BUYING PLANCITY OF CHICAGO | SISTER AGENCIES | COOK COUNTY | STATE OF ILLINOIS
1Q 2019 – 2Q 2020 CONSTRUCTION SUMMIT EDITION
Department of Procurement Services | City Hall 121 N. LaSalle, Room 806 | Bid & Bond, Room 103 | Chicago, Illinois 60602 | 312-744-4900
W W W . C I T Y O F C H I C A G O . O R G / D P S
This document will be updated periodically and is subject to change without notice.
1
Table of Contents
Contributing Agencies in the Buying Plan ........................................................................................................... 2
How-to Use the Buying Plan Guide .................................................................................................................... 3
Contracting Opportunity Highlights
City of Chicago ................................................................................................................................................... 5
Chicago Board of Elections .............................................................................................................................. 31
City Colleges of Chicago .................................................................................................................................. 32
Chicago Housing Authority ............................................................................................................................... 34
Chicago Park District ....................................................................................................................................... 39
Chicago Public Schools .................................................................................................................................... 40
Chicago Transit Authority ................................................................................................................................. 42
Public Building Commission ............................................................................................................................. 49
Metropolitan Pier and Exposition Authority ....................................................................................................... 50
Cook County of Illinois ...................................................................................................................................... 51
Forest Preserves of Cook County .................................................................................................................... 63
Illinois Tollway .................................................................................................................................................. 70
State of Illinois .................................................................................................................................................. 75
Directory of Assist Agencies ............................................................................................................................ 85
● ● ●
1Q 2019 – 2Q 2020
2
City of Chicago Department of Procurement Services (DPS) ● www.cityofchicago.org/dps DPS is committed to providing information, resources and tools to assist you in your efforts to compete for City of Chicago contracting opportunities. We pledge to work together as a team and with our customers to guarantee an open, fair and timely process by establishing, communicating and enforcing superior business practices.
Chicago Board of Election Commissioners ● www.chicagoelections.com/en/job-and-contractor-opportunities.html Learn about doing business with the Chicago Board of Election, which includes managing voter registrations; safeguarding the rights of all voters to cast ballots independently.
Chicago Housing Authority (CHA) ● www.thecha.org/doing-business Learn about the CHA's Department of Procurement and Contracts and its role and responsibility as it relates to purchasing goods and services for all CHA Departments.
Chicago Park District (CPD) ● http://www.chicagoparkdistrict.com/doing-business Learn more about doing business with the Chicago Park District. Download bids; see list of firms that have downloaded bids; track progress on projects being developed for advertisement; see bid tabulations; view and download contracts; track what happens after bids and proposals are received; and more.
Chicago Public Schools (CPS) ● www.csc.cps.k12.il.us/purchasing Learn how to become a vendor and be eligible to do business with the Chicago Public Schools (CPS).
Chicago Transit Authority (CTA) ● www.transitchicago.com/procurement Learn how to become a vendor and be eligible to do business with the Chicago Transit Authority (CTA).
City Colleges of Chicago (CCC) ● www.ccc.edu/Procurement CCC, its trustee, administrator, and staff welcome all companies-both large and small-to do business with CCC, which operates 7 colleges, 5 vocational/technical centers, 3 community learning centers, and a district office.
Metropolitan Pier & Exposition Authority (MPEA) ● www.mpea.com and www.mccormickplace.com Learn more about doing business with the Metropolitan Pier and Exposition Authority and the McCormick Place.
Public Building Commission (PBC) ● www.pbcchicago.com/content/working The PBC serves as a developer of new and renovated public projects that impact our surrounding areas and facilitate community revitalization.
Cook County of Illinois – Office of the Chief Procurement Officer ● www.cookcountyil.gov/Purchasing Our mission is to procure quality goods and services for Cook County agencies at the best price by promoting competition and implementing best practices. To achieve this goal, the Office of the Chief Procurement Officer is committed to implementing open and transparent procurement methods to promote maximum vendor participation while leveraging overall County volume to achieve lower costs.
Forest Preserves of Cook County ● www.fpdcc.com/about/departments/finance-administration Register as a vendor and learn about current RFPs, RFQs, Contracts, and Quotes.
State of Illinois Chief Procurement Office ● www.purchase.state.il.us State of Illinois Department of Central Management Services ● www.illinois.gov/cms/business/procurement Learn about doing business with the state of Illinois.
Illinois Tollway ● http://www.illinoistollway.com/doing-business Learn about how to do business with the Illinois Tollway.
I N T E R E S T E D I N L E A R N I N G M O R E A B O U T P R O C U R E M E N T & C E R T I F I C AT I O N ?
1Q 2019 DPS WORKSHOP SCHEDULE
PROCUREMENT
Procurement Fundamentals: Doing Business with the CityJAN. 16 | FEB. 27 | MAR. 6: 3:15 PM – 4:15 PM
Building Chicago! Construction Contracting OverviewJAN. 10 | MAR. 7: 2:00 PM – 3:00 PM
Propelling Your Business though Aviation OpportunitiesFEB. 7: 3:30 PM – 4:30 PM
Introduction to eProcurementJAN. 24 | FEB. 21| MAR. 21: 2:00 PM – 3:00 PM
Workforce Development Incentives & ProgramsMAR. 13: 2:00 PM – 3:00 PM
Professional Declaration of Eligibility (PDE)MAR. 27: 2:00 PM – 3:00 PM
Workforce Development Incentives & ProgramsNOV. 7: 2:00 PM – 3:00 PM
CERTIFICATION & COMPLIANCE
How to Become CertifiedJAN. 16 | FEB. 27 | MAR. 6: 2:00 PM – 3:00 PM
The ABC’s of DBE and ACDBE CertificationJAN. 9: 3:15 PM – 4:15 PM
TRANSPARENCY AND COMMUNITY OUTREACH
Working with Assist AgenciesMAR. 20: 3:15 PM – 4:15 PM
How to Navigate the DPS WebsiteJAN. 17: 2:30 PM – 3:30 PM
Goldman Sach's 10,000 Small Business Information SessionMAR. 14: 3:15 PM – 4:15 PM
www.cityofchicago.org/dpsevents
DPS teaches 19 free workshops to educate interested citizens and business owners about the latest developments in procurement and certification. The workshops offered this quarter include:
The City’s key priorities in procurement are creating opportunities for businesses of all sizes, and helping businesses grow so that they can participate in the business of Chicago. The Small Business Initiative (SBI) is exclusive to small businesses and limited to construction projects that are under $3 million in total cost. The Mid-Sized Business Initiative (MBI) is for small and mid-sized local construction firms to bid on construction projects valued between $3 million and $10 million. Expands the SBI I & II construction programs. The Target Market Program promotes contracting opportunities exclusively to businesses that are certified as minority or women-owned business enterprises.. These contracting opportunities are indicted in the Buying Plan by the following highlighting:
SBIMBITarget Market
B U Y I N G P L A N H O W - T O G U I D E
W H A T I S T H E B U Y I N G P L A N ?15 month forecast of hundreds of upcoming opportunities to help businesses plan
Includes City of Chicago and 12 additional government agencies
Info included: buying agency, agency department, contract type, anticipated advertisment date, potential subcontracting opportunities
Directory of Assist Agencies with programs for local, small, minority, and women-owned businesses
W H A T T Y P E S O F C O N T R A C T I N GO P P O R T U N I T I E S A R E A V A I L A B L E ?
Small orders (purchases under $100,000)*
Architecture and Engineering
Vehicles & Heavy EquipmentConstruction
Professional Services Commodities
Work Services
*Small orders amount, purchases under $100,000, are for the City of Chicago and may be different for other agencies participating in the Buying Plan.
S M A L L B U S I N E S S I N I T I AT I V E ( S B I ) & M I D - S I Z E B U S I N E S S I N I T I AT I V E ( M B I )
3
City of Chicago Contracting Opportunities
5
This guide has been prepared for informational purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Animal Care & Control
Commodities RESCUE Animal Disinfectant
$250,001 - $500,000
60 1Q 2019 TBD Non-Federal
Animal Care & Control
Commodities Injectable Microchips $100,001 - $250,000
60 2Q 2019 TBD Non-Federal
Animal Care & Control
Commodities IDEXX Laboratory Testing and Supplies
$250,001 - $500,000
60 3Q 2019 TBD Non-Federal
Animal Care & Control
Commodities Compounded Animal Pharmaceuticals
$100,001 - $250,000
60 3Q 2019 TBD Non-Federal
Animal Care & Control
Work Services
Dead Animal Removal and Cremation
$250,001 - $500,000
36 1Q 2019 TBD Non-Federal
Aviation Commodities
Terminal Seating and Related Furniture for Chicago O'Hare and Midway International Airports
$2,000,001 - $3,000,000
60 1Q 2019 None Non-Federal
Aviation Commodities Tower Ground Two-Way Radios and Related Components
$250,001 - $500,000
60 1Q 2019 None Non-Federal
Aviation Commodities ID Badging Supplies $1,000,001 - $2,000,000
60 1Q 2019 None Non-Federal
Aviation Commodities
Purchase of Automated External Defibrillators (AED) and Associated Support Materials
$250,001 - $500,000
60 1Q 2019 None Non-Federal
Aviation Commodities Bagged Deicing Products $500,001 - $1,000,000
60 2Q 2019 None Non-Federal
Aviation Commodities Carpet Matting $250,001 - $500,000
60 2Q 2019 None Non-Federal
Aviation Construction Ring Tunnel Concrete Priorities 3-9
$10,000,001 - $20,000,000
24 1Q 2019
Laborers, Carpenters, Pipefitters, Electricians, Plumbers, Sheet Metal Workers
Non-Federal
Aviation Construction Replace Passenger and Freight Elevators in H&R Building
$1,000,001 - $2,000,000
6 1Q 2019
Elevator Constructors, Electricians, Laborers, Masons, Painters, Carpenters
Non-Federal
City of Chicago Contracting Opportunities
6
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Aviation Construction Pedestrian Tunnels Improvement
Over $20,000,000
12 1Q 2019 Laborers, Carpenters
Non-Federal
Aviation Construction
O'Hare Residential Sound Insulation Program Phase 17 (167 Historical Homes) Bid Package 3
$5,000,001 - $10,000,000
24 1Q 2019
Carpenters, Laborers, Sheet Metal Workers, Electricians
Federal
Aviation Construction Runway 9R-27L Extension - West
Over $20,000,000
30 1Q 2019
Laborers, Equipment Operators, Carpenters, Truck Drivers, Cement Masons
Federal
Aviation Construction Recirculation Bridge Reconstruction
$3,000,001 - $5,000,000
12 1Q 2019 Laborers, Carpenters, Ironworkers
Non-Federal
Aviation Construction Leak Repairs to B & C Tunnel
$10,000,001 - $20,000,000
24 1Q 2019 Laborers, Carpenters
Non-Federal
Aviation Construction Midway Terminal Ramp Improvements
$10,000,001 - $20,000,000
12 1Q 2019
Laborers, Carpenters, Ironworkers, Equipment Operators, Cement Masons
Federal
Aviation Construction O'Hare Relocation of Taxiways A and B East/West Advance Work
Over $20,000,000
24 1Q 2019
Laborers, Carpenters, Ironworkers, Equipment Operators, Cement Masons
Federal
Aviation Construction
RFQ for O'Hare South Airfield Retention Consolidation Design-Build
Over $20,000,000
24 1Q 2019
Laborers, Carpenters, Ironworkers, Equipment Operators, Cement Masons
Non-Federal
Aviation Construction O'Hare Demolition of Building 519
$250,001 - $500,000
2 1Q 2019 Demolition Laborers, Truck Drivers
Non-Federal
Aviation Construction Taxiway A & B Bridge Heating System Upgrades
$2,000,001 - $3,000,000
6 1Q 2019
Laborers, Pipefitters, Equipment Operators, Cement Masons
Non-Federal
Aviation Construction
Landside Fire Main Replacement - Lower Level Utility and Pavement Reconstruction
Over $20,000,000
24 1Q 2020
Laborers, Electricians, Plumbers, Equipment Operators, Carpenters
Non-Federal
Aviation Construction Rotunda Air Handling Units
$10,000,001 - $20,000,000
24 2Q 2019
Laborers, Pipefitters, Electricians, Sheet Metal Workers
Non-Federal
City of Chicago Contracting Opportunities
7
This guide has been prepared for informational purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department
Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Aviation Construction Elevated Parking Structure Repairs
$10,000,001 - $20,000,000
24 2Q 2019 Laborers, Carpenters, Ironworkers
Non-Federal
Aviation Construction
O'Hare Residential Sound Insulation Program Phase 18A (250 Homes)
$5,000,001 - $10,000,000
24 2Q 2019
Carpenters, Laborers, Sheet Metal Workers, Electricians
Federal
Aviation Construction 90" JAWA Relocation $10,000,001 - $20,000,000
12 2Q 2020
Laborers, Pipefitters, Equipment Operators
Non-Federal
Aviation Construction Runway 9R-27L Extension - East
Over $20,000,000
24 3Q 2019
Laborers, Equipment Operators, Carpenters, Truck Drivers, Cement Masons
Federal
Aviation Construction
O'Hare Residential Sound Insulation Program Phase 18B (280 Homes)
$5,000,001 - $10,000,000
24 3Q 2019
Carpenters, Laborers, Sheet Metal Workers, Electricians
Federal
Aviation Construction - MBI-1
Ring Tunnel Exhaust System
$10,000,001 - $20,000,000
24 2Q 2020
Pipefitters, Electricians, Laborers, Sheet Metal Workers
Non-Federal
Aviation Construction - MBI-1
O'Hare Runway 4R-22L Rehabilitation
$10,000,001 - $20,000,000
24 4Q 2019
Laborers, Carpenters, Ironworkers, Equipment Operators, Cement Masons
Non-Federal
Aviation Construction - MBI-2
I-190 Lift Station Replacement
$3,000,001 - $5,000,000
5 1Q 2019
Pipefitters, Electricians, Laborers, Carpenters, Equipment Operators
Non-Federal
Aviation Construction - MBI-2
Spine Road Airside Relocation
$5,000,001 - $10,000,000
12 1Q 2020
Laborers, Equipment Operators, Cement Masons
Non-Federal
Aviation Construction - MBI-2
Incident Management Center (IMC) & AOC Renovations
$1,000,001 - $2,000,000
6 2Q 2019
Carpenters, Painters, Laborers, Electricians
Non-Federal
Aviation Construction - MBI-2
Terminal Core Upper Level Expansion Joints and Sidewalks
$3,000,001 - $5,000,000
12 3Q 2020 Laborers Non-Federal
Aviation Construction - SBI I
Baggage Service Road Retaining Wall Repair
$2,000,001 - $3,000,000
8 1Q 2019
Laborers, Carpenters, Equipment Operators, Painters
Non-Federal
Aviation Construction - SBI I
Water Main Automatic Meter Readers
$2,000,001 - $3,000,000
6 1Q 2020 Pipefitters, Electricians, Plumbers
Non-Federal
City of Chicago Contracting Opportunities
8
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Aviation Construction - SBI I
Terminal Building AOA $3,000,001 - $5,000,000
12 2Q 2020 Carpenters, Laborers
Non-Federal
Aviation Construction - SBI I
Terminal Domestic Water Infrastructure Improvements T1, B & C
$2,000,001 - $3,000,000
12 3Q 2020 Plumbers Non-Federal
Aviation Construction - SBI I
Fire Hydrant & Backflow Prevention Improvements
$2,000,001 - $3,000,000
6 3Q 2020 Plumbers, Equipment Operators
Non-Federal
Aviation Construction - SBI I
O'Hare H&R Plant Life Safety System & Fire Alarm System
$3,000,001 - $5,000,000
12 4Q 2019 Electricians Non-Federal
Aviation Construction - SBI II
T1 B/C Terminal Apron Level Exterior Repairs
$1,000,001 - $2,000,000
6 3Q 2020
Carpenters, Laborers, Equipment Operators, Cement Masons
Non-Federal
Aviation Construction - SBI II
Domestic Water Pump Control Upgrades at H&R Building
$1,000,001 - $2,000,000
6 3Q 2020 Plumbers, Electricians
Non-Federal
Aviation Construction - SBI II
Terminal Apron Level Overhead Roll-Up Door Replacement T1 B & C
$1,000,001 - $2,000,000
6 3Q 2020 Laborers, Carpenters, Electricians
Non-Federal
Aviation Professional Services
RFP for Concessions Management Services at O'Hare International Airport
Over $20,000,000
60 1Q 2019 TBD Non-Federal
Aviation Professional Services
RFQ for Lead Engineering for Terminal Area Plan and Tunnel for O'Hare 21 Program
Over $20,000,000
96 1Q 2019 TBD Non-Federal
Aviation Professional Services
Electronic Logging System at O'Hare and Midway International Airports
$250,001 - $500,000
60 1Q 2019 TBD Non-Federal
Aviation Professional Services
Management of Public Parking Facilities and Ground Transportation at Chicago O'Hare International Airport
Over $20,000,000
120 1Q 2019
Carpenters, Electricians, Painters, Plumbers, Janitors, Security Guards
Non-Federal
Aviation Professional Services
RFP for Aviation Planning Services
Over $20,000,000
60 1Q 2019 TBD Non-Federal
Aviation Professional Services
Management of Public Parking Facilities and Ground Transportation at Chicago Midway International Airport
Over $20,000,000
60 1Q 2019 TBD Non-Federal
Aviation Professional Services
RFP for Terminal 5 Property Management
Over $20,000,000
60 1Q 2019 TBD Non-Federal
Aviation Professional Services
Environmental Consulting Services
TBD 60 1Q 2019 TBD Non-Federal
City of Chicago Contracting Opportunities
9
This guide has been prepared for informational purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department
Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Aviation Professional Services
RFQ for Target Market Construction Management Services (Non-Federal)
Over $20,000,000
60 2Q 2019 TBD Non-Federal
Aviation Professional Services
RFQ for Construction Management Services (Non-Federal)
Over $20,000,000
60 2Q 2019 TBD Non-Federal
Aviation Work Services
Airport Maintenance Over $20,000,000
60 1Q 2019 TBD Non-Federal
Aviation Work Services
Fire Extinguisher Services and Fire Suppression System Services
$500,001 - $1,000,000
60 1Q 2019 Technicians, Sprinkler Fitters
Non-Federal
Aviation Work Services
Airside Snow Removal at O'Hare International Airport
$5,000,001 - $10,000,000
60 1Q 2019 Equipment Operators, Truck Drivers
Non-Federal
Aviation Work Services
Grazing Herd Services $250,001 - $500,000
60 1Q 2019 None Non-Federal
Aviation Work Services
Removal of Rubber and Other Contaminants from Runways and Other Pavements at O'Hare and Midway International Airports
$2,000,001 - $3,000,000
60 1Q 2019 Truck Drivers, Operating Engineers
Non-Federal
Aviation Work Services
Airside Ramp Replacement and Concrete Crushing
Over $20,000,000
60 1Q 2019
Truck Drivers, Cement Masons, Laborers, Equipment Operators
Non-Federal
Aviation Work Services
Airside Concrete Repair and Replacement
$5,000,001 - $10,000,000
60 1Q 2019 Truck Drivers, Cement Masons, Laborers
Non-Federal
Aviation Work Services
Meteorological Services $250,001 - $500,000
60 1Q 2019 None Non-Federal
Aviation Work Services
Target Market - Unarmed Security Guard Services for O'Hare and Midway International Airports
Over $20,000,000
60 1Q 2019 Security Guards Non-Federal
Aviation Work Services
Shuttle Bus Services at O'Hare International Airport
Over $20,000,000
120 1Q 2019 TBD Non-Federal
Aviation Work Services
Purchase of New Paint Sprayers, Pressure Washers, Related Parts, Accessories, Equipment, Supplies and Repair Services
$500,001 - $1,000,000
60 1Q 2019 Technicians Non-Federal
Aviation Work Services
Purchase, Calibration, Maintenance, Repair, Parts and Training for Runway Friction Testing Equipment
$250,001 - $500,000
60 1Q 2019 TBD Non-Federal
City of Chicago Contracting Opportunities
10
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Aviation Work Services
Maintenance of Automated External Defibrillator (AED) Program and Automated Training in AED, Cardiopulmonary Resuscitation (CPR), First Aid and Public Safety Dispatch
$2,000,001 - $3,000,000
60 1Q 2019 TBD Non-Federal
Business Affairs & Consumer Protection
Commodities Motor Vehicle Tax License Plates (Medallions)
$250,001 - $500,000
60 1Q 2019 No Stated Goals Non-Federal
Business Affairs & Consumer Protection
Professional Services
Tobacco Sales to Minors Prevention Program (Youth Personnel Services)
$500,001 - $1,000,000
60 1Q 2019 No Stated Goals Non-Federal
Business Affairs & Consumer Protection
Work Services
Mobile On-Site Shredding Services for the Small Business Center on the Road Expos!
