Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
REVISED FUNCTIONAL SERVICING REPORT
ROYAL LIVING DEVELOPMENT GROUP INC.
3225-3237 NEW STREET
CITY OF BURLINGTON
Submitted to:
Royal Living Development Group Inc.
Submitted by:
Amec Foster Wheeler Environment & Infrastructure
a Division of Amec Foster Wheeler Americas Limited
3450 Harvester Road, Suite 100
Burlington, ON L7N 3W5
Tel: (905) 335-2353
Fax: (905) 335-1414
September 2017
Project No. TPB173022
Royal Living Development Group Inc. Amec Foster Wheeler Revised Functional Servicing Report Environment & Infrastructure 3225-3237 New Street City of Burlington September 2017
P:\2017\Projects\TPB173022 - 3225-3237 New Street, Burlington\05_DEL\01_RPT-TECHMEM\FSR2\17-09 FSR.docx Table of Contents
TABLE OF CONTENTS PAGE
1.0 INTRODUCTION ............................................................................................................. 1
1.1 Existing Site Conditions ....................................................................................... 1 1.2 Proposed Development........................................................................................ 1
2.0 BACKGROUND INFORMATION .................................................................................... 2
2.1 Documents / Reports ........................................................................................... 2 2.2 Drawings .............................................................................................................. 2 2.3 Topographic Survey ............................................................................................. 2
3.0 GRADING AND DRAINAGE ........................................................................................... 3
3.1 Existing Conditions .............................................................................................. 3 3.2 Proposed Grading and Drainage .......................................................................... 3
4.0 SERVICING..................................................................................................................... 4
4.1 Existing Water Servicing ...................................................................................... 4 4.2 Proposed Water Servicing ................................................................................... 4 4.3 Proposed Water Supply Requirements ................................................................ 4 4.4 Existing Sanitary Sewer Servicing ........................................................................ 5 4.5 Proposed Sanitary Sewer Servicing ..................................................................... 5 4.6 Existing Storm Sewer Servicing ........................................................................... 5 4.7 Proposed Storm Sewer Servicing ........................................................................ 6
5.0 STORMWATER MANAGEMENT .................................................................................... 7
5.1 General Description and Criteria .......................................................................... 7 5.2 Runoff Calculations .............................................................................................. 8 5.3 Stormwater Management – Quantity Control (Rational Method) .......................... 9 5.4 Stormwater Management - Quality Control ........................................................ 10
6.0 SUMMARY .................................................................................................................... 11
LIST OF APPENDICES Appendix A - Background Information Appendix B - Sanitary Demand & Water Usage Appendix C - Stormwater Management Calculations
LIST OF FIGURES Figure 1 - Storm Drainage Area Plan
Royal Living Development Group Inc. Amec Foster Wheeler Revised Functional Servicing Report Environment & Infrastructure 3225-3237 New Street City of Burlington September 2017
P:\2017\Projects\TPB173022 - 3225-3237 New Street, Burlington\05_DEL\01_RPT-TECHMEM\FSR2\17-09 FSR.docx Table of Contents
LIST OF DRAWINGS
Sheet 1 - General Notes and Details Sheet 2 - Existing Conditions Plan Sheet 3 - Site Grading Plan Sheet 4 - Site Servicing Plan Sheet 5 - Erosion and Sediment Control Plan Sheet 6 - Cross-Sections Sheet 7 - SWM Tank Details Plan
Amec Foster Wheeler Environment & Infrastructure is committed to achieving sustainability through balancing economic growth, social responsibility and environmental protection. Learn more at:
http://amecfw.com/aboutus/sustainability.htm.
Royal Living Development Group Inc. Amec Foster Wheeler Revised Functional Servicing Report Environment & Infrastructure 3225-3237 New Street City of Burlington September 2017
P:\2017\Projects\TPB173022 - 3225-3237 New Street, Burlington\05_DEL\01_RPT-TECHMEM\FSR2\17-09 FSR.docx Page 1
1.0 INTRODUCTION
Amec Foster Wheeler Environment & Infrastructure has been retained by Royal Living
Development Group Inc. (the “Owner”) to prepare a Functional Servicing Report in support of a
Zoning By-Law Amendment application for the proposed 11-unit townhouse development at
3225-3237 New Street in the City of Burlington (the “City”).
The purpose of this report is to examine and demonstrate the serviceability of this development
with respect to wastewater, stormwater, water servicing, site grading and stormwater
management and ensure servicing strategies are consistent with the City of Burlington, Region of
Halton and Conservation Halton requirements.
1.1 Existing Site Conditions
The existing site of approximately 0.20 ha is located at 3225-3237 New Street, in the City of
Burlington. The site is bounded by New Street to the south, existing townhouses to the east,
Burlington Tailors store to the west and the Hydro corridor/Centennial Bike Trail to the north. The
existing site consist of two (2) one-storey residential houses with separate garages. There are
two (2) existing driveway entrances off of New Street. (Refer to the Existing Conditions Plan).
The legal description is as follows: Lots 2 and 3, Registered Plan 408, in the City of Burlington.
The site is located in an area of the City that is serviced by a network of municipal infrastructure
including roads, sewers, watermains and other services and utilities.
1.2 Proposed Development
The proposed site is for a 3-storey residential townhouse development consisting of 11
townhouse units with driveways, roads and associated visitor parking.
The existing driveway entrances off New Street will be removed and replaced with one (1)
entrance and internal roadway to accommodate the new townhouse development.
Refer to Appendix A for the proposed Site Plan (SP1) prepared by KNYMH Inc.
Royal Living Development Group Inc. Amec Foster Wheeler Revised Functional Servicing Report Environment & Infrastructure 3225-3237 New Street City of Burlington September 2017
P:\2017\Projects\TPB173022 - 3225-3237 New Street, Burlington\05_DEL\01_RPT-TECHMEM\FSR2\17-09 FSR.docx Page 2
2.0 BACKGROUND INFORMATION
2.1 Documents / Reports
Conservation Halton approval email from Leah Chishimba dated November 21, 2014.
2.2 Drawings
Plan and profile drawing for New Street, Sheet 8 of 27 – (City of Burlington – Municipal
Dwg. No. MN-3).
Plan and profile drawing for New Street, Sheet 9 of 27 – (City of Burlington – Municipal
Dwg. No. MN-3).
Plan and profile drawing for New Street, Sta. 2+410 to 2+560, Sheet 15 of 16 – (City of
Burlington – Municipal Dwg. No. MN-3, Contract No. CW 16-04)
Plan and profile drawing for New Street, (1800mm dia. East End Trunk Sanitary Sewer),
Dwg. 4 of 8 – (Halton Region – File No. B-376)
Plan and profile drawing for New Street, (1800mm dia. East End Trunk Sanitary Sewer),
Dwg. 5 of 8 – (Halton Region – File No. B-344)
Plan and profile drawing for New Street (750mm dia. watermain), Sheet 17 of 24 – (Halton
Region – File No. B-10960)
Plan and profile drawing for New Street (750mm dia. watermain), Sheet 18 of 24 – (Halton
Region – File No. B-10961)
2.3 Topographic Survey
Topographic survey prepared by A.T. McLaren Limited dated September 24, 2014
Royal Living Development Group Inc. Amec Foster Wheeler Revised Functional Servicing Report Environment & Infrastructure 3225-3237 New Street City of Burlington September 2017
P:\2017\Projects\TPB173022 - 3225-3237 New Street, Burlington\05_DEL\01_RPT-TECHMEM\FSR2\17-09 FSR.docx Page 3
3.0 GRADING AND DRAINAGE
3.1 Existing Conditions
The existing property is generally flat and there are no known external drainage areas to the site.
The existing residential lots are split drainage. The rear yards drain away from the houses and
towards the existing Hydro corridor to the north. The front yards drain towards the New Street
municipal sewer system to the south. (Refer to Existing Conditions Plan)
3.2 Proposed Grading and Drainage
The proposed grading is designed to direct stormwater runoff via swales and catchbasins to the
storm sewer system without adversely impacting adjacent lots and the proposed residential
development of this site. The storm runoff will be collected and released in a controlled manner.
The site is located near the Regulatory Floodplain for Roseland Creek. A local highpoint or crest
of the floodplain at an elevation of 87.20 m to 87.50 m is located approximately 142 m easterly of
Roseland creek centerline. Spill flows will be conveyed easterly to a low point on New Street
adjacent to the subject property prior to spilling south of New Street and back to Roseland Creek.
Since the existing lot grades will be impacted by spill flow, the proposed grading will be raised to
the regional flood elevation of approximately 87.57 at the north end and 87.44 at the south end.
