CIPAA 2012, Contract Law and You

  • Upload
    el-zhar

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

  • 8/20/2019 CIPAA 2012, Contract Law and You

    1/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 1/18

    My views on the law of contract, with emphasis on Construction Industry & Payment Adjudication Act 2012 Malaysia I am

    a lawyer who, as a jour neyman who has been an entrepreneur, IT Project Manager and Marketing Evangelist, believes

    that CIPAA 2012 has the potential to benefit the construction industry in Malaysia as a whole.

    CIPAA 2012, Contract Law And You

    THURSDAY, NOVEMBER 21, 2013

    Posted by Jonathan Rozario at 2:44 AM  No comments:

    What Is The Difference Between Adjudication, Mediation, Arbitration andLitigation?

    Litigation is the civil action initiated in courts and the outcome is decided by the Judge. It

    is typically complicated and involves high value matters and are brought befor e a Judge

    who draws on the depths of available legal knowledge and precedents, with the

    assistance of opposing lawyers, to make a decision within the rigid legal procedural

    structure. It is therefore easy to see why litigation is costly and of considerable length.

     ADR was introduced to enable parties in a dispute to enlist a third party

    (mediator/adjudicator/arbitrator) to decide in a faster period and free (or freer) from the

    legal confines that is associated with litigation, to lower costs.

    Here's an overview comparison of ADR

    MEDIATION

    very informal

    high confidentiality

    lower cost than arbitration

    shortest period - may conclude within 1 -2 days

     ADJUDICATION

    less formal than arbitration, rules of evidence do not apply

     Adjudicator controls content and outcome of proceeding (if any)

    lower cost than arbitration

    shorter than arbitration - in CIPAA 2012, Adjudicator has to decide within 45

    days

    decision is interim as it may be appealed or stayed or overturned by arbitral

    award or Court

    monetary remedies only

     ARBITRATION

    rules of evidence do not apply but procedural rules applicable

    remedies must be legal capable of being performed

    may take years to conclude

    costs may be higher than litigation because of thoroughness and expediency

    Litigation v Alternative Dispute Resolution

    Recommend this on G oogle

    MONDAY, JULY 15, 2013

    When Will CIPAA 2012 Come into Effect?

    The construction industry in Malaysia awaits with bated breath and wondering when will

    the Minister sign the statute into effect.

    It is my humble opinion that the Government needs to protect itself from the possibility of 

    Search

    SEARCH THIS BLOG

    November  (1)

    July (1)

    May (1)

    March (1)

    February (1)

    January (1)

    December  (2)

    September  (1)

     August (3)

    BLOG ARCHIVE

    MY BLOG LIST

    Inforrm's BlogPrivacy in Court Proceedings:Exposed – Dominic Crossley

    eLawyer Law Blog ForumFour Lame Excuses Not To Quit Your Job

    Media Law JournalThe news according to Mike Hosking

    LawEddie.comWhy Lawyers Should Learn How ToCount

    Legal in M alaysiaHK Global Resources

    Share   0   More Next Blog» Create Blog   Sign In

    http://inares.blogspot.com/2013/11/what-is-difference-between-adjudication.htmlhttp://inares.blogspot.com/2013/11/what-is-difference-between-adjudication.html#comment-formhttp://www.elawyer.com.my/blog/four-lame-excuses-not-to-quit-your-job/http://inforrm.wordpress.com/2014/05/09/privacy-in-court-proceedings-exposed-dominic-crossley/http://inforrm.wordpress.com/http://inares.blogspot.com/2013_01_01_archive.htmlhttp://inares.blogspot.com/2013/11/what-is-difference-between-adjudication.htmlhttp://www.blogger.com/http://www.blogger.com/http://www.blogger.com/home#createhttps://www.blogger.com/next-blog?navBar=true&blogID=5836939343639792982http://feedproxy.google.com/~r/LegalInMalaysia/~3/yjllkFP2l4U/hk-global-resources.htmlhttp://legal-malaysia.blogspot.com/http://feedproxy.google.com/~r/EddieLaw/~3/ad1ZFKoI05w/http://www.laweddie.com/wordpresshttp://www.medialawjournal.co.nz/?p=627http://www.medialawjournal.co.nz/http://www.elawyer.com.my/blog/four-lame-excuses-not-to-quit-your-job/http://www.elawyer.com.my/bloghttp://inforrm.wordpress.com/2014/05/09/privacy-in-court-proceedings-exposed-dominic-crossley/http://inforrm.wordpress.com/http://inares.blogspot.com/2012_08_01_archive.htmlhttp://inares.blogspot.com/2012_09_01_archive.htmlhttp://inares.blogspot.com/2012_12_01_archive.htmlhttp://inares.blogspot.com/2013_01_01_archive.htmlhttp://inares.blogspot.com/2013_02_01_archive.htmlhttp://inares.blogspot.com/2013_03_01_archive.htmlhttp://inares.blogspot.com/2013_05_01_archive.htmlhttp://inares.blogspot.com/2013_07_01_archive.htmlhttp://inares.blogspot.com/2013_11_01_archive.htmlhttp://inares.blogspot.com/2013/07/when-will-cipaa-2012-come-into-effect.htmlhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6330698608258785581&target=pinteresthttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6330698608258785581&target=facebookhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6330698608258785581&target=twitterhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6330698608258785581&target=bloghttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6330698608258785581&target=emailhttp://inares.blogspot.com/2013/11/what-is-difference-between-adjudication.htmlhttp://inares.blogspot.com/2013/11/what-is-difference-between-adjudication.html#comment-formhttp://inares.blogspot.com/2013/11/what-is-difference-between-adjudication.html

  • 8/20/2019 CIPAA 2012, Contract Law and You

    2/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 2/18

    Posted by Jonathan Rozario at 8:25 PM  No comments:

    dealing with a lorry load of payment claims arriving at the doors of its various ministries

    and agencies once the Construction Industry Payment & Adjudication Act 2012 ("CIPAA

    2012") comes into effect. It is envisaged that the exemption card may be played by the

    Government, albeit selectively initially, to minimize the claims arising from payment

    disputes of the construction projects - ongoing or completed, pursuant to s. 40 of CIPAA

    2012.

    The potential "stop work" or "go slow" as a consequence of adjudication decisions being

    enforced by unpaid parties for ongoing Government initiated projects weighs in heavily.

    The impact of such actions maybe too crippling for the Government to deal with unless it

    already has in placed legal personnel trained to deal with the appeal process to avoid

    enforcement. Or else the Government must ready bags full of funds to fork out to deal

    with unfavorable adjudication decisions to avoid enforcement.

    With so much on the Government's plate, is it any wonder why no one seems to know

    when CIPAA 2012 will come into effect?

    Recommend this on G oogle

    SUNDAY, MAY 5, 2013

    Pay Now, Argue Later and CIPAA 2012

    The Kuala Lumpur Regional Centre of Arbitration (KLRCA), has often summarised the

    core concept of the Construction Industry Payment & Adjudication Act 2012 (CIPAA 2012)

    to be "Pay Now, Argue Later". CIPAA 2012 was introduced in Malaysia with the sole aim

    of addressing the payment problem faced by sub-contractors, suppliers, agents,

    professional service providers, (collectively referred to "Claimant") etc in the construction

    industry, whose only remedy for payment disputes was costly and protracted litigation in

    either the court or arbitration. Now, payment disputes can be brought before KLRCA

    certified adjudicators for speedy and cost effective decision.