Under $10,000
36 1Q 2019 M/WBE Non-Federal
Business Affairs & Consumer Protection
Work Services
Shredder Repair and Maintenance
Under $10,000
36 1Q 2019 No Stated Goals Non-Federal
Cultural Affairs and Special Events
Professional Services
Seating Ticket Sales and Marketing for Taste of Chicago
$100,001 - $250,000
36 2Q 2019 Parts, Labor and Transportation
Non-Federal
Cultural Affairs and Special Events
Small Orders Beekeeping Services $50,001 - $100,000
36 3Q 2019
Insurance Provider, Financial Services, Employee Benefits Program
Non-Federal
Cultural Affairs and Special Events
Small Orders Tyvek & Plastic Wristbands
Under $10,000
36 4Q 2019 No Stated Goals Non-Federal
Cultural Affairs and Special Events
Work Services
Sound Equipment Rental for City Festivals and Events
$2,000,001 - $3,000,000
60 1Q 2019
Insurance Provider, Financial Services, Employee Benefits Program
Non-Federal
Cultural Affairs and Special Events
Work Services
Rental Support of Equipment and Supplies for City Festivals and Events
$1,000,001 - $2,000,000
60 1Q 2019
Insurance Provider, Financial Services, Employee Benefits Program
Non-Federal
City of Chicago Contracting Opportunities
11
This guide has been prepared for informational purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department
Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Cultural Affairs and Special Events
Work Services
Rental of Tents for City Festivals and Events
$1,000,001 - $2,000,000
60 1Q 2019
Insurance Provider, Financial Services, Employee Benefits Program
Non-Federal
Cultural Affairs and Special Events
Work Services
Custom Signs and Banner Printing, Installation and Repair
$500,001 - $1,000,000
60 1Q 2019 vehicles Non-Federal
Cultural Affairs and Special Events
Work Services
Maintenance Services for City Festivals
$3,000,001 - $5,000,000
60 2Q 2019
Insurance Provider, Financial Services, Employee Benefits Program
Non-Federal
Cultural Affairs and Special Events
Work Services
Printing of Brochure $250,001 - $500,000
60 2Q 2019
Insurance Provider, Financial Services, Employee Benefits Program, On-site Labor
Non-Federal
Cultural Affairs and Special Events
Work Services
Ground Transportation Services
$250,001 - $500,000
60 2Q 2019
Insurance Provider, Financial Services, Employee Benefits Program
Non-Federal
Cultural Affairs and Special Events
Work Services
Fixed Base Operator for Air & Water Show
$250,001 - $500,000
60 2Q 2019
Insurance Provider, Financial Services, Employee Benefits Program
Non-Federal
Family Support Services
Commodities Purchase of Commercial Appliances
$500,001 - $1,000,000
60 1Q 2019 Delivery, Supplies
TBD
Family Support Services
Professional Services
Safe Environment and Facilities Management for Head Start Program
$1,000,001 - $2,000,000
84 3Q 2019 Professional Services
TBD
Family Support Services
Small Orders Starter Kits Under $10,000
60 2Q 2019 Delivery, Supplies
TBD
Family Support Services
Work Services
Maintenance of Commercial Appliances
$50,001 - $100,000
60 1Q 2019 Labor TBD
Finance Commodities Consumable and Durable Cash Management Supplies and Equipment
$50,001 - $100,000
60 1Q 2019 No Stated Goals Non-Federal
City of Chicago Contracting Opportunities
12
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Finance Professional Services
Accounts Payable Audit Recovery Services
Revenue Generating
60 1Q 2019 No Stated Goals Non-Federal
Finance Professional Services
Employee Wellness Program Administration
$10,000,001 - $20,000,000
60 1Q 2019 TBD Non-Federal
Finance Professional Services
Printing of Cigarette Tax Stamps
$3,000,001 - $5,000,000
60 1Q 2019 No Stated Goals Non-Federal
Finance Professional Services
Armored Car Services $3,000,001 - $5,000,000
60 1Q 2019 No Stated Goals Non-Federal
Finance Professional Services
Insurance Brokerage Services and Administration of an Owner Controlled Insurance Program (OCIP) for O'Hare Airport Construction Projects
$3,000,001 - $5,000,000
60 1Q 2019 TBD Non-Federal
Finance Professional Services
Vehicle Immobilization Devices and Locks (RFP)
$3,000,001 - $5,000,000
60 1Q 2019 TBD Non-Federal
Finance Professional Services
Benefits Management Consulting Services
$3,000,001 - $5,000,000
60 2Q 2019 Accountants, Financial Auditors
Non-Federal
Finance Professional Services
Insurance Brokerage and Consulting Services
$3,000,001 - $5,000,000
60 2Q 2019 TBD Non-Federal
Finance Professional Services
Cost Allocation and Indirect Cost
$3,000,001 - $5,000,000
60 2Q 2019 TBD Non-Federal
Finance Professional Services
Financial Services - Request for Qualifications (RFQ)
$3,000,001 - $5,000,000
60 2Q 2019 TBD Non-Federal
Finance Professional Services
Target Market - Secured Printing of Various Specialty Items
$50,001 - $100,000
60 2Q 2019 Target Market Non-Federal
Finance Work Services
Bicycle Repair Services $50,001 - $100,000
60 2Q 2019 No Stated Goals Non-Federal
Fire Commodities Thermal Imaging Cameras
$250,001 - $500,000
60 1Q 2019 No Stated Goals Non-Federal
Fire Commodities
Hurst Tools, New, Parts, Accessories and Supplies for Hurst Hydraulic Rescue Tools
$2,000,001 - $3,000,000
60 2Q 2019 No Stated Goals Non-Federal
Fire Commodities Safety and Technical Rescue Equipment
$10,000,001 - $20,000,000
60 3Q 2019 No Stated Goals Mixed
City of Chicago Contracting Opportunities
13
This guide has been prepared for informational purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department
Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Fire Commodities Uniforms and Commissary Related Services
$10,000,001 - $20,000,000
60 3Q 2019 TBD Non-Federal
Fire Commodities
CBRN Detection and ID Related Equipment - New Parts, Supplies and Repairs
$1,000,001 - $2,000,000
60 3Q 2019 No Stated Goals Mixed
Fire Small Orders Test Scoring Equipment & Supplies
$10,001 - $50,000
36 1Q 2019 No Stated Goals Non-Federal
Fire Small Orders Maintenance & Repair of Kardex Lectriever Automated Filing System
Under $10,000
24 2Q 2019 No Stated Goals Non-Federal
Fleet & Facility Management
Commodities Office Supplies and Related Services
$10,000,001 - $20,000,000
60 1Q 2019 Material Supplies, Trucking
Non-Federal
Fleet & Facility Management
Commodities Laminating Supplies $500,001 - $1,000,000
60 1Q 2019 No Stated Goals Non-Federal
Fleet & Facility Management
Commodities Framing Board and Lumber
$1,000,001 - $5,000,000
60 1Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Commodities HVAC Parts $5,000,001 - $10,000,000
60 2Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Professional Services
Vehicle & Parts Management & Supply
Over $20,000,000
60 2Q 2019 Delivery, Parts and Labor
Non-Federal
Fleet & Facility Management
Small Orders Ricoh Format Printer Ink Supplies
$10,001 - $50,000
36 1Q 2019 No Stated Goals Non-Federal
Fleet & Facility Management
Small Orders Data Photocard Laminating Color Card Printer w/Parts & Service
$50,001 - $100,000
36 2Q 2019 No Stated Goals Non-Federal
Fleet & Facility Management
Small Orders Window Air Conditioning Units
$10,001 - $50,000
36 2Q 2019 No Stated Goals Non-Federal
Fleet & Facility Management
Small Orders Safety Lane Inspections $50,001 - $100,000
36 3Q 2019 No Stated Goals Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
Vacuum Jet Rodder Truck
$5,000,001 - $10,000,000
60 1Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
Multipurpose Utility Vehicles
$5,000,001 - $10,000,000
60 1Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
Pick Up Trucks $3,000,001 - $5,000,000
60 1Q 2019 Parts, Labor and Transportation
Non-Federal
City of Chicago Contracting Opportunities
14
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Fleet & Facility Management
Vehicles & Heavy Equipment
Truck Mounted Attenuator
$1,000,001 - $5,000,000
60 1Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
3 Wheel Street Sweepers Over $20,000,000
60 1Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
Truck Tractor Trailers $10,000,001 - $20,000,000
60 2Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
Backhoe Loader $5,000,001 - $10,000,000
60 2Q 2019 Parts, Repair, Labor
Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
Lift Trucks, Scissor Lifts and Pallet Jacks
$3,000,001 - $5,000,000
60 2Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
Brush Chipper $500,001 - $1,000,000
60 2Q 2019 No Stated Goals Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
Forestry Aerial Trucks $5,000,001 - $10,000,000
60 3Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
Police Vehicles - Prisoner Squadrols
$3,000,001 - $5,000,000
60 3Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
4x2 Diesel Powered Cab/Chassis w/Platform Bodies and Log Grapples
$3,000,001 - $5,000,000
60 3Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
Deckover Trailers $250,001 - $500,000
60 3Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
Portable Gasoline Powered Generators
$100,001 - $250,000
60 3Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Vehicles & Heavy Equipment
Ambulances $10,000,001 - $20,000,000
60 4Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Work Services
HVAC Maintenance $5,000,001 - $10,000,000
60 1Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Work Services
Car Wash Services $2,000,001 - $3,000,000
60 1Q 2019 No Stated Goals Non-Federal
Fleet & Facility Management
Work Services
Car Sharing $500,001 - $1,000,000
60 1Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Work Services
Emergency Road Tire Service
$250,001 - $500,000
36 1Q 2019 Parts, Labor and Transportation
Non-Federal
City of Chicago Contracting Opportunities
15
This guide has been prepared for informational purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department
Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Fleet & Facility Management
Work Services
Architectural Metal Maintenance
$100,001 - $250,000
60 1Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Work Services
Rental of Heavy Equipment with and Without Operators
$10,000,001 - $20,000,000
60 2Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Work Services
Parts and Service Heavy Machinery and Snow Equipment
$10,000,001 - $20,000,000
60 2Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Work Services
Repair and Maintenance of Elevators, Dumbwaiters, Wheelchair Lifts and Related Equipment
$5,000,001 - $10,000,000
60 2Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Work Services
Repair, Replacement and Maintenance of Various Doors and Motors: Overhead, Revolving, Security, Handicapped and Monumental Entry Doors
$5,000,001 - $10,000,000
60 2Q 2019 Parts, Labor and Transportation
Non-Federal
Fleet & Facility Management
Work Services
Fleet Equipment and Management Services
$5,000,001 - $10,000,000
60 3Q 2019 Parts, Labor and Transportation
Non-Federal
Human Resources
Professional Services
Professional Unemployment Claims Administration
$1,000,001 - $2,000,000
60 1Q 2019 TBD Non-Federal
Human Resources
Professional Services
Background Screening Services
$500,001 - $1,000,000
60 1Q 2019 TBD Non-Federal
Human Resources
Professional Services
Temporary Clerical Personnel Services
$500,001 - $1,000,000
60 2Q 2019 TBD Non-Federal
Human Resources
Small Orders Kardveyer Machine Maintenance
Under $10,000
36 1Q 2019 TBD Non-Federal
Innovation and Technology
Information & Technology
Enterprise Broadband Services
TBD 60 1Q 2019 IT Services Non-Federal
Innovation and Technology
Information & Technology
Enterprise Voice and Private Data Services
TBD 60 1Q 2019 IT Services Non-Federal
Innovation and Technology
Information & Technology
Cellular and Wireless Communication Services
TBD 60 1Q 2019 IT Services Non-Federal
Innovation and Technology
Information & Technology
Computer Hardware, Software, Peripherals, Cloud Services and Related Maintenance and Installation Services
TBD 60 1Q 2019 IT Services Non-Federal
Innovation and Technology
Information & Technology
Web Application, Hosting, Middleware and Environment Support
TBD 60 1Q 2019 Professional Services
Non-Federal
City of Chicago Contracting Opportunities
16
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Innovation and Technology
Information & Technology
Non-Target Market IT Professional Services
TBD 60 1Q 2019 Professional Services
Non-Federal
Innovation and Technology
Information & Technology
E-Plan Maintenance and Support
TBD 60 2Q 2019 Professional Services
Non-Federal
Innovation and Technology
Information & Technology
Utility Billing Integrative Voice Response (IVR) and Full Payment Certificate Maintenance and Support
TBD 60 2Q 2019 Professional Services
Non-Federal
Innovation and Technology
Information & Technology
Hansen Application Maintenance and Support
TBD 60 2Q 2019 Professional Services
Non-Federal
Innovation and Technology
Information & Technology
Water Management/Utility Customer Service, Selling and Information System Maintenance and Support
TBD 60 2Q 2019 Professional Services
Non-Federal
Innovation and Technology
Information & Technology
Consolidated Application Support for Enterprise Applications
TBD 60 TBD Professional Services
Non-Federal
Innovation and Technology
Information & Technology
Target Market Professional Services
TBD 60 TBD Professional Services
Non-Federal
OEMC Commodities Various Communication Cable: Underground & Aerial
$3,000,001 - $5,000,000
60 1Q 2019 Delivery Non-Federal
OEMC Professional Services
FCC Frequency Coordinator
$1,000,001 - $2,000,000
60 3Q 2019 Professional Consulting Services
Mixed
OEMC Professional Services
Camera Infrastructure Program
$2,000,001 - $3,000,000
60 3Q 2019 Security Camera Maintenance
Mixed
OEMC Professional Services
Next Gen 9-1-1 Network $2,000,001 - $3,000,000
60 3Q 2019
Maintenance, installation, accounting, training
Mixed
OEMC Work Services
Portable and Fixed Bollards and Barriers
$2,000,001 - $3,000,000
60 1Q 2019 Delivery, Parts and Labor
Mixed
OEMC Work Services
Portable Gas Generators, Pumps, Replacement Parts, and Maintenance
$250,001 - $500,000
60 1Q 2019 Delivery, Parts and Labor
Non-Federal
OEMC Work Services
Public Alert Weather Siren Construction, Repair and Maintenance
$3,000,001 - $5,000,000
60 3Q 2019 Delivery, Parts and Labor
Mixed
Office of the City Clerk
Professional Services
Digital Daily Parking Permits
TBD 24 TBD TBD Non-Federal
City of Chicago Contracting Opportunities
17
This guide has been prepared for informational purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department
Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Office of the City Clerk
Professional Services
Sales of vehicle sticker emblems
$3,000,001 - $5,000,000
60 TBD TBD Non-Federal
Office of the City Clerk
Professional Services
Printing of vehicle stickers emblems, residential parking passes and related items
$1,000,001 - $2,000,000
60 TBD TBD Non-Federal
Office of the City Clerk
Professional Services
Legislative Management Software
$250,001 - $500,000
24 TBD TBD Non-Federal
Planning & Development
JOC Roof and Porch Repair $2,000,001 - $3,000,000
36 2Q 2019
Emergency Small Repair and Construction Jobs
Federal
Planning & Development
JOC Emergency Heating Repair
$500,001 - $1,000,000
36 2Q 2019
Emergency Small Repair and Construction Jobs
Federal
Planning & Development
Professional Services
Long Term Monitoring and Compliance
$250,001 - $500,000
24 1Q 2019 Professional Consulting Services
Mixed
Planning & Development
Small Orders Property Survey Consulting Services
$10,001 - $50,000
TBD TBD Professional Consulting Services
Non-Federal
Police Commodities Body Armor, Tactical, Technical, and Protective Gear
$5,000,001 - $10,000,000
TBD 1Q 2019 TBD Non-Federal
Police Commodities Veterinarian Services $500,001 - $1,000,000
TBD 1Q 2019 TBD Non-Federal
Police Commodities Horse Feed and Miscellaneous Items
$500,001 - $1,000,000
TBD 1Q 2019 TBD Non-Federal
Police Commodities Firearm & Firearm Accessories
$500,001 - $1,000,000
TBD 1Q 2019 TBD Non-Federal
Public Health Commodities Pharmacy Services $3,000,001 - $5,000,000
60 3Q 2019 Delivery Mixed
Public Health Professional Services
Restaurant Management Certification and recertification
$500,001 - $1,000,000
60 1Q 2019 No Stated Goals Non-Federal
Public Health Professional Services
Mental Health Billing Services
$100,001 - $250,000
36 2Q 2019 No Stated Goals Non-Federal
Public Health Professional Services
STD Clinic lab services $2,000,001 - $3,000,000
60 4Q 2019 No Stated Goals Non-Federal
Public Health Professional Services
Comprehensive Emergency Management Program (CEMP)
$1,000,001 - $2,000,000
60 4Q 2019 Professional Services
Federal
City of Chicago Contracting Opportunities
18
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Public Health Small Orders Infectious medical waste pick up and disposal
$50,001 - $100,000
24 1Q 2019 Parts, Labor and Transportation
Mixed
Public Health Small Orders T-SPOT - TB blood test $10,001 - $50,000
24 1Q 2019 No Stated Goals Federal
Public Health Small Orders Radiation Leak Testing Kits and reading services
Under $10,000
24 1Q 2019 No Stated Goals Non-Federal
Public Health Small Orders Radiation Badges -Dosimeters
Under $10,000
24 1Q 2019 No Stated Goals Non-Federal
Public Health Small Orders Purchase of X-ray fluorescent (XRF) machines
$50,001 - $100,000
36 2Q 2019 No Stated Goals Non-Federal
Public Health Work Services
LPA-1 radiation spectrum maintenance and repair
$100,001 - $250,000
60 2Q 2019 No Stated Goals Federal
Public Health Work Services
Purchase digital data logger (DDL) thermometers and calibration service
$2,000,001 - $3,000,000
60 4Q 2019 Delivery and Parts
Federal
Public Library Commodities Archival Management Tool
$100,001 - $250,000
60 2Q 2019 No Stated Goals Non-Federal
Public Library Professional Services
Digitization Services $500,001 - $1,000,000
60 2Q 2019 TBD TBD
Streets and Sanitation
Aviation Meteorological Services $100,001 - $250,000
60 2Q 2019 No Stated Goals Mixed
Streets and Sanitation
Commodities Mobile Refuse (Black) Carts & (Blue) Carts
$5,000,001 - $10,000,000
36 1Q 2019 Delivery Non-Federal
Streets and Sanitation
Commodities Safety Shoe Service (Mobile and Mail Order)
$500,001 - $1,000,000
36 1Q 2019 No Stated Goals Non-Federal
Streets and Sanitation
Commodities 8ft 16 Gauge Steel Barriers and Replacement Parts
$100,001 - $250,000
36 3Q 2019 TBD Non-Federal
Streets and Sanitation
Commodities Purchase of De-icer Plant Based Accelerator
$100,001 - $250,000
24 3Q 2019 No Stated Goals Non-Federal
Streets and Sanitation
Commodities Purchase of De-icer Organic Based Accelerator
$100,001 - $250,000
24 3Q 2019 No Stated Goals Non-Federal
Streets and Sanitation
Vehicles & Heavy Equipment
Mobile Office Trailer Rental
$250,001 - $500,000
60 1Q 2019 No Stated Goals Non-Federal
City of Chicago Contracting Opportunities
19
This guide has been prepared for informational purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department
Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Streets and Sanitation
Work Services
Target Market - Weed Cutting Services
$5,000,001 - $10,000,000
36 1Q 2019 Target Market Non-Federal
Streets and Sanitation
Work Services
Target Market - Tree Stump and Debris Removal Services
$2,000,001 - $3,000,000
36 1Q 2019 Target Market Non-Federal
Streets and Sanitation
Work Services
Privately Owned Transfer Station Services
Over $20,000,000
60 1Q 2019 Transportation Non-Federal
Streets and Sanitation
Work Services
Management and Operation of City Owned Transfer Stations
Over $20,000,000
60 1Q 2019 Transportation Non-Federal
Streets and Sanitation
Work Services
Pressure Washing Services
$500,001 - $1,000,000
36 2Q 2019 No Stated Goals Non-Federal
Streets and Sanitation
Work Services
Emergency Rental of Heavy Duty Snow Equipment with Operators
$100,001 - $250,000
60 2Q 2019 No Stated Goals Non-Federal
Streets and Sanitation
Work Services
Crime Deterrent System $100,001 - $250,000
36 2Q 2019 No Stated Goals Non-Federal
Streets and Sanitation
Work Services
Salt Pile Tarpaulin Covering and Installation
$2,000,001 - $3,000,000
36 2Q 2020 No Stated Goals Non-Federal
Streets and Sanitation
Work Services
Roll Off Box Services $250,001 - $500,000
60 4Q 2019 No Stated Goals Non-Federal
Transportation Architecture & Engineering
Engineering Services for Highway/Road
$3,000,001 - $5,000,000
60 1Q 2019 Design Engineering
Mixed
Transportation Architecture & Engineering
Harrison Street Viaduct, Phase III
$1,000,001 - $2,000,000
24 1Q 2019
Construction Engineering, Electrical Contracting
Non-Federal
Transportation Architecture & Engineering
Water Street Viaduct: Stetson to Beaubien, Phase III
$1,000,001 - $2,000,000
24 1Q 2019 Design Engineering
Federal
Transportation Architecture & Engineering
Lake Street Bascule Bridge over the Chicago River Phase I
$1,000,001 - $2,000,000
12 1Q 2019 Design Engineering
Non-Federal
Transportation Architecture & Engineering
Traffic Signal Interconnect - Wireless Communication
$1,000,001 - $2,000,000
24 1Q 2019 Design Engineering
Federal
Transportation Architecture & Engineering
Chicago Advisory Systems (Congestion, Truck Route, Detour)
$1,000,001 - $2,000,000
24 1Q 2019 Design Engineering
Federal
Transportation Architecture & Engineering
Grand - Ogden to Jefferson
$1,000,001 - $2,000,000
24 1Q 2019 Design Engineering
Federal
City of Chicago Contracting Opportunities
20
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Transportation Architecture & Engineering
North Avenue - Up Viaduct
$500,001 - $1,000,000
24 1Q 2019 Design Engineering
Federal
Transportation Architecture & Engineering
HSIP Chicago Avenue $250,001 - $500,000
24 1Q 2019 Design Engineering
Federal
Transportation Architecture & Engineering
HSIP Pedestrian Safety Projects (63rd, 79th & Madison)
$100,001 - $250,000
12 1Q 2019 Design Engineering
Federal
Transportation Architecture & Engineering
100th Street Bascule Bridge over the Calumet River, Phase I
$1,000,001 - $2,000,000
12 2Q 2019 Design Engineering
Federal
Transportation Architecture & Engineering
92nd Street Bascule Bridge over the Calumet River, Phase I
$1,000,001 - $2,000,000
12 2Q 2019 Design Engineering
Federal
Transportation Architecture & Engineering
Webster Street Bascule Bridge, Phase III
$1,000,001 - $2,000,000
24 2Q 2019
Construction Engineering, Electrical Contracting
Non-Federal
Transportation Architecture & Engineering
Cortland Street Bascule Bridge, Phase III
