Upload
umar-farooq
View
36
Download
3
Embed Size (px)
DESCRIPTION
a detaile check list for site construction works.
Citation preview
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/CL List Page 1 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
LIST OF CHECKLIST 1 of 1 0
LIST OF CHECKLIST
S.No. Description oF Checklist Form # Rev. #
1 Blank Template No Number *
2 Checklist for transfer of benchmark OHL-CL/FORM/CL/1001 0
3 Checklist for turnover of Benchmark to sub contractor OHL-CL/FORM/CL/1002 0
4 Checklist for Earthwork - Excavation Operations OHL-CL/FORM/CL/1003 0
5 Checklist for Earthwork - Backfilling Operations OHL-CL/FORM/CL/1004 0
6 Stockpile Log for Earthfill OHL-CL/FORM/CL/1005 0
7 Checklist for anti termite treatment + Anti-Termite Application Report (2 Sheets) OHL-CL/FORM/CL/1006 0
8 Checklist for Blinding OHL-CL/FORM/CL/1007 1
9 Checklist for reinforced concrete - Vertical OHL-CL/FORM/CL/1008 1
10 Checklist for reinforced concrete - Slabs and footings OHL-CL/FORM/CL/1009 0
11 Concrete pour log OHL-CL/FORM/CL/1010 0
12 Concrete Cube Register OHL-CL/FORM/CL/1011 0
13 Checklist for concrete masonry works OHL-CL/FORM/CL/1012 0
14 Mortar cube register OHL-CL/FORM/CL/1013 0
15 Checklist for plaster/ render works OHL-CL/FORM/CL/1014 0
16 Work Clearance request OHL-CL/FORM/CL/1015 0
17 DFT Record OHL-CL/FORM/CL/1016 0
18 WFT Record OHL-CL/FORM/CL/1017 0
19 CL for dowel/ rebar planting OHL-CL/FORM/CL/1018 0
20 Weekly Concrete Requisition OHL-CL/FORM/CL/1019 0
21 Weekly Concrete Planner OHL-CL/FORM/CL/1020 0
22 TPI Requisition Form for Inspection/ Testing OHL-CL/FORM/CL/1021 0
23 Log of Third Party Inspection Report/ Testing OHL-CL/FORM/CL/1022 0
24 Weld Visual Inspection Report OHL-CL/FORM/CL/1023 0
25 Punch List OHL-CL/FORM/CL/1024 0
26 CMU Test Log OHL-CL/FORM/CL/1025 0
27 Grout Cube Register OHL-CL/FORM/CL/1026 0
28 Trial Mix Details OHL-CL/FORM/CL/1027 0
29 NCN/ NCR/ SQN Register OHL-CL/FORM/CL/1028 0
30 Concrete Trial Mix Worksheet OHL-CL/FORM/CL/1029 0
31 Weekly mortar/ grout requirement OHL-CL/FORM/CL/1030 0
32 Weekly mortar/ grout planner OHL-CL/FORM/CL/1031 0
33 Checklist for sub structure waterproofing
34 Checklist for Painting works
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
Under Construction and to be submitted progressively as an
attachment to the relevant Method Statement. Sample forms for Items #
1-32 listed above are enclosed.
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/CL List Page 2 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
LIST OF CHECKLIST 1 of 1 0
LIST OF CHECKLIST
S.No. Description oF Checklist Form # Rev. #
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
35 Checklist for Fire proofing paint application
36 Checklist for dry wall installation
37 Checklist for false ceiling works
38 Checklist for tile installation - Dry areas
39 Checklist for tile installation - Wet areas
40 Checklist for Structural Steel erection
41 Checklist for joinery works
42 Checklist for cladding
43 Checklist for curtain walling
44 Checklist for glazing
45 Checklist for concrete repairs
46 Checklist for roofing
47 Checklist for Raised Floors
NOTE:
Under Construction and to be submitted progressively as an
attachment to the relevant Method Statement. Sample forms for Items #
1-32 listed above are enclosed.
The above list is indicative only and Items may be added/ deleted to this list progressively to suit the contract requirements.
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Template Page 3 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
TEMPLATE FOR CHECKLIST 1 of 1 0
Blank Template Only
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/BM-1 Page 4 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
CHECKLIST FOR TRANSFER OF BENCHMARK 1 of 1 0
CHECKLIST FOR TRANSFER OF BENCHMARK
Date: JV Form # OHL-CL/FORM/CL/1001-REV 0
Reference to RFIT # (Only if applicable) Checklist #
Location: Sub Contractor (If app.)