(Refer to Appendix A for Conservation Halton approval email)
Proposed grades along the north and west limits are approximately 0.50 m higher than the existing
grades, and 3:1 sloping is proposed. Overland flow for the 100-year storm event and greater will
be directed toward New Street. (Refer to Site Grading Plan)
Royal Living Development Group Inc. Amec Foster Wheeler Revised Functional Servicing Report Environment & Infrastructure 3225-3237 New Street City of Burlington September 2017
P:\2017\Projects\TPB173022 - 3225-3237 New Street, Burlington\05_DEL\01_RPT-TECHMEM\FSR2\17-09 FSR.docx Page 4
4.0 SERVICING
4.1 Existing Water Servicing
According to the reviewed information obtained from City plans and the Surveyor, there is an
existing 300 mm diameter watermain along the centreline of New Street and an existing 750 mm
diameter watermain on the north side of New Street. Furthermore, there is an existing 1050 mm
watermain within the north boulevard of New Street. The existing houses are currently serviced
by domestic water services connected to the existing 300 mm watermain on New Street.
There is one (1) existing fire hydrant located along the south side of New Street adjacent to the
proposed development, and one (1) existing fire hydrant on the north side of New Street located
approximately 34 m from the west property limit.
4.2 Proposed Water Servicing
The proposed development will be serviced by a 200 mm diameter PVC watermain connected to
the existing 300 mm watermain on New Street via a tapping valve and sleeve, and valve and box
installed at the property line.
The two (2) existing fire hydrants located on New Street will provide the necessary firefighting
coverage for the units fronting New Street. One (1) additional fire hydrant is being proposed within
the development to provide suitable firefighting coverage. The proposed watermain will be
plugged at the end of the internal roadway to accommodate for future townhouse development
on the existing lot to the west.
Water usage is typically based on calculating sanitary discharge flows based on the Ontario
Building Code (OBC) 2012 guidelines. The estimated water usage has been calculated to be
0.320 L/sec (27.62 m3/day) which facilitates for the future development. This estimated water
usage calculation will need to be further refined by the Mechanical Engineer as the project
progresses and as fixture units are confirmed. (Refer to Appendix B for detailed calculations)
4.3 Proposed Water Supply Requirements
The Water Supply for Public Fire Protection was calculated based on the guidelines provided by
the Fire Underwriter’s Survey (FUS), to demonstrate that the existing flows and pressure are
adequate to meet the minimum requirement for fire suppression outlined in the FUS.
According to our calculations for the proposed townhouse development, a minimum fire
suppression flow of approximately 7,000 L/min at a pressure of 140 kPa (20 PSI) will be required.
Hydrant flow testing must take place for verification of pressure and flow required for the proposed
development prior to final drawing approval. (Refer to Appendix B for detailed calculations)
Royal Living Development Group Inc. Amec Foster Wheeler Revised Functional Servicing Report Environment & Infrastructure 3225-3237 New Street City of Burlington September 2017
P:\2017\Projects\TPB173022 - 3225-3237 New Street, Burlington\05_DEL\01_RPT-TECHMEM\FSR2\17-09 FSR.docx Page 5
4.4 Existing Sanitary Sewer Servicing
According to the reviewed information obtained from City plans and the Surveyor, there is an
existing 250 mm diameter sanitary sewer on the north side of New Street that flows westerly to
Dynes Road. There is also an existing 1800 mm diameter sanitary trunk sewer within the north
boulevard of New Street that flows westerly to Dynes Road. The existing houses are currently
serviced by sanitary service laterals connected to the existing 250 mm diameter sanitary sewer
on New Street.
4.5 Proposed Sanitary Sewer Servicing
Sanitary discharge flows for the proposed site were calculated based on the Ontario Building
Code (OBC) 2012 guidelines, along with the proposed site plan statistics found in Appendix A.
Based on the above criteria, the proposed townhouse development will contribute approximately
0.204 L/sec (17.6 m3/day) into the 250 mm diameter sanitary sewer system on New Street. The
existing lot to the west is planned for future development, and future flows will contribute an
additional 0.074 L/sec (6.4 m3/day). Therefore, the total sanitary discharge contributing into the
250 mm diameter sanitary sewer on New Street will be approximately 0.278 L/sec (24 m3/day).
A 200 mm diameter sanitary pipe is proposed to service this site and will be connected to the
existing 250 mm diameter sanitary main via a wye connection. This connection will be adequate
to convey the design flow of 0.278 L/s.
This estimated sanitary demand calculation will need to be further refined by the Mechanical
Engineer as the project progresses and as fixture units are confirmed. (Refer to Appendix B for
detailed sanitary sewer flow calculations)
4.6 Existing Storm Sewer Servicing
According to the reviewed information obtained from City plans and the Surveyor, there is an
existing 375 mm storm sewer on the south side of New Street that flows westerly and connects
into a 675 mm storm sewer. The existing houses are currently serviced by storm service laterals
connected to the existing 375 mm diameter storm sewer on New Street.
Royal Living Development Group Inc. Amec Foster Wheeler Revised Functional Servicing Report Environment & Infrastructure 3225-3237 New Street City of Burlington September 2017
P:\2017\Projects\TPB173022 - 3225-3237 New Street, Burlington\05_DEL\01_RPT-TECHMEM\FSR2\17-09 FSR.docx Page 6
4.7 Proposed Storm Sewer Servicing
Stormwater runoff around the proposed townhouse development will drain overland into swales
and catchbasins and be directed into the proposed storm sewer system. A 300 mm diameter
storm sewer is proposed to be connected to the existing 375 mm storm sewer on New Street.
(Refer to Site Servicing Plan)
On-site storage and controlled release will be required, with proposed underground storage within
the parking lot. A 300 mm diameter storm connection at a slope of 0.5% will be adequate to
convey the controlled design flow of 20 L/s from the residential development.
The existing lot to the west is facilitated for future townhouse development. To accommodate for
future development, the post development flows will need to be controlled to 29 L/s.
Refer to Section 5 for details regarding the on-site storage condition and stormwater management
for the proposed development.
Royal Living Development Group Inc. Amec Foster Wheeler Revised Functional Servicing Report Environment & Infrastructure 3225-3237 New Street City of Burlington September 2017
P:\2017\Projects\TPB173022 - 3225-3237 New Street, Burlington\05_DEL\01_RPT-TECHMEM\FSR2\17-09 FSR.docx Page 7
5.0 STORMWATER MANAGEMENT
5.1 General Description and Criteria
Existing Site Conditions
The subject land of approximately 0.20 ha is located at 3225-3237 New Street, in the City of
Burlington. The site is bounded by New Street to the south, existing townhouses to the east,
Burlington Tailors store to the west and the Hydro corridor/Centennial Bike Trail to the north. The
site is currently developed with two (2) one-storey residential houses.
The existing residential lots are split drainage. The rear yards drain away from the houses to the
north and into the existing Hydro corridor. The front yards drain to the south towards the New
Street municipal sewer system. There are no known external drainage areas to the site.
(Refer to the Existing Conditions Plan)
Proposed Development
The proposed development is comprised of a 3-storey residential townhouse development
consisting of 11 townhouse units with driveways, roads and associated visitor parking totaling
0.20 ha. One (1) entrance off of New Street will accommodate the new townhouse development.
The total impervious area of the proposed site will be 0.147 ha. Due to the small drainage area
of the site, the entire site area was considered to drain directly into the storm sewer system as a
conservative approach. The impervious coverage of the development will increase from 24% to
approximately 74%.
The existing lot to the west is facilitated for future townhouse development with a future site area
of 0.094 ha. The total impervious area of the proposed site including the future property will be
0.194 ha. With the future townhouse area included, the impervious coverage will ultimately
increase from 24% to 66%.
Design Criteria
Due to the small drainage area of the site (less than 5 ha), the Rational Method has been used to
determine design flows as a conservative approach.
Post development peak flow for the 100-year storm event should be controlled to the 5-year target
flow with a composite runoff coefficient of 0.40.
Stormwater should be treated to Level 1 quality (Enhanced) as defined in the MOE 2003
SWMPD Manual, for the removal of 80% of the total suspended solids.
The City of Burlington Intensity-Duration-Frequency (IDF) data to be used for analysis.
Royal Living Development Group Inc. Amec Foster Wheeler Revised Functional Servicing Report Environment & Infrastructure 3225-3237 New Street City of Burlington September 2017
P:\2017\Projects\TPB173022 - 3225-3237 New Street, Burlington\05_DEL\01_RPT-TECHMEM\FSR2\17-09 FSR.docx Page 8
5.2 Runoff Calculations
Target Conditions
The City of Burlington 5-year Intensity Duration Frequency coefficients (A = 697.40, B = 5.00, and
C = 0.764) was used to calculate the intensity values for the 5-year target flows from the site.