$1,000,001 - $2,000,000
24 2Q 2019 Design Engineering
Non-Federal
Transportation Architecture & Engineering
Canal Street: Harrison to Taylor, Phase II
$1,000,001 - $2,000,000
24 2Q 2019 Design Engineering
Non-Federal
Transportation Architecture & Engineering
Streets for Cycling #5 - 2 (Phase I/II Engineering Services)
$1,000,001 - $2,000,000
24 2Q 2019 Design Engineering
Federal
Transportation Architecture & Engineering
Professional Engineering Services for the Arterial Resurfacing Program
$2,000,001 - $3,000,000
48 2Q 2019 Design Engineering
Federal
Transportation Architecture & Engineering
Pedestrian Crash Corridor Improvements on State Routes
$500,001 - $1,000,000
24 2Q 2019 Design Engineering
Federal
Transportation Commodities Non-fabricated Steel $5,000,001 - $10,000,000
60 1Q 2019 Material Supplies, Trucking
Non-Federal
Transportation Commodities
Asphalt Primers, Hot Mix Asphalt, Warm Mix Asphalt, High Performance Cold Patch, Standard Cold Patch, and Hot Pour Joint Sealer Materials
Over $20,000,000
60 1Q 2019 Material Supplies, Trucking
Non-Federal
Transportation Commodities Sign Making Equipment and Supplies
$500,001 - $1,000,000
60 2Q 2019 TBD Non-Federal
Transportation Commodities Speed Bumps $500,001 - $1,000,000
60 3Q 2019 TBD Non-Federal
City of Chicago Contracting Opportunities
21
This guide has been prepared for informational purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department
Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Transportation Construction 31st Street Bridge over Metra and CN RR Reconstruction
$10,000,001 - $20,000,000
12 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Ironworkers, Plumbers, Electricians, Landscapers
Federal
Transportation Construction Traffic Signal Modernization (Various Locations)
$10,000,001 - $20,000,000
TBD 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Ironworkers, Plumbers, Electricians, Landscapers
Non-Federal
Transportation Construction
South Water Street Viaduct - Beaubien Court to Stetson Avenue Viaduct Rehabilitation
$10,000,001 - $20,000,000
12 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Ironworkers, Plumbers, Electricians, Landscapers
Federal
Transportation Construction
Lake Street Bascule Bridge over the South Branch of the Chicago River Structural Repairs
$3,000,001 - $5,000,000
12 1Q 2019 Ironworkers Non-Federal
Transportation Construction Safe Routes to School $1,000,001 - $2,000,000
12 1Q 2019
Concrete, Pavement Marking, Landscape
Federal
Transportation Construction Cicero / Midway Smart Corridor - Phase III Implementation
$2,000,001 - $3,000,000
24 1Q 2019
Construction Engineering, Electrical Contracting
Federal
Transportation Construction Northcenter Town Square
$1,000,001 - $2,000,000
12 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Non-Federal
City of Chicago Contracting Opportunities
22
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Transportation Construction Wells / Wentworth Connector - Section 3 Improvements
Over $20,000,000
24 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Ironworkers, Plumbers, Electricians, Landscapers
Non-Federal
Transportation Construction 43rd Street Pedestrian Bridge over Lake Shore Drive
Over $20,000,000
24 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Federal
Transportation Construction Arterial Resurfacing 2019 - North Area
$5,000,001 - $10,000,000
12 2Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Federal
Transportation Construction Arterial Resurfacing 2019 - Central Area
$5,000,001 - $10,000,000
12 2Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Federal
Transportation Construction Arterial Resurfacing 2019 - South Area
$5,000,001 - $10,000,000
12 2Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Federal
Transportation Construction Arterial Resurfacing 2019 - Far South Area
$5,000,001 - $10,000,000
12 2Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Federal
City of Chicago Contracting Opportunities
23
This guide has been prepared for informational purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department
Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Transportation Construction ADA Ramp Improvements No. 56 and 60 - Central Area
$5,000,001 - $10,000,000
12 2Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Federal
Transportation Construction Loomis Street over the Chicago River Bridge Rehabilitation
$5,000,001 - $10,000,000
12 2Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Ironworkers, Plumbers, Electricians, Landscapers
Non-Federal
Transportation Construction Bridge and Viaduct Painting - Contract #8
$1,000,001 - $2,000,000
12 2Q 2019 Laborers Federal
Transportation Construction Residential Roadway Lighting Improvement - North Area
Over $20,000,000
24 2Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Non-Federal
Transportation Construction Residential Roadway Lighting Improvement - South Area
Over $20,000,000
24 2Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Non-Federal
Transportation Construction Harrison Street Viaduct Over $20,000,000
24 2Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Non-Federal
Transportation Construction Grand - Chicago to Damen
$10,000,001 - $20,000,000
12 3Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Non-Federal
City of Chicago Contracting Opportunities
24
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Transportation Construction
Roosevelt Road - Western Avenue to Lake Shore Drive Traffic Signal Interconnect
$3,000,001 - $5,000,000
12 3Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Federal
Transportation Construction
Stony Island Avenue - 95th Street to Midway Plaisance Traffic Signal Interconnect
$3,000,001 - $5,000,000
12 3Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Federal
Transportation Construction
Broadway / Sheridan - Hollywood to Devon Traffic Signal Interconnect
$1,000,001 - $2,000,000
12 3Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Federal
Transportation Construction Stony Island Cycle Track $1,000,001 - $2,000,000
TBD TBD
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Ironworkers, Plumbers, Electricians, Landscapers
Federal
Transportation Construction - MBI
Community Infrastructure Contract Area 1
$5,000,001 - $10,000,000
24 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Ironworkers, Plumbers, Electricians, Landscapers
Non-Federal
Transportation Construction - MBI
Community Infrastructure Contract Area 2
$5,000,001 - $10,000,000
24 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Ironworkers, Plumbers, Electricians, Landscapers
Non-Federal
City of Chicago Contracting Opportunities
25
This guide has been prepared for informational purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department
Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Transportation Construction - MBI
Community Infrastructure Contract Area 3
$5,000,001 - $10,000,000
24 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Ironworkers, Plumbers, Electricians, Landscapers
Non-Federal
Transportation Construction - MBI
Community Infrastructure Contract Area 4
$5,000,001 - $10,000,000
24 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Ironworkers, Plumbers, Electricians, Landscapers
Non-Federal
Transportation Construction - MBI
Community Infrastructure Contract Area 5
$5,000,001 - $10,000,000
24 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Ironworkers, Plumbers, Electricians, Landscapers
Non-Federal
Transportation Construction - MBI
95th Street, Damen to Wood Streetscape
$3,000,001 - $5,000,000
12 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Non-Federal
Transportation Construction - MBI
Michigan Avenue Streetscape - 24th Place to Cermak Road
$3,000,001 - $5,000,000
12 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Non-Federal
Transportation Construction - SBI II
Broadway Streetscape Section 2, Wilson Avenue to Leland Avenue
$500,001 - $1,000,000
12 1Q 2019
Cement Finishers, Masons, Operators, Truck Drivers, Laborers, Plumbers, Electricians, Landscapers
Non-Federal
City of Chicago Contracting Opportunities
26
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Transportation Work Services
Chicago Tunnel Systems Inspections, Repair, and Maintenance
$3,000,001 - $5,000,000
60 1Q 2019
Laborers, Electricians, Plumbers, Equipment Operators, Carpenters
Non-Federal
Water Management
Commodities Ductile Iron Push-On $10,000,001 - $20,000,000
60 1Q 2019 No Stated Goals Non-Federal
Water Management
Commodities Various Wedge Gate Valves
$1,000,001 - $2,000,000
60 1Q 2019 No Stated Goals Non-Federal
Water Management
Commodities Liquid Chlorine $500,001 - $1,000,000
60 1Q 2019 TBD Non-Federal
Water Management
Commodities Color/B & W Multifunctional Plotter/Scanners
$50,001 - $100,000
60 1Q 2019 Delivery, Supplies
Non-Federal
Water Management
Commodities Reinforced Concrete Sewer Pipe, Fittings, Gaskets and Catch Basin
Over $20,000,000
60 1Q 2019 M/WBE Non-Federal
Water Management
Commodities Water Conservation Kits TBD 60 2Q 2019 TBD Non-Federal
Water Management
Commodities Target Market - Heating Oil Grades 1 & 2
$5,000,001 - $10,000,000
60 2Q 2019 Target Market Non-Federal
Water Management
Commodities Bituminous Fiber Meter Boxes
$500,001 - $1,000,000
60 2Q 2019 No Stated Goals Non-Federal
Water Management
Commodities Plastic Access Panel Doors
$50,001 - $100,000
60 3Q 2019 No Stated Goals Non-Federal
Water Management
Commodities
Replacement Parts for Mueller, Sensus, Neptune, and Badger Water Meter
TBD 60 4Q 2019 TBD Non-Federal
Water Management
Construction Street and Parkway Repairs South Region
$10,000,001 - $20,000,000
60 1Q 2019
Concrete, Pavement Marking, Landscape
Non-Federal
Water Management
Construction Street and Parkway Repairs North Region
$10,000,001 - $20,000,000
60 1Q 2019
Concrete, Pavement Marking, Landscape
Non-Federal
Water Management
Construction New Job Order Contracting Contract
Over $20,000,000
60 1Q 2019 Concrete, Landscape, Hauling
Non-Federal
Water Management
Construction Street and Parkway Restoration North Region
Over $20,000,000
60 1Q 2019
Concrete, Pavement Marking, Landscape
Non-Federal
City of Chicago Contracting Opportunities
27
This guide has been prepared for informational purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department
Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Water Management
Construction Street and Parkway Restoration South Region
Over $20,000,000
60 1Q 2019
Concrete, Pavement Marking, Landscape
Non-Federal
Water Management
Construction Street and Parkway Restoration Central South Region
Over $20,000,000
60 1Q 2019
Concrete, Pavement Marking, Landscape
Non-Federal
Water Management
Construction Street and Parkway Restoration Central North Region
Over $20,000,000
60 1Q 2019
Concrete, Pavement Marking, Landscape
Non-Federal
Water Management
Construction 84th MWRD Sewer Connection Project PN7374
TBD 12 3Q 2019
Sewer Construction/Tunneling, Cleaning, Televising, Concrete, Materials Testing, Asphalt Placement, Trucking, Landscaping
Federal
Water Management
Construction Beach and Midway Sewer Improvement Project PN7110
TBD 12 3Q 2019
Sewer Construction/Tunneling, Cleaning, Televising, Concrete, Materials Testing, Asphalt Placement, Trucking, Landscaping
Federal
Water Management
Construction Blackstone Sewer Improvement Project PN6172
TBD 12 3Q 2019
Sewer Construction/Tunneling, Cleaning, Televising, Concrete, Materials Testing, Asphalt Placement, Trucking, Landscaping
Federal
Water Management
Construction Garfield Ridge Sewer Improvement Project PN7300
TBD 12 3Q 2019
Sewer Construction/Tunneling, Cleaning, Televising, Concrete, Materials Testing, Asphalt Placement, Trucking, Landscaping
Federal
City of Chicago Contracting Opportunities
28
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Water Management
Construction Higgin Sewer Improvement Project PN7289
TBD 12 3Q 2019
Sewer Construction/Tunneling, Cleaning, Televising, Concrete, Materials Testing, Asphalt Placement, Trucking, Landscaping
Federal
Water Management
Construction Northwest Highway Sewer Improvement PN7115
TBD 12 3Q 2019
Sewer Construction/Tunneling, Cleaning, Televising, Concrete, Materials Testing, Asphalt Placement, Trucking, Landscaping
Federal
Water Management
Construction Peoria Ave: 64th to 65th Streets Sewer Improve PN7002A
TBD 12 3Q 2019
Sewer Construction/Tunneling, Cleaning, Televising, Concrete, Materials Testing, Asphalt Placement, Trucking, Landscaping
Federal
Water Management
Construction Jackson Blvd and Fifth Ave Sewer Improvement PN6890
$3,000,001 - $5,000,000
12 3Q 2019
Sewer Construction/Tunneling, Cleaning, Televising, Concrete, Materials Testing, Asphalt Placement, Trucking, Landscaping
Federal
Water Management
Construction Forest Preserve/Osage/Ozanam SIP PN7359 (IEPA)
$1,000,001 - $2,000,000
12 3Q 2019
Sewer Construction/Tunneling, Cleaning, Televising, Concrete, Materials Testing, Asphalt Placement, Trucking, Landscaping
Federal
Water Management
Construction SWPP - Filter Building Roof.
Over $20,000,000
48 TBD TBD Non-Federal
City of Chicago Contracting Opportunities
29
This guide has been prepared for informational purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department
Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Water Management
Construction - MBI
Private Drain Repair Program PN7421A North
$3,000,001 - $5,000,000
36 1Q 2019
Sewer Installation, Drain Connections, Excavation, Trucking, Materials, Traffic Control
Non-Federal
Water Management
Construction - MBI
Private Drain Repair Program PN7421B Central
$3,000,001 - $5,000,000
36 1Q 2019
Sewer Installation, Drain Connections, Excavation, Trucking, Materials, Traffic Control
Non-Federal
Water Management
Construction - MBI
Private Drain Repair Program PN7421C South
$3,000,001 - $5,000,000
36 1Q 2019
Sewer Installation, Drain Connections, Excavation, Trucking, Materials, Traffic Control
Non-Federal
Water Management
Construction - MBI
Private Drain Repair Program PN7421D Far South
$3,000,001 - $5,000,000
36 1Q 2019
Sewer Installation, Drain Connections, Excavation, Trucking, Materials, Traffic Control
Non-Federal
Water Management
Professional Services
New Structural Term Agreement
$3,000,001 - $5,000,000
84 1Q 2019 Material Supplies, Trucking
Non-Federal
Water Management
Professional Services
Water Meter Installation Over $20,000,000
60 1Q 2019
Electrical, Mechanical, Asbestos Remediation, Painting, Landscaping, Asphalt Placement, Plumbing, Interior Construction, Demolition
Non-Federal
Water Management
Work Services
Overhead Crane Maintenance Service
$5,000,001 - $10,000,000
60 1Q 2019 No Stated Goals Non-Federal
Water Management
Work Services
Bird Deterrent Services for Department of Water Management Facilities
$500,001 - $1,000,000
60 1Q 2019 No Stated Goals Non-Federal
Water Management
Work Services
Tradesmen Services Over $20,000,000
60 1Q 2019 M/WBE Non-Federal
City of Chicago Contracting Opportunities
30
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City o
f Ch
icago
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Water Management
Work Services
Master Term Agreement for Roofing Services
$3,000,001 - $5,000,000
60 2Q 2019 Roofers, Sheet Metal Workers
Non-Federal
Water Management
Work Services
Inspection Fabricated Parts & Repair Serv. For Small Centrifugal Pumps
$2,000,001 - $3,000,000
60 2Q 2019 TBD Non-Federal
Water Management
Work Services
Parts and Services for Large Electric Motors
$500,001 - $1,000,000
60 2Q 2019 TBD Non-Federal
Water Management
Work Services
Supervisory Control and Data Acquisition (Scada) Systems Maintenance
$500,001 - $1,000,000
60 2Q 2020 TBD Non-Federal
Chicago Board of Election Contracting Opportunities
31
This guide has been prepared to serve as informational purposes only to the City’s contracting process and as a reference for the future. The City may revise this plan at any time without notice.
Ch
icago
Bo
ard o
f Electio
ns
Agency Contract Type Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
CBOE Work Services Cartage of Election Equipment
$500,001 - $1,000,000
24 1Q 2019 Vehicles Non-Federal
Chicago City Colleges Contracting Opportunities
32
This guide has been prepared to serve as informational purposes only to the City’s contracting process and as a reference for the future. The City may revise this plan at any time without notice.
Ch
icago
City C
olleg
es
Department Contract Type Job Description
Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontracting Opportunities
Academic and Student Affairs and Business Enterprises
Professional Services
Bookstore Operations
$6,000,000 60 1Q 2019 TBD
Administrative Services
Commodity
Pickup Truck with Snow Plow Attachment
$50,000 One -Time Purchase
4Q 2018 TBD
Administrative Services
Commodity and Work Services
Purchase of Vehicle Maintenance and Repair Services
$2,000,001 - $4,000,000
36 4Q 2018 TBD
Administrative Services
Construction Plumbing and Piping Repair
$2,000,001 - $4,000,000
36 1Q 2019 TBD
Administrative Services
Construction Roof Repair- Truman College
$750,000 24 2Q 2019 TBD
Administrative Services
Professional Services
Environmental Hazardous Waste Removal
$5,200,000 36 4Q 2018 TBD
Administrative Services
Work Services Low Voltage Job Order Contracting
$4,000,000 36 1Q 2019 Supplies, Technical, A/E Services
Administrative Services
Work Services
Fire Alarm Panel Replacement- Kennedy-King College
$1,000,000 36 2Q 2019 Supplies, Technical, A/E Services
Human Resources Information Technology
Performance Management Solution
$2,000,001 - $4,000,000
60 2Q 2019 Administrative, Technical
Information Technology
Commodity Audio Visual Equipment and Services
$1,000,001 - $2,000,000
36 4Q 2018 Equipment, Technical and Services
Information Technology
Commodity General IT Equipment
$4,000,001 - $7,000,000
36 4Q 2018 Services and Equipment
Information Technology
Professional Services
Staff Augmentation for Information Technology
$2,000,001 - $4,000,000
36 1Q 2019 Technical
Information Technology
Professional Services
General IT Equipment Service and Repair
$200,000 36 2Q 2019 Technical
Information Technology
Software Solution Business Intelligence & Analytics Tool
$1,000,000 36 1Q 2019 TBD
City Colleges of Chicago
33
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
City C
olleg
es of C
hicag
o
Department Contract Type Job Description
Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontracting Opportunities
Information Technology
Software Solution First Alert System for students
$1,000,000 36 2Q 2019 TBD
Safety and Security Commodity
Supply and Delivery of Security Uniforms
$200,000 36 2Q 2019 TBD
Washburne Culinary Institute
Commodity
Supply and Delivery of Chef Uniform and Cutlery Kits
DUR 36 1Q 2019 TBD
Washburne Culinary Institute
Professional Services
Repair and Maintenance of Restaurant Equipment
$500,000 36 2Q 2019 TBD
Chicago Housing Authority Contracting Opportunities
34
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Ch
icago
Ho
usin
g A
uth
ority
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
CHA Commodities Supply & Delivery of Residential Appliances
$3,000,001 - $5,000,000
48 1Q 2019 No Stated Goals Mixed
CHA Commodities City of Chicago Piggyback Agreement - Dell
$2,000,001 - $3,000,000
TBD 1Q 2019 No Stated Goals TBD
CHA Commodities Lawson HR Upgrade $500,001 - $1,000,000
TBD 1Q 2019 No Stated Goals TBD
CHA Commodities PDF iFilter Maintenance $50,001 - $100,000
24 1Q 2019 No Stated Goals TBD
CHA Commodities
SolarWinds Network Performance Monitor/Engineer's Toolset Annual Maintenance
$10,001 - $50,000
24 1Q 2019 No Stated Goals TBD
CHA Commodities Articulate Maintenance Under $10,000
12 1Q 2019 No Stated Goals TBD
CHA Commodities Quest Reporter Tool Enabled User Account Renewal
Under $10,000
24 1Q 2019 No Stated Goals TBD
CHA Commodities SQWL Sentry Maintenance
Under $10,000
12 1Q 2019 No Stated Goals TBD
CHA Commodities PDF Filter Under $10,000
12 1Q 2019 No Stated Goals TBD
CHA Commodities DB Artisan Support Renewal
Under $10,000
12 1Q 2019 No Stated Goals TBD
CHA Commodities Entryway Mats Services TBD 60 2Q 2019 TBD Federal
CHA Construction Prequalified Task Order Program for General Contractors
TBD 48 1Q 2019 All Basic Construction Trades
Mixed
CHA Construction
Renovation of a Mixed-Use Building: Conversion & Renovation of 1852 S. Albany Phase III: Residential Units
$5,000,001 - $10,000,000
TBD 2Q 2019 All Basic Construction Trades
Mixed
CHA Construction Renovation of Senior Housing: Las Americas Apts. (1611 S. Racine)
$3,000,001 - $5,000,000
TBD 2Q 2019 All Basic Construction Trades
Mixed
Chicago Housing Authority Contracting Opportunities
35
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Ch
icago
Ho
usin
g A
uth
ority
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
CHA Construction Renovation of Senior Housing: Patrick Sullivan Apts. (1633 W. Madison)
$3,000,001 - $5,000,000
TBD 2Q 2019 All Basic Construction Trades
Mixed
CHA Construction
Renovation of a Non-Dwelling Facility: Major Adams Community Center (123 N. Hoyne)
$3,000,001 - $5,000,000
TBD 2Q 2019 All Basic Construction Trades
Mixed
CHA Construction
Renovation of Senior Housing: Maria Diaz Martinez Apts. (2111 N. Halsted)
$3,000,001 - $5,000,000
TBD 3Q 2019 All Basic Construction Trades
Mixed
CHA Construction
Renovation of Senior Housing: Mahalia Jackson Apts. (9141-9177 S. South Chicago Ave)
$5,000,001 - $10,000,000
TBD 4Q 2019 All Basic Construction Trades
Mixed
CHA Construction
Renovation of Senior Housing: Ella Flagg Young Apts. (4645 N. Sheridan)
$5,000,001 - $10,000,000
TBD 4Q 2019 All Basic Construction Trades
Mixed
CHA Construction
Renovation of Senior Housing: Judge Green Apts. (4030 S. Lake Park Ave)
$3,000,001 - $5,000,000
TBD 4Q 2019 All Basic Construction Trades
Mixed
CHA Information & Technology
Fixed Assets Inventory Control
TBD TBD 1Q 2019 TBD Federal
CHA Information & Technology
Enterprise Licensing, Hosting and User Support for youth services database
$10,001 - $50,000
60 1Q 2019 Professional Services
Federal
CHA Information & Technology
PPM Broadband Services (ITS Responsibility Cable/Internet and Phone Services)
TBD TBD 3Q 2019 TBD Federal
CHA Information & Technology
Siemens (ITS/Security) Bryan Land's Team
TBD TBD 4Q 2019 TBD Federal
CHA Information & Technology
Access Database (JOC/Preventative Maint.)
