COMPLETED PROJECTS
Several roads projects were completed in June and reopened to traffic:
Rossdale Road Bridge
Whitemud Drive/17 Street Interchange
66 Street (Anthony Henday Drive to 195 Avenue)
ROADS DESIGN & CONSTRUCTION UPDATE - JULY 2013
DOWNTOWN TRAFFIC DISRUPTIONS
As downtown Edmonton continues to grow and revitalize, significant construction continues, and with it associated
traffic impacts. The City plans and stages construction projects to sustainably support downtown revitalization while
managing traffic disruptions as efficiently as possible. The City is also responsible for managing and accommodating
other various road disruptions such as private development, emergency utility repairs, planned events and festivals
Transportation Services makes every effort to limit the impact to traffic, however it cannot always anticipate where
and when emergency repairs or other unforeseen roadway incidents, such as vehicle collisions, may require additional
road closures. As such, there will sometimes be higher congestion levels into and out of downtown during construction
season.
WEATHER IMPACTS
Despite a rainy June, poor weather will have little impact on most road project schedules. The longest delays in City
road construction are on projects where excavation is ongoing due to the time required to dry out the site before work
can continue. Fortunately, grind and pave locations can continue shortly after rainfall as their work surfaces dry more
quickly.
The Citys priority when dealing with inclement weather is to make certain that work is completed to standard.
This ensures durability, longevity and safety for road users. While completing a project on time is important, it is a
secondary consideration to having work done properly the first time.
The City reminds drivers to respect barricades even in poor weather conditions, as work may be ongoing and hazards
present despite workers not being visible on site.
THE WAY WEMOVE
ARTERIAL PROJECTS
34 AVENUE WIDENING
Activity Construction started Jun 10. Excavation/removals to road subgrade from 48 St working east to 34 St.
Dates Complete excavation/removals to road subgrade from 48 St to 37 St by Jul 12.
Contractor to begin work Jul 16.
63 AVE & ALLENDALE ROAD REHABILITATION
Activity Reconstruction of 63 Ave (99 St to 104 St).
Rehabilitation of Allendale Rd (104 St to 106 St).
Milling and paving of Calgary Trail southbound (63 Ave to 51 Ave).
7/28/2019 City of Edmonton's July 2013 Construction Update
2/3
THE WAY WEMOVE
Impacts Jul 11: 63 Ave westbound closed for road removal and reconstruction. Traffic detoured to 63 Ave
eastbound. Jul 15: single lane closures on Allendale Road.
Jul 29: off-peak lane closures on Calgary Trail.
Pedestrian access maintained on one side of the road at all times. No parking in signed areas.
Access to businesses and residences maintained at all times.
108 STREET STREETSCAPE
Activity Gravel base placement on 108 St between 103 Ave and 104 Ave began first week of July.
New walk on east side of 108 St from 103 Ave to 104 Ave.
Dates Intersection at 108 St and 103 Ave to remain closed until Aug 9.
118 AVENUE STREETSCAPE
Activity SW corner of 106 St and 118 Ave opened to pedestrians.
Concrete work completed on south side.
Asphalt path and landscaping completed on south side.
Dates Project anticipated to be completed by Aug 30.
CENTRAL LRT REHABILITATION & JASPER AVENUE STREETSCAPE
Activity Demolition of roadway complete, except SE quadrant of 101 St.
Smoke exhaust ducting for Central LRT Station removed. New ducting to be constructed following
completion of structure for new exhaust vent location.
LRT topping slab and waterproofing complete, except 101 St SE. Approximately 80% of concrete
roadway surface poured in June.
Structural steel columns, fireproofing nearly complete in LRT station. Architectural finishes
ongoing.
Dates Work on Jasper Ave south sidewalk began in early July. Pedestrian traffic switched to ped corridors
Jul 2.
All concrete roadway to be completed in July except 101 St SE.
Traffic shift on 101 St expected for Jul 28. Work on east side of 101 St will take 8 weeks.
STONY PLAIN ROAD STREETSCAPE
Activity EPCOR completed lighting on the north side of Stony PlainRoad (SPR) between 158 St and 153 St, and installed new
signals at 154 St and 153 St.
New three-colour walk has been poured on north side of
SPR between 158 St and 155 St.
Silva cells for tree pits have been installed on north side of
SPR between 158 St and 155 St.
Dates July 10: EPCOR to complete streetlights to 152 St.
July 12: Contractor to complete all new walk on north side
of SPR between 158 St and 155 St.STONY PLAIN ROAD 3-COLOUR WALK
7/28/2019 City of Edmonton's July 2013 Construction Update
3/3
THE WAY WEMOVE
NEW ARTERIAL PROJECTS
GUARDIAN ROAD/LEWIS ESTATES BOULEVARDActivity EPCOR signal pole relocation.
Installation of mainline sewer from Granville Dr to Whitemud Dr.
Signal installation at Whitemud Dr, Granville Dr, Potter Greens Dr.
Dates Construction began Jul 8.
BRIDGE & INTERCHANGE PROJECTS
23 AVENUE/GATEWAY BOULEVARD
Activity Final 50 mm stone mastic asphalt (SMA) work. Night paving from 8:30 pm-5:30 am Monday to
Friday, 8:30 pm-8:30 am Saturday and Sunday.
Dates Night paving from Jul 22 to Aug 30.
111 STREET/30 AVENUE SW BRIDGE
Activity Bridge deck, approach slabs and barriers poured.
Dates Roadway construction began week of Jun 24.
STONY PLAIN ROAD BRIDGE OVER GROAT ROAD
Activity Stony Plain Road from Connaught Dr to 142 St milling and paving.
ETS Route 398 replaced by on-call shuttle.
Bridge work continues.
Dates Milling and paving on Stony Plain Road done Jul 4-8.
WALTERDALE BRIDGE
Activity Bridge construction work begins mid-July. 2013 work will
include re-grading of south side to accommodate future
realignment of Queen Elizabeth Park Rd and construction
of thrust blocks in river.
Impacts Queen Elizabeth Park Rd closed Jul 15 to Nov 1. Bridge
will remain open throughout construction. Detour using
Walterdale Hill Rd, 99 St/Scona Rd, or 98 Ave/James
MacDonald Bridge. ETS Route 52 will detour using Scona Rd for duration of
project.
Please note that all projected completion dates are weather permitting. Road barricades are in place where required
for public and worker safety. Hazards may be present when workers are not. Permission to use barricades is strictly
enforced. Project details and updates are available at www.edmonton.ca/roadprojects. To view all 2013 construction
go to www.edmonton.ca/constructiononyourstreets
WALTERDALE BRIDGE RIVER BERM