPTER – 7 POUR PLANNING

It is needless to say that any work whether construction activities or our

day-to-day activities, requires specific plans for completion of the same

successfully.

This facilitates: -

??Total under standing of the work.

??Various requirements at different stages of execution of the work.

??Sequence of the work to be followed.

??Proactive approach of attending possible hindrances if any.

??Developing an over all aptitude for systematic approach for

completion any work.

The brief description regarding pre requisite for pour planning and w.r.t

supervision of Civil Engineering Construction is summarized below: -

POUR PLANNING: -

Pour planning refers to ensure systematic arrangement of all

requisite to take up a defined work within schedule time and

preferably ahead of schedule plan.

FOLLOWING ARE REQUISITE FOR PLANNING OF A

POUR.

A. IDENTIFICATION OF POUR. These include identification of: -

i. Location of a pour in a building and reference grids.

ii. Elevation.

B. AVAILABILITY OF LATEST DRAWINGS: -

It is required to check the latest revision of referred drawings and

also following details: -

i. To check for DCN if any.

ii. To check for FCN if any.

iii. To check for ECN if any.

iv. To check the hold in the drawing if any.

v. To check the reference drawings listed in the drawings.

Page 41: Civil Engineers Hand Book for Construction Supervision

C. Quantum of the work: –

Depending upon the size and importance of the pour, following

information helps for effective pour planning: -

1) Quantity of concrete to be done in single stretch.

2) It is preferable to have plan for the daily activities to be completed

w.r.t. the schedule date of pouring.

D. DAILY ACTIVITIES HELPS US TO KNOW ABOUT THE

FOLLOWING: -

??Total no of sub activities required to be done within schedule

time.

??Total quantity of material required being handle.

??Sequencing of activities can be planned effectively.

??Requirement of equipments / machinery can be plan.

??Requirement of construction material and their availability

schedule.

??It also ensure NPCIL acceptance of Material before actual use at

site.

??Availability of qualified manpower for various construction

activities. Work procedure duly approved.

??Various requirement for sub activities to be identified for: -

?? Pre construction

?? During construction

?? Post construction.

E. DEPLOYMENT OF MACHINERIES: -

Since requirements and pour size has been frozen, pre planning of

deployment of machineries is to be ensured with following details: -

??Availability of machineries on the day of concreting.

??The conditions of equipment - Whether break down or working.

??Availability of qualified crew to handle the machineries during

construction

??Availability of manpower for maintenance, if there is breakdown

during execution of work.

Page 42: Civil Engineers Hand Book for Construction Supervision

??To ensure the safe access for deployment of machines at site

including: -

F. AVAILABILITY OF AREA LIGHTING AND PROPER

ILLUMINATION AT WORK SITE.

G. ENSURING SAFE ACCESS.: -

Inspection of access for ramps, any intervening obstacles from batching

plant to site and at site up to pouring point.

H. Stand by arrangement in case failure of

equipment/Mechinary / Lighting arrangement.

I. Arrangement of Sun / Rain protection.

J. Arrangement for green cutting requirement and avalibility of

approved material for green cutting.

K. Availability of required number of mould for concrete cubes /

Cylinder as per requirement.

L. Review of improvement of pour plans done for earlier pours

w.r.t effective out put obtained v/s planned.

M. Necessary alteration or addition in requirements based on

the review as per Para – L above

Page 43: Civil Engineers Hand Book for Construction Supervision

CHAPTER – 8

POUR CHECKING

Page 44: Civil Engineers Hand Book for Construction Supervision

CHAPTER –8 POUR CHECKING

The pre construction stage can be broadly classified as Pour Planning

stage and Pour Checks stage.

??Once pour is planned, it is required to check the various sub

activities listed earlier in chapter – 4 in parallel for speedy

clearance of the pour.

??This is ensured to avoid any delay required for rectification if any

after pour is ready.

Following procedures is to be followed during pour

checking: -

A. SITE REGISTER: - During parallel checking record of sub activities

are to be cleared or observation to be recorded requiring rectification.

This should be maintained at site regularly.

B. Pour Card: - This gives pour inspection information. This enables to

know about all concerned officials have extended their clearance for

the specific pour.

A Checklist can be prepared for specific activities, which shall help for

clearing the pour card.

C. Drawing control record: - Reference drawing must be checked

with updated drawing control record. Further ECN, DCN, FCN, or hold

if any between various grids and elevation also needs to be checked.

Details of pour plan and sequence of concreting to be done at site

and must be properly defined before start of the work.

D. Other requirements: - Following information is also to be identified

before start of the work.

??Type of finish required.

??Slope and its extent on the surface of concrete.

??Location of sump in a pour if any.

??Location of green cutting requirement in a pour.

Page 45: Civil Engineers Hand Book for Construction Supervision

??Level of bulb of PVC water stops, its location and alignment.

??Location and alignment of EP’s.

??Planned schedule for availability of workers during and

immediately after the concreting. If required the shift

arrangement must be ensured.

??In addition to above following details are also important for Site

Supervisor / Site Engineer

??Concrete requisition slip shall be given at least 24 hrs. in advance

for all major pours to ensure availability of approved construction

material.

??Pour card clearance should be ensure before start of the work.

??Assessment of job hazard and preventive measures to be ensured

by Site Engineer.

??Aptitude for safety and house keeping helps for faster and safer

completion.

??Post-concrete inspection report to be prepared for all major pours.

E. Following are also required before start of concrete: -

??To ensure availability and functioning of vibrators.

??Proper walkways.

??Adequate Lighting arrangement.

??Availability of walky talkies / Phones.

??Covering material, for sun / rain protection.

??Dewatering arrangement: - If work is being done during the

monsoon and at lower elevation.

??Stand - by arrangement of machineries to be ensured before start

of the work.

??Stand - by arrangement of power supply to be ensured before

start of the work.

??Ensure the availability of supervision staff for next few hours after

last concrete is placed at site to maintain proper finishing, slope,

etc as per requirement.

Page 46: Civil Engineers Hand Book for Construction Supervision

??Awareness of reporting system to whom matter to be informed, in

case of emergencies. (Knowledge of telephone nos. of immediate

superior official is essential.)

??During pour checking apart from the above requirement should

important for a site supervisor / site engineer.

??Pour card i.e pour inspection clearance.

??Assessment of job hazard and preventive measures.

??Aptitude for safety and house keeping.