$10,001 - $50,000
TBD TBD TBD Federal
CHA Professional Services
Mobility Counseling Services
$5,000,001 - $10,000,000
60 1Q 2019 Professional Services
Federal
CHA Professional Services
Collaboration with Local Workforce Investment Board (LWIA) to provide workforce services to CHA residents
$1,000,001 - $2,000,000
60 1Q 2019 Professional Services
Federal
CHA Professional Services
Vmware Consulting & Training
$1,000,001 - $2,000,000
TBD 1Q 2019 No Stated Goals TBD
CHA Professional Services
Conducting and Managing the CAC/LAC Elections
$250,001 - $500,000
12 1Q 2019 Professional Services
Federal
Chicago Housing Authority Contracting Opportunities
36
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Ch
icago
Ho
usin
g A
uth
ority
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
CHA Professional Services
Internet Bandwidth $250,001 - $500,000
36 1Q 2019 No Stated Goals Federal
CHA Professional Services
Financial Consulting and Advisory Services
$100,001 - $250,000
60 1Q 2019 Professional Services
Federal
CHA Professional Services
Payroll Services for CHA Youth Programs
$100,001 - $250,000
60 1Q 2019 Professional Services
Federal
CHA Professional Services
Hearing Officers $100,001 - $250,000
12 1Q 2019 No Stated Goals TBD
CHA Professional Services
Matter Management $50,001 - $100,000
12 1Q 2019 No Stated Goals TBD
CHA Professional Services
Legal Research Database
$10,001 - $50,000
60 1Q 2019 No Stated Goals TBD
CHA Professional Services
Legal Research $10,001 - $50,000
24 1Q 2019 No Stated Goals TBD
CHA Professional Services
Court Reporting $10,001 - $50,000
24 1Q 2019 No Stated Goals TBD
CHA Professional Services
Messenger Services, Local, Overnight, RUSH, Loop and Surrounding Chicagoland area and suburbs
$10,001 - $50,000
12 1Q 2019 TBD Federal
CHA Professional Services
Carpet Cleaning $10,001 - $50,000
36 1Q 2019 TBD Non-Federal
CHA Professional Services
Lease of Water Coolers/Ice Machines
$10,001 - $50,000
36 1Q 2019 TBD Non-Federal
CHA Professional Services
Brightworks Licensing Under $10,000
TBD 1Q 2019 No Stated Goals TBD
CHA Professional Services
Extermination Under $10,000
12 1Q 2019 TBD Federal
CHA Professional Services
Quarterly Mechanical Maintenance
Under $10,000
36 1Q 2019 TBD Non-Federal
CHA Professional Services
FamilyWorks Services Over $20,000,000
60 1Q 2019 Professional Services
Federal
CHA Professional Services
LIHTC Financial Services/Project Audit
$100,001 - $250,000
48 2Q 2019 Accountants, Financial Auditors
TBD
Chicago Housing Authority Contracting Opportunities
37
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Ch
icago
Ho
usin
g A
uth
ority
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
CHA Professional Services
LIHTC Compliance/File Audits
$100,001 - $250,000
48 2Q 2019 TBD TBD
CHA Professional Services
Construction Escrow Services
$500,001 - $1,000,000
48 4Q 2019 Professional Services
Mixed
CHA Revenue Generating
Vending Services (Snack, Beverage)
Revenue Generating
TBD 2Q 2019 TBDT TBD
CHA Revenue Generating
Vending Services (Ice Cream)
Revenue Generating
TBD 2Q 2019 TBD TBD
CHA Small Orders
Professional Catering Services for Housing Choice Voucher Program meetings.
$10,001 - $50,000
36 1Q 2019 Professional Services
Non-Federal
CHA Small Orders Small Tools & Maintenance Supplies
Under $10,000
12 1Q 2019 TBD Federal
CHA Small Orders Furniture for the CHA Under $10,000
12 1Q 2019 TBD Federal
CHA Small Orders Audio Equipment Under $10,000
12 1Q 2019 TBD Federal
CHA Small Orders Vehicle Detailing Under $10,000
12 1Q 2019 TBD Federal
CHA TBD Albany Terrace/Gaines Development Partner RFP
TBD TBD 1Q 2019 TBD Mixed
CHA TBD Cabrini Rowhomes RFP TBD TBD 1Q 2019 TBD Mixed
CHA TBD Lidia Pucinska Opportunity Notice
TBD TBD 2Q 2019 TBD Mixed
CHA TBD Prequalified Development Teams RFQ
TBD 24 2Q 2019 TBD Mixed
CHA TBD Environmental Services Radon Testing RFP
$10,001 - $50,000
48 2Q 2019 TBD TBD
CHA TBD Flannery Development Partner RFP
TBD TBD 3Q 2019 TBD Mixed
CHA TBD Prequalified Development Teams RFQ
TBD 24 4Q 2019 TBD Mixed
Chicago Housing Authority Contracting Opportunities
38
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Ch
icago
Ho
usin
g A
uth
ority
Department Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
CHA Vehicles & Heavy Equipment
Lease Vehicles for the CHA
$50,001 - $100,000
12 1Q 2019 TBD Federal
CHA Vehicles & Heavy Equipment
Enterprise Vehicle Fleet Sale Lease Back (17-20 Vehicles)
$500,001 - $1,000,000
48 2Q 2019 TBD Federal
CHA Work Services
Implementation of solar arrays and alternative energy systems at CHA properties
TBD TBD 1Q 2019 TBD Non-Federal
CHA Work Services
Elevator Maintenance TBD 60 1Q 2019 TBD Federal
CHA Work Services
Plant Operations $10,000,001 - $20,000,000
60 1Q 2019 TBD Federal
CHA Work Services
Bed Bug Remediation $5,000,001 - $10,000,000
60 1Q 2019 TBD Federal
CHA Work Services
Routine Pest control $3,000,001 - $5,000,000
60 1Q 2019 TBD Federal
CHA Work Services
Fire Alarm system maintenance and repair
$1,000,001 - $2,000,000
60 1Q 2019 TBD Federal
CHA Work Services
Canine Bed Bug Inspections
$2,000,001 - $3,000,000
60 1Q 2019 TBD Federal
CHA Work Services
Mold Remediation and Restoration
TBD TBD 2Q 2019 TBD Federal
CHA Work Services
Laundry Machine Maintenance and Repair
TBD 60 2Q 2019 TBD Federal
CHA Work Services
Commercial Laundry Machines
TBD 60 2Q 2019 TBD Federal
CHA Work Services
Mid-High Rise Building Window Washing (est. 85 Buildings)
$3,000,001 - $5,000,000
60 2Q 2019 TBD Federal
CHA Work Services
Emergency Generator maintenance and repair
$1,000,001 - $2,000,000
60 2Q 2019 TBD Federal
CHA Work Services
Site Base Waitlist Implementation
$250,001 - $500,000
TBD 2Q 2019 TBD Federal
Chicago Park District Contracting Opportunities
39
This guide has been prepared to serve as informational purposes only to the City’s contracting process and as a reference for the future. The City may revise this plan at any time without notice.
Ch
icago
Park D
istrict
Agency Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Park District Commodities Aquatic Supplies $50,001 - $100,000
24 1Q 2019 M/WBE Non-Federal
Park District Commodities Gymnastics Mats: Supply and Delivery
$50,001 - $100,000
12 1Q 2019 M/WBE Non-Federal
Park District Construction General Contractors Pool
TBD 36 Open
Solicitation
Construction Engineering, Quality Assurance/Quality Control
Non-Federal
Park District Construction Artificial Turf Field Repairs
$100,001 - $250,000
36 Open
Solicitation
Small Repair and Construction Jobs
Non-Federal
Park District Construction Rapid Response Services
$50,001 - $100,000
36 Open
Solicitation
All Basic Construction Trades
Non-Federal
Park District Professional Services
Fingerprinting Services $100,001 - $250,000
24 1Q 2019 Professional Services
Non-Federal
Park District Professional Services
Background Checks for Volunteers
$100,001 - $250,000
24 1Q 2019 Professional Services
Non-Federal
Park District Professional Services
Healthy Snack Vending Machine Services
$50,001 - $100,000
24 1Q 2019 M/WBE Non-Federal
Park District Professional Services
Summer Day Camp Bus Transportation Services
$100,001 - $250,000
36 Open
Solicitation Transportation
Non-Federal
Chicago Public Schools Contracting Opportunities
40
This guide has been prepared to serve as informational purposes only to the City’s contracting process and as a reference for the future. The City may revise this plan at any time without notice.
Ch
icago
Pu
blic S
cho
ols
Agency Contract Type
Project Description Estimated Value
Estimated Term
(months)
Anticipated Ad Date
Sub Opportunities
Funding Source
CPS Commodities Musical Instruments $5,000,001 - $10,000,000
12 1Q 2019 TBD Mixed
CPS Commodities End User Computing Agreement with Leasing Option RFP
Over $20,000,000
36 1Q 2019 IT Services Mixed
CPS Commodities Visual and Performing Arts Supplies
Over $20,000,000
24 1Q 2019 Material Supplies, Trucking
Mixed
CPS Commodities Graduation Apparel, Supplies and Services for All Schools
$1,000,001 - $2,000,000
36 4Q 2018 Uniforms Mixed
CPS JOC Job Ordering Contracting Services-Pool
Over $20,000,000
36 2Q 2019 All Basic Construction Trades
Mixed
CPS Professional Services
Real Estate Brokerage Services
TBD 36 1Q 2019 Professional Services
Mixed
CPS Professional Services
Managed Print Services RFP
$5,000,001 - $10,000,000
36 1Q 2019 TBD Mixed
CPS Professional Services
Data Center Services $5,000,001 - $10,000,000
12 1Q 2019 Delivery Mixed
CPS Professional Services
Human Capital Management System and Hosting Services
$5,000,001 - $10,000,000
36 1Q 2019 IT Services Mixed
CPS Professional Services
W-2 And Affordable Care Act 1095-C Processing Services
$100,001 - $250,000
12 1Q 2019
Evaluation, research, QA/QC, Healthcare Consulting Services, Reporting, Information and Technology.
Mixed
CPS Professional Services
Sign Language Interpreting Services
$100,001 - $250,000
TBD 1Q 2019 Professional Services
Mixed
CPS Professional Services
Pharmacy Benefit Management (PBM) Services
Over $20,000,000
TBD 1Q 2019 Professional Consulting Services
Mixed
CPS Professional Services
Medical and Dependent Care Flexible Spending Account (FSA) Service
$100,001 - $250,000
TBD 2Q 2019 Professional Services
Mixed
CPS Professional Services
Banking and Cash Management Services
$1,000,001 - $2,000,000
36 4Q 2018 Accountants, Financial Auditors
Mixed
CPS Professional Services
Alternative Learning Opportunities Program
$2,000,001 - $3,000,000
36 4Q 2018 Professional Consulting Services
Mixed
Chicago Public Schools Contracting Opportunities
41
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Ch
icago
Pu
blic S
cho
ols
Agency Contract Type
Project Description Estimated Value
Estimated Term
(months)
Anticipated Ad Date
Sub Opportunities
Funding Source
CPS Vehicles & Heavy Equipment
Field Trip / Charter Bus Providers
$10,000,001 - $20,000,000
36 1Q 2019 Transportation Mixed
CPS Vehicles & Heavy Equipment
Mobile Food Truck for Student Meals
$100,001 - $250,000
12 1Q 2019 TBD Mixed
CPS Vehicles & Heavy Equipment
Purchase of Vehicles $1,000,001 - $2,000,000
36 4Q 2019 Vehicles Mixed
CPS Work Services
Food Service Equipment and Related Installation Services
$3,000,001 - $5,000,000
24 1Q 2019 All Basic Construction Trades
Mixed
CPS Work Services Facilities Assessment Survey
$1,000,001 - $2,000,000
36 1Q 2019 Professional Services
Mixed
CPS Work Services APPA Cleanliness Audit Services RFP
$1,000,001 - $2,000,000
36 1Q 2019 Professional Services
Mixed
CPS Work Services School Based Tutoring and Mentoring Services
$100,001 - $250,000
12 1Q 2019 Professional Consulting Services
Mixed
CPS Work Services Yearbook Services $1,000,001 - $2,000,000
36 4Q 2018
Product Delivery Services, Boxes Labels
Mixed
CPS Work Services Photography Services for All Schools
$500,001 - $1,000,000
12 4Q 2018 Professional Services
Mixed
Chicago Transit Authority Contracting Opportunities
42
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Ch
icago
Transit A
uth
ority
Agency Contract Type
Project Description Estimated Value
Estimated Term
(months)
Anticipated Ad Date
Sub Opportunities
Funding Source
CTA Commodities
Off the Shelf Uniforms for CTA's Operating and Maintenance Personnel
$10,000,001 - $20,000,000
60 1Q 2019 TBD Non-Federal
CTA Commodities Railroad Ties $3,000,001 - $5,000,000
36 1Q 2019 TBD Federal
CTA Commodities
New Assemblies, Components, and Repair Parts as Required to Maintain Existing Interlock Equipment as Manufactured Exclusively by Ansaldo STS USA Inc
$500,001 - $1,000,000
36 1Q 2019 TBD Federal
CTA Commodities
Furnish and Deliver Stanley Security Solutions Security Products
$250,001 - $500,000
36 1Q 2019 TBD Non-Federal
CTA Commodities
Furnish and Deliver Rail Bound Manganese (RBM) Frogs and Switch Points
$250,001 - $500,000
36 1Q 2019 TBD TBD
CTA Commodities
Furnish and Deliver Aluminum Sheets, Plates and Shapes of Various Sizes & Thickness
$250,001 - $500,000
36 1Q 2020 TBD Non-Federal
CTA Commodities Steel Doors, Doorframes and Door Hardware.
$50,001 - $100,000
36 1Q 2020 TBD Non-Federal
CTA Commodities Furnish and Deliver Various Types of Plywood.
$50,001 - $100,000
36 1Q 2020 TBD Non-Federal
CTA Commodities Furnish and Deliver Tee Rail and Joint Bars
$500,001 - $1,000,000
36 2Q 2019 TBD Federal
CTA Commodities
Supply and Deliver Bulk Rock Sales as Required until May 31, 2019 FOB Destination
$100,001 - $250,000
12 2Q 2019 TBD TBD
CTA Commodities New and Rebuilt Hydraulic Cylinders
$50,001 - $100,000
36 2Q 2019 TBD Non-Federal
CTA Commodities
E-10 and E-85 Ethanol Gasoline for Non-Revenue Vehicles as Required
$10,000,001 - $20,000,000
60 3Q 2019 TBD Non-Federal
CTA Commodities Various Electrical Supplies
$5,000,001 - $10,000,000
36 3Q 2019 TBD Federal
Chicago Transit Authority Contracting Opportunities
43
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Ch
icago
Transit A
uth
ority
Agency Contract Type
Project Description Estimated Value
Estimated Term
(months)
Anticipated Ad Date
Sub Opportunities
Funding Source
CTA Commodities Furnish and Deliver Mca Treated Southern Yellow Pine.
$100,001 - $250,000
36 3Q 2019 TBD Non-Federal
CTA Commodities Various Types of Welding Gases
$100,001 - $250,000
36 3Q 2019 TBD TBD
CTA Commodities
Fiberglass Embedment Graphic Signs for Rail Stations as Required
$100,001 - $250,000
36 4Q 2019 TBD Non-Federal
CTA Commodities
Purchase Anchoring Products Manufactured by Hilti Corporation
$100,001 - $250,000
36 4Q 2019 TBD TBD
CTA Commodities
Furnish and Deliver Bus and Train Washer Brush Sets and Adapters
$100,001 - $250,000
36 4Q 2019 TBD Non-Federal
CTA Commodities
Fareboxes, Vaulting Systems and associated hardware, software and maintenance.
Over $20,000,000
240 TBD TBD TBD
CTA Information & Technology
Text Messaging Services for CTA's Bus Tracker Texting System
$500,001 - $1,000,000
36 1Q 2019 TBD Non-Federal
CTA Information & Technology
VMware Server Virtualization Software Licenses and Support
$100,001 - $250,000
36 1Q 2019 TBD Non-Federal
CTA Information & Technology
Provide Hardware and Software Maintenance and Support of Netapp Storage Systems for A Period of Up To 36 Months from Date of Contract Execution
$100,001 - $250,000
36 2Q 2019 TBD Non-Federal
CTA Professional Services
Event Management Consultants for the CTA’s Red and Purple Modernization Project - Small Business Enterprise (SBE) Program
$1,000,001 - $2,000,000
60 1Q 2019 TBD Federal
CTA Professional Services
Toxicology Services for Drug Testing
$500,001 - $1,000,000
60 1Q 2019 TBD Non-Federal
CTA Professional Services
Inspection, Maintenance, Testing, Recharging and Repairing of Carbon Dioxide & Dry Chemical Fire Extinguishers & Accessories System-Wide as Required for A Period of Up to Thirty-Six (36) Months from Date of Contract
$500,001 - $1,000,000
36 1Q 2019 TBD Non-Federal
Chicago Transit Authority Contracting Opportunities
44
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Ch
icago
Transit A
uth
ority
Agency Contract Type
Project Description Estimated Value
Estimated Term
(months)
Anticipated Ad Date
Sub Opportunities
Funding Source
Execution.
CTA Professional Services
Professional Consulting Services for Actuarial Valuation of CTA’s Injuries and Damage Reserve Liability for A Period of Up to Five Years
$100,001 - $250,000
60 1Q 2019 TBD Non-Federal
CTA Professional Services
Videography Services for the CTA’s Red and Purple Modernization Project - Small Business Enterprise (SBE) Program
Over $115,000
60 1Q 2019 TBD Federal
CTA Professional Services
Photography Services for the CTA’s Red and Purple Modernization Project - Small Business Enterprise (SBE) Program
Over $160,000
60 1Q 2019 TBD Federal
CTA Professional Services
Court Reporting Services for the CTA’s Red and Purple Modernization Project - Small Business Enterprise (SBE) Program
Over $200,000
60 1Q 2019 TBD Federal
CTA Professional Services
Market Research Services for the CTA’s Red and Purple Modernization Project - Small Business Enterprise (SBE) Program
Over $800,000
60 1Q 2019 TBD Federal
CTA Professional Services
Media Production Services for the CTA’s Red and Purple Modernization Project - Small Business Enterprise (SBE) Program
Over $850,000
60 1Q 2019 TBD Federal
CTA Professional Services
Project Phone Hotline for the CTA’s Red and Purple Modernization Project - Small Business Enterprise (SBE) Program
Over $1,700,000
60 1Q 2019 TBD Federal
CTA Professional Services
Office Management Consultants for the CTA’s Red and Purple Modernization Project - Small Business Enterprise (SBE) Program
Over $2,000,000
60 1Q 2019 TBD Federal
CTA Professional Services
Translation Services Consultants for the CTA’s Red and Purple Modernization Project
Over $2,800,000
60 1Q 2019 TBD Federal
Chicago Transit Authority Contracting Opportunities
45
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Ch
icago
Transit A
uth
ority
Agency Contract Type
Project Description Estimated Value
Estimated Term
(months)
Anticipated Ad Date
Sub Opportunities
Funding Source
CTA Professional Services
Marketing and Graphic Arts Services for the CTA’s Red and Purple Modernization Project - Small Business Enterprise (SBE) Program
Over $3,100,000
60 1Q 2019 TBD Federal
CTA Professional Services
General Engineering Consultant Services as Required. Task Order Based. May be Awarded to Multiple Vendors
Over $20,000,000
60 1Q 2019 TBD Federal & Other
CTA Professional Services
Program Management Services for Red Purple Modernization (RPM) Phase One Project and Infrastructure Core Program
Over $20,000,001
60 1Q 2019 TBD TBD
CTA Professional Services
Survey and Geotechnical Services - Small Business Enterprise (SBE) Program
$10,000,000 to $20,000,000
60 1Q 2019 TBD TBD
CTA Professional Services
On-Line Public Auction Services for The Disposition of Obsolete Material for A Period of Up To 36 Months
TBD 36 1Q 2020 TBD Non-Federal
CTA Professional Services
Professional Property Management Services for CTA Office Location at 567 W. Lake Street, 120 N. Racine and The CTA Warehouse Facility Located At 901 W. Division For (3) Years With (2) Funded One-Year Options
Over $20,000,000
36 2Q 2020 TBD TBD
CTA Professional Services
Professional Consulting Services to Assist the Deferred Compensation Committee in Evaluating Investment Decisions For 457 & 401K Plans for A Period of Three Years with Two One-Year Options from December 23, 2013
$250,001 - $500,000
36 3Q 2019 TBD Non-Federal
CTA Professional Services
Develop Detailed Mechanical Electrical Drawings Through Reverse Engineering for Various Rail and Bus Parts
$50,001 to $100,000
36 3Q 2019 TBD Non-Federal
Chicago Transit Authority Contracting Opportunities
46
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Ch
icago
Transit A
uth
ority
Agency Contract Type
Project Description Estimated Value
Estimated Term
(months)
Anticipated Ad Date
Sub Opportunities
Funding Source
CTA Professional Services
Environmental Impact Study for Red Line Extension
TBD TBD TBD TBD TBD
CTA Professional Services
Red Line Extension Preliminary Engineering
TBD TBD TBD TBD TBD
CTA Work Services
Real Estate Services for Up to Five Years from August 7, 2014
$5,000,001 - $10,000,000
60 1Q 2019 TBD Non-Federal
CTA Work Services
Provide Labor, Supervision, Materials, and Power Equipment Necessary for the Cleaning of Sewers, Catch Basins, Oil Separators, and Degreasing Sludge Pits at CTA's Properties
$2,000,001 - $3,000,000
36 1Q 2019 TBD Non-Federal
CTA Work Services
Provide the Inspection, Repair and Maintenance Service for American Disability Act Doors at Various CTA Locations.
$1,000,001 - $2,000,000
36 1Q 2019 TBD Non-Federal
CTA Work Services
Repairs to And Installation of New Fencing at Various CTA Locations in The Chicagoland Area, Including Cta Rapid Transit Lines.
$1,000,001 - $2,000,000
36 1Q 2019 TBD Non-Federal
CTA Work Services
Provide Cleaning Services for The Vacuum Pressure Impregnation (Vpi) System Located at Skokie Shops.
$500,001 - $1,000,000
TBD 1Q 2019 TBD Non-Federal
CTA Work Services
On Site Servicing of Parts Washer Tanks for Twelve Months with One Option Year.
$250,001 - $500,000
12 1Q 2019 TBD Non-Federal
CTA Work Services
Provide Labor, Materials, Tools, and Equipment to Refurbish Alstom 5G and 5H Electric Switch Machines
$100,001 - $250,000
36 1Q 2019 TBD Federal
CTA Work Services
Provide Rapid Transit Car Insect Extermination and Control Services
$100,001 - $250,000
36 1Q 2019 TBD Non-Federal
CTA Work Services
Cleaning and Repair Service for Rail Car Pre-Filters.
$100,001 - $250,000
TBD 1Q 2019 TBD Non-Federal
CTA Work Services
Maintenance, Service, and Consumable Supplies for Two High Volume Xerox Laser Printers
$100,001 - $250,000
36 1Q 2019 TBD Non-Federal
Chicago Transit Authority Contracting Opportunities
47
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Ch
icago
Transit A
uth
ority
Agency Contract Type
Project Description Estimated Value
Estimated Term
(months)
Anticipated Ad Date
Sub Opportunities
Funding Source
CTA Work Services
Digital Printing Services to be Released as Required
$50,001 - $100,000
36 1Q 2019 TBD Federal
CTA Work Services
Refuse removal for the Red-Purple Modernization project area - Small Business Enterprise (SBE) Program
Over $200,000
36 1Q 2019 TBD Federal
CTA Work Services
Printing Services for the CTA’s Red and Purple Modernization Project - Small Business Enterprise (SBE) Program
Over $320,000
60 1Q 2019 TBD Federal
CTA Work Services
Printed material distribution services for the Chicago Transit Authority's (CTA’s) Red and Purple Modernization Program (RPM) - Small Business Enterprise (SBE) Program
Over $350,000
60 1Q 2019 TBD Federal
CTA Work Services
Provide Labor, Supervision, Materials and Power Equipment necessary for cleaning of Sewers, Catch Basins, & Drains of Subway Vent Shaft, Louvers and Emergency Exits
$2,000,001 to $3,000,000
36 1Q 2019 TBD Federal
CTA Work Services
Support Services TBD TBD 2Q 2019 TBD TBD
CTA Work Services
Service and Recondition of 1.5 and 2.5 Gallon Fire Extinguishers
$100,001 - $250,000
36 2Q 2019 TBD Non-Federal
CTA Work Services
Furnish All Labor, Material, Tools, Equipment, and Insurance to Test, Inspect, Repair, and Maintain CTA's Clean Agent Fire Prevention Systems at Various Locations
$500,001 - $1,000,000
36 3Q 2019 TBD Non-Federal
CTA Work Services
An Indefinite-Quantity Contract to Provide Equipment Maintenance Repairs to Safety Vision Road recorder 5000 And/Or 6000 Pro Digital Video Recording System (Dvrs) And Associated Equipment.