S.NO. DESCRIPTION/ TOPICCOMPLIANCE
REMARKSYes No N/A
1 Ensure survey equipment has a valid calibration.
Equipment # Calibration valid till Raise RFIT
2 Permanent bench mark shown by: QP/ KEO/ Others (Circle appropriate) Name:
3 Are these Government installed permanent bench mark
4 How many permamnent bench marks are turned over to us: Insert Number of BMs
5 Details of Permamnent Bench Mark (PBM)
BM ID# Location Northing Easting RL
i
ii
iii
6 Provide details of temporary bench mark (TBM) on site Use notes below for more details
TBM ID# Location Northing Easting RL
i
ii
iii
iv
7 Is the TBM well protected?
8 Is the TBM well highlighted and identified on site?
9 Are the TBM and PBM locations/ details identified on a sketch/ drawing?
Sketch/ Dwg # & Rev Date
NOTES/ REMARKS:
AGENCY >>> OHL-CL JV SURVEYOR OHL-CL JV QC KEO
NAME
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
OHL-CL JV SECTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/BM-1 Page 5 of 65
DATE
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/BM TO to Sub Con-2 Page 6 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
1 of 1 0
CHECKLIST FOR TURNOVER OF TEMPORARY BENCH MARK AT SITE TO SUB CONTRACTOR
Date: JV Form # OHL-CL/FORM/CL/1002-REV 0
Reference to RFIT # (Only if applicable) Checklist #
Location: Sub Contractor (If app.)
S.NO. DESCRIPTION/ TOPICCOMPLIANCE
REMARKSYes No N/A
1 Ensure sub contractors survey equipment has a valid calibration.
Equipment # Calibration valid till Use notes below for more details
2 Permanent bench mark shown by: JV Surveyor (Name)
3 Are these Government installed permanent bench mark
4 How many permamnent bench marks are turned over to sub contractor: Insert Number of BMs
5 Details of Permamnent Bench Mark (PBM)
BM ID# Location Northing Easting RL
i
ii
iii
6 Provide details of temporary bench mark (TBM) on site Use notes below for more details
TBM ID# Location Northing Easting RL
i
ii
iii
iv
7 Is the TBM well protected?
8 Is the TBM well highlighted and identified on site?
9 Are the TBM and PBM locations/ details identified on a sketch/ drawing? Tag to be fixed to the TBM pole
Sketch/ Dwg # & Rev Date
10 Is the above sketch issued to the sub contractor?
Letter/ Transmittal # Date
NOTES/ REMARKS:
AGENCY >>> OHL-CL JV SURVEYOR OHL-CL JV QC SUB CONTRACTOR
NAME
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
CHECKLIST FOR TURNOVER OF TBM AT SITE TO SUB-CONTRACTOR
OHL-CL JV SECTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/BM TO to Sub Con-2 Page 7 of 65
DATE
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/EW - EXC-3 Page 8 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
CHECKLIST FOR EARTHWORK - Excavation Operations 1 of 1 0
CHECKLIST FOR EARTHWORKS - Excavation Operations
Date: JV Form # OHL-CL/FORM/CL/1003-REV 0
Reference to RFIT # (Only if applicable) Checklist #
Location: Sub Contractor (If app.)
S.NO. DESCRIPTION/ TOPICCOMPLIANCE
REMARKSYes No N/A
1 Are the temporary bench marks established and approved by KEO/ QP?
2 Temporary bench mark referenced for this setting out:
3 Is the setting out in accordance to approved shop drawings?
Shop dwg. # and Rev
4 Is sufficient working space allowed around the construction area?
5 Safety:is the JHA or AHA approved by KEO/ QP?
6 Are the excavation levels marked out at site?
7 Equipments used:
8 Ensure excavated material is not stacked beside excavation.
9
10 Is the ITL approved by KEO/ QP to carry out plate bearing tests/
11 Carry out plate bearing tests at designated/ agreed locations After proof rolling. Raise RFIT
12 Are the plate bearing test reults compliant and acceptable? Lab Report #
13 Plate bearing test details
Location Northing Easting RL
i
ii
iii
iv
14 Is the area released for Blinding?
NOTES/ REMARKS:
AGENCY >>> OHL-CL JV SURVEYOR OHL-CL JV QC KEO
NAME
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
Is the excavated bed withing tolerance: + 2 cm allowed
OHL-CL JV SECTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/EW - EXC-3 Page 9 of 65
DATE
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/EW - BFL-4 Page 10 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
CHECKLIST FOR EARTHWORK - Backfilling Operations 1 of 1 0
CHECKLIST FOR EARTHWORKS - Backfilling Operations
Date: JV Form # OHL-CL/FORM/CL/1004-REV 0
Reference to RFIT # (Only if applicable) Checklist #
Location: Sub Contractor (If app.)