    What happens when the Claimant/ himself does not come to the adjudicator with "clean

    hands"? What happens if the Claimant has been accused of defective work which has

    resulted in non-payment by the Respondent? Pay Now, Argue Later will have a bearing on

    the payment dispute as the adjudicator will be tasked in determining the extent of work

    done and decide the amount to be paid.

    The nature of defective work

    The nature and type of defects in construction and engineering projects can vary, and not

    forgetting that the point at which the defects become apparent. On one end of the scale

    minor defects can easily be corrected before the building or plant is handed over to the

    employer, while at the other extreme major or significant defects may occur long after theoriginal work has been completed and require extensive remedial works to fix.

    Some of the defects can arise because the work was not carried out in a 'good and

    workmanlike manner' in accordance with good practice or a particular design, or because

    the wrong materials have been used – matters which would usually be the responsibility

    of the building contractor and its supply chain.

     Alternatively a particular design is not working in the manner that it should as the designer 

    could be at fault.

    In the frequently used design and build scenario, the contractor would normally haveprimary liability for both types of failure – although it may have consequential claims

    against its designers and supply chain.

    On one view identifying a defect should be easy: something has usually not been

    Defective Work In Construction Projects

    http://inares.blogspot.com/2013/05/pay-now-argue-later-and-cipaa-2012.htmlhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=7176895630726898284&target=pinteresthttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=7176895630726898284&target=facebookhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=7176895630726898284&target=twitterhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=7176895630726898284&target=bloghttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=7176895630726898284&target=emailhttp://inares.blogspot.com/2013/07/when-will-cipaa-2012-come-into-effect.html#comment-formhttp://inares.blogspot.com/2013/07/when-will-cipaa-2012-come-into-effect.html

  • 8/20/2019 CIPAA 2012, Contract Law and You

    3/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 3/18

    provided in the manner that it should have been, the foundations of a building could crack

    and subside, the air-conditioning units fail or the roof leak. However, in considering

    'defects' as a matter of principle, work may be defective even if it has been carried out

    with all due skill and care but it fails to meet a particular specification.

    For example, brickwork may be erected correctly but the wrong type or colour of brick

    could have been used in breach of planning permission.

    Potentially difficult arguments can arise where work has been carried out incorrectly by

    the contractor but the architect or engineer's design is also at fault. In these situations,

    the contractor may deny liability on the basis that even though the work was carried out

    defectively, it did not cause the damage complained of. An employer will not be as

    concerned as the contractor and architect to get to the bottom of exactly who is at fault

    for that as long as it can claim against one or both of the parties and both still exist.

    It is often important to distinguish between patent and latent defects. A patent defect is

    one that is detectable either at or before apparent practical completion or during

    the defects liability period. In the past, the courts have held that patent defects must be

    apparent on inspection but need not necessarily have been seen by the people carrying

    out that inspection. By contract, a latent defect is one which has been concealed in the

    works and may not become apparent for many years.

    Typical contractual provisions

    The standard form construction contracts contain provisions dealing with the treatment of 

    defective work during the course of construction, at completion and during the defects

    liability or rectification period. By way of illustration, the contract form may provide that the

    employer may issue instructions requiring the opening up for inspection of any work

    covered up or tests of materials or goods or executed work. The cost of opening up or 

    testing is added to the contract sum, unless the inspection shows that the materials,

    goods, or work are not in accordance with the contract - the contractor then bears those

    costs.

    The question of defects often arises in the context of practical completion (PC), and

    whether or not completion can be said to have occurred even though minor defects exist.

    In the absence of any definition, guidelines have been developed from case law which

    broadly state that:

    · at the date of practical completion the work should be complete and

    free from patent defects;

    · PC will be achieved notwithstanding the presence of latent defects,

    because such defects are by definition not apparent;

    · any defects which are not apparent at PC which do become evident

    during the defects liability period may be addressed in that period;· discretion usually exists to certify PC when minor work remains to be

    carried out, although it is possible to insist on completion of all snagging items

    before PC.

    Rights and remedies

     An issue which often arises in the context of construction projects is whether the

    contractor has a 'right to return' to the site to remedy defects. However, there is no such

    right unless one is specifically conferred upon the contractor by the defects liability

    provisions or otherwise in the contract. Where there is no express right for the contractor 

    to return to the site to attend to remedial works, or the relevant period has passed, an

    employer is entitled to employ others to rectify defects. However, where a third party is

    appointed and that is thought to be unreasonable in the circumstances of the case then

    the employer may be criticised for failing to mitigate its loss.

    The standard forms use different terminology for the defects rectification period, including

  • 8/20/2019 CIPAA 2012, Contract Law and You

    4/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 4/18

    'rectification period', 'maintenance period' and 'defects correction period'. The nature and

    scope of such periods depend on the mechanism adopted in the particular contract, and

    they are typically seen as applying to the whole of the works, the relevant part or section.

    The length of the period will be negotiated by the parties and the nature of the works to be

    undertaken.

    In circumstances where defective work is present, several legal remedies may exist.

    Starting with remedies in contract, where defective work is present as a consequence of 

    a breach of contract then a claiming party is entitled to be put into the position it would

    have been if the work had been correctly carried out. This is achieved by a monetary

    award. The claiming party's losses may be assessed on the basis of:

    · the reasonable cost of repair of the defect work;

    · the difference in value or loss of amenity of the relevant work.

    In strict legal terms the date for assessment of the loss is when the defect is noticed, but

    when considering the cost of repair the date of assessment is usually taken as when it is

    reasonable in the circumstances to undertake the relevant works. A party seeking to bring

    an action for breach of contract in relation to defective works has six years to do so if the

    contract is executed under hand (signed by a single, authorised representative) or 12

    years if the contract is executed by deed. Those periods run from the date of the breach

    of contract. In the case of patent defects this should be obvious, as it is the date when the

    defective work is carried out, but for latent defects the date of cause in action is usually

    taken as being the date on which PC is certified or given. Similar considerations would

    arise in relation to allegations of defective design.

    Betterment

    Where repair works result in a better or newer building, a deduction in damages will not

    usually be made if the claiming party had no reasonable choice but to undertake the

    works in that way. However, if a party chooses to rebuild to a higher standard than was

    strictly necessary it may only be entitled to recover the cost of those works less a credit

    for the betterment element of it. While each case will turn on its own facts, if works are

    said to be unnecessarily expensive the test to be applied is whether the claiming party

    acted reasonably in proceeding in that way. If not, it may struggle to recover the additional

    costs.

    Pure Economic Loss

    Defects in buildings can also pose significant problems for subsequent owners who take

    on responsibility for a building without having procured the relevant work. This is because

    there would be no claim in contract, unless separate rights or a warranty had been

    conferred on that new owner. If this situation arises and the subsequent owner has no

    remedy in contract it raises the question over whether the owner can recover its costs

    and losses in any other way, for example in tort. The general rule is that damage to a

    building which is attributable to a defect in the structure of that building is not recoverable

     – such damage is known as 'pure economic loss' as the only loss sustained is the fact

    that the new owner has paid too much for the property.