??Post-concrete inspection report

??Concrete requisition slips at least 24 hrs in advance to be given to

ensure, availability of approved material for the work.

??Post-concrete inspection report

??Rectification, if found any non-conformance during Post concrete

inspection.

RESPONSIBILITIES OF SUPERVISOR / SITE ENGINEERS: - CHECKING REQUIREMENT PRE CONCRETING: -

i. Site engineer has to ensure that necessary checking at the pour

wise reference to various agencies have been checked and

cleared.

ii. Assessment of safe access, approach for machineries, workers

etc is available.

iii. Requirement w.r.t ramp, slope of access & approach and skilled

manpower to handle the machineries like placer boom, concrete

pumps, vibrators, concrete pipes, and necessary stand by spare

parts is available.

iv. Proper communication system from the batching plant to the

place of pouring the concrete is available.

v. Details regarding location from grid to grid - indicating final level

/ slope or finish to be maintained is identified.

vi. Arrangement for green cutting and stand by arrangement for

concreting is ensured.

Page 47: Civil Engineers Hand Book for Construction Supervision

CHECKING REQUIREMENT DURING CONCRETING

i. Skilled manpower like carpenter is available to review the

position of formwork during concreting.

ii. Proper slope /levels/finishing/green cutting to be made on the

finish concrete surface.

iii. Alignment of support system of formwork needs continuous

attention during concreting.

CHECKING REQUIREMENT POST CONCRETING

Once last batch of concrete is received and placed at site, site

supervisor/ Engineer responsibility dose not ends with placement of

the final load of concrete. Before he leaves the site he must ensure

the arrangement required as per planning of the pour is available.

Further the requirement of maintain green cutting / protection of

the concrete surface from sun / rain and curing arrangement for

the area to be ensured effectively.

Post concrete inspection to done as per requirement w.r.t.

1) Alignment.

2) Dimension.

3) Levels.

4) Slopes.

5) Type of Finish.

6) Location & Levels of embedded parts.

Page 48: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 9 BRIEF DESCRIPTION REGARDING

CONCRETE AND MIX DESIGN DEVELOPMENT

Page 49: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 9 BRIEF DESCRIPTION REGARDING CONCRETE

AND MIX DESIGN DEVELOPMENT

WHAT IS CONCRETE: -

??Concrete is a basically heterogeneous mixture of cement,

aggregates & water along with or without admixture.

??Cement- we are using 43 –Grade ordinary port land cement.

??Aggregates –Coarse aggregates produced from main plant

excavated rock.

??Fine aggregates – Natural sand from Jhalawar river

- Manufactured sand produced at site.

??Water –

??Admixtures - Chemical admixture

- Mineral admixture

NORMAL CLASSIFICATION OF CONCRETES: -

(A) Based on density.

??Lightweight concrete (Density varies from 300 Kg/cu.m to 1850

Kg/cu.m).

??Normal weight concrete -(Density varies from 2200 to 2600

Kg/cu.m)(As per sepc. reqt. - Density = 2360 Kg/cu.m)

??Heavy concrete – (Density = 3300 Kg/cu.m) (As per our reqts.

Density = 3630 Kg/cu.m).

(B) Based on control

?? Nominal mix

?? Controlled mix

(C) Based on strength

?? Lean concrete

?? Normal strength concrete

?? High strength concrete

Page 50: Civil Engineers Hand Book for Construction Supervision

(D) Based on performance

?? Normal concrete

?? High performance concrete

(E) Special concretes

?? Fiber reinforced concretes

?? Polymer concretes

?? Ferro cement etc.

HIGH PERFORMANCE CONCRETE:

High performance concrete is the one, which is specially designed

to perform the intended use as per specified requirements in both its

fresh and hardened state.

??Constructability in fresh state.

??High strength.

??Impermeability in its hardened state.

According to Neville: -

“High performance concrete is concrete selected so as to be fit for

the purpose for which it is required.”

There is no mystery about it, no unusual ingredients are needed

and no special equipment has to be used. “All we use is an

understanding of the behavior of the concrete and will to produce a

concrete mix within closely controlled tolerances”.

INTENDED USE OF CONCRETE IN NUCLEAR STRUCTURES:-

??Radiological protection provided by structures: Uniform shielding

& no through cracks.

??Serviceability: By limiting deformation and leak tightness

??Strength

Page 51: Civil Engineers Hand Book for Construction Supervision

PERFORMANCE REQUIREMENTS OF CONCRETE FOR

NUCLEAR STRUCTUES:

MAIN PARAMETERS

??Compressive strength

??High tensile strength

??High crack resistance

??Good impact resistance

??Low permeability

??Low shrinkage

??Low heat of Hydration

??Low Creep

??Good workability

??Uniform density

??Durability.

CHARATERISTICS OF M-45 GRADE CONCRETE ??Grade of concrete – M-45

??Characteristic compressive strength – 45 mpa

??Characteristic cylinder strength – 36 mpa.

??Characteristic split tensile strength – 3.05 mpa.

??Workability at the time of placement - 175 ± 25 mm slump.

??Placement temperature less than 190 C.

What we do to achieve the intended properties in the high performance

concrete using the same ingredients it nothing but a stringent quality

control and exhaustive study/ testing of the concrete ingredients and to

have better control in selection of ingredients for HPC designing the mix

accordingly.

Page 52: Civil Engineers Hand Book for Construction Supervision

MATERIAL TESTING REQUIREMENTS FOR HPC.

??Cement: Ordinary Portland cement –43 grade – confirming to IS

8112

??Coarse Aggregates

??Fine Aggregates

??Water

??Admixtures

a) Chemical Admixtures: - As per ASTM C-494 –99

??Type – A- Water reducing admixtures

??Type-B- Retarding admixtures

??Type-C- Accelerating admixtures

??Type- D- Water reducing & retarding admixtures

??Type-E-Water reducing & accelerating admixtures

??Type-F- Water reducing & high range admixtures.

??Type-G- Water reducing, high range and retarding admixtures

b) MINERAL ADMIXTURES: -

??Fly ash

??Silica fume

??Combination of fly ash & silica fume

Page 53: Civil Engineers Hand Book for Construction Supervision

BASIC STEPS FOR DESIGNING CONCRETE

MIXES AS PER IS 10262

?? TARGET STRENGTH FOR MIX DESIGN: -

fck = fck + 1.656

fck = Characteristic compressive strength at 28 days.

s= Standard deviation for each grade of concrete.

Characteristic strength is defined as that value below which not more

than 5% results are expected to fall.