Target flow calculations to be based on a composite runoff coefficient of 0.40. Due to the small
total area of the site, the City’s minimum Time of Concentration (Tc) of 10 minutes was used.
(Refer to Appendix C for allowable flow and runoff coefficient calculations). Table 1 below shows
a summary of the target input parameters.
Table 1A. Target Input Parameters (Existing Site)
Catchment C-value Tc
(min.) Intensity (mm/hr)
Area (ha)
Flow (m3/sec)
A1 Pre 0.40 10 88.09 0.20 0.020
As shown in Table 1A above, the post development flows will need to be controlled to the target
flow of 0.020 m3/sec (20 L/sec).
If the existing lot to the west is developed in the future, the allowable target flows will increase
from 0.020 m3/sec to 0.029 m3/sec. Table 1B below shows a summary of the target input
parameters for the proposed site including the future lot development.
Table 1B. Target Input Parameters (Existing Site + Future Lot)
Catchment C-value Tc
(min.) Intensity (mm/hr)
Area (ha)
Flow (m3/sec)
A1 Pre + Future
0.40 10 88.09 0.294 0.029
Proposed Conditions
Stormwater runoff around the proposed townhouse development will be directed towards swales, rear yard catchbasins and road catchbasins, and flows will be directed into the on-site storm sewer system. The storm runoff will be collected and released in a controlled manner without adversely impacting adjacent lots. Overland flow for the 100-year storm event and greater will be directed toward New Street. A1 Post represents the proposed site area that will be controlled via an underground storage tank and orifice control. (Refer to Appendix C for post development calculations). Table 2A below shows a summary of the relevant drainage parameters of the post development drainage area.
Royal Living Development Group Inc. Amec Foster Wheeler Revised Functional Servicing Report Environment & Infrastructure 3225-3237 New Street City of Burlington September 2017
P:\2017\Projects\TPB173022 - 3225-3237 New Street, Burlington\05_DEL\01_RPT-TECHMEM\FSR2\17-09 FSR.docx Page 9
Table 2A. Post Development Input Parameters (Proposed Site)
Catchment C-value Tc
(min.) Area (ha)
A1 Post 0.72 10 0.20
The storm sewer system will convey the minor system (5 year storm) and all major flows (greater than 5-year storm event) will surcharge and be conveyed overland to New Street. (Refer to Storm Drainage Area Plan) A2 Post represents the existing lot area to the west this is planned for future development, and will require additional underground storage and orifice control to accommodate the future development. Refer to the Storm Drainage Area Plan for estimated future storage tank location. Table 2B below shows a summary of the relevant drainage parameters of the proposed site including the future lot development.
Table 2B. Post Development Input Parameters (Proposed Site + Future Lot)
Catchment C-value Tc
(min.) Area (ha)
A1 Post + A2 Post (Future)
0.66 10 0.294
5.3 Stormwater Management – Quantity Control (Rational Method)
Using the City’s IDF data, rational method calculations were undertaken to determine the maximum storage required at a duration event of 2 hours. In order to control post-development flows to 5-year pre-development allowable conditions, a target flow of 0.020 m3/sec is to be satisfied. Based on our stormwater analysis, a total storage volume of ±52.9 m3 will be required within an on-site underground storage tank. Any flows beyond that which is conveyed within the storm sewer system shall be conveyed overland to the existing storm sewer system on New Street To achieve the allowable flow of 0.020 m3/sec during the 100-year storm event, a 100 mm diameter orifice tube is proposed with a maximum head of 0.86 m above the centroid of the orifice. The 100 mm diameter orifice tube will be outletting from proposed CB/MH 1 to the existing storm sewer system. (Refer to Appendix C for detailed orifice calculations).
Royal Living Development Group Inc. Amec Foster Wheeler Revised Functional Servicing Report Environment & Infrastructure 3225-3237 New Street City of Burlington September 2017
P:\2017\Projects\TPB173022 - 3225-3237 New Street, Burlington\05_DEL\01_RPT-TECHMEM\FSR2\17-09 FSR.docx Page 10
Underground Stormwater Tank
An underground storage tank (Stormtech or approved equivalent) is proposed within the visitor parking lot to provide a storage volume of ±58 m3 and surface area of 150 m2 by 0.4 m deep. This storage volume does not include volume accumulated within pipes and manhole structures. (Refer to Site Servicing Plan) To accommodate for the future development to the west, an additional 16 m3 of underground storage would be required.
5.4 Stormwater Management - Quality Control
As per City and HCA requirements, the stormwater should be treated to the Ministry of the
Environment (MOE) Enhanced Level protection and the removal of 80% T.S.S. is required.
An oil/grit separator is proposed to be placed on the storm sewer system prior to outletting the
site to prevent sediment from entering the existing downstream storm system. The STC 300 (or
approved equivalent) oil grit separator has been sized to treat the proposed 0.20 ha site with 74%
total impervious coverage (including roof areas) for a removal efficiency of 86%.
To accommodate for the future development to the west, the proposed STC 300 is adequately
sized to treat the proposed and future site areas totaling 0.294 ha with 66% combined impervious
coverage and removal efficiency of 84%. (Refer to Appendix C for supporting calculations)
The oil/grit separator is proposed to be placed downstream of all on-site catchbasins to prevent
sediment from leaving the site and entering the existing downstream storm system.
L
A
N
D
S
O
F
O
N
T
A
R
IO
H
Y
D
R
O
HALTON CONDOMINIUM PLAN 333
C
O
N
C
E
S
S
IO
N
3
S
.D
LOT 2
LOT 3
LOT 1
P L A N
4 0 8
NEW STREET
3225-3237 NEW STREET
BURLINGTON, ON
ROYAL LIVING DEVELOPMENT
1
TPB173022
PROPOSED
SITE
³
STORM DRAINAGE
AREA PLAN
0.0050.90
1
0.20 0.72
1
0.0940.55
2 (FUT)
0.0050.90
1 (FUT)
“ ”
”
”
’
PROPOSED
SITE
0.005
0.40
ID
0.20 0.40
1 PRE
0.094
0.40
FUT
L
A
N
D
S
O
F
O
N
T
A
R
IO
H
Y
D
R
O
HALTON CONDOMINIUM PLAN 333
C
O
N
C
E
S
S
IO
N
3
S
.D
.S
.
L
O
LOT 2
LOT 3
LOT 1
P L A N
4 0 8
NEW STREET
L
A
N
D
S
O
F
O
N
T
A
R
IO
H
Y
D
R
O
HALTON CONDOMINIUM PLAN 333
C
O
N
C
E
S
S
IO
N
3
S
.D
.S
.
L
O
LOT 2
LOT 3
LOT 1
P L A N
4 0 8
NEW STREET
3225-3237 NEW STREET
BURLINGTON, ON
ROYAL LIVING DEVELOPMENT
SITE GRADING
PLAN
FFE = 88.40
FFE = 88.40
FFE = 88.55(FUT)
PROPOSED
SITE
73
TPB173022
NOT ISSUED FOR CONSTRUCTION
L
A
N
D
S
O
F
O
N
T
A
R
IO
H
Y
D
R
O
HALTON CONDOMINIUM PLAN 333
C
O
N
C
E
S
S
IO
N
3
S
.D
LOT 2
LOT 3
LOT 1
P L A N
4 0 8
NEW STREET
3225-3237 NEW STREET
BURLINGTON, ON
ROYAL LIVING DEVELOPMENT
SITE SERVICING
PLAN
PROPOSED
SITE
74
TPB173022
NOT ISSUED FOR CONSTRUCTION
A
ABC
D
D
³
L
A
N
D
S
O
F
O
N
T
A
R
IO
H
Y
D
R
O
LOT 2
LOT 3
LOT 1
P L A N
4 0 8
NEW STREET
PROPOSED
SITE
A
B
A
A
B
B
A
3225-3237 NEW STREET
BURLINGTON, ON
ROYAL LIVING DEVELOPMENT
CROSS-SECTIONS
76
TPB173022
NOT ISSUED FOR CONSTRUCTION
7
TPB173022
PROPOSED LAYOUT
60 STORMTECH SC-310 CHAMBERS
20 STORMTECH SC-310 END CAPS
152
STONE ABOVE (mm)
152
STONE BELOW (mm)
40 % STONE VOID
57.9
INSTALLED SYSTEM VOLUME (m³)
(PERIMETER STONE INCLUDED)
151
SYSTEM AREA (m²)
50
SYSTEM PERIMETER (m)
PROPOSED ELEVATIONS
MAXIMUM ALLOWABLE GRADE (TOP OF PAVEMENT/UNPAVED):
89.0060
MINIMUM ALLOWABLE GRADE (UNPAVED WITH TRAFFIC):
87.1780
MINIMUM ALLOWABLE GRADE (UNPAVED NO TRAFFIC):87.0250
MINIMUM ALLOWABLE GRADE (BASE OF FLEXIBLE PAVEMENT):
87.0250
MINIMUM ALLOWABLE GRADE (TOP OF RIGID PAVEMENT):
87.0250
TOP OF STONE: 86.7200
TOP OF SC-310 CHAMBER: 86.5680
200 mm TOP MANIFOLD INVERT: 86.2500
300 mm ISOLATOR ROW INVERT: 86.1860
BOTTOM OF SC-310 CHAMBER: 86.1620
BOTTOM OF STONE: 86.010
15.2 m
13.38 m
9.93 m
9.32 m
ISOLATOR ROW
PLACE MINIMUM 3.81 m OF ADS GEOSYNTHETICS
315WTK WOVEN GEOTEXTILE OVER BEDDING
STONE AND UNDERNEATH CHAMBER FEET FOR
SCOUR PROTECTION AT ALL CHAMBER INLET ROWS
200mm X 200mm ADS N-12 TOP MANIFOLD
INVERT 89mm ABOVE CHAMBER BASE
INSPECTION PORT
PROPOSED MH #2 STRUCTURE
SHOWN AS 750 mm NYLOPLAST
(PROVIDED BY STORMTECH)
300 mm ADS N-12 BOTTOM ISOLATION
ROW CONNECTION
INVERT 23 mm ABOVE CHAMBER BASE
ACCEPTABLE FILL MATERIALS: STORMTECH SC-310 CHAMBER SYSTEMS
PLEASE NOTE:
1. THE LISTED AASHTO DESIGNATIONS ARE FOR GRADATIONS ONLY. THE STONE MUST ALSO BE CLEAN, CRUSHED, ANGULAR. FOR EXAMPLE, A SPECIFICATION FOR #4 STONE WOULD STATE: "CLEAN, CRUSHED,
ANGULAR NO. 4 (AASHTO M43) STONE".
