119
COMMERCIAL BUILDING SERVICES FLOW THINKING Chilled Water System Presentation

Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Chilled Water System Presentation

Page 2: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Constant Volume DistributionConstant Volume Distribution

Page 3: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Air-conditioning System Components

Page 4: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Constant Volume System Components

Page 5: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Typical 3-way Valve Zone

Page 6: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Full Load Condition

Page 7: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Fully Loaded Coil

• Supply water temperature 45°F

• Design return water temp. 55°F

• Coil design flow 100 GPM

• Coil design pressure drop 20 FT

• Load (flow x 10°F∆ x 500) 500,000 Btuh

• Coil ∆P @ design flow 20 FT

• Bypass flow 0 GPM

• Bypass ∆P 3-way valve closed

• 3-way valve pressure drop 10 FT

• Pump flow and head 100 GPM @ 30 FT

• Actual return water temp 55 °F

Page 8: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Unloaded Condition

Page 9: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Unloaded Coil

• Supply water temperature 45°F

• Design return water temp. 55°F

• Coil design flow 0 GPM

• Coil design pressure drop 3-way valve closed

• Load (flow x 10°F∆ x 500) 0.0 Btuh

• Coil ∆P @ design flow 0 FT

• Bypass flow 100 GPM

• Bypass ∆P 20 FT

• 3-way valve pressure drop 10 FT

• Pump flow and head 100 GPM @ 30 FT

• Actual return water temp 45 °F

Page 10: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

So What?

• When the load on the coil is zero, the valve is returning “unused”chilled water at essentially supply temperature.

• Cold return water “unloads” the chillers, causing them to operate inefficiently.

Page 11: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Part Load Condition

Page 12: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Partially Loaded Coil

• Supply water temperature 45°F

• Design return water temp. 55°F

• Coil design flow 50 GPM

• Coil design pressure drop 20 FT

• Load (flow x 10°F∆ x 500) 250,000 Btuh

• Coil ∆P @ design flow 5 FT

• Bypass flow ??? GPM

• Bypass ∆P 3-way partially closed

• 3-way valve pressure drop 10 FT

• Pump flow and head ??? GPM @ 30 FT

• Actual return water temp ?? °F

Page 13: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

125

100

75

50

25

0

% Valve Stroke 25 50 75 100

% F

low

1/2 Through Coil1/2 Through Bypass

Fu

ll F

low

T

hro

ug

h C

oil

Fu

ll F

low

T

hro

ugh

Byp

ass

3-way Valve Characteristic

Page 14: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

What’s Really Happening?

Page 15: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Coil with 3-way Valve at Mid-position

• Supply water temperature 45 °F

• Design return water temp. 55 °F

• Load (flow x 10°F∆ x 500) 250,000 Btuh

• Coil design pressure drop 20 FT

• Coil flow 62.5 GPM

• Coil ∆P @ 62.5% flow 7.8 FT

• Coil leaving water temp 53 °F

• Bypass flow 62.5 GPM

• Bypass ∆P 7.8 FT

• 3-way valve pressure drop 10 FT

• Pump flow and head 125 GPM @ 30 FT

• Actual return water temp 49 °F (62.5 GPM @ 53 °F+

62.5 GPM @ 45 °F)

Page 16: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Head2 = Head1(Flow2/ Flow1)2

Head2 = 20(.625/1)2

Head2 = 20(.3906 )

Head2 = 7.8

Page 17: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

∆T = Load/ Flow X 500

∆T = 250,000/62.5 X 500

∆T = 8

Therefore, LWTcoil = 45 + 8 = 53

Page 18: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

RWT = (Flow1 X EWT + Flow2 X LWT)/ Flow1 + 2

RWT = (62.5 X 45 + 62.5 X 53)/125

RWT = 49

Page 19: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

3-way Valve in Mid Position

Page 20: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

1. Low return water temperatures.2. Robs chilled water from other coils at part

load conditions.3. Increases flow in primary piping.4. Adds additional chillers on line.5. Chiller performance is reduced.

3-way Valve System Deficiencies

Page 21: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

1.1

20 30 40 50 60 70 80 90 10010

1.0

0.9

0.8

0.7

0.6

0.5

KW

per T

on

Percent Load

Chiller Performance Curve

Page 22: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Pump Sizing

• Select for full chiller flow

• Head must be adequate for:

– Chiller evaporator

– Longest circuit

– Coil

– Three way valve

– Air separator

Page 23: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

System Configuration

Constant Volume

Page 24: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

Any Questions?

