    COMPLETED PROJECTS

    Several roads projects were completed in June and reopened to traffic:

    Rossdale Road Bridge

    Whitemud Drive/17 Street Interchange

    66 Street (Anthony Henday Drive to 195 Avenue)

    ROADS DESIGN & CONSTRUCTION UPDATE - JULY 2013

    DOWNTOWN TRAFFIC DISRUPTIONS

    As downtown Edmonton continues to grow and revitalize, significant construction continues, and with it associated

    traffic impacts. The City plans and stages construction projects to sustainably support downtown revitalization while

    managing traffic disruptions as efficiently as possible. The City is also responsible for managing and accommodating

    other various road disruptions such as private development, emergency utility repairs, planned events and festivals

    Transportation Services makes every effort to limit the impact to traffic, however it cannot always anticipate where

    and when emergency repairs or other unforeseen roadway incidents, such as vehicle collisions, may require additional

    road closures. As such, there will sometimes be higher congestion levels into and out of downtown during construction

    season.

    WEATHER IMPACTS

    Despite a rainy June, poor weather will have little impact on most road project schedules. The longest delays in City

    road construction are on projects where excavation is ongoing due to the time required to dry out the site before work

    can continue. Fortunately, grind and pave locations can continue shortly after rainfall as their work surfaces dry more

    quickly.

    The Citys priority when dealing with inclement weather is to make certain that work is completed to standard.

    This ensures durability, longevity and safety for road users. While completing a project on time is important, it is a

    secondary consideration to having work done properly the first time.

    The City reminds drivers to respect barricades even in poor weather conditions, as work may be ongoing and hazards

    present despite workers not being visible on site.

    THE WAY WEMOVE

    ARTERIAL PROJECTS

    34 AVENUE WIDENING

    Activity Construction started Jun 10. Excavation/removals to road subgrade from 48 St working east to 34 St.

    Dates Complete excavation/removals to road subgrade from 48 St to 37 St by Jul 12.

    Contractor to begin work Jul 16.

    63 AVE & ALLENDALE ROAD REHABILITATION

    Activity Reconstruction of 63 Ave (99 St to 104 St).

    Rehabilitation of Allendale Rd (104 St to 106 St).

    Milling and paving of Calgary Trail southbound (63 Ave to 51 Ave).

  • 7/28/2019 City of Edmonton's July 2013 Construction Update

    2/3

    THE WAY WEMOVE

    Impacts Jul 11: 63 Ave westbound closed for road removal and reconstruction. Traffic detoured to 63 Ave

    eastbound. Jul 15: single lane closures on Allendale Road.

    Jul 29: off-peak lane closures on Calgary Trail.

    Pedestrian access maintained on one side of the road at all times. No parking in signed areas.

    Access to businesses and residences maintained at all times.

    108 STREET STREETSCAPE

    Activity Gravel base placement on 108 St between 103 Ave and 104 Ave began first week of July.

    New walk on east side of 108 St from 103 Ave to 104 Ave.

    Dates Intersection at 108 St and 103 Ave to remain closed until Aug 9.

    118 AVENUE STREETSCAPE

    Activity SW corner of 106 St and 118 Ave opened to pedestrians.

    Concrete work completed on south side.

    Asphalt path and landscaping completed on south side.

    Dates Project anticipated to be completed by Aug 30.

    CENTRAL LRT REHABILITATION & JASPER AVENUE STREETSCAPE

    Activity Demolition of roadway complete, except SE quadrant of 101 St.

    Smoke exhaust ducting for Central LRT Station removed. New ducting to be constructed following

    completion of structure for new exhaust vent location.

    LRT topping slab and waterproofing complete, except 101 St SE. Approximately 80% of concrete

    roadway surface poured in June.

    Structural steel columns, fireproofing nearly complete in LRT station. Architectural finishes

    ongoing.

    Dates Work on Jasper Ave south sidewalk began in early July. Pedestrian traffic switched to ped corridors

    Jul 2.

    All concrete roadway to be completed in July except 101 St SE.

    Traffic shift on 101 St expected for Jul 28. Work on east side of 101 St will take 8 weeks.

    STONY PLAIN ROAD STREETSCAPE

    Activity EPCOR completed lighting on the north side of Stony PlainRoad (SPR) between 158 St and 153 St, and installed new

    signals at 154 St and 153 St.

    New three-colour walk has been poured on north side of

    SPR between 158 St and 155 St.

    Silva cells for tree pits have been installed on north side of

    SPR between 158 St and 155 St.

    Dates July 10: EPCOR to complete streetlights to 152 St.

    July 12: Contractor to complete all new walk on north side

    of SPR between 158 St and 155 St.STONY PLAIN ROAD 3-COLOUR WALK

  • 7/28/2019 City of Edmonton's July 2013 Construction Update

    3/3

    THE WAY WEMOVE

    NEW ARTERIAL PROJECTS

    GUARDIAN ROAD/LEWIS ESTATES BOULEVARDActivity EPCOR signal pole relocation.

    Installation of mainline sewer from Granville Dr to Whitemud Dr.

    Signal installation at Whitemud Dr, Granville Dr, Potter Greens Dr.

    Dates Construction began Jul 8.

    BRIDGE & INTERCHANGE PROJECTS

    23 AVENUE/GATEWAY BOULEVARD

    Activity Final 50 mm stone mastic asphalt (SMA) work. Night paving from 8:30 pm-5:30 am Monday to

    Friday, 8:30 pm-8:30 am Saturday and Sunday.

    Dates Night paving from Jul 22 to Aug 30.

    111 STREET/30 AVENUE SW BRIDGE

    Activity Bridge deck, approach slabs and barriers poured.

    Dates Roadway construction began week of Jun 24.

    STONY PLAIN ROAD BRIDGE OVER GROAT ROAD

    Activity Stony Plain Road from Connaught Dr to 142 St milling and paving.

    ETS Route 398 replaced by on-call shuttle.

    Bridge work continues.

    Dates Milling and paving on Stony Plain Road done Jul 4-8.

    WALTERDALE BRIDGE

    Activity Bridge construction work begins mid-July. 2013 work will

    include re-grading of south side to accommodate future

    realignment of Queen Elizabeth Park Rd and construction

    of thrust blocks in river.

    Impacts Queen Elizabeth Park Rd closed Jul 15 to Nov 1. Bridge

    will remain open throughout construction. Detour using

    Walterdale Hill Rd, 99 St/Scona Rd, or 98 Ave/James

    MacDonald Bridge. ETS Route 52 will detour using Scona Rd for duration of

    project.

    Please note that all projected completion dates are weather permitting. Road barricades are in place where required

    for public and worker safety. Hazards may be present when workers are not. Permission to use barricades is strictly

    enforced. Project details and updates are available at www.edmonton.ca/roadprojects. To view all 2013 construction

    go to www.edmonton.ca/constructiononyourstreets