2. STORMTECH COMPACTION REQUIREMENTS ARE MET FOR 'A' LOCATION MATERIALS WHEN PLACED AND COMPACTED IN 6" (150 mm) (MAX) LIFTS USING TWO FULL COVERAGES WITH A VIBRATORY COMPACTOR.
3. WHERE INFILTRATION SURFACES MAY BE COMPROMISED BY COMPACTION, FOR STANDARD DESIGN LOAD CONDITIONS, A FLAT SURFACE MAY BE ACHIEVED BY RAKING OR DRAGGING WITHOUT COMPACTION
EQUIPMENT. FOR SPECIAL LOAD DESIGNS, CONTACT STORMTECH FOR COMPACTION REQUIREMENTS.
NOTES:
1. SC-310 CHAMBERS SHALL CONFORM TO THE REQUIREMENTS OF ASTM F2418 "STANDARD SPECIFICATION FOR POLYPROPYLENE (PP) CORRUGATED WALL STORMWATER COLLECTION CHAMBERS", OR ASTM
F2922
"STANDARD SPECIFICATION FOR POLYETHYLENE (PE) CORRUGATED WALL STORMWATER COLLECTION CHAMBERS".
2. SC-310 CHAMBERS SHALL BE DESIGNED IN ACCORDANCE WITH ASTM F2787 "STANDARD PRACTICE FOR STRUCTURAL DESIGN OF THERMOPLASTIC CORRUGATED WALL STORMWATER COLLECTION
CHAMBERS".
3. "ACCEPTABLE FILL MATERIALS" TABLE ABOVE PROVIDES MATERIAL LOCATIONS, DESCRIPTIONS, GRADATIONS, AND COMPACTION REQUIREMENTS FOR FOUNDATION, EMBEDMENT, AND FILL MATERIALS.
4. THE SITE DESIGN ENGINEER IS RESPONSIBLE FOR ASSESSING THE BEARING RESISTANCE (ALLOWABLE BEARING CAPACITY) OF THE SUBGRADE SOILS AND THE DEPTH OF FOUNDATION STONE WITH
CONSIDERATION FOR THE RANGE OF EXPECTED SOIL MOISTURE CONDITIONS.
5. PERIMETER STONE MUST BE EXTENDED HORIZONTALLY TO THE EXCAVATION WALL FOR BOTH VERTICAL AND SLOPED EXCAVATION WALLS.
6. ONCE LAYER 'C' IS PLACED, ANY SOIL/MATERIAL CAN BE PLACED IN LAYER 'D' UP TO THE FINISHED GRADE. MOST PAVEMENT SUBBASE SOILS CAN BE USED TO REPLACE THE MATERIAL REQUIREMENTS OF
LAYER 'C' OR 'D' AT THE SITE DESIGN ENGINEER'S DISCRETION.
MATERIAL LOCATION DESCRIPTION
AASHTO MATERIAL
CLASSIFICATIONS
COMPACTION / DENSITY
REQUIREMENT
D
FINAL FILL: FILL MATERIAL FOR LAYER 'D' STARTS
FROM THE TOP OF THE 'C' LAYER TO THE BOTTOM
OF FLEXIBLE PAVEMENT OR UNPAVED FINISHED
GRADE ABOVE. NOTE THAT PAVEMENT SUBBASE
MAY BE PART OF THE 'D' LAYER
ANY SOIL/ROCK MATERIALS, NATIVE SOILS, OR PER
ENGINEER'S PLANS. CHECK PLANS FOR PAVEMENT
SUBGRADE REQUIREMENTS.
N/A
PREPARE PER SITE DESIGN ENGINEER'S PLANS.
PAVED INSTALLATIONS MAY HAVE STRINGENT
MATERIAL AND PREPARATION REQUIREMENTS.
C
INITIAL FILL: FILL MATERIAL FOR LAYER 'C'
STARTS FROM THE TOP OF THE EMBEDMENT
STONE ('B' LAYER) TO 18" (450 mm) ABOVE THE
TOP OF THE CHAMBER. NOTE THAT PAVEMENT
SUBBASE MAY BE A PART OF THE 'C' LAYER.
GRANULAR WELL-GRADED SOIL/AGGREGATE MIXTURES, <35%
FINES OR PROCESSED AGGREGATE.
MOST PAVEMENT SUBBASE MATERIALS CAN BE USED IN LIEU
OF THIS LAYER.
AASHTO M145¹
A-1, A-2-4, A-3
OR
AASHTO M43¹
3, 357, 4, 467, 5, 56, 57, 6, 67, 68, 7, 78, 8, 89,
9, 10
BEGIN COMPACTIONS AFTER 12" (300 mm) OF
MATERIAL OVER THE CHAMBERS IS REACHED.
COMPACT ADDITIONAL LAYERS IN 6" (150 mm) MAX
LIFTS TO A MIN. 95% PROCTOR DENSITY FOR
WELL GRADED MATERIAL AND 95% RELATIVE
DENSITY FOR PROCESSED AGGREGATE
MATERIALS. ROLLER GROSS VEHICLE WEIGHT
NOT TO EXCEED 12,000 lbs (53 kN). DYNAMIC
FORCE NOT TO EXCEED 20,000 lbs (89 kN).
B
EMBEDMENT STONE: FILL SURROUNDING THE
CHAMBERS FROM THE FOUNDATION STONE ('A'
LAYER) TO THE 'C' LAYER ABOVE.
CLEAN, CRUSHED, ANGULAR STONE
AASHTO M43¹
3, 357, 4, 467, 5, 56, 57
NO COMPACTION REQUIRED.
A
FOUNDATION STONE: FILL BELOW CHAMBERS
FROM THE SUBGRADE UP TO THE FOOT (BOTTOM)
OF THE CHAMBER.
CLEAN, CRUSHED, ANGULAR STONE
AASHTO M43¹
3, 357, 4, 467, 5, 56, 57
PLATE COMPACT OR ROLL TO ACHIEVE A FLAT
SURFACE. ² ³
SUBGRADE SOILS
(SEE NOTE 4)
PAVEMENT LAYER (DESIGNED
BY SITE DESIGN ENGINEER)
SC-310
END CAP
D
C
B
A
PERIMETER STONE
(SEE NOTE 6)
6" (150 mm)
MIN
EXCAVATION WALL
(CAN BE SLOPED OR VERTICAL)
12" (300 mm) MIN 12" (300 mm) MIN34" (865 mm)
16"
(400 mm) MIN
18"
(450 mm) MIN
8'
(2.4 m) MAX
3" (80 mm) MIN
ADS GEOSYNTHETICS 601T NON-WOVEN GEOTEXTILE ALL AROUND
CLEAN CRUSHED, ANGULAR STONE IN A & B LAYERS
16"
(405 mm)
DEPTH OF STONE TO BE DETERMINED
BY SITE DESIGN ENGINEER 6" (150 mm) MIN
*TO BOTTOM OF FLEXIBLE PAVEMENT. FOR UNPAVED
INSTALLATIONS WHERE RUTTING FROM VEHICLES MAY
OCCUR, INCREASE COVER TO 24" (600 mm).