Page 25: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

Variable Volume Constant Speed

Page 26: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Primary – Secondary System

Primary – Includes Chillers & Primary Pump. Circuit Constant water flow through the chiller

is maintained and chilled water isproduced

Secondary – Chilled water is circulated to the Circuit demand area (load) by using

Secondary pumps.

Variable Volume Constant Speed

Page 27: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

PRIMARY - SECONDARY

Page 28: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Other Famous Names of Primary-Secondary

Primary – Production Loop

Secondary – Distribution Loop

Page 29: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Fundamental Idea

Page 30: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

No Secondary Flow

Page 31: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Primary = Secondary

Page 32: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Primary > Secondary

Page 33: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Primary < Secondary

Page 34: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Control Valve in Secondary

Page 35: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

• Use the flow of the largest chiller

– Chiller staging at half of this flow is common

• Head loss in common <1 1/2 ft

– Distribution pipe size is often used where reductions would be inconvenient

• Three pipe diameters between tees

– Excessive length increases total head loss

• Low velocities in system piping

Common Pipe Design Criteria

Page 36: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Variable flow through coil Constant flow through system

Three Way Valve

Variable flow through coil Variable flow through system

Two Way Valve

Control Valve in Secondary

Page 37: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

PRIMARY – SECONDARY CIRCUIT

Variable Volume Constant Speed

Page 38: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Head

F1 F2 F3

H1

H2

H3

Flow

Control Valves Change the Secondary System Curve

Page 39: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

% Flow

125

100

75

50

25

150

25 50 75 100

HDVarying differential pressure absorbed by control valve

System resistance

TDH of pump

Pump curve

Head Absorbed by 2-way Valves

Page 40: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

HP

125

100

75

50

25

150

25 50 75 100

% Design Flow

Primary Pumps = V/V

Secondary Pumps +

Constant Flow Primary Pumps, only

Pump Horsepower Comparison

Page 41: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

% Flow

90

80

70

60

50

40

30

20

10

0 10 1009080706050403020

100

110

120

130

140

150

BaseDesignHP %

% Full Load(Design) HP

Pump Over-haded by 150%Constant Flow, C/S Pump

(3 Way Valve)

Constant Flow, C/S Pump

(3 Way Valve)

C/S Pump(2 Way Valve)

Pump HD Matchedto System @Design Flow

C/S P

ump (2 W

ay Valve)

Constant vs Variable Volume

Page 42: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

Any Questions?

Page 43: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

Step Function of Chillers

Page 44: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Production = Distribution

Page 45: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Distribution > Production

Page 46: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Production > Distribution

Page 47: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

“Loading” a Chiller

• A chiller is a heat transfer device. Like most equipment, it ismost efficient at full load.

• To “load” a chiller means:

– Supply it with its rated flow of water

– Insure that water is warm enough to permit removal of rated Btu without freezing the water

Page 48: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Chiller Performance Curve

1.1

20 30 40 50 60 70 80 90 10010

1.0

0.9

0.8

0.7

0.6

0.5

KW

per T

on

Percent Load

Page 49: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Check Valve in Common?

Page 50: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

What can we do?

Page 51: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

What else can we do?Reset Supply Temperature

• Lower chiller set point when mixing occurs to maintain a constant temperature to the system.

• Expect increases in cost of chiller operation at lower set point: 1-3% per degree of reset.

• Delays start of the next chiller.

Page 52: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

What else can we do?

• Coils that are selected at higher supply temperatures will not be impaired by small changes.

• Loads that require fixed temperatures may use a small chiller toreverse the effects of mixing.

Page 53: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Multiple Chillers

Page 54: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

60/40 Chiller Split to Help Minimize Low Part Load Operation

Page 55: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

0-10 30-40 60-70 90-1000

5

10

15

20

25

30

0-10 30-40 60-70 90-100

% T

ime

% Load

Typical Load Profile

Page 56: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Three Unequally Sized Chillers

Page 57: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

% Load

Time

Approaching Flow = Load

Page 58: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

Any Questions?Alternate

Pumping MethodsComparison

Page 59: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Two Pipe Direct Return

Page 60: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Two Pipe Reverse Return

Page 61: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Primary-Secondary Pumping.

