Upload
vuongtu
View
221
Download
1
Embed Size (px)
Citation preview
CITATION: Ceccon Transport Pty Ltd & Ors v Tomazos
Group Pty Ltd (No 2) [2017] NTSC 55
PARTIES: CECCON TRANSPORT PTY LTD (ACN
009 595 911)
and
CECCON, Suzanne Yoko
and
CECCON, Antonio
and
TOMAZOS GROUP PTY LTD (ACN 009
618 704)
and
TOMAZOS GROUP PTY LTD (ACN 009
618 704)
and
TOMAZOS TRANSPORT PTY LTD
(ACN 159 500 857)
and
CECCON TRANSPORT PTY LTD (ACN
009 595 911)
and
CECCON, Antonio
and
CECCON, Suzanne Yoko
2
TITLE OF COURT: SUPREME COURT OF THE
NORTHERN TERRITORY
JURISDICTION: SUPREME COURT OF THE
NORTHERN TERRITORY
EXERCISING TERRITORY
JURISDICTION
FILE NO: No 108 of 2014 (21451042)
DELIVERED ON: 24 July 2017
DELIVERED AT: Darwin
WRITTEN SUBMISSIONS: 19 April 2017, 11 May 2017, 24 May
2017, 5 June 2017 and 7 June 2017
JUDGMENT OF: HILEY J
CATCHWORDS:
CIVIL LAW - PROCEDURE – Supreme Court Procedure - Practice
Direction No. 6 of 2009 – Defendant’s failure to comply with Practice
Direction No. 6 of 2009 caused delay and unnecessary costs to be incurred
by plaintiffs and prevented proper consideration of an appropriate resolution
of the proceedings – Defendants ordered to pay costs on an indemnity basis
CIVIL LAW – PROCEDURE – Discovery - Failure to give proper discovery
prolonged the dispute – Conduct falls far short of the conduct expected of a
litigant properly advised in relation to the seriousness of complying with the
obligation to give discovery – Indemnity costs may be allowed
CIVIL LAW - PROCEDURE – COSTS – Calderbank settlement offer made
by plaintiffs - Judgment less favourable to defendants than Calderbank offer
– Refusal of offer was unreasonable
3
INTEREST – Interest on costs – Whether a higher interest rate should be imposed
where there is failure to comply with Practice Direction No. 6 of 2009
INTEREST – Interest on pre-judgment damages – Interest should be allowed at
ordinary commercial rates – Where there is no evidence of relevant commercial rates a
fair and reasonable rate should be applied – Prescribed post judgment rates are a useful
guide
Sherwin and Sherwin v Commens and Commens [2008] NTSC 45, Applied
Colgate-Palmolive Pty Limited v Cussons Pty Limited [1993] FCA 801; 46 FCR 225,
Cullen v Trappel (1979-80) [1980] HCA 10; 146 CLR 1, Edgar v Public Trustee for
the NT [2011] NTSC 21, Elite Protective Personnel Pty Ltd & Anor v Salmon [2007]
NSWCA 322, Groote Eylandt Aboriginal Trust Inc v Deloitte, Touche Tohmatsu (No
3) [2017] NTSC 30, Hazeldene's Chicken Farm Pty Ltd v Victorian WorkCover
Authority (No 2) [2005] VSCA 298; 13 VR 435, Hobartville Stud Pty Ltd v Union
Insurance Co Ltd (1991) 25 NSWLR 358, LO v NTA [2017] NTSC 24, Miwa Pty Ltd v
Siantan Properties Pte Ltd (No 2) [2011] NSWCA 344, SMEC Testing Services Ply
Ltd v Campbelltown City Council [2000] NSWCA 323, Spadaccini v Grice [2012]
NTSC 41, The Silver Fox Co Pty Ltd (No 3) (2004) 214 ALR 621, Veetemp
Australasia Pty Ltd v GRD Group NT Pty Ltd [2012] NTSC 93, Referred to
Territory Sheet Metal Pty Ltd v ANZ Banking Group Limited [2010] NTSC 3,
Distinguished
Michael Grant QC (ed) Civil Procedure Northern Territory (Presidian Legal
Publications)
Federal Court of Australia Act 1975 (Cth) s 52(2)(a)
Federal Court Rules 2011 (Cth) 39.06
Supreme Court Rules (NT) 26.03(3), 63.74, 63.74(1), 59.02, 59.02(3)
Supreme Court Act 1979 (NT) s 85,
Northern Territory Supreme Court, Practice Direction No. 6 of 2009 Trial Civil
Procedure Reforms, 11 June 2009.
4
REPRESENTATION:
Counsel:
Plaintiff: B Ilkovski
Defendants: M Crawley
Solicitors:
Plaintiff: Clayton Utz
Defendants: De Silva Hebron Barristers & Solicitors
Judgment category classification: B
Judgment ID Number: Hil1710
Number of pages: 48
IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWIN
Ceccon Transport Pty Ltd & Ors v Tomazos Group Pty Ltd (No 2)
[2017] NTSC 55
No. 108 of 2014 (21451042)
BETWEEN:
CECCON TRANSPORT PTY
LTD (ACN 009 595 911)
First Plaintiff
AND:
CECCON SUZANNE YOKO
Second Plaintiff
AND:
CECCON ANTONIO
Third Plaintiff
AND:
TOMAZOS GROUP PTY LTD
(ACN 009 618 704)
Defendant
AND:
TOMAZOS GROUP PTY LTD
(ACN 009 618 704)
First Plaintiff by Counterclaim
AND:
2
TOMAZOS TRANSPORT PTY
LTD (ACN 159 500 857)
Second Plaintiff by Counterclaim
AND:
CECCON TRANSPORT PTY
LTD (ACN 009 595 911)
First Defendant by Counterclaim
AND:
ANTONIO CECCON
Second Defendant by
Counterclaim
AND:
SUZANNE YOKO CECCON
Third Defendant by Counterclaim
CORAM: HILEY J
REASONS FOR JUDGMENT
(Delivered 24 July 2017)
3
Introduction ............................................................................................. 4
Applications for stay.......................................................................... 5
Plaintiffs’ main submissions ................................................................... 11
Practice Direction 6 of 2009 ................................................................... 15
Indemnity costs ...................................................................................... 26
Discovery .............................................................................................. 27
Settlement offer of 7 August ................................................................... 29
Interest on costs ..................................................................................... 34
Interest payable under the Loan Agreement ............................................. 37
Interest on amounts found due in [213(g)] ............................................... 38
Interest up to judgment ........................................................................... 45
Orders ................................................................................................... 47
4
Introduction
[1] On 31 March 2017 the Court published its reasons for decision
(Reasons)1 and invited submissions from the parties on what orders
should be made consequential upon the Court’s findings and
conclusions set out in the Reasons, in particular orders relating to
interest and costs.
[2] On 11 April the plaintiffs (Ceccon parties) provided draft orders that
included the following:
1. In respect of paragraph 213(a) of the reasons for judgment given
by the Court on 31 March 2017, judgment for the Third Plaintiff
against the Defendant in the amount of:
(a) $901,183.62; and
(b) $221.77 per day for each day after 11 April 2017 until the
amount at paragraph 1(a) above has been paid
2. In respect of paragraphs 213(b), (c), (d), (e) and (f) of the
reasons for judgment given by the Court on 31 March 2017,
judgment for the First Plaintiff against the Defendant in the
amount of $1,023,597.63.
