176
GAIL GAS LTD (A wholly owned subsidiary of GAIL (India) Limited) CNG AND CITY GAS DISTRIBUTION PROJECT BID DOCUMENT FOR SCADA SYSTEM VOLUME – II OF II (TECHNICAL) (BID DOCUMENT NO: 110290/WGI/GAIL GAS/21-R0) INTERNATIONAL COMPETITIVE BIDDING ISSUED DATE: 16.08.2010 ISSUED BY

City Gas gail Jp Kenny- Wood Group India

Embed Size (px)

Citation preview

Page 1: City Gas gail Jp Kenny- Wood Group India

GAIL GAS LTD (A wholly owned subsidiary of GAIL (India) Limited)

CNG AND CITY GAS DISTRIBUTION PROJECT

BID DOCUMENT FOR

SCADA SYSTEM VOLUME – II OF II (TECHNICAL)

(BID DOCUMENT NO: 110290/WGI/GAIL GAS/21-R0)

INTERNATIONAL COMPETITIVE BIDDING

ISSUED DATE: 16.08.2010

ISSUED BY

Page 2: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

0

TABLE OF CONTENT

SHEET 1 of 1

MAIN TABLE OF CONTENTS

S.No. DOCUMENT TITLE DOCUMENT NUMBER No. of

Sheets

1.0 MATERIAL REQUISITION (MR) 11- 0290- 02-11- 02- 001 9

2.0 TECHNICAL SPECIFICATIONS FOR SCADA 11- 0290- 02-11- 02- 002 95

3.0 ARCHITECTURAL DRAWING 11-0290-02-11-01-001 1

4.0 CONTROL CENTER(S) LAYOUT DRAWING 11-0290-02-11-01-002 1

5.0 CNG COMPRESSOR I/O DETAILS 11

6.0 CNG DISPENSER I/O DETAILS 4

7.0 TECHNICAL SPECIFICATION FOR UPS SYSTEM

11-0290-02-10-02-006 13+1

8.0 TECHNICAL DATA SHEET FOR UPS 11-0290-02-11-01-002 7

9.0 QUALIFICATION, PROVENNESS REQUIREMENTS & TECHNICAL FORMS

32

10.0

11.0

12.0

13.0

14.0

15.0.

16.0

Page 1 of 175

Page 3: City Gas gail Jp Kenny- Wood Group India

GAIL GAS LIMITED SCADA

0BCLIENT JOB NO. - MATERIAL REQUISITION FOR SCADA

1BTOTAL SHEETS 9

DOCUMENT NO 11 0290 02 11 02 001

0 12/08/10 ISSUED FOR TENDERING MLS HM HM

REV DATE DESCRIPTION PREP CHK APPR

Page 2 of 175

Page 4: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 001 0

GAIL GAS LIMITED

MATERIAL REQUISITION FOR SCADA

SHEET 2 of 9

TABLE OF CONTENT

1. SCOPE OF SUPPLY

2. REMARKS

3. SPECIAL INSTRUCTION TO BIDDER

4. INFORMATION/ DOCUMENTS/ DRAWINGS TO BE SUBMITTED BY SUCCESSFUKL BIDDER

Page 3 of 175

Page 5: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 001 0

GAIL GAS LIMITED

MATERIAL REQUISITION FOR SCADA

SHEET 3 of 9

1.0 SCOPE OF SUPPLY

1.1 General

This Material Requisition covers, supply, installation, testing & commissioning of SCADA System for City Gas Distribution (CGD) networks of Kota, Dewas, Sonepat and Meerut City.

The scope work covers: project management, system design, detailed engineering, manufacture/procurement and supply of all related goods and providing all related services including installation, testing, integration, trial run, commissioning, warranty, training, etc. complete in all respect, including the related civil works, cabling, preparation of the related drawings, documents, etc. for implementation of the SCADA system, which shall comprise of optical fiber and GPRS based communication, as per requirements in tender specification. The scope of supply & works shall be in accordance with the requirements of this Requisition; also includes shipment documentation, and at site support for maintenance requirements.

Item Description Quantity Remarks

1.0 Supply of MCC (Master Control Center) equipment at Noida, broadly comprising of redundant SCADA Servers (Primary & Secondary), 2 nos. Operating Stations, 1 no. Engineer Station, 60" large LCD screen, telecom equipments including Router & Switch, 3 Printers ( color laser, jet printer, dot matrix), UPS, fully wired, configured & equipped with all specified interfaces and capable of supporting interfaces, Furniture as specified in the Tender

LOT

2.0 OPTIONAL - Supply of SMCC (Standby-Master Control Center) equipment at XXXX, broadly comprising of redundant SCADA Servers (Primary & Secondary), 2 nos. Operating Stations, 1 no. Engineer Station, telecom equipments including Router & Switch, 3 Printers ( color laser, jet printer, dot matrix), UPS, fully wired, configured & equipped with all specified interfaces and capable of supporting interfaces, Furniture as specified in the Tender

LOT

3.0 Supply of CCC (City Control Center) equipment at Dewas, Sonepat, Kota, Meerut, broadly comprising of redundant Data Concentrator ( SCADA RTU), 2 nos. Operating Stations, telecom equipments including Router & Switch, GPRS, 2 Printers ( jet printer, dot matrix), UPS, fully wired, configured & equipped with all specified

4 No.

Page 4 of 175

Page 6: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 001 0

GAIL GAS LIMITED

MATERIAL REQUISITION FOR SCADA

SHEET 4 of 9

interfaces and capable of supporting interfaces, Furniture as specified in the Tender

4.0 Supply of remote telemetry units (RTU) along with associated cabinets, accessories including OFC & GPRS connectivity as per tender specification for City Gate Stations (CGS) at Dewas(1), Sonepat(1), Kota(2), Meerut(1) and SPARE (1).

6 SETS

5.0 Supply of remote telemetry units (RTU) alongwith associated cabinets, accessories including OFC & GPRS connectivity as per tender specification for online CNG Stations at Dewas(2), Sonepat(4), Kota(4), Meerut (5) and SPARE (3).

18 SETS

6.0 Supply of remote telemetry units (RTU) alongwith associated cabinets, accessories including OFC & GPRS connectivity as per tender specification for Daughter CNG Stations at Kota(1), Meerut(1) and SPARE (1).

3 SETS

7.0 Supply of Local Craft Terminal (LCT) for local management of Remote telemetry units (RTU), 1 for each city plus 1 SPARE.

5 No.

8.0 Supply of GPRS for Flow Computers / EVCs as per tender specification for Large Industrial Stations (MRS) at Dewas(25), Sonepat(20), Kota(21), Meerut (20).

86 No.

9.0 Supply of Mandatory Spares LOT

10.0 Supply of 2 years O&M Spares - OPTIONAL

11.0 Installation, integration, testing, commissioning etc. of SCADA equipment including UPS & Furniture at Master Control Station (MCC) at Noida compatible to operate with ITU-T G-652,G-655 fiber, fully wired, configured & equipped with all specified interfaces and capable of supporting interfaces as specified in the Tender

LOT

12.0 OPTIONAL - Installation, integration, testing, commissioning etc. of SCADA equipment including UPS & Furniture at Sub-Master Control Station (SMCC) at xxx compatible to operate with ITU-T G-652,G-655 fiber, fully wired, configured & equipped with all specified interfaces and capable of supporting interfaces as specified in the

LOT

Page 5 of 175

Page 7: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 001 0

GAIL GAS LIMITED

MATERIAL REQUISITION FOR SCADA

SHEET 5 of 9

Tender

13.0 Installation, integration, testing, commissioning etc. of SCADA equipment including UPS & Furniture at City Control Station (CCC) at Dewas, Sonepat, Kota, Meerut compatible to operate with ITU-T G-652,G-655 fiber, fully wired, configured & equipped with all specified interfaces and capable of supporting interfaces as specified in the Tender

4 LOT

14.0 A Installation, cabling, integration, testing, commissioning etc. of RTU (Item 4&5 above) at Dewas.

3 No.

14.0 B Installation, cabling, integration, testing, commissioning etc. of RTU (Item 4 &5 above) at Sonepat.

5 No.

14.0 C Installation, cabling, integration, testing, commissioning etc. of RTU (Item 4,5 &6 above) at Kota.

7 No.

14.0 D Installation, cabling, integration, testing, commissioning etc. of RTU (Item 4,5 &6 above) at Meerut

7 No.

15.0 A

Installation, cabling, integration, testing, commissioning etc. of GPRS on Flow Computers / Electronic Volume Correctors at Dewas.

28 No.

15.0 B

Installation, cabling, integration, testing, commissioning etc. of GPRS on Flow Computers / Electronic Volume Correctors at Sonepat.

25 No.

15.0 C

Installation, cabling, integration, testing, commissioning etc. of GPRS on Flow Computers / Electronic Volume Correctors at Kota.

28 No.

15.0 D

Installation, cabling, integration, testing, commissioning etc. of GPRS on Flow Computers / Electronic Volume Correctors at Meerut

27 No.

16.0 A Integration of SCADA equipment at MCC with CCC at Dewas SCADA equipments including supply of all hardwares and softwares

LOT

16.0 B Integration of SCADA equipment at MCC with CCC at Sonepat SCADA equipments including supply of all

LOT

Page 6 of 175

Page 8: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 001 0

GAIL GAS LIMITED

MATERIAL REQUISITION FOR SCADA

SHEET 6 of 9

hardwares and softwares

16.0 C Integration of SCADA equipment at MCC with CCC at Kota SCADA equipments including supply of all hardwares and softwares

LOT

16.0 D Integration of SCADA equipment at MCC with CCC at Meerut SCADA equipments including supply of all hardwares and softwares

LOT

17.0 OPTIONAL - Integration of SCADA equipment at SMCC with 4 CCCs at Dewas, Sonepat, Kota, Meerut SCADA equipments including supply of all hardwares and softwares

LOT

18.0 OPTIONAL - Integration of SCADA equipment at MCC with SMCCs SCADA equipments including supply of all hardwares and softwares

LOT

19.0

19 A

19 B

19 C

19 D

19 E

Maintenance Support for 5 years:

1st Year rate

2nd Year rate

3rd Year rate

4th Year rate

5th Year rate

Yearly Contract

20.0 Training for 75 Man days for SCADA System as per tender specification. And documentation

LOT

21.0 Unloading at site, storage, Insurance of material from receipt of material at site till commissioning and handing over of complete works ,handling transportation from store to different work sites, assembly installation along with associated civil and structural works, including supply of installation material i.e. Cables, Cable trays, Cable glands, pre-fab cables, connectors as per MR, testing, loop checking, pre-commissioning, system commissioning, SAT, trial run, handing over to client as per tender specification / MR.

Part of Site Works.

Page 7 of 175

Page 9: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 001 0

GAIL GAS LIMITED

MATERIAL REQUISITION FOR SCADA

SHEET 7 of 9

22.0 Supply of fully equipped Test RTUs (with all type of I/Os, Serial Interface and Communication interfaces) at MCC for Test use.

2 Nos.

23.0 Man days Rate 10 Man Days

2.0 REMARKS 2.1 Supplier’s Compliance

Supplier shall submit his bid in full compliance with the requirements of this MR and attachments.

Bidder shall include the following statement in his bid:

We certify that our bid is fully complying with your enquiry dated …... and referenced …………,

Compliance with this material Requisition in any instance shall not relieve the Vendor of his responsibility to meet the specified performance.

2.2 Compliance with Specification

The supplier shall be completely responsible for the design, materials, fabrication, testing, and inspection, preparation for shipment & transfer of above material to nominated delivery point strictly in accordance with the MR & all attachments thereto.

2.3 Supplier’s Scope

Supplier’s scope of work includes the equipment with all internals & accessories shown on the data sheets, specifications and all unmentioned parts necessary for a satisfactory operation & testing except those which are indicated to be out of Supplier’s supply.

2.4 The seller shall provide and explain in his proposal how the system can be expanded and demonstrate that the supplied SCADA system is capable of working with RTUs from other vendors.

2.5 Supply of all items / equipments including softwares, installation materials etc. required to execute the SCADA system complete in all respects and as per the Bill of Material / Schedule of Rates (SOR). However, if any additional items are required to meet the functionality of the SCADA system as per this tender, vendor shall supply the same without any cost and time implication to Gail Gas Limited.

Page 8 of 175

Page 10: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 001 0

GAIL GAS LIMITED

MATERIAL REQUISITION FOR SCADA

SHEET 8 of 9

3.0 SPECIAL INSTRUCTIONS TO BIDDERS 3.1 Bidder to note that no correspondence shall be entered into or entertained after the bid

submission. 3.2 Bidder shall furnish quotation only in case he can supply material & works strictly as per

this Material Requisition and specification/data sheets forming part of Material Requisition.

3.3 If the offer contains any technical deviations or clarifications or stipulates any technical

specifications (even if in line with MR requirements) and does not include complete scope & technical/ performance data required to be submitted with the offer, the offer shall be liable for rejection.

3.5 The submission of prices by the Bidder shall be construed to mean that he has

confirmed compliance with all technical specifications of the corresponding item(s). 3.6 Supplier must note that stage wise inspection for complete fabrication, testing including

raw material inspection to be carried out. 3.7 Vendors for bought out items to be restricted to the approved vendor list attached with

Bid document. Approval of additional vendor if required, for all critical bought out items shall be obtained by the supplier from the purchaser before placement of order. Credentials / PTR of the additional vendor proposed to be submitted by supplier for review and approval of Purchaser / Purchaser’s representative.

3.8 All material shall be delivered at Company’s designated storage yards. The destination

(Noida / Kota / Sonepat / Devas / Meerut) for delivery of items will be informed to successful vendor before dispatch of the equipment.

4.0 INFORMATION/ DOCUMENTS / DRAWINGS TO BE SUBMITTED BY SUCCESSFUL

BIDDER

Successful Bidder shall submit six copies unless noted otherwise, each of the following: 4.1 Inspection & test reports for all mandatory tests as per the applicable code as well as test

reports for any supplementary tests, in nicely bound volumes. 4.2 Statutory test certificates, as applicable. 4.3 Filled in Quality Assurance Plan (QAP) for Purchaser's / Consultant's approval. These

QAPs shall be submitted in four copies with in 15 days from LOI / FOI.

Page 9 of 175

Page 11: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 001 0

GAIL GAS LIMITED

MATERIAL REQUISITION FOR SCADA

SHEET 9 of 9

4.4 Within two (2) weeks of placement of order, the detailed Functional Design Specification with System Architectural Drawing showing module level details for Purchaser's / Consultant's approval.

4.5 Detailed completion schedule activity wise (Bar Chart), within one week of placement of

order. 4.6 Weekly & fortnightly progress reports for all activities including procurement. 4.7 Purchase orders of bought out items soon after placement of order.

4.8 Manufacturer's drawings for bought out items, in 4 copies, for Purchaser's/Consultant's approval within 4 weeks.

4.9 Manufacturer related information for design of civil foundation & other matching items

within 4 weeks of FOI / LOI. 4.10 All approved drawings / design calculation/ maintenance / operating manual documents

as well as inspection and test reports for Owner's / Consultants reference / record in nicely category-wise bound volumes separately.

4.11 A list of documents to be furnished along with supply. Note: All drawings, instructions, catalogues, etc., shall be in English language and all

dimensions shall be metric units. --------------------------------------------------x--------------x--------------------------------------------------------------------------------

Page 10 of 175

Page 12: City Gas gail Jp Kenny- Wood Group India

GAIL GAS LIMITED TECHNICAL SPECIFICATION FOR SCADA

0BCLIENT JOB NO. - TECHNICAL SPECIFICATION FOR SCADA

1BTOTAL SHEETS 95

DOCUMENT NO 11 0290 02 11 02 002

0 12/08/10 ISSUED FOR TENDERING MLS HM HM

REV DATE DESCRIPTION PREP CHK APPR

Page 11 of 175

Page 13: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 2 of 95

TABLE OF CONTENT

1. INTRODUCTION

2. REFERENCES

3. DESCRIPTION OF SCADA SYSTEM SITES

4. SCADA SYSTEM REQUIREMENTS

5. COMMUNICATION MEDIUM

6. SERVER CONTROL APPLICATION

7. CITY GAS DISTRIBUTION NETWORKS 8. PHILOSOPHY FOR SCADA SYSTEM

9. SCADA SOFTWARE PHILOSOPHY

10. SCALABILITY

11. GENERAL SITE INFORMATION AND ENVIRONMENT CONDITIONS

12. SCOPE OF SUPPLY & SERVICES

13. DESIGN / SYSTEM GUIDELINES 14. SPECIFICATIONS

15. SCADA SYSTEM SIZING 16. SUPPLY AND STORAGE OF EQUIPMENT 17. WARRANTY 18. OTHER REQUIREMENTS 19. TEST CATEGORIES, INSTALLATION, TESTING AND COMMISSIONING 20. SPARES PHILOSOPHY 21. QA / QC REQUIREMENTS

22. INPUT / OUTPUT DETAILS

Page 12 of 175

Page 14: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 3 of 95

23. POST WARRANTY ONSITE MAINTENANCE SUPPORT 24. PROJECT EXECUTION 25. MAN DAYS RATES 26. ATTACHMENTS

Page 13 of 175

Page 15: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 4 of 95

1.0 INTRODUCTION GAIL GAS LIMITED [A wholly owned subsidiary of GAIL (India) Ltd. ] is in the process of supplying piped natural gas to the domestic, commercial, industrial and CNG for vehicle transportation sections within the Geographical area of Kota City, Sonepat City, Meerut City and Dewas City. In future this operation of Gail Gas Limited (GGL) will expand to more Geographical area of cities in India; 30 cities are expected to be added in next five years. To facilitate the operation, monitoring, control, maintenance, supervision and management of the City Gas Distribution (CGD) network, the SCADA (Supervisory Control & Data Acquisition) system function is to provide safe and efficient operation of the pipeline and facilities with the minimum of manned intervention. The SCADA system operation shall be based on a 24 hour per day, 365 day per year schedule. Each city gas distribution network is primarily distributed among following major categories.

1. City Gate Station (CGS) 2. Industrial Metering System 3. Medium Industries and Commercial Metering System 4. CNG Stations.

CGS: GGL receives Natural Gas from GAIL inside the particular city and CGS is interface station between the GAIL Main Natural Gas Pipeline and GGL city gas distribution (CGD) network.

CNG Stations: There are two categories of CNG stations: a. Online CNG Stations – On line stations are connected to the pipeline and have high compression capacity. These stations supply CNG to both vehicles and daughter stations (through mobile cascades). Typically, they have the facility of filling all types of vehicles – buses, autos, cars etc. these CNG station comprises of compressors, dispensers, storage cascades and Facility for filling the mobile cascades. These stations are also classified as Mother Stations.

b. Daughter Stations – the Daughter Station dispenses CNG using mobile cascades. These mobile cascades at daughter stations are replaced when pressure falls. Pressure depleted mobile cascade is refilled at the Mother Station. There is reduction in storage pressure at daughter station with each successive filling.

2.0 REFERENCES

2.1 Codes and Standards The following standards shall be considered part of this specification insofar as they give definitions, describe requirements and provide tests that the equipment supplied shall meet. The standards used shall be the latest revision in force, including any addenda, supplements or revisions thereto. 2.1.1 International Standards

Page 14 of 175

Page 16: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 5 of 95

API • API 1113 Developing a Pipeline Supervisory Control Center • API 1130 Computational Pipeline Monitoring ANSI • ANSI/NFPA 75 Standard for the Protection of Electronic Computer Data

Processing Equipment NEMA • NEMA ICS 1 General Standards for Industrial Control and Systems • NEMA ICS 2-230 Components for Solid-State Logic Systems • NEMA ICS 3-304 Programmable Controllers • NEMA ICS-6 Enclosures for Industrial Controls and Systems IEC • IEC 61131 Programmable controllers - ALL PARTS • IEC 60870-5-101 Telecontrol equipment and systems - Part 5-101:

Transmission protocols - Companion standard for basic telecontrol tasks

ISA

• ISA S5.1 Instrumentation symbols and identification • ISA S5.2 Binary logic diagrams for process operation • ISA-5.3-1983 Graphic Symbols for Distributed Control/Shared Display Instrumentation, Logic, and Computer Systems • ISA S5.4 Instrument loop diagrams • ISA-5.5-1985 Graphic Symbols for Process Displays • ISA S18.1 Alarm annunciation sequence and specification • ISA-50.02 Fieldbus Standard for Use in Industrial Control Systems Part

2: Physical Layer Specification and Service Definition • ISA RP55.1 Hardware testing of digital process computers • ISA-RP60.3-1985 Human Engineering for Control Centers • ISA S71.04 Environmental conditions for process measurement and

control systems: Airborne contaminants • ISA S72.1 LAN Industrial data highway • EWICS-1998 Guidelines for the Use of Programmable Logic Controllers in

Safety Related Systems • EWICS-1997 Guidelines on Achieving Safety in Distributed Systems

2.1.2 Indian Standards • IS 732-1989 Code of Practice for Electrical Wiring Installations • IS 3034-1993 Fire Safety of Industrial Buildings: Electrical, Generating and Distribution Stations – Code of Practice • IS 3043 Code of practice for earthing • IS 5572-1994 Classification of Hazardous Areas (other than mines) Having Flammable Gases and Vapors for Electrical Installation • IS 5887 – 1980 Testing of computer based systems • IS 8239-1916 Classification of Maximum Surface temperatures of

Electrical Equipment for use in Explosive Atmospheres

Page 15 of 175

Page 17: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 6 of 95

2.1.3 Other Standards

• API MPMS 12.2 Calculation of Petroleum Quantity Using Dynamic Measurement Methods and Volume Correction Factors

• IEEE 472 Guide for Surge Withstand Capability • IEEE C37.1 Automatic and Supervisory Station Control and Data

Acquisition • IEEE 730 Software Quality Assurance Plan • IEEE 830 Software Requirement Specification • IEEE 802.3 Standard CSMA/CD Media Access Control (Ethernet) • IEEE 829 Software Test Documentation • ANSI MC8.1 Recommended Practice Hardware Testing of Digital

Process Computers • ITU V.23 Modem VF interference • ITU V.24 DCE/DTE Interface • BS 5345: Part 4:1977 UK Code of Practice for Intrinsic Safety • BS 5501: Part 6:1977 Intrinsic Safety ‘e’ • BS 1259: 1958 Intrinsic Safety Standard • EIA-232 Interface between data terminal equipment and data

communication equipment employing serial binary data interchange

• EIA-422 Electrical characteristics of balanced voltage digital interface circuits

• EIA-485 Electrical Characteristics of Generators and Receivers for use in Balanced Digital Multipoint Systems

• ISO/9001/02/03 Quality System for Design/Production and Installations / Final Inspection and Testing

• MIL-STD-461B Radio Frequency and Electro-magnetic Interference 3.0 DESCRIPTION OF SCADA SYSTEM SITES

Two control centers are proposed at national level; Master Control Center (MCC) & Standby Master Control Center (SMCC). MCC will be located in Noida and SMCC at another location; both Control Centers will communicate with City Control Center (CCC) of each city. The propose of the control rooms and other stations is to provide the following: a. MASTER CONTROL CENTER (MCC): Master Control Center shall be based in NOIDA to monitor, control and configure the CGD systems of all cities under GAIL GAS Operation. The MCC will communicate with all the City Control Centers. MCC will have two servers, one primary and other redundant. If MCC Primary Server fails MCC Redundant Server takes over. Operator Stations in MCC communicate to this MCC Server; Operator Stations are not disturbed if these servers swap internally (i.e. seamless connection).

Page 16 of 175

Page 18: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 7 of 95

Scope of Supply at MCC o Supply, installation and commissioning of redundant SCADA servers with 19” TFT type LCD Monitor.

o Supply, installation and commissioning of two nos. of operator station with 21” TFT type LCD Monitor.

o Supply, installation and commissioning of one nos. of Engineer station with 21” TFT type LCD Monitor.

o Supply, installation and commissioning of wall mounted 60” large LCD monitor with Digital Dolby sound System.

o Supply, installation and commissioning of console desk and training desk. o Supply, installation and commissioning of telecom system to connect the remote station.

o Supply, installation and commissioning of laser printer suitable for A3 & A4 size paper for report printing.

o Supply, installation and commissioning of desk jet printer for reports. o Supply, installation and commissioning of B&W dot matrix printer for alarm/event. o Supply, installation and commissioning of networking hardware including 100 MBPS Managed Ethernet Switch for local area network, Router for Wide Area Network connectivity with SMCC and CCCs (via Leased Line).

o Supply of SCADA Software

o Supply, installation and commissioning of UPS system to provide uninterrupted power supply to all equipments.

o Supply of required Furniture as shown in Control Center Layout Drawing.

b. STANDBY-MASTER CONTROL CENTER (SMCC): OPTIONAL It is intension that control shall normally be from the MCC. The Standby-Master Control Center (SMCC) shall be able to monitor and control total CGD systems in case of any emergency at MCC in NOIDA. The SMCC shall normally be on line but configuration services at SMCC will be disabled while control is from the MCC. Control shall be transferred to the SMCC by an operator action in normal operation mode of MCC as well automatically in the event of a total system failure at the MCC & vice-versa. Control permission shall be operator initiated operation of MCC and automatic in case of total failure of MCC. The SMCC will communicate with MCC & all the City Control Centers. SMCC will have two servers, one primary and other redundant. If SMCC Primary Server fails SMCC Redundant Server takes over.

Scope of Supply at SMCC

o Supply, installation and commissioning of redundant SCADA servers with 19” TFT type LCD Monitor.

o Supply, installation and commissioning of two nos. of operator station with 21” TFT type LCD Monitor.

Page 17 of 175

Page 19: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 8 of 95

o Supply, installation and commissioning of one nos. of Engineer station with 21” TFT type LCD Monitor.

o Supply, installation and commissioning of telecom system to connect the remote station.

o Supply, installation and commissioning of laser printer suitable for A3 & A4 size paper for report printing.

o Supply, installation and commissioning of desk jet printer for reports. o Supply, installation and commissioning of B&W dot matrix printer for alarm/event. o Supply, installation and commissioning of networking hardware including 100 MBPS Managed Ethernet Switch for local area network, Router for Wide Area Network connectivity with SMCC and CCCs (via Leased Line).

o Supply, installation and commissioning of UPS system to provide uninterrupted power supply to all the equipments.

o Supply of required Furniture as shown in Control center Layout Drawing.

c. CITY CONTROL CENTER (CCC) City Control Center shall collect all the data of the City Gas Distribution Network and will send it to MCC & SMCC in addition to monitor and control CGD network of the city. CCC will be made in Kota, Meerut, Dewas and Sonepat city.

Scope of Supply at CCC o Supply, installation and commissioning of redundant Data Concentrator (SCADA RTU) for collecting data of CGD network and interfacing with MCC & SMCC.

o Supply, installation and commissioning of two nos. of operator station with 21” TFT type LCD Monitor.

o Supply, installation and commissioning of telecom system to connect the remote station.

o Supply, installation and commissioning of B&W laser jet printer suitable for A4 size paper for report printing.

o Supply, installation and commissioning of B&W dot matrix printer for alarm/event. o Supply, installation and commissioning of networking hardware including 100 MBPS Managed Ethernet Switch for local area network, Leased Line (2mbps) Communication with MCC & SMCC, GPRS Communication with CGS & DRS, Daughter Station & FC/EVC at MRS. Data Concentrator will be fitted with GPRS communication card.

o Supply, installation and commissioning of UPS system to provide uninterrupted power supply to all equipments.

o Supply of required Furniture as shown in Control Center Layout Drawing.

Page 18 of 175

Page 20: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 9 of 95

d. CITY GATE STATION (CGS): GAIL has Flow Meter & Flow Computer / EVC and its signals shall be made available to GAIL GAS SCADA RTU through serial port. GAIL GAS LIMITED will be installing Odorizing Unit which shall be connected to SCADA RTU through serial port at Odorizing Unit electronic panel for monitoring, Odorizing Agent Stock and mixing ratio shall also be polled by RTU. Details shall be furnished to vendor at detail engineering stage. Scope of Supply at CGS

o Supply, installation and commissioning of non-redundant RTU

o Supply, Installation and commissioning of telecom system. o Integration of existing flow boss 600 / EVC and Odorizing system with upcoming SCADA system.

o Supply, laying and terminating the cables.

e. CNG STATIONS:

Online CNG Station CNG stations are having compressors monitored and controlled by PLC panels; these PLCs shall be polled by SCADA RTU, additionally: - Report gas compressed by CNG compressors - Report critical compressor parameters - Report sale / collection through dispensers at mother / daughter station. - Report stock of CNG in the fixed cascades at mother / daughter stations. - Report stock in transit on the mobile cascades. - Monitor turnaround time of mobile cascades by capturing dispatch data time stamp at mother station and receipt date & time stamp at Daughter Station.

CNG stations are having Dispensing Stations which shall communicate with SCADA for: - Report Filling No. with Gas Quantity filled, Pressure and Total Bill amount. - Receive Uploading of price. Scope of Supply at Online CNG Station

o Supply, installation and commissioning of non-redundant RTU

o Integration of SCADA RTU at each CNG stations with Siemens makes existing Local control system (PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO).

o Integration of Local Control system (Mass Flow Meters at each dispenser / compressor / fixed cascade / mobile cascade & Dispensers) with proposed SCADA system.

o Supply, installation and commissioning of telecom system.

o Supply, laying and terminating the cables.

Page 19 of 175

Page 21: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 10 of 95

Scope of Supply at Daughter CNG Station

o Supply, installation and commissioning of non-redundant RTU.

o Supply, installation and commissioning of telecom system. RTU shall be fitted with GPRS communication card for communication with CCC.

o Integration of Local Control system (Mass Flow Meters at each dispenser / mobile cascade & Dispensers) with proposed SCADA system.

o Supply, laying and terminating the cables.

o Integration of RTU system with upcoming SCADA system.

f. LARGE INDUSTRIAL STATIONS: It is an interface station between GGL and industrial user who take natural gas at high amounts. MRS is installed; Flow Computers or EVC are equipped with GSM card and vendor shall procure GPRS connectivity in the name Gail Gal Limited. These FC / EVCs will be polled by SCADA system. Scope of Supply at Large Industrial Stations

o Integration of existing flow computer / EVC with proposed SCADA system.

o Supply, Installation and commissioning of telecom system, GPRS shall be installed on Flow Computer / EVC.

4.0 SCADA SYSTEM REQUIREMENTS

The SCADA system shall provide following features as a minimum: a. SCALABLE as more cities will be added to this SCADA system in future. Basic requirements like Modularity, Expendability and Homogeneity.

b. Distributed architecture for future expansion and variety of communication media. c. Data acquisition and control of various critical field equipments. d. Processing the field data to detect alarms and other significant process changes. e. Logging, reporting and trending capabilities at the MCC and SCC. f. Database historian, which provides for archiving and retrieval of history data. g. Presenting the data to the operator via easy to understand graphical displays, alarms, trends and reports.

h. Interface with local monitoring system like Flow Computer and third party system. i. Performing system monitoring and diagnostics to detect failure of hardware and / or software and take appropriate actions including remote diagnostic facilities for the trouble shooting.

j. Interfacing with RTU is over the network using different protocols (i.e. DNP 3.0 IEC, and Modbus RTU).

k. Flexibility / compatibility with future up-gradation of technology. l. Use of standard protocol m. Back up on removable storage media such as writable CD, Tapes, Optical Disks etc.

Page 20 of 175

Page 22: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 11 of 95

n. Interface with GPS receiver for time synchronization o. Time synchronization of all control centers, RTUs, PLC and FCs. p. The SCADA software with the main SCADA database shall be SCADA server resident and shall be built around Microsoft Windows Server operating system or Unix operating system. Vendor to ensure that offered operating system life is minimum plus 5 years.

q. The SCADA HMIs and web server shall be Microsoft Windows based. r. The SCADA system shall provide generic ODBC interface for interfacing third party software applications.

s. The SCADA system will be WEB enabled so as to view the reports and HMI displays through Internet / Intranet.

t. The networking shall support OSI TCP/IP network connectivity. u. RTUs shall be IP based. NOTES: I . All the hardware to be supplied, as part of the contract shall be newly manufactured utilizing good engineering practices. The SCADA Vendor shall source the hardware either from the OEMs or from the authorized agent of the OEMs.

II. Each SCADA server shall be based on 64 bits multiple processors architecture with two processors installed.

III. SCADA Vendor shall ensure that the offered SCADA servers, workstations, Web server models meet the above requirement and in case model number is required to be upgraded to meet the functionality and for fulfilling the system loading requirements, the same shall be done by the SCADA vendor, at any stage of the project implementation without any price and schedule implications.

IV. In case the SCADA vendor is not manufacturing the RTUs, then the SCADA vendor shall procure the complete RTUs from the RTU manufacturer. The complete RTU with all its components along with the RTU cabinets completely wired and tested shall be supplied from the proven manufacturing facilities and locations.

5.0 COMMUNICATION MEDIUM

• Telecommunication channels based on any combination of leased line 2 MBPS (point to point or multi-dropped) / dial-up line / VPN (point to point or multi-dropped) / TCP/IP shall be used to connect MCC, SMCC and CCCs.

• Use GPRS communication between CCC and CGS / Mother CNG station / Online CNG Stations / Daughter CNG Station. However, all RTUs shall be equipped with OFC & GPRS (redundant) connectivity.

• Use GPRS communication between CCC and MRS (FC / EVC). NOTE: Vendor will procure Third party Communication links (Leased line & GPRS) to meets all the above requirements (in the name of GAIL Gas Ltd.)

Page 21 of 175

Page 23: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 12 of 95

6.0 SERVER CONTROL APPLICATION Redundant (Primary & Secondary) servers at MCC and SMCC to provide SCADA functionality with respect to data collection, HMI function and SCADA system interfaces to other systems. The application shall be developed for Managing the MCC & SMCC servers remotely and locally. Following options shall be available: a. Server states – it shall be possible to stop and start any server; Stopping and Starting servers includes disabling and enabling communication channels respectively.

b. Synchronizing – it shall be possible to synchronize (internal copy of data files / SQL tables for history and events) between any servers in any direction.

c. Station Connection – it shall be possible to connect station to any required server d. Separate servers for independent processing and interfaced through a dual redundant LAN network shall be provided for:

• SCADA Database Servers • Printer Server (if required) • Video Wall Servers • Web Servers

7.0 CITY GAS DISTRIBUTION (CGD) NETWORKS

7.1 CITY DEWAS 7.1.1 CGS: 1 No.

• Flow Computer (Details of Serial Port will be furnished during detail Engineering)

• Odorizing Units (Details of Serial Port will be furnished during detail Engineering) 7.1.2 Online CNG Station: 2 No.

• Xxx o Compressors (1 no.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

• Xxx o Compressors (1 no.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

Page 22 of 175

Page 24: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 13 of 95

7.1.3 MRS

o Flow Computers – 5 nos. o EVC – 20 nos.

7.2 CITY SONEPAT 7.2.1 CGS: 1 No.

• Flow Computer (Details of Serial Port will be furnished during detail Engineering)

• Odorizing Unit (Details of Serial Port will be furnished during detail Engineering)

7.2.2 Online CNG Station: 4 Nos.

• Xxx o Compressors (1 nos.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

• Xxx o Compressors (1 nos.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

• Xxx o Compressors (1 nos.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

• Xxx o Compressors (1 nos.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

Page 23 of 175

Page 25: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 14 of 95

7.2.3 MRS

o Flow Computers – 5 nos. o EVC – 15 nos.

7.3 CITY KOTA 7.3.1 CGS: 2 No.

• Xxx o Flow Computer (Details of Serial Port will be furnished during detail Engineering)

o Odorizing Unit (Details of Serial Port will be furnished during detail Engineering)

• Xxx o Flow Computer o Odorizing Unit

7.3.2 Online CNG Station: 4 Nos.

• Xxx o Compressors (1 nos.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

• Xxx o Compressors (1 nos.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

• Xxx o Compressors (1 nos.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

Page 24 of 175

Page 26: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 15 of 95

• Xxx o Compressors (1 nos.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

7.3.3 Daughter Station: 1 nos.

• Xxx o Mobile Cascade o Dispensers (X nos.) o Compressor

7.3.4 MRS

Flow Computers – 6 nos. EVC – 15 nos.