• Simplest to install.

• Simplest to operate.

• Flexible in design for present and future.

• Efficient to operate.

• May over-pressurize near zones.

Page 62: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Primary-Secondary-Tertiary

Page 63: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Primary-Secondary-Tertiary Pumping.

• Best piping flexibility.

• Best expansion flexibility.

• Provides hydraulic decoupling.

• Efficient to operate.

• May require added horsepower.

• Requires additional pumps and piping.

• Increased controls complexity.

Page 64: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Primary-Secondary-Tertiary Hybrid

Page 65: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Primary-Secondary-Tertiary Hybrid Pumping.

• Low present horsepower.

• Low future horsepower.

• Good piping flexibility.

• Good expansion flexibility.

• Provides hydraulic decoupling.

• May require added horsepower

• Requires additional pumps and piping.

• Increased controls complexity.

Page 66: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Primary-Secondary Zone Pumping

Page 67: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Primary-Secondary Zone Pumping.

• Low ‘built out’ horsepower.

• Low system head.

• Increased control complexity.

• Present horsepower total higher due to future needs.

• Present pumps sized for future requirements.

• Difficult to apply in retrofits projects.

Page 68: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

Any Questions?

Page 69: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

Variable Volume Variable Speed

Page 70: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Why Do We Need Variable Speed Secondary Pumps ???

•For Energy Saving….

•For better & optimise operation….

Page 71: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

How Do We Achieve This Reduction In Power Consumption ??

By Using Variable Frequency Drive and Logic controller with the Secondary Pumps….

Page 72: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Power Comparison at Reduced Speed

Page 73: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Basic Law which helps in achieving this – Affinity law

1. Flow2 = Flow1(Speed2/ Speed1)

2. Head2 = Head1(Speed2/ Speed1)2

3. BKW2 = BKW1(Speed2/ Speed1)3

If Diameter of Impeller is to be trimmed then instead of speed the same can be used in above formulas.

Page 74: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

0

50

100

150

200

250

300

350

400

450

50 100 150 200 250 300 350 400 450 500

Motor Horsepower

An

nu

al O

pe

rati

ng

Co

st

$1

00

0

$0.10/kWh

Operating Cost

Page 75: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Head

Flow

Pump Curve

System

Curve

System Curveas two wayvalves close

Variable flow system

Page 76: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Q

H

Pump Curve

System Curveat design flow

System Curveat part load

Increased head loss

Energy savings offset

Page 77: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Head

Flow

SinglePump

Pumps inParallel

SystemCurve

Pumps in parallel

Page 78: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Horsepower%

100

90

80

70

60

50

40

30

20

10

00 10 20 30 40 50 60 70 80 90 100

Flow%

Single Large Pump

Two ParallelPumps

Single ParallelPump

Parallel pumping power savings

Page 79: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Theoretical Savings

Page 80: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

���

���

���

��

��

��

��

��

��

��

��� ��� ��� ��� ��� �� �� ��� ��� �����

100 %

90 %

80 %

70 %

60 %

50%

40 %

30 %

80 %

85 %80 %70 %60 %50 %

85 %

% Speed Curves

Constant Efficiency Curve

% EfficiencyH

ead,

Fe

et

GPM

Establishing Efficiency Curves

Page 81: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

750

900 1150 1450 1770600

900

1150

1450

1770

600

A

B

C

D

E

4500 gpm @ 100 FT, 85.9 %

Variable Speed Efficiencies

Page 82: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

“No Valve” System Curve

Flow

piping headloss curve

Distribution

Pum

p T

DH

Overall system curve

Head 80

60

40

20

110

0200 400 600 800 1000 1200 1400 16000

100

Set Point

25 FT Differential Head Maintained Across Load

(Set Point)

Page 83: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Effect of Constant Set Point

piping headloss curve

Distribution

Pum

p T

DH

Overall system curve

Head

80

60

40

20

110

0200 400 600 800 1000 1200 1400 16000

Flow

100

Control curveSet point,

25 FT

Page 84: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

100%

75%

50%

Flow

Head

Control Curve

Variable Head Loss∆P

P1 P2

Control curve

Page 85: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Annual

Operating

Cost

($1000/year

@

$0.10/kwh)

50

45

40

35

30

25

20

15

10

05

00

1000 2000 3000 4000 5000

Total Equivalent Pipe Length (feet)