$250,001 - $500,000
TBD 3Q 2019 TBD Non-Federal
Chicago Transit Authority Contracting Opportunities
48
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Ch
icago
Transit A
uth
ority
Agency Contract Type
Project Description Estimated Value
Estimated Term
(months)
Anticipated Ad Date
Sub Opportunities
Funding Source
CTA Work Services
Static and Digital Advertising Services in and Upon Specific Properties of the CTA
TBD 60 4Q 2019 TBD Non-Federal
CTA Work Services
Furnish All Labor and Equipment Required to Test, Inspect, Repair & Maintain CTA's Water-Based Fire Prevention Systems at Various Locations System-Wide.
$1,000,001 - $2,000,000
36 4Q 2019 TBD Non-Federal
CTA Work Services
Rental of Various Sizes of Mobile Cranes with Crews.
$1,000,001 - $2,000,000
TBD 4Q 2019 TBD Non-Federal
CTA Work Services
Onsite Maintenance And/Or Repairs for Robinair Refrigerant Recovery & Recycling System.
$100,001 - $250,000
TBD 4Q 2019 TBD Non-Federal
CTA Work Services
Inspection, Maintenance, Testing, Recharging and Repairing of Carbon Dioxide and Dry Chemical Fire Extinguishers and Accessories System Wide as Required
$500,001 - $1,000,000
36 4Q 2020 TBD Non-Federal
Public Building Commission Contracting Opportunities
49
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Pu
blic B
uild
ing
Co
mm
ission
Agency Contract Type Project Description
Estimated Value
Estimated Term
(Months)
Anticipated
Ad Date
Subcontractor Opportunities
Funding Source
PBC Construction Chicago Public Library
$2,000,001 - $3,000,000
TBD 1Q 2019 All Basic Construction Trades
TBD
PBC Design Build Chicago Public Schools
Over $20,000,000
TBD 1Q 2019 All Basic Construction Trades
TBD
PBC JOC Chicago Public Schools
$1,000,001 - $2,000,000
TBD 1Q 2019 All Basic Construction Trades
TBD
PBC JOC Chicago Park District
$1,000,001 - $2,000,000
TBD 1Q 2019 All Basic Construction Trades
TBD
PBC Professional Services
Architectural Services - LIQ
TBD TBD 1Q 2019 TBD TBD
PBC Professional Services
Engineering Services - LIQ
TBD TBD 1Q 2019 TBD TBD
PBC Professional Services
Roof Consultant $500,001 - $1,000,000
TBD 1Q 2019 TBD TBD
PBC Professional Services
Elevator Consultant
$500,001 - $1,000,000
TBD 1Q 2019 TBD TBD
MPEA Contracting Opportunities
50
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Metro
po
litan P
ier and
Exp
ositio
n A
uth
ority
Agency Contract Type Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
MPEA Commodities Meeting Room Furniture
TBD TBD 2Q 2019 TBD Non-Federal
MPEA Commodities Packed Goods (Food and Desserts)
TBD TBD 2Q 2019 TBD Non-Federal
MPEA Commodities Small wares (Forks, Spoons, Knives, Roll-Ups etc.)
TBD TBD 2Q 2019 TBD Non-Federal
MPEA Information & Technology
Cisco Smartnet TBD TBD 2Q 2019 IT Services Non-Federal
MPEA Information & Technology
Copier Lease TBD TBD 2Q 2019 Parts, Delivery, Maintenance, Installation
Non-Federal
MPEA Information & Technology
Interactive Floor Plan and Room Diagram Application
TBD TBD 2Q 2019 IT Services Non-Federal
MPEA Professional Services
Event Merchandise Sales
TBD TBD 2Q 2019 TBD Non-Federal
MPEA Professional Services
Kitchen Maintenance Services
TBD TBD 2Q 2019 Professional Consulting Services
Non-Federal
Cook County Contracting Opportunities
51
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Co
ok C
ou
nty
Agency Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Cook County
Adult Probation - COGNITIVE BEHAVIORAL TREATMENT
$100,001 - $250,000
TBD 1Q 2019 TBD TBD
Cook County
Animal Control - LICENSED VETERINARY SERVICES FOR LOW COST RABIES & MICROCHIP CLINICS 2019
$10,001 - $50,000
TBD 1Q 2019 TBD TBD
Cook County
Bureau of Technology - MULTIFUNCTION PRINTING DEVICES
$1,000,001 - $2,000,000
TBD 1Q 2019 TBD TBD
Cook County
Capital Planning & Policy - CCB MAIN HOLDING AREA ADA IMPROVEMENTS & LOCKUP
$5,000,001 - $10,000,000
TBD 1Q 2019 TBD TBD
Cook County
Capital Planning & Policy - COUNTYWIDE CF REDEVELOPMENT PROJECTS
$3,000,001 - $5,000,000
TBD 1Q 2019 TBD TBD
Cook County
Capital Planning & Policy - COUNTYWIDE PS ROOF REPLACEMENTS
$5,000,001 - $10,000,000
TBD 1Q 2019 TBD TBD
Cook County
Capital Planning & Policy - JHS ELEVATOR MODERNIZATION
$250,001 - $500,000
TBD 1Q 2019 TBD TBD
Cook County
Capital Planning & Policy - JHS OVERHEAD PAGING & NURSE CALL UPGRADE
$250,001 - $500,000
TBD 1Q 2019 TBD TBD
Cook County
Capital Planning & Policy - POST 8 NEW CONSTRUCTION
$50,001 - $100,000
TBD 1Q 2019 TBD TBD
Cook County
Clerk of the Circuit Court - WEARING APPAREL
$50,001 - $100,000
TBD 1Q 2019 TBD TBD
Cook County
Comptroller - BUNDLED DEFERRED COMPENSATION SERVICES FOR 457(B) PLANS FOR PARTICIPANTS EMPLOYED BY CCG AND FOREST PRESERVE
Under $10,000 TBD 1Q 2019 TBD TBD
Cook County
County Clerk - DOCUMENT MANAGEMENT SOFTWARE
$500,001 - $1,000,000
TBD 1Q 2019 TBD TBD
Cook County
County Clerk - JUDGMENT BOOK COVERS
$10,001 - $50,000
TBD 1Q 2019 TBD TBD
Cook County
Countywide - FORD FUSION HYBRIDS
$100,001 - $250,000
TBD 1Q 2019 TBD TBD
Cook County Contracting Opportunities
52
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Co
ok C
ou
nty
Agency Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Cook County
Countywide - HANDICAP VAN $50,001 - $100,000
TBD 1Q 2019 TBD TBD
Cook County
Countywide - ONLINE LEGAL RESEARCH SERVICES
TBD TBD 1Q 2019 TBD TBD
Cook County
Countywide - POLICE SUVS $500,001 - $1,000,000
TBD 1Q 2019 TBD TBD
Cook County
Environmental Control - BROWNFIELD ASSESSMENT CONTRACT
$500,001 - $1,000,000
TBD 1Q 2019 TBD TBD
Cook County
Environmental Control - COLLECTION OF ELECTRONIC RECYCLABLES
TBD TBD 1Q 2019 TBD TBD
Cook County
Environmental Control - COMPUTER REPLACEMENT
$10,001 - $50,000
TBD 1Q 2019 TBD TBD
Cook County
Facilities Management - SERVICE, MAINTENANCE AND REPAIR FLAGPOLES
$50,001 - $100,000
TBD 1Q 2019 TBD TBD
Cook County
Facilities Management - SUPPLY, CUSTOM FLOOR MATS W/ COUNTY LOGO
$250,001 - $500,000
TBD 1Q 2019 TBD TBD
Cook County
Facilities Management - SUPPLY, GLASS
$250,001 - $500,000
TBD 1Q 2019 TBD TBD
Cook County
Juvenile Probation - MENTAL HEALTH SERVICES FOR COURT INVOLVED YOUTH
$5,000,001 - $10,000,000
TBD 1Q 2019 TBD TBD
Cook County
Juvenile Probation - REPORTING CENTERS FOR COURT INVOLVED YOUTH
$5,000,001 - $10,000,000
TBD 1Q 2019 TBD TBD
Cook County
Juvenile Probation - URINALYSIS TESTING FOR COURT INVOLVED YOUTH
$50,001 - $100,000
TBD 1Q 2019 TBD TBD
Cook County
Office of the Chief Judge - LUNCH AND DINNER JUROR MEALS - MAYWOOD
$10,001 - $50,000
TBD 1Q 2019 TBD TBD
Cook County
Office of the Chief Judge - RED JOURNAL DIARIES
$10,001 - $50,000
TBD 1Q 2019 TBD TBD
Cook County
Public Defender - DOCUMENT STORAGE BOXES
$10,001 - $50,000
TBD 1Q 2019 TBD TBD
Cook County
Revenue - CITATION BOOKLETS Under $10,000 TBD 1Q 2019 TBD TBD
Cook County Contracting Opportunities
53
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Co
ok C
ou
nty
Agency Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Cook County
Revenue - CUSTOMIZED ENVELOPES
$10,001 - $50,000
TBD 1Q 2019 TBD TBD
Cook County
Revenue - VEHICLE STICKER APPLICATION AND FULFILLMENT SERVICES
$50,001 - $100,000
TBD 1Q 2019 TBD TBD
Cook County
Revenue - VEHICLE STICKER TAGS $10,001 - $50,000
TBD 1Q 2019 TBD TBD
Cook County
Revenue - VEHICLE STICKERS $10,001 - $50,000
TBD 1Q 2019 TBD TBD
Cook County
Risk Management - HEALTH & GROUP BENEFITS CONSULTING
$1,000,001 - $2,000,000
TBD 1Q 2019 TBD TBD
Cook County
Risk Management - UNEMPLOYMENT COMPENSATION CLAIMS PROGRAM SERVICES
$100,001 - $250,000
TBD 1Q 2019 TBD TBD
Cook County
Sheriff's Office - CONTRACT INSTRUCTORS FOR RECRUIT AND SPECIALIZED TRAINING. WE ANTICIPATE THAT THE RFP WILL BE AWARDED IN 2019.
$3,000,001 - $5,000,000
TBD 1Q 2019 TBD TBD
Cook County
Sheriff's Office - ENTRANCE LEVEL CORRECTIONAL OFFICER AND PROMOTIONAL FOR CORRECTIONS & COURT SERVICES
$500,001 - $1,000,000
TBD 1Q 2019 TBD TBD
Cook County
Sheriff's Office - INMATE EVIDENCE BAGS
$50,001 - $100,000
TBD 1Q 2019 TBD TBD
Cook County
Sheriff's Office - MAINTENANCE OF LAWN CARE AND SNOW REMOVAL EQUIPMENT
$50,001 - $100,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - 2 - WAY RADIOS
$250,001 - $500,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - BARTLETT ROAD BRIDGE REPAIR
$250,001 - $500,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - BENTLEY PROFESSIONAL SERVCES AND SOFTWARE LICENSES.
$100,001 - $250,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - CAL-SAG CHANNEL BRIDGE STEEL TRUSS STRENGTHENING (4 BRIDGES)
$2,000,001 - $3,000,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - CENTRAL AVE PHASE I RFQ
$500,001 - $1,000,000
TBD 1Q 2019 TBD TBD
Cook County Contracting Opportunities
54
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Co
ok C
ou
nty
Agency Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Cook County
Transportation and Highways - COUNTY LINE ROAD (SOUTH) - I-294 RAMP TO NORTH AVE, NEW INTERCHANGE RAMP
>$20,000,000 TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - GROUP 3-2016 LAKE COOK ROAD - RAUPP BOULEVARD TO HASTINGS LANE
>$20,000,000 TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - LAKE-COOK RD BRIDGE REPAIR
$250,001 - $500,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - PAVEMENT PRESERVATION AND REHABILITATION SOUTH 2019
$3,000,001 - $5,000,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - PHASE I RFQ - 143RD ST
$100,001 - $250,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - PHASE I RFQ - 170TH ST
$250,001 - $500,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - PHASE I RFQ - EAST LAKE AVE
$100,001 - $250,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - PHASE I RFQ - LEHIGH AVE
$250,001 - $500,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - PHASE I RFQ -MEACHAM AVE
$250,001 - $500,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - PROFESSIONAL SERVICES CONTRACT TO DEVELOP A COUNTY WIDE TRANSIT PLAN TO DETERMINE HOW BEST TO UTILTIZE COUNTY DOLLARS AND ADVOCACY TO IMPROVE TRANSIT SERVICES WITHIN COOK COUNTY
$500,001 - $1,000,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - TOUHY AVENUE RECONSTRUCTION IMPROVEMENT- ELMHURST ROAD TO MT. PROSPECT ROAD
>$20,000,000 TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - VARIOUS DRAINAGE ENGINEERING SERVICES
$500,001 - $1,000,000
TBD 1Q 2019 TBD TBD
Cook County
Transportation and Highways - WEST LAKE AVENUE - WOLF ROAD TO LANDWEHR
$3,000,001 - $5,000,000
TBD 1Q 2019 TBD TBD
Cook County
Treasurer - PRINTING AND MAILING SERVICES
TBD TBD 1Q 2019 TBD TBD
Cook County
Bureau of Administration - BLANK ENVELOPES
$50,001 - $100,000
TBD 2Q 2019 TBD TBD
Cook County Contracting Opportunities
55
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Co
ok C
ou
nty
Agency Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Cook County
Bureau of Administration - PRINTED ENVELOPES
$50,001 - $100,000
TBD 2Q 2019 TBD TBD
Cook County
Bureau of Technology - ENTERPRISE CITATION MANAGEMENT
$500,001 - $1,000,000
TBD 2Q 2019 TBD TBD
Cook County
Bureau of Technology - ENTERPRISE IDENTITY AND ACCESS MANAGEMENT (IAM)
$1,000,001 - $2,000,000
TBD 2Q 2019 TBD TBD
Cook County
Bureau of Technology - ERP SUPPORT - DEV & SUPPORT
$500,001 - $1,000,000
TBD 2Q 2019 TBD TBD
Cook County
Bureau of Technology - IT TRAINING (PMP, ITIL, MICROSOFT .NET)
$100,001 - $250,000
TBD 2Q 2019 TBD TBD
Cook County
Capital Planning & Policy - DOC - NEW JAIL (REPLACEMENT)
$3,000,001 - $5,000,000
TBD 2Q 2019 TBD TBD
Cook County
Capital Planning & Policy - DOC PARKING LOT A RESURFACING
$250,001 - $500,000
TBD 2Q 2019 TBD TBD
Cook County
Capital Planning & Policy - JHS - MECHANICAL AND ELECTRICAL SYSTEMS RENEWAL / REPLACEMENT
$3,000,001 - $5,000,000
TBD 2Q 2019 TBD TBD
Cook County
Capital Planning & Policy - JSH - MECHANICAL SYSTEMS RENEWAL / REPLACEMENT
$3,000,001 - $5,000,000
TBD 2Q 2019 TBD TBD
Cook County
Capital Planning & Policy - JTDC FIRE GRADE DOORS
$100,001 - $250,000
TBD 2Q 2019 TBD TBD
Cook County
Clerk of the Circuit Court - BATTERY PACKS FOR PALLET JACKS
$10,001 - $50,000
TBD 2Q 2019 TBD TBD
Cook County
Clerk of the Circuit Court - MAINTENANCE OF WAREHOUSE EQUIPMENT
Under $10,000 TBD 2Q 2019 TBD TBD
Cook County
Clerk of the Circuit Court - PRINTED CERTIFIED MAIL ENVELOPES
$10,001 - $50,000
TBD 2Q 2019 TBD TBD
Cook County
Clerk of the Circuit Court - PRINTING OF BAIL BONDS
$100,001 - $250,000
TBD 2Q 2019 TBD TBD
Cook County
Clerk of the Circuit Court - PRINTING OF CIVIL LAW CITATIONS & LOCAL ORDINANCE TICKETS
$100,001 - $250,000
TBD 2Q 2019 TBD TBD
Cook County
Clerk of the Circuit Court - PRINTING OF COURT FILE JACKETS
$250,001 - $500,000
TBD 2Q 2019 TBD TBD
Cook County Contracting Opportunities
56
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Co
ok C
ou
nty
Agency Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Cook County
Clerk of the Circuit Court - PRINTING OF PERSONAL & SUBURBAN TICKETS
$250,001 - $500,000
TBD 2Q 2019 TBD TBD
Cook County
Environmental Control - DILUTION SYSTEMS
$50,001 - $100,000
TBD 2Q 2019 TBD TBD
Cook County
Environmental Control - FIELD TECH SMALL SUV REPLACEMENT
$10,001 - $50,000
TBD 2Q 2019 TBD TBD
Cook County
Environmental Control - LAB POOL VEHICLE REPLACEMENT
$10,001 - $50,000
TBD 2Q 2019 TBD TBD
Cook County
Environmental Control - MONITORING TECHNICIAN SERVICES
$50,001 - $100,000
TBD 2Q 2019 TBD TBD
Cook County
Facilities Management - SERVICE METAL MAINTENANCE
$250,001 - $500,000
TBD 2Q 2019 TBD TBD
Cook County
Facilities Management - SERVICE, BOILER CONTROL, CALIBRATION, TESTING, MAINTENANCE AND REPAIR
$500,001 - $1,000,000
TBD 2Q 2019 TBD TBD
Cook County
Facilities Management - SERVICE, REPAIR LIGHT DUTY MACHINES
$100,001 - $250,000
TBD 2Q 2019 TBD TBD
Cook County
Facilities Management - SUPPLY MOTORS
$250,001 - $500,000
TBD 2Q 2019 TBD TBD
Cook County
Facilities Management - SUPPLY PUMPS
$250,001 - $500,000
TBD 2Q 2019 TBD TBD
Cook County
Facilities Management - SUPPLY, ROOFTOP HANDLER
$50,001 - $100,000
TBD 2Q 2019 TBD TBD
Cook County
Facilities Management - SUPPLY, STEAM VALVES AND CONTROLLER
$10,001 - $50,000
TBD 2Q 2019 TBD TBD
Cook County
Facilities Management - SUPPLY, SWITCH GEAR AND DISTRIBUTION
$50,001 - $100,000
TBD 2Q 2019 TBD TBD
Cook County
Homeland Security & Emergency Management - CONTRACT TO PURCHASE FLEET VEHCILES
$100,001 - $250,000
TBD 2Q 2019 TBD TBD
Cook County
Homeland Security & Emergency Management - DESIGN AND PURCHASE OF NEW ASSET MANAGEMENT SYSTEM
$50,001 - $100,000
TBD 2Q 2019 TBD TBD
Cook County
Homeland Security & Emergency Management - HONDA MOTORS
$10,001 - $50,000
TBD 2Q 2019 TBD TBD
Cook County Contracting Opportunities
57
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Co
ok C
ou
nty
Agency Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Cook County
Human Resources - JOB CLASSIFICATION AND COMPENSATION SURVEY/STUDY
$1,000,001 - $2,000,000
TBD 2Q 2019 TBD TBD
Cook County
Human Resources - LEAVE MANAGEMENT SERVICES
$250,001 - $500,000
TBD 2Q 2019 TBD TBD
Cook County
Juvenile Temporary Detention Center - CONTRACT MAINTENANCE SERVICE - SANITARY DISPOSAL
Under $10,000 TBD 2Q 2019 TBD TBD
Cook County
Juvenile Temporary Detention Center - COUNTYWIDE BOTTLED DRINKING WATER AND COOLER RENTAL
$10,001 - $50,000
TBD 2Q 2019 TBD TBD
Cook County
Juvenile Temporary Detention Center - DAIRY PRODUCTS
$500,001 - $1,000,000
TBD 2Q 2019 TBD TBD
Cook County
Juvenile Temporary Detention Center - MAINTENANCE AND REPAIR OF DATA PROCESSING - RMIS
$250,001 - $500,000
TBD 2Q 2019 TBD TBD
Cook County
Juvenile Temporary Detention Center - REFRIGERATION EQUIPMENT PREVENTIVE MAINTENANCE & REPAIR
$10,001 - $50,000
TBD 2Q 2019 TBD TBD
Cook County
Medical Examiner - AUTOPSY SAW REPLACEMENT PROGRAM - 3YR. WITH ONE 24 MO. RENEWAL
$100,001 - $250,000
TBD 2Q 2019 TBD TBD
Cook County
Office of the Chief Judge - LAUNCH AND DINNER JUROR MEALS - DALEY CENTER
$500,001 - $1,000,000
TBD 2Q 2019 TBD TBD
Cook County
Public Defender - NEW POSTAGE MACHINES AND SERVICE NEEDED OFFICE WIDE, 12+ LOCATIONS AND UNITS
$10,001 - $50,000
TBD 2Q 2019 TBD TBD
Cook County
Public Guardian - HOMECARE DEPT INVENTORY SOFTWARE PROGRAM ENHANCEMENT
$10,001 - $50,000
TBD 2Q 2019 TBD TBD
Cook County
Public Guardian - JUVENILE DIVISION SOFTWARE PROGRAM ENHANCEMENT
$10,001 - $50,000
TBD 2Q 2019 TBD TBD
Cook County
Revenue - GAMBLING DECALS $10,001 - $50,000
TBD 2Q 2019 TBD TBD
Cook County
Revenue - THERMO PAPER FOR CITATION PRINTERS
$100,001 - $250,000
TBD 2Q 2019 TBD TBD
Cook County
Revenue - USED CAR LOOKUPS $50,001 - $100,000
TBD 2Q 2019 TBD TBD
Cook County
Sheriff's Office - FOOD SERVICE - PRISONER LUNCHES
$100,001 - $250,000
TBD 2Q 2019 TBD TBD
Cook County Contracting Opportunities
58
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Co
ok C
ou
nty
Agency Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Cook County
Sheriff's Office - MAINTENANCE AND REPAIR OF TAYLOR DUNN CARTS
$50,001 - $100,000
TBD 2Q 2019 TBD TBD
Cook County
Transportation and Highways - INVEST IN COOK: RIDGELAND AVENUE BUS PAD PROJECT 88TH TO 108TH
>$20,000,000 TBD 2Q 2019 TBD TBD
Cook County
Adult Probation - DRUG COURT ASSESSMENT EVALUATOR SERVICES
$100,001 - $250,000
TBD 3Q 2019 TBD TBD
Cook County
Adult Probation - DRUG TESTING SERVICES
$1,000,001 - $2,000,000
TBD 3Q 2019 TBD TBD
Cook County
Adult Probation - SUBSTANCE ABUSE COUSELING SERVICES (MULTIPLE CONTRACTS, AVERAGE $150K PER CONTRACT)
$1,000,001 - $2,000,000
TBD 3Q 2019 TBD TBD
Cook County
Bureau of Administration - PRINTED CARBONLESS FORMS
$500,001 - $1,000,000
TBD 3Q 2019 TBD TBD
Cook County
Bureau of Administration - RISO, 2 COLOR PRESS
$50,001 - $100,000
TBD 3Q 2019 TBD TBD
Cook County
Bureau of Technology - PRODUCTION ENVIORNMENT REFRESH
$500,001 - $1,000,000
TBD 3Q 2019 TBD TBD
Cook County
Bureau of Technology - SAN EXPANSION
$250,001 - $500,000
TBD 3Q 2019 TBD TBD
Cook County
Bureau of Technology - TEST/DEVELOPMENT EXPANSION, DMZ EXPANSION
$500,001 - $1,000,000
TBD 3Q 2019 TBD TBD
Cook County
Bureau of Technology - UNIFIED COUNTY- HOSTING & DR STRATEGIES
$500,001 - $1,000,000
TBD 3Q 2019 TBD TBD
Cook County
Bureau of Technology - UPDATE THE GIS ENTERPRISE BY MIGRATING EXISTING SYSTEM AND DB TO A NEW ENVIRONMENT
$250,001 - $500,000
TBD 3Q 2019 TBD TBD
Cook County
Bureau of Technology - UPDATE THE PINMAP APPLICATION TO A NEWER VERSION OF ARCGIS
$500,001 - $1,000,000
TBD 3Q 2019 TBD TBD
Cook County
Bureau of Technology - USING EXISTING LIDAR DATA TO CREATE DERIVITITIVE DATA
$500,001 - $1,000,000
TBD 3Q 2019 TBD TBD
Cook County
Capital Planning & Policy - CHDG TENANT BUILD-OUT
$3,000,001 - $5,000,000
TBD 3Q 2019 TBD TBD
Cook County
Capital Planning & Policy - COUNTY BUILDING RECORDER OF DEEDS: CCL LEAKAGE
$3,000,001 - $5,000,000
TBD 3Q 2019 TBD TBD
Cook County Contracting Opportunities
59
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Co
ok C
ou
nty
Agency Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Cook County
Capital Planning & Policy - COUNTYWIDE DOC CAMERA PROJECT PHASE II
$250,001 - $500,000
TBD 3Q 2019 TBD TBD
Cook County
Capital Planning & Policy - JHS ROOF REPLACEMENT
$5,000,001 - $10,000,000
TBD 3Q 2019 TBD TBD
Cook County
Capital Planning & Policy - JTDC EAST ELEVATOR MODERNIZATION
$3,000,001 - $5,000,000
TBD 3Q 2019 TBD TBD
Cook County
Capital Planning & Policy - LOGAN SQUARE HEALTH CENTER
$3,000,001 - $5,000,000
TBD 3Q 2019 TBD TBD
Cook County
Capital Planning & Policy - SECURITY ENHANCEMENTS
$3,000,001 - $5,000,000
TBD 3Q 2019 TBD TBD
Cook County
Capital Planning & Policy - WHITCOMB BUILDING - ROOF REPLACEMENT