7.4 CITY MEERUT

7.4.1 CGS 1 No.

• Flow Computer (Details of Serial Port will be furnished during detail Engineering)

• Odorizing Unit (Details of Serial Port will be furnished during detail Engineering)

7.4.2 Online CNG Station: 5 Nos.

• Xxx o Compressors (1 nos.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

• Xxx o Compressors (1 nos.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

Page 25 of 175

Page 27: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 16 of 95

• Xxx o Compressors (1 nos.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

• Xxx o Compressors (1 nos.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

• Xxx o Compressors (1 nos.) Kirloskar make, Siemens make PLC (S7), MMI OP77B, CPU – S7 300 – 315 – 2DP (2A010-OABO)

o Flow meter input o Air Compressor status o Dispensers (X nos.) o Fixed Cascade

7.4.3 Daughter Station: 1 Nos.

• Xxx o Mobile Cascade o Dispensers (X nos.) o Compressor

7.4.4 MRS

Flow Computers – 5 nos. EVC – 15 nos.

8.0 PHILOSOPHY FOR SCADA SYSTEM

SCADA Server # 1 and SCADA Server # 2 shall be configured in dual hot standby mode as Primary and Secondary at MCC & SMCC.

The flow computers, PLCs and gas chromatographs of the remote sites, where RTU is installed, will be connected to the RTU. The RTU will poll these devices through its

Page 26 of 175

Page 28: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 17 of 95

serial port. RTU in turn will be polled from DATA concentrator at CCC. The field devices of the sites not having RTU will be polled directly from DATA concentrator.

Normally, the primary server shall poll the DATA concentrator. The communication channels between MCC and CCCs shall be Leased Line (point to point or multi-drop)/ VPN (point to point or multi-drop)/ Dialup / TCP/IP.

In case of flow computers / RTUs / GCs having in-built GSM modems and having GPRS connectivity, the SCADA system shall have the provision of polling these flow computers or EVCs through GPRS / VPN connectivity.

8.1 Setup at MCC, Noida

The SCADA system shall comprise of two SCADA servers, one Web Server, one engineering workstation, Two Operator workstation, one GPS time server, one switch, one router, One 60 Inch LCD screen and associated SCADA system accessories.

All the SCADA database of the CCC shall be available in SCADA servers at MCC. Any changes in the database of the SCADA system at CCC for addition, modification, deletion etc of RTUs / FC / IEDs shall be carried out from SCADA servers or engineering workstation at MCC. Data concentrator of CCC will be connected to SCADA system at MCC through dedicated 2 MBPS links (Leased Line).

The SCADA system for Integrated SCADA data will have provision to upload nominations through excel file. Screen shall be provided to view and edit the nominations.

Health status of each of the SCADA Servers, Web server, and HMIs shall be updated in SCADA system on real-time basis.

8.2 SCADA Server redundancy and fail over :

SCADA Server # 1 and SCADA Server # 2 shall be configured in dual hot standby mode as Primary and Secondary.

If the Primary Server fails completely, due to any one of CPU failure / disc failure / power supply failure / software failure, the secondary server shall become the primary server within 2 minutes and smooth changeover shall be accomplished automatically without causing any loss of data and control and without any effect on SCADA functionality. Operator shall be informed about the failed system by a suitable event/message by new primary SCADA server.

On re-induction of failed SCADA Server, the operator shall be informed by a suitable event message generated by the system that the Server is fully synchronized with the

Page 27 of 175

Page 29: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 18 of 95

primary SCADA Server. Based on the decision by supervisor or system engineer, the restored machine shall continue to be hot standby or it shall be possible by system engineer to change the status of restored machine as primary machine.

8.3 Time Synchronization between SCADA Servers:

The SCADA servers shall synchronize its time through GPS time server.

8.4 Database and Alarm Synchronization between SCADA Servers:

The database and alarms of secondary server shall always be synchronized with its primary SCADA server. Operator supervisory actions (manual inputs, online SCADA database, alarm acknowledgements, alarm inhibit, digital controls, set-point controls etc.) shall be updated from the active Server to database of standby SCADA Server to maintain database sync.

9.0 SCADA SOFTWARE PHILOSOPHY

9.1 Standard Software

As far as practical all software modules shall be of OEM’s standard software. Standard software shall be defined as follows:

• Software which has been previously installed and provided satisfactory operation and control of similar control systems

• Software that requires minimal tailoring with agreed parameters to suit the requirements specified, is scaleable for different size sites.

• Software for which standard documentation is available • Software for which correction/updating facilities are available to all users • The latest version supported by the Bidder.

Configuration function blocks and ladder logic shall conform to these definitions. Any known bugs, faults or problems are to be identified at the tender submission stage.

9.2 Non-Standard Software

Where software development is required either to provide a specified or optional function, the item shall be clearly noted as ‘non-standard’.

Sufficient, detailed, descriptive information concerning ‘non-standard’ software, shall be submitted to enable a full understanding of the proposed algorithm, method of programming, structure, method of testing and proposed documentation.

Page 28 of 175

Page 30: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 19 of 95

9.3 Program Structure

All compiled software functions shall be constructed from individual modules, with clearly defined interfaces between the modules. Each module shall provide a specific component function and be designed such that changes in one module require no changes to any other module.

The program shall be well documented with the reason for each module included in the program. Notes shall be included explaining any calculations or logic used. Reference to logic diagrams and the logic diagram number system shall also be included.

9.4 Programming Languages

Programming languages supported by the operating system software shall be stated, specifically detailing what is offered. Further, the language(s) that the application programs are written in shall be stated.

The programming languages offered should include ‘hooks’ to the real time database, through database subroutine calls.

High level programming language(s) shall be provided to implement applications and logic programs on SCADA level.

9.5 Editors, Libraries and System Utilities

The system shall include a full screen editor, routine library and system utilities such that facilities exist to perform programming and system maintenance on the system programs.

Database Software Interfaces

9.5.1 Real-Time Database

The real-time database shall be a high performance memory based design capable of providing a high rate of data processing to support concurrent real-time SCADA functions such as data collection/processing, alarm/event processing, historical data management and HMI requests. All access to the real-time database shall be based on Structured Query Language (ANSI SQL 92) commands. SQL access to the database shall be possible from Bidder supplied programs as well as custom user written programs using languages such as C, C++ and Java. The system shall also be provided with a graphical user interface for direct interactive user queries of the database. Access to the real-time database shall be restricted by user logon privileges.

Page 29 of 175

Page 31: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 20 of 95

9.5.2 Historical Database

Real-time data shall be saved into a historical database system for long term processing and archiving. The historical database shall be disk based and shall use the RAID disk array as the storage media. It shall be possible archive the historical database. The database “engine” shall be based on common industry based products such as Oracle and Sybase. The use of proprietary database system for this function shall not be permitted. Discrete (status) data shall be treated as a time stamp on the change of state from 1 to 0 and vice versa.

9.6 SCADA Displays

Project specific displays shall include overview and mimic displays of the overall pipeline system. Specific details shall include a detailed view of each major portion of the overall pipeline system.

The SCADA displays shall be subject to approval by the Owner. The general arrangement of screen displays shall have active icons located at the top of the display. SCADA Bidder “standard” displays shall include: • Logs and Tabular Displays • Graphics package • Reports • Displays

Details of standard SCADA displays required are listed below.

9.6.1 Logs and Tabular Displays

• Database summaries (Analog, status, etc.) • System status summary • Security Audit log • Communications summary • Active Alarm summary • Event / Alarm summary • Disabled Alarms • Remote processor status • System Parameters • Hourly Reports • Daily Reports • Monthly Reports

Page 30 of 175

Page 32: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 21 of 95

9.6.2 Graphics package: • Multiple Trends (multi-pen, sliding window) including Real time trends with trend alarms

• Set point, process variables and controller outputs • Alarm deviation limits • Alarm Messages and device status • Single loop displays • Real time plots of process variables with colour to indicate exceeding of pre-set limits

• Bar Graph displays • Scratch pad notes for control operators

Project specific displays shall include overview and mimic displays of the overall pipeline system. Specific details shall include a detailed view of each major portion of the overall pipeline system. Standard Graphic Displays These system displays can be roughly divided up into the following groups:

� Detailed - Provides detailed information about a particular point. This information includes current values, scanning, control, alarming, history, and algorithm details.

� Trend - Provides a very flexible way of graphing historical process values. Trends include single, dual and triple bar charts, multi-plot charts, and x-y charts.

� Group - Provides a means of viewing information about a group of points on one display. The information can be displayed as a multi-plot trend, numerically, or as the current values.

� Summary-- Lists a summary of available items. They allow you to choose one of the items to look at in further detail (for example, Report Summary).

� Status-- Provides detailed status information about the EPKS system. This includes information about channels, controllers, printers, and Stations.

Customized Graphic Display Builder shall be provided for building customized graphics displays. In case of City Gas Distribution project, following custom graphics can be prepared:

� Detail site display showing CNG stations parameters � Detail site display showing Daughter station/CGS station/District Regulating Station parameters.

� Detail system architecture.

9.6.3 Standard & customized Reports:

Reports extract information from the server database. Reports may be requested and

printed on demand, or scheduled to be automatically generated reports at pre-defined

times. Reports can be sent to printers or to operator Station displays. System shall

produce both:

Page 31 of 175

Page 33: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 22 of 95

� Standard Reports, which are preformatted reports provided with EPKS and

contain information about alarms, events, points, and so on.

� Custom Reports, which can contain almost any kind of information stored in the

server database.

These reports shall be produced either on request or as scheduled in SCADA system to

automatically produce reports at pre-defined times.

Standard (Pre-Formatted) Reports � Alarm/Event Log reports all alarms and events in a specified time period. By using filters, this report provides an operator and/or point trace facility.

� Alarm Duration Log reports the time of occurrence and elapsed time before return-to-normal for specific alarms in a specified time period.

� Point Attribute Log reports on points displaying specific attributes, such as off-scan, bad data, and alarm inhibit.

� Point Cross-Reference determines database references for specified points to enable easier system maintenance when points are decommissioned or renamed.

Customized Reports � Free Format Report Writer generates reports in flexible formats, which may include math and statistical functions such as Max/Min and standard deviation. We can do perform following function through free format reports

� Get values from point parameters

� Perform calculations on those values (for example, addition, subtraction,

multiplication, division, and exponentiation)

� Retrieve historical data to determine summations, maximums, minimums,

and standard deviations

� Generate an X-Y plot of the historical values for two points

� Store new values or calculations in the server database or in operating

system files

Content of the reports can be determined in consultation with GGL during detail engineering stage.

Reports shall be available in MS Office files. Automatic generation of Email on stated time shall be offered. Shift reports, day reports, alarm by email shall be provided and explained by seller.

Page 32 of 175

Page 34: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 23 of 95

The analysis tools and client software shall work on both real time data and historical data. Data processing, generation of various reports and logs shall be explained by the seller. Historical storage and archiving facilities, engineering computation facilities will be provided by the seller.

9.6.4 Alarm Philosophy

Alarm reporting constitutes one of the most critical man-machine communication issues and must be organized such that system abnormalities are presented in a clear, unambiguous and convenient manner to the operating personnel. The following general requirements are intended to ensure dependable and timely operation of the alarm subsystem: • The system shall be able to hold at least 5,000 alarms and events in a FIFO buffer on disk for the operator alarms screen MMI display • Displayed Alarm Summary shall prioritize alarms by time with the latest alarm at the top of the display • Repetitive reporting and logging of any single alarm condition shall not occur • The alarm subsystem software shall be designed to ensure that no system alarms are lost during normal or burst periods due to conditions such as internal buffer overflow. • The capability to allow the operator to inhibit the reporting of any alarm condition (device failures, communication failures, changes of status, etc) shall be provided and it shall be logged as an event. • The system shall be capable of alarming on all digital inputs, analog inputs and calculated points in the system. • Unacknowledged alarms shall be uniquely identified by flashing and colour on all summary, station schematic and tabular displays. • In general, a return-to-normal condition shall be treated as an alarm condition. • The RTU’s shall time stamp status changes to the nearest one millisecond and pass the time stamp to the SCADA system for display in the alarm displays and event summaries. • Analog and pulse input accumulators shall be time stamped to the nearest millisecond when scanned by the RTU. • A minimum of 4 levels of alarming for prioritization purposes. The levels are emergency, high priority, normal priority and low priority. • The ability to link alarms to particular operator consoles. Alarms shall be printed as they occur if selected so by the operator, otherwise they shall be sent to a file for viewing and printing by the operator as required. All alarms shall be stored on the servers in files. The operator shall have the ability to review the alarm files and print out alarms individually or by page as required. Alarm and event logs shall be reconciled on the primary and backup servers on the network, so that the complete histories would be presented to the operator.

Page 33 of 175

Page 35: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 24 of 95

Alarms & Event Management: SCADA System will provide comprehensive alarm and event detection, management, and reporting facilities. The standard Alarm Summary display allows operators to focus in on the problem at hand by supporting filters. Alarms may be filtered by:

Area Acknowledge Status Priority

Alarms on the Alarm Summary display can be acknowledged either individually or per page. On custom graphics, alarms can similarly be acknowledged on an individual or per page basis. Colors for the various priority levels of alarms can be configured by the user for display purposes in the Alarm Summary and on custom graphics. System shall supports the configuration of alarm priority colors, and these alarm priorities are also displayed on all process graphic displays. This enables operators to immediately determine which alarm conditions on their displays are most important. In addition to this feature, the alarm annunciator in the Station status zone blinks with the color of the highest priority unacknowledged alarm – another time saving feature for plant personnel.

o Alarm type: For SCADA point structures, up to 9 alarms can be configured for a point. Supported alarms include: 1. PV Hi --Process variable high limit alarm 2. PV Lo –Process variable low limit alarm 3. PV HiHi –Process variable high high limit alarm 4. PV Lolo –Process variable low low limit alarm 5. Deviation Hi –Positive deviation limit alarm 6. Deviation Lo –Negative deviation limit alarm 7. Rate of Change –PV rate of change alarm 8. Control Fail –Control fail alarm 9. Control Timeout –Control timeout alarm

o Alarm priority:

Each of the configured alarms can be assigned a priority ranging from General, Low, High, and Urgent. An alarm sub priority (0 to 15) can also be assigned to further differentiate alarms.

Page 34 of 175

Page 36: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 25 of 95

Priority Event

General

Audible Display Print

General Y N N N

Low Y Y Y Y

High Y Y Y Y

Urgent Y Y Y Y

The Event Summary list events that occur in the system, including:

• Alarms • Alarm Acknowledgments • Return to Normal • Operator Control Actions • Operator Login, logout & Security Level Changes • On-line Database Modifications • Communications Alarms • System Restart messages

9.7 Structure and Navigation Displays shall be organized in a hierarchical structure starting from the overview displays and moving progressively downwards with increasing level of details. Each display shall be linked to related displays such as adjacent facilities or a functionally similar system. It shall be possible to maneuver upwards, downwards and sideways in the hierarchical layers using simple pointer commands. A mechanism using layered pull-down menus shall be provided to allow quick and direct access to any display in the system without a need to actual navigate through a series of intermediate displays. In no case shall it be necessary to use a command line entry to bring up a display. All screen displays shall be identified by a unique serial number on the display.

9.8 Historical Storage & Archiving

The SCADA system shall provide storage of archived selected data. Some data files will be held online as historical data. Selected data files shall also be archived to permanent storage. Bidder shall include full details of the historical storage and archiving system offered. This should include details of :

Page 35 of 175

Page 37: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 26 of 95

• How the historical and archive data can be accessed by the SCADA system and other users. • Server capability and redundancy • Hard disk configuration • Database structures and operating system • Configurable data retention time • Dead banding capability for Analog inputs • Reduction group functions including compression and reduction of data, group average, group maximum and minimum • Event messages • OPC data

9.8.1 Historical Storage Historical storage shall be held on line and shall be limited to the current day and the previous thirty-five days of data, arranged such that the previous data is always available for review. Data to be held in the historical log shall include: • All status changes • All calculated and real Analog data • All alarms

9.8.2 Archived Storage

Archive storage of selected data will include but not necessarily be limited to the following: • System Reports held in archive for 35 days. • Monthly System Report, comprising a summary of the operations for the month. • Analog Point File, comprising selected Analog trend records stored and archived daily. The archive system shall allow the transfer of archive data in at least text format to other computer based systems, and shall also allow hard copy printouts of archive data. The archive system shall archive the required data files daily. The system shall verify the correct receipt of archive data. In the event that data cannot be archived satisfactorily the archive system shall generate an appropriate message and hold the data until the next archive period or until a manual archive command is initiated

9.9 Antivirus Software

♦ Antivirus should be controlled & managed through main server of the network

♦ The antivirus must able to Detect, block, and remove viruses, spyware, adware, even rootkits—insidious programs designed to tamper with computer system.

♦ In antivirus there should have emerging threats analyzer and blocker in milliseconds, so need not to wait for regular updates to arrive.

Page 36 of 175

Page 38: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 27 of 95

♦ The antivirus should have Site Advisor which would help users to know about a website's risks before you click to stop malware threats. There should be "phishing" protection alerts for user to websites that may try to steal networks identity or gain access to your financial information.

♦ Antivirus should have firewall facility which would Block outsiders from hacking and check incoming and out going data.

♦ Stay safe with instant message and email link checking. Identifies and prevents network, server, and computer system from clicking on harmful website links in your browser, email, or instant messages.

♦ Stay safe with instant message and email link checking.

9.10 Software Licensing and Revision Upgrades

All software provided to meet the requirements of this specification shall be provided complete and without further or ongoing licensing fees. All revision upgrades released prior to the issue of the Final Certificate shall be provided free of any charges or installation fees. The Owner may elect not to upgrade to the new revision. The Owner, as the owner of the licenses, may transfer them should the plant change ownership.

9.11 System Security Requirements

The SCADA system shall be provided with a security / access management system to restrict access to authorized users only. The security / access management shall apply to all SCADA workstations, MCC, SMCC and Web based terminal access sessions. Multiple security access levels shall be provided to allow differentiation of privileges for the following as a minimum: • Casual user (view only) • Operator (can issue commands via MMI system) • MCC operator • Maintenance and support staff (can make changes to SCADA database). • System supervisor (have access to program files and can make system level changes)

Security Configuration The security provided for the SCADA system can be described as follows:

1. Windows operating system security. 2. Station security

Windows Operating system security

To prevent an operator from accessing the operating system and software other than SCADA station software, the operator station SHALL be configured as a secure station through setup Windows 2000 operating system security.

For example, the following security will be setup through Windows 2000 Local Security Policy and System Registry:

Page 37 of 175

Page 39: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 28 of 95

� Setup operator automatic logon � Create a batch file which starts station automatically � Prevent operators from shutting down their computer � Remove access to applications via Task Manager and Windows Explorer � Prevent users from locking the computer

Station security When you build a Station, you define the security method that will control access to functions at that Station. You choose between:

• Station-based security

• Operator-based security

Station-based security Station-based security works as follows:

• Station starts without prompting users to enter any form of operator ID or

password.

• The initial security level setting allows users to perform the basic operating

functions associated with the user level of Oper (for example, acknowledging

alarms and controlling points).

• Users only need to use a password if they want to change to a higher level of

security.

• Asset assignment applies to the Station, not to the operator.

Operator-based security Operator-based security provides a higher level of security than Station-based security. In general, Operator-based security with traditional operator accounts shall work as follows:

• GAIL GAS LIMITED will assign a specific security level to each user.

• Users cannot access any Station functions unless they enter a valid ID and

password.

• To access a higher security level than the one they are currently using, users need

to sign off and sign on again as a different operator who has the higher security

level.

Page 38 of 175

Page 40: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 29 of 95

• Assignable assets are assigned to the operator, irrespective of which Station they

are currently logged on to.

Security Levels - It shall be possible to set different security levels; these levels are

shown in the following table in ascending order of access.

Security Levels

Default Security Level Acronym Default Meaning

View Only, previously called Lvl1 (Available with

operator-based security only)

View-only mode

Ack Only, previously called Lvl2 (Available with

operator-based security only)

Alarm acknowledgement mode

Oper Operator mode

Supv Supervisor mode

Engr Engineer mode

Mngr Manager mode

9.12 Audit Logging of Commands The Web based terminal, MCC, SMCC, HMI operator logon sessions shall be logged in the operational log to track the controls and actions taken by individual operators as events. The system shall also provide the ability to log engineering changes with details of activities for tacking of all system related changes. The log shall be stored electronically on disk and be accessible by the system supervisor logon permission only. The entries within the log shall contain as a minimum the date and time of commands, the command executed, the point number, database reference number and the name and identity number of the operator. The date and time of operator log on and logoff shall also be recorded in the log. The audit log shall be viewable by the supervisor and able to be printed.

9.13 HMI WEB Display Builder. The SCADA system shall have Web server technology for enabling GGL to provide secure read-only access to casual users. For example, GGL production manager requires access to the latest production figures, but does not need control of the

Page 39 of 175

Page 41: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 30 of 95

process. WEB Server shall provide GGL production manager with read-only access on request to the process graphic displays without providing any control.

Casual users can navigate through process schematics and other displays in the same

way as navigating to any Web site or Web page.

There are two types of access to the WEB Server:

Standard access: With standard access, users are provided with a "snapshot" of your plant displays with data current at the time of navigating to the display using any Web browser. Users are isolated from control of the plant and therefore do not have access to process alarms, that is, users cannot view or acknowledge alarms. Users are limited to using the navigation controls on the pages. Premium access: With premium access, users are provided with "live" plant displays with updating data, using Internet Explorer. Users do not have any control of the plant and do not have access to process alarms, that is, users cannot view or acknowledge alarms. Their interaction is limited to navigation controls and copying trend and report data to other applications such as Microsoft Excel and Microsoft Word.

9.14 GENERAL

The data acquisition function shall provide all the aspects needed to support data collection from the field including the requesting of data from RTUs/PLCs/IEDs and the processing of analog and digital data received from the same. The data is to be collected from field Devices like RTU/PLC/IED over leased line / dial-up / TCP/IP.

For polling on dial up, system shall be configured to provide redundancy in telephone lines. In case of failure of particular telephone line, the stations/IEDs to be polled on failed telephone line shall be polled automatically on other telephone line.

In case of flow computers / RTUs / GCs having in-built GSM modems and having GPRS connectivity, the SCADA system shall have the provision of polling these flow computers/ RTUs / GCs through GPRS / VPN connectivity

The frequency of data polling from a field device should be configurable and the duration of may vary from 10 seconds up to 24 hours i.e. poll the device once in a day. The total no of devices (RTUs and IEDs) shall be distributed across the ports of the terminal server and polling rate shall be configurable device-wise.

All polled data shall be time tagged and quality tagged at the server immediately upon receipt of the data.

Page 40 of 175

Page 42: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 31 of 95

All analog polled data shall be checked for High, High-High, Low - Low and Low alarm limit violation at the SCADA server. Similarly all polled digital inputs shall be checked for alarm violation/events immediately upon receipt of data at the server.

The following types of data are to be retrieved from the various types of field devices

a) Analog input (4-20 mA) like Pressure, Temperature etc.

b) Digital input (Dry contacts, On-Off) like status of valve, compressor Run/Stop etc.

c) Serial data from IEDs (PLCs and Flow computers) either directly by the RGMC Servers or through the RTUs.

The SCADA system shall support DNP 3.0, IEC-5-101, Modbus and DF1 protocols. It shall be possible to read and write data (analog and digital) directly from IEDs / PLCs through serial link using Modbus / DF1 / Bells protocols.

For some devices e.g. for valves, it shall be possible to use two digital inputs i.e. open status and close status to derive four states of the valve - Open, Close, Travel and Error.

10.0 SCALABILITY

The SCADA system shall be configured and sized for the system based on I/O count as listed in tender document. All hardware, software and memory storage to meet this requirement shall be provided with the initial SCADA system. The SCADA system shall be capable of expansion to include future City Gas Distribution (CGD) Network systems, to be provided with the same monitoring and control capability. SCADA System Software and Hardware to be designed in such a way that presently it will cater to the requirement of four cities, but should be configurable to add RTUs and CCCs of 30 more cities in next 5 years span. The seller shall provide and explain in his proposal how the system can be expanded and demonstrate that the supplied SCADA system is capable of working with RTUs from other vendors.

The SCADA system shall be latest, field proven open architecture and shall be based on a client/server computer network, using industry standard operating systems, networks, and protocols. The system shall allow the distribution of system functions across the network to enhance flexibility and performance. Supplier shall provide latest version of operating and application system software at the time of FAT. The Vendor is required to supply a complete, functioning system complying with the following design considerations: -

a) Client — Server architecture

Page 41 of 175

Page 43: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 32 of 95

b) Dual, redundant hardware configuration for data processing and server applications, power supply and communication functions. c) Redundant network interlace for connection to SCADA Servers I other external systems via open connectivity provided by Ethernet I TCP-IP. d) Object oriented design features e) Open system compliance (SQL and OPC support) f) Compliance to OSI standards for Open system I Open architecture g) Inherent “Reporting By Exception” data transfer from RTUs h) Software capable of rapid application development in multi-high level languages i) Embedded ‘event driven’ design features j) Communication support over leased lines and Fiber Optic k) ‘Off the Shelf” hardware & software with availability and support. I) Increased level of diagnostics in I/O, processing and communication. m) Time synchronization with GPS n) SCADA clients and servers in a dual, redundant Ethernet I TCP-IP network to provide operator interface I monitoring and to be located in the MCC / SMCC. o) Communication protocol between master station & RTUs shall confirm to IEC 60870- 5-104 or DNP 3.0 over Ethernet. p) Multiple types of Communication media support to SMCS. q) Robustness under consistently high operating temperatures. r) Modularity in Functional and Operational Design. s) The SCADA system must be capable of communicating, via open systems applications, with other open architecture-compliant devices and platforms, which will be configured to provide operators and maintenance personnel access to system information, including the ability to: i. View the status and values of all configured DIs, DOs, Als and AOs. ii. View all fault alarms. iii. Exercise forcing of selected (pre-configured) digital outputs. iv. All Processing configuration parameters and diagnostic statistics.

t) Hardware design and construction should allow for the easy installation of additional modules or cards to handle new or additional RTU communications.

11.0 GENERAL SITE INFORMATION AND ENVIRONMENT CONDITIONS

All the equipment supplied under this contract shall be suitable for continuous operation under the environmental conditions prevailing at site. The equipment shall be suitable for transportation under proper packed conditions by road, air, sea, conforming to standards. The equipment shall also be resistant to termite, fungus, rodents and salty environment. All enclosed equipment shall be constructed to allow free air flow for proper heat dissipation, and ventilation grill shall not obstruct operation and maintenance of equipment. All equipment shall withstand international standards for vibration under industrial operation.

Page 42 of 175

Page 44: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 33 of 95

ENVIRONMENTAL SPECIFICATIONS: All equipment, test instruments, special tools and tackles etc. shall be capable of maintaining the guaranteed performance with operational lifetime of 20 years minimum when operating continuously under the following environmental conditions:

1 Temperature

Operate For all supplies 0º to + 48º C guaranteed and up to +55º C degraded.

Storage -10º C to +70º C

2 Humidity At any relative humidity up to 95% within the temperature range of 0º C to 40º C

3 Altitude At any altitude up to 600m above sea level

4 Sand and Dust The housing to be supplied along with the equipment should be in such a way that entry for dust, insect / rodent is totally prohibited.

5 Tropicalisation Shall be fully tropicalised with all cards & confirmedly coated with lacquer.

6 Shock and vibration Shall withstand transportation and handling by air, sea and road under packed conditions.

7 Salt, fog and mould Shall withstand continuous usages in marine growth environment.

8 Electromagnetic Shall meet the requirements as per IEC Compatibility-801.

12.0 SCOPE OF SUPPLY & SERVICES

The SCADA Vendor shall undertake full responsibility for providing a complete and evolutionary state of the art SCADA system with Open architecture, meeting the objectives, functional and specific requirements described in the tender. i. Vendor’s scope of supply and services shall include, but not limited to all the

activities of the project management, design, engineering, training, factory testing, supply, installation, commissioning, site testing, test run, packaging, forwarding, transportation, insurance, port handling, custom clearance, inland transportation (freight), insurance, port handling, custom clearance, inland transportation etc., receipt & storage at site, warranty, quality assurance and quality control of the system and documentation with the turnkey responsibility and meet the requirements described in the specifications and taking care of complete requirements of tender specifications. Vendor to provide logistic support certificate from original equipment manufacturer in case of supplier.

ii. The scope of supply and services shall also include fulfillment of complete telemetry requirements for monitoring and control as per the project requirements detailed in tender specification.

iii. Supply of all items/equipments including cabinets etc., special tools, test equipments (if any), software, installation materials etc.

Page 43 of 175

Page 45: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 34 of 95

iv. Supply of engineering manuals, all documentation, drawings and other information required including user operation & maintenance manuals and handbook of inventory of all the equipments supplied and installed in hardcopy & softcopy. Furnishing as built documents, drawings and CDs of the complete system as per tender requirements.

v. Supply of loose mandatory spares. vi. Supply of hardware / software necessary for proper functioning of the system. vii. Performing all works required for designing, engineering, testing, supply,

installation interfacing with communication channels, IED’s, and instrumentation and electrical system etc,, commissioning, site testing, test run and putting into full commercial operation of the system complete in all respect.

viii. All cables between respective equipments, telecom cables, power supply & power distribution cables, earthing cables/strips etc covering the complete requirements of the tender. In addition to the supply of cables, glands and interconnection of cabling and accessories including cable routing. The activities of signal identification at site, cable laying, routing, cable termination, ferruling, glanding, dressing etc. are in vendor’s scope.

S. No.

Type of Cabling Location From To Scope of SCADA vendor

1. Serial Interface Cables (RS 232 / 485)

New RTU locations

New RTUs IEDs (FC/ EVC, PLC, GC, etc. at Remote locations.

Complete interfacing requirements including supply of cables with connectors, at PLC end, modem end, and RS 232 / 485, intrinsically safe box (ISB) ends.

2. Power Cables MCC, SMCC, CCCs, New RTU locations

Power Distribution Cabinet

SCADA subsystems or components

Supply of cable including glanding, termination, ferruling, dressing etc. at RTU / SCADA system ends.

3. Telecom Interface Cable

MCC, SMCC & CCCs

Telecom equipment rack

Routers at MCC, SMCC, CCCs

Supply, laying, routing, glanding, termination at both ends (G.703 interface)

Note: a) Distance between Telecom Panel and SCADA equipment at MCC, SMCC & CCC

shall be firmed up during detail engineering b) Distance between IEDs and RTU Panel to be considered as 15 meters. However,

these distances shall be firmed up during detail engineering.

Page 44 of 175

Page 46: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 35 of 95

ix. Minor Civil Works. For MCC, SMCC, CCC and RTU locations, civil work shall consist of: a) Civil work required for interconnecting cabling at control rooms between various systems & equipments with telecommunication system and the power supply unit along with cable routing and dressing.

b) Associated grouting and fixing of equipment. c) Providing and laying perforated trays etc. for point a) above. d) Any masonry work associated with entry and ingress of equipment inside the control rooms including making goods and finishing such masonry work

e) All civil works including mounting, grouting, erection etc. of RTU panels at remote site.

13.0 DESIGN / SYSTEM GUIDELINES: 13.1 DESIGN GUIDELINES:

i. The system design shall be flexible enough to meet future expansion program up to the maximum capacity of each system and sub-system without deteriorating the performance of the system. SCADA System Software and Hardware to be designed in such a way that presently it will cater to the requirement of four cities, but should be configurable to add RTUs and CCCs of 30 more cities in next 5 years span.

ii. In general, specifications provided throughout this document shall apply. In case of conflict more stringent specifications shall override specifications given elsewhere and decision of the Owner/Engineer in all such cases shall be final.

iii. Equipments shall conform to the similar housing standards and shall preferably be integrated in one 19” or slim rack or ETSI rack.

iv. The optical and multiplexing equipment should be able to work continuously in non air-conditioned environment (guaranteed performance) under prevailing environmental conditions of the sites. v. All venting, cooling shall be natural.

vi. All equipments shall have sufficient number of alarms and supervisory indications and shall be provided with self-diagnostic facilities. All alarms and monitoring & diagnostic facilities shall be built-in & shall be displayed on the front panel of the equipments for ease of maintenance. It shall be possible to transmit these indications, parameters to the control stations.

vii. The equipments shall be fully based on solid-state technology. The system hardware shall be modular to have flexibility to meet any demand for expansion or modification with minimum changes.

Page 45 of 175

Page 47: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 36 of 95

viii. All equipments shall be immune to EMI; RFI interferences generated by any nearby

source & shall meet the latest international standards in this regard.

ix. The equipments shall be capable of functioning with minimum maintenance and shall be preferred to have no requirement of any preventive maintenance. x. All PCBs used shall be glass epoxy type and shall not chip owing to repeated soldering / de-soldering. The PCBs shall not warp on any account.

xi. All wiring-including field interconnection wiring shall be cabled and clamped to the chassis. The wiring shall follow standard color-code. All patch cords shall be provided with connectors matching to the cable used and shall have identification markings.

xii. All sub-assemblies or modules, switches and controls and the circuit components shall be so mounted as to permit their replacement without appreciable disturbance to other components.

xiii. If the vendor is not using distributed power supply system on individual module basis then the Power supply cards shall be duplicated (1+1). However, one standalone power supply card shall be able to run the system for its entire lifetime & there shall be sharing of load between the two power supply cards under normal conditions.

xiv. Racks for all the equipment of individual system, sub-system shall be provided from the reputed manufacturers only and they shall adhere to all the quality norms.

xv. The equipment construction should be such that it does not allow ingress or entry of rodents, insects, and dust. For this, equipment should be suitably sealed from all sides, top and bottom.

xvi. All the special tools and tackles, etc. shall be procured and supplied as a package with its carrying cases, accessories (interconnecting cables, connectors, lamps, batteries, fuses etc.) for their respective manufacturer.

xvii. Termination for all user interfaces shall be provided with 100% spares capacity.

xviii. All equipment racks, housings shall be provided with antistatic wristbands.

xix. The nodes (stations) should be hitless i.e. removing or inserting plug-in-units must not affect the existing traffic on other units.

xx. The configuration of the nodes should be easily expandable by adding plug-in-units and modifying software settings.

Page 46 of 175

Page 48: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 37 of 95

13.2 SYSTEM GUIDELINES: a) Vendor shall be totally responsible for the completion of the project. Owner/Engineer reserves the right to modify, revise, and alter the specifications of equipments and systems prior to acceptance of any offer. System requirements may be modified after selection of successful vendor to meet operational requirements not envisaged at the time of selection of Vendor.

b) Owner/Engineer reserves the right to modify the system requirements till such time the system is ready for final acceptance. Vendor shall undertake to meet the revised requirements without any financial implication to the Owner provided no additional equipments are required.

c) In case at the time of implementation there is any change in the network design & configuration to meet the owner’s operational requirements, the vendor shall undertake all the activities such as design, manufacture, supply, Installation, etc. of additional equipment hardware and software for which additional financial implication, if any, shall be approved by the owner on the basis of sufficient details and justifications being provided by the vendor.

d) If during the course of execution of the work any discrepancy or inconsistency, error or omission in any of the provisions of the contract is discovered, the same shall be referred to the Owner/Engineer who shall give his decision in the matter and issue instruction directing the manner in which the work is to be carried out. The decision of the Owner/Engineer shall be final and conclusive and the Vendor shall carry out the work in accordance thereof.

e) The vendor to give full documentary proof of satisfactory working of the Quoted system along with the bid.

14.0 SPECIFICATIONS

14.1 SYSTEM HARDWARE SPECIFICATIONS

Specification SCADA servers Web Server HMIs

Make COMPAQ / HP / SUN / IBM / DELL

COMPAQ / HP / IBM / DELL

COMPAQ / HP / IBM / DELL

Processor For Windows: Quad Core Intel Xeon 2.93 GHz (dual processor). For UNIX: 64 bits RISC based high performance processor (Min. 4)

Quad Core Intel Xeon 2.93 GHz

Quad Core Intel Xeon 2.93 GHz

Page 47 of 175

Page 49: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 38 of 95

L2 External CPU Cache

512 KB 512 KB 512 KB

Shared L3 cache

2 MB 2 MB 2 MB

RAM (ECC SDRAM / RDRAM)

8 GB 4 GB 4 GB

PCI Slots Min. 5 Min. 2 Min. 2

Hot pluggable bays

6 0 2

Hard disk controller

Dual channel ultra wide SAS

Dual channel ultra wide SAS

Dual channel ultra wide SAS

Hard Disk Drives

6 X 146 GB Ultra-320 Hot pluggable SAS, OEM Make

2 X 146 GB SAS 2 X 146 GB Ultra-320 Hot pluggable SAS, OEM Make

DVD+/- RW Drive with drivers

Double Layer SuperMulti (SATA)

Double Layer SuperMulti (SATA)

Double Layer SuperMulti (SATA)

Internal DAT DDS-4 (20/40 GB) DDS-4 (20/40 GB)

DDS-4 (20/40 GB)

Graphic sub system with driver s/w

PCI VGA with 32 MB RAM PCI VGA with 32 MB RAM

PCI VGA with 32 MB RAM

LCD color monitor

19” NA 21”

Network card with teaming facility

32 bit PCI Redundant ETHERNET Controller ( 100 / 1000 Mbps)

32 bit PCI Redundant ETHERNET Controller ( 100 / 1000 Mbps)

32 bit PCI Redundant ETHERNET Controller ( 100 / 1000 Mbps)

Mouse 2/3 button Infrared 2/3 button Infrared

2/3 button Infrared

Keyboard 104 Keys 104 Keys 104 Keys

Power supply Redundant hot pluggable Redundant hot pluggable

Redundant hot pluggable

Power fail protect and auto restart

Y Y Y

Fan Redundant Redundant Redundant

Serial port 2 2 2

Parallel port 1 1 1

USB port 4 4 4

OS software Windows 2008 (Enterprise Server) or latest / Solaris 10 or latest

Windows XP Professional or latest

Windows XP Professional or latest

Page 48 of 175

Page 50: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 39 of 95

Following manageability features for servers shall be provided:

• Pre failure warranty for Processor, Memory & HDD.