INSPECTION & MAINTENANCE
STEP 1) INSPECT ISOLATOR ROW FOR SEDIMENT
A. INSPECTION PORTS (IF PRESENT)
A.1. REMOVE/OPEN LID ON NYLOPLAST INLINE DRAIN
A.2. REMOVE AND CLEAN FLEXSTORM FILTER IF INSTALLED
A.3. USING A FLASHLIGHT AND STADIA ROD, MEASURE DEPTH OF SEDIMENT AND RECORD ON MAINTENANCE LOG
A.4. LOWER A CAMERA INTO ISOLATOR ROW FOR VISUAL INSPECTION OF SEDIMENT LEVELS (OPTIONAL)
A.5. IF SEDIMENT IS AT, OR ABOVE, 3" (80 mm) PROCEED TO STEP 2. IF NOT, PROCEED TO STEP 3.
B. ALL ISOLATOR ROWS
B.1. REMOVE COVER FROM STRUCTURE AT UPSTREAM END OF ISOLATOR ROW
B.2. USING A FLASHLIGHT, INSPECT DOWN THE ISOLATOR ROW THROUGH OUTLET PIPE
i) MIRRORS ON POLES OR CAMERAS MAY BE USED TO AVOID A CONFINED SPACE ENTRY
ii) FOLLOW OSHA REGULATIONS FOR CONFINED SPACE ENTRY IF ENTERING MANHOLE
B.3. IF SEDIMENT IS AT, OR ABOVE, 3" (80 mm) PROCEED TO STEP 2. IF NOT, PROCEED TO STEP 3.
STEP 2) CLEAN OUT ISOLATOR ROW USING THE JETVAC PROCESS
A. A FIXED CULVERT CLEANING NOZZLE WITH REAR FACING SPREAD OF 45" (1.1 m) OR MORE IS PREFERRED
B. APPLY MULTIPLE PASSES OF JETVAC UNTIL BACKFLUSH WATER IS CLEAN
C. VACUUM STRUCTURE SUMP AS REQUIRED
STEP 3) REPLACE ALL COVERS, GRATES, FILTERS, AND LIDS; RECORD OBSERVATIONS AND ACTIONS.
STEP 4) INSPECT AND CLEAN BASINS AND MANHOLES UPSTREAM OF THE STORMTECH SYSTEM.
NOTES
1. INSPECT EVERY 6 MONTHS DURING THE FIRST YEAR OF OPERATION. ADJUST THE INSPECTION INTERVAL BASED ON PREVIOUS
OBSERVATIONS OF SEDIMENT ACCUMULATION AND HIGH WATER ELEVATIONS.
2. CONDUCT JETTING AND VACTORING ANNUALLY OR WHEN INSPECTION SHOWS THAT MAINTENANCE IS NECESSARY.
SUMP DEPTH TBD BY
SITE DESIGN ENGINEER
(24" [600 mm] MIN RECOMMENDED)
12" (300 mm) HDPE ACCESS PIPE REQUIRED
USE FACTORY PRE-FABRICATED END CAP
PART #: SC310EPE12B
TWO LAYERS OF ADS GEOSYNTHETICS 315WTK WOVEN
GEOTEXTILE BETWEEN FOUNDATION STONE AND CHAMBERS
4' (1.2 m) MIN WIDE CONTINUOUS FABRIC WITHOUT SEAMS
CATCH BASIN
OR
MANHOLE
SC-310 ISOLATOR ROW DETAIL
NTS
STORMTECH HIGHLY RECOMMENDS
FLEXSTORM PURE INSERTS IN ANY UPSTREAM
STRUCTURES WITH OPEN GRATES
COVER ENTIRE ISOLATOR ROW WITH ADS
GEOSYNTHETICS 601T NON-WOVEN GEOTEXTILE
5' (1.5 m) MIN WIDE
SC-310 CHAMBER
SC-310 END CAP
OPTIONAL INSPECTION PORT
SC-310 6" INSPECTION PORT DETAIL
NTS
SC-310 CHAMBER
FLEXSTORM CATCH IT
PART# 6212NYFX
WITH USE OF OPEN GRATE
6" (150 mm) INSERTA TEE
PART# 6P26FBSTIP*
INSERTA TEE TO BE CENTERED
ON CORRUGATION CREST
6" (150 mm) SDR35 PIPE
CONCRETE COLLAR
12" (300 mm) NYLOPLAST INLINE
DRAIN BODY W/SOLID HINGED
COVER OR GRATE
PART# 2712AG6IP*
SOLID COVER: 1299CGC*
GRATE: 1299CGS
18" (450 mm) MIN WIDTH
CONCRETE SLAB
8" (200 mm) MIN THICKNESS
PAVEMENT
CONCRETE COLLAR NOT REQUIRED
FOR UNPAVED APPLICATION
* THE PART# 2712AG6IPKIT CAN BE
USED TO ORDER ALL NECESSARY
COMPONENTS FOR A SOLID LID
INSPECTION PORT INSTALLATION
PART # STUB A B C
SC310EPE06T / SC310EPE06TPC
6" (150 mm) 9.6" (244 mm)
5.8" (147 mm)
---
SC310EPE06B / SC310EPE06BPC ---
0.5" (13 mm)
SC310EPE08T / SC310EPE08TPC
8" (200 mm) 11.9" (302 mm)
3.5" (89 mm)
---
SC310EPE08B / SC310EPE08BPC ---
0.6" (15 mm)
SC310EPE10T / SC310EPE10TPC
10" (250 mm) 12.7" (323 mm)
1.4" (36 mm)
---
SC310EPE10B / SC310EPE10BPC ---
0.7" (18 mm)
SC310EPE12B
12" (300 mm) 13.5" (343 mm)
---
0.9" (23 mm)
ALL STUBS, EXCEPT FOR THE SC310EPE12B ARE PLACED AT BOTTOM OF END CAP SUCH THAT THE OUTSIDE DIAMETER OF
THE STUB IS FLUSH WITH THE BOTTOM OF THE END CAP. FOR ADDITIONAL INFORMATION CONTACT STORMTECH AT
1-888-892-2694.
* FOR THE SC310EPE12B THE 12" (300 mm) STUB LIES BELOW THE BOTTOM OF THE END CAP APPROXIMATELY 0.25" (6 mm).
BACKFILL MATERIAL SHOULD BE REMOVED FROM BELOW THE N-12 STUB SO THAT THE FITTING SITS LEVEL.
NOTE: ALL DIMENSIONS ARE NOMINAL
NOMINAL CHAMBER SPECIFICATIONS
SIZE (W X H X INSTALLED LENGTH) 34.0" X 16.0" X 85.4" (864 mm X 406 mm X 2169 mm)
CHAMBER STORAGE 14.7 CUBIC FEET (0.42 m³)
MINIMUM INSTALLED STORAGE* 31.0 CUBIC FEET (0.88 m³)
WEIGHT 35.0 lbs. (16.8 kg)
*ASSUMES 6" (152 mm) ABOVE, BELOW, AND BETWEEN CHAMBERS
PRE-FAB STUBS AT BOTTOM OF END CAP FOR PART NUMBERS ENDING WITH "B"
PRE-FAB STUBS AT TOP OF END CAP FOR PART NUMBERS ENDING WITH "T"
PRE CORED END CAPS END WITH "PC"
34.0"
(864 mm)
16.0"
(406 mm)
90.7" (2304 mm) ACTUAL LENGTH 85.4" (2169 mm) INSTALLED LENGTH
ACCEPTS 4" (100 mm) SCH 40 PVC
PIPE FOR INSPECTION PORT. FOR
PIPE SIZES LARGER THAN 4" (100 mm)
UP TO 10" (250 mm) USE INSERTA TEE
CONNECTION CENTERED ON A
CHAMBER CREST CORRUGATION
OVERLAP NEXT CHAMBER HERE
(OVER SMALL CORRUGATION)
BUILD ROW IN THIS DIRECTION
START END
A A
B C
SC-310 TECHNICAL SPECIFICATION
NTS
9.9"
(251 mm)
15.6"
(396 mm)
TRAFFIC LOADS: CONCRETE DIMENSIONS
ARE FOR GUIDELINE PUPOSES ONLY.