    In 2011 the Court of Appeal clarified that, ordinarily, contractors will not owe duties not to

    cause pure economic loss. Therefore they will not owe such duties to subsequent

    owners.

    Limited exceptions may apply if the new owner is able to show that the contractor had

    assumed responsibility for that loss through the provision of skilled advice or services or 

    at least some design responsibility, and that the owner had relied on that advice or 

    services or design. Such situations have been held to arise, for example, where a

    specialist subcontractor provides services to the contractor who employed it and where a

    civil engineer provided design services. However, such situations are complicated and

    the preferable route would always be to ensure that any new owner had the appropriate

  • 8/20/2019 CIPAA 2012, Contract Law and You

    5/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 5/18

    contractual protection to try and guard against its losses.

    Set off, abatement and withholding

    Defective work also raises issues relating to certain 'self help' remedies, including

    common law set off or abatement and equitable set off.

    Common law set off or abatement: A summary of the legal principles :-

    · in a contract for labour and materials where performance has been

    defective the employer is entitled to maintain a defence of abatement;

    · the measure of the abatement is the amount by which the product of 

    the contractor's endeavours has been diminished in value as a result of the

    defective performance;

    · depending on the facts, this difference may be determined by

    comparing the market value of what has been constructed with what ought to

    have been built, or by reference to the cost of remedial works (but not the cost

    of the remedial works themselves);

    · the measure of abatement can never exceed the sum which would

    otherwise be due to the contractor as payment;

    · abatement is not available as a defence to a claim in respect of 

    professional services;

    · claims for delay, disruption or damage caused to anything other than

    that which the contractor has constructed cannot feature in a defence of 

    abatement.

    Equitable set-off 

    This is permitted where a party has a cross-claim which it would be unjust not to take into

    account. This is a wide test and will cover any cross-claim 'closely connected' with the

    claim being made.

    The issues surrounding set off and abatement lead us to the restrictions on those rights

    under CIPAA 2012. The Act provides that a party to a construction contract may not

    withhold payment after the final due date. Period. Unlike similar statute in the UK which

    provides that a party may not withhold payment after it becomes due unless it gives an

    effective notice of its intention to withhold payment including its grounds for doing so to

    the other party. This is to stop contractors abusing their position to wrongfully withhold

    sums due to subcontractors who typically have no quick or cheap means to challenge the

    withholding.

    The "Pay Now, Argue Later" principle of CIPAA 2012 may result in prolonged litigation.

    The losing party of the adjudication decision will seek to appeal the decision in court and

    stay the execution of the decision. This will certainly defeat the noble aim of CIPAA 2012

    to resolve payment disputes quickly and cost effectively.

    Practical issues

     As a starting point, it is worth thinking about how defects and completion issues should

    be addressed at procurement stage. Whether something is defective will often depend

    not so much on whether it is completed competently from a workmanship perspective but

    on the precise standard and specification to be met. Similarly, if specific tests are to be

    passed these will need to be provided for contractually, and consideration given to

    whether general or liquidated damages should apply in the event of failure. The precise

    standard and level of completion required for PC is something which can often cause

    arguments, so careful consideration should be given to whether the completion

    requirements are clear and what risks they may hold.

    It goes without saying that those passing their obligations down a supply chain should

    seek the same assumption of responsibility in relation to defects.

  • 8/20/2019 CIPAA 2012, Contract Law and You

    6/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 6/18

    Turning to the execution phase of the contract, the practical issues tend to focus around

    evidence and notices. Defects are most likely to be picked up on site if there is regular 

    monitoring and testing. It will be a commercial judgement for employers and contractors

    as to how much they wish to spend monitoring and testing the works, but what is crucially

    important is that if defects are identified that are likely to have implications for the project

    then comprehensive records will need to be taken. Similarly, if it is intended to reduce a

    payment or advance a claim as a result of a defect, then consideration should very rapidly

    be given to the basis of the claim. It is also not uncommon for issues to arise as to

    whether an employer waived or agreed to allow a defect to remain. Again, evidence of 

    agreement or waiver should be obtained.

    Post completion, if a defect occurs within a defects liability period under a contract then in

    all probability the employer will be entitled to require the contractor to correct the defect. In

    some forms this is the case even if it is not clear that the defect is the contractor's

    responsibility, although the contractor will be entitled to payment if it is proved the defect

    is not one for which is it responsible.

    Clearly, early consideration should be given to the contractual procedures and relevant

    notices. Even if the defects liability period has ended the contractor will in the vast

    majority of cases remain liable in damages.

    If you are an end user who did not employ the contractor or design team then you will

    want to consider whether you have the benefit of any assignment of the relevant building

    contract or professional appointments, or alternatively whether you have collateral

    warranties or third party rights.

     YONG MOK HIN v. UNITED MALAY STATES SUGAR INDUSTRIES

    LTD

    [1964] 1 LNS 230

    DW3, a civil and structural engineer, who inspected the work at the end of the same

    year also testified about the defective work as enumerated in para. 7 of thestatement of defence. The plaintiff sought to argue that the architect had supervised

    the work and had issued the certificate Exh. P2, had signed in the plaintiff's pass

    book, and lastly the defendant company had by their letter stated that the work was

    satisfactory. In my judgment such certificate or letter only represents the approximate

    value of the work done or materials used. It is not conclusive on the parties as an

    expression of satisfaction with the quality of the work or materials. That is subject to

    readjustment upon the issue of the final certificate. Having considered the evidence,

    I am satisfied that the work was defective and was due to bad workmanship.

    The defendant company opted to accept repudiation and sue for damages for 

    incomplete and defective work. The law with regard to the measure of damages is

    adequately stated at p. 442 of the 9th Edn. of Hudson on "Building and Engineering

    Contracts".

    ... the direct measure of damage will be the difference between the

    reasonable cost to the employer of repairing the defects or completing the

    work, together with any sums paid by or due from him under the contract, and

    the sums which would have been payable by him under the contract if it had

    been properly carried out. (Where the former does not exceed the latter, only

    nominal damages would be recoverable). Such damages are clearly

    recoverable within the first branch of the in Hadley v. Baxendale [1854] 9 Ex

    341 as likely to arise in the usual course of things from the breach".

    The editor cited several authorities and I think it would be sufficient if I only cite the

    case of Hirt v. Hahn [1876] 61 Missouri 496.

    B agreed to erect a house for the plaintiff according to plans by a certain day.

    The defendants were B's sureties. After partly completing, B ceased work,

  • 8/20/2019 CIPAA 2012, Contract Law and You

    7/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 7/18

    and the plaintiff, after giving notice to the sureties, entered and completed

    and sued the sureties. Held, that the measure of damage was what it cost the

    plaintiff to complete the house substantially as it was originally intended, and

    in a reasonable manner, less any amount that would have been due and

    payable to B by the plaintiff had B completed the house at the time agreed by

    the terms of his contract".

    That is an American case but the principle enunciated was approved by the Court of 

     Appeal in Mertens v. Home Freeholds Co [1921] 2 KB 526 at p. 535 where LordSterndale said:

    It is true that that is an American case. Though I cannot put my finger on them

    for the moment I feel satisfied that there are English cases which fix the same

    measure of damages. At any rate for the purpose of this case it is sufficient

    to say we all consider that the proper measures of damages for the breach of 

    a building contract such as this".