Code provides values of standard deviations for various grades of

concrete as per degree of control

Mean str. x = ex

n

Standard deviation e = e (x-x)2

n-1

Coeff. Of variation = ? x 100

x

1.65á

MEAN

95%

Page 54: Civil Engineers Hand Book for Construction Supervision

B) SELECTION OF WATER CEMENT RATIO: - Water cement ratio

may be selected based on concrete target strength for different cement

strength & the same is to be checked according to limitations given for

environmental exposure conditions by IS code IS 456-2000.

C) ESTIMATION OF ENTRAPPED AIR:

Max size of agg. (mm) concrete Entrapped air % of volume of 10 3% 20 2% 40 1%

a) Selection of water content & fine to total aggregate ratio from

tables given in IS code according to max. size of aggregates.

b) From water qty. – Calculate cement from W/C ratio.

Min. cement content to be ensured as per durability requirements

fixed by IS under the specified environmental exposure

conditions.

c) Calculate volume of aggregates content in the mix

d) Doses of admixtures and final adjustment of water content

maintaining w/c ratio as per workability requirements are

established based on actual trials in which minor adjustment are

to be done in aggregates quantity to ensure correct yield.

e) Temperature requirements can be met by the addition of ICE

replacing equal qty. of water depending on concrete ingredient

temperatures & ambient conditions.

ACCEPTANCE CRITERIA AS PER IS 456-2000 Compressive strength – (a) Mean strength determined from any group of four consecutive test

results complies with the appropriate limits – in column 2 of table

below: -

(b) Any individual test result complies with the appropriate limits in

column 3 of table below.

Page 55: Civil Engineers Hand Book for Construction Supervision

Specified grade Mean strength for (a)

(N/mm2) Individual test

results in (N/mm2) M15

=fck + 0.825 x ? or fck + 3 (N/mm2) which ever is greater

=fck –3 (N/mm2)

M20 Or

=fck + 0.825 x ? or =fck –4 (N/mm2)

Above

fck + 4 (N/mm2) which ever is greater

HPC should performs satisfactorily in the working environment during its

anticipated exposure condition during service: -

THE FACTORS INFLUENCING DURABILITY INCLUDE: -

a) The environment

b) The cover to embedded steel.

c) The type and quality of constituent’s materials

d) The cement content & water /cement ratio of concrete.

e) Workmanship to obtain full compaction & efficient using.

f) The shape & size of the member

(a) ALKALI AGGREGATES REACTION: -

ALKALI SILICA REACTION – Alkali react in the silica

(amorphous or partly crystallized) resulting in swelling causes an

expansive pressure.

SiO2 + NaOH + nH2O ----- Na2 SiO3 . nH2O

(b) SULPHATE ATTACK The main chemical reaction is the forming of tricalcium sulfo

aluminates hydrate as follow:

3 CaSO4 + 3 CaO.Al2 O3 + nH2O= 3 CaO.Al2O3.3 CaSO4.30-32 H2O Due to its high amount of crystalline water, this compound is

highly expansive. The expansion causes the concrete to crack.

CREEP: - Creep can be defined as “the time dependent increase in

strain without increase of stress i.e. under sustained stress.

Under sustained stress with time the gel, the absorbed water

layer, the water held in the gel pores and capillary pores yields, flows &

readjust themselves which behavior is termed as creep in concrete.

Page 56: Civil Engineers Hand Book for Construction Supervision

Age of loading Creep coefficient ration of

ultimate creep strain plastic strain

7 days 2.2 28 days 1.6 1 year 1.1

SHRINKAGE:

a) Plastic shrinkage

b) Drying shrinkage

Total Shrinkage strain = 0.0003

Page 57: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 10

REQUIREMENT FOR CONCRETE PRODUCTION, TRANSPORTATION, AND

PLACEMENT.

Page 58: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 10 REQUIREMENT FOR CONCRETE PRODUCTION,

TRANSPORTATION, AND PLACEMENT. It is important for Site Engineer/ Site Supervisor engaged in the Civil

Engineering construction that the required quality of the work should be

obtained while executing the work. Out of the total Civil work, concreting

constitute the major part of the work hence required to exercise due

care while production of concrete either through a Batching Plant or

Concrete mixer, transportation of concrete either through manually or

mechanically by transit mixers and placement of the concrete to the

desired location in a pour either through manually or machineries i.e by

crane or through a concrete pump or placer booms or through a chute.

Awareness regarding the requirement at every stages are to be decided

based on the requirement and mode of production/ transportation /

placement methods for concrete. Following are few areas requirements

are listed for exercising care by Site Engineer for the above for effective

and desired output.

A. CARE REQUIRED DURING PRODUCTION OF CONCRETING: -

The care required during production of concreting depends on various

factors.

1. Based on the production of the concrete.

Using concrete mixtures

Using batching plants.

2. Depending on the weather condition i.e. is hot weather concreting

or cold weather concreting.

3. Based on the time of concreting i.e. concreting done during day or

night.

4. Based on distance of batching plant from the point of placement

Page 59: Civil Engineers Hand Book for Construction Supervision

5. Based on the mode of transportation proposed i.e. manual /

through transit mixture.

6. Based on the mode of placement of concrete i.e. by manual/ by

crane / by concrete pump / placer boom / by chute etc.

7. Based on the Rate of pour required.

8. Based on the vertical drop of concrete from batching plant in to

transit mixture.

a. In addition to above site engineer required to ensure the

following based on the requisition of concrete received for

production of concrete.

i. Availability of tested and approved construction material in required

quantity.

ii. The safe access for transportation of construction material to

batching plant / concrete mixture.

iii. Availability of power supply / DG supply / diesel fuel etc for running

the batching plant / mixture for the desired duration.

iv. Based on the past record of batching plant /mixture for production

of concrete for no. of running hours / cumulative concrete

production in cu. m., availability of spare parts to be ensured which

needs frequently repair / replacement to avoid any delay during

concreting.

v. Availability of supporting machines like welding arrangement, skilled

/ unskilled crew for repairing the system.

vi. Proper calibration of batching plant / weigh batcher prior to start

the work. This is generally done at fixed frequencies.

vii. Required rate of pour.

viii. Ensuring safety aspects at batching plant.

ix. Proper illumination and communication system at batching plant for

effective coordination with engineers at point of placement.