3. The Amended Counterclaim is dismissed.
1 Ceccon Transport Pty Ltd & Ors v Tomazos Group Pty Ltd [2017] NTSC 25 .
5
[3] The plaintiffs also foreshadowed written submissions in relation to:
(a) the proper rate of interest payable on the amounts found due in
paragraphs 213(b), (c), (d), (e) and (f) of the Reasons;
(b) costs, including costs on an indemnity basis; and
(c) interest on costs and the rate of interest.
[4] The defendant and plaintiffs by Counterclaim (Tomazos parties)
indicated that they:
(a) propose to appeal against the Court’s decision, apart from the
Court’s dismissal of the claim regarding the transfer of a unit;
(b) do not agree with the plaintiffs’ calculations concerning interest
on the loan, oppose an order for costs and wished to make
submissions on the rate of interest otherwise payable; and
(c) sought a stay of the question of costs and of execution of the
judgment pending the outcome of the proposed appeal.
Applications for stay on costs and stay of execution
Stay on costs
[5] On 30 May 2017 I rejected the application for a stay on the costs issue.
The main reason underlying that stay application was a contention that
the submissions would involve the disclosure of confidential
information such as without prejudice offers and things said and done
6
in the course of mediation. Tomazos contended that the disclosure of
such material may be prejudicial to the foreshadowed appeal. 2 Counsel
also submitted that the fact that a successful appeal would render any
costs order otiose is a relevant matter, but accepted that this is not
decisive.3
[6] Counsel for the Tomazos parties indicated that they might call
evidence from Mr Maurice QC, who had conducted a mediation on
4 August 2015. The parties agreed that they would attempt to provide
the Court with a document indicating relevant matters concerning the
mediation without the need for the mediator to give evidence.
However counsel for the Tomazos parties did not proceed with either
of these proposals. I indicated that I was prepared to make appropriate
orders, if requested, to preserve the confidentiality of settlement
discussions including settlement offers. As matters transpired, the only
disclosure that was made about such matters was the two settlement
offers made by the plaintiffs, the first on 7 August 2015, three days
after the unsuccessful mediation, the second on 7 March 2016, the first
day of the hearing.
[7] No attempt was made to identify any possible ground of appeal. Costs
orders are part of the final orders disposing of most cases, and are
often the subject of the appellate intervention. Even if the Tomazos
2 In this context the Tomazos parties referred to The Silver Fox Co Pty Ltd (No 3) (2004)
214 ALR 621 at 624. 3 In this context the Tomazos parties referred to Groote Eylandt Aboriginal Trust Inc v
Deloitte, Touche Tohmatsu (No 3) [2017] NTSC 30 at [14].
7
parties were successful on appeal it does not necessarily follow that if
a costs order is made it will be quashed. Much will depend upon the
basis for the successful appeal.
[8] In those circumstances I considered there was no proper reason why the
matter should not be finalised in the normal way by dealing with costs
now, notwithstanding the possibility of an appeal.4
Stay of execution
[9] In their written submissions of 19 April 2017 the Tomazos parties
stated that they understand the first plaintiff has ceased trading and
that nothing is otherwise known of the financial position of the
plaintiffs. Absent any such assets, a successful appeal would be
rendered nugatory if the plaintiffs had no capacity to repay the
judgment. They sought the opportunity for this issue to be addressed
by affidavits and supplementary submissions.
[10] In his affidavit of 10 May 2017 Mr De Silva stated that he was
instructed to appeal the judgment both in respect of the claim and
counterclaim. He said:
The Tomazos entities are concerned that if the judgment is paid
and the appeal is successful, the plaintiffs may not have the
capacity to repay the judgment. Apart from the fact that Ceccon
Transport Pty Ltd has ceased trading, nothing is known of the
financial position of any of the plaintiffs. Accordingly, the
4 See for example discussion in LO v NTA [2017] NTSC 24, The Silver Fox Co Pty Ltd (No
3) (2004) 214 ALR 621 at 624 and Groote Eylandt Aboriginal Trust Inc v Deloitte, Touche
Tohmatsu (No 3) [2017] NTSC 30 at [14].
8
Tomazos entities seek a stay of the judgment on such terms as
the court may deem appropriate.
[11] No further affidavits were provided. In their further submissions of
11 May 2017 the Tomazos parties simply stated that they rely upon the
previous submissions.
[12] In their submissions in reply, counsel for the plaintiffs referred to s 57
of the Supreme Court Act (NT) which empowers the Court or the Court
of Appeal to stay the whole or part of a proceeding under a judgment
appealed from where an appeal has been instituted. Subsection 57(3)
provides that:
Except as expressly provided by this section or by the Rules or
any other law in force in the Territory, the institution of an
appeal does not operate as a stay of execution
[13] Counsel cited relevant decisions5 and summarised the relevant factors
to be considered in the discretion to grant or refuse a stay as follows:
(a) A successful party at first instance is entitled to the “fruits of their
victory”;
(b) The onus is upon the applicant for a stay to demonstrate a reason
or an appropriate case to warrant the exercise of discretion in
favour of a stay;
5 Alexander v Cambridge Credit Corp Ltd (1985) 2 NSWLR 685, pp 693-695; followed by
Kearney J in Enterprise Gold Mines NL v Mineral Horizons NL (1988) 52 NTR 13; see
also to like effect Henderson & Ors v Purairclean Pty Ltd & Anor[No 3] [2013] NTSC
73.
9
(c) The onus is upon the applicant for a stay to demonstrate a proper
basis for a stay that will be fair to all parties;
(d) In determining what terms will be fair to the parties, the Court
will weigh considerations such as the balance of convenience and
the competing rights of the parties;
(e) This may require a condition on the grant of a stay that the
applicant pay either part or whole of the judgment debt or give
security for part or whole of the judgment debt to reflect a fair
adjustment of the rights of the parties;
(f) Where there is a risk that, if a stay is granted, the assets of the
applicant will be disposed of the Court may, in the exercise of its
discretion, refuse to grant a stay;
(g) Where there is a risk that the appeal will prove abortive if the
applicant succeeds and a stay is not granted, courts will normally
exercise their discretion in favour of granting a stay; and
(h) In considering whether to exercise their discretion to grant a stay,
courts will not generally speculate about the appellant's prospects
of success. However this does not prevent making some
preliminary assessment about whether the appellant has an
arguable case when considering the specific terms of a stay that
will be appropriate fairly to adjust the interest of the parties.
10
[14] I do not consider that the Tomazos parties have shown that a stay
should be granted. More is required than the vague concerns expressed
by the Tomazos parties and their lawyers. They have the onus of
showing why a stay should be granted. There is no evidential onus on
a respondent to an application for a stay to show why it should enjoy
the fruits of victory.
[15] Although it may not normally be relevant for a court to consider the
prospects of an appeal against its decision succeeding, the fact that no
appeal has been instituted and that the scope of a potential appeal has
not been described is relevant. This is particularly so in the present
matter where a substantial part of the plaintiffs’ success on their claim
is based on admissions made, albeit late, by the Tomazos parties.
[16] Counsel for the plaintiffs submitted the Tomazos parties have not
explained why there is any need or imperative to protect the subject
matter of the litigation where much of the judgment debt relates to
admitted facts. The Counterclaim is not a legal set off against these
amounts, nor, most probably, an equitable one. The Tomazos parties
merely wish to not have to pay over anything on the speculation of an
offsetting claim. An attempt to secure such a benefit in these
circumstances is totally destructive of the Ceccon parties ’ legitimate
interests in enjoying the fruits of victory. The denial of the fruits of
victory require appropriate conditions on the grant of a stay, and the
Tomazos parties’ failure to offer any appropriate conditions is, again, a
11
failure to discharge its onus to enliven the Court’s discretion in a
proper and justified manner.