    However, the cost of completion means the cost of completing the contract work, but

    not different work. Thus in Milwaukee City v. Shailer [1898] 84 Fed Rep 106 another 

     American case, Shailer contracted to construct a tunnel for the city. The contract

    provided that in case of default, the city should be entitled to complete the work at

    Shailer's expense. On Shailer's default the city constructed a tunnel which was

    essentially different in plan and cost of construction from that contemplated by the

    contract. It was held that the city was not entitled to recover damages from Shailer.

    Mr McDonald, a quantity surveyor, testified that a total sum of $377,221.92 would be

    the cost of remedying defective work and completing the project from where the

    plaintiff had left it. He based his valuation on the current and appropriate building

    rates for this quality of work pertaining to this part of Malaysia. It must be borne in

    mind that the original contract price was $187,500, and the figure quoted by DW6

    would therefore include the cost for the variation and remedying defective work. Thecost of putting right defective work, he stated, was $21,095.75. Therefore,

    arithmetically, $168,720 would be the cost of the extra work. In this connection the

    cost of extra work must be considered in the light of all the surrounding

    circumstances. Thus an employer may have deliberately chosen a small-time

    contractor with limited resources of capital, plant and labour to do the work in the

    hope of getting a cheaper job. The plaintiff is a class 'E' PWD contractor with a

    ceiling of $50,000. As no fixed amount was agreed upon in respect of extra work,

    and considering that work was to be done by a contractor of the same class as the

    plaintiff, and in view of the principle enunciated in Milwaukee City v. Shailer, supra, I

    would consider a sum of $126,540 (750f $168,720) as reasonable. In the

    circumstances, the amount that would cost the defendant company to complete the

    work and remedy defects would be $335,135.75.

     As against that amount must be deducted the contract price as varied that would

    represent the costs which the plaintiff would have expended on the whole project as

    varied. I assess that figure in the following manner:

    Original contract price $187,500

    Extra work 74,000

    ;$261,500.00 ($74,000 is made up of $24,000, the cost of alteration from

    zinc walls to 9" brick walls; $40,000 for a third store; and $10,000 for labour 

    and miscellaneous expenses). From the amount of $261,500 must be

    deducted the sum of $36,000 as representing the fifth progress payment.

    Therefore the amount which would be due to the plaintiff would be $225,500.

    The measure of damages would be the difference between the reasonable costs of 

  • 8/20/2019 CIPAA 2012, Contract Law and You

    8/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 8/18

    Posted by Jonathan Rozario at 7:19 PM  No comments:

    completing the work as varied and the amount that would have been due to the

    plaintiff had he completed the work as varied, and that is $109,635.75.

    Recommend this on G oogle

    SATURDAY, MARCH 30, 2013

    Posted by Jonathan Rozario at 5:17 AM  No comments:

    Can You Refuse To Pay Contractors Costs?

    This question can be answered by looking at the express

    provisions in the contract.

    Unless there is an express provision in the contract that

    states the contractor will only be paid when the client pays

     “pay when paid”), the client should still pay on time, or the

    provisions of the late payment legislation will apply.

    It has been the norm for construction contracts to contain

    such provision, which means that even if the contractor

    completes the job, payment is still subject to the client

    himself getting paid.

    Such pay when paid clause will become void when the

    Construction Industry & Payment Adjudication Act 2012

    (“CIPPA 2012”) comes into force, and a default payment

    clause will be activated and it may be reasonable to imply

    payment terms of 30 days or sooner.

    If there is no provision for payment terms in the contract,then arguably payment may be due on presentation of theinvoice. Should the invoice not be paid promptly, thenCIPAA 2012 provides a quick and less expensive methodfor contractors to recover payment.

    What are the terms of the contract?

    Recommend this on G oogle

    FRIDAY, FEBRUARY 8, 2013

    Do I Need a Lawyer To Handle Payment Disputes In CIPAA 2012?

    Lets face it. The professional relationship with a lawyer is best described by U2... "I can't

    live, with or without you".

    Like it or not, if a payment dispute in a construction contract is brought to adjudication

    within the ambit of Construction Industry Payment & Adjudication Act 2012 ("CIPAA

    2012"), the services of lawyers will be inevitable, ultimately.

    CIPAA 2012 enables an unpaid party to make a "Payment Claim" for work done or goods

    / services supplied under a written contract for construction works carried out wholly or 

    partly in Malaysia. If the claim remains unpaid by the non-paying party, the unpaid party

    can then proceed to submit an "Adjudication Claim" lodged with the KLRCA, and thereon

    proceed with the appointment of the adjudicator, whose job will be to come up with the

    http://inares.blogspot.com/2013/02/do-i-need-lawyer-to-handle-payment.htmlhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6975956604066218494&target=pinteresthttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6975956604066218494&target=facebookhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6975956604066218494&target=twitterhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6975956604066218494&target=bloghttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6975956604066218494&target=emailhttp://inares.blogspot.com/2013/03/can-you-refuse-to-pay-contractors-costs.htmlhttp://inares.blogspot.com/2013/03/can-you-refuse-to-pay-contractors-costs.html#comment-formhttp://inares.blogspot.com/2013/03/can-you-refuse-to-pay-contractors-costs.htmlhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=22569588395424554&target=pinteresthttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=22569588395424554&target=facebookhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=22569588395424554&target=twitterhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=22569588395424554&target=bloghttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=22569588395424554&target=emailhttp://inares.blogspot.com/2013/05/pay-now-argue-later-and-cipaa-2012.html#comment-formhttp://inares.blogspot.com/2013/05/pay-now-argue-later-and-cipaa-2012.html

  • 8/20/2019 CIPAA 2012, Contract Law and You

    9/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 9/18

    adjudication decision which has to be delivered within 45 days of either the Adjudication

    Response or Adjudication Reply, whichever is the later.

     A two-tier involvement can be anticipated for lawyers in payment disputes brought for 

    adjudication in CIPAA 2012, i.e. - pre-adjudication decision and post-adjudication

    decision.

    CIPAA 2012 does not impose any specific format on parties for filing of various

    documents to bring or to defend a claim to be adjudicated by an adjudicator certified by

    Kuala Lumpur Regional Centre For Arbitration ("KLRCA") at this moment. This is quite

    unlike an action in the Courts whereby the format and filing of cause papers is determined

    by various statutes and therefore requires the services of a lawyer if one is to avoid the

    pitfalls of Do-It-Yourself litigation.

    The scope of involvement of lawyers at initial stages of the Payment Claim and Payment

    Response may not be required by parties, especially where the disputed amount is not

    substantial, and the payment dispute does not involve complicated facts and issues. The

    preparation of documents required for "Payment Claim" by the unpaid party and

    "Payment Response" by the non-paying party, and subsequently the "Adjudication Claim"

    and "Adjudication Response" can very well be handled by non-lawyers. It can be ably be

    dealt with by persons within the company with sufficient legal exposure, but with detailedpersonal knowledge as to the details of the dispute at hand. The key contribution a lawyer 

    can provide at this stage is to provide compilation expertise to prepare relevant

    submissions in what may turn out to be invaluable when the adjudication decision is

    disputed in Court or arbitration.