$500,001 - $1,000,000
TBD 3Q 2019 TBD TBD
Cook County
Comptroller - SPREADSHEET SERVER/SOFTWARE MAINTENANCE
$10,001 - $50,000
TBD 3Q 2019 TBD TBD
Cook County
County Clerk - HELP DESK AND SUPPORT FOR EARLY VOTING & ELECTION DEPT ACF
$250,001 - $500,000
TBD 3Q 2019 TBD TBD
Cook County
County Clerk - RENTAL OF ELECTION VEHICLES
$100,001 - $250,000
TBD 3Q 2019 TBD TBD
Cook County
Countywide - AUTO BODY REPAIR, 3 ZONES
$100,001 - $250,000
TBD 3Q 2019 TBD TBD
Cook County
Environmental Control - AIR MOINTOR TRAILERS
$250,001 - $500,000
TBD 3Q 2019 TBD TBD
Cook County
Environmental Control - FLOW SYSTEMS
Under $10,000 TBD 3Q 2019 TBD TBD
Cook County
Environmental Control - PARTICULATE SPECIAT MONITORS
$100,001 - $250,000
TBD 3Q 2019 TBD TBD
Cook County
Environmental Control - SONIC METEO DATA TRANSL SYS
$10,001 - $50,000
TBD 3Q 2019 TBD TBD
Cook County
Environmental Control - STANDARDS $10,001 - $50,000
TBD 3Q 2019 TBD TBD
Cook County
Facilities Management - SERVICE, REPLACE HANDICAPP DOORS
$10,001 - $50,000
TBD 3Q 2019 TBD TBD
Cook County Contracting Opportunities
60
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Co
ok C
ou
nty
Agency Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Cook County
Facilities Management - SUPPLY COOLING TOWER FANS
$10,001 - $50,000
TBD 3Q 2019 TBD TBD
Cook County
Facilities Management - SUPPLY, BEARING AND SHIVES
$50,001 - $100,000
TBD 3Q 2019 TBD TBD
Cook County
Facilities Management - SUPPLY, EXHAUST UNITS
$50,001 - $100,000
TBD 3Q 2019 TBD TBD
Cook County
Facilities Management - SUPPLY, LAMPS
$250,001 - $500,000
TBD 3Q 2019 TBD TBD
Cook County
Homeland Security & Emergency Management - CONSULTANT FOR CONTINUITY OF OPERATIONS / GOVERNMENT
$100,001 - $250,000
TBD 3Q 2019 TBD TBD
Cook County
Homeland Security & Emergency Management - GENERATOR MAINTENANCE
$100,001 - $250,000
TBD 3Q 2019 TBD TBD
Cook County
Homeland Security & Emergency Management - HVAC MASTER REPAIR CONTRACT (FOR THE EOC)
$100,001 - $250,000
TBD 3Q 2019 TBD TBD
Cook County
Homeland Security & Emergency Management - PURCHASE OF PORTABLE RADIOS AND ACCESSORIES
$3,000,001 - $5,000,000
TBD 3Q 2019 TBD TBD
Cook County
Homeland Security & Emergency Management - REPAIR AND UPGRADE ARMORED RESCUE VEHICLE
$100,001 - $250,000
TBD 3Q 2019 TBD TBD
Cook County
Homeland Security & Emergency Management - WANCO BOARD MAINTENANCE
$50,001 - $100,000
TBD 3Q 2019 TBD TBD
Cook County
Juvenile Probation - CLINICAL EVALUATIONS AND ASSESSMENTS FOR COURT INVOLVED YOUTH OF THE CHILD PROTECTION DIVISION AND JUVENILE PROBATION DEPARTMENT
$3,000,001 - $5,000,000
TBD 3Q 2019 TBD TBD
Cook County
Juvenile Temporary Detention Center - LAUNDRY ROOM EQUIPMENT
$10,001 - $50,000
TBD 3Q 2019 TBD TBD
Cook County
Sheriff's Office - ALTERNATIVE TEMPORARY HOUSING
$3,000,001 - $5,000,000
TBD 3Q 2019 TBD TBD
Cook County
Sheriff's Office - ALTERNATIVE TEMPORARY HOUSING
$500,001 - $1,000,000
TBD 3Q 2019 TBD TBD
Cook County
Sheriff's Office - CONTINUUM OF CARE ABUSE AND MENTAL HEALTH TREATMENT PROGRAM
$3,000,001 - $5,000,000
TBD 3Q 2019 TBD TBD
Cook County Contracting Opportunities
61
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Co
ok C
ou
nty
Agency Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Cook County
Sheriff's Office - MAIL MACHINE LEASE
$10,001 - $50,000
TBD 3Q 2019 TBD TBD
Cook County
Transportation and Highways - COUNTY LINE ROAD (NORTH) - I-294 RAMP TO GRAND AVE, NEW INTERCHANGE RAMP
$5,000,001 - $10,000,000
TBD 3Q 2019 TBD TBD
Cook County
Transportation and Highways - PHASE II RFQ - BUSSE RD.
$100,001 - $250,000
TBD 3Q 2019 TBD TBD
Cook County
Transportation and Highways - PHASE II RFQ - CENTRAL ROAD
$250,001 - $500,000
TBD 3Q 2019 TBD TBD
Cook County
Transportation and Highways - PHASE II RFQ - SANDERS RD
$500,001 - $1,000,000
TBD 3Q 2019 TBD TBD
Cook County
Transportation and Highways - PROFESSIONAL SERVICES CONTRACT TO INVESTIGATE TRUCK MOBILITY AND INVESTMENT NEEDS IN SOUTHWEST COOK COUNTY, AS WELL AS IDENTIFY PRIORITY DEVELOPMENT SITES
$250,001 - $500,000
TBD 3Q 2019 TBD TBD
Cook County
Transportation and Highways - SALT DOME MAINTENANCE AND REPAIR
$50,001 - $100,000
TBD 3Q 2019 TBD TBD
Cook County
Capital Planning & Policy - COUNTY BUILDING 8TH FLOOR RENOVATION AND DEPARTMENT CONSOLIDATION
$3,000,001 - $5,000,000
TBD 4Q 2019 TBD TBD
Cook County
Capital Planning & Policy - COUNTYWIDE CF ELEVATOR RENOVATIONS
$250,001 - $500,000
TBD 4Q 2019 TBD TBD
Cook County
Capital Planning & Policy - COUNTYWIDE PS MECHANICAL ELECTRICAL PLUMBING PROJECTS
$3,000,001 - $5,000,000
TBD 4Q 2019 TBD TBD
Cook County
Capital Planning & Policy - JHS OVERHEAD PAGING & NURSE CALL UPGRADE
$250,001 - $500,000
TBD 4Q 2019 TBD TBD
Cook County
Comptroller - EBS CONSULTING SERVICES FOR PAYROLL/ACCOUNTING AREAS
$250,001 - $500,000
TBD 4Q 2019 TBD TBD
Cook County
County Clerk - OPTICAL SCAN BALLOT PRINTING SERVICES
$1,000,001 - $2,000,000
TBD 4Q 2019 TBD TBD
Cook County
Homeland Security & Emergency Management - EMERGENCY PREPAREDNESS GOODS AND RELATED SERVICES
$3,000,001 - $5,000,000
TBD 4Q 2019 TBD TBD
Cook County
Juvenile Temporary Detention Center - COUNTYWIDE SCAVENGER SERVICES - REPUBLIC SERVICES
$50,001 - $100,000
TBD 4Q 2019 TBD TBD
Cook County Contracting Opportunities
62
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Co
ok C
ou
nty
Agency Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Cook County
Juvenile Temporary Detention Center - DRY PRODUCTS
$3,000,001 - $5,000,000
TBD 4Q 2019 TBD TBD
Cook County
Juvenile Temporary Detention Center - PRODUCE
$100,001 - $250,000
TBD 4Q 2019 TBD TBD
Cook County
Juvenile Temporary Detention Center - WEARING APPAREL
$100,001 - $250,000
TBD 4Q 2019 TBD TBD
Cook County
Medical Examiner - BODY BAGS $50,001 - $100,000
TBD 4Q 2019 TBD TBD
Cook County
Recorder of Deeds - ACCOUNTING SOFTWARE THAT IS COMPATIBALE WITH INCOMING LAND RECORDS MANAGEMENT CASHIERING SYSTEM.
$50,001 - $100,000
TBD 4Q 2019 TBD TBD
Cook County
Sheriff's Office - FOOD SERVICE - INMATES
$10,000,001 - $20,000,000
TBD 4Q 2019 TBD TBD
Cook County
Transportation and Highways - AZTECA/CITYWORKS SOFTWARE LICENSES AND PROGRAM SERVICES
$100,001 - $250,000
TBD 4Q 2019 TBD TBD
Cook County
Transportation and Highways - JOE ORR RD - TORRENCE TO BURNHAM CONSTRUCTION ENGINEERING RFQ
$1,000,001 - $2,000,000
TBD 4Q 2019 TBD TBD
Cook County
Transportation and Highways - LAKE COOK ROAD BMP MONITORING AND MAINTENANCE
$10,001 - $50,000
TBD 4Q 2019 TBD TBD
Cook County
Transportation and Highways - LAKE COOK ROAD BUFFALO CREEK RELOCATION MAINTENANCE AND MONITORING
$100,001 - $250,000
TBD 4Q 2019 TBD TBD
Cook County
Transportation and Highways - OLD ORCHARD RD - WOOD TO SKOKIE CONSTRUCTION ENGINEERING RFQ
$2,000,001 - $3,000,000
TBD 4Q 2019 TBD TBD
Cook County
Transportation and Highways - PAVEMENT PRESERVATION AND REHABILITATION NORTH 2020
$3,000,001 - $5,000,000
TBD 4Q 2019 TBD TBD
Cook County
Transportation and Highways - PAVEMENT PRESERVATION AND REHABILITATION SOUTH 2020
$3,000,001 - $5,000,000
TBD 4Q 2019 TBD TBD
Cook County
Transportation and Highways - SKOKIE VALLEY TRAIL - LAKE COOK TO VOLTZ CONSTRUCTION ENGINEERING RFQ
$250,001 - $500,000
TBD 4Q 2019 TBD TBD
Forest Preserves of Cook County Contracting Opportunities
63
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Fo
rest Preserves o
f Co
ok C
ou
nty
Agency Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Forest Preserves of Cook County
Commodities Aftermarket agricultural parts
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Aftermarket radiator parts/service
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Allianz MT350 parts Under $10,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Alternators and Starters $10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Ammunition Under $10,000
12 1Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Art Program supplies Under $10,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Auto body repair $50,001 - $100,000
12 1Q 2019 M/WBE Non-Federal
Forest Preserves of Cook County
Commodities Bobcat parts and services
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Boss snow plow parts/service
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Box lunches Under $10,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Briggs and Stratton parts and services
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Chevy parts and services $10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Culvert Piping $10,001 - $50,000
36 1Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Cummins parts and service
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Cylinder repair and replacement
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County Contracting Opportunities
64
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Fo
rest Preserves o
f Co
ok C
ou
nty
Agency Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Forest Preserves of Cook County
Commodities Darley parts and equipment
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Electrofishing Backpack Unit
Under $10,000
12 1Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Electrical Supplies $10,001 - $50,000
12 1Q 2019 Delivery and Parts
Non-Federal
Forest Preserves of Cook County
Commodities Elk Grain Mix Under $10,000
12 1Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Elk Hay Under $10,000
12 1Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Equipment purchases and repairs
$10,001 - $50,000
12 1Q 2019 M/WBE Non-Federal
Forest Preserves of Cook County
Commodities Farm equipment $10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Ford OEM passenger cars and light duty trucks parts and service
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Ford/Motor craft parts and services
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Ford/New Holland tractor parts and service
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities General automotive parts $10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Graveley parts and services
$10,001 - $50,000
12 1Q 2019 M/WBE Non-Federal
Forest Preserves of Cook County
Commodities HVAC Supplies $10,001 - $50,000
12 1Q 2019 Delivery and Parts
Non-Federal
Forest Preserves of Cook County
Commodities Hydraulic hose repair/replacement
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities International parts and service
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities John Deere parts and service
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County Contracting Opportunities
65
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Fo
rest Preserves o
f Co
ok C
ou
nty
Agency Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Forest Preserves of Cook County
Commodities Loadmaster parts $10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Massey Ferguson parts and equipment
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Meyer snow plow parts $10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Misc. Supplies and Equipment
$10,001 - $50,000
12 1Q 2019 M/WBE Non-Federal
Forest Preserves of Cook County
Commodities Monroe parts and service $10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Morbark parts and equipment
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Motorcraft batteries $10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Muffler repair/replacement
$10,001 - $50,000
24 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Nature Education Program supplies
Under $10,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Nuts, bolts, general mechanical supplies
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Office Supplies Under $10,000
12 1Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Oils and Lubricants $10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Plumbing Supplies $10,001 - $50,000
12 1Q 2019 Delivery and Parts
Non-Federal
Forest Preserves of Cook County
Commodities Police Equipment $10,001 - $50,000
12 1Q 2019 M/WBE Non-Federal
Forest Preserves of Cook County
Commodities Police Uniforms $10,001 - $50,000
12 1Q 2019 TBD Non-Federal
Forest Preserves of Cook County
Commodities Postage Under $10,000
12 1Q 2019 M/WBE Non-Federal
Forest Preserves of Cook County Contracting Opportunities
66
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Fo
rest Preserves o
f Co
ok C
ou
nty
Agency Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Forest Preserves of Cook County
Commodities Prentice Forestry parts and equipment
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities SaltDogg and Buyers plow parts
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Smithco parts $10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Steel materials and supplies
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Sterling and Freightliner parts
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Stihl parts and equipment
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Supplies and Equipment $10,001 - $50,000
12 1Q 2019 M/WBE Non-Federal
Forest Preserves of Cook County
Commodities Tires $50,001 - $100,000
12 1Q 2019 M/WBE Non-Federal
Forest Preserves of Cook County
Commodities Transmission repair and replacement
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Trout Stocking $10,001 - $50,000
TBD 1Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Upholstery repair/replacement
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Western snow plow parts/services
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Windshield repair and replacement
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Aquatic Herbicide $10,001 - $50,000
12 2Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Bird Food $10,001 - $50,000
12 2Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Chains, hooks and rigging
$10,001 - $50,000
12 2Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County Contracting Opportunities
67
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Fo
rest Preserves o
f Co
ok C
ou
nty
Agency Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Forest Preserves of Cook County
Commodities Lumber Supplies $10,001 - $50,000
12 2Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Pool Supplies $10,001 - $50,000
12 2Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Prescribed Fire Supplies $10,001 - $50,000
12 2Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Recycled Multiuse Copy Paper
$10,001 - $50,000
12 2Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Stihl Chainsaw Supplies Under $10,000
12 2Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Supply and Delivery Toilet Tissue
$10,001 - $50,000
12 2Q 2019 Janitorial Supplies, Fuel
Non-Federal
Forest Preserves of Cook County
Commodities Trailers and towing supplies
$10,001 - $50,000
12 2Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Ultra-Low Freezer $10,001 - $50,000
12 2Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Welding supplies $10,001 - $50,000
12 2Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Pumpkin purchase Under $10,000
12 3Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Straw program purchase Under $10,000
12 3Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Commodities Baiting Supplies Under $10,000
12 Open Solicitation
Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Ecology supplies Under $10,000
12 Open Solicitation
Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Equipment purchases and repairs
$50,001 - $100,000
12 Open Solicitation
Parts, Labor and Transportation
Non-Federal
Forest Preserves of Cook County
Commodities Fisheries supplies Under $10,000
12 Open Solicitation
Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Other materials, office supplies
$10,001 - $50,000
12 Open Solicitation
Delivery, Supplies
Non-Federal
Forest Preserves of Cook County Contracting Opportunities
68
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Fo
rest Preserves o
f Co
ok C
ou
nty
Agency Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Forest Preserves of Cook County
Commodities Trail amenities, signage, posts
$10,001 - $50,000
12 Open Solicitation
Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Transportation and travel, toll charges
Under $10,000
12 Open Solicitation
Transportation Non-Federal
Forest Preserves of Cook County
Commodities Trap Building Supplies Under $10,000
12 Open Solicitation
Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Wildlife supplies $50,001 - $100,000
12 Open Solicitation
Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Chemistry Control Supplies
Under $10,000
12 TBD Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities Freezer Storage System Under $10,000
12 TBD Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Commodities GPS Tracking collars and location fees
$10,001 - $50,000
12 TBD Delivery Non-Federal
Forest Preserves of Cook County
Construction Overhead Door Repair Services
$10,001 - $50,000
12 1Q 2019 Labor, Parts Non-Federal
Forest Preserves of Cook County
Construction Fencing Repair Services $10,001 - $50,000
12 2Q 2019 Labor, Parts Non-Federal
Forest Preserves of Cook County
Professional Services
ANSI inspections for lift trucks
Under $10,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Professional Services
Association Fees Under $10,000
TBD 1Q 2019 TBD Non-Federal
Forest Preserves of Cook County
Professional Services
Front end alignments $10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Professional Services
Law Enforcement Processing
$10,001 - $50,000
12 1Q 2019 Professional Services
Non-Federal
Forest Preserves of Cook County
Professional Services
Picnic Permit and Membership Reservation Software
$250,001 - $500,000
84 1Q 2019 It services Non-Federal
Forest Preserves of Cook County
Professional Services
Printing Under $10,000
12 1Q 2019 Delivery, Supplies
Non-Federal
Forest Preserves of Cook County
Professional Services
Program support for a variety of activities related at sites around the county
Under $10,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County Contracting Opportunities
69
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Fo
rest Preserves o
f Co
ok C
ou
nty
Agency Contract Type
Project Description Estimated Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Forest Preserves of Cook County
Professional Services
Single canoe program support
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Professional Services
Sponsorship Consultant $50,001 - $100,000
84 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Professional Services
Testing $10,001 - $50,000
12 1Q 2019 Professional Consulting Services
Non-Federal
Forest Preserves of Cook County
Professional Services
Training and Environmental Education
$10,001 - $50,000
12 1Q 2019 Professional Services
Non-Federal
Forest Preserves of Cook County
Professional Services
Veterinary Services Under $10,000
12 1Q 2019 Professional Services
Non-Federal
Forest Preserves of Cook County
Professional Services
Voyaber canoe program support
$10,001 - $50,000
12 1Q 2019 No Stated Goals Non-Federal
Forest Preserves of Cook County
Professional Services
Consulting Services Fundraising - Capital Campaign
$10,001 - $50,000
12 2Q 2019 Professional Consulting Services
Non-Federal
Forest Preserves of Cook County
Professional Services
Digital Records Consultant to Export copy of Paper vision
$10,001 - $50,000
12 2Q 2019 Professional Consulting Services
Non-Federal
Forest Preserves of Cook County
Professional Services