• Automatic Server Recovery.

• System Management Tool to monitor operation of the Server.

• Integrated Management Display.

• Server hardware configuration and intelligent software integration tool.

• Server Health Log Utility. Note:

The specifications mentioned is the basic minimum requirements. However, the SCADA vendor should upgrade / resize (on higher side) the specifications as per offered SCADA system to meet the functional requirements specified in the tender. At any stage of system implementation, it is found that the SCADA Servers, HMI workstations and remote workstations selected by the SCADA vendor are not having adequate processing power, main memory etc to meet the system performance requirements of this specification, SCADA vendor shall replace these with higher end machines with no cost and time implication.

14.2 Server Machine Specification

Server Processors The SCADA hardware shall be based on multiple-processor RISC servers running under UNIX or Windows operating system. The servers shall possess sufficient CPU processing power, memory and disk storage to carry out all the necessary functions, within the specified response times for data processing. Each server shall have a minimum number of parallel CPU’s. The minimum number of servers required is defined in the SCADA Datasheets. At least two are configured as a redundant pair for real-time database functions.

RAID Drives The SCADA Operating system and real-time database shall be stored on RAID 1 disk drive. Historical database shall be RDBMS based and historical data shall be stored in common external RAID based storage drive, shared between both Hot & standby SCADA servers. The system shall have the capability to store and archive all the historical data. The most recent data will be stored on external RAID storage and be available to operators and workstation users on demand. Long term data will be archived on removable media. The databases shall be configurable and expandable without software redesign by the Owner's programming personnel. Interface between the RAID array and the servers shall be SCSI or preferably Fiber Channel. Multiple dedicated RAID controllers shall be provided if required to maximize system throughput and minimize Read/Write delays. Disk drives that make up the RAID array shall be hot pluggable and replaceable on-line with no need to shut down the system or the RAID system. The system shall be capable of automatic recovery from a single disk drive failure.

Page 49 of 175

Page 51: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 40 of 95

Each disk array's total capacity shall be expandable. Making a change in the system configuration and adding more drives shall be possible without any requirement to physically shutdown of the disk array and restart the system. Minimum capacity of the data disk array i.e. useable data storage with the ability of expansion shall be as defined in the SCADA Datasheets. The Bidder shall verify disk systems sizing calculation and spare capacity requirements described in the SCADA Datasheets. Power supply of the disk array shall be redundant with either power supply capable of providing power for the entire disk system. Similarly, any fans or other types of system cooling shall also be redundant in design. The system shall be provided with a simple to use graphical user interface for configuration and management. This configuration and management function shall be accessible from any of the workstations on the SCADA network. " Memory Minimum high-speed RAM size shall be as defined in the SCADA Datasheets. The amount of RAM shall manage the database and provide the required performance. Memory shall be internally expandable to a minimum total capacity as defined in the SCADA Datasheets. Power Supplies Servers shall be equipped with dual redundant power supplies, each fed from a different power circuit and from different sources. Each power supply shall be capable of supplying the entire power requirement of the server. Layout The servers shall be designed to be easily serviceable. A rack-layout design with the computers standing on slide-out rails is preferred. Equipment Room The servers shall be located in an equipment room with other equipment such as RTU, communication equipment and mass storage devices such as the RAID disk array and CD/DVD disk drives. All SCADA equipment shall be mounted in cabinets. Pairs of redundant servers shall be located in separate cabinets.

14.3 Operator Station Machine Specification

Operator Workstation At the MCC & CCC (each), two operator workstations while at SMCC one operator workstation shall be provided.

Page 50 of 175

Page 52: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 41 of 95

Each workstation shall consist of one CPU box with the number of display screens per workstation as defined in the SCADA Datasheets. • Operator work stations provided for the SCADA system shall support the operator interface and RTU real time system functions and MMI interface functions when expanded to the ultimate size as per future requirement. • The databases shall be field configurable and expandable without software redesign by owner’s programming personnel. • Operator workstation shall be used to access the database of process information in the SCADA server that will be connected to both SCADA LANS and allow the user to interact with the information in the SCADA system. Individual network cards shall be installed to connect each LAN. Disk storage hardware • System storage shall be based on a multi ported RAID disk array. The disk array shall be accessible by each server. Interface between the RAID array and the servers shall be SCSI or preferably fiber channel. • Multiple dedicated RAID controllers shall be provided to maximize system throughput and minimize read/write delays. • The system software shall reside on a separate RAID 1 disk system. • Data archiving of historical data of the SCADA system shall be provided using CD ROM disk media using DVD based technology to provide a high capacity system that requires minimal and infrequent operation interaction.

Functions The Operator Workstations provided for the SCADA system shall support the Operator Interface and real-time and archival system functions for the SCADA system. Operator Workstations shall be used to access the process information database of the SCADA, Historian or in the RTU’s, when RTU is configured as OPC Server or as a Web Server. Each operator workstation shall be connected to both SCADA LAN’s and shall allow the user to interact with the information in the SCADA system. Individual network cards shall be installed to connect to each LAN. The Operator Workstation shall be the main interface for all SCADA system functions including: • Graphical displays showing the process conditions of the system. • Trends of selected process variables. • Alarm and Event management including alarm acknowledgement. • Commands and controls to change the operating state of the pipeline facilities such as opening or closing of valves. • Summaries and reports. • System maintenance and configuration changes. • Programming and system level access to the servers. • Intelligent Cause and Effect displays for the station logic with ‘what-if’ analysis. • Safe start up and shut down guide lines.

Page 51 of 175

Page 53: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 42 of 95

• Diagnostics of the system up to card level and Instrumentation including system-malfunction indications. • Tuning displays. • Sequencing guides. All displays and MMI functions shall reside on each workstation. Each workstation shall have its own display images updated when necessary over the network to achieve a fast display response time. Memory Minimum high-speed RAM size shall be as defined in the SCADA Datasheets. The amount of RAM shall manage the database and provide the required performance. Memory shall be internally expandable to a minimum total capacity as defined in the SCADA Datasheets. Displays Each operator workstation shall support video adapters with dual display ports with a single keyboard and pointing device. The minimum quantity of displays per workstation shall be as specified in the SCADA Datasheets. Each display shall be capable of displaying a minimum resolution as specified in The SCADA Datasheets. 21” LCD flat panel monitors shall be used.

14.4 Engineer Station Machine Specification

At the MCC and SMCC, one engineering workstation shall be provided at each location. The engineering workstation shall include multiple parallel CPU’s as defined in The SCADA Datasheets. Functions The engineering workstation shall have all the functionalities of the operator workstation plus as required for making database changes, creation and modification of graphics & reports, addition/deletion of remote workstations etc. The engineering workstation shall be equipped with all required software to carry out the above mentioned engineering activities independently. Once the changes have been carried out, it shall be possible to download these changes in the SCADA servers

Memory Minimum size of high speed RAM shall be as defined in The SCADA Datasheets. The amount of RAM shall be as required to manage database and MMI functions and provide the required performance. Memory shall be internally expandable to a minimum total capacity defined in The SCADA Datasheets. RAID The disk system shall be a standalone RAID 5 disk array for the database connected to this workstation. Disk system shall be sized to provide sufficient disk space to store all required program and data files while retaining a minimum of 100% spare unused capacity. As a minimum, the disk space shall be as defined in The SCADA Datasheets.

Page 52 of 175

Page 54: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 43 of 95

Backup The engineering workstation shall have backup software and hardware installed to allow automatic and manual backups as required of the complete system. It is preferred that the total system is backed up on to a single medium. If multiple backup media are required then a 'stacker" type hardware unit shall be supplied.

Engineering Facilities

The Operator Interface system shall include facilities for viewing all system data and displays, and for the creation and modification of the control system configuration, including the following: • Boolean or logic changes to calculations • Control algorithm configuration • Display building • Report generation • Log generation • Database changes • Configuration off-line or on-line • Alarm configuration • High level language programming • Communication and trouble shooting • Field I/O data • Server capability and redundancy • Hard disk configuration • Database structures and operating system • Configurable data retention time • ODBC connectivity The system shall allow the operator when selecting a field point on a display to view relevant data concerning the point. This shall include at least the tag name, current status, engineering value, instrument specifications, cause and effect details etc. The engineering facilities shall include a system for generating and maintaining full documentation of the control system including all control logic and operator interface configurations. The engineering facilities shall be available on any one-Operator station. All configuration data shall be saved to disk. The Bidder shall include details of the engineering facilities offered.

14.5 Large Video Screen Specification

Large screen display shall be connected to the either of the two HMI work stations through a switch. The screen will be suitable for 24 hrs 7 days a week for Master Control Room Mimic display in ambient conditions.

Page 53 of 175

Page 55: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 44 of 95

Make Sony / Samsung / Equiv.

Type LCD type

Quantity 1 Nos.

Viewable Area 60”

Image Quality Crystal Clear

Interface Analog

Mounting Wall Mounted

Supply Vendor to specify. Large Video Screen

specification

Connected with One of the operator station through Splitter cable

14.6 RTU SPECIFICATIONS

General Specifications a) The RTU shall be a powerful Intelligent Device specifically designed for the

Integrated Control System applications where, in addition to the traditional RTU functions, enhanced communication capabilities mixed with high performance control strategies are required.

b) The RTU shall be designed to monitor and control process instruments, CNG compressors, Gas Dispensers, Gas Metering Stations, etc. It shall process the analog data for high-low limit violations as per stored limit tables and communicate same to master station. Linear conversion to engineering units and input filtering (conversion of raw data to normalize value (e.g. to 0 to 10) for communication shall also be acceptable.

c) The RTU equipment shall function continuously without requiring any preventive

maintenance.

d) RTU shall comprise of following subsystem:

•••• Central processor with system software.

•••• Analog input module

•••• Digital input module

•••• Digital Output module

•••• Communication module

•••• Serial ports

•••• SMPL power supply

•••• Diagnostic tools.

e) RTU Communication:

•••• RTUs shall be IP based.

Page 54 of 175

Page 56: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 45 of 95

•••• Time-stamped Parameter values to be available from RTU to SCADA.

•••• The scheme employed should result in availability of all the Point / Parameter values in SCADA System at a time resolution of 1 second.

•••• It shall be possible to integrate the RTUs through serial & Ethernet port. Communication of RTU with serial port and Ethernet port shall be tested during FAT.

•••• It should be possible to integrate the RTUs to SCADA system through Fiber Optic communication system.

•••• The data transfer between RTU and Third Party Equipment like Flow Computers, PLCs etc should be based on Modicon Modbus RTU Standards / protocol where the values of Computed Flow & other parameters are made available to RTU.

•••• The RTU shall support both internal and external communication function.

•••• The communication network internal to the RTU shall be designed and implemented in such a way that the passing of data and commands between modules shall not be prevented by the failure of any module not directly involved in the communication exchange. In addition, the network shall not become overloaded under the heaviest traffic possible in RTUs ultimate expansion configuration.

•••• The master station shall initiate communication with a selected RTU by addressing function. Each RTU shall recognize its own unique address and shall have the capability of being assigned ant address within a range of possible address (256 minimum). LED indication shall be provided in the RTU to check the health of RTU communication.

•••• RTUs shall be multi-dropped on a pair of communication channels. Upon failure of primary channel, RTU shall respond to master station requests / interrogation on secondary channel automatically without loss of data & operation. System shall provide status on availability of each channel.

•••• The RTU shall support 100 Mbps redundant Ethernet communication speeds. The RTU shall be designed to build up hierarchical data transport networks on diversified transmission media, supporting multiple communication protocols.

•••• The RTU shall be equipped with asynchronous and synchronous serial communication channels that can be connected to wide range of different communication media, in single or redundant configuration.

1. 2/4 wires analog / digital dedicated communication lines, in point-to-point or multi-drop modes.

2. Dedicated RS – 232 / RS – 485. 3. LAN (Ethernet) interface. 4. Protocols supported by RTU shall be:

a. SCADA/RTU: i. DNP3

Page 55 of 175

Page 57: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 46 of 95

ii. IEC – 870-5-101 iii. TCP/IP

b. Field: MODICON MODBUS RTU Serial Link Requirements:

The interconnecting RS485 / RS232 cables and connectors for each of the RTU location and for each of the serial ports, with complete line drivers, software drivers & connectors at both ends and interfacing require in built for communication with owners PLC systems shall be included in the Vendor’s scope. Vendor shall develop, configure and establish the communication for retrieval of data from PLC systems, which support Modbus Protocol for serial link connectivity for all the RTUs in the CGD network. The RTU serial ports shall support different baud rates and it shall be possible to vary the baud rate of each port in order to optimize the communication.

(i) The serial link shall support transmission of all types of data and status bits including floating point, integer values and alarm arrays. The Owner shall furnish the make & model no. of PLC system. SCADA vendor shall assume full responsibility for obtaining the full protocol information, memory map, details of connectors etc. from the PLC based systems suppliers. Further necessary connectors (ensuring compatibility), interconnection, interfacing, engineering required for retrieval of the data from the PLC systems to make the link fully operational shall be in vendor’s scope. It is the SCADA vendor’s responsibility to coordinate with the suppliers of PLC systems as intimated and establish the communication for transfer of data & control with them to meet the complete functionality.

(ii) The RTU memory size shall be adequate for required numbers of

serial points as per RTU I/O Count & the number of serial ports for each RTU.

(iii) The PLC system data shall be scanned by the RTU much faster than

RTU poll time by MCC.

f) RTU Detailed Technical Features:

The RTU shall be a single microprocessor based modular electronic control device equipped with I/O terminals suitable for connecting directly to the field wiring of analog & digital devices. Galvanic isolated IS barriers will be incorporated wherever necessary in instrumentation panel. The following features shall be provided as a minimum:

• Each I/O shall be protected against the reverse polarity of the power voltage to I/O.

Page 56 of 175

Page 58: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 47 of 95

• Multiple (min. 4) RS – 232C & RS – 485 serial ports capable of each carrying a different Communication protocol.

• Act like a data concentrator for the local Intelligent Electronic Devices (IED).

• Minimum two Ethernet ports encapsulating TCP/IP network capability to IEEE 802.3 10/100 Base – T specifications.

• Communication management over redundant multiple links.

• Local data archiving & processing.

• Time synchronization via SCADA master with resolution of 100 msec.

• Time stamping to 1 second or better resolution for all digital, analog and pulse accumulator inputs & exception reports.

• Multi loop control, logic control and sequencing.

• Remote loading of configuration, parameters and application SW onto RTU flash memory (e.g. addition, deletion, modification and reassignment with different range, limits etc. from workstation to avoid local engineering at RTU level. The remote configuration w.r.t. following parameters for the points defined in RTU shall be done from master station:

o Analog alarm limits. o Analog scaling factor for engineering unit conversion o Threshold value. o Smoothing factor (filter time constant) o Directly handle standard I/O modules and perform intelligent process control functions for applications requiring highly accurate measurement of process variables, closed loops control, logic control and sequences, sophisticated algorithms, easy programmable through user friendly sequences configuration.

• Redundancy shall be achieved on the communication level.

• Fault detection and auto-diagnostics; both local and remote.

• Single 32-bit CPUs with minimum 166 MHz system clock. 32 M byte SDRAM (up to 64 M byte expansions piggyback).

• Low power consumption.

• Certified for industrial environments (according to CE).

• Field terminations incorporating scaling resistors test and isolation links.

• Removal and replacement of I/O modules and communication modules without powering down the RTU.

• Optical / galvanic isolation on all digital inputs. Digital bounce elimination circuits.

• Masking of selected inputs should be under the master’s control. It should have the feature of derivation of calculated Analog Point based on +, -, *, /, and square root. Calculation shall be performed

Page 57 of 175

Page 59: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 48 of 95

in RTU in engineering units with 16 bit floating point accuracy; required in case engineering conversion is being done at RTU level.

• Field inputs initiated discrete control action.

• Discrete control action corresponding to remote control command reception.

• Operator initiated discrete control action with check before execute and time out feature.

• Operator initiated discrete control with sequencing and interlocking.

• Derivation of counter values using integration of hardware and software generated analog points.

• RTU resident accumulator points driven by analog points.

• Flow computers, PLC, Dispenser, Odorizing Unit interfacing through RS 485 / RS 232 ports for serial data.

• RTU shall have should have the feature of Derivation of calculated digital point based on AND / OR / NOT etc.

• Integration of Hardware and Software generated points. These calculated Analog and Digital points is given same treatment as the acquired point for setting limits, generating alarms and reporting to SCADA master.

• Power failure and restoration should not result in Malfunctioning / Accidental activation of controls.

• Select – Check – Execute and Time-Out features of operator controls.

• SCAN disable / enable facilities for a selected single point, group of points under a defined process. Fast scanning of selected I/O points; it is expected that scan rate shall not exceed 100 msec. the scan rates for individual I/O modules shall be such that time-tagging resolution and system performance requirements are achieved. The consideration of scan time shall include the acquisition of data, processing and updating of RTU database. The overall RTU local scan shall be defined as the time required to acquire field data and update the RTU database and the same shall be much faster than RTU poll time by master station.

• Add / delete a RTU, event logger in online mode without disturbing the SCADA facilities.

• Should support various schemes for data transfer to SCADA systems such as Polling from Master SCADA system, RBE (Report by Exception), Request and Fast Update of some configured selected parameter. It should be possible to configure RTU so that only fast changing / critical parameters or only those parameters which have changed beyond dead band are transferred to master station to suit the limited bandwidth availability.

• Scan and acquire the data (single bit / two bit data) on continuous basis at 1 second or less, interval from the field instruments.

• RTU shall be capable of updating process parameters data and configuration data in its own built-in-memory. Time stamping of all

Page 58 of 175

Page 60: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 49 of 95

field values at RTU shall be required. In the event of failures or break of communication link, the RTU shall continue to scan all parameters and update its database. RTU shall retain its database till it is completely read by master station in order to take care of no loss of data on failure of master station. The RTU shall scan the field and the memory buffer is to be sized to store all the changing data (i.e. new exception report for the data every poll time) and master station receive the same without any loss of data and alarms in the SCADA system to care of channel, SCADA server switchover times.

• Further to take care of long term communication outages with master station the RTU shall be designed to also scan the field and store in the memory upto 1000 field exception reports during period of communication outage for retrieval by master station subsequently.

• The RTU system shall have the facility to attach to digital event signal a time tag generated by RTU local clock to enable the occurrence to be recorded and transferred with the resolution of 100 msec.

• It shall be possible to have highest priority of alarms, in order for the same to be sent to master station.

• Every control associated with RTU shall report the status of the point after control execution. In case the status has not changed within specified time it shall be reported to master station for not having executed the control.

• The RTU shall not generate any false control signal due to power supply on-off condition.

• It shall have feature of connecting pluggable Programming Diagnostic Test unit (PDT) / Local Craft Terminal (LCT) with keyboard & monitors diagnostic and programmable aid to troubleshoot and configure tool for RTU and I/O modules. It shall be possible to exercise all the functions of RTU without disconnecting the RTU from process. Vendor shall supply the programming diagnostic test unit loaded with all the softwares for programming / configuration of RTUs along with all accessories i.e. keyboard, monitor, cables, connectors, power supply unit, charger etc. with proper enclosure and shall operate on integral battery, which shall be rechargeable type. The battery shall be able to supply power as a minimum for 8 hours before requiring recharge action. Also, PDT shall operate on 230V AC power supply.

g) RTU Configuration: The RTUs provided shall be self-contained units capable of collecting data from dry contacts, current or voltage signals and contact-making pulsing devices.

Page 59 of 175

Page 61: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 50 of 95

All RTUs shall include the following features:

• The RTU configurator shall support latest Windows OS.

• Auto configuration on ‘Power up’, not requiring any external RTU configurator.

• No false outputs shall occur during power up or power down.

• A minimum of 256 unique I/O addresses.

• Selection of interlock to prohibit more than one control selection at a time at the RTU.

• No single component logic failure shall result in a false output operation. The failure of the first component, which in conjunction with a second component failure could cause a false command, shall be detectable in the course of normal RTU operation.

• Remote downloading of configuration, parameter changes and application SW onto RTU memory from the Master and the sub-master. While downloading configuration remotely, the configuration can be made online only when all the configuration has been received successfully by the RTU. In no case it should replace the online configuration in between remote downloading.

• Remote diagnostic capability from the Master and the sub-master.

• The RTU shall have self diagnostic feature and software watchdog timer devices to monitor & report the healthiness of CPU, memory, power supply, communication interfaces and I/O modules at the local level. Further RTU shall support remote diagnostics from master station and displayed in RTU status graphic.

• The analog input card shall generate an event, if it is out of calibration, which shall be sent to master station. Further if analog output card is not self-calibrating type then all analog outputs shall be wired back as analog inputs and calculations performed on each channel to detect AO card out of calibration. This out of calibration shall be available as part of RTU status graphic along with set point value displayed in the graphic, next to the corresponding controller symbol.

• The bidder shall supply all required support equipment for future reprogramming of the RTU by the Owner.

The following are preferred methods of programming tools:

• Program loader; handheld, capable of minor modification to software, plus Software packages for programming of the RTU on a compatible laptop / notepad PC.

• The final application programs shall reside on EPROM or a similar component. It should be possible:

o Enter program titles, comments and I/O lists. o Produce documentation, including cross reference lists. o Modify the program off-line, whilst the system is on-line. The changes made must be saved permanently and not lost when the RTU does a reboot.

Page 60 of 175

Page 62: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 51 of 95

o Modify the program on-line, whilst the system is on-line. The changes made to be stored permanently and not lost when the RTU does a reboot.

o Store input values as discrete identities in an event of loss of communication and to be transferred to the master when normalcy is restored.

• RTU shall be fully wired till terminal board for additional 25% over and above the configured I/O count estimated for each type of input (AI/DI/AO/DO/Serial) including supply and installation of necessary cards and other hardware. SCADA vendor shall detail the shelf and inter-shelf wiring and termination of the wiring harness between the RTU, the terminal block area and the field instrumentation. Easy access to cabinet wiring, for maintenance purposes is essential. The RTU components shall be designed for high temperature rating and low power consumptions so that air exchange with the ambient environment will not be required.

• The I/O point wires shall not be directly terminated on the RTU I/O boards. Terminal blocks / panels is to be provided in the RTU cabinet. Cross ferruling shall be done,

• Installation tools, tackles and accessories, cables, marker ferrules, lugs, cable ties, cable glands, gland hoods, conduits, tray etc. shall be provided by the vendor.

• The system shall be designed by selecting high grade components of proven quality and proper design of system electronics. Due consideration shall be given to the specified environmental and temperature conditions.

h) Programming Diagnostic Test Unit (PDT) / Local Craft Terminal (LCT): PDT / LCT shall have following minimum specifications:

• IBM/Sony/DELL / HP/ INTEL centrino core 2 Duo processor 2.93 GHz / 2MB Cache / 667 MHz fsb), 2 GB DDR2 SDRAM expandable to 4 GB, 160 GB SATA Hard Disk Drive, DVD-R/RW ( Dual layered Super DVD drive) 15.4” WXGA TFT Display 3X USB 2.0, Bluetooth, SD Media Slot Intel Graphics Media accelerator X 3100, Gigabit Ethernet, TPM, 56K Modem, battery, charger, carry case, installed with all programming / configuration / diagnostic / maintenance softwares. Also, CD media for all the loaded softwares (including OS and RTU programming / configuration tools) along with drivers to be supplied, PDT unit shall have serial port (RS232C DB-9 port). In case same is not available in PDT, then USB to RS232C convertor shall be supplied by vendor. Vendor shall also supply cable and convertor for RTU configuration using PDT.

• The RTU configuration software shall support latest Windows OS and licensed software of RTU, Windows OS and any other software needed for RTU programming to be provided by the vendor along with all the drivers.

Page 61 of 175

Page 63: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 52 of 95

• It shall be possible to off-scan RTU points.

• RTU shall be able to store the configuration data and the process database upon power failure for at least one month on continuous basis. Upon restoration of power, RTU shall resume the normal operation automatically.

• RTU shall operate from power supply level of 24V DC. Separate on/off power supply switch and fuse shall be supplied with each RTU. Vendor shall indicate power consumption for all RTUs. Adequate isolation of input, output and power supply circuits shall be provided along with over voltage and short circuit protection. Termination for connections of power supply should be of standard industrial type.

• Should work with any type of grounding (Negative, Positive or Floating as per the field requirement).

• Cut-off the power as and when the input power goes out of range (18 to 36V DC) and switch on automatically when input voltage returns to the normal range.

• Each enclosure will incorporate the specified RFI / EMI shielding control requirements by meeting latest standards of IEC-801, MIL, and VDE etc.

• RTUs at CGS and Online CNG stations shall communicate with MS over Optical Fiber Cable (OFC) while RTUs at Corridor CNG station and Daughter shall communicate over VSAT.

• The RTU shall be configured such that failure of any part of RTU subsystem (module) except the CPU, power supply module shall not directly affect the integrity of the unit as a whole.

• It shall be possible to output any AI (including serial data from IEDs) & DI point value available in real time data base at master station as AO (including serial data to IED) & DO to any RTU respectively. The relay contact configuration shall be provided upto the RTU terminal block. The DO command contact closure duration shall be configurable. It shall be possible to configure DO contact closure duration open or close for a long duration as per the DI status.

• Non-availability of any one of the two communication channels should not hamper the functioning of the other RTUs multi dropped on the pair of channels.

• Vendor to ensure that open / close status of valves (open state first wired and thereafter close state) be wired consecutively in the RTUs.

Page 62 of 175

Page 64: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 53 of 95

• At RTU, failure of a module in a subsystem shall be identified by an individual LED display.

• Each I/O shall be protected against reverse polarity of the power supply to I/O.

• All data shall be available in engineering units in the RTU Database.

• RTU scanning time of Input and Output points shall be as specified earlier. All Analog and Digital input points shall be time stamped to a time resolution as specified. The actual time stamp for each point shall be reported to the SCADA Master station when the RTU is polled. For digital points the time stamp shall occur when the change of state is first noted before the de-bounce timer starts. For analog and pulse accumulator points the time stamp shall be the time when the RTU analog point is polled.

• RTU shall be capable of interfacing both 4-20 mA and 0-5 V signals.

i) Enclosures Vendor shall supply the RTU and all associated hardware mounted inside a suitable enclosure as specified herein. The enclosures provided shall accommodate the full extent of the future expansion (sufficient power supply capacity, rack space, termination space, cabling space, bus slots, etc.) for the RTU as defined in the bid. The enclosure shall have proper lifting arrangements. Cabling, Fasteners, Fittings, Screw-heads, nuts and bolts shall be compliant with relevant International Standards.

All Enclosures and equipment within it should have identification to be finalized during detail engineering. The RTU shall be mounted in IP 52 carbon steel freestanding cabinets (frame minimum thickness shall be 1.6 mm) with lockable front and rear doors and bottom cable entry and with gaskets and fittings to keep out moisture, corrosive, salts, dust and gases. All doors drawers, trays, and other weight supporting parts shall be fabricated of metal adequately reinforced to limit vibration and ensure plane surfaces and shall be well-housed and tidy in appearance.

The cabinets [minimum 1100 mm height (1000 mm height + 100 mm base channel), 1000 mm width and 800 mm depth] self-standing type, with bottom entry for cable connections, fitted with concealed hinges with pull pins for door removal shall be provided for RTUs at all stations. This is approximate dimensions, vendor to size the cabinet after taking into account the ease of

Page 63 of 175

Page 65: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 54 of 95

operation and maintenance of RTUs. The dimensions will be finalized during detail engineering. A document pocket shall be provided in each cabinet for storage of documentation. The configuration of all enclosures, electronic chasis, modules and cabling shall permit ease of access to all serviceable equipment. Test equipment connections shall be adequately labeled and shall be readily accessible without the need to remove any board or portion of the equipment or power supply. All cabling, fastenings, fittings, screw heads, nuts and bolts shall be International Standard sizes suitable for prolonged use. The equipment and all modules therein shall be clearly labeled in English for ease of recognition without module removal.

Power cables shall enter the bottom of the cabinets via suitable termination assemblies and internal power distribution wiring shall be installed in separate conduits. Signal cables shall enter through the bottom of the cabinets via suitable termination assemblies. No opening other than cable entry points through glands shall be provided at bottom of cabinet. The exposed surfaces of equipment enclosures shall exhibit a uniform finish and appearance. The colour and finish texture of the equipment enclosure shall be subject to approval. All metal parts shall be treated to prevent corrosion. Painted surfaces shall be cleaned, primed and undercoated prior to painting to ensure a wear resistant finish. A preparatory powder coating process is preferred.

For adequate light inside the cabinet, a tube light shall be provided which shall operate on 24V DC. Exhaust fans shall be provided to remove heat and provide ventilation and these shall operate on 24V DC.

j) Insulation and Isolation Requirements

The RTU including all Status inputs, Control output, Analog inputs, Power supply inputs and Communications inputs/outputs shall meet the following insulation and isolation levels specified in IEC 255.

Insulation: The RTU shall be designed to withstand a Power withstand test voltage of 1.5 KV rms and shall conform to IEC 255-5 test standards.

Isolation: The RTU shall have an isolation resistance of more than 5 Mega ohms. It shall also pass an impulse withstand test of 5 kV and shall conform to IEC 255-4 test standards.

High Frequency Disturbance: The RTU shall be designed to pass a high frequency disturbance test to a 5 kV impulse test voltage and shall conform to IEC 255 test standards.

Page 64 of 175

Page 66: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 55 of 95

k) Labeling The vendor shall supply and install labels to identify all equipments in accordance with the equipment identification on the Drawings finalized during detail engineering. Each site cabinet shall have a site name label mounted on the door. All labels shall be manufactured from SS or similar material with black lettering engraved on a white background and secured using rivets. All engraved letters on labels shall be in block capitals, with black letters on white background. RTU card files, power distribution boards, terminations etc. complete in all respects properly correlating with drawings is to be ensured by the vendor.

l) Termination and Input / Output wiring

The vendor shall ensure clear and adequate segregation between terminals and cables in the following categories:

• Analog

• Digital

• Intrinsically Safe

• High Level (above 50 V)

Terminal protection is to be provided as required by statutory regulations. The RTU shall contain Terminal facilities for connection of field wiring the terminations shall provide a means of circuit isolation and test access without the need for disconnection of wires. Captive screw and saddle compression connections made from parts that are suitably treated to resist corrosion shall be used. The terminations shall be segregated according to signal type. Each terminal shall be clearly marked using a permanent marker to provide for its unique identification.

I/O board termination assemblies shall be of the plug-in variety using a suitable modular plug and socket arrangement. It shall be possible to remove and replace a faulty board without the need to individually unmake and remake each circuit connection. Ribbon cable connectors shall not be used at the I/O termination boards.

The equipment shall make extensive use of plug in modules. Input and Output modules shall be capable of being removed from or inserted into a fully powered and operational rack without risk of damage. Failure and subsequent replacement of an input or output module shall not effect other modules or cause a system failure. Modules shall be arranged so that they may be removed without unsoldering or unscrewing wires or breaking any other kind of permanent fastening. The hardware shall be modular in construction and replacements and adjustments can be made as far as possible with the system on-line. The bidder shall deploy means to ensure that the wrong cards cannot be put into card frame slots.

Page 65 of 175

Page 67: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 56 of 95

Sufficient space for termination shall be provided within the enclosure to support the maximum possible required capacity and future capacity as nominated elsewhere in the bid.

A single point earth shall be provided in the RTU in the form of a bolt compression type earth lug capable of accommodating a standard earthing cable. Wiring within the enclosure shall be protected from wear and tear, against accidental cuts, and from contact with enclosure parts or surfaces. The design, wiring and layout of the RTU enclosures shall be subject to review and approval. No more than two wires to be connected to one terminal and only wire to be connected to each side of the terminal block, except for terminal jumpers, provided they are crimped together by the same cable lug or wire pin.

m) I/O Connections The vendor shall include schematic diagrams showing proposed connection arrangements at the I/O modules for analog input signals, MODBUS / digital inputs voltage-free contacts and digital output circuits (both DO and AO). Module power supply and communication connections shall also be shown. Vendor to submit I/O list along with cable termination and parameter detail for each site during commissioning of RTUs.

n) Status Input Requirements

Visual indication by means of LED shall be provided for each input to indicate the condition of the input. A lit LED shall indicate that the external contact is closed. Each status input shall be isolated from high electrical noise and properly filtered for contact bounce such that contact transitions must last for a minimum of time to be specified before a change is reported. The time of the change is at the initial contact.

The bid shall describe the use of the digital inputs as pulse counting accumulators and detail the maximum contacts repeat rate, maximum number of counts before rollover of the counting register or buffer, and the process of reporting accumulator values to the station RTU. The RTU shall provide necessary voltage for the status input contacts.

o) Digital Input Module

• Ability to sense change of state of volt-free dry contact (min. 32 Volt-free contacts-2 wire isolated). The contact bounce suppressor and high noise immunity circuit shall be employed.

• Internal voltage shall source power to convert contact state of volt-free dry contact into logic level signals.

• Ability to register single momentary change od state (less than 5 msec.), until it has been read and reset by data processing system.

• At least 1.5kV RMS isolation between input lines and the system / circuit ground.

• All the inputs shall have galvanic isolation with opto-isolators.

• The card shall have loop & state LED for each input.

Page 66 of 175

Page 68: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 57 of 95

• Contact wetting shall be 2-4 mA per input at 24V DC.

• Resistance recognized shall be i) not exceeding 1 kilo ohms as a closed contact and ii) not less than 50 kilo ohms as an open contact.

• Insulation resistance 20 M ohms at 500V DC inputs.

• Mixing of NO / NC contacts shall be possible in the same card.

NOTE: Internal voltage of the system to be used for sensing plant dry contact (as said above) shall be isolated power w.r.t. the system input power. All the digital input parameters shall be NC (Normally Closed) type.

p) Digital Output Module

• Output type: Min. 12 relay contacts.

• LED indication for each DO point shall be provided.

• Miniature power relay shall be provided.

• 1 NO + 1 NC relay contacts configuration to be provided upto the RTU terminal block.

• Potential free contact rating of output interposing relay for each DO point (contact rating 48V DC, 2A; 230V AC, 5A).

• Isolation shall be 2kV RMS Contacts to logic.

• DO command activation shall be configurable pulse duration. The contact output subsystem shall provide momentary 2 sec closure of potential free contact relay output for operation of valves. It shall be possible to configure DO contact duration for a longer duration and all contacts shall be voltage-free. It shall not be possible for RTU to energies an output that has not been selected for control. An RTU start, following power failure shall not reset the output circuits, shall not generate false control signal and shall cancel any pending control selection.

• Output contacts shall be monitored via opto-isolators, shall be short circuit proof and protected by suitable mechanism like fuse with suitable fuse blown indication provided.

q) Analog to Digital Convertor

• Resolution 16 bits.

• Linearity + or – 1 LSB.

• Repeatability + or – 1 LSB.

• Accuracy + / - 0.2% of full scale over operating range

• Cross-talk better than 120 dB.

• Input shall be guarded two wire differential.

• Provision for a high accuracy reference voltage shall exist on the board and shall be used for checking the accuracy of conversion

r) Pulse Input Module

Suitable for accepting through switch select either of the following inputs:

Page 67 of 175

Page 69: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 58 of 95

• Voltage free dry contact relay operation (Max. 25 contact closures per second). Contact bounce shall be suppressed.

• Magnetic pick-up coil of 1500 ohms impedance and output voltage and frequency (up to 5 KHz) proportional to the flow rate. Voltage output varies from 250 mV to 25V. Suitable sensitivity and dynamic signal range shall be incorporated.