[17] I agree with those contentions. I reject the application for stay of
execution.
Plaintiffs’ main submissions
[18] The Ceccon parties seek the following orders for costs and interest.
(1) Tomazos Group Pty Limited and Tomazos Transport Pty Limited
jointly and severally pay the costs of the Plaintiffs and Defendants
by Counterclaim on an indemnity basis;
(2) In the alternative to (1), Tomazos Group Pty Limited and Tomazos
Transport Pty Limited jointly and severally pay the costs of the
Plaintiffs and Defendants by Counterclaim on:
(i) the standard basis up to and including 6 August 2015; and
(ii) an indemnity basis from 7 August 2015;6
(3) In the alternative to (1) and (2), Tomazos Group Pty Limited and
Tomazos Transport Pty Limited jointly and severally pay the costs
of the Plaintiffs and Defendants by Counterclaim on:
6 On 7 August 2015 Ceccon offered to settle the claims and counterclaims in the proc eeding
on the basis that the Tomazos parties pay $2,100,000 (plus any applicable GST) to the first
plaintiff. That offer was not accepted.
12
(i) the standard basis up to and including 6 March 2016; and
(ii) an indemnity basis from 7 March 2016;7
(4) In the alternative to (1), (2) and (3), Tomazos Group Pty Limited
and Tomazos Transport Pty Limited jointly and severally pay the
costs of the Plaintiffs and Defendants by Counterclaim on:
(i) an indemnity basis in respect of costs incurred or determined
to be attributable to the November 2011 Sale Agreement or
Alternative November 2011 Sale Agreement; and
(ii) the standard basis otherwise;
(5) In the alternative to (1)-(4), Tomazos Group Pty Limited and
Tomazos Transport Pty Limited jointly and severally pay the costs
of the Plaintiffs and Defendants by Counterclaim on the standard
basis;
(6) Tomazos Group Pty Limited and Tomazos Transport Pty Limited
jointly and severally pay interest on costs at a rate of 15.5% per
annum; and
(7) Tomazos Group Pty Limited to pay interest on the balance of any
amounts found to be payable in the Reasons at the rate of interest
prescribed for post judgment interest under the Supreme Court
7 On 7 March 2016 Ceccon offered to settle the claims and counterclaims in the proceeding
on the basis that the Tomazos parties pay $2,500,000 (plus any applicable GST) to the
first plaintiff. That offer was not accepted.
13
Rules 1987 (NT) (the Rules) for each relevant period plus an
additional 8% as simple interest.
[19] The Ceccon parties’ advanced the following contentions underpinning
these orders:
(a) The orders sought in:
(i) 2(1) and 2(7) above are justified because the Tomazos parties
did not comply with Practice Direction 6 of 2009 (PD6) in
any material respect on the claim or the counterclaim and
notwithstanding being given a reasonable opportunity to do
so;
(ii) 2(1) above is justified because of the Court’s findings in
respect of the Tomazos parties' failure to properly comply
with the order for general discovery and failed to discover
documents in accordance with their continuing duty to do so
and only well after the failure to discover was brought to
their attention;
(b) The orders sought in 2(2) and 2(3) above are justified because the
Tomazos parties did not accept two Calderbank offers (one dated
7 August 2015 and the other 7 March 2016) which:
(i) were a genuine compromise;
14
(ii) had terms less favourable to the Ceccon parties than the
findings made in the Reasons; and
(iii) were, in the circumstances, unreasonably rejected by the
Tomazos parties;
(c) The order sought in 2(4) above is justified as a more limited
alternative to proposed order 2(1) in view of the Court's findings
about the Tomazos parties' failure to comply with the order for
general discovery;
(d) The order sought in 2(5) above is justified because the Ceccon
parties succeeded on substantially all of their claims and in
successfully defending the Tomazos parties’ counterclaim; and
(e) The order sought in 2(6) above is justified because it compensates
the Ceccon parties for having to finance this litigation by paying
fees to their legal representatives, however, the rate is higher
because it is related to the orders sought in 2(1) and 2(7) and the
argument developed below in respect of the Tomazos parties'
failure to comply with PD6 in any material respect.
15
Practice Direction 6 of 2009
[20] In Spadaccini v Grice8 Barr J explained the history and purpose of
PD6. At [44] he said:
… PD6 requires that parties to a dispute “should follow a
reasonable procedure, suitable to their particular circumstances,
which is intended to avoid litigation.” PD6 provides substantial
detail as to the required pre-commencement procedure, but I
briefly summarise the first two steps in the procedure as
follows: (1) the plaintiff should send a letter to the defendant
with details of the claim, supported by copies of the essential
documents on which the plaintiff relies and any documents
(except privileged documents) which might significantly impair
the plaintiff’s case; (2) the defendant should acknowledge the
plaintiff’s claim letter promptly, and then provide a full written
response, as appropriate, accepting the claim in whole or in part
and making proposals for settlement; or stating that the claim is
not accepted. The defendant must be precise about what parts,
if any, are accepted and what parts are rejected and provide
detailed reasons (including supporting documents) for non-
acceptance. PD6 requires pre-commencement discovery of
documents by both sides.
[21] The relevant costs and interest provisions in PD6 are:
13. If, in the opinion of the Court, non-compliance with this
Part has led to the commencement of proceedings which
might otherwise not have needed to be commenced, or has
led to delay or costs being incurred in the proceedings that
might otherwise not have been incurred, the orders the
Court may make include:
13.1 an order that the party at fault pay the costs of the
proceedings, or part of those costs, of the other party
or parties;
13.2 an order that the party at fault pay those costs on an
indemnity basis;
8 [2012] NTSC 41 at [37] - [47.
16
13.3 if the party at fault is a plaintiff in whose favour an
order for the payment of damages or some specified
sum is subsequently made, an order depriving that
party of interest on such sum and in respect of such
period as may be specified, and/or awarding interest at
a lower rate than that at which interest would
otherwise have been awarded;
13.4 if the party at fault is a defendant and an order for the
payment of damages or some specified sum is
subsequently made in favour of the claimant, an order
awarding interest on such sum and in respect of such
period as may be specified at a higher rate than the
rate at which interest would otherwise have been
awarded.
…
27 The Court will take into account, amongst other matters,
whether a party has complied with its duties under the
Rules and further this Practice Direction when considering:
27.1 the exercise of its discretion as to costs under r.63.03;
27.2 the exercise of its discretion in relation to interest
under s 84 of the Supreme Court Act.
28. Notwithstanding O.63.74, where the Court decides that a
party has failed to comply with its duties under the Rules
and this Practice Direction, the Court may award interest
on costs at a rate not exceeding the rate fixed by the Rules,
plus 8%.
[22] The Ceccon parties contend:
(a) that the Tomazos parties did not comply with PD6 in any material
respect on the claim or the counterclaim notwithstanding being
given a reasonable opportunity to do so; and
17
(b) their failure to comply with PD6 in the circumstances of this
proceeding is such as to justify the Court making orders that the
Tomazos parties:
(i) pay the Ceccon parties' costs on an indemnity basis
(PD6 [13.1] and [13.2]);
(ii) pay interest on amounts awarded at a higher rate than the rate
at which interest would otherwise have been awarded
(PD6 [13.4]); and
(iii) pay interest on costs (PD 6 [28]).
[23] The relevant circumstances in relation to compliance with PD6 are
deposed to in paragraphs [4] to [17] of the affidavit of Mark Spain
made on 19 April 2017 and the annexures referred to therein (Spain
Affidavit) and in paragraphs [3] to [17] of the affidavit of David De
Silva made on 19 April 2017 (De Silva Affidavit).