ACTUAL CONCRETE SLAB MUST BE
DESIGNED GIVING CONSIDERATION FOR
LOCAL SOIL CONDITIONS, TRAFFIC
LOADING & OTHER APPLICABLE DESIGN
FACTORS
ADAPTER ANGLES VARIABLE 0°- 360°
ACCORDING TO PLANS
A
18" (457 mm)
MIN WIDTH
AASHTO H-20 CONCRETE SLAB
8" (203 mm) MIN THICKNESS
VARIABLE SUMP DEPTH
ACCORDING TO PLANS
[6" (152 mm) MIN ON 8-24" (200-600 mm),
10" (254 mm) MIN ON 30" (750 mm)]
4" (102 mm) MIN ON 8-24" (200-600 mm)
6" (152 mm) MIN ON 30" (750 mm)
12" (610 mm) MIN
(FOR AASHTO H-20)
INVERT ACCORDING TO
PLANS/TAKE OFF
BACKFILL MATERIAL BELOW AND TO SIDES
OF STRUCTURE SHALL BE ASTM D2321
CLASS I OR II CRUSHED STONE OR GRAVEL
AND BE PLACED UNIFORMLY IN 12" (305 mm)
LIFTS AND COMPACTED TO MIN OF 90%
INTEGRATED DUCTILE IRON
FRAME & GRATE/SOLID TO
MATCH BASIN O.D.
NYLOPLAST STRUCTURE
NTS
NOTES
1. 8-30" (200-750 mm) GRATES/SOLID COVERS SHALL BE DUCTILE IRON PER ASTM A536
GRADE 70-50-05
2. 12-30" (300-750 mm) FRAMES SHALL BE DUCTILE IRON PER ASTM A536 GRADE 70-50-05
3. DRAIN BASIN TO BE CUSTOM MANUFACTURED ACCORDING TO PLAN DETAILS
4. DRAINAGE CONNECTION STUB JOINT TIGHTNESS SHALL CONFORM TO ASTM D3212
FOR CORRUGATED HDPE (ADS & HANCOR DUAL WALL) & SDR 35 PVC
5. FOR COMPLETE DESIGN AND PRODUCT INFORMATION: WWW.NYLOPLAST-US.COM
6. TO ORDER CALL: 800-821-6710
A PART # GRATE/SOLID COVER OPTIONS
8"
(200 mm)
2808AG
PEDESTRIAN LIGHT
DUTY
STANDARD LIGHT
DUTY
SOLID LIGHT DUTY
10"
(250 mm)
2810AG
PEDESTRIAN LIGHT
DUTY
STANDARD LIGHT
DUTY
SOLID LIGHT DUTY
12"
(300 mm)
2812AG
PEDESTRIAN
AASHTO H-10
STANDARD AASHTO
H-20
SOLID
AASHTO H-20
15"
(375 mm)
2815AG
PEDESTRIAN
AASHTO H-10
STANDARD AASHTO
H-20
SOLID
AASHTO H-20
18"
(450 mm)
2818AG
PEDESTRIAN
AASHTO H-10
STANDARD AASHTO
H-20
SOLID
AASHTO H-20
24"
(600 mm)
2824AG
PEDESTRIAN
AASHTO H-10
STANDARD AASHTO
H-20
SOLID
AASHTO H-20
30"
(750 mm)
2830AG
PEDESTRIAN
AASHTO H-20
STANDARD AASHTO
H-20
SOLID
AASHTO H-20
VARIOUS TYPES OF INLET AND
OUTLET ADAPTERS AVAILABLE:
4-30" (100-750 mm) FOR
CORRUGATED HDPE
WATERTIGHT JOINT
(CORRUGATED HDPE SHOWN)
APPENDIX A
Background Information
APPENDIX B
Sanitary Demand & Water Usage and FUS
3215 North Service Road Burlington, ON L7N 3G2 Tel +1 905 335 2353 Fax +1 905 335 1414 amecfw.com
Amec Foster Wheeler Environment & Infrastructure, Registered office: 2020 Winston Park Drive, Suite 700, Oakville, Ontario L6H 6X7 Registered in Canada No. 773289-9; GST: 899879050 RT0008; DUNS: 25-362-6642
P:\Work\TP114107\land\design\Calcs 2017\Halton Region -Water and Wastewater calcs incl future.doc
March 8, 2017 Our File: TPB173022 The Regional Municipality of Halton 1151 Bronte Road Oakville ON L6M 3L1 Dear Sir/Madam: RE: Water Usage and Sanitary Discharge Report for Royal Living Development,
Proposed Townhouse Development, 3225-3237 New Street, City of Burlington Background
Royal Living Development proposes to construct an 11-unit townhouse development at 3225-3237 New Street, Lots 2 and 3, Registered Plan 408, in the City of Burlington.
The site is currently occupied by two (2) one-storey residential houses. The site has an area of 0.20 ha, of which 0.053 ha will be landscaped. The property will be developed in one phase. Also, the existing lot to the west with an area of 0.094 ha is facilitated for future townhouse development, of which 0.047 ha will be landscaped. The sanitary discharge calculations will include the proposed site and accommodate for the future townhouse development. Table 8.2.1.3.A of the Ontario Building Code has been used to calculate water usage and sanitary discharge for residential occupant loadings. This development does not require water in the process and cooling water will not be required. Sanitary Discharge (Proposed Site) Residential Occupancy – Townhouses:
1. No. of Townhouse Units = 11 2. Bedrooms per Unit = 3
From the Ontario Building Code Table 8.2.1.3.A, Residential Occupancy, Dwellings 3 bedroom dwelling = 1,600 L / day / unit
Occupant Load = 1,600 L/ d / unit x 11 units = 17,600 L / day = 17.6 m3 / day
Total sanitary discharge for the Proposed Site = 17.6 m3 / day
Continued... Royal Living Development March 8, 2017
P:\Work\TP114107\land\design\Calcs 2017\Halton Region -Water and Wastewater calcs incl future.doc Page 2 of 3
Sanitary Discharge (Future Site) Residential Occupancy – Townhouses:
3. No. of Townhouse Units = 4 4. Bedrooms per Unit = 3
From the Ontario Building Code Table 8.2.1.3.A, Residential Occupancy, Dwellings 3 bedroom dwelling = 1,600 L / day / unit
Occupant Load = 1,600 L/ d / unit x 4 units = 6,400 L / day = 6.4 m3 / day
Total sanitary discharge for the Future Site = 6.4 m3 / day Therefore, Total Sanitary Discharge = Proposed Site + Future Site
= 24 m3 / day
Continued... Royal Living Development March 8, 2017
P:\Work\TP114107\land\design\Calcs 2017\Halton Region -Water and Wastewater calcs incl future.doc Page 3 of 3
Water Usage Residential Occupancy – Townhouses:
Total water usage for the Site = 24 m3 / day (see above)
Landscaping for Proposed Site: Site landscaping area = 0.053 ha = 530 m2
25.4 mm / m2 / week x 530 m2 = 1.92 m3 / day
Total landscape water usage for the Proposed Site = 1.92 m3 / day
Landscaping for Future Site: Site landscaping area = 0.047 ha = 470 m2
25.4 mm / m2 / week x 470 m2 = 1.70 m3 / day
Total landscape water usage for the Future Site = 1.70 m3 / day
Therefore, Total Water Usage = 24 m3 / day + 1.92 m3 / day + 1.70 m3 / day = 27.62 m3 / day
Yours truly, Amec Foster Wheeler Environment & Infrastructure, a Division of Amec Foster Wheeler Americas Limited Per: Paul Pagazani, P. Eng. Per: Angelo J. Cutaia, P. Eng. Senior Engineer Principal Consultant PP/kf
WATER SUPPLY FOR PUBLIC FIRE PROTECTION - 1999
Project Name: 3225-3237 New Street, Burlington
Project Number: TPB173022
Date: March 2017
Prepared by: P. Pagazani
GUIDE FOR DETERMINATION OF REQUIRED FIRE FLOW
F = 220 C ( A ) 0.5 An estimate of the fire flow required for a given area may be determined by this formula.
F = required fire flow in litres per minute
Townhouse Units - Entire Row:
OUTLINE OF PROCEDURE
A. Determine the type of construction.
= 1.0 non-combustable construction
B. Determine the largest townhouse row of unit, Units 1 to 6.
= 846.7 m2 includes Units 1 to 6 and all 3-storeys.