• Suitable galvanic isolation for inputs shall be provided.

• Counters shall accumulate pulses and transfer the same to microprocessor in a predetermined manner.

s) Analog Input Module

• Input type: Min. 16 isolated current inputs.

• Range: 4-20mA DC, 0-5V signals.

• Serial mode rejection: greater than 30dB at 50Hz.

• Common mode rejection: greater than 100dB at 50Hz.

• Roll over bit: 1 bit.

• Temp. coefficient: 0.005% per degree C.

• Accuracy: +/- 0.1% of range including drop in resistor.

t) Analog Output Module

• Output shall be 4 to 20 milli-amps DC source to drive upto 1k ohms load; Minimum 4 completely isolated current (4-20 mA) outputs.

• DAC type: 12 bit binary (exclusive of sign bit).

• DAC span: 10V or 5V.

• Isolation: each output shall be isolated from logic and others to 500 Volts.

• Differential linearity: ½ L.S.B.

• Temp. coefficient: 0.01% FSD per degree C.

• Retentivity: Set point value to be held by AO card till updated by the new set-point value from Master station.

• Output will be floating with isolation to Ground.

• Overall accuracy shall be better than +/- 0.1% of full scale.

• The output shall withstand indefinite open circuit.

• Output resolution shall be better than 0.5% over the range and the temperature linearity shall be better than 0.3%.

u) Power Supply Module

• Power supply available to vendor at one point at each site shall be 230V AC, 50 Hz.

• Vendor shall convert to suitable power supply source (redundant) as required for their system from above available supplies level.

• It shall be capable of converting 18 to 40V DC to required output voltages for various RTU modules.

• It shall support a load of at least 150 Watts.

• A provision of display and monitoring of input and output voltages with the help of onboard LEDs and test points respectively.

Page 68 of 175

Page 70: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 59 of 95

• It shall support any type of grounding.

v) Set Point Controls All analog output control functions shall utilize the select-check-operate control sequence associated with set point control.

w) Interlocking Logic

The means to minimize the risk of incorrect operation or incorrect sequence of operations can be included within RTU as a logical interlocking function.

x) Serial Link Requirements

Vendor shall develop, configure and establish the communication for retrieval of data from the flow computers / Compressor PLCs at CNG stations / Odorizing Units. Vendor shall be provided information on make, model no. and protocol details of these IEDs during detail engineering or prior to FAT. Vendor to simulate the above devices using protocol analyzers / PC / other means to demonstrate during FAT. Vendor shall provide all software tools and programs (source code) used to interface RTUs with Flow Computers / PLCs / IEDs. It shall be possible to integrate other IEDs with RTU in future; RTU shall have provision for achieving this.

14.7 HMI (Colour TFT Monitor, Keyboard & Mouse) Each colour monitor will comprise of TFT – LCD Monitor and protect facilities with controls of contrast, brightness and power. The display shall be flicker free. (i) For high resolution graphic display, the resolution shall be minimum 1280X1024

with SCADA software fully supporting this resolution. (ii) The monitor shall meet international requirements for agency compliance for

emissions (X ray, RFI/EMI), health & safety. The monitor shall meet antiglare standard, present improved viewing environment with flat profile, high contrast and provide easily accessible operating controls.

(iii) Monitor shall be connected to the system by a quick connect plug and socket connection for easy removal and replacement.

(iv) The keyboard shall be included for each workstation, PC, server and remote workstation.

(v) Mouse shall be included as curser control device for each workstation, PC, server and Remote Workstation for navigation & control.

The HMI shall, as a minimum, include the following functions:

• Display Requests

• Supervisory control

• Alarm and event message display

• Alarm message acknowledge

• Alarm inhibit, poll inhibit, point scan inhibit

• Report and log output request

Page 69 of 175

Page 71: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 60 of 95

• Monitor hard copy printout

• Monitor analog trending

• Bar graph display

• Manual data entry

• Assignment of console or workstation operating modes

• Display page definition and modification

• Report and log definition, modification and control

• Alarm and event message definition and modification

• Display and modification of system parameters

• Database management

• System configuration management

• Error statistics acquisition and management

• System resource utilization

• Daily alarms and operator actions

• System status display including all system nodes, RTUs, communication channel links etc.

• HMIs shall be Microsoft windows based.

14.8 LAN SWITCHES AND WAN ROUTERS LAN switches & WAN routers shall be provided at MCC, SMCC & CCCs; with number of ports suitable to meet future requirements of 5 years as explained in the tender. LAN

• Dual redundant switched network (with LAN switches in redundant configuration)

• The LAN shall meet IEEE 802 standards.

• Based on 100/1000 Mbps speed switched network.

• Flexible conduit shall be provided over all interconnecting cables from LAN switches to respective equipments to provide mechanical strength and rodent protection.

• The LAN switches make shall be equipped with 24 Nos. of ports.

• Jack panel (24 port), UTP cables, patch etc for LAN interconnection.

• CISCO / 3COM / IBM make

SCADA vendor shall supply all the interconnecting cables and conduits. WAN ROUTERS

a. The WAN routers shall be configured to provide communication paths and provide the facility adaptive packet and message routing through any available communication link. The WAN routers shall provide facility of multiple protocol router and bridge that provides high bandwidth connections into backbone networks for remote sites.

b. The hardware deign shall be based on distributed processing architecture with packets forwarding to be performed on the network interface modules. It shall be based on the modular design and architecture and shall allow new network

Page 70 of 175

Page 72: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 61 of 95

interface cards to be added in the racks without powering down the unit and ensuring no disruption of service to the network users.

c. The routers shall support both intra-area and inter-area routing for transporting messages between nodes and shall support the network routing / bridging services for OSI, TCP/IP, X.25, LAT and other industry standard wide area networks / protocols.

The routers shall be of CISCO make. WAN router shall support speed upto 2 Mbps. The WAN Router shall have G.703 WAN ports as per following:

Location No. of Routers

Min. No. of WAN ports in Router

Min. No. of LAN (Ethernet) ports in router

At MCC, SMCC, 1 16 2

CCC (Kota, Devas, Meerut & Sonepat) 4 2 2

The routers shall be configured for interconnectivity of SCADA equipments at MCC, SMCC and four CCCs.

14.9 WEB SERVER SYSTEM

(i) The Web Server System shall be provided in MCC to make the SCADA system web enabled, which shall support HTTP / XML for web clients. The users using Internet explorer browser shall access the web server at MCC. The web displays shall be simple to customize for corporate look & feel using web templates and style sheets. The web server shall be able to provide the other information irrespective of which SCADA server is primary at that instant. The supplied system shall have the following facilities implemented for the web client

:

• To view pre-selected / pre-configured MMI displays i.e. graphics with online updation and reports using Internet explorer browser through Internet. The number and format of displays shall be finalized during detailed engineering. The web clients can access these SCADA functions without additional configuration.

• Access to the SCADA data via web browsers shall be restricted to read only to prevent the possibility of unauthorized modifications.

• At a time, minimum 50 numbers of concurrent users shall be able to access the web server using internet explorer browser through internet.

(ii) The web server system shall provide the following functionalities: -

• Protecting against access & modifications by unauthorized users, prevent importation of viruses and providing the security features of address translation

• User authentication & login privileges, URL filtering, packet filtering, protocol filtering,

Page 71 of 175

Page 73: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 62 of 95

• Perform Stateful Inspection of connections

• Perform proxy operations on selected applications (http, SNMP, FTP etc)

• Intrusion detection & prevention

(iii) The web server system shall include the following: - • Firewall Router • Web security appliance • Web server

In order to meet the requirements of User Authentication, login privileges preventing access to unauthorized users & protect the system from network attacks, suite of software & hardware protection levels shall be built in as part of system architecture in a multi-layer concept. The firewall router providing the functionality of packet filtering & Stateful inspection along with web security appliance for content filtering, intrusion detection & prevention, anti spam, anti virus will fulfill this objective. (iv) The dedicated firewall WAN router shall be provided at MCC equipped with

necessary hardware! Software interfaces to provide connectivity to the Purchaser’s Internet link. Connections of the web server to the systems outside the SCADA system shall be performed through firewall environment. The firewall shall significantly reduce the processing load on the active SCADA server and the bandwidth requirements of the WAN topologies.

The firewall router shall be configured to function as the network device providing the only connection between the outside world and the SCADA System.

14.10 SCADA System Redundancy The SCADA system shall be completely redundant in design, built of dual redundant modules or subsystems, like servers, networks, workstations, communication equipment, printers and RTUs. Individual network cards shall be installed in these devices to connect to each LAN. Dual LAN network is planned and all servers, HMIs, Printers, Data Concentrators, Routers are dropped on both the LANs. Switchover between redundant equipment or sub-systems in case one of the current primary fails, shall be transparent and bump-less for both the process and the operators, apart from the event/alarm announcing the switchover. Switchovers can be initiated manually as well. The primary shall stay primary until a failure occurs or manually commanded to change over.

The system shall constantly check the statuses of both the primary and the secondary modules and indicate failures of either of them. The system shall indicate the current primary / backup / start-up / failed status of each component.

Page 72 of 175

Page 74: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 63 of 95

14.11 PRINTERS Network printers shall be provided at the MCC, SMCC and CCC. Mechanical dot matrix printers in sound-proof cases shall be supplied for alarm logging. The printers shall be connected to both SCADA LANs and shall include a self-contained printer server for standalone operation. The control system shall allow the reproduction of any display from a simple operator command without additional equipment. Colour laser jet printer and B/W Laser printer shall have LAN interface cards (1 0/1 00 Mbps) so that they can be connected to LAN.

B/W Laser jet printers B/W Laser jet printer shall have following specifications: Type of printer : Plain paper, transparencies, laser printing Graphic resolution : 1200 X 1200 dpi Text resolution : 1200 X 1200 dpi Printing speed : Typical 20 pages per minute Buffer size : 64MB upgradeable to 256 MB Electrical : 230 V AC ± 10%, Energy star compliant (Power save mode for

standby). Paper Size : A4 Paper eject capacity : Mi 600sheets Paper trays : 2 nos. Mounting : On Printer desk Noise level : Less than 56 dBA printing at 1 m distance Accessories : All Consumables till the end of Warranty for black cartridge

and cut sheet papers, to be included in scope of supply. Colour Laser Jet Printer Colour laser jet printer shall have following specifications: Type of printer : Plain paper, laser colour printing with built in colour and black cartridges. Graphic resolution : 600 X 600 dpi Text resolution : 600 X 600 dpi Printing speed : Typical 6 pages per minute Electrical : 230 V AC ± 10%, Energy star compliant (Power save mode for standby). Paper Size : A3 & A4 Paper eject capacity : Mm. 200 sheets Paper trays : 1 no. Buffer size : 64 MB upgradeable to 256MB

Page 73 of 175

Page 75: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 64 of 95

Mounting : On Printer desk Noise level : Less than 56 dBA printing at 1 m distance Accessories : Both colour & black cartridge to be built in. All

Consumables till the end of Warranty for color print cartridges and black cartridge and cut sheet papers to be included in scope of supply.

14.12 GPS TIME SERVER

GPS time server i.e. GPS clock along with Network Time Protocol shall be provided at MCC and SMCC to synchronize the clocks of workstations on the Dual LAN and to synchronize the RTUs time with MCC. The GPS configuration and set-up software shall be available in the system. The antenna, cables, lightening protection device, mounting accessories (cable length to be suitable for control room! building layout), converter, power supply unit (as applicable) need to be included.

14.13 DISK STORAGE HARDWARE

Data archiving of historical data of the SCADA system shall be provided using DVD-based technology that requires minimal and infrequent operator interaction.

14.14 NETWORK EQUIPMENT

All the equipment required for SCADA network viz. Switches, Routers, Firewalls, etc. shall be proven industrial grade from reputed suppliers.

14.15 CABINETS SCADA Vendor shall provide the following cabinets as a minimum: - a) SCADA Equipment cabinet(s) for mounting the Routers, GPS server, LAN switches, Fire wall router, Web security appliance and communication interfaces etc. at the MCC& SMCC rooms.

b) Power distribution cabinet at MCC, SMCC & CCC rooms. c) SCADA cabinet at CCC rooms for mounting Data Concentrator, Ethernet switches,

WAN Routers and power distribution arrangement. d) RTU cabinet at each of the RTU locations. Sub-distribution to all the power users within the System cabinets, workstations and printers will be by the Bidder. Each item within the panel requiring electrical power shall be fed from a fused mains isolator, with a MCB for each consumer. Sufficient isolation facilities on the DC sub-system shall be provided to enable maintenance of components with minimum disturbance to healthy devices.

Page 74 of 175

Page 76: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 65 of 95

The power distribution shall be sized to provide 20% spare feeders of each rating or one number minimum fully wired up to terminal blocks. In addition, 10% spare space for future additional requirement shall also be provided. All power supply units shall be monitored for faults by hardwiring into the System as digital inputs. The Bidder shall increase the input count as required to include these alarms. Power distribution to control devices shall be arranged such that the loss of an individual circuit does not result in complete loss of control capability or create unsafe operating conditions. System shall be capable of detecting failure of power to a loop, an open input circuit etc. All the 24V DC power supply units should be redundant with diode OR-ing and the maximum load (including installed spares) on each supply should not be more than 70% of the rating. It shall be possible to remove at least one power supply for maintenance without affecting the overall load requirements of the system. Panels shall be provided with easily accessible 110V AC and 240V AC utility outlets. Total number will depend on final panel layout. A single power supply feeder of 240V AC will be provided by Owner for the utility outlets.

14.16 DESKS / FURNITURE

SCADA vendor shall provide following aesthetically looking desks and chairs for the MCC, SMCC & CCC as per Control Center(s) Layout Drawing attached in the tender document. • MCC Console Desks for mounting of SCADA HMI workstations, SCADA Engineering cum HMI workstation, SCADA server HMIs, Printers & Executive chairs at Operator Room & Equipment Room. • SMCC Console Desks for mounting of SCADA HMI workstations, SCADA Engineering cum HMI workstation, SCADA server HMIs, Printers & Executive chairs at Operator Room & Equipment Room. • CCC Console Desks for mounting of SCADA HMI workstations, SCADA Data Concentrator HMI workstation, Printers & Executive chairs at Operator Room & Equipment Room. A. The desks shall provide work surface, lockable drawers, and internal power distribution for VDUs and internal fitting arrangements for system unit with all storage and peripheral devices, telephones / handset panels mounting provisions. B. Executive chairs shall be swivel based and selected with ergonomic consideration.

Page 75 of 175

Page 77: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 66 of 95

C. The control room equipment layouts and color, design & layout of the desks shall be selected with the following considerations for the respective room: - • Uniformity of the color • Operator viewing angle • Illumination requirement in operator area • Lighting arrangement • Color of the walls and floors to be suitable with color of the desks and consoles D Each desk shall be designed to be: -

o Fully equipped with all components and internal wiring necessary to ensure continuous and trouble free operation. o Suitable for continuous use, using quality furniture. o Complete with all fittings o Protect exposed surfaces subject to heavy wear. o Ensure that all surfaces are flush with no apparent overlap and treated to eliminate reflection and glare. o Ensure that no cables, connectors for power connections, LAN connections and system connectivity with peripheral devices shall be externally visible on the console desk. o Ensure that no holes, welds, screw heads, butt joints or cut edges are visible in the fully assembled console. o Allow space to accommodate communications panel & associated equipment. o Allow fast and convenient servicing of console mounted equipment with no disassembly of the console. o Install all cable connections by quick disconnect and secure plugs & sockets.

15.0 SCADA SYSTEM SIZING

SCADA System for Integrated SCADA data at MCC & SMCC shall have a minimum database sizing as follows:

Sl. No.

Point Type System capacity requirement

To be configured while execution

1 Analog Input 50000 6500

2 Digital Input 70000 8000

3 Analog Output 15000 1600

4 Digital Output 50000 6000

5 Host resident calculation points 50000 6500

6 Analog accumulator point 50000 6000

Page 76 of 175

Page 78: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 67 of 95

The SCADA system for Integrated SCADA data should have capacity for graphics, reports, as per following:

Sl. No.

Point Type System capacity requirement

To be configured while execution

1 Graphics 3000 100

2 Reports (Formats) 1500 100

3 Points for Historical Trends 3000 400

4 Points for Real Time Trends 5000 500

Notes:

i. SCADA vendor is required to incorporate the complete requirements of telemetered points for SCADA system taking the inputs from the I/O point list which shall be provided during detailed engineering.

ii. The requirements of direct I/O from IEDs, host resident calculated points, application points, which are to be built-in SCADA tags, are also to be considered by SCADA vendor as part of SCADA database.

16.0 SUPPLY AND STORAGE OF EQUIPMENT:

This shall include but not limited to supply and storage of equipment and all other items required for installation and commissioning of the network including the following: a) Transportation of equipment and all other components from locations of manufacturing to the locations of installation.

b) Storage during transit, transit insurance & storage/ warehousing as required till the readiness of owner’s sites.

c) Statutory clearances including clearances of customs, excise, octroi and others, as required for all the supplied items.

17.0 WARRANTY:

The system shall be guaranteed to give specified performance for a period of 24 months (two years) from the date of acceptance of the system by the owner. This warranty shall survive inspection of goods and acceptance of the system. Contractor’s engineer, capable of trouble shooting and looking after the health of the system during the guarantee period, shall be made available all through the warranty period of 24 (twenty four) months as & when required. Additionally the following shall also apply:

Page 77 of 175

Page 79: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 68 of 95

• During the warranty, the contractor shall use his own instrument, spares, man-hour, communication facilities, hardware, software, materials, etc. for the rectification of any problem.

• The “turnaround time” for the rectification of the problem shall not exceed 24 hours. (Turnaround time: From the time of placement of first service call to contractor’s representative until the system is restored fully to the satisfaction of the Owner.)

18.0 OTHER REQUIREMENTS: 18.1 SYSTEM AVAILABILITY REQUIREMENTS

i. The SCADA System Availability of 99.98% is to be ensured by the SCADA vendor.

ii. The SCADA vendor shall ensure that calculation of availability takes into account the MTTR of RTU as 8 hrs and MCC equipments as 2 hrs.

iii. Automatic switchover of redundant equipments! sub-systems (with failure annunciation) shall take place in order to maintain normal system operation. Removal of faulty equipments shall in all cases be possible without affecting normal system operation

18.2 ERROR DETECTION PROBABILITY

Error detection capability is required for achieving high order of reliability of data transmission. The telemetry system with error detection facility should confirm to IEC60870-5-104 / DNP 3.0 over Ethernet..

18.3 ENGINEERING REQUIREMENTS:

a) The equipment shall be fully solid state and adopt state of the art technology. b) The equipment shall be compact and in composite construction and light weight.

The actual dimensions and weight of the equipment shall be furnished by the manufacturer.

c) All connectors shall be reliable and of standard type to ensure failure free

operation over long periods and under specified environmental conditions. d) All connectors and the cable used shall be of low loss type and suitably shielded. e) The equipment shall be housed in standard 19” rack, or ETSI rack and with front

access. The equipment shall have natural cooling arrangement, use of forced cooling is allowed provided :

Page 78 of 175

Page 80: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 69 of 95

The fan failure is reported to LCT/CCC/MCC/SMCC. Multiple fans are there in one tray with hot standby redundancy. Fans are DC operated. MTBF for fan is better than 60,000 hours.

f) The plug-in units shall be suitable type to allow their removal/insertion while the

equipment is in energized condition. g) The mechanical design and construction of each card/unit shall be inherently

robust and rigid under all conditions of operation, adjustment, replacement and storage.

h) Each sub-assembly shall be clearly marked with schematic reference to show its

function, so that it is identifiable from the layout diagram in the handbook. i) Each terminal block and individual tags shall be numbered suitably with clear

identification code and shall correspond to the associated wiring drawings. j) All controls, switches, indicators etc. shall be clearly marked to show their circuit

diagrams and functions. 18.4 MAINTENANCE REQUIREMENTS:

Maintenance philosophy is to replace faulty units/subsystems after quick online analysis through monitoring sockets and alarm indications. The actual repair will be undertaken at centralized repair centers. The corrective measures at site shall involve replacement of faulty units/subsystems. The equipment shall have easy access for servicing and maintenance. Extension of degraded paths to test access points for diagnostic work after traffic is switched over to the healthy path should be provided. Suitable alarms shall be provided for identification of faults in the system and faulty units. Suitable potential free contacts should be provided for extension of summary alarms. As and when bugs found/determined in the software, the manufacturer will provide patches/firmware replacement if involved free of cost for three years. Modified documentation (hard copies and soft copies) wherever applicable shall also be supplied free of cost. Ratings and types of fuses used are to be indicated by the supplier

Page 79 of 175

Page 81: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 70 of 95

18.5 EQUIPMENT SAFETY AND PROTECTION REQUIREMENTS:

The equipment shall have a terminal for grounding the rack. Protection against short circuit/open circuit in the accessible points shall be provided. All switches/controls on front panel shall have suitable safeguards against accidental operations. The equipment shall be adequately safeguarded to prevent entry of dust, insects and lizards. SURGE PROTECTION, TRANSIENT SUPPRESSORS, RFI FILTERS Protection devices shall be provided in all the equipments to guard against the effects of lightning strikes and induced high voltages. Card level transient suppressors shall be provided wherever necessary.

18.6 OPTICAL SAFETY

All optical Interfaces must fulfill the latest version of ITU-T standards and recommendation including the following minimum requirements

a) Automatic laser shutdown (ALS) shall be implemented b) Optical connection ports and optical source devices shall be marked with

warning labels. A facility is required to prevent hazard to personnel due to the escape laser radiation from a ruptured cable or uncoupled connector.

18.7 JITTER

The output jitter, Input jitter tolerance at the Optical channels shall be as per ITU-T Rec. G. 825 and G. 958.

18.8 OPERATING PERSONNEL SAFETY REQUIREMENTS:

The operating personnel should be protected against shock hazards as per IS-8437 (1993) “Guide on the effects of current passing through the human body” (equivalent to IEC publication 479-1–1984).

18.9 ELECTROMAGNETIC COMPATIBILITY (EMC):

The equipment shall conform to the EMC requirements as per the following standards and limits indicated therein: Conducted and radiated emissions – To comply with class A [for low capacity (below 34 Mbps data rate)] of C ISPR 22 (1993) “Limits and methods of measurement of radio disturbance characteristics of information Technology Equipment”.

Page 80 of 175

Page 82: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 71 of 95

Electrostatic discharge – To comply with IEC 1000-4-2 “Testing and measurement techniques of Electrostatic discharge immunity test” under following test levels

Contact discharge level 2 (+ 4 KV) Air Discharge level 3 (+ 8 KV) Fast transients common mode burst – To comply with IEC 100-4-4 “Testing and measurement techniques of electrical fast transient/burst immunity test” under level 2 (1 KV for DC power lines: 1 KV for signal control lines) Immunity: IEC 1000-4-3 “Radiated RF electromagnetic field immunity test” under Test level 2 (Test field strength of 3 V/m). Surges Common and differential mode – To comply with IEC-4-6 “Immunity to conducted disturbances” indicated by radio frequency field”.

18.10 EARTHING SYSTEM:

Standard: IS 3043-1966 or equivalent BIS & IEC standard The earthing material to be used shall be Electrolytic Copper having the material specifications confirming to the IS standards The dimension of the Earthing strip, which shall be connected between Earth pit & the equipment or the earthing distributor, shall not be less than 25 mm x 5 mm. Earthing of all electronic equipments is required to reduce the effects of interference and personal safety of operation and maintenance personal. Each panel, cabinet and individual equipment shall be equipped with continuous lugs/strips. All these lugs/strips shall be properly secured to the AC mains earthing bus. Separate earthing shall be provided for system grounding and main frame grounding. Separate earth pits shall be provided for electrical and instrument at each station (MCC, SMCC & CCC) having maximum 1 ohm resistance.

18.11 VENDOR DATA REQUIREMENT AND DOCUMENTATION:

Six sets of documentation shall be supplied with each submission. During system definition / engineering stage, Owner/consultant shall review/approve drawings/documents to be mutually agreed with vendor. Prior to submitting the following documents for WGI / GGL review / records, the SCADA vendor shall review, duly sign & stamp all the documents and ensure compliance to the requirements of the contract.

Page 81 of 175

Page 83: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 72 of 95

With initial offer following documents shall be submitted: 1) System description 2) System configuration diagram 3) List of special tools and tackles 4) Power consumption details per unit per station 5) List of mandatory spares 6) Complete details of various items quoted along with description, catalogs, calculations etc.

In addition to hard copies, 2 sets of soft copies of initial technical offer shall be provided in CD-ROM’S for records only.

Language and Units All drawings, documents, information, correspondence, test reports, operating and maintenance instructions and like items shall be in the English language and SI Units. In the case of pamphlets and trade brochures, English translations neatly marked on the documents shall be deemed to have complied with this clause. Drawing and Information Schedule The Bidder shall supply a schedule of the drawings and information, which he expects to prepare or provide for use during the Contract. The schedule shall show the program for the preparation and submission of such drawings and information. The list shall be kept up to date during the contract period and shall not be amended or deviated from without prior approval of the Owner.

Approval of Drawings Drawings and information submitted by the Bidder will be reviewed by the Owner to assess compliance with the requirements of the Specification. The Owner shall retain drawings and information that is submitted to the Owner for review and a copy shall be returned to the Bidder within 5 working days of receipt. Approval by the Owner shall not relieve the Bidder of his responsibilities under the Contract.

Document Submittal Procedure

Drawings and other information submitted to the Owner for review, approval and/or information shall be forwarded under the cover of an approved Document Transmittal Form identifying the document, the purpose of the submittal, the Bidder's name contract/order number and the date of submission. When submitting documents, the Bidder shall use document numbers assigned by the Owner.

Document Media All documents and textual data other than drawings and Operating and Maintenance Manuals shall be submitted in duplicate and be clear, legible and readily reproduced onto A4 size white paper.

Page 82 of 175

Page 84: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 73 of 95

FUNCTIONAL DESIGN SPECIFICATIONS (FDS) SCADA vendor to note that the SCADA system tender completely covers the operational and functional requirements of the SCADA system for GAIL GAS Limited CGD networks. The requirements of SCADA FDS shall be to focus on the implementation aspects of these requirements.

FDS shall be custom defined for this project and include the implementation aspects of tender requirements in the following sections.

FDS shall cover SCADA implementation aspects [ Complete details of systems configuration, Redundancy and backup aspects (system failover & fall backs), alarms management & HMI philosophy, covering implementation aspects of tender requirements, Interfacing, Integration and communication aspects between various subsystems including with Telecom system, communication protocol interfacing with Flow Computers / EVC, PLCs, and other IEDs, description of SCADA / third party software interface, system timeouts, computers switchover timing etc.

Human Machine Interface (HMI) Document The HMI documents shall be generated for SCADA systems covering all the displays, graphics and reports, in colour printouts ensuring proper view-ability and legibility. The colouring scheme for various displays taking care of the colours for the titles / headings / sub-headings, background colour, static texts, dynamic values, CGD networks and other equipments etc. shall be highlighted in the dedicated sections of the HMI document.

SCADA Telemetry Points Database Document SCADA vendor is required to incorporate the complete requirements of telemetered points for SCADA system taking the inputs from I/O point database (I/O Point list) which shall be provided by WGI / GGL during detail engineering. The information like engineering units, ranges, alarm limits, set points, and digital contact configuration shall be taken care of by SCADA vendor during detail engineering.

All the calculated, server resident points and system status related points are also to be included in this document.

ENGINEERING DRAWINGS / DOCUMENTS Arrangement

Arrangement drawings shall include all information required to enable the Owner to design and detail works associated with the Contract Works and to be provided by the Bidder. Arrangement drawings shall show location and details of interface points. Working Drawings Working drawings shall include sufficient information to enable the Owner to determine if the Works can be installed, operated and maintained in accordance with the Contract. Manufacture or construction of any part of the system shall not commence without the Owner's approval of the general arrangement and details applicable to that part.

Page 83 of 175

Page 85: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 74 of 95

Where items of system are ‘site run’ the Bidder shall provide ‘as constructed’ information and/or drawings prior to Practical Completion of the Works. Flow Charts and Logic Diagrams

Flow charts and Logic diagram drawings shall be produced for all system and RTU functions. The Logic diagrams shall cover all sites and items of field equipment. The logic diagrams shall be generated for each site location and shall specifically include and individually reference each field device at these sites. The logic diagrams shall cover all programmed or hardwired logic used at each site and be directly referenced in the IEC 61131-3 programming documentation used to configure and program the field RTU’s. The Logic diagrams shall be grouped and referenced by site, sub-system and individual equipment referencing numbers and labels. Field Points, which are included in the logic diagrams, shall be referenced by their Tag, valve or code number. Detailed flow chart drawings shall be provided for all system and RTU functions at the detailed engineering stage of the project in accordance with the above document submittal procedures. The following major functions, shall have Logic Diagrams generated by the Bidder as a minimum: Any other functional logic sequences required for the monitoring and control of the stations. Each of these functions shall have logic diagrams generated and supplied by the Bidder for each location and instance these functions are implemented. There shall be individual Logic diagrams for each instance of each of the above functions with each diagram referencing the specific equipment at each location using the above mentioned equipment referencing conventions. Typical logic diagrams will be provided by Owner The logic diagram drawings provided by Vendor shall not be limited to these example diagrams but shall describe all functions supplied for the SCADA system. Logic Diagram Index

A Logic diagram Index in electronic and hardcopy form shall also be generated and supplied by the Bidder. The Index shall be supplied in a database format to allow electronic searches on each of the field entries of the index. The index shall have a reference entry for all supplied logic diagrams. The index shall also cross-reference each field instrument device, SCADA I/O point, RTU I/O point reference, field tag number, field marshalling cubicle and terminal block number. The Logic Diagrams and index shall be created for the purpose of mapping all functional logic to field and interconnected equipment references.

Page 84 of 175

Page 86: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 75 of 95

Equipment Configuration Settings All communication and SCADA equipment configuration settings for each commissioned item shall be documented and supplied by the Bidder to the Owner.

Ownership of Drawings

Drawings and transparencies supplied under the Contract shall become the absolute property of the Owner and may be used at his discretion for ordering spare and/or replacement parts in India or elsewhere or any other purpose he may require in relation to the facility for which they were provided.

SCADA DOCUMENTATION Operating and Maintenance Manuals

The Bidder shall supply comprehensive operating and maintenance manuals for all equipment provided under the Contract. The Owner attaches importance to the provision of proper operating and maintenance manuals and regard shall therefore be paid to the detail and completeness of such documents. All instructions shall be supplied in the form of manuals provided with strong covers, and shall incorporate a clearly indexed loose leaf system to permit the insertion of individual sheets as revisions become necessary. Operating and maintenance drawings shall include As-Built drawings. Selected drawings shall be bound into the manuals, reduced, so that they fit neatly into the manual format and shall be folded and bound so that they may be read when the manual is closed. Drawings shall generally be located at the back of each section, but may be located within the text provided that they are placed close to the related description. Where equipment is altered or modified, or there is difference between first and later units, appropriate revised instructions, diagrams and drawings shall be supplied for insertion in the appropriate sections of the manuals. The Operating and Maintenance Manual shall: • Contain sufficient detail to enable the Owner’s personnel to maintain all parts of the equipment in good running condition and carry out overhauls of the equipment from time to time

• Describe in full detail all the procedures for operating and interpreting the hardware and system software tests/diagnostics before and during operation

• State the Bidder's recommendations for preventive maintenance, including frequency of inspection and guidance in locating and rectifying faults

• Include Electrical Data sheets • Include Functional Diagrams • Include Logic Diagrams • Include Performance Test reports

Page 85 of 175

Page 87: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 76 of 95

The manuals shall include copies of all drawings referred to in the text, together with any other drawings necessary for a full understanding of the functioning, operation, testing and maintenance of the system, which shall include: • Component list for all items providing identification of each component by original manufacturer's part numbers.

• The manuals shall be as concise as possible and the written descriptions shall refer to drawings rather than repeat details shown on drawings.

• The manuals shall be specially prepared for the station as installed and shall apply specifically to such system.

The Bidder shall keep the final operating and maintenance instructions up to date throughout the defects liability period of the Works. Revision sheets shall be submitted for all copies of all instructions that may be necessary as a result of any modifications to the station or operating and maintenance procedures by the Bidder or Owner during this period.

Configuration Manuals Documentation shall be provided which describes fully all of the following: • The method of configuring both hardware and software; • The method of modifying existing configuration; • The method of testing and tuning a configured system; • The method of creating and modifying operator interface displays including graphics, trend displays, reports and data logs;

• The method for creating, modifying and scheduling of applications programs, including full details on the editor, compiler program and linker; and

• The ‘as commissioned’ configuration for each equipment item including communication and SCADA system equipment.

Documentation shall also be provided which includes a detailed description of all of the function blocks included in the system. Such documentation shall include a comprehensive technical description of the theory of operation of each function block including equations and diagrams together with all other necessary information to give a complete understanding of the functional facilities. The descriptions shall integrate both the hardware and software component parts of the respective functions. Manuals At least 10 days prior to the FAT, the proposed Operating and Maintenance Manuals and Final Drawings shall be submitted for review by the Owner.

Page 86 of 175

Page 88: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 77 of 95

As-Built Manuals The operating and maintenance manuals and drawings shall be updated with changes made to the equipment, configuration, parameters or operating procedures during the installation and commissioning. As-Built Operating and Maintenance Manuals shall be supplied prior to taking the Final Acceptance of the System.

In addition to hard copies, 2 sets of soft copies of initial technical offer shall be provided in CD-ROM’S for records only.

POWER CONSUMPTION and UTILITY REPORT (PUCR)

SCADA vendor shall furnish power consumption details with detailed break-up for each sub-system / equipments including inrush current and its duration during detailed engineering. This document will be submitted at the earliest so that required power availability can be ascertained by GAIL GAS LIMITED in time.

Quality assurance program, equipment & system test plans.

Expansion possibilities of the system without causing deterioration in the system performance.

Any other data, document not specifically mentioned but required for the satisfactory completion, operation, maintenance of the system shall be provided like Bill of Material, Installation & test procedure, Site execution plan.

Pre- FAT test results. Factory Acceptance Test (FAT) procedure. FAT document for SCADA system shall contain test sections to test all the aspects of SCADA System as covered in Purchase Requisition (PR), FDS and HMI documents.

Site Acceptance Test (SAT) procedure. System integration test procedure Trial Run /Performance Test Procedure.

STATION FOLDERS: In addition to above documents vendor shall provide 1 set of folder containing all information including maintenance details covered above, at each station. In addition to hard copies 4 sets of soft copies in CD-ROM form shall be provided for records.

Page 87 of 175

Page 89: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 78 of 95

18.12 TRAINING REQUIREMENTS

Vendor shall provide training for SCADA system of total 75 man-days. a) SCADA vendor shall train GGL’s total 3 engineers, in 2 batches, each for 15 days duration. The depth of the training shall be adequate enough to enable the GGL to (but not limited to):

• Operation & maintain system

• Add new RTUs and change media of communication between CCC and RTUs.

• Generation and modification of HMIs (graphics & reports) and Point database.

• Integration of new IEDs like PLCs and Flow Computers with the system.

• System internals

• Integration with third party software using OPC.

• Back ups and other jobs related to SCADA system house keeping.

• Loading of system software on new machine. b) SCADA vendor shall train GGL’s total 15 Operators (SCADA user’s) in 3 batches, each batch for 2 days.

The number of persons as well as man-weeks mentioned is the minimum number to be trained at the lab facility where the all the types of equipments supplied are simulated for practical training. The course shall be designed to train the trainees in all aspects of System Engineering, equipment operation and functional details, theory of operation of equipments, troubleshooting and familiarization with the equipments at card level, the operation of equipments and system including testing of equipments/sub-assembly, preventive breakdown, trouble shooting and normal maintenance activities. All equipment used for training shall be identical to those supplied for site installation. Vendor’s offer excludes costs of transportation, lodging and boarding of the trainees, which shall be arranged by the Owner. The number of personnel to be trained and the duration of the course shall be mutually agreed with successful Vendor. Vendor shall specify in his offer the types of courses he intends to impart, including but not limited to, the ones aforementioned. Vendor shall provide comprehensive documentation, course material, manuals, literature etc. as required for proper training of personnel at his own cost. Consolidated and comprehensive documentation shall be available to each participant. After the completion of course, all such materials shall become the property of the OWNER. Vendor shall update the course material & manuals in case there are any changes owing to revision/modifications in equipment/system specifications. Vendor shall, Forty five (45) days prior to start of training, send complete training program including details of each course, duration, subject matter etc. The Owner/engineer reserves the right to suggest any additions/deletions in the program which shall be incorporated by the Vendor at no additional cost.