[24] The plaintiffs contend, and I accept, that the solicitors for Ceccon
Transport Pty Ltd (Ceccon Transport):
(a) filed the writ and a general endorsement of claim on 31 October
2014 to preserve the claims due to the potential expiry of
limitation periods;
18
(b) thereafter complied with the requirements of PD6 as soon as
reasonably possible, commencing with a detailed letter on
7 November 2014 (the PD6 letter); and
(c) served an amended writ and a general endorsement of claim on
4 February 2015 following a period of approximately three months
during which Tomazos Group Pty Ltd (Tomazos Group) failed to
provide any meaningful response or reasonable explanation as to
why a response could not be provided in accordance with the
requirements of PD6.
[25] Indeed it appears that no meaningful response was forthcoming from
the Tomazos parties until 29 April when they filed their defence and
counterclaim. Moreover the Tomazos parties appear to have made no
attempt to provide their own PD6 letter before filing their
counterclaim. That counterclaim raised a significant number of
complex issues which were independent of those raised by the
plaintiffs and were responsible for a very significant part of the
proceedings, particularly leading up to and during the hearing of the
matter.
[26] The PD6 letter provided details of the claims referred to in these
proceedings as the Loan Agreement, Material Sale and Supply, the
November 2011 Sale Agreement, the Supply and Fit Agreement, the
Validation and Accessibility Agreement, and the Gunn Point
19
Rehabilitation Agreement. It also contained a claim for damages for
breach of an agreement by Tomazos to transfer freehold title in an
apartment to be selected by Ceccon. The letter included a Schedule
quantifying the amount said to be due, a copy of a number of important
documents and a copy of PD6 and an explanatory document.
[27] The plaintiffs were substantially successful in establishing those
claims, apart from the claims regarding rehabilitation (which was not
ultimately pressed) and the claims regarding the apartment and some
small items such as the $600 genset hut. There was no contest in
respect of the claims regarding the $400,000 owing under the Loan
Agreement and that interest of at least 7% per annum was payable
thereon, the $322,886.79 owing for the Material Sale and Supply
(Reasons [213(b)]), liability to pay about $101,000 for the stockpiled
materials (Reasons [141] – [143]), the $2,500 owing under the Supply
and Fit Agreement (Reasons [213(d)]), the $5,782.26 payable under the
Supply and Haulage Agreement (Reasons [213(e)]) and the
$133,029.50 payable under the Validation and Accessibility Agreement
(Reasons [213(f)]). These items comprise at least $1.1M of the
defendant’s liability. Apart from the dispute concerning the tran sfer of
the apartment, the main issues at trial concerned items of much lower
monetary significance than the obvious and longstanding indebtedness
exceeding $1.1M. These concerned the rate of interest payable on the
$400,000 outstanding under the Loan Agreement, the precise quantities
20
of building materials and machinery and equipment used by Tomazos
(and hence the total amount payable under the November 2011 Sale
Agreement), claims for relatively small amounts such as the $600
genset hut, the $10,000 fuel bund wall, the $12,720.26 on Ceccon’s
account with Boral, and the Counterclaim.
[28] The PD6 letter complied with the requirements set out in
subparagraphs [6.1] to [6.7] of PD6. This included requesting that
Tomazos Group acknowledge receipt of the PD6 letter within 14 days
and provide a full response to the PD6 letter by no later than
28 November 2014. The PD6 letter asserted that 28 November 2014
was a reasonable period on the basis that the matters claimed had been
the subject of numerous discussions between the parties. The letter
also indicated Ceccon’s desire to enter into mediation once Tomazos
provided a detailed response.
[29] Over the next weeks and then months there were further
communications between the solicitors, mainly initiated by Ceccon ’s
solicitors. On 14 November De Silva Hebron wrote and advised that it
acted for Tomazos Group, acknowledged receipt of the PD6 letter and
stated that a substantive response would be provided "in due course”.
De Silva Hebron first met and received instructions from its clients,
presumably Tony and John Tomazos, on 21 November. On
1 December, after receiving a letter from Clayton Utz querying the
delay, De Silva Hebron wrote requesting further information and
21
foreshadowing a response on 19 December. Clayton Utz provided
further information including copies of numerous tax invoices on
12 December. On 17 December De Silva Hebron wrote again,
indicating that it would not be responding to the PD6 letter until
16 January and would not be able to participate in mediation before
16 February 2015. De Silva Hebron wrote again on 16 January and
indicated that it would respond to the PD6 letter on 23 January. This
did not occur either. No explanation was provided as to why this did
not occur.
[30] Following a directions hearing before the Master when concerns were
expressed about the fact that the writ had not been served, Clayton Utz
filed and served an amended writ and endorsement on Tomazos on
4 February. In his affidavit of 19 April 2017 Mr De Silva said that a
substantive response to the PD6 letter was nearly completed by
4 February 2015 but that once the amended writ was served focus was
given to the proceedings and not responding to the PD6 letter. No
other explanation was provided as to why Tomazos did not reply to the
PD6 letter either soon after 4 February 2015, or ever.
[31] De Silva Hebron filed an appearance on 11 February 2015, instructed
counsel on 19 February and requested further and better particulars on
27 February.
22
[32] By letter dated 17 March, De Silva Hebron advised that the loan
monies were owed to Mr Tony Ceccon, not to the then plaintiff Ceccon
Transport. The letter also stated that a counterclaim was being
considered, and proposed that a mediation be held in no less than four
weeks’ time. No information was provided about a potential
counterclaim apart from reference to a possible breach of the
“Validation and Accessibility Contract” dated 26 October 2012.
[33] On 1 June Ceccon Transport amended its statement of claim, inter alia
adding Mr and Mrs Ceccon as plaintiffs. The Tomazos parties
amended their defence and counterclaim on 9 June. The Master
ordered general discovery on 24 June.
[34] The parties engaged in mediation before Mr Maurice QC on 4 August,
however the matters were not then resolved. Three days later, on
7 August, the plaintiffs offered to settle the whole of the proceedings
by accepting $2.1 million plus any applicable GST inclusive of costs.
[35] Little was said by De Silva Hebron in its correspondence between
14 November 2014 and 17 March 2015 to explain why no meaningful
response to the PD6 letter could be provided. In his affidavit of
10 May 2017 Mr Da Silva says that he first met his clients on
21 November 2015 and took initial instructions from them then. He
said that from that meeting he anticipated that he would be in a
position to deliver a formal response to the PD6 letter within a
23
reasonable period. However he failed to take into account a number of
things, including various other commitments that he had between then
and the end of January 2015, the fact that Tomazos’ business like the
balance of the construction industry in Darwin shuts down from
roughly the middle of December to the middle of January, and that
John Tomazos and Tony Tomazos would be absent from Darwin at
various times over the Christmas break period.
[36] I agree with counsel for Ceccon that the time afforded for the Tomazos
parties to respond was generous and reasonable having regard to the
object and purposes of PD6 and the indicative timeframe contemplated
in PD6. I also agree that the Tomazos parties did not comply with PD6
in any material respect on the claim or counterclaim, notwithstanding
being given a reasonable opportunity to do so. The explanations for
the continuing delays from 14 November 2014 until Tomazos filed a
defence and counterclaim on 29 April 2015 are unsatisfactory. Had
Tomazos Group responded to the PD6 letter when its lawyers said they
would, or even by the latest of the dates which they indicated,
23 January 2015, it is unlikely that the plaintiffs would have had to
incur the cost and delays associated with preparing and filing such a
detailed statement of claim as was filed on 17 March 2015.