    If a lawyer is involved in the preparation of all documents and communications between

    parties and the appointed adjudicator prior to the adjudication decision, he / she will be

    able to provide valuable input in such preparation, including being able to keep an eye

    open to look out for issues which may result in improperly procured adjudication decision,

    such as denial of natural justice and bias, fraud, bribery, etc which can then be used to

    contest the adjudication decision and get it set aside by the Courts.

    The growth and penetration of CIPAA 2012 will largely depend on KLRCA, as theadjudication authority, who can be expected to introduce rules, policies and guidelines to

    regulate adjudication claims, including standardization of the format of cause papers and

    its administration. As this evolves, the level of expertise required to adhere to such rules

    will follow naturally and resulting in it becoming a specialized area for claim consultants

    which is likely to consist mostly of lawyers, or at the very least those who are legally

    trained.

    Both the winning and the aggrieved party can be expected to turn to the Courts., either to

    enforce the adjudication decision or to set aside and/or stay the execution of the same.

    So then, it follows that both parties will have to engage services of their lawyer as such

    applications are highly technical in nature with specific formats and procedures to adhere

    to.

    The options available to the aggrieved party includes:

    1. apply to the High Court to set aside the adjudication decision on grounds that it was

    improperly procured through :

      a. fraud or bribery;

      b. there has been a denial of natural justice;

      c. the adjudicator has not acted independently or impartiality; or 

      d. the adjudicator has acted in access of his jurisdiction.

    2. apply to the High Court for a stay of the adjudication decision.

    If a lawyer had been involved during the pre-adjudication decision, then he / she would

    have been able to identify the grounds on which the adjudication decision may be set

    aside.

    One thing is certain. The way documents are filed and kept will be of utmost importance

    A Two-Tier Involvement

    Pre-Adjudication Decision.

    Post-Adjudication Decision

  • 8/20/2019 CIPAA 2012, Contract Law and You

    10/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 10/18

    Posted by Jonathan Rozario at 4:00 PM  1 comment:

    in enabling the payment dispute to progress smoothly. Whether lawyers are involved or 

    not, the success or failure in such payment disputes will rest on parties' ability to compile

    its documents quickly, given the short time frames accorded to the parties for filing of 

    relevant cause papers under CIPAA 2012.

    Recommend this on G oogle

    SUNDAY, JANUARY 13, 2013

    How To Enforce An Adjudication Decision In CIPAA 2012 Malaysia

    The success of Construction Industry Payment & Adjudication Act 2012 ("CIPAA 2012")

    as a legal mechanism for unpaid parties in a construction contract for works carried out

    wholly or partly in Malaysia to settle payment disputes will be largely determined by the

    "bite" which enables the successful party to enforce the adjudication decision.

    If the unpaid party / claimant obtains an adjudication decision in his favour, s.28 CIPAA

    2012 empowers him to enforce it by applying to the High Court for an order as if it were a

     judgment or order of the High Court. This means that the whole gamut of enforcement via

    the Court including writ of seizure and sale, winding-up proceeding, bankruptcy, debtor 

    summons and likely garnishee order, is available by the winning unpaid party to enforce

    the decision obtained at adjudication.

    The key proviso is that the adjudication decision has not been stayed or set aside or 

    overruled by arbitration or the Court. However,as enforcement through the mechanisms

    of the Court will be costly and maybe time consuming, it is envisaged that it will be a

    disincentive in cases where the claim amount does not justify it.

    1. suspend the performance or reduce the rate of progress of performance in theconstruction contract in which the payment dispute arose;

    2. obtain payment of the adjudicated decision direct from the principal of the construction

    contract.

    If the proper procedure of providing written notice of intention to do so to the other party if 

    the adjudicated amount is not paid within 14 calendar days from the date of receipt of the

    notice. S.29 of CIPAA 2012 affords protection to the party who exercises his right to

    suspend or "go-slow" without having to repudiate or terminate the on-going construction

    contract, and also being able to be entitled to recover any loss and expenses incurred as

    a result of the suspension or "go-slow" from the Respondent of the adjudicated decision.

    The other option open to the unpaid party of the adjudication decision, pursuant to s.30

    CIPAA 2012 is to attempt to to get the principal of the party against whom the adjudication

    decision is made.

    This will only be effective if money is due or payable by the principal to the party against

    Respondent of the said decision, at the time the request was received from the unpaid

    party.

    If the said Respondent or losing party fails to show proof of payment to the unpaid party,

    the principal shall pay the adjudicated amount to the party who obtained the adjudicationdecision in his favour.

    Within CIPAA 2012, the principal referred to does not necessarily mean the ultimate

    Employer / Developer / Owner in the construction contract between the unpaid party

    Claimant and the non-paying party Respondent. The "principal" means the party one

    Enforcement Through the High Court of Malaysia

    Other than enforcement of the adjudication decision through the Court,

    CIPAA 2012 offers a rather more effective method of enforcing the said

    decision, i.e:

    1. Suspend or Slow Work Performance

    2. Direct Payment From Principal

    http://inares.blogspot.com/2013/01/how-to-enforce-adjudication-decision.htmlhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=1142843408249720645&target=pinteresthttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=1142843408249720645&target=facebookhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=1142843408249720645&target=twitterhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=1142843408249720645&target=bloghttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=1142843408249720645&target=emailhttp://inares.blogspot.com/2013/02/do-i-need-lawyer-to-handle-payment.html#comment-formhttp://inares.blogspot.com/2013/02/do-i-need-lawyer-to-handle-payment.html

  • 8/20/2019 CIPAA 2012, Contract Law and You

    11/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 11/18

    Posted by Jonathan Rozario at 3:52 AM  No comments:

    level above the said Respondent and in many cases may turn out to be the Main

    Contractor or even a sub-contractor as the construction industry in Malaysia tends to

    have a long chain in the construction process consisting of a chain of sub contractors,

    manpower providers, tools and machinery providers, outsourced maintenance

    contractors and services providers, consultancy services, hardware and building material

    suppliers, etc.

    It is anticipated after CIPAA 2012 comes into force, many principal / employers consisting

     owners, developers, main contractors and possibly large sub-contractors in the

    construction industry in Malaysia will be surprised to one day receive a notice demanding

    payment for the adjudicated amount for work done or goods supplied by a sub-contractor 

    or supplier 2 levels below the principal. Are you ready Malaysia?

    Recommend this on G oogle

    MONDAY, DECEMBER 10, 2012

    Construction Industry & Payment Adjudication Act 2012 - An Overview

    The construction industry in Malaysia is headed for a seismic upheaval in 2013, if industry

    players embrace the new payment regime imposed by CIPAA 2012. The Act will regulate

    payment disputes in the construction industry for construction works undertaken wholly or 

    partly in Malaysia for buildings, telecommunication, oil & gas, infrastructure, maintenance,

    exterior and interior design, and shall be extended to consultancy services such as

    architectural services, engineering, surveyors, planning & feasibility studies, project

    management, and procurement. The scope of CIPAA 2012 is extensive and extends to

    "services" and "supply".

    Payment disputes are the concern of this Act and can be brought to an adjudicator 

    certified by Kuala Lumpur Regional Centre of Arbitration (KLRCA) as an alternative

    form of dispute resolution. It is believed to be cheaper and faster than litigation through the

    Courts. This Act gives wide powers to the adjudicator with a view to enable a decision tobe made within 45 days upon the close of pleadings. As such, the underlying approach

    for justice of this Act is "Pay Now, Argue Later ". This rough justice approach lays in stark

    contrast to the fine justice approach adopted by the Courts.