Page 60: Civil Engineers Hand Book for Construction Supervision

B. CARE REQUIRED DURING TRANSPORTATION OF CONCRETE: -

The care required during transportation of concrete depends on various

factors: -

1. Mode of transportation, i.e based on the mode of transportation

proposed i.e. manual / through transit mixture.

2. Based on distance of batching plant from the point of

placement.

3. Based on the mode of placement of concrete i.e. by manual/ by

crane / by concrete pump / placer boom / by chute etc.

4. Depending on the weather condition i.e. is hot weather

concreting or cold weather concreting.

5. Based on required rate of pour.

6. Based on stand by arrangement of transit mixers.

7. Based on arrangement for availability of fuel, proper air pressure

in tyres condition of transit mixers.

8. Based on safe access from batching plant to point of placement

and necessary turning areas for transit mixers safely at site.

9. Walkie - Talkie to be provided in transit mixers for effective

coordination.

10. Restriction of traveling speed of loaded and empty transit mixers

11. Ensure availability of water in water tank of transit mixers for

immediate cleaning after concreting is done.

12. Sun protection of transit mixers and its pipes with gunny bags

and ensuring the wetness of the same.

C. CARE REQUIRED DURING PLACEMENT OF CONCRETE: -

It is the most important criteria of concrete since it decides the final

quality and strength of concrete is structures.

The cares required during placement of concrete are as follows: -

Page 61: Civil Engineers Hand Book for Construction Supervision

1. Required consistency to be maintained from the point of

production to point of placing. RPM of transit mixture should

be around 4-5 RPM.

2. Ensure safe access for labours / skilled workers.

3. Ensure planned arrangement of layout of concrete pipe

route.

4. Ensure Sun / Rain protection for green concrete.

5. Ensure proper arrangement of vibratos.

6. Ensure the location of EP’s / Water stop / level of concrete

etc as per drawing during concreting.

7. Ensure type of finish and slope required in concrete.

8. Ensuring the green cutting application within planned

duration after concreting is done.

9. Ensure that no cold joints should form.

10. Use of cement slurry to maintain the concrete green in case

of delay in receiving the successive batch of concrete at site.

Keep the check on time taken from batching plant to the

time at point of placement w.r.t consistency and

temperature.

11. Avoid over vibration in concrete.

12. Avoid vibration of initially hardened layer over which new

concrete is been placed.

13. Maintain all safety aspects particularly while working in

height and hazardous area.

14. Ensure proper illumination and communication.

15. Have leadership quality during difficult situations at site

especially work done in night hrs/ total power cut situation /

during any accident at site / during any industrial relation

problem at site.

Page 62: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 11 POST-CONCRETE INSPECTION

Page 63: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 11

POST-CONCRETE INSPECTION Responsibility of Site Engineer is not only to ensure proper pour planning

and effective execution of the work but also to ensure that desired

results w.r.t quality of the work, i.e finishing, slope, alignment and

bulging etc.

After formwork is removed site engineer must ensure the following w.r.t

post concrete inspection.

1. Depending up on the tolerance available as per drawing and

specification post concrete inspection to be made very next day

after removal of the formwork.

2. Depending upon inspection testing plan record must be generated

to have specific identification of nonconformance noticed beyond

the acceptable limit.

3. Specific attention is given in the following area particularly: -

DEFECTS IN THE CONCRETE NOTICED.

i. Identification of honeycomb portion.

ii. Identification of bulging beyond the acceptable limit.

iii. Identification of poor finish achieved against requirement

beyond the acceptable limit.

iv. Identification of improper slope in the concrete floor against

requirement beyond the acceptable limit.

v. Identification of poor construction joint needs immediate repair

and attention to make it ready to received next course of

concrete.

vi. Identification of projected reinforcement or any other support

casted for giving support of formwork needs to be treated

properly after the purpose achieved for which it has been left.

Page 64: Civil Engineers Hand Book for Construction Supervision

vii. Identification of tie holes which is to be repaired immediately

before going ahead for next pours.

viii. Removal of the left shutter / formwork piece / gunny bags etc.

to be ensured, from concrete surface.

ix. Identification of location of critical EP’s if it is dislocated from the

position or identification any left out of EP’s if due to over sight

or mismatch in the drawings.

x. Identification of the location of the PVC water stop and their

joints.

xi. Identification of cracks to be ensured along with the comments

if it is serious.

xii. Identification of grouting nozzles etc to be made which have to

be placed before next course of concrete.

xiii. It must be ensured that scaffolding, pipes, other construction

material should not be stacked on already constructed walls /

locations where further pours are to be done and PVC water

stop is partly embedded. This shall protect the PVC water bar

from getting damaged.

Necessary non-conformance to be issued for repair and rectification and final inspection to be made to ensure correctness of the above issues.

*****

Page 65: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 12 VARIOUS TYPES OF FINISHES

IN CONCRETE

Page 66: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 12 VARIOUS TYPES OF FINISHES IN CONCRETE Various construction requirements particularly for the surface finish are decided based on the functional requirement / Aesthetical requirement in structure. VARIOUS TYPES OF FINISHES IN CONCRETE: -

Type of Finishes in concrete: -

(1) Formed Surface

Finish F1: - Shall apply to all formed surfaces for which finish F2, F3 or

any other special finish is not specified. Finish F1: - Shall include filling

all form tie holes.

Finish F2: - Shall apply to all formed surfaces so shown in the drawings

or specified by the Engineer. Finish F2- shall include filling all form tie

holes repair of gradual irregularities exceeding 6 mm, removal of ridges

and fins and abrupt irregularities by grinding.

Finish F3- shall apply to all formed surfaces exposed to view or where

shown on the drawings or specified by the Engineer. Finish F3- shall

include all measures specified for finish F2 and in addition, filling air

holes with mortar and treatment of the entire surface with sack rubbed

finish. It shall also include clean up of loose and adhering debris, where

a sack rubbed finish is specified, the surfaces shall be prepared within

two days after removal of the forms. The surfaces shall be wetted and

allowed to dry slightly before mortar is applied by sack rubbing. The

mortar used shall consist of one part cement to one and one half parts

by volume of fine (IS No 16 mesh) sand. Only sufficient mixing water to

give the mortar a workable consistency shall be used. The mortar shall

then be rubbed over the surface with a fine burlap or linen cloth so as to

fill all the surface voids. The mortar in the voids shall be allowed to

stiffen and solidify after which the whole surface shall be wiped clean

with burlap so that the entire surface presents a uniform appearance

without air holes and irregularities.