[37] I also agree with Ceccon’s counsel that the following reasons,
individually and collectively, demonstrate that the Tomazos parties'
failure to comply with PD6 caused delay, unnecessary costs to be
24
incurred and (ultimately) prevented a proper consideration by the
parties of an appropriate resolution of the proceeding.
[38] First, it can be inferred that the absence of a substantive response to
the PD6 letter meant that Tomazos did not give early and proper
consideration to the matters required in paragraphs [8] to [10] of PD6.
Tomazos Group had access to and control of necessary documents to
verify and assess the claims. Had Tomazos given early and proper
consideration to a substantive PD6 response then the admissions that
were made much later in the proceeding could have been made much
earlier. If Tomazos had done this, the complexion of the entire
litigation would have been different: positions based on proper
documentary records would have been advanced, and discussions at a
mediation could have had better prospects of resolving the matter. All
this should have occurred before the parties became more entrenched in
their positions and invested so much in the legal process and in legal
costs. Delay and increased costs inevitably followed from Tomazos’
lack of engagement with PD6.
[39] Secondly, Tomazos’ failure to give early and proper consideration to
the matters required in paragraphs [8] to [10] of PD6 carried over into
Tomazos’ approach to giving discovery. The Court’s findings in
connection with the Tomazos parties’ failure to give discovery are of a
serious nature. Had the Tomazos parties given early and proper
consideration to PD6 and then to their discovery obligations, the
25
admissions that were made much later in the proceeding could have
been made earlier. The Tomazos parties failed to comply with two
fundamental disclosure regimes, the PD6 pre-action disclosure regime
and discovery during the course of litigation. Failure to deal properly
with the former disclosure regime defeats an important policy of
litigating in this Court, and the failure to deal properly with the latter
disclosure regime goes to the heart of fundamental obligations in
adversarial litigation. The failure to comply with PD6 and discovery
obligations increased the number of issues in dispute, made the
litigation more complex, and caused it to be more protracted and costly
overall.
[40] Thirdly, the Tomazos parties did not make any attempt to engage in the
PD6 process in relation to their Counterclaim. The Counterclaim was
the single biggest component of this litigation. Had PD6 been
complied with, the inherent difficulty of some of different causes of
action and their speculative nature, could have been given early and
proper consideration. There was avoidance in dealing with the Ceccon
parties’ claim and more interest given to setting up the (unsuccessful)
artifice of the Counterclaim. This also increased the number of issues
in dispute, made the litigation more complex, and caused it to be more
protracted and costly overall.
[41] In summary, although the main claims of the plaintiffs were not in
dispute, the Tomazos parties appear to have attempted to stall payment
26
of them for as long as they could and to have belatedly asserted the
counterclaim as a further attempt to further delay the inevitable.
[42] The Tomazos parties did not comply with PD6.
Indemnity costs
[43] I consider that this failure constitutes proper reason for the Tomazos
parties to pay costs of the Ceccon parties on an indemnity basis under
[13.1] and [13.2] of PD6.
[44] I consider it fair and just that Ceccon’s costs be paid on that
(indemnity) basis from 23 February 2015. That is, one month after the
latest of the dates by which De Silva Hebron had indicated they would
respond to the PD6 letter. Had they done that then, made concessions
of the kind referred to in [19] above, attempted to define the real issues
in dispute, and engaged with the plaintiffs in a meaningful way, it is
likely that the plaintiffs would not have had to incur the kind of costs
that they subsequently incurred.
[45] Costs payable by the Tomazos parties to the Ceccon parties up to
22 February 2015 will be assessed on a standard basis. This will
include Ceccon’s costs of complying with PD6.
[46] Because I have reached these conclusions on the basis of Tomazos’
failures to comply with PD6 there is no need for me to consider in
detail, at least in respect of the costs issue, the ramifications, all
27
adverse to the Tomazos parties, of Tomazos’ inadequate discovery and
of their failure to accept the offers made on behalf of the Ceccon
parties, particularly the offer made on 7 August 2015. However, I shall
discuss those matters as they are relevant to other aspects of the
plaintiffs’ claims, for example the quantum of interest payable on
costs.
Discovery
[47] A Court can order costs on an indemnity basis where there is evidence
of particular misconduct that causes loss of time to the Court and to
other parties Colgate-Palmolive Pty Limited v Cussons Pty Limited.9
[48] Orders for general discovery were made by the Master on 24 June
2015, some two weeks before the mediation attempted before
Mr Maurice QC and almost nine months before the commencement of
the trial on 7 March 2016.
[49] At paragraphs [161] – [165] of the Reasons I made findings critical of
the very late and, even then, inadequate disclosure of documents by the
Tomazos parties. The documents produced during the final days of the
hearing, particularly on 26 May 2016, included a very large number of
invoices dockets and similar documents that occupied two cardboard
cartons. I agree with Ceccon’s counsel that the failure to give
discovery prolonged the dispute about the stockpiles. Had discovery
9 [1993] FCA 801; 46 FCR 225 at [24].
28
been given promptly, Tomazos’ denials that they used the stockpiles
could not have been maintained for as long as they were.
[50] Counsel for the Tomazos parties responded by saying that “ultimately,
the discovery was made and is in evidence.” They also submitted that
the plaintiffs did not rely upon that discovery in support of their case at
all and the late discovery had no bearing on the outcome of the case as
determined by the Court.
[51] I accept from Ceccon’s counsel that the late discovery given by the
Tomazos parties on use of the stockpiles was very significant to the
way that the Ceccon parties were forced to run their case. First,
Mr Preston’s evidence would not have been necessary if it were not for
the fact that the Tomazos parties denied use of the stockpiles and
documents created by Mr Preston indicated the contrary. Mr Preston
was called to explain documents he created whilst employed by
Tomazos Group and which should have been discovered by the
Tomazos parties, but were not.
[52] Secondly, the late discovery necessitated the post-hearing amendment
concerning the Alternative Sale Agreement. If the documents were
discovered earlier, the amendment may have been made sooner or the
Tomazos parties may have admitted the claim, as they should have.
Once those documents were produced, albeit late, the ability of the
Ceccon parties to supplement the evidence of Mr Preston and
29
successfully prove Tomazos’ substantial use of the stockpiles was
considerably enhanced. The documents did have a bearing on the
outcome of the case.
[53] I agree with Ceccon’s counsel that Tomazos Group’s conduct falls far
short of the conduct expected of a litigant properly advised in relation
to the seriousness of complying with the obligation to give discovery.
I agree this was a case where a dispute was unnecessarily prolonged
and Court time lost in dealing with a factual reality that should not
have been contested.
Settlement offer of 7 August
[54] On 7 August 2015, three days after the full day mediation before
Mr Maurice QC, the Ceccon parties sent a letter to De Silva Hebron
expressed to be “without prejudice save as to costs.” It said:
1. Our clients offer to settle the claims and counterclaims in
the Proceeding on the following terms:
(a) the Defendants pay $2,100,000.00 to Ceccon
Transport Pty Ltd on or before 14 September 2015
(plus any applicable GST);
(b) the parties release and discharge each other from all
matters arising on the claims and the counterclaims in
the Proceeding; and
(c) the parties consent to orders that the Proceeding by
claim and by counterclaim be dismissed.
30
2. The above offer is made inclusive of costs and interest and
pursuant to Rule 26.11 of the Supreme Court Rules.
3. If the offer is accepted it will be immediately binding and
enforceable but our clients will require all parties to
execute a deed of settlement and release to formalise and
more fully give effect to the terms of settlement.4.The
above offer is made inclusive of costs and interest and
pursuant to Rule 26.11 of the Supreme Court Rules.