Page 88 of 175

Page 90: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 79 of 95

General The Bidder shall provide a comprehensive training program for the Owner's engineering, maintenance and operations staff. The Bidder shall provide for approval, a training program that shall provide the required standard of operational expertise needed to operate and maintain the installation. The training shall be specific to the SCADA system installation, not general in nature and includes: • The provision of site lectures • Comprehensive explanatory and guidance notes • Visual and audio aids • Practical hands on training The material used to provide the training (slides, notes, etc) shall remain the property of the Owner following completion of the training courses. The personnel offered by the Bidder shall be suitably experienced and qualified and be sufficient in number to ensure that the Owner's staff are effectively and comprehensively trained. Operations Training Operations training shall be provided for operators at Noida MCC. Maintenance Training Maintenance training shall be provided for two engineers or technicians at Noida MCC Programming and Configuration Training System programming and configuration training shall be provided for two engineers. Training shall be provided at the Bidder's premises prior to dispatch of equipment to site, and shall include:

• System software installation, version upgrade and configuration • Logic configuration • Database design • Graphics and display configuration • Reporting • Applications programming • Trouble shooting and Maintenance

SCADA Training Owner personnel shall be trained in each aspects of the system required for day-to-day and emergency operations. Training courses shall be given for: • Operators, • Application and system programmers,

Page 89 of 175

Page 91: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 80 of 95

18.13 PACKING:

All equipments shall be individually packed in suitable containers/crates designed to avoid damage to the equipments during transit and storage in accordance with best commercial practice and with the requirements of applicable specifications. The material used for packaging, wrapping, sealing, moisture resistant barriers, corrosion preventers, etc. shall be of recognized brands and shall conform to best standards in the areas in which the articles are packed. The packing shall protect the equipment from impact, vibration, rough handling, rain, dust damp, insects, rodents etc. Each container/crate shall be subjected to impact, vibration and other mechanical tests. Each container shall be clearly marked with the following information at prominent places.

CLIENT : GAIL GAS LIMITED PROJECT : City Gas Distribution Projects. DESCRIPTION : : SERIAL NO. OF EQUIPMENTS : PO NO. : ADDRESS All equipment shall be tested for damage after their receipt at respective sites. If any equipment, part, subsystem, component, accessory is found to be damaged during the transit, the same shall be replaced by the Vendor, free of all costs to the Owner. The vendor shall replace such item as shall be indicated to him within 30 days of receipt of information.

19.0 TEST CATEGORIES, INSTALLATION, TESTING AND COMMISSIONING

a) The following tests (in the same sequence) shall be conducted for acceptance of the

equipments and the system before final acceptance of the system.

1. Pre-Factory Acceptance Testing 2. Factory Acceptance Testing (FAT) 3. Pre-commissioning test (after installation) for total integrated system. 4. Commissioning 5. Site Acceptance Testing (SAT) 6. Performance Testing / Trial Run

b) These tests shall be carried out on all equipments supplied by Vendor including those

supplied by sub-vendors, if any. c) Vendor shall arrange all necessary test instruments, manpower, power supply,

accessories etc during above testing activities.

Page 90 of 175

Page 92: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 81 of 95

d) All technical personnel assigned by Vendor shall be fully conversant with the system specifications and requirements. They shall have the specific capability to make the system operative quickly and efficiently and shall not interfere or be interfered by other concurrent testing, construction and commissioning activities in progress. They shall also have the capability to incorporate any minor modifications / suggestions put forward by Owner/Engineer.

e) The Vendor shall arrange power supply and any temporary commissioning facility

including communication system required for installation / testing / commissioning of the telecommunication equipments.

f) Test Plan:

Vendor shall submit to Owner and Engineer ‘Test Plans’ well in advance of commencement of actual testing in each of the above mentioned test categories.

The plans shall include:

1. System, Equipment functional and performance description (in short) and Tests to be conducted and purpose of test.

2. Test procedures (including time schedule for the tests) and identification of test inputs details and desired test results

g) Test Report : The observations and test results obtained during various tests conducted shall be

compiled and documented to produce Test Reports by Vendor. The Test Reports shall be given for each equipment/item and system as a whole. The report shall contain the following information to a minimum:

1. Test results 2. Comparison of test results and anticipated (as per specifications) test result as

given in test plans and reasons for deviations, if any. 3. The data furnished shall prove convincingly true.

h) The system meets the Guaranteed Performance objectives i) Mechanical and Electrical limits were not exceeded. j) Failure profile of the equipments during the tests are well within the specified limits

Failure of Components: Till the Owner accepts the system, a log of each and every failure of components shall be maintained. It shall give the date and time of failure, description of failed component, circuit, module, component description, effect of failure of component on the system/equipment, cause of failure, data and time of repair, mean time to repair etc. Detailed documentation for the same shall be submitted to Owner for future reference.

Page 91 of 175

Page 93: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 82 of 95

If the malfunctions and /or failures of a unit / module / sub-system / equipment repeat during the test, the test shall be terminated and Vendor shall replace the necessary component or module to correct the deficiency. Thereafter, the tests shall commence all over again from the start. If after the replacement, the equipment still fails to meet the specification, Vendor shall replace the equipment with a new one and tests shall begin all over again. If a unit/sub-system/module has failed during the test, the test shall be suspended and restarted all over again only after the Vendor has placed the Equipment back into acceptable operation. Owner’s approval shall be obtained for any allowable logistics time required to replace the failed component/unit/module/sub-system.

Readjustments No adjustments shall be made to any equipment during the acceptance tests. If satisfactory test results cannot be obtained unless readjustments are made, Vendor shall carry out only those readjustment needed to ready the equipment/system for continuance of tests. A log of all such adjustments shall be kept giving date and time, equipment, module, circuit, adjustments, reasons, test result before and after adjustment etc. Fresh acceptance tests shall be conducted after the readjustments have been completed.

19.1 PRE - FACTORY ACCEPTANCE TEST

General All equipment and components of the system shall be subject to inspection and testing both during and upon completion of manufacture and on site. Bidder shall include with his response full details of all type tests carried out on boards and modules, and tests normally carried out in their works including to what standards these are carried out. These tests shall preferably be in accordance with International or National Standards. Inspection During Manufacture The Owner reserves the right to inspect any part or the whole of the Works during or on completion of manufacture. Every facility shall be provided by the Bidder to enable the Owner or his nominated representative to carry out the necessary inspection of the system. No item shall be dispatched from the Bidder’s works without a release being issued by the Owner. The passing of such inspection or the waiving of inspection shall not prejudice the right of the Owner to reject the system if it is subsequently found that it does not comply with the Specification.

Page 92 of 175

Page 94: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 83 of 95

19.2 FACTORY ACCEPTANCE TEST (FAT) The Bidder shall prepare and submit to the Owner for approval a detailed system test schedule and procedures one weeks prior to the scheduled test. The testing shall include:

• Verifying the correct inventory of hardware, software and documentation. • Exercising and testing the computer, peripherals, communication equipment, and RTU’s.

• Demonstrating correct operation of all SCADA system functions including SCADA, RTU programs, HMI, applications, etc.

• Control operation of each control output shall be demonstrated with proper lights or other indications to confirm the operation for all control points.

• Create and handle typical error and device failure conditions including data link failure, RTU communication failure, telemetry failure, modem failure, etc.

• Demonstrate the correct operation of the SCADA communication and networking plan including alternate routing of traffic between networks and alternative path links, protection of the SCADA network by the firewall, address allocation strategies etc.

• All specified VDU displays and hardcopy reports must be shown to be implemented and verified for accuracy.

• Demonstration of performance of the RTU’s including: • Accuracy of measurement and control functions. • Proper operation of all input and output functions. • Proper link up with database. • Demonstration of the on-line interactive display builder, database editing, and report and log format generation.

• Load test to demonstrate overall system performance. See the Minimum FAT Requirements document for further requirements.

After the successful completion of all the above tests, a three day continuous run of the system shall be performed without loss of any function, without any hardware or software/firmware failure, during which time actual operation is simulated and all functions are exercised to determine possible weaknesses. Faulty and/or incorrect operation of major functions (major discrepancies) may, at the discretion of Owner, be cause for the dispersion or restarting of the entire test, pending the correction of the problem. Minor discrepancies noted shall be corrected and retested. The Owner reserves the right to request additional retesting of modules that it suspects may be impacted by corrections. The Bidder shall demonstrate at the Bidder's premises, to the satisfaction of the Owner, that the complete fully assembled system performs in the manner specified herein. The Bidder shall prepare a set of test procedures, which will be used for testing the SCADA system. Each inspection or test procedure / record shall be laid out clearly and include the following details: • The inspection or test name. • A Purpose section explaining the reason for the inspection or test.

Page 93 of 175

Page 95: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 84 of 95

• A Procedure section explaining step-by-step procedures to be followed and the responses / values to be expected at each step. Where a range of values can be obtained the range is to be identified.

• A space for recording the name of the test. • A space indicating inspection or test, pass or failure. • A space for the signature of the Owner’s Representative. • A space for any comments.

The Bidder shall provide input simulation and output monitoring equipment, together with any other necessary test equipment to permit all station input/output signals to be simulated / monitored simultaneous and the system functional requirements to be readily verified. The Bidder shall provide office facilities for the Owner during the FAT. Upon completion of the tests and before dispatch of the equipment from the works, the Bidder shall forward certified test results to the Owner for approval. The Owner may be present at all tests. The Bidder shall give one weeks notice, in writing, before such tests are carried out. For all testing in the Bidder's premises (including configuration testing) the Bidder shall provide: • All power supplies for the duration of testing • All test equipment and interconnections • All manpower required for testing

19.3 INSTALLATION:

After successful completion of factory acceptance testing, equipments shall be sent to site for installation. Equipments without factory acceptance certificates shall not be acceptable at site. Transportation, lifting, unloading, shifting and installation of any equipment required for the SCADA system is in Bidder's scope. The Bidder shall be responsible for the installation of all the remote RTU sites, Operator interface, cabinets, processors and communication equipment. Startup of all equipment supplied is part of the SCADA and Telecommunication system contract. The Bidder shall provide the necessary personnel and equipment to install the system. All the equipment, except monitors, printers and keyboards mounted on a control desk, shall be installed in cabinets. Prior to installation, all equipments shall be checked for completeness as per the specifications of equipment required for a particular station. Installation shall be carried out in accordance with the installation manuals and approved installation drawings in the best workmanship.

Page 94 of 175

Page 96: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 85 of 95

Vendor shall indicate the number of teams and the list of equipments for each teams to be deployed for installation of the total telecom system in order to complete the work within the stipulated time frame. Vendor shall bring all installation tools, accessories, special tools, spars parts etc. at his own cost as required for the successful completion of the job.

If during installation and commissioning any repairs are undertaken, the maintenance spares supplied with equipments shall not be used for the repair. Vendor shall arrange his own spare parts for such activities till the system has been finally accepted by the Owner. A detailed report & log of all such repairs shall be made available by the vendor to Owner/Engineer and shall include cause of faults and repair details, within 2 weeks of fault occurrence. A detailed time schedule for these activities shall be submitted by Vendor to Owner/Engineer to enable their representatives to be associated with the job. Vendor shall include all installation materials required for proper installation of the equipments. These shall include but not be limited to, all connectors, inter-bay and inter equipment cables, power supply cables and connectors, power distribution boxes, anchoring bolts, nuts, screws, washers, main distribution frames, audio distribution frames, voice frequency cables, junction boxes etc. The installation of equipments shall be done as to present neat and clean appearance in accordance with approved installation document drawings. All inter bay, power supply and other cables shall be routed through wall mounted cable trays. No cable shall be visible. All through wall openings, trenches etc. shall be properly sealed to prevent the entry of rodents, insects and foreign materials.

19.4 PRE-COMMISSIONING

On completion of installation of equipments, the correctness and completeness of the installation as per Manufacturer’s manual and approved installation documents shall be checked by the vendor on his own. A list of Pre-Commissioning tests (same as approved by the Owner/Engineer for site acceptance testing) and activities shall be prepared by vendor and the test shall be carried out by the vendor on his own. After the tests have been conducted to the Vendor’s own satisfaction, the vendor shall provide the test results for review by Owner/Engineer and then offer the system for Site Acceptance Testing.

During pre-commissioning, if any fault occurs to any equipment or system, vendor shall identify the same and provide report/history of all faults to the Owner. During installation and pre-commissioning of the SCADA system, vendor shall have enough number of commissioning spares so that the installation is not held up because of non-availability of commissioning spares. Vendor shall ensure that the spares meant for operation and maintenance are not used during installation and commissioning.

Page 95 of 175

Page 97: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 86 of 95

19.5 COMMISSIONING The Bidder shall do the commissioning of the overall system. The commissioning shall:

• Check all the field I/O connections to the RTU’s at the interface points. • Verify the remote RTU’s are communicating correctly with the SCADA Master station

• Check every I/O point from the field interface through to the MCC display, activate each set point and control to ensure the correct actions, alarms, and trend values occur.

• Verify all database points and displays developed • Verify the RTU is controlling the field equipment correctly • Verify all systems in the scope of supply.

19.6 SITE ACCEPTANCE TEST (SAT)

The Bidder shall carry out commissioning checks to ensure the SCADA system is performing satisfactorily before offering the SCADA system for Site Acceptance Test. Written evidence of satisfactory performance during the commissioning tests will be required before site acceptance tests may proceed. The available RTU’s shall be commissioned onto the system at this stage. A Site Acceptance Test (SAT) of all SCADA system functions similar to that for the FAT shall then be performed. The Bidder shall be responsible for writing the FAT and SAT test procedure manual, with suitable provision for sign-off of each section and/or comments on retesting, and submitting same to the Owner for approval prior to commencement of testing. Site Acceptance tests shall comprise an Operations test, during which no failure shall occur, followed by a long-term Performance Test. The dates for these tests will be determined by the Owner, and will be conducted with the SCADA system on-line and connected to the actual field devices.

19.7 OPERATION TEST

The Operations Test shall cover the entire SCADA system (including hardware and software) and shall be carried out over a period of 3 days during which time there shall not be a single component or program failure. During this period the system performance tests described in the Tender Document / specification shall be conducted. At the completion of the Operations Test the Owner will commence using the SCADA system operationally.

19.8 PERFORMANCE TEST / TRIAL RUN On successful completion of the Operations Test, the long-term Performance Test shall commence and shall continue for a period of 30 days. The SCADA system shall be deemed to have passed the performance test if all the following conditions have been met during the test: • There is no unexplained software or component failure.

Page 96 of 175

Page 98: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 87 of 95

• There is no unexplained system shutdown or failures that occur more than once in a given item of equipment. • There are no known uncorrected hardware or software problems or deficiencies. Failure to pass the tests will result in the Bidder rectifying the faults at his expense and a new series of tests being scheduled. All tests shall be carried out to the satisfaction of the Owner and all system failures shall be fully documented showing the cause and corrective action taken. Four copies of all test results shall be provided to the Owner for review. During the course of the performance test the Bidder shall have available qualified personnel ready to correct any malfunction or carry out any modification necessary to either the hardware equipment or software programs. Each time a fault occurs the Bidder’s representative shall remain on site until the trouble is corrected and the Owner has verified proper operation of the system.

During trial run, if any fault occurs to any equipment of system, vendor shall identity and rectify the same and provide report, history of all faults to the Owner. Ideally, using the ‘Trial run, no shutdown of the system due to failure of equipment, power supply etc. should happen. A record of all failures shall be kept for each manned/unmanned station and the availability of the system on per hop and end to end basis shall be calculated, accordingly and results submitted to Owner/engineer/Consultant. If the system fails to come up to the guaranteed performance, the Vendor, within a period of thirty (30) days shall take any and all corrective measures and resubmit the system for another ‘Trial Run’. All modifications, changes, corrective measures, labour etc. shall be at the cost of the Vendor. In case the date of completion for the second trial run exceeds the time schedule for the project, he shall be liable to pay liquidated damages. If the system fails to reach the guaranteed performance even after the second trial run, the Owner shall be free to take any action as he deems fit against the Vendor and to bring the system to the guaranteed performance with the help of third party at the expense of the vendor

19.9 SYSTEM SUPPORT The Bidder shall specify any special requirements needed to fully support the complete commissioning of the system. The software shall be fully covered by an agreed warranty. Any software defects, malfunctions or problems experienced by Owner during the warranty period shall be repaired free of additional charges.

20.0 SPARES PHILOSOPHY

Bidder shall attach a list a list of 2 years operation & maintenance spares alongwith the unit rates on respective vendors / sub-vendors letterheads which would be necessary

Page 97 of 175

Page 99: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 88 of 95

for 2 years trouble free operation and maintenance of the system. The owner shall be free to select the items of spares and the quantity at the time of awards of contract or during the execution of the project before completion of warranty. Vendor shall provide the address, contact person, fax and telephone numbers of the manufacturer of the spare parts. The vendor shall warrant that spare part for the system would be available for minimum of 10 years after warranty period after system commissioning (owner’s taking over). After this period if the vendor discontinues the production of the spare parts, then he shall give atleast 12 months notice prior to such discontinuation so that Owner may order the requirements of spares in one lot.

In the bid, the vendor shall provide unit price of each Spare module / card, which shall be valid for the procurement of the spares for operation and maintenance in subsequent years.

20.1 MANDATORY SPARES

10 % mandatory spares shall be provided for all electronic cards, etc. (with round off at higher side with 2 cards minimum in case of total 3 cards or more. In case of 1 or 2 cards, only one spare card shall be provided). These spare shall be supplied by the bidder alongwith the respective equipment. Equipped spare cards/interfaces offered SCADA equipment shall be taken into accounting and considering during calculation of mandatory spares. The above spares are not applicable for motherboard and laptops. 100% spares shall be provided for consumables e.g. fuses, lamps, plugs, clamps etc. Mandatory spares shall be calculated individually for each site/city. List of mandatory spares shall be provided along with the offer. Spares shall be provided from the same manufacturing facility/location from where the respective equipment, sub-system are offered.

20.2 COMMISSIONING SPARES The commissioning spares shall be arranged by the vendor to cater to the needs / requirement during installation, commissioning, site acceptance testing, trial run and warranty period. These spares shall be readily available with the vendor. These commissioning spares are different from Mandatory Spares and vendor shall not use mandatory spares as commissioning spares. Vendor shall provide a list of commissioning spares (with Serial & Part number for each system, sub-system) with the bid. Vendor has to return to M/S Gail Gas Limited the leftover commissioning spares in working condition after commissioning.

Page 98 of 175

Page 100: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 89 of 95

21.0 QA / QC REQUIREMENTS The Bidder shall operate a Quality System meeting the requirements of the relevant part of ISO 9002. Bidder shall provide documents such as plans, procedures, instructions, etc. for the accomplishment of all works covered in this specification to provide the required quality. Specific adherence to the guidelines set down in ISO 9002 series documentation shall be detailed out by the bidder and shall be subject to review and approval by the Company. Vendor shall submit the quality management system meeting the requirements of ISO 9001 – 2000 which he proposes to operate while executing the job. The system documents shall cover Quality Plan for this job, procedures, work instructions, inspection and test plans (ITP) and test results reporting format to provide an approach for achieving the required quality job. The quality system shall be reviewed and approved by the company. Owner reserves the right to undertake such audit as deemed necessary to assess the effectiveness of the Bidder’s quality system.

22.0 INPUT / OUTPUT DETAILS 22.1 RTU I/0

Sl. No.

Location Analog Input (AI)

Analog Output(AO)

Digital Input(DI)

Digital Output(DO)

Serial Ports

1. CGS Note 1 Note 1 Note 1 Note 1 12 Nos. ( 6 each RS 232 & RS 485)

2. Online CNG Stn.

Note 1 Note 1 6, Note 1

Note 1 24 Nos. (12 each RS 232 & RS 485)

3. Daughter CNG Stn.

Note 1 Note 1 Note 1 Note 1 18 Nos. (9 each RS 232 & RS 485)

NOTES:

1. Minimum one number of AI card, AO card, DI card and DO card (each) shall be supplied with each RTU.

2. I/O details of one CNG Compressor (Kirloskar) PLC (Siemens) is attached, tags in SCADA will be distinguished by ‘prefix code’ of the compressor location.

3. I/O details of one CNG Dispenser (Tulsa) PLC is attached in the tender, tags in SCADA will be distinguished by ‘prefix code’ of the dispenser location.

4. I/O details of Odorizing Unit at CGS PLC will be provided to vendor during detail engineering.

5. I/O points of UPS at MCC, SMCC & CCC shall also be considered by SCADA Vendor.

Page 99 of 175

Page 101: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 90 of 95

22.2 NUMBER OF FACILITIES / STATIONS:

S. No.

DESCRIPTION KOTA SONEPAT MEERUT DEWAS TOTAL

1. No. City Gate Station (CGS)

2 1 1 1 5

2. No. Online CNG Station

4 4 5 2 15

3. No. Daughter CNG Station

1 0 1 0 2

4. No. MRS 6 FC + 15EVC

5 FC + 15 EVC

5 FC + 15 EVC

5 FC + 20 EVC

21 FC + 65 EVC

FC: Flow Computer EVC: Electronic Volume Corrector

22.3 NUMBER OF RTU & GPRS:

NOTE:

1. Detailed information of FC & EVC existing GSM card will be provided to vendor during detail engineering. Vendor shall procure GPRS connectivity in the name of GGL.

S. No.

DESCRIPTION KOTA SONEPAT MEERUT DEWAS SPARE TOTAL

1. No. RTU - City Gate Station (CGS)

2 1 1 1 1 6

2. No. RTU - Online CNG Station

4 4 5 2 3 18

3. No. RTU - Daughter CNG Station

1 0 1 0 1 3

4. No. GPRS for MRS (FC / EVC)

21 20 20 25 0 86

5. No of consumers to be polled through GPRS

28 25 27 28 ------ 108

Page 100 of 175

Page 102: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 91 of 95

23.0 POST WARRANTY ONSITE MAINTENANCE SUPPORT

Vendor shall provide onsite maintenance support to owner for SCADA system maintenance for five years on annual contract basis.

a) The bidder shall include proposal at the time of bid for providing post warranty maintenance for 5 years after completion of warranty period and provide the total i.e. comprehensive maintenance of the SCADA system and any other system / sub system which is part of this tender.

b) The proposal shall include supply of maintenance spares, tools and tackle as required; travel, boarding & lodging of service engineer. The bid shall be made year wise upto 5 years and the price validity shall be available for the entire period of contract.

c) In the event of any malfunction of the system hardware / system software, experienced service engineer shall be made available at site within 24 hours on the receipt of such information from owner.

d) Owner personnel will work on system day to day basis and wherever possible, owner shall inform the type of failure of hardware / software to vendor based on diagnostic available with the system. However vendor shall be fully responsible to attend and rectify the root cause and failure at the shortest possible time.

e) Vendor may utilize the spare modules available with owner if necessary and available with owner at site, which are part of mandatory spares supplied with system as per this tender. However if vendor desires, additional spares other than what is available as mandatory spares may be stored at client premises to meet the schedule of rectification of fault during emergency / maintenance.

In case any hardware / software used from owner stock, it shall be replaced by vendor within 7 days with no cost to owner. Vendor shall maintain a record of all faults during post warranty period.

f) The service under Post Warranty Maintenance Agreement, including supply of spare parts and services, shall broadly comprise of:

• Preventive Maintenance

• Periodic Maintenance

• Emergency Service

• Software Support

Preventive Maintenance Once in a year during planning shutdown, client will inform the vendor one month in advance for shutdown dates. Preventive maintenance shall involve complete overhaul of the system, inspection of hardware and software, fault prediction, inspection of power supply quality, environmental operating condition checks, calibration checks, major

Page 101 of 175

Page 103: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 92 of 95

repairs / replacement of cards and accessories because of expected ageing failure and detailed reporting, manual cleaning of each card and cabinet filters. This visit is in addition to visit required for periodic maintenance. Periodic Maintenance

Site visits, minimum two times in a year for total expected days ten in a year; schedule of visit to be discussed and finalized jointly between vendor and owner after placement of order / delivery. It shall include inspection of general healthiness of the system, study and advice on daily maintenance, inspection of hardware & software, if any problem is reported, running of test programs, on-line servicing and solving reported problems. Checks shall be conducted on running system i.e. (i) On-line sub-system (ii) Power supply checks (iii) TFT (iv) Printer etc.

Cleaning of cabinet filters, minor modification / addition related to system configuration / data base. Vendor shall also take backup in 2 copies of the last updated software.

Emergency Service In the event of any malfunction of the SCADA system hardware / system software during this period, Service Engineer must report at site within 24 hours of report of failure, with necessary spares. The system must be brought back within 24 hours after reporting at site.

Notes:

1. Vendor to note that while carrying out the Post Warranty Maintenance Contract activities, Gail Gas engineers shall be associated. On-job training of these associated engineers shall be covered under the scope.

2. This shall include all items being supplied by vendor, including ant bought out items

but not limited to the following:

(i) Labor and materials, at no additional cost, to repair any system devices including RTU, servers, HMIs and related equipment, network devices, printers etc.

(ii) Labor and material, at no additional cost, to provide tests and adjustment to

system devices including printers. (iii) Regular checkups to ensure that a correct procedure is established for data

base backup and archiving. Software Maintenance / Support

Vendor to maintain the existing operation & application software to improve upon performance of the system. Software modification and upgradation, as & when required, shall also be covered under this scope at no extra cost.

Page 102 of 175

Page 104: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 93 of 95

24.0 PROJECT EXECUTION 24.1 PROJECT PROGRAM REQUIREMENTS

I) The time for completion of all the works under this project including supply & delivery

of equipments and systems at all specified stations, installation & commissioning of SCADA system and handing over to the company on turnkey basis shall be within the time schedule specified in the commercial section. II) The SCADA vendor shall submit a bar chart showing vendors program for delivery, installation & commissioning meeting the following requirements along with his offer. The same shall be reviewed after award of contract. III) The SCADA vendor shall, within 30 days after receipt of notification of an award of Contract, provide the WGI / GGL with the detailed PERT/CPM diagram for approval by the WGI / GGL After the work is started an updated PERT/CPM diagram shall be supplied every month showing changes in scheduling which reflects the project status at the end of the previous month. The PERT/CPM diagram shall cover but is not limited to: 1. PROJECT EXECUTION ACTIVITIES 2. FUNCTIONAL DESIGN SPEC. (FDS) DOCUMENTS FOR SCADA 3. BALANCE ENGINEERING 4. ORDERING OF EQUIPMENT 5. DRAWING/DOCUMENT REVIEW (COVERING ALL DOCUMENTS AND PLANNING 2 WEEKS REVIEW TIME STARTING FROM DOCUMENT RECEIVED IN THE WGI OFFICE FOR EACH DOCUMENT) 6. PRE FAT FOR SCADA SYSTEM 7. FAT FOR SCADA SYSTEM 8. PACKAGING 9. TRANSPORTATION 10. INSTALLATION OF EQUIPMENTS 11. INTEGRATION WITH TELECOM SYSTEM, ELECTRICAL & INSTRUMENTATION SYSTEMS 12. PRE- SAT FOR SCADA SYSTEM 13. SAT FOR INTEGRATED SCADA SYSTEM 14. TRIAL RUN 15. TRAINING 16. WARRANTY IV) The SCADA vendor shall also submit every month [or earlier] a “Hold up & Slippage Report” wherever necessary. He shall provide additional efforts whenever the PERT/CPM diagram indicates a delay in completion date. All extra costs incurred by the SCADA vendor for such additional efforts in order to prevent a possible delay in the completion date shall be to his account.

Page 103 of 175

Page 105: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 94 of 95

24.2 PROJECT EXECUTION ORGANIZATION

I) SCADA vendor shall furnish as a part of the proposal the project execution organization chart showing the no., level and category of engineering managers envisaged to carry out the project execution & management functions including QA/QC support as per the contract requirements to the satisfaction of the WGI / GGL. II) The project execution shall be carried out by appointing a Project coordinator who will be responsible for coordinating various activities within the respective disciplines. III) Overall project management functions shall be carried out by Project Manager from the SCADA vendor, who shall control the execution of the project. The Project Manager should have at least 15 years experience and should have successfully executed at least two projects for SCADA system.

24.3 PROJECT SITE ORGANIZATION

I) SCADA vendor shall furnish, as a part of the proposal, the project site organization chart showing the no., level and type of engineers & specialists envisaged to carry out the complete works as per the contract requirements to the satisfaction of the WGI / GGL. II) SCADA vendor shall ensure that as a minimum suitable nos. of following type and level of experienced engineers! specialists shall be available at site, well conversant in their respective areas of specialization and experienced on system hardware & software, during installation, RTUs online testing, commissioning, Pre-SAT, SAT and Trial run phases of the project. a. Computer hardware & system software specialist. b. SCADA software, database, HMI, interfacing with telecom system and networking specialist(s). c. RTUs and telemetry equipments specialist. d. Application software, SCADA interfacing specialist(s) e. The site manager responsible for smooth co-ordination and interfacing of all the systems. SCADA vendor shall engage adequate no. of qualified and experienced engineers on the system and who were involved in various stages of system design, engineering, integration, development and FAT, for overall site implementation of SCADA system. III) SCADA Vendor shall be fully responsibility for site management, installation, online testing, commissioning, Pre-SAT, site acceptance testing and Trial run of SCADA system.

Page 104 of 175

Page 106: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11- 0290- 02-11- 02- 002 A

GAIL GAS LIMITED

TECHNICAL SPECIFICATION FOR SCADA

SHEET 95 of 95

25.0 Man Day Rates Gail Gas Limited may require services of SCADA engineer for expansion of SCADA system (at MCC & SMCC) for adding new CGD networks; addition of RTUs, interfacing of IEDs, which are not covered in the present scope of work. These services will be required during five years period after placement of order. Number of man days required will be approximately 10 days. The SCADA vendor has to quote for providing services of SCADA engineer at MCC / SMCC and CCC for 10 man days. The man day rates will include all traveling, boarding, lodging, local conveyance and all taxes and duties. The services of SCADA engineer will be used by Gail Gas Limited as per the requirements during next five year period. While 10 man days rates will be used as part of price bid evaluation, Gail Gas Limited reserves the right to utilize all or part of 10 man’s – days as per actual requirement. Payment will be released by Gail Gas Limited as per actual number of man days utilized. The engineer of SCADA vendor shall be called for a minimum of five days at a time. The days will be counted from the date of report at MCC / SMCC / CCC. The intervening holidays while working shall also be counted for payment. At least 8 hour services are to be provided on each day by the visiting SCADA engineer.

26.0 ATTACHMENTS

i. SCADA Architecture Drawing ii. Control Center(s) Layout Drawing iii. CNG Compressor I/O Details iv. CNG Dispenser I/O Details v. Odorizing Unit I/O List (will be given to Vendor during detail engineering) vi. CGS I/O List (will be given to Vendor during detail engineering) vii. Technical Specifications for UPS System viii. Technical Data Sheet for UPS ix. Qualification, Provenness Requirements & Technical Forms

Page 105 of 175

Page 107: City Gas gail Jp Kenny- Wood Group India

Page 106 of 175

Page 108: City Gas gail Jp Kenny- Wood Group India

Page 107 of 175

Page 109: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

0

SHEET 1 of 11

CNG COMPRESSOR PLC

I/O DETAILS

Page 108 of 175

Page 110: City Gas gail Jp Kenny- Wood Group India

W.O.INS88

1200 SCHM CNG COMPRESSOR - ENGINE DRIVEN

M/S KIRLOSKAR PNEUMATICS CO. LTD

M/S GAIL

1880 / DDK / 27273

Mr. Gaurav Kharadi

CNG COMPRESSOR

Positronics Representative

Client

End Client

Customer Project Number :

Project

KPCL Project Number

Page 109 of 175

Page 111: City Gas gail Jp Kenny- Wood Group India

SR.NO. CARD CH.NO. TAG NAME ADDRESS DATA TYPE HLTHY COND. TAG DESCRIPTION

1 1 LSL_103 I 0.0 BOOL NC MAKE UP WATER TANK EJW

2 2 LSL_104 I 0.1 BOOL NC MAKE UP WATER TANK AW

3 3 SPARE_I02 I 0.2 BOOL NO SPARE

4 4 VSH_102 I 0.3 BOOL NC COMP. VIBRATION VERY HIGH

5 5 LSL_102 I 0.4 BOOL NC ENGINE LUBE OIL LEVEL LOW

6 6 FSL_101 I 0.5 BOOL NC LUBRICATOR NO FLOW SWITCH 120 SEC

7 7 LSL_101 I 0.6 BOOL NC COMP. LUBE OIL LEVEL LOW

8 8 FD_101 I 0.7 BOOL NC FLAME DETECTOR WITHIN ACOUSTICAL ENCLOSURE - ENGINE

9 9 FD_102 I 1.0 BOOL NC FLAME DETECTOR WITHIN ACOUSTICAL ENCLOSURE - COMP.

