City of Phoenix

Aviation Department

Project No. AV21000097-1

Design Services

June 6, 2017

Pre-Submittal Meeting

Phoenix Sky Harbor International Airport

Terminal 4, S-1 Concourse

Liz Blakley, Contract Specialist

Candace Huff, PE, Special Projects Administrator

B.A. Golston, Project Manager

Rick Slankard, Superintendent

Sarah Carter, Program Manager

Dustin Loftis, Airside Superintendent

Jody Springer, Supervisor III

Welcome and Introductions

Meeting Overview

Sign-in please…copies of sign in sheet will be

available on website:

http://phoenix.gov/streets/procurement/

current-opportunities

Please hold questions until the Q&A period.

This is the ONLY opportunity to discuss this

project with City staff.

Notification of change to the Request for

Qualifications are posted on our website:

Project Description

Project Scope of Work

SOQ Criteria

Submittal Requirements

Selection Schedule

Questions?

Agenda

On October 25, 2016, the Phoenix City Council approved

construction and funding of T4 S-1:

Up to eight new gates at PHX

Allow for additional and newer facilities to enhance

customer service

More easily serve passengers and support long term

airline activity.

Southwest Airlines is the Tenant

Project Description

A new 3-4 level concourse (basement, apron and

passenger levels) with approximately 30,000 square feet

per level; mezzanine potential.

Connector bridge with moving walkways.

Transfer bridge with moving walkways.

Aircraft apron and hydrant fueling system.

Security screening expansion at Checkpoint D.

Ticketing counter and baggage claim carousel expansion

Baggage handling system and EDS expansion to service

T4 S1 and T4 S2 demand.

Project Scope of Work

Aircraft parking plan.

Public Restrooms.

Associated structural, electrical, mechanical and civil

work.

Retail and food and beverage shell spaces.

Potential International Facilities.

Passenger boarding bridge and gate equipment.

Airside, landside access and loading dock.

Service road below taxiways.

Project Scope of Work(cont…)

Project Scope of Work – Ref Plan

The project scope will be finalized at the completion of our terminal

and concourse planning study.

(cont…)

Project Scope of Work – Site Plan(cont…)

Planning - the scope of the planning study anticipates:

Concept planning for a new 8 gate concourse (S1)• Gate and seating layouts

• Commercial and support spaces

Concept planning of the apron and stand to support (S1)• Aircraft parking and Passenger Boarding Bridge configuration

• Ground Service Equipment (GSE) movement areas and airside

vehicle roadways

Confirmation the existing processor to support (S1)• Ticketing counters

• Baggage claim and handling

• Security screening

• Commercial and support spaces

Planning

Project Schedule / Budget

• Budget: $250M

• Construction cost: approximately $180M

* Operational Readiness and Testing

Excellent Design & Construction Administration services

Quality design - within scope, budget and schedule

Active airside and landside environment – Minimize

Operational disruptions

Extensive input and coordination with various City, State

and Federal Departments, Aviation Project Management

team, Aviation Divisions and vested stakeholders

Address all Federal, State and Local requirements

Possible Airport Improvement Program (AIP) grant

compliance required

Public Art – Procurement and install (design by the City)

Utilize the City’s web based project management system,

Unifier

Project Expectations

13

QUESTIONS?

The selection of the Consultant will be based on the

following qualifications:

General Information – 10 points

Design Experience of the Prime Firm – 20 points

Construction Administration and Inspection Exp. – 15

points

Experience of Key Personnel and Subconsultants – 20

points

Project Understanding and Approach – 30 points

Overall Evaluation – 5 points

Statement of Qualifications

Each page side with criteria information will be counted.

Pages that have photos, charts, and graphs will be

counted toward maximum number of pages.

Front and back cover, Table of Contents and tab dividers

will NOT be counted toward the maximum page limit,

UNLESS they include information that may be

considered by the selection panel.

Statement of Qualifications, Cont.

Submit 10 copies of the SOQ

SOQ due:

12:00 p.m. Noon – Arizona Local Time

Friday, June 16, 2017

City Engineer

CITY OF PHOENIX

200 W. Washington Street, 6th Floor

Phoenix, AZ 85003

c/o Liz Blakley

Statement of Qualifications, Cont.

Grounds for Disqualification:

Receipt of submittal after specified cut-off date and

time

Too few copies of the submittal

Deposit of submittal in the wrong location

Statement of Qualifications, Cont.

Cover Letter (company name, address and contact

information)

Evaluation Criteria (including project organizational chart)

Additional Content (resumes or other information)

MAXIMUM pages permitted is 20 pages:

Cover Letter (Not included in 20 pages)

+ Evaluation Criteria (including organizational chart)

+ Additional Content (resumes or other information)

= 20 MAXIMUM pages permitted

Submittal Requirements

• SOQs due at 12:00 p.m. June 16, 2017

• Interview Notification July 12, 2017

• Interviews July 26, 2017

• Scope Meeting September 2017

Selection Schedule

Request for Qualifications

Notifications

Power Point Presentation

Plan Holder List

Firms to be Interviewed

http://phoenix.gov/streets/procurement/project-

interviews

Award

http://phoenix.gov/streets/procurement/bid-results

Streets Transportation Webpage

Liz Blakley, Contracts Specialist

(602) 681-5317

[email protected]

Questions After Today