Curing of surface shall be continue for a period of ten days.

Page 67: Civil Engineers Hand Book for Construction Supervision

2) UNFORMED SURFACES

Finish U1 Finish U1 requires the surface in the specified slope /grade and

the gradual surface irregularities not exceeding 6 mm when measured

with respect to a plane surface parallel to slope with a template 300 mm

long.

Screeding the surface of the concrete to the required slopes and

grade as specified on drawings. Surfaces to be covered with concrete

topping, terrazzo and similar surfaces shall be smooth screeded and

leveled to produce even surface, irregularities not exceeding 6 mm.

Finish U2

Requirements shall be same as for U1 finish except the abrupt

irregularities shall be repaired slope and grade. The surface shall have

wooden finish.

Finish U3

Requirement shall be same as for U2 finish except that the

surface shall have steel trowel finish and the edges of the concrete shall

have the finish with edging tools.

Repair of gradual irregularities exceeding 6 mm, finishing joints

and edges of concrete with edging tools.

SURFACE PREPARATION FOR CONCRETE Site engineers must ensure the following points for surface preparation

while proposing concreting against rock surface or existing concrete

surface.

(A) Rock Surface (i) Inspection of rock surface for soundness.

(ii) Cleaning of the surface to receive concrete.

(B) Concrete Surface (i) Surface preparation: -

a) By Green Cutting

b) By Chipping

c) Cleaning of the surface

(ii) Wetting of the surface prior to concreting.

Page 68: Civil Engineers Hand Book for Construction Supervision

Chapter - 13 DEFECTS IN CONCRETE AND ITS

REPAIR

Page 69: Civil Engineers Hand Book for Construction Supervision

CHAPTER – 13 DEFECTS IN CONCRETE AND ITS REPAIR

Post concrete inspection is a tool to identify the possible general defects

in newly hardened concrete. The typical defects are: -

a. Occurrence of surface blemishes.

b. Honey comb.

c. Cavity holes due to tie rods.

d. Various types of cracks in concrete.

i. Plastic shrinkage cracks.

ii. Plastic settlement cracks.

iii. Drying shrinkage cracks etc.

A. Occurrence of surface blemishes.

The exposed surface area of concrete is blemished when spots or area

vary noticeably and detract from the appearance of surrounding surface

areas. Before treatment of blemishes, the contract documents should be

referred to for identifying the acceptable level of blemishes for the

various surface to be produced under the terms of given in the contract.

Any repair process for treatment of blemishes so chosen should also be

evaluated to determine if it would produce a less apparent and more

pleasing appearance than the original blemish

Repair

When concrete surface is noticed with air bug holes: -

Site engineer can follow either of the following methods for corrective

action.

1) Sack rubbing to repair the blemishes and the fill air bug holes.

2) Action should be such that the treatment is less apparent and

more pleasing appearance.

3) Such treated surface should be cured properly

Page 70: Civil Engineers Hand Book for Construction Supervision

B. HONEY COMB: - During concreting if the voids left in the concrete

due to failure of mortar to effectively fill the space among coarse

aggregate than structure is said to have defect of honeycomb. Such

defects occur due to: -

? ?Congested reinforcement.

? ?Improper vibration.

? ?Difficult construction.

? ?Improper mix i.e. improper aggregate ratio of fine aggregate to

total aggregate.

? ?Leakage of slurry from formwork gaps or damaged formwork.

Site engineer can follow the either of the methods to minimize the

defects: -

? ?Ensure proper vibration.

? ?Ensure proper consistency using water-reducing admixture to

increase slump.

? ?Ensure no gaps in the formwork to prevent slurry leakage.

? ?Using polymer modified cement sand mortar – by hand of

toweling – this method can be used if honeycomb is less than

concrete cover.

? ?If it is more than concrete cover that the area must be chipped off

and concrete must be replaced with normal insitu concrete of

same grade.

C. Cavity holes due to tie rods.

Tie rods, made of reinforcement steel, are often used to ensure that

the form assembly remains intact when subjected to concrete

pressure during concreting process. These tie rods are fixed with

cones at both ends. These cones are open from outer end hence,

when the formwork is removed, they are visible as holes. As this rods

are made of reinforcement and their ends are open to atmosphere, if

left expose for a long period, they are susceptible to correction.

? ?Repair method: - By dry pack mortar

Page 71: Civil Engineers Hand Book for Construction Supervision

CRACKS IN CONCRETE

CRACK IN CONCRETE: - This defect permits the ingress of aggression

agent in the structure and adversely affect.

A. The durability.

B. Water tightness.

C. Integrity of structure i.e. strength

Sound transmission: - Crack trough NDT techniques

D. Various types of cracks in concrete.

PLASTIC SHRINKAGE CRACKS: - This caused due to repaid loss of

moisture due to temperature of ambient air and concrete, relative

humidity and prevailing wind velocity at the surface of concrete.

Site engineer should take following precautions to prevent rapid moisture

loss due to hot weather and dry wind.

I. Covering the concrete by plastic sheet.

II. To provide sunshade during concreting.

III. Use fog nozzles to saturate air above green concrete surface.

IV. Use of windbreaker to reduce wind velocity.

PLASTIC SETTLEMENT CRACKS: -concrete is consolidated after initial

placement vibration and finishing. The plastic concrete generally give

local retrain by reinforcement etc. and result cracks or known as plastic

settlement crack.

Site engineer should follow following preventive measure to minimize the

plastic settlement cracks.

??Maintain proper cover in concrete.

??Provision of time interval between placement of concrete in slabs

and beams.

??Use or minimum slump concrete.

Page 72: Civil Engineers Hand Book for Construction Supervision

Drying shrinkage cracks: - When concrete is wet, it tends to expand.

It reduces its volume, when loss of moisture from cement paste occurs.

It can be explained in simple words. If this shrinkage can occur without

any restrain no cracks will appear. But combination of shrinkage and

restrain provided by another part of structure or by sub grade develops

the tensile stress in concrete. This is resulting in crack known as drying

shrinkage crack.

Site engineer should follow the following methods to reduce

this effects: -

??Use less w/c ratio in a concrete mix.

??Use large amount of aggregate.

??Proper consolidation of concrete.

REPAIRING OF CRACKS: - In spite of precaution observed some

times cracks are seen in the concrete surface and needs repair. The

repairing of cracks mainly depends on: -

??Location and width of cracks.

??Extent of crack

??General condition of concrete.

