CIM Health Check. Raj Chudgar Program Director for Market Redesign. 2. Major challenge for Nodal is the successful integration of CIM data between NMMS, EMS, MMS and other Nodal systems. 1. 2. 3. 4. 3. CIM critical dependency is on successful model integration of EMS, MMS and NMMS. - PowerPoint PPT Presentation
Citation preview
TPTF
CIM Health Check
Raj ChudgarProgram Director for Market Redesign
TPTF2
CIM XML
CRR
CIM XML
AREVA CIM Importer
ABB CIM Importer
Nodal – EMS
SESCADA
TCM
Dyn Ratings
FOD
RLC
LFC
AS Mon
MMS
SCED
RUC
DAM
NMMS
CIM Importer
CIM Exporter
Augmented PSSE File
Registration
OS
MIS
Outages for CRR
Equipment List
CIM XML
ZONALEMS
AREVA CIM EXPORTER
Major challenge for Nodal is the successful integration of CIM data between NMMS, EMS, MMS and other Nodal systems
CIM critical dependency is on successful model integration of EMS, MMS and NMMS
1
23
4
TPTF3
CIM Impacts on the Nodal Early Delivery Systems (EDS)
EDS 2 Release 4 NOMCR Checkout and Network Model Verification
Current X X X
EDS 3 Release 6.3 LFC Testing ERCOT system June ‘08 X X X
EDS 3 Release 7.5 CRR Integration Testing June ‘08 X
EDS 4 Release 9.3 Initial DAM/RUC Execution *(as discussed at last TPTF, ERCOT is implementing a workaround to start 9.3)
April ’08 X X X
EDS 4 Release 9.4 DAM, RUC and Adjustment Period Execution
May ’08 X X X
EDS 4 Release 9.5 Execute Full Nodal Integrated System
July ’08 X X X
EMS Z
onal
Expor
ter
NMM
S Exp
orte
r
MM
S Impo
rter
EMS Im
porte
r
14 2 3
TPTF4
CIM Exporter/Importer still under development – making progress, final health check at next TPTF meeting, listed below is the current state
Design/BuildExporter/Importer
Design Documents Complete & Build
TestingCIM Exporter or
CIM Importer Test Plan
Data ValidationData Model and
Data
Market Trials Mitigation
NMMS
Initial Design complete. Refactoring in progress.
ERCOT NMMS testing exporter since April
2007
Data Model: updated per downstream system
request. Will need to sync up data model versions in
the future
Data: ON GOING, waiting for EMS importer
NOMCR Market Trials • Model exchange with multiple vendors on-going
• Planning Interoperability Test with all vendors at ERCOT
MMS
Initial Design complete. Refactoring in progress
MMS CIM importer testing since November
2007. Outstanding issues communicated to
NMMS team
Data Model: Few critical issues remain. MMS
Application able to import NMMS Nodal Model. Will
need to sync up data model versions in the
future
Data: ON GOING,
Starting to use CIM for 9.3 Trials
• ABB maintaining detailed prioritized spreadsheet with all modeling and data issues.
• ERCOT helping define and execute CIM importer tests during MMS3 pre-FAT&FAT and MMS4 pre-FAT&FAT
• ERCOT performing internal due diligence of all CIM attributes necessary to execute all functions
• Regular conversations on the status of the CIM importer between ERCOT & ABB (technical leads, project engineers and project managers)
EMS
Initial Design in progress. Network Model testing in progress.
Data model: Network model validation in
progress. Will need to sync up data model
versions in the future
Data: ON GOING
Not Using CIM • ERCOT escalation to AREVA mgmt on delay of product
• ERCOT personnel planned to be at AREVA to push delivery
• ERCOT doing preliminary testing in parallel to reduce testing cycle
• ERCOT setting up hardware in advance of product delivery
1
2
3
CIM Component Measurement Items