Fire and Intrusion Alarm Maintenance and Monitoring
$500,001 - $1,000,000
36 2Q 2019 Professional Services
Non-Federal
Forest Preserves of Cook County
Professional Services
Software Consultant for Development of new Asset Management Database to Replace Building Data Subscription
$10,001 - $50,000
12 2Q 2019 Professional Consulting Services
Non-Federal
Forest Preserves of Cook County
Professional Services
Vegetation Management $2,000,001 - $3,000,000
60 2Q 2019 Professional Services
Non-Federal
Forest Preserves of Cook County
Professional Services
Hematological testing services
$10,001 - $50,000
TBD TBD Professional Services
Non-Federal
Forest Preserves of Cook County
Professional Services
Unconscious/Implicit Bias Training
$10,001 - $50,000
TBD TBD Professional Services
Non-Federal
Forest Preserves of Cook County
Revenue Generating
Hay Mowing Under $10,000
TBD 3Q 2019 Professional Services
Non-Federal
Illinois Tollway Authority Contracting Opportunities
70
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Illino
is Tollw
ay Au
tho
rity
Agency Contract Type Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
IL Transit Authority
Commodities Crackseal Material Contract
$250,001 - $500,000
36 1Q 2019 TBD Non-Federal
IL Transit Authority
Commodities Electrical Wire and Cable
$50,001 - $100,000 24 1Q 2019 TBD Non-Federal
IL Transit Authority
Commodities Guardrail Parts (Gibraltar, Nucor, SKT, and Trinity)
$100,001 - $250,000
12 1Q 2019 TBD Non-Federal
IL Transit Authority
Commodities Janitorial Supplies $100,001 - $250,000
24 1Q 2019 TBD Non-Federal
IL Transit Authority
Commodities Sand, Stone, and Gravel
$100,001 - $250,000
36 1Q 2019 TBD Non-Federal
IL Transit Authority
Commodities Traffic Control Channelizers
$100,001 - $250,000
36 1Q 2019 TBD Non-Federal
IL Transit Authority
Commodities
Various Work Uniforms, Outerwear, Accessories, and Polo Shirts
$1,000,001 - $2,000,000
TBD 1Q 2019 TBD Non-Federal
IL Transit Authority
Commodities Weather-Treated Wood Sign Posts
$50,001 - $100,000 12 1Q 2019 TBD Non-Federal
IL Transit Authority
Commodities Carbon Monoxide Detectors
$100,001 - $250,000
60 2Q 2019 TBD Non-Federal
IL Transit Authority
Commodities Flares and Fuses $50,001 - $100,000 36 2Q 2019 TBD Non-Federal
IL Transit Authority
Commodities Guardrail Fasteners $50,001 - $100,000 24 2Q 2019 TBD Non-Federal
IL Transit Authority
Commodities Light Poles, Arms, and Bases
$100,001 - $250,000
24 2Q 2019 TBD Non-Federal
IL Transit Authority
Commodities Luminaires and Components
TBD TBD 2Q 2019 TBD Non-Federal
IL Transit Authority
Commodities Replacement Door and Hardware
TBD TBD 2Q 2019 TBD Non-Federal
IL Transit Authority
Commodities Carpentry Supplies TBD TBD 3Q 2019 TBD Non-Federal
Illinois Tollway Authority Contracting Opportunities
71
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Illino
is Tollw
ay Au
tho
rity
Agency Contract Type Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
IL Transit Authority
Commodities
Motorist Warning Devices: Message Signs, Arrow Boards, and Light Towers
$1,000,001 - $2,000,000
12 3Q 2019 TBD Non-Federal
IL Transit Authority
Construction CA Cooling Tower and Chiller Replacement
TBD TBD 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction CTS - Advance ITS Relocations MP 17.8 to 33.7
$5,000,001 - $10,000,000
TBD 1Q 2019 IT Services Tollway
IL Transit Authority
Construction Drainage Improvements on I-90 MP 15.45 to 34.5
TBD TBD 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction Drainage Improvements on I-90 MP 59.55 to 73.1
TBD TBD 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction
Electronic Toll Collection Improvements on I-90 M.P. 12.5
TBD TBD 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction
Grading, Erosion Control and Sluice Gate Repair; I-294 MP 44.3 to 44.6
TBD TBD 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction
Grading, Shoulder Rehab and Retaining Walls MP 30.5 to 33.5
TBD TBD 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction I-294(Grand Ave to Wolf Rd) and I-490 Ramp S2
Over $20,000,000 24 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction
I-57 CD Roads A & C, Dixie Hwy, 147th St & 149th St Retaining Walls north of I-294, Ramp H and Plaza L
Over $20,000,000 24 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction
I-88 Pavement and Structural Preservation IL 56 to IL 59
$5,000,001 - $10,000,000
TBD 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction Illinois Tollway Customer Service Center at CA
$5,000,001 - $10,000,000
TBD 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction M-8 Reconstruction Over $20,000,000 12 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction Mile Long Bridge Package-1
Over $20,000,000 24 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction O'Hare Oasis to Balmoral Ave (Outside Lanes)
Over $20,000,000 12 1Q 2019 All Basic Construction Trades
Tollway
Illinois Tollway Authority Contracting Opportunities
72
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Illino
is Tollw
ay Au
tho
rity
Agency Contract Type Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
IL Transit Authority
Construction Roadway Reconstruction East-West Connector
$10,000,001 - $20,000,000
TBD 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction S/W Landscaping Planting, I-94 MP 13.0 to 22.5
TBD 60 1Q 2019 Landscaping Tollway
IL Transit Authority
Construction
South Tri-State Barrier Wall & Sign Structure Repairs and Bridge Demo MP 3.2 to 14.7
TBD TBD 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction Bridge Improvement BNSF Railroad Bridge
Over $20,000,000 36 2Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction
Deerpath Road Bridge Reconstruction MP 114.2
TBD TBD 2Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction IL-390 and IL-19 Interchange Construction
Over $20,000,000 24 2Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction Landscaping on I-88 US 30 to IL 26 MP 44.0 to 54.25
TBD TBD 2Q 2019 Landscaping Tollway
IL Transit Authority
Construction West Terminal Interchange - Ramp Bridges
Over $20,000,000 24 2Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction FCWRD Sanitary Sewer Relocation
$5,000,001 - $10,000,000
12 3Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction
I-90, Pavement and Structural Preservation & Rehabilitation MP 2.6 to 18.3
TBD 12 3Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction I‐294 (North Avenue to Addison Creek)
Over $20,000,000 12 4Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction I‐490/I‐90 System Interchange
Over $20,000,000 24 4Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Construction Landscaping on I-88 IL 26 to IL 251 MP 54.25 to 76.5
TBD TBD 4Q 2019 Landscaping Tollway
IL Transit Authority
Construction "CTS - Bridge Rehabilitation
TBD TBD TBD TBD TBD
IL Transit Authority
Information & Technology
EMC Hardware, Software, Maintenance Services and Support
$1,000,001 - $2,000,000
36 1Q 2019 TBD Non-Federal
Illinois Tollway Authority Contracting Opportunities
73
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Illino
is Tollw
ay Au
tho
rity
Agency Contract Type Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
IL Transit Authority
Information & Technology
Transponder Packaging and Distribution Services
$10,000,001 - $20,000,000
60 1Q 2019 TBD Non-Federal
IL Transit Authority
Information & Technology
Tripwire Software Maintenance and Support
$500,001 - $1,000,000
36 1Q 2019 TBD Non-Federal
IL Transit Authority
Information & Technology
Security and Toll Audit Video Management System
$1,000,001 - $2,000,000
One-Time Purchase
2Q 2019 TBD Non-Federal
IL Transit Authority
Information & Technology
Payment Card Industry Compliance Analysis
TBD TBD 3Q 2019 TBD Non-Federal
IL Transit Authority
Information & Technology
System Integrator Services
TBD TBD 3Q 2019 TBD Non-Federal
IL Transit Authority
MP 31.05 to 33.18"
$5,000,001 - $10,000,000
TBD 1Q 2019 All Basic Construction Trades
Tollway
IL Transit Authority
Professional Services
Non-Illinois License Plate Registration Retrieval Services
TBD TBD 1Q 2019 TBD Non-Federal
IL Transit Authority
Professional Services
Workers Compensation Claim Administration Services
$500,001 - $1,000,000
60 1Q 2019 TBD Non-Federal
IL Transit Authority
Vehicles & Heavy Equipment
Light-Duty Trucks $1,000,001 - $2,000,000
12 2Q 2019 TBD Non-Federal
IL Transit Authority
Vehicles & Heavy Equipment
Medium-Duty Trucks $250,001 - $500,000
60 2Q 2019 TBD Non-Federal
IL Transit Authority
Vehicles & Heavy Equipment
Mowing Tractors and Equipment
TBD 12 2Q 2019 TBD Non-Federal
IL Transit Authority
Work Services Building Glass Repair Services
$100,001 - $250,000
24 1Q 2019 TBD Non-Federal
IL Transit Authority
Work Services Health Fair Screenings
$100,001 - $250,000
60 1Q 2019 TBD Non-Federal
IL Transit Authority
Work Services
Landscaping on I-88 IL 251 to Kishwaukee River Bridge MP 76.5 to 91.62
TBD 48 1Q 2019 Landscaping Tollway
IL Transit Authority
Work Services
Landscaping on I-88 IL 251 to Kishwaukee River Bridge MP 76.5 to 91.62
TBD TBD 1Q 2019 Landscaping Tollway
Illinois Tollway Authority Contracting Opportunities
74
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Illino
is Tollw
ay Au
tho
rity
Agency Contract Type Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
IL Transit Authority
Work Services S/W Landscaping Planting, I-90 MP 3.3 to 13.0
TBD 48 1Q 2019 Landscaping Tollway
IL Transit Authority
Work Services S/W Landscaping Planting, I-94 MP 1.0 to 13.0
TBD 60 1Q 2019 Landscaping Tollway
IL Transit Authority
Work Services Stroke Screening Services
TBD 36 1Q 2019 TBD Non-Federal
IL Transit Authority
Work Services Navistar Truck Repair Services
$250,001 - $500,000
24 2Q 2019 TBD Non-Federal
IL Transit Authority
Work Services Safe Repair and Maintenance Services
TBD TBD 2Q 2019 TBD Non-Federal
IL Transit Authority
Work Services UPS, Generator, and ATS Maintenance and Repair Services
$1,000,001 - $2,000,000
36 3Q 2019 TBD Non-Federal
Illinois Tollway Bid Letting Schedule https://www.illinoistollway.com/documents/20184/86505/Construction+Bid+Letting+Schedule/9daeb74d-04df-43b1-988f-3c1a9a6c9832 Illinois Tollway Online Plan Room https://www.illinoistollwaybidding.com/ Illinois Tollway Professional Services Look Ahead Schedule https://www.illinoistollway.com/documents/20184/87722/PSB+Look+Ahead+Tentative+Schedule_March+2017/2833d1df-5e49-48cc-87ee-09b48d9985d5
State of Illinois Contracting Opportunities
75
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
State o
f Illino
is
Department Contract Type
Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Aging IFB IT Resources $832,000.00 24 1Q 2019 YES TBD
Aging RFP CCU Time and Rate Study
$500,000.00 36 1Q 2019 YES TBD
Aging RFP AAA Quality Review $600,000.00 36 2Q 2019 YES TBD
CMS- BOSS IFB ROCK SALT, BULK - FY'20 CY'19-'20
$70,000,000.00 24 TBD YES TBD
CMS-BOSS IFB Asbestos Assessment - Statewide
$200,000.00 60 1Q 2019 TBD TBD
CMS-BOSS IFB Auto Glass Repair & Replacement
$345,000.00 36 1Q 2019 TBD TBD
CMS-BOSS IFB Auto Glass Repair & Replacement
$345,000.00 36 1Q 2019 TBD TBD
CMS-BOSS IFB HVAC Southern Region
$500,000.00 60 1Q 2019 TBD TBD
CMS-BOSS IFB Roofing Services - Northern Region
$500,000.00 60 1Q 2019 TBD TBD
CMS-BOSS IFB Roofing Services - Central Region
$500,000.00 60 1Q 2019 TBD TBD
CMS-BOSS IFB Collection Cups for Random Drug Testing
$825,000.00 48 1Q 2019 TBD TBD
CMS-BOSS IFB Court Reporting Services
$1,000,000.00 36 1Q 2019 YES TBD
CMS-BOSS IFB HVAC Central Region
$1,000,000.00 60 1Q 2019 TBD TBD
CMS-BOSS IFB Roofing Services - Chicago Area
$1,000,000.00 60 1Q 2019 TBD TBD
CMS-BOSS IFB Surplus Management $2,000,000.00 120 1Q 2019 YES TBD
State of Illinois Contracting Opportunities
76
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
State O
f Illino
is
Department Contract Type
Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
CMS-BOSS IFB LENS BLANKS - ICI $2,501,310.00 24 1Q 2019 TBD TBD
CMS-BOSS IFB MC LAB GASES-CYLINDER,BULK,RENTALS
$3,006,839.14 72 1Q 2019 TBD TBD
CMS-BOSS IFB MC TIRES $18,520,000.00 48 1Q 2019 TBD TBD
CMS-BOSS IFB VIRGIN/RECYCLE COPY PAPER
$19,000,000.00 72 1Q 2019 YES TBD
CMS-BOSS IFB Carpentry Services Central Region - Statewide Master
$500,000.00 60 2Q 2019 TBD TBD
CMS-BOSS IFB MC CORRUGATED BOXES
$1,715,555.00 48 2Q 2019 TBD TBD
CMS-BOSS IFB
VENDING EQUIP FOR DHS BUSINESS ENTERPRISE PRGM FOR BLIND
$2,562,100.00 24 2Q 2019 TBD TBD
CMS-BOSS IFB Waste Hauling - Statewide Master
$3,500,000.00 60 2Q 2019 TBD TBD
CMS-BOSS IFB Lab Supplies, Chemicals & Equipment
$12,500,000.00 72 2Q 2019 TBD TBD
CMS-BOSS IFB Truck Fleet Overflow Repair
$35,000,000.00 60 2Q 2019 YES TBD
CMS-BOSS IFB Painting Services - Chicago Region
$200,000.00 60 3Q 2019 TBD TBD
CMS-BOSS IFB Wearing Apparel, Institutional
$450,000.00 48 3Q 2019 TBD TBD
CMS-BOSS IFB Gloves, Exam and Disposable
$1,200,000.00 36 3Q 2019 TBD TBD
CMS-BOSS IFB Snow Removal - Central Region
$150,000.00 60 4Q 2019 TBD TBD
CMS-BOSS IFB Uniforms, Staff - IDOC
$3,600,000.00 24 4Q 2019 TBD TBD
CMS-BOSS RFP Fleet & Business Mobility Leasing Solution
$200,000,000.00 120 1Q 2019 YES TBD
State of Illinois Contracting Opportunities
77
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
State o
f Illino
is
Department Contract Type
Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
CMS-BOSS RFP Fleet & Business Mobility Leasing Solution
$200,000,000.00 120 1Q 2019 YES TBD
CMS-BOSS RFP
Insurance Brokerage Services
$2,000,000.00 60 2Q 2019 YES TBD
DCFS IFB Mobile Fingerprint Scanner Software
$350,000.00 48 2Q 2019 TBD TBD
DCFS IFB Mobile Fingerprint Scanner Software
$350,000.00 48 2Q 2019 TBD TBD
DCFS IFB GAAP Assistance $325,000.00 60 3Q 2019 TBD TBD
DCFS IFB GAAP Assistance $325,000.00 60 3Q 2019 TBD TBD
DCFS RFP Medical Director $1,500,000.00 120 1Q 2019 TBD TBD
DCFS RFP Medical Director $1,500,000.00 120 1Q 2019 TBD TBD
DCFS RFP Licensing Unit Data Entry Consulting
$2,800,000.00 36 2Q 2019 YES TBD
DCFS RFP CCWIS Business Process Redesign
$3,600,000.00 36 2Q 2019 TBD TBD
DCFS RFP CCWIS Business Process Redesign
$3,600,000.00 36 2Q 2019 TBD TBD
DCFS RFP CCWIS Systems Integrator
$5,000,000.00 48 2Q 2019 Yes TBD
DCFS RFP CCWIS Systems Integrator
$5,000,000.00 48 2Q 2019 TBD TBD
DCFS RFP OITS Staff Augmentation
$9,600,000.00 48 2Q 2019 TBD TBD
DCFS RFP OITS Staff Augmentation
$9,600,000.00 48 2Q 2019 TBD TBD
DCFS RFP Children’s SSI Application Services
$12,000,000.00 120 2Q 2019 Yes TBD
State of Illinois Contracting Opportunities
78
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
State O
f Illino
is
Department Contract Type
Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
DCFS RFP Children’s SSI Application Services
$12,000,000.00 120 2Q 2019 YES TBD
DCFS RFP CCWIS Case Management
$18,000,000.00 120 2Q 2019 Yes TBD
DCFS RFP CCWIS Provider Management
$18,000,000.00 120 2Q 2019 Yes TBD
DCFS RFP CCWIS Case Management
$18,000,000.00 120 2Q 2019 YES TBD
DCFS RFP CCWIS Provider Management
$18,000,000.00 120 2Q 2019 YES TBD
DHS IFB Large Format Printer w/ Maintenance for DHS Print Shop
$25,000.00 36 1Q 2019 YES TBD
DHS IFB
Forklift Repair & Maintenance for Downstate Warehouse
$10,000.00 36 2Q 2019 TBD TBD
DHS IFB Mailing Machine/Equipment
$700,000.00 12 2Q 2019 YES TBD
DHS IFB Nurse Investigator $1,800,000.00 60 2Q 2019 YES TBD
DHS IFB
Prescription Medicine Program, connecting care providers to one another through internet
$4,800,000.00 24 2Q 2019 YES TBD
DHS IFB 16' Box Truck for Des Plaines Warehouse
$75,000.00 1 4Q 2019 TBD TBD
DHS RFP DRS HSP Personal Assistant Training Program
$7,282,200.00 108 2Q 2019 YES TBD
DHS RFP Permanent Supportive Housing Consultant
$1,120,000.00 60 3Q 2019 YES TBD
DoIT IFB Docuware Software Licensing and Maintenance
$600,000.00 60 1Q 2019 TBD TBD
DoIT IFB Multi-Functional Device Leases
$90,000,000.00 120 1Q 2019 TBD TBD
DoIT IFB
ITRP Business and Process Analysis IT/Telecom Billing IFB
$200,000.00 24 2Q 2019 TBD TBD
State of Illinois Contracting Opportunities
79
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
State o
f Illino
is
Department Contract Type
Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
DoIT IFB ITRP Enterprise Licensing Program Technical Support
$1,000,000.00 24 2Q 2019 TBD TBD
DoIT IFB ITRP Enterprise Licensing Program Management
$1,000,000.00 24 2Q 2019 TBD TBD
DoIT IFB
ITRP Enterprise Licensing Program Application Development
$1,000,000.00 24 2Q 2019 TBD TBD
DoIT RFP Digital Kiosks TBD 120 1Q 2019 TBD TBD
DoIT RFP VoIP & Cisco Equipment and Services
$230,000,000.00 120 2Q 2019 TBD TBD
DoIT RFP Session Initiation Protocol (SIP) Trunk
$30,000,000.00 120 3Q 2019 TBD TBD
EPA IFB Household Hazardous Waste
$10,000,000.00 84 1Q 2019 TBD TBD
EPA RFP Total Daily Maximum Loads
$500,000.00 60 1Q 2019 TBD TBD
EPA RFP GAAP Accounting $550,000.00 84 1Q 2019 TBD TBD
EPA RFP Corrective Action Contractors
$100,000,000.00 108 1Q 2019 YES TBD
IDNR Land Mgmt. - 20 pickup trucks
$900,000.00 6 2Q 2019 TBD TBD
IDNR IFB Land Mgmt. - 15 cabins
$750,000.00 18 3Q 2019 TBD TBD
IDOC/ICI IFB Purchase of Filing Cabinet Kits
$100,000.00 36 1Q 2019 TBD TBD
IDOC/ICI IFB Purchase of Stacking Chair Kits
$100,000.00 36 2Q 2019 TBD TBD
IDOC/ICI IFB Purchase of Task Chair Kits
$240,000.00 36 2Q 2019 TBD TBD
IDOC/IDJJ IFB Commissary Items unknown 36 3Q 2019 Yes TBD
State of Illinois Contracting Opportunities
80
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
State O
f Illino
is
Department Contract Type
Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
IDOC/IDJJ IFB Chillers unknown 36 3Q 2019 TBD TBD
IDOC/IDJJ IFB Pest Control unknown 60 3Q 2019 TBD TBD
IDOC/IDJJ IFB Cable TV/Satellite Services
unknown 60 3Q 2019 TBD TBD
IDOC/IDJJ IFB Fire Extinguisher Maintenance
unknown 60 3Q 2019 TBD TBD
IDOC/IDJJ TBD Generators unknown 36 3Q 2019 TBD TBD
IDOR IFB Data Analytics $900,000.00 9 1Q 2019 TBD TBD
IDOR IFB IT - Automated System Testing Tool
$1,000,000.00 12 3Q 2019 TBD TBD
IDOT IFB Barriers, Median Separator Systems
$100,000.00 36 1Q 2019 TBD TBD
IDOT IFB Chain & Hook $180,000.00 24 1Q 2019 TBD TBD
IDOT IFB Attenuator, Crash Cushion
$400,000.00 36 1Q 2019 TBD TBD
IDOT IFB Steel Tubular Posts $800,000.00 24 1Q 2019 TBD TBD
IDOT RFP
Federal Compliance Reviews for Rural Grantees - This service shall review how well Illinois’ 45-50 rural and small urbanized grantees comply with Sections 5311, 5311(f), and Downstate Operating Assistance Program (DOAP) requirements as well as develop a compliance report for each of these Grantees.
$800,000.00 60 1Q 2019 YES TBD
State of Illinois Contracting Opportunities
81
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
State o
f Illino
is
Department Contract Type
Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
IDOT RFP
General Planning & Performance Management Services - shall provide expertise and assistance in all aspects of transportation planning, performance management, and development of state and federal competitive grant applications.
$5,500,000.00 108 1Q 2019 YES TBD
IDOT RFP
Automated License Plate Reader - The Services provide hardware, software installation of an automated license recognition & USDOT number recognition (ALPR) system at the I55/70 Maryville weigh station.
$1,900,000.00 72 3Q 2019 YES TBD
IDOT RFP
IT Audit - This audit services reviews the design of major new electronic data processing systems & major modifications for adequate audit trails & accountability.