10 10 LSL_105 I 1.1 BOOL NC LUBE OIL TANK LEVEL LOW

11 11 ZSL_101 I 1.2 BOOL NC CO2 SYSTEM CYLINDER-1 HEALTHY CONTACT

12 12 PSL_101 I 1.3 BOOL NC CO2 SYSTEM PRESSURE SW

13 13 ZSL_102 I 1.4 BOOL NC CO2 SYSTEM CYLINDER-2 HEALTHY CONTACT

14 14 SPARE_I15 I 1.5 BOOL - SPARE

15 15 SPARE_I16 I 1.6 BOOL - SPARE

16 16 SPARE_I17 I 1.7 BOOL - SPARE

17 17 CO2_SYS_BYPASS_SW I 2.0 BOOL NC - BYPASS CO2 SYSTEM BYPASS SELECTION SW

18 18 COMP_START_PB I 2.1 BOOL NO COMP. START PB

19 19 COMP_STOP_PB I 2.2 BOOL NC COMP. STOP PB

20 20 EMRG_STOP_PB I 2.3 BOOL NC EMERGENCY STOP PB

21 21 FAULT_ACK_PB I 2.4 BOOL NO FAULT ACKNOWLEDGE PB

22 22 FAULT_RESET_PB I 2.5 BOOL NO FAULT RESET PB

23 23 OP_INCR_PB I 2.6 BOOL NO PB FOR OPERATOR PANEL - INCREMENT

24 24 SPARE_I27 I 2.7 BOOL - SPARE

25 25 OP_DECR_PB I 3.0 BOOL NO PB FOR OPERATOR PANEL - DECREMENT

26 26 OP_OUTPUT_STATUS I 3.1 BOOL NO PB FOR OPERATOR PANEL - OUTPUT STATUS

27 27 OP_SCROLL_UP I 3.2 BOOL NO PB FOR OPERATOR PANEL - SCROLL UP

28 28 OP_SCROLL_DOWN I 3.3 BOOL NO PB FOR OPERATOR PANEL - SCROLL DOWN

29 29 OP_PB I 3.4 BOOL NO PB FOR OPERATOR PANEL - HOME

30 30 S1_SPARE_SW I 3.5 BOOL - S1 SPARE SW

31 31 COMP_AUTO / MAN_SW I 3.6 BOOL NC - AUTO S2 COMP. AUTO / MANUAL SW

32 32 SPARE_I37 I 3.7 BOOL - SPARE

DI-1

INS88 - DIGITAL INPUTS

Page 110 of 175

Page 112: City Gas gail Jp Kenny- Wood Group India

SR.NO. CARD CH.NO. TAG NAME ADDRESS DATA TYPE TAG DESCRIPTION

1 1 SOV_101 Q 0.0 BOOL COMP. SUCTION SHUTOFF VALVE

2 2 SOV_102 Q 0.1 BOOL 1st STAGE SUCTION SEPARATOR DRAIN VALVE

3 3 SOV_103 Q 0.2 BOOL 2nd STAGE SUCTION SEPARATOR DRAIN VALVE

4 4 SOV_104 Q 0.3 BOOL 3rd STAGE SUCTION SEPARATOR DRAIN VALVE

5 5 SOV_105 Q 0.4 BOOL DISCHARGE FILTER AFTER COOLER DRAIN VALVE

6 6 SOV_107 Q 0.5 BOOL ENGINE STARTER SHUTOFF VALE (FOR CRANCKING)

7 7 SOV_501 Q 0.6 BOOL SOV FOR CO2 FLOODING SYSTEM CYLINDER-1

8 8 SOV_502 Q 0.7 BOOL SOV FOR CO2 FLOODING SYSTEM CYLINDER-2

9 9 ENG_IGNITION_GRND Q 1.0 BOOL ENGINE IGNITION GROUNDING

10 10 SOV_110 Q 1.1 BOOL CASCADE HIGH BANK

11 11 SOV_111 Q 1.2 BOOL CASCADE MEDIUM BANK

12 12 SOV_112 Q 1.3 BOOL CASCADE LOW BANK

13 13 SOV_114 Q 1.4 BOOL MOBILE BANK

14 14 HOOTER Q 1.5 BOOL HOOTER

15 15 SOV_106 Q 1.6 BOOL ENGINE FUEL INLET LINE SHUTOFF VALVE

16 16 SPARE_Q17 Q 1.7 BOOL SPARE

17 17 SPARE_Q20 Q 2.0 BOOL SPARE

18 18 SPARE_Q21 Q 2.1 BOOL SPARE

19 19 SPARE_Q22 Q 2.2 BOOL SPARE

20 20 SPARE_Q23 Q 2.3 BOOL SPARE

21 21 SPARE_Q24 Q 2.4 BOOL SPARE

22 22 SPARE_Q25 Q 2.5 BOOL SPARE

23 23 SPARE_Q26 Q 2.6 BOOL SPARE

24 24 SPARE_Q27 Q 2.7 BOOL SPARE

25 25 SPARE_Q30 Q 3.0 BOOL SPARE

26 26 SPARE_Q31 Q 3.1 BOOL SPARE

27 27 SPARE_Q32 Q 3.2 BOOL SPARE

28 28 SPARE_Q33 Q 3.3 BOOL SPARE

29 29 SPARE_Q34 Q 3.4 BOOL SPARE

30 30 SPARE_Q35 Q 3.5 BOOL SPARE

31 31 SPARE_Q36 Q 3.6 BOOL SPARE

32 32 SPARE_Q37 Q 3.7 BOOL SPARE

DO-1

INS88 - DIGITAL OUTPUTS

Page 111 of 175

Page 113: City Gas gail Jp Kenny- Wood Group India

LO-LO LO HI HI-HI LO-LO LO HI HI-HI LO-LO LO HI HI-HI

1 1 PT_105 INT PIW 256 GAS RECOVERY VESSEL PRESSURE 4..20 mA 0 - 60 Kg/Cm2 - 10 35 -

2 2 PT_106 INT PIW 258 ENGINE FUEL GAS PRESSURE 4..20 mA 0 - 10 Kg/Cm2 0.7 2

3 3 PT_107 INT PIW 260 ENGINE LUBE OIL PRESSURE 4..20 mA 0 - 10 Kg/Cm2 2 10 SEC

4 4 PT_108 INT PIW 262 COMP. LUBE OIL PRESSURE 4..20 mA 0 - 10 Kg/Cm2 2 10 SEC

5 5 PT_109 INT PIW 264 ENGINE STARTING AIR PRESSURE 4..20 mA 0 - 25 Kg/Cm2 6

6 6 PT_110 INT PIW 266 INLET (FINAL DISCHARGE) PRESSURE TO PRIORITY PANEL 4..20 mA 0 - 400 Kg/Cm2

7 7 PT_111 INT PIW 268 INLET (FINAL DISCHARGE) PRESSURE TO PRIORITY PANEL 4..20 mA 0 - 400 Kg/Cm2

8 8 SPARE_PIW_270 INT PIW 270 SPARE 4..20 mA -

9 1 GD_101 INT PIW 272 GAS DETECTOR WITHIN ACOUSTICAL ENCLOSURE - ENGINE 4..20 mA 0 - 100 % 50

10 2 GD_102 INT PIW 274 GAS DETECTOR WITHIN ACOUSTICAL ENCLOSURE - COMP. 4..20 mA 0 - 100 % 50

11 3 TE_113 INT PIW 276 ENGINE EXHAUST GAS TEMP. 4..20 mA 0 - 1000 Deg °C 750

12 4 ENG_SPEED INT PIW 278 PULSE INPUT FROM ENGINE TECHOMETER 4..20 mA 0 - 2000 rpm 1800

13 5 TE_101 INT PIW 280 1st STAGE SUCTION TEMP. RTD (PT100) Not Applicable

14 6 TE_102 INT PIW 282 1st STAGE DISCHARGE TEMP. RTD (PT100) Not Applicable 150

15 7 TE_103 INT PIW 284 2nd STAGE SUCTION TEMP. RTD (PT100) Not Applicable

16 8 TE_104 INT PIW 286 2nd STAGE DISCHARGE TEMP. RTD (PT100) Not Applicable 140

17 1 TE_105 INT PIW 288 3rd STAGE SUCTION TEMP. RTD (PT100) Not Applicable

18 2 TE_106 INT PIW 290 3rd STAGE DISCHARGE TEMP. RTD (PT100) Not Applicable 110

19 3 TE_107 INT PIW 292 AFTER COOLER TEMP. RTD (PT100) Not Applicable 60

20 4 TE_108 INT PIW 294 ENGINE LUBE OIL TEMP. RTD (PT100) Not Applicable 80

21 5 TE_109 INT PIW 296 COMP. LUBE OIL TEMP. RTD (PT100) Not Applicable 80

22 6 TE_110 INT PIW 298 ENGINE JACKET WATER OUTLET TEMP. RTD (PT100) Not Applicable

23 7 TE_111 INT PIW 300 ENGINE JACKET WATER INLET TEMP. RTD (PT100) Not Applicable 100

24 8 TE_112 INT PIW 302 ENGINE AUX. WATER OUTLET TEMP. RTD (PT100) Not Applicable 90

25 1 PT_101 INT PIW 304 1st STAGE SUCTION PRESSURE 4..20 mA 0 - 40 Kg/Cm2 16 21 120 SEC 120 SEC

26 2 PT_102 INT PIW 306 1st STAGE DISCHARGE PRESSURE 4..20 mA 0 - 100 Kg/Cm2 - 65

27 3 PT_103 INT PIW 308 2nd STAGE DISCHARGE PRESSURE 4..20 mA 0 - 250 Kg/Cm2 - 170

28 4 PT_104 INT PIW 310 3rd STAGE DISCHARGE PRESSURE 4..20 mA 0 - 400 Kg/Cm2 - 260

29 5 SPARE_PIW_312 INT PIW 312 SPARE 4..20 mA - - - - -

30 6 SPARE_PIW_314 INT PIW 314 SPARE 4..20 mA - - - - -

31 7 SPARE_PIW_316 INT PIW 316 SPARE 4..20 mA - - - - -

32 8 SPARE_PIW_318 INT PIW 318 SPARE 4..20 mA - - - - -

SETPOINTS INITIAL BYPASS TIMER (SEC) TRIP DELAY TIMER (SEC)

INS88 - ANALOG INPUTS

INSTRUMENT RANGEI/P TYPESR.NO. CARD CH.NO. TAG NAME DATA TYPE ADDRESS TAG DESCRIPTION

AI-4

AI-1

AI-2

AI-3

Page 112 of 175

Page 114: City Gas gail Jp Kenny- Wood Group India

RS-485

Master

Sr.

No.Description

Tag

NameSlave Address

Baud

RateParity

Stop

Bits

Data

Bits

1 Flow meter-1 FM-101 1 9600 None 1 8

2 Flow meter-2 FM-102 2 9600 None 1 8

3 Flow meter-3 FM-103 3 9600 None 1 8

Sr.

No.

Require on

OP77B

1 YES

2 YES

3 7 DAYS

4 12 MONTHS

5 3 SHIFTS

6 2 FORTNIGHTS

MODBUS DETAILS

Description Comments

Current Flow Value

Communication Interface

Modbus Driver in PLC

Totalised Flow Value

Monthly Record

Shift-Wise Record

Forth - Night Record

No. of Days Record

Page 113 of 175

Page 115: City Gas gail Jp Kenny- Wood Group India

SR. NO. TAG NAME ADDRESS DATA TYPE DESCRIPTION

1 DIGITAL_IP ID 0 DWORD 32 DIGITAL INPUT BITS

2 DIGITAL_OP QD 0 DWORD 32 DIGITAL OUTPUT BITS

3 PT_105_HI DB13.DBD12 REAL GAS RECOVERY VESSEL PRESSURE

4 PT_105_LO DB13.DBD16 REAL

5 PT_105_ACT DB13.DBD28 REAL

6 PT_106_HI DB13.DBD44 REAL ENGINE FUEL GAS PRESSURE

7 PT_106_LO DB13.DBD48 REAL

8 PT_106_ACT DB13.DBD60 REAL

9 PT_107_LL DB13.DBD88 REAL

10 PT_107_ACT DB13.DBD92 REAL

11 PT_108_LL DB13.DBD120 REAL

12 PT_108_ACT DB13.DBD124 REAL

13 PT_109_LO DB13.DBD144 REAL ENGINE STARTING AIR PRESSURE

14 PT_109_ACT DB13.DBD156 REAL

15 PT_110_ACT DB13.DBD188 REAL INLET (FINAL DISCHARGE) PRESSURE TO PRIORITY PANEL

16 PT_111_ACT DB13.DBD220 REAL INLET (FINAL DISCHARGE) PRESSURE TO PRIORITY PANEL

17 SPARE_PIW_270_ACT DB13.DBD252 REAL SPARE AI-1 CHANNEL-8

18 GD_101_HH DB14.DBD20 REAL

19 GD_101_ACT DB14.DBD28 REAL

20 GD_102_HH DB14.DBD52 REAL

21 GD_102_ACT DB14.DBD60 REAL

22 TE_113_HH DB14.DBD84 REAL

23 TE_113_ACT DB14.DBD92 REAL

24 ENG_SPEED_HH DB14.DBD116 REAL

25 ENG_SPEED_ACT DB14.DBD124 REAL

26 TE_101_ACT DB14.DBD156 REAL 1st STAGE SUCTION TEMP.

27 TE_102_HH DB14.DBD180 REAL

28 TE_102_ACT DB14.DBD188 REAL

29 TE_103_ACT DB14.DBD220 REAL 2nd STAGE SUCTION TEMP.

30 TE_104_HH DB14.DBD244 REAL

31 TE_104_ACT DB14.DBD252 REAL

32 TE_105_ACT DB15.DBD28 REAL 3rd STAGE SUCTION TEMP.

33 TE_106_HH DB15.DBD52 REAL

34 TE_106_ACT DB15.DBD60 REAL

35 TE_107_HH DB15.DBD84 REAL

36 TE_107_ACT DB15.DBD92 REAL

37 TE_108_HH DB15.DBD116 REAL

38 TE_108_ACT DB15.DBD124 REAL

39 TE_109_HH DB15.DBD148 REAL

40 TE_109_ACT DB15.DBD156 REAL

41 TE_110_ACT DB15.DBD188 REAL ENGINE JACKET WATER OUTLET TEMP.

42 TE_111_HH DB15.DBD212 REAL

43 TE_111_ACT DB15.DBD220 REAL

44 TE_112_HI DB15.DBD236 REAL ENGINE AUX. WATER OUTLET TEMP.

45 TE_112_ACT DB15.DBD252 REAL

46 PT_101_HH DB15.DBD20 REAL

47 PT_101_LL DB15.DBD24 REAL

48 PT_101_ACT DB15.DBD28 REAL

49 PT_102_HH DB15.DBD52 REAL

50 PT_102_ACT DB15.DBD60 REAL

51 PT_103_HH DB15.DBD84 REAL

52 PT_103_ACT DB15.DBD92 REAL

53 PT_104_HH DB15.DBD116 REAL

54 PT_104_ACT DB15.DBD124 REAL

55 SPARE_PIW_312_ACT DB15.DBD156 REAL SPARE AI-4 CHANNEL-5

SCADA TAGS

Page 114 of 175

Page 116: City Gas gail Jp Kenny- Wood Group India

56 SPARE_PIW_314_ACT DB15.DBD188 REAL SPARE AI-4 CHANNEL-6

57 SPARE_PIW_316_ACT DB15.DBD220 REAL SPARE AI-4 CHANNEL-7

58 SPARE_PIW_318_ACT DB15.DBD252 REAL SPARE AI-4 CHANNEL-8

59 AUTO_START_P DB20.DBD0 REAL COMPRESSOR AUTO START PRESSURE

60 AUTO_STOP_P DB20.DBD4 REAL COMPRESSOR AUTO STOP PRESSURE

61 MANUAL_RESTART_P DB20.DBD8 REAL COMPRESSOR RE-START PRESSURE

62 BUS_DISPENSER_SP DB20.DBD12 REAL BUS DISPENSER SOV-117

63 HIGH_CASCADE_SP DB20.DBD16 REAL HIGH BANK SOV-110

64 MED_CASCADE_SP DB20.DBD20 REAL MEDIUM BANK SOV-111

65 LOW_CASCADE_SP DB20.DBD24 REAL LOW BANK SOV-112

66 MOBILE_BANK_SP DB20.DBD32 REAL MOBILE BANK SOV-114

67 CMP_START_DS_SPEED_SP DB20.DBD48 REAL COMP. START DESIRED SPEED TO ENERGIZE SOV107

68 ENG_ATND_FULL_SPEED DB20.DBD52 REAL ENGINE ATTAINS FULL SPEED

69 INTIAL_BYPASS_TIMER_1_SP DB10.DBW2 INT INITIAL BYPASS TIMER FOR PT-107 & PT-108

70 INTIAL_BYPASS_TIMER_1_ET DB10.DBW62 INT

71 SOV102_CLOSE_T_SP DB10.DBW12 INT SOV-102 CLOSE TIMER

72 SOV102_CLOSE_T_ET_H DB41.DBD6 INT

73 SOV102_CLOSE_T_ET_M DB41.DBD10 INT

74 SOV102_CLOSE_T_ET_S DB41.DBD14 INT

75 SOV102_OPEN_T_SP DB10.DBW22 INT SOV-102 OPEN TIMER

76 SOV102_OPEN_T_ET DB41.DBD32 INT

77 INTIAL_BYPASS_TIMER_2_SP DB10.DBW32 INT INITIAL BYPASS TIMER FOR PT-101

78 INTIAL_BYPASS_TIMER_2_ET DB10.DBW36 INT

79 INTIAL_BYPASS_TIMER_3_SP DB10.DBW42 INT INITIAL BYPASS TIMER FOR FSL-101

80 INTIAL_BYPASS_TIMER_3_ET DB10.DBW46 INT

81 IGN_TIMER_SP DB10.DBW52 INT ENGINE IGNITION GROUNDING TIMER

82 IGN_TIMER_ET DB10.DBW58 INT

83 SOV_107_PRESET_TIMER_SP DB10.DBW62 INT SOV-107 PRESET SPEED REACHED TIMER

84 SOV_107_PRESET_TIMER_ET DB10.DBW68 INT

85 SOV105_CLS_T_ATN_FUL_SPD_SP DB10.DBW72 INT SOV-105 CLOSE AFTER ENGINE ATTENDED FULL SPEED TIMER

86 SOV105_CLS_T_ATN_FUL_SPD_ET DB10.DBW78 INT

87 SOV104_CLS_T_ATN_FUL_SPD_SP DB10.DBW82 INT SOV-104 CLOSE AFTER ENGINE ATTENDED FULL SPEED TIMER

88 SOV104_CLS_T_ATN_FUL_SPD_ET DB10.DBW88 INT

89 SOV103_CLS_T_ATN_FUL_SPD_SP DB10.DBW92 INT SOV-103 CLOSE AFTER ENGINE ATTENDED FULL SPEED TIMER

90 SOV103_CLS_T_ATN_FUL_SPD_ET DB10.DBW98 INT

91 SOV_103_CLOSE_T_SP DB10.DBW102 INT SOV-103 CLOSE TIMER WHEN COMP. RUNNING

92 SOV_103_CLOSE_T_ET DB10.DBW106 INT

93 SOV103_OPEN_T_SP DB10.DBW112 INT SOV-103 OPEN TIMER WHEN COMP. RUNNING

94 SOV103_OPEN_T_ET DB10.DBW116 INT

95 SOV104_CLOSE_T_SP DB10.DBW122 INT SOV-104 CLOSE TIMER WHEN COMP. RUNNING

96 SOV104_CLOSE_T_ET DB10.DBW126 INT

97 SOV104_OPEN_T_SP DB10.DBW132 INT SOV-104 OPEN TIMER WHEN COMP. RUNNING

98 SOV104_OPEN_T_ET DB10.DBW136 INT

99 SOV105_CLOSE_T_SP DB10.DBW142 INT SOV-105 CLOSE TIMER WHEN COMP. RUNNING

100 SOV105_CLOSE_T_ET DB10.DBW146 INT

101 SOV105_OPEN_T_SP DB10.DBW152 INT SOV-105 OPEN TIMER WHEN COMP. RUNNING

102 SOV105_OPEN_T_ET DB10.DBW156 INT

103 AUTO_STOP_SP DB10.DBW162 INT COMP. AUTO STOP TIMER

104 AUTO_STOP_ET DB10.DBW166 INT

105 SOV106_DENG_SP DB10.DBW172 INT SOV-106 DE-ENERGIZE TIMER

106 SOV106_DENG_ET DB10.DBW178 INT

107 SOV110_OFF_DELAY_SP DB10.DBW182 INT HIGH BANK SOV-110 OFF DELAY TIMER

108 SOV110_OFF_DELAY_ET DB10.DBW184 INT

109 SOV111_OFF_DELAY_SP DB10.DBW192 INT MEDIUM BANK SOV-111 OFF DELAY TIMER

110 SOV111_OFF_DELAY_ET DB10.DBW194 INT

111 SOV112_OFF_DELAY_SP DB10.DBW202 INT LOW BANK SOV-112 OFF DELAY TIMER

112 SOV112_OFF_DELAY_ET DB10.DBW204 INT

113 SOV114_OFF_DELAY_SP DB10.DBW212 INT MOBILE BANK SOV-114 OFF DELAY TIMER

114 SOV114_OFF_DELAY_ET DB10.DBW214 INT

Page 115 of 175

Page 117: City Gas gail Jp Kenny- Wood Group India

115 FM_101_CURRENT_FLOW DB33.DBD0 REAL FM-101 CURRENT FLOW

116 FM_101_TOTALIZER DB33.DBD24 REAL FM-101 TOTALIZER

117 FM_101_DAY_1 DB36.DBD0 REAL FM-101 FLOW RECORDS DAY-1

118 FM_101_DAY_2 DB36.DBD4 REAL FM-101 FLOW RECORDS DAY-2

119 FM_101_DAY_3 DB36.DBD8 REAL FM-101 FLOW RECORDS DAY-3

120 FM_101_DAY_4 DB36.DBD12 REAL FM-101 FLOW RECORDS DAY-4

121 FM_101_DAY_5 DB36.DBD16 REAL FM-101 FLOW RECORDS DAY-5

122 FM_101_DAY_6 DB36.DBD20 REAL FM-101 FLOW RECORDS DAY-6

123 FM_101_DAY_7 DB36.DBD24 REAL FM-101 FLOW RECORDS DAY-7

124 FM_101_DAY_8 DB36.DBD28 REAL FM-101 FLOW RECORDS DAY-8

125 FM_101_DAY_9 DB36.DBD32 REAL FM-101 FLOW RECORDS DAY-9

126 FM_101_DAY_10 DB36.DBD36 REAL FM-101 FLOW RECORDS DAY-10

127 FM_101_DAY_11 DB36.DBD40 REAL FM-101 FLOW RECORDS DAY-11

128 FM_101_DAY_12 DB36.DBD44 REAL FM-101 FLOW RECORDS DAY-12

129 FM_101_DAY_13 DB36.DBD48 REAL FM-101 FLOW RECORDS DAY-13

130 FM_101_DAY_14 DB36.DBD52 REAL FM-101 FLOW RECORDS DAY-14

131 FM_101_DAY_15 DB36.DBD56 REAL FM-101 FLOW RECORDS DAY-15

132 FM_101_DAY_16 DB36.DBD60 REAL FM-101 FLOW RECORDS DAY-16

133 FM_101_DAY_17 DB36.DBD64 REAL FM-101 FLOW RECORDS DAY-17

134 FM_101_DAY_18 DB36.DBD68 REAL FM-101 FLOW RECORDS DAY-18

135 FM_101_DAY_19 DB36.DBD72 REAL FM-101 FLOW RECORDS DAY-19

136 FM_101_DAY_20 DB36.DBD76 REAL FM-101 FLOW RECORDS DAY-20

137 FM_101_DAY_21 DB36.DBD80 REAL FM-101 FLOW RECORDS DAY-21

138 FM_101_DAY_22 DB36.DBD84 REAL FM-101 FLOW RECORDS DAY-22

139 FM_101_DAY_23 DB36.DBD88 REAL FM-101 FLOW RECORDS DAY-23

140 FM_101_DAY_24 DB36.DBD92 REAL FM-101 FLOW RECORDS DAY-24

141 FM_101_DAY_25 DB36.DBD96 REAL FM-101 FLOW RECORDS DAY-25

142 FM_101_DAY_26 DB36.DBD100 REAL FM-101 FLOW RECORDS DAY-26

143 FM_101_DAY_27 DB36.DBD104 REAL FM-101 FLOW RECORDS DAY-27

144 FM_101_DAY_28 DB36.DBD108 REAL FM-101 FLOW RECORDS DAY-28

145 FM_101_DAY_29 DB36.DBD112 REAL FM-101 FLOW RECORDS DAY-29

146 FM_101_DAY_30 DB36.DBD116 REAL FM-101 FLOW RECORDS DAY-30

147 FM_101_DAY_31 DB36.DBD120 REAL FM-101 FLOW RECORDS DAY-31

148 FM_101_JAN DB36.DBD196 REAL FM-101 FLOW RECORDS MONTH-JANUARY

149 FM_101_FEB DB36.DBD200 REAL FM-101 FLOW RECORDS MONTH-FEBRUARY

150 FM_101_MAR DB36.DBD204 REAL FM-101 FLOW RECORDS MONTH-MARCH

151 FM_101_APR DB36.DBD208 REAL FM-101 FLOW RECORDS MONTH-APRIL

152 FM_101_MAY DB36.DBD212 REAL FM-101 FLOW RECORDS MONTH-MAY

153 FM_101_JUNE DB36.DBD216 REAL FM-101 FLOW RECORDS MONTH-JUNE

154 FM_101_JULY DB36.DBD220 REAL FM-101 FLOW RECORDS MONTH-JULY

155 FM_101_AUG DB36.DBD224 REAL FM-101 FLOW RECORDS MONTH-AUGUST

156 FM_101_SEPT DB36.DBD228 REAL FM-101 FLOW RECORDS MONTH-SEPTEMBER

157 FM_101_OCT DB36.DBD232 REAL FM-101 FLOW RECORDS MONTH-OCTOBER

158 FM_101_NOV DB36.DBD236 REAL FM-101 FLOW RECORDS MONTH-NOVEMBER

159 FM_101_DEC DB36.DBD240 REAL FM-101 FLOW RECORDS MONTH-DECEMBER

160 FM_101_FORTNIGHT_1 DB36.DBD244 REAL FM-101 FLOW RECORDS FORTNIGHT-1

161 FM_101_FORTNIGHT_2 DB36.DBD248 REAL FM-101 FLOW RECORDS FORTNIGHT-2

162 FM_101_SHIFT_1 DB36.DBD272 REAL FM-101 FLOW RECORDS SHIFT-1

163 FM_101_SHIFT_2 DB36.DBD276 REAL FM-101 FLOW RECORDS SHIFT-2

164 FM_101_SHIFT_3 DB36.DBD280 REAL FM-101 FLOW RECORDS SHIFT-3

165 FM_102_CURRENT_FLOW DB34.DBD0 REAL FM-102 CURRENT FLOW

166 FM_102_TOTALIZER DB34.DBD24 REAL FM-102 TOTALIZER

167 FM_102_DAY_1 DB37.DBD0 REAL FM-102 FLOW RECORDS DAY-1

168 FM_102_DAY_2 DB37.DBD4 REAL FM-102 FLOW RECORDS DAY-2

169 FM_102_DAY_3 DB37.DBD8 REAL FM-102 FLOW RECORDS DAY-3

170 FM_102_DAY_4 DB37.DBD12 REAL FM-102 FLOW RECORDS DAY-4

171 FM_102_DAY_5 DB37.DBD16 REAL FM-102 FLOW RECORDS DAY-5

172 FM_102_DAY_6 DB37.DBD20 REAL FM-102 FLOW RECORDS DAY-6

173 FM_102_DAY_7 DB37.DBD24 REAL FM-102 FLOW RECORDS DAY-7

Page 116 of 175

Page 118: City Gas gail Jp Kenny- Wood Group India

174 FM_102_DAY_8 DB37.DBD28 REAL FM-102 FLOW RECORDS DAY-8

175 FM_102_DAY_9 DB37.DBD32 REAL FM-102 FLOW RECORDS DAY-9

176 FM_102_DAY_10 DB37.DBD36 REAL FM-102 FLOW RECORDS DAY-10

177 FM_102_DAY_11 DB37.DBD40 REAL FM-102 FLOW RECORDS DAY-11

178 FM_102_DAY_12 DB37.DBD44 REAL FM-102 FLOW RECORDS DAY-12

179 FM_102_DAY_13 DB37.DBD48 REAL FM-102 FLOW RECORDS DAY-13

180 FM_102_DAY_14 DB37.DBD52 REAL FM-102 FLOW RECORDS DAY-14

181 FM_102_DAY_15 DB37.DBD56 REAL FM-102 FLOW RECORDS DAY-15

182 FM_102_DAY_16 DB37.DBD60 REAL FM-102 FLOW RECORDS DAY-16

183 FM_102_DAY_17 DB37.DBD64 REAL FM-102 FLOW RECORDS DAY-17

184 FM_102_DAY_18 DB37.DBD68 REAL FM-102 FLOW RECORDS DAY-18

185 FM_102_DAY_19 DB37.DBD72 REAL FM-102 FLOW RECORDS DAY-19

186 FM_102_DAY_20 DB37.DBD76 REAL FM-102 FLOW RECORDS DAY-20

187 FM_102_DAY_21 DB37.DBD80 REAL FM-102 FLOW RECORDS DAY-21

188 FM_102_DAY_22 DB37.DBD84 REAL FM-102 FLOW RECORDS DAY-22

189 FM_102_DAY_23 DB37.DBD88 REAL FM-102 FLOW RECORDS DAY-23

190 FM_102_DAY_24 DB37.DBD92 REAL FM-102 FLOW RECORDS DAY-24

191 FM_102_DAY_25 DB37.DBD96 REAL FM-102 FLOW RECORDS DAY-25

192 FM_102_DAY_26 DB37.DBD100 REAL FM-102 FLOW RECORDS DAY-26

193 FM_102_DAY_27 DB37.DBD104 REAL FM-102 FLOW RECORDS DAY-27

194 FM_102_DAY_28 DB37.DBD108 REAL FM-102 FLOW RECORDS DAY-28

195 FM_102_DAY_29 DB37.DBD112 REAL FM-102 FLOW RECORDS DAY-29

196 FM_102_DAY_30 DB37.DBD116 REAL FM-102 FLOW RECORDS DAY-30

197 FM_102_DAY_31 DB37.DBD120 REAL FM-102 FLOW RECORDS DAY-31

198 FM_102_JAN DB37.DBD196 REAL FM-102 FLOW RECORDS MONTH-JANUARY

199 FM_102_FEB DB37.DBD200 REAL FM-102 FLOW RECORDS MONTH-FEBRUARY

200 FM_102_MAR DB37.DBD204 REAL FM-102 FLOW RECORDS MONTH-MARCH

201 FM_102_APR DB37.DBD208 REAL FM-102 FLOW RECORDS MONTH-APRIL

202 FM_102_MAY DB37.DBD212 REAL FM-102 FLOW RECORDS MONTH-MAY

203 FM_102_JUNE DB37.DBD216 REAL FM-102 FLOW RECORDS MONTH-JUNE

204 FM_102_JULY DB37.DBD220 REAL FM-102 FLOW RECORDS MONTH-JULY

205 FM_102_AUG DB37.DBD224 REAL FM-102 FLOW RECORDS MONTH-AUGUST

206 FM_102_SEPT DB37.DBD228 REAL FM-102 FLOW RECORDS MONTH-SEPTEMBER

207 FM_102_OCT DB37.DBD232 REAL FM-102 FLOW RECORDS MONTH-OCTOBER

208 FM_102_NOV DB37.DBD236 REAL FM-102 FLOW RECORDS MONTH-NOVEMBER

209 FM_102_DEC DB37.DBD240 REAL FM-102 FLOW RECORDS MONTH-DECEMBER

210 FM_102_FORTNIGHT_1 DB37.DBD244 REAL FM-102 FLOW RECORDS FORTNIGHT-1

211 FM_102_FORTNIGHT_2 DB37.DBD248 REAL FM-102 FLOW RECORDS FORTNIGHT-2

212 FM_102_SHIFT_1 DB37.DBD272 REAL FM-102 FLOW RECORDS SHIFT-1

213 FM_102_SHIFT_2 DB37.DBD276 REAL FM-102 FLOW RECORDS SHIFT-2

214 FM_102_SHIFT_3 DB37.DBD280 REAL FM-102 FLOW RECORDS SHIFT-3

215 FM_103_CURRENT_FLOW DB35.DBD0 REAL FM-103 CURRENT FLOW

216 FM_103_TOTALIZER DB35.DBD24 REAL FM-103 TOTALIZER

217 FM_103_DAY_1 DB38.DBD0 REAL FM-103 FLOW RECORDS DAY-1

218 FM_103_DAY_2 DB38.DBD4 REAL FM-103 FLOW RECORDS DAY-2

219 FM_103_DAY_3 DB38.DBD8 REAL FM-103 FLOW RECORDS DAY-3

220 FM_103_DAY_4 DB38.DBD12 REAL FM-103 FLOW RECORDS DAY-4

221 FM_103_DAY_5 DB38.DBD16 REAL FM-103 FLOW RECORDS DAY-5

222 FM_103_DAY_6 DB38.DBD20 REAL FM-103 FLOW RECORDS DAY-6

223 FM_103_DAY_7 DB38.DBD24 REAL FM-103 FLOW RECORDS DAY-7

224 FM_103_DAY_8 DB38.DBD28 REAL FM-103 FLOW RECORDS DAY-8

225 FM_103_DAY_9 DB38.DBD32 REAL FM-103 FLOW RECORDS DAY-9

226 FM_103_DAY_10 DB38.DBD36 REAL FM-103 FLOW RECORDS DAY-10

227 FM_103_DAY_11 DB38.DBD40 REAL FM-103 FLOW RECORDS DAY-11

228 FM_103_DAY_12 DB38.DBD44 REAL FM-103 FLOW RECORDS DAY-12

229 FM_103_DAY_13 DB38.DBD48 REAL FM-103 FLOW RECORDS DAY-13

230 FM_103_DAY_14 DB38.DBD52 REAL FM-103 FLOW RECORDS DAY-14

231 FM_103_DAY_15 DB38.DBD56 REAL FM-103 FLOW RECORDS DAY-15

232 FM_103_DAY_16 DB38.DBD60 REAL FM-103 FLOW RECORDS DAY-16

Page 117 of 175

Page 119: City Gas gail Jp Kenny- Wood Group India

233 FM_103_DAY_17 DB38.DBD64 REAL FM-103 FLOW RECORDS DAY-17

234 FM_103_DAY_18 DB38.DBD68 REAL FM-103 FLOW RECORDS DAY-18

235 FM_103_DAY_19 DB38.DBD72 REAL FM-103 FLOW RECORDS DAY-19

236 FM_103_DAY_20 DB38.DBD76 REAL FM-103 FLOW RECORDS DAY-20

237 FM_103_DAY_21 DB38.DBD80 REAL FM-103 FLOW RECORDS DAY-21

238 FM_103_DAY_22 DB38.DBD84 REAL FM-103 FLOW RECORDS DAY-22

239 FM_103_DAY_23 DB38.DBD88 REAL FM-103 FLOW RECORDS DAY-23

240 FM_103_DAY_24 DB38.DBD92 REAL FM-103 FLOW RECORDS DAY-24

241 FM_103_DAY_25 DB38.DBD96 REAL FM-103 FLOW RECORDS DAY-25

242 FM_103_DAY_26 DB38.DBD100 REAL FM-103 FLOW RECORDS DAY-26

243 FM_103_DAY_27 DB38.DBD104 REAL FM-103 FLOW RECORDS DAY-27

244 FM_103_DAY_28 DB38.DBD108 REAL FM-103 FLOW RECORDS DAY-28

245 FM_103_DAY_29 DB38.DBD112 REAL FM-103 FLOW RECORDS DAY-29

246 FM_103_DAY_30 DB38.DBD116 REAL FM-103 FLOW RECORDS DAY-30

247 FM_103_DAY_31 DB38.DBD120 REAL FM-103 FLOW RECORDS DAY-31

248 FM_103_JAN DB38.DBD196 REAL FM-103 FLOW RECORDS MONTH-JANUARY

249 FM_103_FEB DB38.DBD200 REAL FM-103 FLOW RECORDS MONTH-FEBRUARY

250 FM_103_MAR DB38.DBD204 REAL FM-103 FLOW RECORDS MONTH-MARCH

251 FM_103_APR DB38.DBD208 REAL FM-103 FLOW RECORDS MONTH-APRIL

252 FM_103_MAY DB38.DBD212 REAL FM-103 FLOW RECORDS MONTH-MAY

253 FM_103_JUNE DB38.DBD216 REAL FM-103 FLOW RECORDS MONTH-JUNE

254 FM_103_JULY DB38.DBD220 REAL FM-103 FLOW RECORDS MONTH-JULY

255 FM_103_AUG DB38.DBD224 REAL FM-103 FLOW RECORDS MONTH-AUGUST

256 FM_103_SEPT DB38.DBD228 REAL FM-103 FLOW RECORDS MONTH-SEPTEMBER

257 FM_103_OCT DB38.DBD232 REAL FM-103 FLOW RECORDS MONTH-OCTOBER

258 FM_103_NOV DB38.DBD236 REAL FM-103 FLOW RECORDS MONTH-NOVEMBER

259 FM_103_DEC DB38.DBD240 REAL FM-103 FLOW RECORDS MONTH-DECEMBER

260 FM_103_FORTNIGHT_1 DB38.DBD244 REAL FM-103 FLOW RECORDS FORTNIGHT-1

261 FM_103_FORTNIGHT_2 DB38.DBD248 REAL FM-103 FLOW RECORDS FORTNIGHT-2

262 FM_103_SHIFT_1 DB38.DBD272 REAL FM-103 FLOW RECORDS SHIFT-1

263 FM_103_SHIFT_2 DB38.DBD276 REAL FM-103 FLOW RECORDS SHIFT-2

264 FM_103_SHIFT_3 DB38.DBD280 REAL FM-103 FLOW RECORDS SHIFT-3

265 COMP_RUN_HOURS DB22.DBD2 REAL COMP. RUNNING HOURS

266 COMP_RUN_MINUTES DB22.DBD6 REAL COMP. RUNNING MINUTES

267 COMP_RUN_SECONDS DB22.DBD10 REAL COMP. RUNNING SECONDS

268 SET_PASSWORD DB23.DBW72 INT DEFAULT / SET PASSWORD

269 ACT_PASSWORD DB23.DBW74 INT PASSWORD VALUE ACTUAL

Page 118 of 175

Page 120: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

0

SHEET 1 of 4

CNG DISPENSER (TULSA) PLC

I/O DETAILS

Page 119 of 175

Page 121: City Gas gail Jp Kenny- Wood Group India

DISPENSER MODBUS REGISTER ADDRESS FILE

Listed below are the two functions with one sample each of SCADA via modbus as it pertains to NM18 boards :-

1) Price change and nozzle authorize command is done via function 16 (hex 10) write multiple registers to address

location 6000 (hex 1770)

a) You will send a packet similar to the one below

01 10 17 70 00 05 0A 12 12 23 23 34 34 45 45 04 04 B1 1C

01 is pump ID

10 is write multiple registers

17 70 is register 6000

00 05 is number of registers being sent, four prices in total

0A is number of data bytes or 05*2=A

12 12 23 23 34 34 45 45 are 4 BCD prices for four different applications in the future 12 12 = Rs 12.12 per KG side

1 price and 23 23=Rs 23.23 per KG

B1 1C are 16 bit CRC values for the packet

Note:- Prices will only appear when delivery starts this is weights and measures requirement. Current delivery prices

will not change during delivery.

2) Status is polled via function 03 read multiple registers to address location 5000 (hex 1388).

a) You will send a packet similar to the ones below

01 03 13 88 00 15 00 AB or 01 03 13 88 00 1D 01 6D or 01 03 13 88 00 49 00 92

01 is pump id you are polling

03 is read multiple registers

13 88 is register 5000

00 1D is number of registers 21 (hex 15).