    The adjudicator's decision is final and can be enforced in court, unless set aside or 

    stayed or brought to arbitration or appealed in court. Other avenues opened to the winning

    claimant if payment not settled by losing respondent within the time stipulated in the

    decision, is to slow work rate, stop work (without having to repudiate the contract) or 

    make a payment claim directly to the employer (a level directly above the

    respondent/losing party in the construction chain).

    This Act is expected to shake up the payment malaise currently afflicting the construction

    industry and related consultancy service providers. Conditional payment terms such as"Back-to-back " and "financial draw down" payment terms is prohibited and shall be

    deemed to be void pursuant to s. 35 CIPAA 2012. Payment shall be based on actual work

    done or goods delivered, if contract terms does not contain specific clauses governing

    payment or by operation of s.35 deemed void, reference to s.36 CIPAA 2012 shall be

    necessary. S. 36 provides for "the right to progress payment at a value calculated by

    reference" to the contract price, variation order or a reasonable cost of carrying remedial

    work or dimunition of value. Reference to prescribed fees by relevant regulatory board

    shall be made in the event there is no agreed or stipulated fees or price in the contract.

    The frequency of progress payment is monthly for construction work or construction

    consultancy services, and in cases of supply of construction materials, equipment or 

    workers, payment shall be upon delivery of such. The due date for payment is 30calendar days from the receipt of the invoice.

    This means that employers (not necessarily limited to developers / main contractors only,

    and may include the sub-contractor who purchases material or rents equipment) can no

    longer make reference to conditional payment terms in the contract or purchase order or 

    CIPAA 2012 - Are you ready Malaysia?

    An Overview

    http://inares.blogspot.com/2012/12/construction-industry-payment.htmlhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=4291010568330064874&target=pinteresthttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=4291010568330064874&target=facebookhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=4291010568330064874&target=twitterhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=4291010568330064874&target=bloghttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=4291010568330064874&target=emailhttp://inares.blogspot.com/2013/01/how-to-enforce-adjudication-decision.html#comment-formhttp://inares.blogspot.com/2013/01/how-to-enforce-adjudication-decision.html

  • 8/20/2019 CIPAA 2012, Contract Law and You

    12/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 12/18

    Posted by Jonathan Rozario at 6:11 AM  1 comment:

    work order to put off paying for work done or goods/materials, equipment or workers

    supplied to delay making payment in Malaysia anymore. The impact of CIPAA 2012, I

    believe, will be felt most within this scenario, which is likely to see suppliers or sub-sub

    contractors bringing payment disputes to the adjudicator upon after the invoice becoming

    due and unpaid.

     However, work done outside the scope of the contract, i.e quantum meruit, is not

    expected to be covered by this Act, unless a variation order in writing can be proved.

    So ready or not Malaysia, this Act will come into force upon execution by the Minister of 

    Works.

    Recommend this on G oogle

    MONDAY, DECEMBER 3, 2012

    Posted by Jonathan Rozario at 1:55 AM  No comments:

    Can The Main Contractor Impose Liquidated Damages Fixed Under TheMain Contract On A Subcontractor Who Finishes Late?

    Presumption : Subcontractor has contractual obligation to finish within a timescale and is

    in breach of the obligation if he completes late.

    Where a subcontractor is in breach he will have a liability to pay damages to the main

    contractor.

    The injured party is entitled to recover any loss likely to arise in the usual course of things

    from the breach, plus such other loss as was in the contemplation of the parties at the

    time the contract was made and which is likely to result from the breach.

    The main contractor, as injured party, is entitled to levy a claim for damages against a

    subcontractor who completes late. These damages will include any liability the main

    contractor has to pay liquidated damages to the employer which result from the delay.

    This will apply irrespective of the value of the subcontract work.

    It is open to the subcontractor to argue, if the main contract liquidated damages are

    extremely high, that the sum involved was outside his contemplation at the time the

    contract was entered into. To forestall this type of argument main contractors, usually

    with the tender enquiry documents will set out details of the main contract (including the

    sum included for liquidated damages).

    Where the subcontractor is nominated and the main contract provides for an extension of 

    time where work is delayed by the subcontractor no claim from the employer for 

    liquidated damages will arise provided that the contractor has properly claimed the

    extension of time.

    Relevant cases:

    1. Hadley v. Baxendale (1854)2. Victoria Laundry (Windsor) Ltd v. Newman Industries (1949)

    3. M.J. Gleeson plc v. taylor Woodrow Construction Ltd (1989)

    Recommend this on G oogle

    SUNDAY, SEPTEMBER 2, 2012

    Basics of Construction Contracts In Malaysia

    Construction projects typically involve several different parties – owners, designers, prime

    contractors, subcontractors, architects, consultants, suppliers – with different interests . Due to themany variables, construction projects have its associated risks . Therefore, the purpose of the

    construction contract is to:

    (1) allocate the duties between the parties;

    (2) recognize and allocate the risk to the different parties; and

    http://inares.blogspot.com/2012/09/basics-of-construction-contracts.htmlhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=741794146973922725&target=pinteresthttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=741794146973922725&target=facebookhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=741794146973922725&target=twitterhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=741794146973922725&target=bloghttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=741794146973922725&target=emailhttp://inares.blogspot.com/2012/12/can-main-contractor-impose-liquidated.htmlhttp://inares.blogspot.com/2012/12/can-main-contractor-impose-liquidated.html#comment-formhttp://inares.blogspot.com/2012/12/can-main-contractor-impose-liquidated.htmlhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6857667163659485539&target=pinteresthttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6857667163659485539&target=facebookhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6857667163659485539&target=twitterhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6857667163659485539&target=bloghttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=6857667163659485539&target=emailhttp://legal-dictionary.thefreedictionary.com/quantum+meruithttp://inares.blogspot.com/2012/12/construction-industry-payment.html#comment-formhttp://inares.blogspot.com/2012/12/construction-industry-payment.html

  • 8/20/2019 CIPAA 2012, Contract Law and You

    13/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 13/18

    (3) reduce the uncertainty surrounding the project and allow the parties to plan for the project and

    the future as best as possible.

    In Malaysia, the introduction of Construction Industry Payment & Adjudication Act 2012 ("CIPAA

    2012") is envisioned to regulate payment disputes which currently afflicts the construction industry.

    The scope of CIPAA 2012 is expected to include the oil & gas industry, petrochemical,

    telecommunication, utilities, infrastructure supply contracts, project and management, in addition to

    typical building construction projects.

    Construction work must be carried out wholly or partly in Malaysia, and any payment dispute arising

    from a written contract may be referred to an adjudicator registered with the KL Regional Centre for 

     Arbitration. The approach of such process is "PAY NOW, ARGUE LATER".

    Construction contracts may be verbal. However, it is recommended that construction contracts be

    in writing in order to bring any payment dispute to be adjudicated within the ambit of CIPAA 2012. A

    written contract presents a c lear record of the parties’ agreement, whereas and oral agreement is

    subject to the parties’ recollection of the terms.