4. Our clients reserve the right to allocate the settlement sum
to the various claims in the Proceeding at their discretion
and for this to be recorded in the proposed deed of
settlement and release.
5. The offer is open for acceptance before 4:00pm on Friday,
14 August 2015.
The offer is made without prejudice except as to costs in
accordance with the principles discussed in Cutts v Head [1984]
Ch 290. If the offer is not accepted and any further litigation
and shoes, reserve the right to refer to the letter on questions
respecting costs in accordance with those principles. Please let
us know if your clients accept this offer, in which case we will
prepare the deed of settlement and release.
[55] There was no attempt made on behalf of the Tomazos parties to put a
counter-offer, either whilst Ceccon’s offer was open, or subsequently,
or to seek further time for consideration of Ceccon’s offer.
[56] Ceccon contends that as a result of the judgment that will follow from
the Reasons, the Tomazos parties will be ordered to pay $1,924,781.25
plus interest plus costs plus interest on costs. This will exceed the
amount that Ceccon offered to accept. Consequently Ceccon would be
entitled to indemnity costs from the date of the offer.
31
[57] The general principles regarding offers of the kind made by the Ceccon
parties on 7 August are well established.
[58] An offer made inclusive of costs can be properly considered to be a
Calderbank offer.10 A Calderbank offer does not automatically result
in the court making an order for indemnity costs. 11 The question that
the court has to determine in deciding whether to award indemnity
costs is:
…whether the offeree's failure to accept the offer, in all the
circumstances, warrants departure from the ordinary rule as to
costs, and that the offeree ends up worse off than if the offer
had been accepted does not of itself warrant departure.12
[59] In the context of a Calderbank offer, this generally devolves into a
consideration of the following two questions:
(a) whether the offer was a genuine offer of compromise; and
(b) whether it was unreasonable for the offeree not to accept the offer
in the circumstances.13
[60] As to the first of these questions, a genuine compromise involves a
party giving something away.14 As to the second of these questions, a
court will take into account various factors such as the stage of the
10 See Elite Protective Personnel Pty Ltd & Anor v Salmon [2007] NSWCA 322; Veetemp
Australasia Pty Ltd v GRD Group NT Pty Ltd [2012] NTSC 93. 11 See SMEC Testing Services Ply Ltd v Campbelltown City Council [2000] NSWCA 323. 12 Ibid at [37]. 13 See Miwa Pty Ltd v Siantan Properties Pte Ltd (No 2) [2011] NSWCA 344 at [8] and
Edgar v Public Trustee for the NT [2011] NTSC 21. 14 See Hobartville Stud Pty Ltd v Union Insurance Co Ltd (1991) 25 NSWLR 358 at 368 and
Miwa Pty Ltd v Siantan Properties Pte Ltd (No 2) [2011] NSWCA 344.
32
proceeding at which the offer was received, the time allowed to the
offeree to consider the offer, the extent of the compromise offe red, the
offeree's prospects of success assessed as at the date of the offer, the
clarity with which the terms of the offer were expressed and whether
the offer foreshadowed an application for indemnity costs in the event
of the offeree's rejecting it.15
[61] Counsel for the Tomazos parties did not challenge Ceccon’s contention
that the offer was less favourable to the plaintiffs and hence more
advantageous to Tomazos than the amount to which the Ceccon parties
were found to be entitled. However counsel contended that the offer
did not satisfy all of the criteria noted in paragraphs [59] and [60]
above. Amongst other things counsel contended that the offer was
imprecise in terms of dollars because it included the possible addition
of GST, it was inclusive of costs as a result of which its real value was
difficult to assess, the offer did not clearly foreshadow an application
for indemnity costs, and that the failure to accept the offer was not
unreasonable. Reasons for the latter contention included that the
defendants were still actively engaged in assessing the merits and value
of the counterclaims, that the loan was found to be with Tony Ceccon,
not Ceccon Transport, and that the offer was made shortly after the
attempted mediation.
15 See Hazeldene's Chicken Farm Pty Ltd v Victorian WorkCover Authority (No 2) [2005]
VSCA 298; 13 VR 435 and Miwa Pty Ltd v Siantan Properties Pte Ltd (No 2) [2011]
NSWCA 344 at [12].
33
[62] In my view the offer did meet the two criteria noted in paragraph [59]
above. It was made three days after the attempted mediation. This
would have been a time in the proceedings, perhaps the most
appropriate time prior to the period leading up to the hearing itself,
when both parties would have been extremely cognisant of the
respective strengths and weaknesses of their cases. This was the time
for settlement to be seriously explored by both part ies. Although the
time for acceptance was only seven days, less than the 14 day period
required for offers under SCR 26.03(3), I think that time was
reasonable in the circumstances. Those circumstances included the fact
that the PD6 letter had been sent more than eight months earlier,
pleadings had been exchanged and discovery provided, and position
papers would have been prepared for and used during the full day
mediation on 4 August.
[63] In Elite Protective Personnel Pty Ltd & Anor v Salmon Basten JA stated:
Greater sympathy may be accorded a defendant who receives an
offer early in proceedings where there has been no reasonable
opportunity for it to assess its questions of liability or its likely
exposure in damages. Such matters must be assessed on a case
by case basis. Usually litigation will not be the first that the
defendant hears of the claim. However, a defendant which
receives an offer of settlement in circumstances where it
reasonably requires more time to consider its position would no
doubt be advised to respond to that effect and, if necessary,
make a counter-offer in due course.16
16 [2007] NSWCA 322 at [147].
34
[64] I consider that it was unreasonable for the Tomazos parties not to
accept the offer in the circumstances. It seems that the only
uncertainty in the minds of the Tomazos parties concerned the strength
or otherwise of their own counterclaim rather than the strength and
likely quantum of the plaintiffs’ claims.
[65] Quite apart from the consequences that might flow from the Tomazos
parties’ failure to comply with PD6 and with their discovery
obligations, their failure to accept the offer would also lead me to
decide that Tomazos should pay Ceccon’s costs on an indemnity basis.
Interest on costs
[66] I have found that the Tomazos parties are liable to pay the costs of the
Ceccon parties on a standard basis until 22 February 2015 and then on
an indemnity basis.17
[67] Ceccon submits that the Tomazos parties should also pay interest on
those costs at a rate of 15.5% per annum. That rate is derived by using
the rate fixed under the Rules, namely 7.5%, and adding another 8% as
contemplated by paragraph [28] of PD6 because of Tomazos’ failures
to comply with PD6 and their discovery obligations under the Rules.
[68] Counsel for the Tomazos parties did not respond to this submission
except to submit that the Court should adopt the usual course of
leaving it to the Taxing Master to determine entitlement to interest on
17 See [44] - [46] above.
35
costs, both as to the rate and from when it should run, a course
provided for by SCR 63.74. In light of the fact that I am also dealing
now with other aspects regarding costs and interest, I consider it more
appropriate that I deal with this issue now rather than leaving it to the
Taxing Master.
[69] As Ceccon’s counsel pointed out, SCR 63.74(2) provides that a rate of
interest that the Taxing Master may fix under SCR 63.74(1) in respect
of costs, shall not exceed the rate from time to time fixed in accordance
with SCR 59.02 as interest payable on a judgment debt.