00 AB is crc.

b) You will get a response similar to the one below

01 03 22 00 00 06 73 00 00 17 35 00 00 29 00 00 00 74 00 66 72 92 61 66 68 72 31 66 66 73 19 66 66 75 42 07 07

00 00 00 00 00 00 00 00 11 00 00 12 34 45 67 23 45 67 89 AB CD CD EF 00 B3 9C

01 is pump id

03 is response to read multiple registers

Page 120 of 175

Page 122: City Gas gail Jp Kenny- Wood Group India

22 is 34 bytes of data to follow

00 00 06 73 is Rs 000006.73 for side1 current value on dispenser screen

00 00 17 35 is Rs 000017.35 for side2 current value on dispenser screen

00 00 29 00 is Kg 0000.2900 for side1 current value on dispenser screen

00 00 74 00 is Ks 0000.7400 for side2 current value on dispense screen

66 72 92 61 is Totalizer Rs 667292.61 for side1

66 68 72 31 is Totalizer Rs 666872.31 for side2

66 66 73 19 is Totalizer Kg 666673.19 for side1

66 66 75 42 is Totalizer Kg 666675.42 for side2

“B3 9C is 16 CRC value for transmission”

Page 121 of 175

Page 123: City Gas gail Jp Kenny- Wood Group India

Protocol Requirement

1. Communication Settings

a. Protocol modbus RTU

a. Baud-rate 2400, 4800, 9600

b. Data Bits 8

c. Stop bit 1

d. Parity none

2. Data format

a. Protocol Method (Bi-Directional or Uni-Directional) modbus bidirectional (Half Duplex)

b. Start Byte Dispenser id

c. Stop Byte CRC

d. Data Type (ASCII or Binary) Binary 8bit RTU

e. Data description 8bit RTU

Function code 3 Read multiple holding regs

Connections Details

Connection Details for RS485 Interface

a. RS485+ (RS485A)

b. RS485- (RS485B)

Page 122 of 175

Page 124: City Gas gail Jp Kenny- Wood Group India

GAIL GAS LIMITED CITY GAS DISTRIBUTION PROJECT

CLIENT JOB NO 0290 TECHNICAL SPECIFICATION FOR

UPS SYSTEM TOTAL SHEETS 13

DOCUMENT NO 11 0290 02 10 02 006

0 01/06/10 ISSUED FOR TENDER GK SB HM

A 26/05/10 ISSUED FOR REVIEW GK SB HM

REV DATE DESCRIPTION PREP CHK APPR

Page 123 of 175

Page 125: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-02-006 A

TECHNICAL SPECIFICATION FOR

UPS SYSTEM Page 2 of 13

TABLE OF CONTENTS

1.0 SCOPE 2.0 CODES AND STANDERDS 3.0 GENERAL REQUIREMENTS 4.0 SITE CONDITIONS 5.0 TECHINICAL REQUIREMENTS 6.0 INSPECTION, TESTING AND ACCEPTANCE 7.0 SITE ACCEPTANCE TESTS 8.0 PACKING AND DESPATCH

Page 124 of 175

Page 126: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-02-006 A

TECHNICAL SPECIFICATION FOR

UPS SYSTEM Page 3 of 13

1. SCOPE 1.1. The specification covers the design, manufacture, testing at works and dispatch in well

packed condition of Uninterrupted Power Supply System required to supply AC power for non linear loads.

1.2. The scope shall include the following:

i) Full wave controlled rectifier ii) Inverter iii) Static switches iv) Nickel Cadmium (Ni-Cd) battery v) Static voltage stabilizer for bypass supply vi) Isolation input and output transformers to achieve desired output voltage &

isolation vii) UPS Distribution Board viii) Interconnecting cabling between various units of UPS ix) Manual bypass switches x) All other items required, but not specified for safe and reliable operation of UPS

system. The exact scope shall be as indicated in specification sheet.

2. CODES & STANDARDS 2.1. The equipment shall conform to the latest issue of the following and relevant Indian

Standard specifications or equivalent specification of the country of origin or IEC specifications.

2.2 The equipment offered shall generally conform to the following codes / standards:

IS: 13314 -- Solid state inverters run from storage batteries.

IS : 11260 -- Stabilized power supplies AG output.

lEC: 146 -- Solid state inverters.

2.3 The equipment shall also conform to the provision of Indian Electricity Rules, Indian Supply

Act and any other statutory regulations in force from time to time.

Page 125 of 175

Page 127: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-02-006 A

TECHNICAL SPECIFICATION FOR

UPS SYSTEM Page 4 of 13

2.4 In the event of conflict between this specification and other documents, the following order

of priority may be followed:

a) Data sheets b) This specification c) Codes & Standards 3. AMBIENT CONDITIONS

Ambient Air Temperature

Maximum - 50 0 C

Minimum - 4 0 C

Relative Humidity:

Maximum - 90%

Minimum - 41%

4. DESIGN AND OPERATIONAL REQUIREMENTS. SYSTEM OPERATION 4.1. The UPS unit and its associated equipment shall be suitable for operating at the

specified rating continuously with the specified voltage and frequency variations under the ambient conditions without exceeding the temperature rise limits specified in relevant standards and without any detrimental effect on any part.

4.2. The UPS system shall be based on latest generation of IGBT based, pulse width

modulated (PWM) design with proven performance. The system should be able to communicate with RTU’s on modbus protocol and provided with multi-dropping facility.

4.3. Redundant scheme with by-pass(FIGURE:-1)

Under normal operating conditions, both inverter units should run in parallel sharing 50% load in synchronism with by-pass power and supply uninterrupted a.c. power to load. On failure of one of these inverters, the faulty inverter should get automatically disconnected from the load and healthy inverter should supply 100% load in synchronism with by pass supply. In the event of second inverter also developing a fault, a no-break load transfer to standby power supply should take place through static switch.

Output frequency of the inverters must remain synchronized to one another, which in turn

shall be synchronized to the standby power supply frequency provided the latter does not vary by more than ±5%. It should be possible to change the setting of frequency range of synchronism between above limits in steps of ± 1%. Outside these limits, inverter should desynchronize with the bypass and run at its own frequency. When running at its own frequency, frequency variation shall be maintained less than ± 0.1%. Resynchronization with bypass power supply must take place automatically with some time delay when frequency comes back to ± 5% range. Change-over from inverter to bypass or bypass to

Page 126 of 175

Page 128: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-02-006 A

TECHNICAL SPECIFICATION FOR

UPS SYSTEM Page 5 of 13

inverter shall also be possible in desynchronized mode of operation. Change-over time in both synchronized and desynchronized mode operation shall be indicated.

4.4. In case of AC input power failure or battery charger failure. the battery shall supply

power to inverter without any interruption. The charger shall be designed for simultaneously feeding complete inverter load and for float/rapid charging the battery to its rated capacity. Charger shall be equipped with 'On Line' automatic as well as manual charging facility.

4.5. The UPS unit shall be suitable for 0.7 lagging to unity power factor loads. The overall load

power factor may be taken as 0.8 lagging. 4.6. The maximum waveform distortion of the output voltage shall not exceed 5% r.m.s for

linear load and 10% r.m.s. for non-linear loads. The UPS unit shall be suitable for operation for non-linear loads having crest factor of 3.

4.7. The inverter steady state output voltage and frequency (free running) variation shall not

exceed ±1% for specified input power supply condition and no-load to full load condition. 4.8. Voltage dip/rise on sudden application / throw of 100% load or on changeover from

inverter to bypass or vice versa shall not exceed 15% and shall be recovered within 100 m.sec. to rated voltage.

4.9. UPS shall be designed for overload of 125% for 10 min. and 150% for 10 sec. After which

drooping characteristic shall come into operation. 4.10. On failure of the main supply, inverter unit shall continue to supply rated load from the

battery bank for 12 hours duration. 4.11. Charger shall simultaneously supply entire power necessary for inverter and to keep the

battery of required capacity in fully charged condition. Provision for automatic charging in both float and boost shall be made.

4.12. Battery shall be Ni-Cd battery. The battery capacity shall be decided considering load

power factor as 0.8, derating factor for ageing 0.8 and derating for minimum ambient temperature as applicable. Design margin of 10% shall be considered. Battery isolation switch, battery bank with rack, inter-cell connectors etc. shall be considered.

4.13. The ventilation fans, if provided shall be supplemented by 100% redundant fan in normal

operation. Normal and redundant fan shall run together. The power supply for fan shall be tapped from the inverter output. It should be possible to operate inverter even after the failure of the fan without temperature rise inside the inverter cubicle exceeding the safe operating temperature limits for 2 hours with alarm for fan failure

4.14. In case of inverter failure due to any reason or overload, affected unit should be isolated

and changeover to other inverter or to bypass should take place automatically. 4.15. Noise level at a distance of 1m from UPS panels shall not exceed 60 dB.

Page 127 of 175

Page 129: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-02-006 A

TECHNICAL SPECIFICATION FOR

UPS SYSTEM Page 6 of 13

4.16. UPS system shall be provided with necessary control, protection, metering, indication, alarm & annunciation for reliable and safe operation of the system. The suggestive list is indicated in Annexure-II.

4.17. All semi-conducting devices shall be protected by fast acting semi-conducting fuses. 4.18. The battery may be taken out of service for maintenance during which period it shall be

possible for the inverter to continue operation taking power from the rectifier. The input filter of the inverter shall be suitably designed to take care of this operational requirement.

4.19. It shall be possible to vary the output voltage steplessly within ± 5% of the specified

output voltage. This adjustment shall be possible to be made when UPS is in operation. 4.20. UPS system shall be suitable for both floating output or earthing of one leg in case of

single phase system / star-point in case of three phase system. 4.21. The UPS system shall have very high system of reliability having minimum MTBF of

50,000 hrs. Vendor shall furnish the value of MTBF, MTTR and availability factor. 5. CONSTRUCTIONAL DETAILS 5.1. The equipment shall preferably be supplied in enclosed, dust & vermin proof, floor

mounted, sheet steel enclosure. In case, it is necessary to provide opening for ventilation, this should be closed by fine mesh. Minimum degree of protection for enclosure shall be IP-41 as per IS-13997.

5.2. Enclosure shall be fabricated with cold rolled sheet annealed steel of minimum thickness

2.0 mm. 5.3. The door hinges shall be concealed type. The doors and the removable covers shall be

provided with non-deteriorating neoprene gaskets without any discontinuities. Gaskets shall be held in position in groove in shaped sheet steel work or these shall be of U type.

5.4. All external hardware shall be cadmium/zinc plated steel. Hardware for fixing the

removable parts shall be provided with retaining devices. 5.5. Panels shall be liberally designed. All components shall be so mounted that they are

easily accessible for inspection and maintenance. 5.6. UPS unit shall preferably have separate panels for each rectifier inverter units, bypass

supply, distribution boards, etc. Various panels of UPS except distribution boards shall be mounted side-by-side & bolted together to form compact assembly.

5.7. Distribution boards shall be of fixed type single front execution in fully compartmentalised

design and divided into distinct panels each comprising of bus-bar chambers, individual feeder modules and vertical cable alley.

Page 128 of 175

Page 130: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-02-006 A

TECHNICAL SPECIFICATION FOR

UPS SYSTEM Page 7 of 13

5.8. Mounting height of components requiring operation and observations shall not be lower than 300 mm and higher than 1800 mm.

5.9. All the live parts which are accessible after opening the front cover / back cover shall be

properly insulated or provided with insulating barrier to prevent accidental contact. Bus bars of distribution boards shall be PVC sleeved.

5.10.Nameplate consisting of black perpex with white engraving shall be provided for each

panel and for each equipment mounted on the front of the panel. Suitable label identification for each component mounted inside the panel shall also be provided.

5.11.All the wirings shall be properly laid and ferruled at both ends. PVC channels may be

used for wiring. For control wiring, minimum 0.5 sq.mm. Copper conductor shall be used.

5.12.The power connections may be made by PVC insulated flexible copper cables or taped copper / aluminium strip.

5.13.All power & control cables shall enter from the bottom. 5.14.Removable bolted aluminium gland plate, heavy duty compression type rolled aluminium

cable glands, crimping type aluminium cable lugs for Al. Cables and copper cable lugs for Cu. Cables, pressure clamp / bolted type terminals etc. shall be provided for each incoming and outgoing cable.

5.15.Terminal blocks shall be grouped according to circuit functions and suitably numbered.

20% extra terminals shall be provided in the terminal block. 5.16.A suitably sized earth bus shall be provided at the bottom of panel with provision for earth

connection at both ends to purchaser’s earth grid. 5.17.All panels shall be of same height so as to form a bank, which shall give good aesthetic

appearance. 6. COMPONENT DETAILS 6.1. All components shall conform to relevant IS/IEC standards and shall be of reputed make.

Makes of all components shall be subject to purchaser’s / consultant’s approval. 6.2. THYRISTORS, DIODES AND TRANSISTORS. The thyristors, diodes and transistors shall have adequate safety margins to withstand

specified operating conditions. A factor of safety of minimum 4 shall be taken against voltage surges.

6.3. PCBs All electronic control & monitoring printed circuit boards shall be fixed type on ceramic insulators to avoid loose contacts due to vibration/long usage. Failure of each PCB shall

be indicated by visual alarm and indication. The visual fault diagnostic shall preferably indicate fault into various sections of the cards. All printed circuit board shall be mounted on fixed ceramic insulator.

Page 129 of 175

Page 131: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-02-006 A

TECHNICAL SPECIFICATION FOR

UPS SYSTEM Page 8 of 13

6.4. ELECTROLYTIC CAPACITORS These may be polarised aluminium type I, suitable for long life and category I, as per IS: 4317 or equivalent IEC. The capacitor shall preferably be self-healing type. These

shall be so located in inverter panels that the operating temperature does not exceed 65oC maximum.

6.5. TRANSFORMERS AND CHOKES All transformers and chokes shall be of dry type and air cooled. This shall be class ’H’

insulated, vacuum impregnated. Class F / Class B insulated cast resin transformers and chokes are also acceptable.

6.6. INSTRUMENTS Ammeters & voltmeters shall be moving coil type of class 1.5 accuracy as per IS: 1248.

These shall be flush mounting type of minimum size of 96 mm x 96 mm. Frequency meter shall be of read type having range of 45 Hz to 55 Hz. Alpha-numeric Liquid Crystal Display for metering various parameters is also acceptable.

6.7. STATIC SWITCHES Static switches shall be naturally commutated type with parallel inverse connected thyristors. These shall be rated for continuous duty for 100% load. Short time rated static switches are not acceptable. 6.8. VOLTAGE STABILIZER Voltage stabilizer shall be static type and shall satisfy the following requirements : i) Maximum output voltage variation under steady state condition shall be ± 2%. ii) Maximum harmonic distortion shall be less than 5%. iii) The output voltage shall be restored within ± 2% of nominal value in less than 2 secs. 6.9. INDICATION LAMPS / LCD DISPLAY

All indication lamps shall be of LED type suitable for the specified control voltage, having minimum illumination of 40 millicandella. The colour of the LEDs shall be as follows :

ON: Red OFF: Green FAULT: Yellow LCD display is acceptable for Audio and visual alarm. 6.10. MCB For isolating devices of various equipment, MCB shall be used. These shall be provided

with overload and short circuit protective devices and shall conform to IS: 2516. Battery Circuit Breaker shall have under voltage trip and reverse polarity protection

Page 130 of 175

Page 132: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-02-006 A

TECHNICAL SPECIFICATION FOR

UPS SYSTEM Page 9 of 13

device. 7. MONITORING SYSTEM 7.1. Microprocessor based monitoring system for UPS to supervise the UPS operation on PC

shall be provided to indicate following data:

i) Output voltage of UPS ii) Battery DC Voltage iii) Input voltage of each rectifier (ph to ph) iv) Input current of each rectifier v) Output current of each inverter vi) Output voltage of each inverter vii) Bypass frequency viii) Output frequency of each inverter

7.2. Print out facility shall be available for all the Alarms and Faults conditions. 8. PAINTING 8.1. The enclosure after pre-treatment, shall be painted with two coats of anti-rust paint

followed by two coats of anticorrosive paint.

8.2. All paints shall be carefully selected to withstand tropical heat and extremes of weather.The paint shall not scale off, crinkle or be removed by abrasion due to normal handling.

8.3. Unless otherwise specified, the finishing shade shall be light grey Shade No. 631 as per

IS:5. 8.4. Electrostatic powder paint shall be preferred. 9. TESTS AND INSPECTION 9.1. The UPS units shall be subjected to test as per relevant standards. The test shall include,

but not limited to the following :

i) Rectifier & inverter soft starting ii) Regulation test

Page 131 of 175

Page 133: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-02-006 A

TECHNICAL SPECIFICATION FOR

UPS SYSTEM Page 10 of 13

iii) Heat run test for 8 hours iv) Overload test v) Test for changeover time in synchronised and desynchronised mode. vi) Test for dynamic response and transient performance vii) Sequence & transfer test viii) Noise level measurement ix) Test to check the selectivity of protective devices x) Alarm test (simulation of various fault conditions) xi) Measurement of harmonic distortion xii) Ventilation test (operation without redundant fan) xiii) Insulation test xiv) Current division in parallel UPS

9.2. All the above tests shall be carried out in presence of purchaser’s representative. In addition, the equipment shall be subjected to stage inspection during process of manufacture at works and site inspection.

9.3. These inspections shall however, not absolve the vendor from his responsibility for

making good any defects, which may be noticed subsequently. 10. DRAWINGS AND DOCUMENT 10.1. Drawings and documents as per Annexure-I shall be supplied. 10.2. All drawings and documents shall have the following description written boldly: -- Name of client -- Name of Consultant -- Order Number Code No. and Description

Page 132 of 175

Page 134: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-02-006 A

TECHNICAL SPECIFICATION FOR

UPS SYSTEM Page 11 of 13

11. SPARES 11.1. Item wise spare parts as listed in MANDATORY SPARE LIST shall be offered along with

main equipment with recommended quantity. 11.2. Any other spare parts required, but not specified, shall also be offered. 12. PACKING 12.1.The board shall be properly packed before dispatch to avoid damage during transport,

storage and handling. 12.2.The packing box shall contain a copy of the installation, operation and maintenance

manual. 12.3. A sign to indicate the upright position of the panels to be placed during transport and

storage shall be clearly marked. Also proper arrangement shall be provided to handle the equipment.

13. DEVIATIONS 13.1. Deviations, if any, from this standard shall be clearly indicated in the offer with reasons

thereof. Deviations from the data indicated in specification shall be shown clearly by encircling it and indicating the revised data in specification.

14. MAKE UPS - HI-REL ELECTRONICS / DB POWER / TATA LIBERT / EMERSON / GUTOR ELECTRONICS Ni-Cd BATTERY - HBL NIFE POWER SYSTEM / AMCO POWER SYSTEM

Page 133 of 175

Page 135: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-02-006 A

TECHNICAL SPECIFICATION FOR

UPS SYSTEM Page 12 of 13

ANNEXURE I

DRAWINGS & DOCUMENTS FOLLOWING DRAWINGS AND DOCUMENTS FOR ALL EQUIPMENT OF UPS SYSTEM SHALL BE SUPPLIED

1. Data sheet

2. Technical Particulars

3. Block Diagram

4. General Arrangement drawings and foundation plan

5. Data sheet for battery & Sizing calculation

6. Feeder Details for Distribution Boards

7. Descriptive literature and catalogues

8. Bill of materials

9. Schematic & Wiring Diagram

10. Installation, operation & maintenance manual

11. Spare parts list with identification

12. Test Certificates

13. Guarantee Certificates

Page 134 of 175

Page 136: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-02-006 A

TECHNICAL SPECIFICATION FOR

UPS SYSTEM Page 13 of 13

ANNEXURE II

METERING INDICATIONS AND ALARM SCHEDULE A. METERING 1. Incoming Voltmeter with selector switches for each incomer

2. Ammeter with selector switches for each incomer

3. Ammeter & Voltmeter at each inverter output and bypass output

4. Frequency meter & power factor meter at one common point of output

5. Ammeter & Voltmeter at incoming of each UPS distribution boards

6. Battery charge / discharge Ammeter

B. LED INDICATION 1. A.C. Mains ‘ON’

2. Load on inverter

3. Battery on float

4. Battery on boost

5. Fault (one lamp for all types of fault)

6. Fan failure indication

C. AUDIO-VISUAL ALARM (with Accept & Reset facilities) 1. Mains failure

2. Inverter output over voltage

3. Inverter output under voltage

4. Inverter temperature high

5. Static switch failure

6. Fan failure

Page 135 of 175

Page 137: City Gas gail Jp Kenny- Wood Group India

Page 136 of 175

Page 138: City Gas gail Jp Kenny- Wood Group India

GAIL GAS LIMITED CITY GAS DISTRIBUTION PROJECT

CLIENT JOB NO 0290 TECHNICAL DATA SHEET FOR UPS TOTAL SHEETS 07

DOCUMENT NO 11 0290 02 10 03 002

0 01/06/10 ISSUED FOR TENDER GK SB HM

A 26/05/10 ISSUED FOR REVIEW GK SB HM

REV DATE DESCRIPTION PREP CHK APPR

Page 137 of 175

Page 139: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-03-002 0

TECHNICAL DATA SHEET FOR UPS

Page 2 of 7

DATA SHEET FOR UPS SYSTEM

PART-1 PURCHASER’S DATA

RATING AND JOB REQUIREMENTS

1.0 GENERAL

1.1 Ref. Standard : Relevant ISS & JPK’s Spec. 2.0 AMBIENT CONDITIONS

2.1 Max. Temp. : 50°C 2.2 Min. Temp. : 4°C 2.3 Design Temp. : 60°C 2.4 Relative Humidity : 100% 2.5 Altitude above MSL : Less than 1000 MTS 2.6 Atmosphere : Dust and Vapour 2.7 Location : Indoor 3.0 TESTS

: Routine Test 4.0 SUPPLY

- UPS have- Rectifier cum Battery charger, - Inverter

- Ni-Cd Battery - Interconnecting cable

5.0 ERECTION, TESTING & COMMISSIONING

- YES 6.0 QUANTITY

- 1 No for each station 7.0 UPS- INPUT

7.1 Rated Voltage : 415V ± 10% 7.2 Rated frequency : 50 Hz ± 5% 7.3 No. of Phase & wire : 3P + 4W 7.4 Earthing mode : Solidly earthed

Page 138 of 175

Page 140: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-03-002 0

TECHNICAL DATA SHEET FOR UPS

Page 3 of 7

7.5 Power factor : 0.7 to 0.8 lagging 8.0 UPS - OUT PUT

8.1 Rated Power : SCADA Vendor to specify 8.2 Voltage : 230V ± 1% 8.3 Wave form : Sinusoidal 8.4 Frequency : 50 Hz ± 0.5% 8.5 No. of phases and wire : 1 Ph. + 2W 8.6 Load Power factor range : 0.8 lag to 1.0 8.7 Total Harmonic distortion : <3%LL,<5%NLL 8.8 Current crest factor : Upto 3 8.9 Unbalanced load : Upto 100% 8.10 Overload capacity : 150% for 1 minute, 125% for 10 minutes 8.11 UPS system overall efficiency: > 85% 9.0 BATTERY : Ni-Cd Battery

10.0 CABLE SIZE

- Main : ** Sq mm YWY (Min.) - Load : ** Sq mm YWY (Min.) - Battery : ** Sq mm YWY (Min.) 11.0 PAINTING TYPE & SHADE

: Epoxy, 631 of IS 5 12.0 SPECIFIC REQUIREMENTS

The UPS system shall be designed as follows:

12.1 Each system includes one rectifier and one inverter .

12.2 MCB will be provided for the battery, MCCB will be provided for UPS inputs & outputs.

12.3 Each UPS system is sized for 100% full load continuously.

12.4 Ni-Cd battery should give 12 hrs. back up to UPS for all stations.

12.5 Contractor shall carry out the full load test of UPS at site.

12.6 Minimum two nos. earthpit shall be provided in one grid to achieve less than 1 ohm resistance.

12.7 ** vendor to check and specify.

Page 139 of 175

Page 141: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-03-002 0

TECHNICAL DATA SHEET FOR UPS

Page 4 of 7

PART-2

TECHNICAL DATA FROM MANUFACTURERS

1.0 STATIC INVERTER : 1.1 APPLICATION : 1.2 TYPE : 1.3 DUTY : 1.4 ENCLOSURE : 1.5 COOLING : 1.6 DESIGN AMBIENT TEMPERATURE : 1.7 INVERTER CAPACITY : 1.8 OVER LOAD CAPACITY : 1.9 POWER WALK IN : 1.10 VOLTAGE : A. INVERTER INPUT (BATTERY OUTPUT) B. NOMINAL OUTPUT 1.11 VOLTAGE REGULATION : A. REGULATION FOR 0-100% LOAD AND : FOR MIN. TO MAX. DC BATTERY VOLTS AND FOR BOTH THE CONDITIONS EXISTING SIMULTANEOUSLY. B. DYNAMIC RESPONSE OR TRANS. : VOLTAGE REGULATION AT 100% STEP LOAD CHANGE (APPLICATION OR REMOVAL). C. DYNAMIC RESPONSE OR TRANSIENT : VOLTAGE REGULATION DURING TRANSFER OF LOAD TO ALTERNATE SOURCE. D. DYNAMIC RESPONSE OR TRANSIENT : VOLTAGE REGULATION DURING TRANSFER OF LOAD TO SYSTEM OUTPUT. E. DYNAMIC RESPONSE OR TRANSIENT : VOLTAGE REGULATION AT ABRUPT + 10% CHANGE OF INPUT VOLTAGE. F. DYNAMIC RESPONSE OR TRANSIENT : VOLTAGE REGULATION AT FAILURE/ RECOVERY OF COMMERCIAL POWER G. TRANSIENT RECOVERY OR RESPONSE : TIME. H. STEADY STATE : (0-100% LOAD AT ALL INPUT VOLTAGES AND ALL POWER FACTORS) I. TRANSIENT VOLTAGE : (ON APPLICATION OR REMOVAL OF 100% LOAD)

Page 140 of 175

Page 142: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-03-002 0

TECHNICAL DATA SHEET FOR UPS

Page 5 of 7

J. TIME TO RECOVER FROM TRANSIENT TO : NORMAL VOLTAGE 1.12 WAVE FORM : A. NOMINAL FREQUENCY : B. FREQUENCY RANGE FOR ALL : CONDITIONS OF INPUT SUPPLIES, LOADS AND TEMP. OCCURING SIMULTAN. OR IN ANY COMBINATION (AUTO CONTROLLED) C. SYNCHRONISTION LIMITS : (FOR MAINTENANCE OF SYNCHRONISM BETWEEN INVERTER AND STANDBY A.C. SOURCE) D. FIELD ADJUSTMENT RANGE FOR (C) : ABOVE. E. TOTAL HARMONIC CONTENT AT 100% : LINEAR LOAD. F. HARMONIC CONTEMT FOR ANY SINGLE HARMONIC I) AT 100% LINEAR LOAD : II) AT 100% NON LINEAR LOAD : G. FREQUENCY ACCURACY FOR INTERNAL : OSCILLATION. H. SLEW RATE : I. OUTPUT VOLTAGE ADJUSTMENT RANGE : AT RATED LOAD 1.13 RATED OUTPUT CURRENT AT RATED OUTPUT VOLTAGE WITH CURRENT LIMIT NOT OPERATING A. CURRENT : B. DURATION : 1.14 EFFICIENCY AT FULL LOAD : (WATT OUTPUT/WATT INPUT) 2.0 STATIC TRANSFER SWITCH ASSEMBLY 2.1 TYPE : 2.2 DUTY : 2.3 ENCLOSURE : 2.4 COOLING : 2.5 AMBIENT TEMPERATURE : 2.6 CAPACITY A. CONTINUOUS : B. OVERLOAD : C. PEAK : 2.7 NORMAL VOLTAGE : 2.8 TRANSIENT VOLTAGE TOLERANCE : 2.9 TRANSFER TIME MILLI SECONDS :

Page 141 of 175

Page 143: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-03-002 0

TECHNICAL DATA SHEET FOR UPS

Page 6 of 7

3.0 AVERAGE SENSE VOLTAGE 3.1 INSTANTANEOUS SENSE VOLTAGE : 3.2 ANTI CYCLING CIRCUIT : 3.3 SYNCHRONOUS DISCONNENT RANGE : 3.4 MANUAL BY-PASS SWITCH : 3.5 TYPE : 3.6 VOLTAGE : 3.7 RATED CURRENT : 4.0 RECTIFIER/BATTERY CHARGER 4.1 CHARGER : 4.2 TYPE : 4.3 DUTY : 4.4 ENCLOSURE : 4.5 COOLING : 4.6 AMBIENT TEMPERATURE : 4.7 A.C. INPUT A. SUPPLY : B. VOLTAGE VARIATION : C. FREQUENCY VARIATION : D. COMBINED VOLT FREQUENCY : VARIATION E. SHORT-CIRCUIT LEVEL : F. SYSTEM EARTHING : 4.8 D.C. OUTPUT : FEATURES PROVIDED A. AUTOMATIC VOLTAGE REGULATION : B. CURRENT LIMITING CIRCUITRY : C. SMOOTHING FILTER CIRCUIT : D. SOFT START FEATURE : E. AUTOMATIC LOAD SHARING DURING : PARALLEL OPERATION F. SCR SURGE PROTECTION AND FAST : ACTING HRC FUSES G. DC EARTH FAULT ALARM : 5.0 ACDB INCOMER MCB (0NE NO.) : CURRENT RATTING : MAKE : VOLTAGE FAULT LEVEL :

Page 142 of 175

Page 144: City Gas gail Jp Kenny- Wood Group India

Document No. Rev

11-0290-02-10-03-002 0

TECHNICAL DATA SHEET FOR UPS

Page 7 of 7

OUTGOING FEEDERS (MCB) : QUANTITY : CURRENT RATING : VOLTAGE : 6.0 BATTERY 6.1 TYPE : 6.2 NO. OF BATTERY SET : 6.3 DC VOLTAGE OF BATTERY SET : 6.4 NOMINAL DISCHARGE VOLTAGE : 6.5 CELL END VOLTAGE AT THE END DUTY : CYCLE 6.6 DUTY CYCLE : 6.7 NUMVER OF CELLS PER BATTERY : 6.8 BATTERY CIRCUIT BREAKER IN : SEPARATE WALL CUBICLES 7.0 SCHEMATIC DIAGRAM OF UPS SYSTEM SHALL BE FURNISHED * * *

Page 143 of 175

Page 145: City Gas gail Jp Kenny- Wood Group India

QUALIFICATION, PROVENNESS REQUIREMENTS & TECHNICAL FORMS 1.0 Section 1

1.1 QUALIFICATION & PROVENNESS REQUIREMENTS 1.1.1 Bidder shall have successfully executed a SCADA system project for hydrocarbon

pipeline(s) / Production! Distribution network with their own SCADA software or SCADA software from their SCADA excellence centre, with turnkey responsibility covering scope from Project Management, Design, Engineering, Procurement, Inspection at works, Supply, Installation, Integration, Testing, Commissioning, Site acceptance testing and Trial run, which has been working satisfactorily for at least 4000 hours.

1.1.2 In case bidder does not have experience of all above mentioned activities from the proposed location, bidder shall involve the services / expertise of their SCADA excellence centre, who is having the field proven experience of having successfully executed similar SCADA projects with activities as mentioned above and the proposed SCADA excellence centre assumes the complete responsibility for the following as a minimum:

a) Supply of SCADA software. b) Approval of QA / QC programs conforming to their own standards for carrying out the activities being proposed to be carried out by the bidder. c) Either carryout system engineering, system integration, testing and factory acceptance of the complete SCADA system or approve design drawings and documents, participate in system integration, testing and factory acceptance with bidder in case bidder is having requisite experience for carrying out any or all such activities. d) Participation in commissioning and site acceptance of complete system. e) Provide logistic support to the bidder. f) Provide performance guarantee of the fully integrated SCADA system. Accordingly the duly signed & stamped ‘Performance Guarantee Certificate’ & ‘Capability Assessment Certificate’ as per the formats enclosed in this MR shall be furnished by the bidder along with their bid.

1.1.3 While submitting their bid, the Bidder shall ensure that the selected APPS sub-vendor shall have executed at least two (2) online Application Software Projects with their own APPS software, having transient modeling enveloping mass balance leak detection for hydrocarbon natural gas and liquid pipelines, either independently or along with a SCADA system supplier, with scope covering design, engineering, integration, testing, supply, installation and commissioning, Site acceptance testing and trial run and have been working satisfactorily for minimum 4000 hours.

1.1.4 All activities / services, equipments, systems, subsystems and software as offered shall be from proven manufacturing facilities / locations from where similar activities, services, equipments, systems! Sub-systems and software have been supplied! performed and have completed 4000 hours of successful continuous operation.

Page 144 of 175

Page 146: City Gas gail Jp Kenny- Wood Group India

1.1.5 Vendor must ensure the following while quoting:

1.1.5.1 The system as offered must meet the provenness requirements specified in the clause 1.1.4.

1.1.5.2 All activities as offered shall be carried out by agency and from the location which meets the provenness requirements specified in clause 1.1.4. 1.1.5.3 In addition to clause no. 1.1.4, all bought-out items shall also meet the following:

a. All bought-out items shall be designed, engineered, manufactured, fully assembled, wired and tested by the manufacturer at their works only. b. All bought out items/sub systems shall be fully tested at a manufacturer’s shop prior to shipment by manufacturer to vendor works for assembly. All such test reports shall be submitted to owner/ WGI for review. c. All such sub-systems shall also be made available during integrated factory acceptance test at vendor’s works. d. For all bought out items (RTU etc.), vendor shall indicate a nominated sub-vendor whose offer shall be evaluated. Vendor shall furnish complete technical details of the same.

1.1.5.4 For the bought out items, in case vendor proposes to carryout activities by any agency other than the manufacturer then the following requirements shall be complied by the vendor: - a) The manufacturer of the item / subsystem must furnish a certificate for owning full responsibility of the overall system and its performance. b) The agency and activity location must meet the requirements specified in pare 1.1 .5.2 above. The information must be filled up in the PTR format enclosed along with. C) The manufacturer must approve all documents including software documents generated by the agency (if other than manufacturer). d) The manufacturer’s qualified, competent and regular employee must be present during all technical meetings, system integration, factory acceptance test, system start-up & commissioning and site acceptance testing.

1.1.6 CERTIFICATE FOR LOGISTIC SUPPORT 1.1.6.1 Vendor shall furnish a certificate for providing necessary support services. The

certificate shall be as per the format enclosed in this document and shall be duly signed by them and their principal(s).The formats enclosed shall be complete as follows:

PERFORMA III:- To be completed and signed by vendors principal’s corporate level

signatory. For vendors who have their controlling business group corporate office overseas, it must be completed and signed by their overseas corporate official only.

PERFORMA IV:- To be completed and signed by vendors’ corporate level signatory.

Page 145 of 175

Page 147: City Gas gail Jp Kenny- Wood Group India

PERFORMA V:- To be completed and signed by the corporate level signatory of the bought out items like RTU etc. Vendors who have their controlling business group corporate office overseas, it must be completed and signed by their overseas corporate office only. 1.1.6.2 Proposals received without the certificate, or with unsigned / unstamped certificate, or matter with revised text, or certificate not on company’s letterhead shall not be considered for further evaluation.

1.1.6.3 Certificate from sub vendors for systems such as APPS system, RTU, etc. shall also be furnished .The certificates issued by the local agents shall not be acceptable.

1.1.7 Bidder shall submit Documentary evidence along with their bid against above mentioned qualification & provenness requirements.

1.1.8 GGL/WGI reserves the right to verify the correctness of documentary evidence

furnished in the offer.

1.1.9 GGLIWGI reserves the right to qualify the Bidder, APPS sub-vendor for fulfillment of the qualification & provenness requirements utilizing in-house data.

1.1.10 GGL/WGI reserves the right to assess the capability and capacity of Bidder, sub-vendor. GGL/WGI reserves the right to verify the successful operation and performance of reference projects. Bidder shall arrange permissions for visiting these installations, if required.

1.2 BID OUTLINE REQUIREMENTS Bidder is required to mandatorily make a proposal in a format as outlined below in order to achieve the objective of maintaining uniform proposal structure.

TECHNICAL PROPOSAL COVERING LETTER & SYNOPSIS OF THE PROPOSAL CHAPTER I : COMPOSITION OF THE BID This chapter is to describe the various parties who have been involved to bid for this project clearly defining the Bidder and sub-vendor. In addition the project organization structure putting together various parties together with inter-relationship shall also be submitted along with Project Management & Responsibility (PMR) form duly filled in. No. of personnel and their Resume in the related areas and the organizational structure of the various parties shall also be attached.