    When entering into a written contract, the parties should make certain that the writing accurately

    reflects the agreement between the parties. The parole evidence rule may prohibit evidence of 

    contract terms differing from those in the written agreement. The integration clause of a contract

    also prohibits evidence of other terms or negotiations.

    It must be emphasized that CIPAA 2012 only recognizes written contracts and not verbal or oral

    contracts, to be adjudicated by a Kuala Lumpur Regional Centre of Arbitration (KLRCA) certified

    adjudicator.

    This is the typical contract with a negotiated lump sum price. This type of contract is preferred by

    owners for the following reasons:

      • owners can utilize a competitive bidding process

      • all risks are placed on the general contractor

    • the general contractor must control costs and perform efficiently

    Before entering into this type of contract, the owner must have detailed plans and specifications for 

    the project, and the general contractor must have clear and specific instructions and scope of work.

     A cost plus contract is often used in the absence of detailed plans and specifications. The general

    contractor is paid for all costs incurred. The general contractor is also normally paid a fee for 

    overhead and profit, plus a fee for general condit ions. The owner assumes all risks of excess ive

    costs . Frequently, an incentive provision is used to encourage cost savings by the general

    contractor.

    Similar to a cost-plus contract, but with some protection for the owner, utilizing a GMP (guaranteed

    maximum price) as a cap for project. The GMP is typically adjusted with each change order, just

    as a lump sum contract price is adjusted. This type of contract is amenable to the design build

    situation, where the general contractor also serves as a designer. The GMP is arrived at after the

    project has been completed to the design development stage.

    In most contracts, the contract documents are "incorporated by reference." Contract documents

    usually include plans and specifications, the “prime contract” between the owner and all prime

    Is a verbal agreement enforceable?

    Stipulated value or lump sum contracts?

    What is a cost plus contracts with a management fee?

    What is a GMP?

    What are the contract documents?

  • 8/20/2019 CIPAA 2012, Contract Law and You

    14/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 14/18

    contractors, including the general contractor, addenda, building codes and regulations, and

    modifications to the plans and specifications after execution of the contract.

    It is important for a contractor to review all contract documents incorporated by reference, as the

    terms of those documents may be binding on the contractor. For instance, if a prime contract

    (between the owner and a general contractor) contains an arbitration provisions, courts will typically

    enforce the arbitration requirement against a subcontractor in contract with the general contractor. It

    is not necessary, however, that contracts provide for adjudication before payment disputes are

    brought for adjudication within CIPAA 2012.

    On a smaller scale, a written contract may be referenced withi n documents used in the supply of goods and/or services,

    such as work order, purchase order, invoice, delivery order, etc.

    Disputes regarding scope of work are often the basis of construction claims. Scope of work is

    defined as the extent of a contractor's responsibility to perform certain contract work. To determine

    the scope of work, the contractor may have to look to other contract documents – plans and

    specifications, contracts with others – and to industry standards (building codes, etc.)

    The scope of work issues between the owner and the general contractor differ from the scope of work issues between the general contractor and subcontractors. The general contractor must be

    sure that all of the scope of work is contracted to subcontractors, and that there are no overlapping

    scope of work issues.

    Questions regarding scope of work should be resolved in the written contract . Scope of work

    references should be detailed in the contract. If detailed specifications are available, refer to the

    specifications in designating scope of work.

    It must be pointed out that the scope of CIPAA 2012 is limited to payment disputes.

    The price in the contract will either be lump sum, unit price, or time and material. The contract

    should include a definite price, or a definite method of determining price. Absent price, an otherwise

    valid contract will be interpreted as requiring payment of a fair value ( quantum meruit ).

    Progress payments are periodic payments constituting partial payment of the contract sum. The

    contract should include a specific provision for time and method of payment and calculation of 

    amount.

     A schedule of values should be prepared by the contractor and approved by the owner and

    architect. The schedule should accurately break down the scope of work into component parts, and

    assign a value to each component part.

    Applications for payment should be measured against the schedule of values. The application

    typically includes the amount of work in place, the cost of materials stored on site, the costs of 

    labor to date, less an amount for retainage and previous payments. The application is usually

    certified by the architect or owner and the payment is due thereafter.

    It must be noted that CIPAA 2012 prohibits conditional payment terms such as "Pay When Paid",

    "Back to Back" or " Pay If Paid".

    One of the greatest concerns and risks on a construction project is payment by the owner, or main

    contractor or employer. Once the contract work has been fully performed, everyone wants to be,

    and should be, fully paid. One of the risks of nonpayment is the owner's or main contractor's or 

    employer's potential inability to pay. Throughout the work chain of contractors, sub contractors,

    sub-sub contractors and suppliers there is a need to agree on who bears the risk of nonpayment –

    the general contractor or the subcontractor, etc

    Contractors routinely try to shift the burden of nonpayment to subcontractors. "Pay when paid" and

    "pay if paid" and "pay upon financial drawdown" provisions are popular and widely used. Such

    conditional payment terms only serve to delay the time for payment to the subcontractor even in

    situations where the contracted work has been completed and complied with.

    What is the scope of work?

    What is the contract sum?

    What are the methods for payment of the contract sum?

    Pay when paid, or pay if paid provisions

  • 8/20/2019 CIPAA 2012, Contract Law and You

    15/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 15/18

    Posted by Jonathan Rozario at 3:10 AM  No comments:

    Typical pay when paid clauses provide something like:

    "The total price paid to [subcontractor] shall be [contract price], no part of which shall be paid until 5

    days after payment is received from owner."

    or 

    ". . . the Contractor shall pay the Subcontractor each progress payment and final payment . . .

    within three working days after he receives payment from the Owner . . . ."

    In Thos. J. Dyer v. Bishop International Engineering Co., the Sixth Circuit U.S. Court of Appeals

    refused to enforce a pay when paid clause. In Dyer, a general contractor was not paid on a project

    after the owner declared bankruptcy. The general contractor, in turn, did not pay its subcontractor 

    for the work it performed.

    The introduction of CIPAA 2012 deems that such conditional payment are void and unenforceable.

    This, I believe, is where the impact of CIPAA 2012 will be keenly felt by players in the construction

    industry in Malaysia.

    Typical schedule provisions

    The schedule for completion of the contract work is an essential component of the contract, and a

    frequent focus of construction litigation. In a perfect world, the contract will incorporate a detailed

    computer generated completion schedule, with milestone dates for the essential tasks, and theschedule will be updated periodically to reflect changes in the schedule to reflect changes and

    progress.

     At a minimum, the prime contracts should include a date of commencement of the work,

    a project duration (the time that the prime contractor agrees to reach substantial completion of its

    scope of work), and a definition of substantial completion.

    The date of commencement is subject to change, based on several factors. The most common

    factors affecting the date of commencement influenced by the owner are owner funding, the delivery

    of final plans and specifications, the availability of the building permit. Changes in the date of 

    commencement change the date of substantial completion.

    The project duration is measure either in calendar days or working days, and is based on the

    number of days that the parties predict it will need to complete the project. Project duration is

    subject to lengthen based on several factors: changes directed by the owner, unforseen conditions,

    force majeure, weather, contractor issues.