Following methods can be used for repair of cracks: -

1) GROUTING: - Wide crack can be filled by either cement grout or

various chemical grouts.

2) Dry packing: - Method used for minor dormant cracks but not

effective for active cracks.

Cracks are widened to a slot of 15-20mm vide and 20-25 deep with

base width slightly more than surface width. This is packed by

cement mortar with low w/c ratio.

3) Gravity filling: - Cracks can be filled upto with low viscosity

epoxies.

Page 73: Civil Engineers Hand Book for Construction Supervision

4) Routing and sealing: - This method is used where structural

repair is not necessary. This procedure is more accurate for flat

and horizontal surface like floors / pavements. These methods can

be commonly used for water proofing by sealing cracks on

concrete surface on concrete surface, where water stands or

hydrostatic pressure applied.

5) Injection grouting: - Repairing of narrow crack width upto 0.05

mm can be done. In this method GI or PVC nozzle is drilled in the

cracked over upto depth of thickness of half the member and

grouting is done.

Every Engineer has to deliver the output based on the requirement and

facing the challenges to meet the quality standards with optimum use of

manpower. It is need less to say that in a competitive environment, the

restricted and compressed time schedule, the structural adequacies for

the various problems are need to be reviewed as listed below: -

(1) Overall strength and stability of the structure.

(2) Surface finish and appearance of the structure i.e. cracks

leaching discoloration etc.

(3) Effect of leakage /seepage and effect of un-stability due to

local parameters like improper backfilling/ undulations etc.

(4) Durability with respect to corrosion, carbonation and sulphate

attack.

Various type defect and damages in structures have been noticed over a

period of time in various localities this has resulted a need for an

Engineer to understand these defect and their respective possible

causes. Responsibility is not only limited to identification of the damages

but require to recommend necessary corrective measures including

investigations if necessary.

Page 74: Civil Engineers Hand Book for Construction Supervision

Brief details of defects and damages occurred in concrete are

indicated below along with their possible causes and suggested

investigations for ready reference: -

CONCRETE

Visible Defect Possible Causes Investigation Suggested

Rust on surface. Iron compounds in

aggregates, nails/wires

left in formwork.

Chemical analysis of

samples.

Rust stains on surface. Corrosion of binding wires,

corrosion of reinforcement

steel.

Check cover and

carbonation of concrete.

Cracking of concrete

cover, exposure of

reinforcement and

spelling of concrete

Corrosion of reinforcement

and other steel due to

moisture and chloride

ingress, frost attack and

poor quality of concrete

low density, high porosity

and high water to cement

ratio).

Check cover, test for

chlorides and

carbonation, check

reinforcement adequacy.

Surface crazing. Concrete Mix too wet and

poor curing.

Check concrete mix and

construction method

used.

Random diagonal

cracking, lateral

cracking at equal

spacing

Inadequate protection

against shrinkage, over

rich or over wet and non-

cohesive concrete.

Check reinforcement,

spacing of joint, analyze

samples of concrete.

Repetitive vertical or

horizontal cracks.

Joint spacing too large. Examine joint

details/spacing check

concrete sample and

aggregates used.

Page 75: Civil Engineers Hand Book for Construction Supervision

Wet and damp spots,

deteriorated applied

finishes without

cracking.

Honeycombs due to poor

placement of concrete

mix, poor compaction or

water stopper missing.

Check concrete after

recovering applied

finishes, checks detailing

of joints, check for water

stopper, test and analyze

concrete.

Cracks at intervals. Restrained shrinkage,

reinforcement too near

the surface, corrosion of

reinforcement, moisture

movements.

Check spacing of joints

9design), check

distribution of

reinforcement, concrete

sample.

Faulty movement joints,

faulty or missing water

stopper, inadequate or

improperly constructed

join, inadequate

reinforcement.

Check concrete at joints,

check water bars and

reinforcement details.

Rust stains below

mortar covering of

external pre-stressing.

Tendon corrosion, poor

grouting of tendons.

Check location/ extent of

corrosion.

Map cracking. Alkali-silica reaction (ASR),

early drying out

conditions, over rich

mixes, over compaction

and poor curing.

Check concrete

constituents, pertographic

analysis.

Surface abrasion. Excessive wear. Check abrasive loading,

check quality of concrete

surface, check history of

usage.

Page 76: Civil Engineers Hand Book for Construction Supervision

Cracking or spelling

with or without staining

(generally parallel to the

direction of

reinforcement steel).

Corrosion of reinforcement

steel or pre-stress tendons

corrosion of encases steel,

alkali silica reaction (ASR),

restrained by

reinforcement.

Check condition of

embedded steel, check

cover, carbonation,

chloride content, check

presence of ASR.

Deflection. Shrinkable aggregate,

premature removal of

formwork, overloading.

Analysis of concrete

samples design check.

Local settlements along

with diagonal cracks on

footings (foundation)

Poor sub grade

compaction, inadequate

reinforcement, ground

movement due to water /

erosion/ mining/ shrinkage

clays, peat or other

causes.

Investigate foundation

design and substrate.

Vertical or slightly

inclined cracks on sides

and soffit on central

part of RCC beams.

If less than 0.3 mm:

Normal if wider than 0.5

mm: Overload, excessive

shrinkage of slab,

premature removal of

props.

Check design, compare

actual load with design

load, check span/ depth

ration with codal

requirements, check

temperature gradient

Diagonally inclined

cracks in beams,

generally at or close to

the supports.

Overloading, inadequate

beams depth,

inadequately provided

reinforcement to prevent

shear.

Check actual shear

resistance against codal

allowance.

Vertical cracks in RCC

beams at regular

intervals.

Shrinkage around stirrups.

Page 77: Civil Engineers Hand Book for Construction Supervision

Helical cracks in RCC

beams face and

extending around the

section perimeters.

Tensional shear stresses. Check actual tensional

resistance against codal

requirement

Excessive deflection of

RCC beams.

Inadequate depth,

overloading, formwork

defect, inadequate or

displace reinforcement,

shrinkable aggregate,

materials defective or

deteriorated, bond failure

between reinforcement

and concrete.

Check span/depth ratio

with codal requirements,

compare actual and

theoretical deflections,

check loading history,

cover meter check, test

concrete, check for

defects in construction.

Pre-stressed concrete

beams with excessive

deflection, excessive

handing, loose or

defective anchorage

segment separation,

grout disturbance and

distribution not proper,

segmental shear cracks.