Single C/S Pump, N

o Overheading

Singl

e C/S

Pum

p, 2

00%

Ove

rhea

ded

Variable Speed Pump

Large systems, long pipe runs

Page 86: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Variable Head Loss Ratio

Perc

ent D

esig

n B

HP

% Flow

90

80

70

60

50

40

30

20

10

0 10 1009080706050403020

100C/S, Constant Flow System Pump Head Matched to

System at Design Flow

C/S, Variable Flow

V/S, 0% Variable Hd Loss, 100% Constant ∆ Hd

V/S, 25% Variable Hd Loss, 75% Constant ∆ Hd

V/S, 50% Variable Hd Loss, 50% Constant ∆ Hd

V/S, 75% Variable Hd Loss, 25% Constant ∆ Hd

V/S, 100% Variable Hd Loss, 0% Constant ∆ Hd

Base

Page 87: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Variable Head Ratio w/ Overheading

90

80

70

60

50

40

30

20

10

0 10 1009080706050403020

100

110

120

130

140

150

BaseDesignHP %

% Full Load(Design) HP

Pump O’Headed by 150%Constant Flow, C/S Pump

(3 Way Valve)

Constant Flow, C/S Pump

(3 Way Valve)

C/S Pump(2 Way Valve)

Pump HD Matchedto System @Design Flow

* 25/75 Means:25 % Variable HD Loss75 % Constant HD Loss

C/S Pump (2 W

ay Valve)

V/S, 1

00% Constant H

D

V/S, 25/75*

V/S, 50/50

V/S, 75/25

V/S, 1

00% V

ariable H

D

Page 88: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Locations of Sensor

Where to install the Sensor?

What type of Sensor?

Page 89: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Chillers

Primary Pumps

Secondary Pumps

Load

Balancing Valve 2 – Way Valve

Panel with PLC & VFD`s

Air -Separator

Co

mm

on

Single Point Pressure Sensing

Single Point Pressure Sensor

Page 90: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Single Point Pressure Sensor

Is Single Point Pressure Sensor Correct?

Wrong !!

Why?

-Pump is a differential pressure device.

-A single point is only influence by pressure. This is good for booster only.

-In a closed loop system, system pressure rises due to thermal expansion,

pumps will slow down.

-When static pressure decrease, pumps will speed up.

-This is self-defeating since now the pump speed is not influence by the

system load changes, but rather by system water pressure.

-Therefore, single pressure sensor are a misapplication in a closed loop

HVAC system.

Page 91: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Chillers

Primary Pumps

Secondary Pumps

Load

Balancing Valve 2 – Way Valve

Panel with PLC & VFD`s

Air -Separator

Co

mm

on

Primary - Secondary Circuit With Variable Speed Secondary Pumps

DPT

Single Point Differential Pressure Sensor

Page 92: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Opening/Closing of 2- Way Valve-Signal from the sensor, installed at load

regulates the valve opening & closing.