CHAPTER II: PROVENNESS REQUIREMENTS In this section Bidder is required to fill PTR form, Certificates for Logistic Support, Performance Guarantee Certificates, Capability Assessment Certificate [attached in Section -2] and submit all the supporting documents.

Page 146 of 175

Page 148: City Gas gail Jp Kenny- Wood Group India

CHAPTER III: TECHNICAL FORMS Bidder is required to complete PTR form along with all supporting documents, ROC (Responsive Offer Criteria) Form, SST (SCADA system technical) Form, SOS (Source Of Supply) Form, Deviation Form (Form H -Technical) [attached in Section - 2] and PCUR (Power Consumption & UPS Requirements), VACR (Ventilation and Air Conditioning Requirements) forms [Annexure A & B].

CHAPTER IV : SYSTEM GENERAL TECHNICAL REQUIREMENTS

CHAPTER V : SYSTEM CONFIGURATION, HARDWARE AND SOFTWARE DETAILS

CHAPTER VI : RTUs HARDWARE AND SOFTWARE DETAILS CHAPTER VII : COMMUNICATION AND CHANNELING PLAN REQUIREMENTS, POLL TIME, UPDATION TIME AND AVAILABILITY CALCULATIONS

CHAPTER VIII : HMI WITH DETAILS OF GRAPHICAL DISPLAYS PACKAGE & REPORT PACKAGE

CHAPTER IX : APPLICATION SOFTWARE, SCADA INTERFACING

CHAPTER X : INSTALLATION AND COMMISSIONING

CHAPTER XI : FACTORY ACCEPTANCE TEST, SITE ACCEPTANCE TEST, TRIAL RUN

CHAPTER XII : PROJECT EXECUTION AND BAR CHART ACTIVITY SCHEDULE

CHAPTER XIII : DOCUMENTATION

CHAPTER XIV : WARRANTY

CHAPTER XV : TRAINING

CHAPTER XVI : TEST INSTRUMENTS

CHAPTER XVII : POST WARRANTY MAINTENANCE CONTRACT

CHAPTER XVIII : BIDDER’S PROFILE PAMPHLETS

CHAPTER XIX : TECHNICAL BROCHURES FOR SERVERS, HMI, WORKSTATIONS,

REMOTE WORKSTATIONS, ROUTERS, LAN DEVICES, PERIPHERALS, RTUs, SCADA SOFTWARE, APPLICATION SOFTWARE, WEB SERVER SYSTEM, OPC SERVER ETC.

Page 147 of 175

Page 149: City Gas gail Jp Kenny- Wood Group India

1.3 The scope of supply, works, responsibilities, qualification requirements, provenness requirements, functional & operational requirements, technical specifications and SCADA system execution requirements are explicitly stated in the Tender. Bidder is required to study these requirements in detail and make a proposal in an outline as defined above, completely meeting these requirements.

1.3.1 Bidder shall be fully responsible for all the activities for design, engineering, supply, factory testing, integration, installation, commissioning, site acceptance testing, Trial run, warranty, training and documentation of integrated SCADA system, with Bidder having single point responsibility for successful implementation of integrated SCADA system.

1.3.2 The responsiveness of the bid shall be ascertained through compliance in the Responsive Offer Criteria [ROC] form with bid having incomplete scope of supply & works and! or which does not comply with the technical requirements shall be considered as substantially non-responsive. The bid determined as substantially non- responsive is liable to be rejected by the WGI / GGL without any reference to the bidder and may not be subsequently made responsive by the Bidder by correction of the non-conformity. The decision of the WGI / GGL in this regard shall be final.

1.3.3 Bidder is required to mandatorily make a proposal in a format as outlined in cI. 1.2 above and further it is in the interest of Bidder to submit complete and comprehensive proposal leaving no scope for the WGI / GGL to raise any further questionnaires as the proposal may only be evaluated on the basis of what has been submitted by the bidder at the first instance in order to adhere with very strict project schedule requirements.

Page 148 of 175

Page 150: City Gas gail Jp Kenny- Wood Group India

2.0 Section 2

PERFORMA - I

Technical Checklists Have you filled up the following formats, which form a part of technical checklist and un-priced bid?

Sl. No. Checklist point Yes/No

1. Performa – II. (Technical Questionnaire )

2. Performa –III ( Certificate of logistics support)

3. Performa –IV ( Certificate of logistics support)

4. Performa –V ( Certificate of logistics support)

5. Performa-VI (Performance Guarantee Certificate)

6. Performa – VII (Capability Assessment Certificate)

7. Performa –VIII ( Proven track record) (PTR)

8. Performa –IX (Project management responsibility ) (PMR)

9. Performa – X (Responsive Offer Criteria (ROC) )

10. Performa – XI (Source of Supply (SOS) )

11. Performa – XII (SCADA System Technical (SST))

12. Performa - XIII (Deviation Form)

13. Performa – XIV (Vendor data requirement)

Page 149 of 175

Page 151: City Gas gail Jp Kenny- Wood Group India

PERFORMA - II.

TECHNICAL QUESTIONAIRE This questionnaire shall be dully filled in and submitted along with un-priced sets of offers to avoid further queries and to ensure proper evaluation of your offer in time. If this is not complied with your offer is liable to be rejected.

Sl. No.

DESCRIPTION BIDDER’S RESPONSE.

1. Have you filled up ‘NO DEVIATION FORM ‘and submitted the same?

2. Have you filled and submitted ‘PROVEN TRACK RECORD (PTR) FORM’?

3. Have you filled and submitted ‘SOURCE OF SUPPLY FORM’? All major equipments have to be supplied from sub vendor’s given in MR

4. Have you provided list of 2 years spares for operation and maintenance along with unit rates?

5. Have you provided list of commissioning spares?

6 Have you provided list of mandatory spares along with detailed basis of quantities arrived at?

7 Have you enclosed the catalogs/literature in ENGLISH language including model decoding details, drawing etc necessary for evaluation of your offer?

8. Have you confirmed that documents required as per vendor data requirement will be supplied after placement of order?

9 Have you furnished ‘LOGISTIC SUPPORT CERTIFICATE’ and ‘PERFORMANCE GUARENTEE CERTIFICATE’?

Signature of bidder with stamp

Page 150 of 175

Page 152: City Gas gail Jp Kenny- Wood Group India

PERFORMA - III.

CERTIFICATE FOR LOGISTIC SUPPORT (TO BE SIGNED BY VENDOR’S PRINCIPAL CORPORATE LEVEL SIGNATORY ON COMPANY LETTERHEAD)

I, ON BEHALF OF M/s______________ CONFIRM THAT THE SCADA SYSTEM QUOTED BY MIs_______________ FOR GAIL GAS LIMITED PROJECT AGAINST MATERIAL REQUISITION 110290/WGI/GAIL GAS/21-R0 SHALL CONTINUED TO BE SUPPORTED BY US AND QUOTED SYSTEM SHALL NOT BE WITHDRAWN FROM “INDIAN” MARKET AS A MATTER OF CORPORATE POLICY.

I, FURTHER CONFIRM THAT IN CASE OF PLACEMENT OF ORDER BY M/S BCPL ON MIs_________________ MIS BCPL SHALL BE SUPPORTED IN PROVIDING BACK-UP ENGINEERING, MAINTENANCE SUPPORT, AND SPARE PART SUPPORT FOR A PERIOD OF NOT LESS THAN TEN (10) YEARS FROM THE DATE OF PLACEMENT OF ORDER.

(SIGNATURE WITH SEAL)

Page 151 of 175

Page 153: City Gas gail Jp Kenny- Wood Group India

PERFORMA - IV

CERTIFICATE FOR LOGISTIC SUPPORT (TO BE SIGNED BY VENDORS CORPORATE LEVEL SIGNATORY ON COMPANY LETTERHEAD)

I, ON BEHALF OF M/s______________ CONFIRM THAT THE SCADA & APPS SYSTEM QUOTED BY US FOR GAIL GAS LIMITED PROJECT, AGAINST MATERIAL REQUISITION 110290/WGI/GAIL GAS/21-R0 SHALL CONTINUE TO BE SUPPORTED BY US AND OUR PRINCIPAL M/S________________

I, FURTHER CONFIRM THAT IN CASE OF PLACEMENT OF ORDER BY M/S BCPLON US WE SHALL CONTINUE TO SUPPORT M/S BCPL IN PROVIDING BACK-UP ENGINEERING, MAINTENANCE SUPPORT, AND SPARE PART SUPPORT TO BCPL FOR A PERIOD OF NOT LESS THAN TEN (10) YEARS FROM THE DATE OF PLACEMENT OF ORDER.

(SIGNATURE WITH SEAL)

Page 152 of 175

Page 154: City Gas gail Jp Kenny- Wood Group India

PERFORMA - V

CERTIFICATE FOR LOGISTIC SUPPORT (TO BE SIGNED BY VENDOR’S CORPORATE LEVEL SIGNATORY ON COMPANY LETTERHEAD)

Applicable for all major sub-systems bought-out by the vendor (See Note)

I, ON BEHALF OF M/s_________________________ CONFIRM THAT THE ____________________QUOTED BY US THROUGH M/S _________________FOR GAIL GAS LIMITED PROJECT, AGAINST MATERIAL REQUISITION 110290/WGI/GAIL GAS/21-R0 SHALL CONTINUE TO BE SUPPORTED BY US AND OUR PRINCIPAL M/S________________

I, FURTHER CONFIRM THAT IN CASE OF PLACEMENT OF ORDER BY M/S BCPL ON MIS____________________ WE SHALL CONTINUE TO SUPPORT M/S BCPL IN PROVIDING BACK-UP ENGINEERING, MAINTENANCE SUPPORT, AND SPARE PART SUPPORT FOR A PERIOD OF NOT LESS THAN TEN (10) YEARS FROM THE DATE OF PLACEMENT OF ORDER.

(SIGNATURE WITH SEAL)

Note: This form has to be filled separately by the sub vendor for major sub-systems.

Page 153 of 175

Page 155: City Gas gail Jp Kenny- Wood Group India

PERFORMA - VI PERFORMANCE GUARANTEE CERTIFICATE

[To be signed by Principal’s (SCADA excellence centre) corporate level signatory on company’s letterhead]

I,_____________________on behalf of M/s. ______________________________, certify that in the event of placement of order for__________________ SCADA system by GAIL GAS LIMITED on M/s______________________

a) The complete SCADA system software with its performance certificate shall be supplied by us.

b) We shall carryout system engineering, system integration, testing and factory acceptance of the complete SCADA system [OR] We shall approve design drawings and documents prepared by M/s. , participate in system integration, testing and factory acceptance with M/s.____________________

c) M/s. ________________________, shall stand guarantee for the performance of the complete SCADA system at site.

d) Our involvement shall be ensured during commissioning and site acceptance of complete system.

e) We shall provide all required logistic support to M/s.___________________

f) With the methodology proposed herein, we M/s ____________________ shall stand guarantee for the fully integrated SCADA system as per the specified performance specifications.

SIGNATURE WITH SEAL AUTHORIZED, SENIOR MANAGEMENT LEVEL SIGNATORY Note: 1. For b) tick, whichever clause is applicable considering experience of the bidder 2. For c), Principal to write their name.

Page 154 of 175

Page 156: City Gas gail Jp Kenny- Wood Group India

PERFORMA - VII

CAPABILITY ASSESSMENT CERTIFICATE (To be signed by Principal corporate level signatory on company’s letterhead)

I,_______________________ on behalf of M/s._______________________ certify that we have evaluated the facilities available with M/s.___________________ and approve them for carrying out the following activities: System Engineering System Assembly Component Procurement System Integration System Testing System Installation System Commissioning (Tick which one is applicable) We also confirm that QA/QC procedure being followed by M/s._______________ at their works is similar to those being followed by us at our works.

SIGNATURE WITH SEAL AUTHORIZED, SENIOR MANAGEMENT LEVEL SIGNATORY

Page 155 of 175

Page 157: City Gas gail Jp Kenny- Wood Group India

PERFORMA - VIII

PROVEN TRACK RECORD (PTR) FORM A)

1. Name and address of Bidder Tel. No., Fax no., E-Mail & Website address (Works location & address)

2. Name and address of SCADA excellence centre (as applicable) Tel. No., Fax no., E-Mail & Website address (Works location & address)

3.

a. Area of operation of Bidder b. Area of operation of SCADA excellence centre c. Bidder is an Indian subsidiary of the SCADA excellence centre as above (yes / no) d. SCADA excellence centre is supplier of SCADA systems with his own SCADA software (yes / no) e. SCADA excellence centre’s own SCADA software based system offered for this project. (Yes / no)

B) Details of SCADA projects as executed by the Bidder / SCADA excellence centre (as applicable) BID QUALIFICATION CRITERIA (BQC) FORM

S.N Details

As offered for this project

Reference Project

1.0 Project Name & Description

1.1 Details of the application

1.2 a)

Nature of project (hydrocarbon pipeline(s) / Production/ Distribution network)

b) Project details (Length of pipeline / network, No. of pump stations , compressor stations

1.3 No. of RTUs

1.4 Make/Title of SCADA software implemented

2.0 Name of owner of the project

Page 156 of 175

Page 158: City Gas gail Jp Kenny- Wood Group India

2.1 Name & address of owner’s contact person

2.2 Telephone, FAX No., E-mail of owners contact person

3.0 Date of complete system successful commissioning (dd/m m/yyyy)

3.2 Whether the system has been satisfactorily working for at least 4000 hours before the bid closing date [yes/no]

3.3 a) Documentary evidence furnished [yes/no] b) Fill reference of the document support i.e. type of document/ No./ Date etc.

4.0 Scope of responsibility of the Bidder: The above referred project have been executed by the Bidder with the following activities carried out by bidder

Project Management [yes/no]

Design [yes/no]

Engineering [yes/no]

Integration [yes/no]

Testing [yes/no]

Supply [yes/no]

Installation & commissioning [yes/no]

SAT & Trial run [yes/no]

5.0

Scope of responsibility of the SCADA excellence centre (as applicable): The above referred projects have been executed by the SCADA excellence centre with the following scope

Job executed with turnkey responsibility of his own by the SCADA excellence centre [yes/no]

Project Management [yes/no]

Design [yes/no]

Engineering [yes/no]

Integration [yes/no]

Testing [yes/no]

Supply [yes/no]

Page 157 of 175

Page 159: City Gas gail Jp Kenny- Wood Group India

Installation & commissioning [yes/no]

SAT & Trial run [yes/no]

C) Details of SCADA software provenness

S.N Details

As offered for this project

Reference Project

1.0 Project Name & Description

1.1 Details of the application

1.2 No. of RTUs

1.3 Make / Title of SCADA software implemented

1.4 Operating system title for SCADA servers

1.5 Make/ model no. for SCADA servers for these implemented projects

1.6 Whether similar SCADA software offered for this pipeline project (Yes / No)

2.0 Name of owner

2.1 Name & address of owner’s contact person

2.2 Telephone, FAX No., E-mail of owners contact person

3.0 Date of system successful commissioning (dd / mm / yyyy)

3.1 Location from where following SCADA services were carried out for the above project.

(a) System Design

(b) Engineering

(c) Factory Acceptance Testing

3.2

Location from where systems design, engineering and factory acceptance testing for SCADA are proposed to be carried out for this project.

Page 158 of 175

Page 160: City Gas gail Jp Kenny- Wood Group India

3.3

Whether the SCADA software, as offered is from manufacturing facilities! locations from where similar SCADA software has been supplied and have completed 4000 hours of successful continuous operation [yes/no]

4.0 a) Documentary evidence furnished [yes/no] b) Fill reference of the document i.e. type of document, No., Date etc.

D) Details of RTUs provenness

S.N . Details

As offered for this project

Reference Project

1.0 Project Name & Description

1.1 Details of the application

1.2 No. of RTUs

1.3 Make and Model no. of RTUs implemented

1.4 Whether similar RTUs offered for this pipeline project (Yes/No)

2.0 Name of owner

2.1 Name & address of owner’s contact person

2.2 Telephone, FAX No., E-mail of owners contact person

3.0 Date of system successful commissioning (dd / mm / yyyy)

3.1

Whether the RTUs, as offered are from manufacturing facilities! locations from where similar RTUs have been supplied and have completed 4000 hours of successful continuous operation [yes/no]

3.2 a) Documentary support furnished [yes/no] b) Fill reference of the documentary support i.e. type of document! No.! Date etc.

Signature of the Authorized signatory, Stamp and Date

Bidder

Page 159 of 175

Page 161: City Gas gail Jp Kenny- Wood Group India

PERFORMA - IX

PROJECT MANAGEMENT AND RESPONSIBILITY (PMR) FORM

Name of SCADA vendor (Bidder & Principal (SCADA excellence centre)):

SCADA vendor’s works with location:

Activity / project responsibility

Performed by SCADA vendor (Bidder / Principal) [Yes / no] [Note-I]

Single source responsibility with performance guarantee for successful execution of the project

Yes

Project management Yes

Project basic engineering activities including design Yes (P)

Application software design & engineering Yes

Development & implementation of SCADA interface Yes

Detailed system engineering Yes (P)

Integration of SCADA & application software Yes

Documentation for:

i) SCADA documents Yes

iii) FAT & SAT documents Yes (P)

iv) Detailed engineering drawings and documents. Yes (P)

v) Construction drawings & documents Yes

Factory acceptance testing of integrated SCADA system including RTUs

Yes (P)

Installation & commissioning for the system at various locations

Yes (P)

Site acceptance testing & Trial run Yes (P)

Page 160 of 175

Page 162: City Gas gail Jp Kenny- Wood Group India

Warranty Yes (P)

Training Yes (P)

Notes:

1. In case bidder is a subsidiary of SCADA system Principal (SCADA excellence centre), bidder shall fill the split of responsibilities for the above activities between bidder & his principal in line with the proven capabilities of bidder. 2. For the activity performed by the SCADA vendor (Bidder / Principal) the same is differentiated by letter ‘P against the party who is primarily responsible for the same. Additionally split between principal & bidder to be differentiated by letter ‘PP or ‘BP’ against the party who is primarily responsible for the same.

Signature of the Authorized signatory, Stamp and Date

Bidder

Page 161 of 175

Page 163: City Gas gail Jp Kenny- Wood Group India

PERFORMA - X

RESPONSIVE OFFER CRITERIA (ROC) FORM Column to be tilled [yes/ no] 1.0 Scope of supply and works as per the Tender complied with :

2.0 SCADA System configuration and networking as per the Tender complied with:

3.0 The requirements & completeness of Bill of material complied with:

4.0 Confirm that all deviations from all the sections of the Tender are only listed in deviation form (Form H- Technical) and all remaining clauses of the Tender are deemed to be fully complied with All the forms have been furnished in the offer and are duly filled, stamped and signed

5.0 by authorized representatives of SCADA vendor at the required places

Signature of the Authorized signatory, Stamp and Date

Bidder

Name of the Authorized signatory Stamp & Date

Note: - These confirmations by the SCADA vendor need to be categorical with no conditions! no further reference to be made to the technical offer sections.

Page 162 of 175

Page 164: City Gas gail Jp Kenny- Wood Group India

PERFORMA - XI

SOURCE OF SUPPLY FORM (SOS) FORM Indicate for each Item: Model No.; Name of supplier; Place of manufacturing and supply A SCADA System

1. SCADA Servers with peripherals & storage devices and colour monitors 2. HMI workstations with peripherals & storage devices and colour monitors 3. Large Screen LCD colour monitor 4. SCADA Engineering cum HMI workstation with peripherals, storage devices and colour monitor 5. Data Concentrator 6. System software 7. Ethernet switches 8. B/W Laser jet printers 9. Colour Laser jet printer 10. WAN routers 11. GPS time server 12. Firewall router 13. Web security appliance and web security software 14. Antivirus Software 15. System cabinet & Power distribution cabinet 16. Console desks & Desks with executive chairs at MCC, SMCC & CCCs

B RTUs 1. Complete RTUs with cabinets for all City Gate Stations (CGS) locations 2. Complete RTUs with cabinets for all Online CNG station locations 3. Complete RTUs with cabinets for all Daughter CNG station locations

C SCADA Software

D a) Surge Protection devices (lightening)

b) Isolating barriers

E Test equipments 1. Portable Diagnostic test units 2. Portable Plant simulators 3. Digital Multi-meters

F Miscellaneous items (SCADA vendor to specify all the remaining items e.g. GPRS cards etc..)

SCADA vendor Signature of the authorized signatory

Name of the authorized signatory Stamp & Date

Page 163 of 175

Page 165: City Gas gail Jp Kenny- Wood Group India

PERFORMA - XII

SCADA SYSTEM TECHNICAL (SST) FORM

A. SCADA SYSTEM 1.0 Computer Systems at MCC & SMCC 1.1. Two SCADA Servers included [yes/no] 1.2. Large Screen 60” LCD for MCC included [Yes/No] 1.3. HMI workstations as per the requirements included [yes/no]

2.0 Make / Model of the SCADA SERVER systems

2.1. SCADA SERVERS

Specification SCADA servers OFFERED SCADA SERVER

Make COMPAQ / HP / SUN / IBM / DELL

Processor For Windows: Quad Core Intel Xeon 2.93 GHz (dual processor). For UNIX: 64 bits RISC based high performance processor (Min. 4)

L2 External CPU Cache

512 KB

Shared L3 cache 2 MB

RAM (ECC SDRAM / RDRAM)

8 GB

PCI Slots Min. 5

Hot pluggable bays 6

Hard disk controller Dual channel ultra wide SAS

Hard Disk Drives 6 X 146 GB Ultra-320 Hot pluggable SAS, OEM Make

DVD+/- RW Drive with drivers

Double Layer SuperMulti (SATA)

Internal DAT DDS-4 (20/40 GB)

Graphic sub system with driver s/w

PCI VGA with 32 MB RAM

LCD color monitor 19”

Network card with teaming facility

32 bit PCI Redundant ETHERNET Controller ( 100 / 1000 Mbps)

Mouse 2/3 button Infrared

Keyboard 104 Keys

Power supply Redundant hot pluggable

Power fail protect Y

Page 164 of 175

Page 166: City Gas gail Jp Kenny- Wood Group India

and auto restart

Fan Redundant

Serial port 2

Parallel port 1

USB port 4

OS software Windows 2008 (Enterprise Server) or latest / Solaris 10 or latest

2.2. WEB servers

Specification Web Server OFFERED WEB SERVER

Make COMPAQ / HP / IBM / DELL

Processor Quad Core Intel Xeon 2.93 GHz

L2 External CPU Cache

512 KB

Shared L3 cache 2 MB

RAM (ECC SDRAM / RDRAM)

4 GB

PCI Slots Min. 2

Hot pluggable bays 0

Hard disk controller Dual channel ultra wide SAS

Hard Disk Drives 2 X 146 GB SAS

DVD+/- RW Drive with drivers

Double Layer SuperMulti (SATA)

Internal DAT DDS-4 (20/40 GB)

Graphic sub system with driver s/w

PCI VGA with 32 MB RAM

LCD color monitor NA

Network card with teaming facility

32 bit PCI Redundant ETHERNET Controller ( 100 / 1000 Mbps)

Mouse 2/3 button Infrared

Keyboard 104 Keys

Power supply Redundant hot pluggable

Power fail protect and auto restart

Y

Fan Redundant

Serial port 2

Parallel port 1

USB port 4

OS software Windows XP Professional or latest

Page 165 of 175

Page 167: City Gas gail Jp Kenny- Wood Group India

2.3. MAKE/MODEL OF THE HMI WORKSTATION, HMI CUM ENGINEERING WORKSTATION, HMI SCADA SERVER

Specification HMIs OFFERED HMI

Make COMPAQ / HP / IBM / DELL

Processor Quad Core Intel Xeon 2.93 GHz

L2 External CPU Cache 512 KB

Shared L3 cache 2 MB

RAM (ECC SDRAM / RDRAM)

4 GB

PCI Slots Min. 2

Hot pluggable bays 2

Hard disk controller Dual channel ultra wide SAS

Hard Disk Drives 2 X 146 GB Ultra-320 Hot pluggable SAS, OEM Make

DVD+/- RW Drive with drivers

Double Layer SuperMulti (SATA)

Internal DAT DDS-4 (20/40 GB)

Graphic sub system with driver s/w

PCI VGA with 32 MB RAM

LCD color monitor 21”

Network card with teaming facility

32 bit PCI Redundant ETHERNET Controller ( 100 / 1000 Mbps)

Mouse 2/3 button Infrared

Keyboard 104 Keys

Power supply Redundant hot pluggable

Power fail protect and auto restart

Y

Fan Redundant

Serial port 2

Parallel port 1

USB port 4

OS software Windows XP Professional or latest

Page 166 of 175

Page 168: City Gas gail Jp Kenny- Wood Group India

To be tilled 2.4. Single 21” TFT LCD Monitor for Engineering cum HMI workstation in MCC & SMCC rooms included [yes/no] 2.5. 21” TFT LCD Monitors for each Operator workstations included [yes/no] a) Graphic resolution (1280 x 1024) [yes/no] b) Functional and alphanumeric keyboards as per spec. [Yes/no] c) Mouse as per spec. [Yes/no] d) Required no. of ports and LAN interface cards (10/100 Mbps) with each HMI workstation [yes/no] e) Interchangeability of two HMI workstations wrt SCADA functionality [yes/no]

3.0 System Architecture as per specifications [yes/no] 3.1. System availability (99.98%) 3.2. Applicable standard for LAN 3.3. Dual redundant LAN [Yes/No] 3.4. System configured in dual hot standby mode for MCC & SMCC (Yes/No) 3.5. The switchover time between active and standby SCADA workstations at MCC & SMCC within 1 minute and switchover without any loss of data & control and without any effect on SCADA functionality [yes/no] 3.6. Complete database synchronization between active and standby SCADA servers at MCC automatically [yes/no] 3.7. System redundancy switchover & backup requirements as per MR complied [yes/no] 3.8. Complete database synchronization between active and standby SCADA servers at MCC and SMCC automatically [yes/no] 3.9. Complete database synchronization between active and standby Data Concentrators at CCC automatically [yes/no]

4.0 The poll time with all I/O parameters of all RTUs of Gail Gas Limited including time for scanning, polling, processing and updation on database [5 seconds] 4.1. System database I/O capacity as per spec. [Yes/no] 4.2. System HMI capacity as per spec. [Yes/no] 4.3. System expandability to take care of future expansion as per Tender confirmed [yes/no]

5.0 Percentage utilization for SCADA Server 5.1. Average CPU utilization (50%) 5.2. Average Main memory utilization. (50%) 5.3. Disc utilization (Max. 50%)

6.0 Percentage utilization for HMI workstations 6.1. Average CPU utilization (50%) 6.2. Average Main memory utilization (50%) 6.3. Disc utilization (Max. 50%)

7.0 a) Updation time of any graphic display on color HMI of MCC & SMCC [less than 5 sec.]

Page 167 of 175

Page 169: City Gas gail Jp Kenny- Wood Group India

b) Callup time of any graphic display on color HMI of MCC & SMCC [less than 5 sec.] c) Callup & Updation time of any graphic display on color HMI of CCC workstation [less than 10 sec.] To be tilled

8.0 Title and version for SCADA SIW

8.1. Type of operating system (indicate separately for SCADA servers, SCADA HMI, Operator workstations and web server. 8.2. Database access through SQL supported by SCADA database management system [yes/no] 8.3. Time synchronization of all the nodes on dual LAN at the MCC & SMCC and between RTUs and MCC & SMCC as per specifications [yes/no]

9.0 Printers as per spec. [Yes/no]

10.0 GPS time server as per spec. [Yes/no]

11.0 a) SCADA scan tasks / RTU polling software are integral part of SCADA software running in main SCADA servers (yes/no) b) Ethernet connectivity for RTUs and Operator Workstations as per MR complied (yes/ no)

12.0 WAN routers as per spec. (Yes/no)

13.0 Dedicated firewall WAN router as per spec. (Yes/no)

14.0 Web server as per spec. (Yes/no)

15.0 Web security appliance and software as per spec. (Yes/ no)

B RTUs 1.0 All RTUs for Gail Gas Limited project to be same make & model no., differing only in RTU I/O cards or serial interfacing [yes/no] 1.1. Make/Model No. of RTUs 1.2. Microprocessor type 1.3. Word length (32 bits for CPU processing) 1.4. a) Two Ethernet ports for providing RTU Ports A & B separately [yes/no] b) Communication cards model no. c) Redundant Processor card & Redundant Power supply card [yes/no]

Page 168 of 175

Page 170: City Gas gail Jp Kenny- Wood Group India

1.5. a) RTU max. I/O cards capacity b) The I/O cards not to be combined for functionalities i.e. each card to perform dedicated functionality wrt Analog input, Analog output, Digital Input, Digital output, [yes/no]

1.6. No. of Al points per card a) Limited to Mm 16 - Max.32 points per card [yes/no] b) Max. No. of Al boards per RTU c) AID converter resolution (mm. 12 bits) d) Accuracy (± 0.1% of range)

1.6. No. of AO points per card a) Limited to Mm 4 - Max.16 points per card [yes/no] b) Max. No. of AO boards per RTU c) Accuracy (± 0.1% of range)

1.7. No. of Dl points per card a) To be limited to 32 Dl per card [yes/no] b) Max. No. of Dl cards per RTU c) Flexibility of mixing NO/NC contacts in same board (Yes/No)

1.8. No. of DO points per card a) To be limited to 16 DO per card [yes/no] b) Max. No. of DO cards per RTU c) Potential free contact rating of output interposing relay for each DO point 48 V DC, 2A; 230 VAC, 5 A)

To be tilled

1.9. RTU Engineering Features: a) Time tagging at RTU Level for analog and digital inputs (Yes/No) b) Self Diagnostic of the RTU up to card level and diagnostic reporting to MCC, SMCC & CCC complied (Yes/No) c) Select check back execute and time out feature complied [yes/no] d) Interfacing with Instrumentation PLC based system as per specifications complied [yes/no] e) High/Low limit checking for analog inputs in RTU at RTU level or SCADA host level (RTU level/SCADA Host level) f) Engineering Unit conversion for analog inputs at RTU level or SCADA host level (RTU level/SCADA Host level)

1.10. IP55 cabinet/enclosure for RTUs complied [yes/no] 1.11. Supportability of portable programmable diagnostic test [PDT] unit with each RTU [yes/no] 1.12. No. of serial ports supported by various RTUs are as per Tender [yes/no] 1.13. Communication protocol between Master station and RTUs [IEC 870-5-iO4

Page 169 of 175

Page 171: City Gas gail Jp Kenny- Wood Group India

or DNP 3.0 over Ethernet]

SCADA vendor

Signature of the authorized signatory

Name of the authorized signatory Stamp & Date

Page 170 of 175

Page 172: City Gas gail Jp Kenny- Wood Group India

PERFORMA - XIII

DEVIATION FORM (FORM H -Technical)

Name of SCADA vendor: Schedule of Deviations in reference to the Tender for SCADA. 1. SCADA vendor may give here a consolidated list of technical deviations for all sections of the MR, which for an appropriate offer is considered unavoidable by him. 2. Deviations mentioned elsewhere in the offer shall not be taken cognizance by the WGI / GGL and any such deviations if indicated elsewhere other than this form will render the offer non-responsive and shall liable to be rejected. 3. SCADA vendor shall state the reasons for the deviations in the ‘Remark column. 4. All other clauses of the Tender (not mentioned in this form) shall be deemed to be fully complied by the SCADA vendor. 5. Only the deviations listed herein, in conjunction with the Tender Package, shall constitute the contract requirements for the award of job to the SCADA vendor.

Page 171 of 175

Page 173: City Gas gail Jp Kenny- Wood Group India

PERFORMA - XIV

VENDOR DATA REQUIREMENT

After Purchase order

Sr.no.

Description Prints with

Quote Prints Date needed

Final documentation/

as built

1 System descriptions including configuration diagram , loop protection schemes , proposed channeling plan , power consumption detail per unit per station

4

2 Technical manuals of each type of equipments

4 5W

3 Functional design specifications for each system i.e. detailed system design, system descriptions with drawings, equipment schedule, power requirements, system availability, rack layout for each station.

4* 6W 4+2S

4 Equipment layout for each station

4* 8W 4+2S

5 Power supply distribution, earthing arrangement for each station.

4 8W 4+2S

6 Site acceptance testing procedure

4* 16W 4+2S

7 Maintenance manual comprising of preventive maintenance, trouble shooting procedure including failure analysis.

10W

8 Station folder, Maintenance folder, Station Inventory folder.

#

9 Factory acceptance testing procedure.

12 W

10 Mandatory spares & 4 #

Page 172 of 175

Page 174: City Gas gail Jp Kenny- Wood Group India

recommended spares for 2 years operation.

11 Certificates from statutory bodies for ex-proof equipment.

4 6W

# - Details of Schedule in the Annexure given above may be submitted in weeks.

(Signature and stamp of Bidder) NOTES: 1. FOLD ALL DRAWINGS TO 216mm x 279mm AND ROLL TRANSPARENCIES. 2. VENDOR TO PROVIDE ALL TRANSPERANCIES AND PRINTED MATTER TO WGI. ATTENTION – PROJECT DEPARTMENT. LEGEND: CATEGORIES PRECEEDED WITH ‘*’ WILL BE APPROVED FOR FABRICATION BY WGI. THE REMAINING DRAWINGS ARE NEEDED FOR INFORMATION ONLY. A/C = AS COMPLETED, A/R= AS REQUIRED, W/S= WITH SHIPMENT, W= WEEKS, S= SOFT COPY IN PDF FORM. # - After Trial run before final acceptance of the system by Owner/Consultant 1.0 Vendor must take care of the following while submitting drawings and documents for review as indicated in Vendor Data requirement enclosed. 1.1 A blank space measuring 75mm W x 40 mm H shall be provided on all vendor drawing for marking review codes etc. by WGI. 1.2 The review of vendor drawings shall be done as applicable under the following review codes: a) Review code A: No comments b) Review code B: Proceed with manufacture/ fabrication as per commented drawing. Revised drawing required. c) Review code C : Document does not conform to basic requirements as marked. Resubmit it for review. d) Review code D: Retained for information/records.

Page 173 of 175

Page 175: City Gas gail Jp Kenny- Wood Group India

2.0 Review of the vendor drawings by WGI would be only to check compatibility with basic design and concepts and would in no way absolve the manufacturer/fabricator of his responsibility to meet applicable codes, specifications and statutory rules/regulations. 3.0 For drawings / documents indicated as FOR INFORMATION in the Vendor Data Requirement. Vendor must mark FOR INFORMATION ONLY on the submitted drawing/document

ANNEXURE - 1. SPECIAL INSTRUCTIONS TO VENDORS GENERAL

1. Offer must be complete in all respect complying fully to the Tender requirements without exception. No price change whatsoever shall be allowed to the vendor after submission of bid even if it results from any technical clarification. Note that all items included in this Tender shall be ordered on a single vendor. Vendor shall also note that all the quantities of various items indicated in this Tender are indicative and actual BOM shall be sole responsibility of the vendor in line with Tender requirements. 2. Any price change subsequent to the submission of the offer because of any technical query or any other reason attributable to the vendor may lead to rejection of the offer 3. Vendor to furnish ‘NO DEVIATION CERTIFICATE’ 4. Vendor shall categorically sign and stamp each and every sheet of the Material Requisition including:- a) Vendor Data Requirements b) Special Instructions To Vendor c) Job Specifications. d) List of Attachments 5. Vendor shall furnish the drawings/documents submission schedule within 15 Days of the receipt of LOI / FOI. 6. Vendor shall submit the Technical questionnaire duly filled in along with the offer. An offer without the filled in Technical questionnaire shall be considered as incomplete and is liable to be rejected. 7. Bidder shall submit the price details against each Item specified in this Tender in the separate price schedule sheet with unit rate. No information / description, technical or non-technical, other than what is required as per price format shall be filled or submitted. Unit rates as asked, shall be provided separately

Page 174 of 175

Page 176: City Gas gail Jp Kenny- Wood Group India

8. Model numbers of each item including the accessories shall be indicated in the Source of Supply form. 9. Offered models shall be accompanied with technical catalogues in English language.

10. Vendor shall be responsible for selection of correct model of the instruments to meet the purchaser's specifications. In case the model is required to be changed at a later stage, to meet the purchaser's specifications as per the requisition, the same shall be done by the vendor without any price and delivery implications. 11. Equipment Qualification Criteria: The make and model number of the all equipment

as offered shall be field proven. It shall be operating satisfactorily in similar applications for a period of 4000 Hrs as on bid due date. 12. Offers will be evaluated as received on the basis of the above points.

Page 175 of 175