Overloading, overstressing

or poor concrete,

inadequate pre-stresses,

displaced tendons,

material defective or

deteriorated.

Check deflection, and

stresses against actual

load, check conditions of

all tendons, check design,

check cover by cover

meter.

Bowing of pre-stressed

columns.

Distortion during erection,

concrete creep or

shrinkage, tendon

fractures, defective

material or material

deterioration.

Check loading conditions,

check design and

construction defects,

check cover by cover

meter, check tondon

condition at any fracture.

Excessive deflection in

slabs and / or heaving

of tiles or cracking of

tiles on the top surface.

Inadequate depth,

overloading, for long

period, defective

formwork, inadequate or

Check span/depth ratio

with code requirements,

compare actual and

theoretical deflections,

Page 78: Civil Engineers Hand Book for Construction Supervision

displaced steel

reinforcement, material

defective or deteriorated,

lack of continuity.

check loading history,

check cover by cover

meter, check for

shrinkable aggregates.

Cracking of slab and /

or finishes over

supports.

Plastic and drying

shrinkage cracks, slab

designed as simply

supported but constructed

as continuous or with

fixed supports, inadequate

top reinforcement in

continuously designed

slab, excessive support

memento relaxation,

inadequate top steel at

supports, top steel

displace.

Check design, check

construction defects and

cover by cover meter.

Page 79: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 14 VARIOUS TYPES OF JOINTS

Page 80: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 14 VARIOUS TYPES OF JOINTS

The site engineer is required to complete the work as per drawing

requirement to the minimum possible time. It is a fact that the entire

work can not be completed in just single pour due to the constraint of

non availability of resources as per requirements, due to technical

reasons i.e considering thermal strain and expansion & contraction

properties of structure. Generally there are following types of joints are

to be handled during Civil construction.

1) CONSTRUCTION JONTS: -

2) EXPANSION JOINT AND CONTRACTION JOINT: -

3) COLD JOINT: -

CONSTRUCTION JONTS: -

Construction joints occur wherever concreting is stopped or delayed and

when the fresh concrete placed against hardened concrete subsequently

cannot be integrated into previous by vibrating. Horizontal construction

joints occur at levels between two successive lift of concrete, whereas

vertical construction joints occur where structure of such length that is

not feasible to place the entire length in one continuous operation.

Construction joints, are required by the construction operation.

Construction joint locations depend on sequence of concreting

operations or are part of the contract drawings. Construction joint

location need to be planned ahead of placing of concrete and should

adhere to those pre identified locations. Generally, they mark the top of

a lift, the end of a monolith, or the end of a days work. They should be

properly located and well bonded.

Page 81: Civil Engineers Hand Book for Construction Supervision

The following factors are to be considered for location and treatment of

construction joints to make them perfect and avoid cold joints.

??When the work is to be interrupted, horizontal and vertical

construction joints and bonding keys should be located in

conformity with the relevant contract specifications/drawings.

??Construction joints should be located in the floor slab and beams

near the middle of the span (where the shear is least) and should

be vertical in the absence of provisions in construction drawings.

In a column, the joint should be formed about 75 mm below the

lowest soffit of the beams framing in to it.

??Because construction joints frequently leak and degrade in the

weather, as far as possible, they should be avoided. Before fresh

concrete is placed. Existing concrete surface must be made rough

by hacking or green cutting.

??The rough surface should be thoroughly wetted for about two

hours and should be dried and coated with 1:1 freshly mixed

cement –sand slurry, immediately before pacing the new

concrete.

GREEN CUTTING FOR CONSTRUCTION JOINT TREATMENT: -

Where higher degree of quality of construction joint treatment is

required as per contract specification/or drawings, green cutting should

be applied. The entire construction joint should be treated by Green

cutting using air / water jet at a suitable pressure to remove the laitance

from the green concrete surface to received subsequent pour of concrete

over it. A suitable, approved brand of surface retarder should be used to

retard setting time of green concrete to a depth of 5 to 8 mm. Green

cutting should b done only after the final setting of concrete, so that the

additional water available from air water jet used for green cutting on

the surface does not harm the quality of the concrete. Prior to

commencement of the green cutting operation, a mockup should be

Page 82: Civil Engineers Hand Book for Construction Supervision

made for each grade of concrete, with different types of cement and

different kinds of exposure of the proposed construction joint.

EXPANSION AND CONTRACTION JOINTS: - Expansion and

contraction joints should be strictly as per the relevant construction

drawings only. Line and level of water –stop and expansion boards, if

any at these joints should be safeguarded from damage or dislocation

during placing and consolidation of concrete.

*****

Page 83: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 15

ASSESSMENT OF SAFE WORKING CONDITIONS

WHILE EXECUTING THE JOB.

Page 84: Civil Engineers Hand Book for Construction Supervision

CHAPTER–15 ASSESSMENT OF SAFE WORKING

CONDITIONS WHILE EXECUTING THE JOB. Responsibility of Site engineer with respect to safety requirements at site is most important parameter. Every site engineer must ensure availability of safe working condition while executing the job. Following few areas must be given attention.

1. Suitable scaffolds shall be provided for workmen for all works

that cannot safely be done from the ground..

2. Scaffolding or staging more than 3.5 m above the ground or

floor, swing of suspended from an overhead support or erected

with stationary support shall have standard guard rail properly

attached bolted, braced or otherwise secured at least 1.0 meter

high above the floor or platform of staging..

3. Working platforms of scaffolds shall have toe boards at least 15

cm in height to prevent materials from falling down.

4. Working platform, gangways and stairways shall be so

constructed that they shall not sag unduly or unequally

5. Safe means of access shall be provided to all working platforms

and other elevated working places

6. Adequate precautions shall be taken to prevent danger from

electrical lines and equipment. No scaffolding, ladder, working

platform, gangway runs, etc. shall exist within 3 meters of any

uninsulated electric wire.

7. Proper house keeping must be maintained at site.

8. Necessary personnel protective equipments must be used while

working.

9. Safety work permits to be ensured while working at height,

hazardous operations, work in radiation area, work in and

around water body.

Page 85: Civil Engineers Hand Book for Construction Supervision

10. Slope of ladder shall not be steeper than 1 in 4 i.e. 1 horizontal

to 4 vertical.

11. Ladder shall not be used for climbing with carrying materials in

hands.

12. Due care must be taken while removal of formwork.

13. Use of safety belt to be ensured while `working at height.

14. Proper illumination and frequent checking of scaffold to be

maintained.