C. Determine the height in storeys.
= 3 storeys
D. Using the fire flow formula above, determine the required fire flow to the nearest 1,000 litres/minute.
= 6402 L/min Round to 6000 L/min
= -25% non-combustible -1500 L/min = 4500 L/min
F. Determine the decrease, if any, for automatic sprinkler protection. Do not round off the value.
= 0 L/min no sprinkler protection (0% reduction)
G. Determine the total increase for exposures. Do not round off the values.
= 65% 2,925 L/min increase Separation Charge Total
South Exposure 10.1 to 20m 15%
East Exposure 20.1 to 30m 10%
West Exposure 3.1 to 10m 20%
North Exposure 3.1 to 10m 20%
H. To the answer obtained in E, subtract the value obtained in F and add the value obtained in G.
= 7425 L/min Round to 7000 L/min
C = coefficient related to the type of construction
= 1.5 for wood frame construction (structure essentially all combustible)
= 1.0 for ordinary construction (brick or other masonry walls, combustible floor and interior)
= 0.8 for non-combustible construction (unprotected metal structural components, masonry or metal wall)
= 0.6 for fire-restive construction (fully protected frame, floors, roof)
A = the total floor area in m2 (including all storeys, but excluding basements at least 50% below grade)
in the building being considered
E. Determine the increase or decrease for occupancy and apply to the value obtained in D above.
Do not round off the answer.
65%
APPENDIX C
Stormwater Management Calculations
A1 Pre Internal Site Area
(ha) % Impervious
Total Area: 0.200 Total Area: 1998 m2
Impervious: 0.047 Coefficient: 0.90 Impervious: 472 m2 24%
Lawns / Unimproved: 0.153 Coefficient: 0.20 Lawns / Unimproved: 1526 m2 76%
Composite C: 0.37
Therefore, a composite runoff coefficient of 0.40 will be assumed for the existing detached residential lots.
Prepared By: Paul Pagazani, P.Eng. Date: March 2017
Pre-Development Composite Coefficient
3225-3237 New Street, Burlington
File No. TPB173022
Time of Concentration Calculation Post Development Allowable Peak Flow
Area Number Area C Tc Storm
Event
(ha) (min.) 2
A1 Pre 0.200 0.40 10 5
100
Rational Method Calculation: Proposed Site
Event 2 yr Formula: I = a/(b+T)^cIDF Data Set City of Burlington a,b,c Constants
a = 592.60 T Time of concentration
b = 6.00 I Rainfall intensity
c = 0.780
Area Number A C AC Tc I Q Q
(ha) (min.) (mm/h) (m3/s) (L/s)
A1 Pre 0.200 0.40 0.08 10 68.2 0.015 15
Event 5 yr
IDF Data Set City of Burlington
a = 697.40
b = 5.00
c = 0.764
Area Number A C AC Tc I Q Q
(ha) (min.) (mm/h) (m3/s) (L/s)
A1 Pre 0.200 0.40 0.08 10 88.1 0.020 20
Event 100 yr
IDF Data Set City of Burlington
a = 1114.20
b = 5.00
c = 0.761
Area Number A C AC Tc I Q Q
(ha) (min.) (mm/h) (m3/s) (L/s)
A1 Pre 0.200 0.40 0.08 10 141.9 0.032 32
20
32
Rational Method
Allowable Flow Calculations
Prepared By: Paul Pagazani, P.Eng. Date: March 2017
3225 New Street, Burlington -Royal Living Development
File No. TPB173022
Peak Flow
(L/s)
15
Time of Concentration Calculation Post Development Allowable Peak Flow
Area Number Area C Tc Storm
Event
(ha) (min.) 2
A1 Pre 0.200 0.40 10 5
A1 Future 0.094 0.40 10 100
Rational Method Calculation: Proposed Site including Future Lot
Event 2 yr Formula: I = a/(b+T)^cIDF Data Set City of Burlington a,b,c Constants
a = 592.60 T Time of concentration
b = 6.00 I Rainfall intensity
c = 0.780
Area Number A C AC Tc I Q Q
(ha) (min.) (mm/h) (m3/s) (L/s)
A1 pre + A1 future 0.294 0.40 0.12 10 68.2 0.022 22
Event 5 yr
IDF Data Set City of Burlington
a = 697.40
b = 5.00
c = 0.764
Area Number A C AC Tc I Q Q
(ha) (min.) (mm/h) (m3/s) (L/s)
A1 pre + A1 future 0.294 0.40 0.12 10 88.1 0.029 29
Event 100 yr
IDF Data Set City of Burlington
a = 1114.20
b = 5.00
c = 0.761
Area Number A C AC Tc I Q Q
(ha) (min.) (mm/h) (m3/s) (L/s)
A1 pre + A1 future 0.294 0.40 0.12 10 141.9 0.046 46
29
46
File No. TPB173022
Prepared By: Paul Pagazani, P.Eng. Date: March 2017
Peak Flow
(L/s)
22
Rational Method
Allowable Flow Calculations3225 New Street, Burlington -Royal Living Development
A1 Post Internal Site Area
(ha) % Impervious
Total Area: 0.200 Total Area: 1998 m2
Impervious: 0.147 Coefficient: 0.90 Impervious: 1470 m2 74%
Lawns / Unimproved: 0.053 Coefficient: 0.20 Lawns / Unimproved: 528 m2 26%
Composite C: 0.72
A2 Post Future Site Area
(Future) (ha)
Total Area: 0.094 Total Area: 940 m2
Impervious: 0.047 Coefficient: 0.90 Impervious: 470 m2 50%
Lawns / Unimproved: 0.047 Coefficient: 0.20 Lawns / Unimproved: 470 m2 50%
Composite C: 0.55
Prepared By: Paul Pagazani, P.Eng. Date: March 2017
Post-Development Composite Coefficient
3225-3237 New Street, Burlington
File No. TPB173022
Project: 3225 New Street, Burlington -Royal Living Development
Project No.: TPB173022
Date: March 2017
Prepared by: P. Pagazani
A1 POST 100 - year A1 PRE 5 - year
CONTROLLED ALLOWABLE FLOW
Areas C AxC Areas C AxC
0.147 0.90 0.132 0.200 0.40 0.080
0.053 0.20 0.011 0 0.20 0.000
0 0.20 0.000 0 0.20 0.000
0 0.20 0.000 0 0.20 0.000
TOTAL 0.200 0.143 TOTAL 0.200 0.080
0.72 avg. C 0.40 avg. C
a b c a b c
1114.2 5 0.761 697.4 5 0.764
t i Q Vol in set Q out Vol out Vol req'd t i Q
10 141.89 0.056 33.78 0.020 11.73 22.05 10 88.094 0.020
15 113.99 0.045 40.71 0.016 14.13 26.58 15 70.712 0.016
20 96.19 0.038 45.81 0.013 15.89 29.92 20 59.629 0.013
25 83.73 0.033 49.84 0.012 17.27 32.56 25 51.875 0.012
30 74.46 0.030 53.19 0.010 18.43 34.76 30 46.112 0.010
40 61.50 0.024 58.57 0.008 20.28 38.30 40 38.056 0.008
50 52.79 0.021 62.85 0.007 21.74 41.10 50 32.647 0.007
60 46.49 0.018 66.41 0.006 22.97 43.45 60 28.735 0.006
70 41.69 0.017 69.49 0.006 24.02 45.47 70 25.759 0.006
80 37.90 0.015 72.20 0.005 24.95 47.25 80 23.410 0.005
90 34.83 0.014 74.63 0.005 25.78 48.85 90 21.503 0.005
100 32.27 0.013 76.84 0.004 26.53 50.31 100 19.920 0.004
110 30.11 0.012 78.87 0.004 27.23 51.64 110 18.583 0.004
120 28.26 0.011 80.75 0.004 27.87 52.88 120 17.436 0.004
130 26.66 0.011 82.51 0.004 28.47 54.04 130 16.440 0.004
140 25.24 0.010 84.15 0.003 29.03 55.12 140 15.567 0.003
150 23.99 0.010 85.70 0.003 29.56 56.14 150 14.793 0.003
160 22.88 0.009 87.16 0.003 30.06 57.11 160 14.103 0.003
170 21.88 0.009 88.56 0.003 30.53 58.02 170 13.483 0.003
180 20.97 0.008 89.88 0.003 30.98 58.90 180 12.923 0.003
190 20.15 0.008 91.15 0.003 31.42 59.73 190 12.414 0.003
200 19.40 0.008 92.37 0.003 31.83 60.54 200 11.948 0.003
100-yr Design Storm 5-yr Design Storm
Proposed Site (0.20ha) Only
Project: 3225 New Street, Burlington -Royal Living Development
Project No.: TPB173022
Date: March 2017
Prepared by: P. Pagazani
A1 + A2 POST 100 - year A1 PRE 5 - year
CONTROLLED ALLOWABLE FLOW
Areas C AxC Areas C AxC
0.147 0.90 0.132 0.200 0.40 0.080
0.053 0.20 0.011 Future 0.094 0.40 0.038
Future 0.047 0.90 0.042 0 0.20 0.000
Future 0.047 0.20 0.009 0 0.20 0.000
TOTAL 0.294 0.195 TOTAL 0.294 0.118
0.66 avg. C 0.40 avg. C
a b c a b c
1114.2 5 0.761 697.4 5 0.764
t i Q Vol in set Q out Vol out Vol req'd t i Q
10 141.89 0.077 46.01 0.029 17.25 28.76 10 88.094 0.029