    Recommend this on G oogle

    FRIDAY, AUGUST 24, 2012

    Natural Justice As The Basis To Set Aside An Adjudication Decision -Section 15 (b) Construction Industry Payment & Adjudication Act 2012 of Malaysia

    http://inares.blogspot.com/2012/08/natural-justice-as-basis-to-set-aside.htmlhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=7406769318517657256&target=pinteresthttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=7406769318517657256&target=facebookhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=7406769318517657256&target=twitterhttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=7406769318517657256&target=bloghttp://www.blogger.com/share-post.g?blogID=5836939343639792982&postID=7406769318517657256&target=emailhttp://inares.blogspot.com/2012/09/basics-of-construction-contracts.html#comment-formhttp://inares.blogspot.com/2012/09/basics-of-construction-contracts.html

  • 8/20/2019 CIPAA 2012, Contract Law and You

    16/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 16/18

    Section 15 Construction Industry Payment & Adjudication Act 2012 of Malaysia("CIPAA

    2012") provides that:-

    "An aggrieved party may apply to the High Court to set aside an adjudication decision on

    one or more of the following grounds:

    (a) The adjudication decision was improperly procured through fraud or bribery;

    (b) there has been a denial of natural justice;

    (c) the adjudicator has not acted independently or impartially; or 

    (d) the adjudicator has acted in excess of his jurisdiction."

    This post seeks to explore the concept of natural justice.

    It is a term that denotes specific procedural rights in the English legal system. There are

    two rules that natural justice is concerned with - the rule against bias and the right to a fair 

    hearing.

    This basic concept of impartiality where a person is barred from deciding any case inwhich he may be, or suspected to be biased, applies to courts of law, tribunals,

    arbitrators and all those having the duty to act judicially, including adjudicators.

    Bias may be actual, imputed or apparent. Actual bias is established where it is actually

    established that a decision-maker was prejudiced in favour of or against a party, which is

    in practice, very hard to prove.

    One form of imputed bias is biased on the decision-maker being a party to a suit, or 

    having a pecuniary or proprietary interest in the outcome of the decision. Once this fact

    has been established, the bias is irrebuttable and disqualification is automatic - the

    decision-maker will be barred from adjudicating the matter without the need for any

    investigation into the likelihood or suspicion of bias.

    In certain limited situations, bias can also be imputed when the decision-maker's interest

    in the decision is not pecuniary but personal.

     Apparent bias is present where a judge or other decision-maker is not party to a matter 

    and does not have an interest in its outcome, but through his conduct or behaviour gives

    rise to a suspicion that he is not impartial.

    Exceptions to the rule against bias includes Necessity and Waiver.

    Necessity is where a disqualified adjudicator cannot be replaced. as no one else is

    authorized to act. Waiver of the right to object, and proceedings are allowed to continue if 

    no objection is raised as soon as the prejudiced party has knowledge of the bias.

    The effect of a finding of bias - judgment not void but voidable. This advice is not wrong in

    the context of a judicial act under review, where the judgment will be held valid unless

    reversed on appeal.

    The aspects of a fair hearing includes:

    i. Prior notice of hearing - the right to adequate notification of the date, time, place of the

    hearing as well as detailed notification of the case to be met.

    ii. Opportunity to be heard - the right to have a hearing and be allowed to present his own

    case. However, this requirement does not necessarily mean the decision-maker has tomeet the complainant face to face.

    iii. Conduct of the hearing - the adjudicator has to ask whether the person charged has a

    proper opportunity to consider, challenge or contradict any evidence, and whether the

    person is also fullly aware of the nature of the allegations against him.

    When can an adjudication decision be set aside?

    What Is Natural Justice?

    1. Rule Against Bias

    2. Right To A Fair Hearing (Audi Alteram Partem)

    http://www.rcakl.org.my/userfiles/File/CIPAA%20Act%20746%20ENG.pdf

  • 8/20/2019 CIPAA 2012, Contract Law and You

    17/18

    5/10/2014 CIPAA 2012, Contract Law And You

    http://inares.blogspot.com/ 17/18

    iv. Right to legal representation

    The adjudicator issued a decision that the defender should repay the full amount withheld

    as liquidated and ascertained damages. The pursuer now raised proceedings to recover 

    the sums found due by the adjudicator by means of court proceedings via a motion for 

    summary decree. The only defence advanced was that the adjudicator's decision is

    vitiated by a breach of the principles of natural justice, due to the fact that the

    adjudicator had requested for to grant an extension of four days as he wished to "discuss

    one point in particular with [his] appointed legal adviser". The result of the discussions

    with the legal adviser was not made known to the parties, nor was either party told of the

    terms of the discussions that had taken place, or to see their result. Neither party was

    invited by the adjudicator to comment or make submissions upon the advice tendered,

    and neither party requested any opportunity to do so.

    Held :

    1. It is important that confidence in the adjudication process should be maintained. For 

    such confidence to be maintained, it is important that adjudicators should be clearly seen

    to give parties a fair opportunity to present their arguments by fulfilling the principle of audi 

    alteram partem.

    2. The mere possibility of injustice is sufficient for a challenge to an adjudicator's decision

    for the reasons set out in para 1. above. The parties do not know the content of the legal

    advice obtained by the adjudicator. It could have been crucial. Indeed, because the

    adjudicator asked for advice on a particular matter, it is reasonable inference that he

    thought that it was important. I do not think that the possibility of injustice can be excluded.

    3. I conclude that the defender has stated a relevant defence to the pursuer's claim to

    enforce the adjudicator's decision. It follows that the pursuer has not satisfied the test for 

    summary decree, namely that the question of law that arises as to the relevancy of the

    defender's averments admits of a clear and obvious answer in the pursuer's favour.

    Pursuer's motion for summary decree is refused.

    If an adjudicator's decision was to be challenged on account of a breach of the principles

    of natural justice, the breach must be substantial and relevant.

    Lord Reid - this is at least clear : no tribunal, however informal, can be entitled to reach a

    decision against any person without giving to him some proper opportunity to put forward

    his case.

    This is a case involving a statutory tribunal that determined the valuation of wool.

    Lord President Clyde - "Although quasi-judicial bodies such as this tribunal are not Courts

    of law in the full sense, it has been the law of Scotland that they must conform to certain

    standards of fair play, and their failure to do so entitles a Court of law to reduce their 

    decisions. Were it not so, such tribunals would soon fall into public disrepute, and

    confidence in them would evaporate. Fair and equal opportunity afforded to all interests

    before the tribunal is the fundamental basis upon which the tribunal must operate, and, in

    the absence of such fair play to all, it is right and proper that a Court of law should reduce

    the tribunal's decision...

    The test is not 'Has an unjust result been reached?' But 'Was there an opportunity

    afforded for injustice to be done?' If there was such an opportunity, the decision cannot

    stand".

    It was accepted that the principles of natural justice were applicable to adjudication

    proceedings. It was further accepted that if an adjudicator obtains material from sources

    other than the parties, including his own knowledge and experience, he must give the

    parties a reasonable opportunity to comment on that material.

    Summary of Cases

    1. Costain Ltd v. Strathclyde Builders Ltd [2003]

    2. Discain Project Services Ltd v Opecprime Development Ltd [2001]

    3. Inland Revenue v Barrs [1961]

    4. Barrs v British Wool Marketing Board [1957]

    5. Balfour Beatty Construction Ltd v London Borough of Lambeth [2002]

  • 8/20/2019 CIPAA 2012, Contract Law and You

    18/18