[70] Counsel noted that SCR 59.02(3) states that a judgment debt carries
interest from the date of judgment at the rate per annum fixed for
s 52(2)(a) of the Federal Court of Australia Act 1975 (Cth) from time
to time. Section 52(2)(a) states that interest in respect of the post
judgment period is payable at the prescribed rate fixed by rule 39.06 of
the Federal Court Rules 2011 (Cth). Rule 39.06 sets the prescribed
rate as:
(a) for the period from 1 January to 30 June in any year – the rate that
is 6% above the cash rate last published by the Reserve Bank of
Australia before the period commenced; and
(b) for the period from 1 July to 31 December in any year – the rate
that is 6% above the cash rate last published by the Reserve Bank
of Australia before the period commenced.
36
[71] The cash rate last published by the Reserve Bank of Australia before the period
from 1 January to 30 June commenced was 1.50%. Accordingly the rate of
interest fixed is payable on a judgment debt is 7.5% per annum.
Counsel for the Tomazos parties have not challenged any of these
conclusions, presumably accepting that the Tomazos parties should pay
interest on the costs to be ordered in Ceccon’s favour at the rate of
7.5% per annum.
[72] The question for the Court is whether a higher interest rate should be
imposed, as appears to be contemplated by paragraph [28] of PD6.
Although neither counsel adverted to this point, it is arguable that [28]
is inconsistent with the intention if not the wording of SCR 63.74(2).
Without needing to answer that question I see no particular reason in
the present matter to allow interest on costs at a rate higher than that
contemplated by SCR 63.74, namely the rate of 7.5% per annum
payable on a judgment debt. The situation might be different , for
example, if normal commercial interest rates were higher than they
have been for the last several years or if there was some evidence that
the Ceccon parties did or were obliged to incur higher interest rates in
order to pay their costs. In light of my conclusion that most of
Ceccon’s costs are to be paid on an indemnity basis, I doubt that the
Ceccon parties will be disadvantaged by not being awarded inte rest on
their costs at a higher rate.
[73] Accordingly I will order that the Tomazos parties pay interest on the
37
costs awarded in favour of the Ceccon parties at the rate of 7.5%` per
annum.
Interest payable under the Loan Agreement
[74] In the draft orders provided on 11 April 2017, counsel for the Ceccon
parties contended that there should be judgment for the Third Plaintiff
in the amount of $901,183.62 and $221.77 per day for each day after
11 April 2017 until that amount has been paid. That amount of
$901,183.62 included the $400,000 of the original debt still owing plus
interest amounting to $501,183.62.
[75] In their submissions of 19 April 2017 the Tomazos parties contended
that the total amount owing as at 3 April 2017 was $854,206, of which
the interest component was $454,206. With their reply submissions of
24 May 2017 the Ceccon parties provided a detailed schedule showing
how they made their calculations and submitted that at that date,
24 May 2017, the interest due was $510,719.83, and was continuing at
a daily rate of $221.27. Interest would continue to accrue at that rate
until judgment when the covenant to pay interest in the Agreement
would be merged in the judgment. Thereafter the total judgment debt
would carry interest at the rate fixed under the Rules, namely at 7.5%
as I have already concluded.
[76] In their supplementary submissions of 5 June 2007 the Tomazos parties
contended that the difference between the calculations of the
38
competing parties relates to the timing of assessment. They wrongly
assumed that Ceccon calculated interest on a daily basis , as a
consequence of which Ceccon’s figures were higher than they should
have been.
[77] In their submissions in reply to those submissions, the Ceccon parties
agree that interest was to be calculated and compounded annually in
accordance with paragraph [112] of the Reasons, and pointed out that
their calculations were so performed. Included with those submissions
was a detailed explanation of the calculations set out in the schedule
that was attached to their reply submissions of 24 May 2017.
[78] I am satisfied that interest was compounded annually, as at 3 April
each year, and that the plaintiffs’ calculations are correct. The total
sum owing as at 3 April 2017 was $899,409.44 and interest is accruing
on that amount at the rate of $221.77 per day and will continue to
accrue at that rate until judgment.
Interest on amounts found due in [213(g)]
[79] The Ceccon parties contend that Tomazos Group Pty Limited should
pay interest on the balance of any amounts found to be payable in
paragraphs [213(b)] to [213(f)] of the Reasons at the rate of interest
prescribed for post judgment interest under the Rules for each relevant
period plus an additional 8% as simple interest.
39
[80] Section 84 of the Supreme Court Act 1979 (NT) gives the Court the
power to order that “there shall be included in the sum for which
judgment is given interest at such rate as it thinks fit on the whole or
any part of that sum for the whole or any part of the period between the
date when the cause of action arose and the date of the judgment.” It
does not authorise the giving of interest upon interest, and this could
only apply to amounts referred to in paragraphs [213(b)] to [213(f)] of
the Reasons.
[81] Where, as here, no particular rate is prescribed, interest should be
allowed at “ordinary commercial rates”.18 It is open to a party to call
evidence about interest rates, but it has been held that where no such
evidence has been called, it is appropriate to apply the rates applicable
to post judgment interest under the Rules. I have already discussed
this in [70] - [71] above. In Sherwin and Sherwin v Commens and
Commens19 at [67] - [72], this Court found that the rates applicable to
post judgment interest under the Rules was a fair and reasonable rate of
interest.
[82] Accordingly, the Ceccon parties submit that the appropriate base rate
of interest is the rate applicable to post judgment interest under the
Rules. This rate of interest varied during the period from when the
causes of action for the amounts payable in respect to paragraphs
18 Cullen v Trappel [1980] HCA 10; 146 CLR 1 at 21. 19 [2008] NTSC 45 (Sherwin).
40
[213(b)] to [213(f)] of the Reasons accrued, from between 10.75% and
7.75%.
[83] The Ceccon parties submit in the alternative that the appropriate base
rate of interest is 9% as this was the continuing interest rate that the
parties had agreed on in respect of the Loan Agreement.
[84] They also point out that PD6 [27] provides that the Court will take into
account whether a party has complied with its duties under the Rules
and PD6 when considering the exercise of its discretion in relation to
interest under s 84 of the Supreme Court Act 1979 (NT) . Paragraph
[13.4] of PD6 also contemplates that where the Court considers that
non-compliance with PD6 has led to delay or costs being incurred in
the proceedings that might otherwise not have been incurred, it may
order interest on part or all of the amount which the defendant is
ordered to pay the plaintiff at a higher rate than the rate at which
interest would otherwise have been awarded. The Ceccon parties
submit that had the Tomazos parties complied with PD6 the
proceedings might otherwise have resolved. Although PD6 does not
specify a higher rate for the purpose of pre-judgment interest the
Ceccon parties contend that the rate of 8% contemplated in [28] of PD6
for interest on costs is appropriate.
41
[85] Counsel for the Tomazos parties accept that prejudgment interest
should be allowed at ordinary commercial rates. However they dispute
that the rate claimed by the Ceccon parties can be so described.
[86] Counsel contended that Sherwin should not be followed because there
was no effective contradictor to the proposition put by the plaintiffs.
Counsel also submitted that the decision in Sherwin does not reflect the
practice adopted in the Northern Territory, citing the following passage
in paragraph [8.24.21] of Grant, Civil Procedure Northern Territory .20
Grant QC (as he then was) said:
Interest should be referable to the yield the plaintiff would have
received for the past, not the rate of interest which the plaintiff
as a notional borrower would have paid: see Guley v Sabbadin
(1979) 41 SASR 142. This is because interest is to compensate
the plaintiff for being kept out of the money, not to put the
plaintiff in the position of a commercial lender over the period.
For that reason, retail deposit and investment rates will be the
appropriate measure, rather than the lending rates such as the
small business variable and the housing loan variable rates .