15 113.99 0.062 55.45 0.023 20.78 34.67 15 70.712 0.023
20 96.19 0.052 62.38 0.019 23.36 39.02 20 59.629 0.019
25 83.73 0.045 67.88 0.017 25.40 42.47 25 51.875 0.017
30 74.46 0.040 72.44 0.015 27.10 45.34 30 46.112 0.015
40 61.50 0.033 79.77 0.012 29.82 49.95 40 38.056 0.012
50 52.79 0.029 85.59 0.011 31.97 53.62 50 32.647 0.011
60 46.49 0.025 90.45 0.009 33.77 56.68 60 28.735 0.009
70 41.69 0.023 94.63 0.008 35.32 59.32 70 25.759 0.008
80 37.90 0.020 98.33 0.008 36.68 61.64 80 23.410 0.008
90 34.83 0.019 101.64 0.007 37.91 63.73 90 21.503 0.007
100 32.27 0.017 104.65 0.007 39.02 65.63 100 19.920 0.007
110 30.11 0.016 107.42 0.006 40.04 67.38 110 18.583 0.006
120 28.26 0.015 109.98 0.006 40.98 68.99 120 17.436 0.006
130 26.66 0.014 112.36 0.005 41.86 70.50 130 16.440 0.005
140 25.24 0.014 114.60 0.005 42.69 71.92 140 15.567 0.005
150 23.99 0.013 116.71 0.005 43.46 73.25 150 14.793 0.005
160 22.88 0.012 118.71 0.005 44.20 74.51 160 14.103 0.005
170 21.88 0.012 120.60 0.004 44.90 75.71 170 13.483 0.004
180 20.97 0.011 122.41 0.004 45.56 76.85 180 12.923 0.004
190 20.15 0.011 124.14 0.004 46.20 77.94 190 12.414 0.004
200 19.40 0.010 125.79 0.004 46.81 78.99 200 11.948 0.004
100-yr Design Storm 5-yr Design Storm
Proposed Site (0.20ha) including Future Lot (0.094 ha)
ORIFICE SIZING CALCULATIONS
Project: 3225 New Street, Burlington -Royal Living Development
Project No.: TPB173022
Date: March 2017
C = 0.72 (5-yr release to City storm sewer system)
Q = 0.0200 From Allowable Flow Calculations
Water Elevation = 86.95 Water elevation at 100-yr storm
invert = 86.04 invert of CB/MH 1
head = 0.860 to center of orifice
orifice dia = 0.100 assumed orifice
Dia. = 0.100 outlet orifice pipe
Q = 0.0200 flow check
Proposed Site (0.20ha) Only
Project Information & LocationProject Name 3225-3237 New Street, Burlington Project Number TPB173022
City Burlington State/ Province Ontario
Country Canada Date 3/6/2017
Designer Information EOR Information (optional)
Name Paul Pagazani Name
Company Amec Foster Wheeler Company
Phone # 905-335-2353 Phone #
Email [email protected] Email
Brief Stormceptor Sizing Report - 3225-3237 New Street, Burlington
Site Name 3225-3237 New Street, Burlington
Target TSS Removal (%) 80
TSS Removal (%) Provided 86
Recommended Stormceptor Model STC 300
Stormceptor Sizing SummaryStormceptor Model % TSS Removal
Provided
STC 300 86
STC 750 91
STC 1000 92
STC 1500 92
STC 2000 93
STC 3000 94
STC 4000 96
STC 5000 96
STC 6000 97
STC 9000 98
STC 10000 98
STC 14000 98
StormceptorMAX Custom
The recommended Stormceptor Model achieves the water quality objectives based on the selected inputs, historical rainfall records and selected particle size distribution.
Stormwater Treatment Recommendation The recommended Stormceptor Model(s) which achieve or exceed the user defined water quality objective for each site within the project are listed in the below Sizing Summary table.
Stormceptor Brief Sizing Report – Page 1 of 2
Notes• Stormceptor performance estimates are based on simulations using PCSWMM for Stormceptor, which uses the EPA Rainfall and Runoff modules.• Design estimates listed are only representative of specific project requirements based on total suspended solids (TSS) removal defined by the selected PSD, and based on stable site conditions only, after construction is completed.• For submerged applications or sites specific to spill control, please contact your local Stormceptor representative for further design assistance.
Drainage Area
Total Area (ha) 0.20
Imperviousness % 74.0
Water Quality Objective
TSS Removal (%) 80.0
Runoff Volume Capture (%)
Oil Spill Capture Volume (L)
Peak Conveyed Flow Rate (L/s) 20.00
Water Quality Flow Rate (L/s)
Rainfall
Station Name HAMILTON A
State/Province Ontario
Station ID # 3194
Years of Records 34
Latitude 43°10'N
Longitude 79°56'W
Up Stream Storage
Storage (ha-m) Discharge (cms)
0.000 0.000
0.003 0.010
0.005 0.020
Particle Size Distribution (PSD)The selected PSD defines TSS removal
Fine Distribution
Particle Diameter(microns)
Distribution %
Specific Gravity
20.0 20.0 1.30
60.0 20.0 1.80
150.0 20.0 2.20
400.0 20.0 2.65
2000.0 20.0 2.65
Up Stream Flow Diversion
Max. Flow to Stormceptor (cms)
Sizing Details
For Stormceptor Specifications and Drawings Please Visit: http://www.imbriumsystems.com/technical-specifications
Stormceptor Brief Sizing Report – Page 2 of 2
Project Information & LocationProject Name 3225-3237 New Street, Burlington Project Number TPB173022
City Burlington State/ Province Ontario
Country Canada Date 3/6/2017
Designer Information EOR Information (optional)
Name Paul Pagazani Name
Company Amec Foster Wheeler Company
Phone # 905-335-2353 Phone #
Email [email protected] Email
Brief Stormceptor Sizing Report - 3225-3237 New Street, Burlington
Site Name 3225-3237 New Street, Burlington
Target TSS Removal (%) 80
TSS Removal (%) Provided 84
Recommended Stormceptor Model STC 300
Stormceptor Sizing SummaryStormceptor Model % TSS Removal
Provided
STC 300 84
STC 750 90
STC 1000 91
STC 1500 91
STC 2000 92
STC 3000 93
STC 4000 95
STC 5000 95
STC 6000 96
STC 9000 97
STC 10000 97
STC 14000 98
StormceptorMAX Custom
The recommended Stormceptor Model achieves the water quality objectives based on the selected inputs, historical rainfall records and selected particle size distribution.
Stormwater Treatment Recommendation The recommended Stormceptor Model(s) which achieve or exceed the user defined water quality objective for each site within the project are listed in the below Sizing Summary table.
Stormceptor Brief Sizing Report – Page 1 of 2
Notes• Stormceptor performance estimates are based on simulations using PCSWMM for Stormceptor, which uses the EPA Rainfall and Runoff modules.• Design estimates listed are only representative of specific project requirements based on total suspended solids (TSS) removal defined by the selected PSD, and based on stable site conditions only, after construction is completed.• For submerged applications or sites specific to spill control, please contact your local Stormceptor representative for further design assistance.
Drainage Area
Total Area (ha) 0.294
Imperviousness % 66.0
Water Quality Objective
TSS Removal (%) 80.0
Runoff Volume Capture (%)
Oil Spill Capture Volume (L)
Peak Conveyed Flow Rate (L/s) 29.00
Water Quality Flow Rate (L/s)
Rainfall
Station Name HAMILTON A
State/Province Ontario
Station ID # 3194
Years of Records 34
Latitude 43°10'N
Longitude 79°56'W
Up Stream Storage
Storage (ha-m) Discharge (cms)
0.000 0.000
0.005 0.015
0.007 0.029
Particle Size Distribution (PSD)The selected PSD defines TSS removal
Fine Distribution
Particle Diameter(microns)
Distribution %
Specific Gravity
20.0 20.0 1.30
60.0 20.0 1.80
150.0 20.0 2.20
400.0 20.0 2.65
2000.0 20.0 2.65
Up Stream Flow Diversion
Max. Flow to Stormceptor (cms)
Sizing Details
For Stormceptor Specifications and Drawings Please Visit: http://www.imbriumsystems.com/technical-specifications
Stormceptor Brief Sizing Report – Page 2 of 2