15. All loose material should be removed.

16. Any material having fire hazard to loose formwork pieces,

wooden block must be removed from the working area.

17. Ensure deployment of only quality and skilled manpower for

handling. The movement of construction, concrete, formwork,

re-steels pipes etc at site.

18. Ensure to avoid any temporary steep slope or ramp at site for

movement of works and machineries.

19. Maintain a house keeping culture at site. Ensure to stack all

construction material like formwork, pipes etc properly stacked

so that safe approach is maintained.

20. Construction material likes re steel, aggregate, sand, also to

stacked properly.

21. Ensure proper communication while entering in a hazardous

area.

22. Inculcate the safety as culture and habit within the group.

Page 86: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 16

IMPORTANCE OF JOB HAZARD ANALYSIS.

Page 87: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 16 IMPORTANCE OF JOB HAZARD

ANALYSIS. Work can only be said to complete successfully if requirements

with respect to quality have been maintained without any

accident during execution of the work. Safe working condition

not only increases the output, but also gives satisfaction and

confidence while working in any of difficult conditions.

For a Site engineer it always preferred that we must know about the

work in totality. This will help us to identify the various sub activities

involved in the work and to assess the possible hazards during executing

the work. Action required to prevent such possible hazards must be

enlisted and honest efforts must be made to avoid any unsafe conditions

during execution of the work. It is preferred that job hazard analysis

should be done before start of the work.

Sample format for job hazard analysis in given below for ready

reference.

Name of the work : -

MAJOR ACTIVITY TO BE TAKEN UP: -

Duration of the activities : -

Sr.no Activities Possible hazards Action to be

taken for

prevention of

hazards

Page 88: Civil Engineers Hand Book for Construction Supervision

CHAPTER - 17

AWARENESS OF QA REQUIREMENTS

Page 89: Civil Engineers Hand Book for Construction Supervision

CHAPTER – 17 AWARENESS OF QA REQUIREMENTS

A most impartment part for implementing any QA requirement

needs to understand about the intent and meaning of the

quality. The brief description about the terms generally used

related to QA are summarized below.

Quality: - Totality of feature and characteristic of product or service

that bears on its ability to satisfy stated or implied need.

Stated needs means contractual needs.

Implies Need means – Identifies and defined needs i.e Usability, Safety,

Reliability, Availability and Maintainability.

Specification: - Document that describes the requirement with which

the product / service has to confirm.

It should refer to – pattern, drawing, or code. Or indicate the criterion by

which checks to be made.

Checks used to confer the specification requirement.

Procedures. : - An identified and defined sequential activities to

perform the task is known as procedure. It is specified way to perform

the activity. It contain purpose and Scope, What, When, By Whom,

Where, How the activities to be done, Reference, Control Required and

record to be maintained.

Inspection: - Activities such as measuring examining, testing, gauging

are made and compared with the standard to determine the conformity

of requirement.

Quality assurance: - Adequate and proper planning and systematic

action which are necessary to provide adequate confidence that product

or service will satisfy given requirement for quality.

Page 90: Civil Engineers Hand Book for Construction Supervision

Quality Control: - The operational techniques are performed to full fill

the requirement of quality.

1) Monitoring a process.

2) Removes causes of conformity at relevant stages to increase

economic effectiveness

Process: - A set of interrelated resources and activates which

transforms input to output.

Quality surveillance: - The continuing monitoring and verification of

status of procedure, methods, conditions referred as quality surveillance.

In relation to stated reference to ensure that specified requirement is

made.

Quality surveillance: - Takes in to accounts the areas to deterioration

or degradation with time.

Quality System: - It is defined as organization structure management

function that determines and implement quality policy.

Quality Management: - It is aspect of overall management function

that determines and implements quality policy.

Quality policy: - It is defined overall intensions and direction of an

organization as regard to quality formally expressed by top

management.

Total quality management: -

1) It is a management approach of an organization cantered on

quality.

2) Based on participation of all its members.

Page 91: Civil Engineers Hand Book for Construction Supervision

3) Aiming at long-term success through customer satisfaction, and

benefits to the member of organization at safety.

Quality manual: - A document stating the quality policy and describing

the quality system of and organization.

QA Plans: - It is a systematic way of describing the extent and

responsibility for checking and acceptance of various sub activities with

respect to defined references and specification.

Quality Audit: - It is systematic and independent examination to

determine.

1) Whether the quality activities and related result comply with the

planned arrangement.

2) Whether there planned arrangement are implemented effectively

or not.

3) Planned arrangements are suitable to achieve the objective.

Site engineer must know that there are three Quality Assurance

manual in our organization.

(i) Topical QA manual: -

A document stating quality policy and describe the quality

system of total organization.

(ii) Project QA manual: -

A document stating quality policy and describe the quality

system of specific project in line with requirement stated in

topical QA manual.

(iii) Specific work related QA manual: -

A document stating quality policy and describe the quality

system of agency executing the specific job / contract in a

project in line with requirement stated in topical QA manual and

Project QA manual.

Page 92: Civil Engineers Hand Book for Construction Supervision

Site engineer also must ensure the following while supervising

the work: -

1) Implementation of relevant specification required for the work.

2) Implementation of work procedure for specific construction

activity.

3) Inspection and testing plan for the referred work.

4) Ensure availability and use of proper approved construction

material at site.

5) Ensure the deployment of qualified manpower at site for various

construction activities.

6) Ensure concrete pour plan arrangement as per schedule plan.

7) Proper supervision during pre execution, during concreting and

post concreting.

8) Ensure repair of defects / deficiencies, if found as per approved

procedure.

9) Ensure appropriate documentation for the work.

Page 93: Civil Engineers Hand Book for Construction Supervision

Effective and desired results with optimum use of departmental manpower engaged in Supervision of Construction activities is always a major concern of NPCIL vision and policy. He has provided Enthusiastic and inspiring support for development of this document

C.P. JHAMB PROJECT DIRECTOR, RAPP-5&6

Providing dedicated & committed leadership

Development of this document as handy tool and reference to requirement of Site Supervisors and Site Engineers directly connected with the work was the vision ofSh. D.K.JAIN, Chief Engineer (Civil), RAPP-5&6. This could be made possible due to his efficient and able leadership, effective guidance, continuous motivation and appreciation at every stage.

D.K.JAINCHIEF ENGINEER (CIVIL), RAPP-5&6

A man with inspiring and strong vision.