[87] Counsel for the Tomazos parties then referred to the decision of this
Court in Territory Sheet Metal Pty Ltd v ANZ Banking Group Limited 21
where the Court took an average of cash management account rates and
short-term fixed deposit rates to arrive at a rate of 3.8%. However in
that matter the Court had the benefit of data from four major banks
indicating commercial rates relating to cash management account
20 Michael Grant QC (ed) Civil Procedure Northern Territory (Presidian Legal
Publications). 21 [2010] NTSC 3 at [196] – [197] (Territory Sheet Metal).
42
transactions and short-term fixed interest deposit transactions during
applicable periods.
[88] No such evidence was tendered in the present matter. As counsel for
Ceccon submits, the only evidence that might be relevant is the fact
that the parties agreed to the 9% rate under the Loan Agreement.
[89] In Territory Sheet Metal ,22 Olsson AJ referred to and did not disagree
with what Southwood J had said in Sherwin. Just below the passage
quoted in [86] above Grant QC said:
It is open to the plaintiff to call evidence about interest rates,
but in more recent cases (see, eg, Sherwin v Commens [2008]
NTSC 45 at [67] – [68]; Helvixa Pty Ltd v Lederer [2007]
NSWSC 49 at [16]), it has been held that in the absence of such
evidence it is appropriate to apply the rates from time to time
applicable to post judgment interest which, under SCR 59.02(3),
is the rate of interest specified in the Federal Court Rules: Acer
Forester Pty Ltd v Complete Crane Hire (NT) Pty Ltd [2013]
NTSC 62 at [51].
[90] After further discussion about Sherwin and Territory Sheet Metal Grant
QC said:
The matter of determining the appropriate rate of interest
requires a broad and practical approach, whereby the purpose
for which interest is awarded is considered and care is taken not
to over compensate the plaintiff or to do an injustice to the
defendant.
[91] I consider that the approach adopted in Sherwin should be followed
where there is no evidence of relevant commercial interest rates. That
22 Ibid at [195].
43
is, the rates fixed for post-judgment interest pursuant to s 85 of the
Supreme Court Act 1979 (NT) and under SCR 59.02(3) should normally
be applied.
[92] However in the present case I consider that an interest rate of 9% is
appropriate. Although that is a little higher than the current rate for
post-interest judgment, that is the rate that was agreed to when the
Loan Agreement was entered into. There has been no significant
change to commercial interest rates since then. The imposition of that
rate is also intended to reflect the fact that PD6 contemplates that in
situations such as I have found to exist in the present matter, the
interest might be higher than that that might otherwise be ordered.
[93] Despite Ceccon’s submissions to the effect that I should increase the
rate by 8%, the figure referred to in paragraph [28] of PD6 in relation
to interest on costs, I consider that the plaintiffs would be adequately
compensated by allowing them interest at the rate of 9% agreed under
the Loan Agreement, noting also the orders that I will be making
concerning indemnity costs and interest thereon.
[94] The remaining question concerns the starting point for the payment of
interest on each of the items referred to in paragraphs [213(b)] to
[213(f)] of the Reasons.
[95] As to interest on the amount owing for the Material Sale and Supply
referred to in [213(b)] of the Reasons, the only challenge on the part of
44
the Tomazos parties concerned the rate. Interest should run from
1 November 2011.
[96] In relation to the Alternative November 2011 Sale Agreement the
Tomazos parties point out that the plaintiffs’ original case based on the
sale of all of the stockpiles, machinery and equipment was abandoned
and the Court found that Tomazos was only liable to pay for what was
used. They also point out that the Notice of Claim was not given until
7 November 2014 and that no invoice was issued until 22 July 2015. In
light of this, they submit that interest should run from that date.
[97] I agree with Ceccon’s reply to the effect that the production of an
invoice did not create the obligation to pay. Rather it was the use and
appropriations of the stockpiles over the 13 month period from
1 November 2011 to about 1 December 2012 that created the obligation
to pay and gave rise to the cause of action. As it is not possible to
know the exact dates on which particular stockpiles23 were used during
that 13 month period, I consider that interest on the amount due in
relation to the stockpiles should run from about midway between those
dates, namely from 15 May 2012.
[98] I also agree with Ceccon that interest on the miscellaneous machinery
and materials24 should run from 1 November 2011, as those items were
immediately available for use and many were used when Tomazos
23 Reasons [213(c)(i)]. 24 Reasons [213(c)(ii)].
45
commenced operating from the Boral yard. So too for the $10,000
payable for the fuel bund wall, as Tomazos had the benefit of the fuel
bund wall from 1 November 2011.25
[99] As to interest on the amount owing for the supply and installation of
the hungry boards, referred to in [213(d)] of the Reasons, I reject
Tomazos’ contention that interes t should not commence until
21 January 2015 when an invoice was issued. I agree that the
obligation to pay arose in October 2012 when Ceccon supplied the
hungry boards and that interest should run from 30 October 2012.
[100] In relation to the amount owing for supply and haulage referred to in
[213(e)] of the Reasons, Tomazos accepts that interest should accrue
from November 2011. As there is some uncertainty as to when in
October and November 2011 those events occurred, it is appropriate
that interest accrue from 1 November 2011.
[101] The parties agree that interest on the amount payable under the
Validation and Accessibility Agreement referred to in [213(f)] of the
Reasons should run from 24 September 2014.
Interest up to judgment
[102] As at 24 July 2017, the amount payable under the Loan Agreement is
$924,248. It comprises the $899,409.44 that was due on 3 April 2017
25 Reasons [213(c)(iii)].
46
plus interest from then at the rate of $221.77 per day namely
$24,838.49.26
[103] In relation to interest payable in respect of the other items referred to
in [213(b)] to [213(f)] of the Reasons it is convenient to provide the
following table. I have rounded up or down some amounts to the
nearest dollar.
Item Principle
$
Start
date
Period Interest
@ 9%
Total $
P & I
Material
Sale and
Supply
322,887 1/11/1127 5 Y +
266
days
166,477 489,364
Stockpiles 494,05528 15/5/1229 5 Y + 71
days
230,974 725,029
Machinery
and
materials
55,344 1/11/1130 5 Y +
266
days
28,535 83,879
Fuel bund 10,000 1/11/1131 5 Y + 5,156 15,156
26 See [78] above. 27 See [95] above. 28 This amount includes GST. 29 See [97] above. 30 See [98] above. 31 See [98] above.
47
266
days
Hungry
boards
2,500 30/10/1232 4 Y +
268
days
1,065 3,565
Supply and
Haulage
5,782 1/11/1133 5 Y +
266
days
2,981 8,763
Validation
and
Accessibility
Agreement
133,030 24/9/1434 2 Y +
304
days
33,917 166,947
TOTAL 1,023,598 469,105 1,492,703
[104] Accordingly the total amount payable in respect of the items referred to
in [213(b)] to [213(f)] of the Reasons is $1,492,703, which comprises
$1,023,598 principle and $469,105 interest.
Orders
[105] I make the following orders:
32 See [99] above. 33 See [100] above. 34 See [101] above.
48
1. Judgment for the Third plaintiff against the Defendant in the
amount of $924,248.
2. Judgment for the First Plaintiff against the Defendant in the
amount of $1,492,703.
3. The Amended Counterclaim is dismissed.
4. The Defendant and the Plaintiffs by Counterclaim jointly and
severally are to pay the costs of the Plaintiffs and Defendants by
Counterclaim on a standard basis up to 22 February 2015 and on
an indemnity basis thereafter, together with interest thereon at the
rate of 9% per annum.
-------------------------