-This way differential across 2-way valve also

changes & accordingly output signal is given to

PLC.

```

Temperature Sensor

Load

Output to PFU from DPT

2 Way Valve Control

Page 93: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

Question:

Can we put the DPT across coil alone?

Page 94: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

Question:

Across the pumps?

Page 95: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Primary - Secondary Circuit With Variable Speed Secondary Pumps

Single Point Differential Pressure Sensor

To Maximize energy system, we must maximize the

variable head loss in the system. This is done by locating

the sensor at the most remote zone ( hydraulically) in the

system.

Page 96: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

piping head loss curve

Distribution

Pu

mp

TD

H

Overall system curve

Ft H

d

80

60

40

20

110

0

200 400 600 800 1000 1200 1400 16000

Flow, gpm

100

Control curve

Set point, 25 FT

System Control Curve

Page 97: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Variable vs Constant Head Loss

Page 98: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

The “Active Zone”

• Zone set points do not have to be the same.

• Pump controller scans all zones often, comparing process variable to set point in each case.

• Pumps are controlled to satisfy the worst case.

• What happens to the rest of the zones?

Page 99: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

PFU

PMU

4 – 20 mA

Set Value

From Field Sensor (DPT)

PFU – Pump Functional Unit

PMU – Pump Management Unit

Basic Concept

Output

To

VFD/Pump

Page 100: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

ChillersSecondary

Pumps

Balancing Valve

DPTDPT

Co

mm

on

Panel with PLC & VFD`s

Load

Different Sensor Signal To Common PFU Panel

Multi Point Differential Pressure Sensor

Page 101: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

PFU

PMU

Set Value

Multiple Process Signals From Field Sensors

POSSIBILITY OF MULTIPLE PROCESS SIGNALS FROM DIFFERENT ZONES

All zones can have different set values

Module

VFD

VFD

Multi Point Differential Pressure Sensor

Page 102: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

PFU

PMU

Set ValueMultiple Process Signals From Field Sensors

POSSIBILITY OF MULTIPLE PROCESS SIGNALS FROM DIFFERENT ZONES

All zones can have different set values

Signal

Comparator

VFD

VFD

Multi Point Differential Pressure Sensor

Signal

Comparator

4 – 20 mA Sig

Page 103: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

HVAC Control System

DPT Signal Comparator

Page 104: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

HVAC Control System

DPT Signal Comparator

- High and Low Signal Selections

- Signal Averaging

- High/Low Limit Control

The module has the addition following features :

1) LED status indications

2) Accepts voltage or milliamp input signal

3) DIP switch-selectable operating modes

4) Accepts 24 VAC/DC power

Page 105: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

HVAC Control System

DPT Signal Comparator

Benefits

1) We are able to supply VFD systems with multiple inputs signals ranges to compete

with our competitors.

2) We are able to use Grundfos PFU 2000 as the main processor to control the full system

operations.

3) We will be minimising outsourcing or external controller in order to serve the HVAC

market.

4) The MM allows us to integrate into the system multiple sensor control at a more cost

effective price.

Page 106: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Other Types of Systems

HVAC System

Page 107: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Chillers

Primary Pumps

Balancing Valve

Secondary Pumps

Air -Separator

Expansion Tank

Load

Panel with PLC & VFD`s

Co

mm

on

DPT

2 – Way Valve

DPT

Separate System for Each Zone

Page 108: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Systems In Multi - Zones

Two options:

1. Separate Systems can be used for different zones. So each zone will have its own sensor.

2. Signal from different zone sensors is given to the common PFU and most deviated signal, from the set point, is given as output.

Separate System for Each Zone

Page 109: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Chillers

Primary Pumps

Balancing Valve

Air -Separator

Expansion Tank

Load

Co

mm

on

DPT

2 – Way Valve

DPTVFD pumps For Each Zone

E-pumpsE-pumps

Tertiary Pumping System

Secondary Pump

Page 110: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Reverse Return Pumping

Load

Air -Separator

Chillers

Primary Pumps

Secondary Pumps

Balancing Valve

Panel with PLC & VFD`s

Co

mm

on

DPT

Page 111: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Reverse Return Pumping

Benefits :

1) Equalize the pressure drops of each zone.

2) Selections of the sensor becomes easier.

3) If load are similar or symmetrical, 1 centrally located sensor

is adequate.

4) As in direct return system, multiple sensor can still provide a

benefit to the end user.

Page 112: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Type of VFD Systems

Page 113: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Possible Options of Variable Speed panels

Type ME - Multiple Pumps & Multiple VFDs.

Type MF - Common VFD for Multiple Pumps.

Page 114: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Signal from Field Sensor(s) (DPT)

Panel with

PFU & PMU

VFD - 1 VFD - 2

Secondary Pumps

System with Multi Pumps & Multi VFDs

Page 115: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

Signal from Field Sensor(s) (DPT)

VFD

Panel with

PFU & PMU

Secondary Pumps

System with Common VFD for All Pumps

Page 116: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

APPROVAL FROM INTERNATIONAL AGENCIES

Approval from – CE, U/L Conforms to - Electromagnetic compatibility (89/336/EEC) to standard EN 50 081 – 1 and EN 50 082 – 2 and Electrical equipment design 73/23/EEC standard to EN 60 204-1.

Page 117: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

PFU

PMU

Single PMU For Control of 8 Zones/Pumps

PFU

Page 118: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

COMMERCIAL BUILDING SERVICES FLOW THINKING

PFU

PMU

Single PMU For Control of 8 Zones/Pumps

PFUPFU PFU

Page 119: Chilled Water System Presentation– Chiller evaporator – Longest circuit – Coil – Three way valve – Air separator. COMMERCIAL BUILDING SERVICES FLOW THINKING System Configuration

The End