$586,000.00 48 4Q 2019 YES TBD
IDPH RFP Family Planning Data and Billing System
$700,000.00 120 1Q 2019 YES TBD
IDPH RFP
Laboratory Information Management System (LIMS)
$1,920,000.00 120 1Q 2019 YES TBD
IDPH RFP Trauma Registry System
$3,750,000.00 120 1Q 2019 YES TBD
IDPH RFP HIV/AIDS Integrated Data System
$8,143,500.00 120 1Q 2019 YES TBD
IDPH RFP Environmental Health Licensing System
$3,700,000.00 120 2Q 2019 YES TBD
IDPH RFP Vital Records (Births/Deaths) System
$14,000,000.00 120 2Q 2019 YES TBD
State of Illinois Contracting Opportunities
82
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
State O
f Illino
is
Department Contract Type
Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
IDPH RFP Medical Cannabis Information System
$6,000,000.00 120 3Q 2019 YES TBD
IDVA IFB Paratransit Shuttle Bus - Manteno Home
$110,000.00 12 1Q 2019 TBD TBD
IDVA IFB Air Mattress Rentals - Manteno
$160,000.00 24 1Q 2019 TBD TBD
IDVA IFB
Shower Room Plumbing Replacement and Tile Repair - Manteno
$180,000.00 12 1Q 2019 TBD TBD
IDVA IFB Permanent Overhead Lifts & Installation- Manteno
$250,000.00 12 1Q 2019 TBD TBD
IDVA IFB
Solar Powered Hydrants and Mixing Valve Installations - Manteno
$400,000.00 12 1Q 2019 TBD TBD
IDVA IFB Coffee Shop - Quincy Home
$1,000,000.00 120 1Q 2019 TBD TBD
IDVA IFB Mattresses - Quincy $150,000.00 12 2Q 2019 TBD TBD
IDVA IFB Food Service Contract - Manteno Home
$15,000,000.00 60 3Q 2019 TBD TBD
IDVA RFP Electronic Medical Records Database - Whole Agency
$2,000,000.00 120 2Q 2019 TBD TBD
IHDA IFB Offsite Document Storage
$1,200,000.00 120 1Q 2019 TBD TBD
IHDA RFP
Property Management & Construction Management Services
$500,000.00 36 1Q 2019 YES TBD
IHDA RFP Cloud File Electronic Archival and Search
$2,500,000.00 120 2Q 2019 YES TBD
IHDA RFP Mortgage Loan Outside Quality Control
$2,400,000.00 120 3Q 2019 TBD TBD
IHDA RFP Lender Oversight $500,000.00 120 4Q 2019 TBD TBD
Illinois State Police
IFB Augmented Reality Mapping System
$300,000.00 5 1Q 2019 TBD TBD
State of Illinois Contracting Opportunities
83
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
State o
f Illino
is
Department Contract Type
Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
Illinois State Police
IFB Oracle Database Appliance
$250,000.00 12 2Q 2019 TBD TBD
Illinois State Police
IFB Raincoats $375,000.00 24 2Q 2019 TBD TBD
Illinois State Police
IFB Ford Expedition EL $464,000.00 12 2Q 2019 TBD TBD
Illinois State Police
IFB Miscellaneous Vehicle Purchase
$5,700,000.00 36 2Q 2019 TBD TBD
Illinois State Police
IFB Next Generation 9-1-1 Equipment
$20,000,000.00 120 2Q 2019 TBD TBD
Illinois State Police
IFB Maintenance of DNA Equipment
$500,000.00 60 3Q 2019 Yes TBD
Illinois State Police
IFB DNA Robot Maintenance
$500,000.00 60 3Q 2019 Yes TBD
Illinois State Police
IFB Scanning Electron Microscope Purchase
$1,200,000.00 24 3Q 2019 TBD TBD
Illinois State Police
RFP Next Generation 9-1-1 System
$200,000,000.00 120 2Q 2019 TBD TBD
ISAC RFP Online Tutoring $735,000.00 84 1Q 2019 TBD TBD
ISBE RFP Youth Risk Behavior Surveys
$365,000.00 60 1Q 2019 YES TBD
ISBE RFP
Administrative Reviews for child Nutrition Program Appeals
$600,000.00 72 1Q 2019 YES TBD
ISBE RFP Data Warehouse Data Analysts (2)
$1,520,000.00 48 1Q 2019 YES TBD
ISBE RFP SharePoint SW Developers
$1,700,000.00 60 1Q 2019 YES TBD
ISBE RFP Student Information System (SIS) Project
$6,000,000.00 60 1Q 2019 YES TBD
ISBE RFP Evaluation of Career and Technical Education Program
$3,000,000.00 60 2Q 2019 YES TBD
State of Illinois Contracting Opportunities
84
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
State O
f Illino
is
Department Contract Type
Project Description Estimated
Value
Estimated Term
(Months)
Anticipated Ad Date
Subcontractor Opportunities
Funding Source
ISBE RFP Illinois Science Assessment
$10,000,000.00 60 2Q 2019 YES TBD
LABOR TBD GAAP accounting $20,000.00 TBD TBD TBD TBD
Lottery (458) RFP
Systems Testing and Certification Services - independent, 3rd party, System Quality Assurance and certification services related to Lottery's transition of our Central Gaming System provider.
$550,000.00 60 TBD TBD TBD
Lottery (458) RFP Legal Services $4,000,000.00 24 TBD TBD TBD
Illinois Procurement Bulletin: www.purchase.state.il.us/ Illinois Capitol Development Procurement Bulletin Board: https://www2.illinois.gov/cdb/procurement/ Illinois Public Institutions of Higher Education Procurement Bulletin Board: www.procure.stateuniv.state.il.us Illinois Department of Transportation Procurement Bulletin Boards: Engineering, Architectural & Professional Services http://www.idot.illinois.gov/doing-business/procurements/engineering-architectural-professional-services/ Land Acquisition Services http://www.idot.illinois.gov/doing-business/procurements/land-acquisition-services/ Construction Services http://www.idot.illinois.gov/doing-business/procurements/construction-services/ Construction Letting and Bidding https://webapps.dot.illinois.gov/WCTB/LbHome Contractors Bulletin http://www.idot.illinois.gov/doing-business/procurements/construction-services/construction-bulletins/contractors-bulletin/index IDOT Chief Procurement Office https://www2.illinois.gov/cpo/dot/
Assist Agencies 85
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Assist Agencies are comprised of not-for-profit agencies and/or chamber of commerce agencies that represent the interest of small, minority and/or women owned businesses.
51st Street Business Association * 220 E. 51st Street Chicago, IL 60615 Phone: 773-285-3401 Fax: 773-285-3407 Email: [email protected] Web: www.51stStreetChicago.com Maintains list of certified firms: Yes Provides training for businesses: Yes
African American Contractors Association - AACA P.O. Box #19670 Chicago, IL 60619 Phone: 312-915-5960 Email: [email protected] Web: www.aacanatl.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Angel of God Resource Center, Inc. 14527 S. Halsted Chicago, IL 60827 Phone: 708-392-9323 Fax: 708-880-0121 Email: [email protected]; [email protected] Web: www.angelofgodresourcecenter.org Maintains list of certified firms: No Provides training for businesses: Yes
Association of Asian Construction Enterprises * 5677 W. Howard Niles, IL 60714 Phone: 847-673-7377 Fax: 847-673-2358 Email: [email protected] Maintains list of certified firms: Yes Provides training for businesses: Yes
Austin African American Business Networking Assoc. 5820 W. Chicago Ave., Chicago, IL 60651 Phone: 773-626-4497 Email: [email protected] Web: www.aaabna.org Maintains list of certified firms: No Provides training for businesses: Yes
Black Contractors Owners and Executives * 7811 S. Stony Island Ave. Chicago, IL 60649 Phone: 773-346-5658 Fax: 773-346-5659 Email: [email protected] Web: www.bcoechicago.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Black Contractors United * 12000 S. Marshfield Ave. Calumet Park, IL 60827 Phone: 708-389-5730 Fax: 708-389-5735 Email: [email protected] Web: www.blackcontractorsunited.com Maintains list of certified firms: Yes Provides training for businesses: Yes
Business Leadership Council * 230 W. Monroe Street, Ste 2650 Chicago, IL 60606 Phone: 312-628-7844 Fax: 312-628-7843 Email: [email protected] Web: www.businessleadershipcouncil.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Center for Community Development Initiatives * 8016 S. Halsted Street Chicago, IL 60620 Phone: 872-205-5821 Email: [email protected] Web: www.ccdiil.org Maintains list of certified firms: Yes Provides training for businesses: Yes
LGBT Chamber of Commerce of Illinois * 3179 N. Clark St., 2nd Floor Chicago, IL 60657 Phone: 773-303-0167 Fax: 773-303-0168 Email: [email protected] Web: www.lgbtcc.com Maintains list of certified firms: Yes Provides training for businesses: Yes
Chatham Business Association Small Business Dev.* 800 E. 78th Street Chicago, IL 60619 Phone: 773-994-5006 Fax: 773-855-8905 Email: [email protected] Web: www.cbaworks.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Chicago Minority Supplier Development Council Inc. * 105 W. Adams, Suite 2300 Chicago, IL 60603-6233 Phone: 312-755-2550 Fax: 312-755-8890 Email: [email protected] Web: www.chicagomsdc.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Assist Agencies 86
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Chicago Urban League * 4510 S. Michigan Ave. Chicago, IL 60653 Phone: 773-624-8810 Fax: 773-451-3579 Email: [email protected] Web: www.cul-chicago.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Chicago Women in Trades (CWIT) 2444 W. 16th Street Chicago, IL 60608 Phone: 312-942-1444 Jayne Vellinga, Executive Director Email: [email protected] Web: www.chicagowomenintrades2.org Maintains list of certified firms: No Provides training for businesses: Yes
Contractor Advisors Business Development Corp. * 1507 E. 53rd Street, Suite 906 Chicago, IL. 60615 Phone: 312-436-0301 Email: [email protected] Web: www.contractoradvisors.us Maintains list of certified firms: Yes Provides training for businesses: Yes
Cosmopolitan Chamber of Commerce 1633 S. Michigan Avenue Chicago, IL. 60616 Phone: 312-971-9594 Fax: 312-341-9084 Email: [email protected] Web: www.cosmochamber.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Do For Self Community Development Co. * 7447 S South Shore Drive, Unit 22B Chicago, IL 60649 Phone: 773-356-7661 Email: [email protected] Web: www.doforself.org Maintains list of certified firms: No Provides training for businesses: Yes
Far South Community Development Corporation 9923 S. Halsted Street, Suite D Chicago, IL 60628 Phone: 773-941-4833 Fax: 773-941-5252 Email: [email protected] Web: www.farsouthcdc.org Maintains list of certified firms: No Provides training for businesses: Yes
Federation of Women Contractors * 216 W. Jackson Blvd. #625 Chicago, IL 60606 Phone: 312-360-1122 Fax: 312-750-1203 Email: [email protected] Web: www.fwcchicago.com Maintains list of certified firms: Yes Provides training for businesses: Yes
Fresh Start Home Community Development Corp. 5168 S. Michigan Avenue, 4N Chicago, IL 60615 Phone: 312-632-0811 Fax: 855-270-4175 Email: [email protected] Web: www.FreshStartNow.us Maintains list of certified firms: Yes Provides training for businesses: Yes
Greater Englewood Community Development Corp. * 815 W. 63rd Street Chicago, IL 60621 Phone: 773-651-2400 Fax: 773-651-2400 Email: [email protected] Web: www.greaterenglewoodcdc.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Greater Pilsen Economic Development Assoc. * 1801 S. Ashland Chicago, IL 60608 Phone: 312-698-8898 Email: [email protected] Web: www.greaterpilsen.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Greater Far South Halsted Chamber of Commerce * 10615 S. Halsted Street Chicago, IL 60628 Phone: 518-556-1641 Fax: 773-941-4019 Email: [email protected] Web: www.greaterfarsouthhalstedchamber.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Greater Southwest Development Corporation 2601 W. 63rd Street Chicago, IL 60629 Phone: 773-362-3373 Fax: 773-471-8206 Email: [email protected] Web: www.greatersouthwest.org Maintains list of certified firms: No Provides training for businesses: Yes
Assist Agencies 87
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Hispanic American Construction Industry Association (HACIA) * 650 W. Lake St., Unit 415 Chicago, IL 60661 Phone: 312-575-0389 Fax: 312-575-0544 Email: [email protected] Web: www.haciaworks.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Illinois Hispanic Chamber of Commerce * 222 Merchandise Mart Plaza, Suite 1212 c/o 1871 Chicago, IL 60654 Phone: 312-425-9500 Email: [email protected] Web: www.ihccbusiness.net Maintains list of certified firms: Yes Provides training for businesses: Yes
Illinois State Black Chamber of Commerce * 411 Hamilton Blvd., Suite 1404 Peoria, Illinois 61602 Phone: 309-740-4430 / 773-294-8038 Fax: 309-672-1379 Email: [email protected]; [email protected] www.illinoisblackchamberofcommerce.org Maintains list of certified firms: Yes Provides training for businesses: Yes
JLM Business Development Center* 2622 W. Jackson Boulevard Chicago, IL 60612 Phone: 773-826-3295 Fax: 773-359-4021 Email: [email protected] Web: www.jlmcenter.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Latin American Chamber of Commerce * 3512 W. Fullerton Avenue Chicago, IL 60647 Phone: 773-252-5211 Fax: 773-252-7065 Email: [email protected] Web: www.LACCUSA.com Maintains list of certified firms: Yes Provides training for businesses: Yes
National Association of Women Business Owners * 500 Davis Street, Ste 812 Evanston, IL 60201 Phone: 773-410-2484 Fax: 847-328-2018 Email: [email protected] Web: www.nawbochicago.org Maintains list of certified firms: Yes Provides training for businesses: Yes
National Black Wall Street * 4655 S. King Drive, Suite 203 Chicago, IL 60653 Phone: 773-268-6900 Fax: 773-392-0165 Email: [email protected] Web: www.nationalblackwallstreetchicago.org Maintains list of certified firms: Yes Provides training for businesses: Yes
National Organization of Minority Engineers (NOME)* 33 W. Monroe, Suite 1540 Chicago, IL 60603 Phone: 312-960-1239 Email: [email protected] Web: www.nomeonline.org Maintains list of certified firms: Yes Provides training for businesses: Yes
NDIGO Foundation 329 W. 18th Street, Ste 613 Chicago, IL 60616 Phone: 312-264-6272 Email: [email protected] Web: www.ndigo.com Maintains list of certified firms: No Provides training for businesses: Yes
Neighborhood Development Services, NFP * 10416 South Maryland Avenue Chicago, IL 60628 Phone: 773-413-9348 Fax: 773-371-0032 Email: [email protected] Web: www.ndsnfp.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Public Narrative 600 S. Michigan Avenue Chicago, IL 60605 Phone: 312-369-6400 Email: [email protected] Web: www.publicnarrative.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Rainbow/PUSH Coalition * 930 E. 50th Street Chicago, IL 60615 Phone: 773-256-2768 Fax: 773-373-4103 Email: [email protected] Web: www.rainbowpush.org Maintains list of certified firms: Yes Provides training for businesses: No
Assist Agencies 88
This guide has been prepared for information purposes and to serve as a reference for future contracting opportunities. This plan may be revised at any time without notice.
Real Men Charities, Inc. 2423 E. 75th Street Chicago, IL 60649 Phone: 773-425-4113 Email: [email protected] Web: www.realmencook.com Maintains list of certified firms: No Provides training for businesses: Yes
RTW Veteran Center 7415 E. End, Suite 120 Chicago, IL 60649 Phone: 773-406-1069 Fax: 866-873-2494 Email: [email protected] Web: www.rtwvetcenter.org Maintains list of certified firms: Yes Provides training for businesses: Yes
South Shore Chamber, Inc. * 1750 E. 71st Street Chicago, IL 60649-2000 Phone: 773-955- 9508 Tonya Trice, Executive Director Email: [email protected] Web: www.southshorechamberinc.org Maintains list of certified firms: Yes Provides training for businesses: Yes
St. Paul Church of God in Christ Community Development Ministries, Inc. (SPCDM) 4550 S. Wabash Avenue Chicago, IL. 60653Phone: Phone: 773-538-5120 Fax: 773-538-5125 Email: [email protected] Web: www.stpaulcdm.org Maintains list of certified firms: No Provides training for businesses: Yes
Sustainable Options for Urban Living, Inc. (SOUL) 11603 S. Throop Street Chicago, IL 60643 Phone: 773-250-1770 Ext 702 Email: [email protected] Web: www.soul-program.com Maintains list of certified firms: Yes Provides training for businesses: Yes
The Monroe Foundation 1547 South Wolf Road Hillside, Illinois 60162 Phone: 773-315-9720 Email: [email protected] Web: www.themonroefoundation.org Maintains list of certified firms: No Provides training for businesses: Yes
Turn 2 Growth 15475 S. Park South Holland, IL 60473 Phone: 708-913-4700 Fax: 708-880-1583 Email: [email protected] Web: www.turn2growth.org Maintains list of certified firms: Yes Provides training for businesses: Yes
US Minority Contractors Association, Inc. * 1250 Grove Ave. Suite 200 Barrington, IL 60010 Phone: 847-708-1597 Fax: 847-382-1787 Email: [email protected] Web: www.USMinorityContractors.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Women’s Business Development Center * 8 S. Michigan Ave., 4th Floor Chicago, IL 60603 Phone: 312-853-3477 Fax: 312-853-0145 Email: [email protected] Web: www.wbdc.org Maintains list of certified firms: Yes Provides training for businesses: Yes
Urban Broadcast Media, Inc. 4108 S. King Drive, Chicago, IL 60653 Phone: 312-614-1075 Email: [email protected] Web: www.urbanbroadcastmedia.org Maintains list of certified firms: No Provides training for businesses: Yes
Women Construction Owners & Executives (WCOE) * Chicago Caucus 308 Circle Avenue Forest Park, IL 60130 Phone: 708-366-1250 Email: [email protected] Web: www.wcoeusa.org Maintains list of certified firms: Yes Provides training for businesses: No
Your Community Consultants Foundation 9301 S. Parnell Ave., Chicago, IL 60620 Phone: 773-224-9299 Fax: 773-371-0032 Email: [email protected] Maintains list of certified firms: No Provides training for businesses: Yes
GOVERNMENT PROCUREMENT COMPLIANCE (GPC) FORUM
Collectively, our regional governments procure a wealth of goods and services annually. By making our processes more streamlined, standardized, equitable, and transparent, we are not only creating an environment in which businesses of all sizes can flourish, but will be better stewards of taxpayer dollars.
In January 2014, under the leadership of Mayor Rahm Emanuel, the City of Chicago Department of Procurement Services (DPS) initiated a series of meetings with the City’s sister agencies and invited County, State and Federal government as well as the Affirmative Action Advisory Board and non-profit assist agencies representing the vendor community.
These meetings have grown into the Government Procurement Compliance (GPC) Forum, a strategic planning effort, which entails the formation a number of working subcommittees tasked with researching and reviewing best practices and recommending solutions to shared challenges.
One of the objectives of the GPC for its participating agencies was to rollout this unified quarterly buying plan across the City, its sister agencies, as well as the County and State, so that vendors can better plan for bidding on government business.
The GPC Forum includes:
• Over 60 participants
• Over 40 government entities and non-profit assist agencies representing local small minority andwomen-owned businesses
• Members of the Affirmative Action Advisory Board
• Members from the Office of the Inspector General
• 4 working subcommittees: Legal Issues/Payments; Transparency, Outreach & Capacity Building forVendors; Certification, Compliance & Good Faith Efforts, and Transportation
Subcommittees are made up of a mix of government institutions and assist agencies to foster an environment of collaboration and inclusion.
GPC Forum MISSION
Drive bold, cross-agency improvements to make our region the benchmark for procurement, certification, and compliance processes that are
streamlined, standardized, equitable and transparent.
89
Participating Government and Procurement Institutions
• City of Chicago
• Chicago Housing Authority
• Chicago Park District
• Chicago Transit Authority
• City Colleges of Chicago
• Chicago Public Schools
• Public Building Commission
• Chicago Board of Elections
• Cook County Forest Preserves
• Cook County Procurement &Compliance
• Illinois Comptroller
• Illinois State Treasurer
• Illinois Tollway
• Metra
• Metropolitan Pier & ExpositionAuthority
• Metropolitan Water ReclamationDistrict
• State of Illinois
• U.S. Small Business Administration
• U.S. General Services Administration
Participating Assist Agencies
• Black Contractors United
• Chatham Business Association
• Chicago Minority Supplier Development Council
• Chicago Urban League
• Chicago Women in Trades
• Contractor Advisors Business Development Corp.
• Cosmopolitan Chamber of Commerce
• Do For Self Community Development
• Far South Community Development Corporation
• Federation of Women Contractors
• Greater Far South Halsted Chamber of Commerce
• Greater Southwest Development Corporation
• Hispanic American Construction Industry Association (HACIA)
• Illinois Hispanic Chamber of Commerce
• Illinois State Black Chamber of Commerce
• LGBT Chamber of Commerce of Illinois
• National Organization of Minority Engineers (NOME)
• Rainbow PUSH
• Real Men Charities, Inc.
• RTW Veteran Center
• South Shore Chamber, Inc.
• St. Paul Church of God in Christ Community Development Ministries, Inc. (SPCDM)
• The Monroe Foundation
• U.S. Minority Contractors Association
• Women’s Business Development Center
• Women Construction Owners and Executives
90
D E P A R T M E N T O F
PROCUREMENT SERVICES
C I T Y O F C H I C A G O
Special thanks to Reverend J.L. Miller and the JLM Life Center for hosting the 2019 Construction Summit.
The JLM Center brings the local community together through enrichments and positive self-development experiences. Whether an individual is seven or seventy, the JLM Center has a lot to offer that meets both the personal and educational interests. Each program and activities are designed to emphasize a sense of community for all residents of the City of Chicago.
JLM offers the following programs and services:
Student Outreach and Re-engagement Program (S.O.A.R) | Chicago Public Schools Safe Haven ProgramNarcotics/ Alcoholics Anonymous | Produce Mobile | Urban Transformation Network | Teen Reach
Chicago Alternative Policing Strategies (C.A.P.S) | Top Box Foods | ComEd | Dental MobileCTA Over 50 Basketball League
For more information, visit www.jlmcenter.org or call (773) 826-3064
Rahm Emanue l , Mayor
CONSTRUCT ION SUMMIT 2019
W W W . C I T Y O F C H I C A G O . O R G / D P SChicagoDPS @ChicagoDPS ChicagoDPS
FEBRUARY 6,2019J L M C e n t e r | 2 6 2 2 W. J a c k s o n B l v d . | 1 0 a m - 2 p m
R E G I S T E R N O W
COME OUT AND NETWORK! SCAN ME