S.NO. DESCRIPTION/ TOPICCOMPLIANCE
REMARKSYes No N/A
1 Is the sub contractor for Earthworks approved by KEO/ QP?
2 Is the Independent Testing Lab (ITL) approved by KEO/ QP?
3 Safety:is the JHA or AHA approved by KEO/ QP? AHA#
4 Is the stockpile tested and approved by the ITL? ITL Report #
SP # Lab Test Report # MDD Value OMC Value
5 Define grids for backfill:
6 Define Layer # and RL of top of backfill: Raise RFIT
7 Area of backfill =
8 Testing Details
i Does the testing equipment carry a valid calibration certificate?
ii Is the moisture content of fill material within 2% of OMC?
iii Total number of test points taken = By ASTM D 698 - Std. effort
iv Required compaction =
v Total number of passing results =
vi Total number of failing results =
vii Retesting details:
9 Other Miscellaneous Information:
i Time tested:
ii
iii Atmospheric humidity =
10 Equipments used
11 NOTE: Carry out anti termite treatment to penetrations at each layer. Includes Columns, MEP pipes
NOTES/ REMARKS: * Stockpile log is maintained separately.* Moisture content of fill material =
AGENCY >>> OHL-CL JV SURVEYOR OHL-CL JV QC KEO
NAME
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
Ambient Temperature oC =
OHL-CL JV SECTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/EW - BFL-4 Page 11 of 65
DATE
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/SP Log-5 Page 12 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
STOCKPILE LOG FOR EARTHFILL MATERIAL 1 of 1 0
SP#MDD/ OMC DETAILS ATTERBERG LIMITS CBR SIEVE ANALYSIS
RFIT #MDD OMC REPORT # LL PL PI REPORT # REPORT # REPORT #
% REPORT # % REPORT #
AGENCY >>> THIRD PARTY LABORATORY OHL-CL JV QC KEO
NAME
JV's Internal Form/ Checklist
STOCKPILE LOG FOR EARTHFILL (Form # OHL-CL/FORM/CL/1005-REV 0)
ORGANIC CONTENT
CHEMICAL ANALYSIS TRL # TO
KEO2.5 MM
PENETRATION
RESULT/ STATUS
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/SP Log-5 Page 13 of 65
DATE
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Anti Termite-6.1 of 2 Page 14 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
CHECKLIST FOR ANTI TERMITE TREATMENT 1 of 1 0
CHECKLIST FOR ANTI TERMITE TREATMENT
Date: JV Form # OHL-CL/FORM/CL/1006 (1/2)-REV 0
Reference to RFIT # (Only if applicable) Checklist #
Location: Sub Contractor (If app.)
S.NO. DESCRIPTION/ TOPICCOMPLIANCE
REMARKSYes No N/A
1 Is the supplier/ applicator approved by KEO/ QP? Prequalification approval
2 Is the method statement approved?
3 Is the JHA or AHA approved?
4 What is the approved product: DURSBAN 4TC
5 What is the rate of dilution: 1litre to 49litres water
6 What is the rate of application: 5lts of diluted solution per sqm
7 Area to be treated (this session) =
8 Quantity of chemical placed in dilution tank =
9 Treatment method - in channel or spraying?: Spraying
10 What stage of treatment is this? Raise RFIT for anti termite treatment
Under Blinding: Under G Slab Barrier Treatment
Note: Treatment to penetrations to be one with backfilling operations
11 Is the treated area covered* within 72 hours? *Polythene sheet or blinding
NOTES/ REMARKS:
AGENCY >>> OHL-CL JV SURVEYOR OHL-CL JV QC KEO
NAME
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
OHL-CL JV SECTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Anti Termite-6.1 of 2 Page 15 of 65
DATE
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Anti Termite Rep6.2of2 Page 16 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
ANTI TERMITE TREATMENT APPLICATION REPORT 1 of 1 0
ANTI-TERMITE TREATMENT APPLICATION REPORTDate: JV Form # OHL-CL/FORM/CL/1006 (2/2)-REV 0Reference to RFIT # (Only if applicable) Checklist # Location: Sub Contractor Qatar Pest Control Co. WLL
1 Is the soil to be treated conformant and released? If yes, give RFIt ref. #
2 Date and time treatment requested by Construction
3 Actual date and time of treatment
4 Moisture content of soil before treatment application (by Independent Lab - M/S QIL)
5 Define grids of area of application
6 Total area to be treated in SqM
7 Product to be used Dursban 4TC
8 Rate of dilution 1 ltr Dursban 4TC: 49 Ltr of Water
9 Total quantity of undiluted Dursban 4TC used (In this session for the area in #6 above)
10 Rate of application (this session) - Ltr per LM or SqM, specify
NOTES/ REMARKS:
AGENCY >>> OHL-CL JV QC QP/ KEO
NAME
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
SUB CONTRACTOR - QATAR PEST CONTROL CO. WLL
OHL-Contrack JV SECTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Anti Termite Rep6.2of2 Page 17 of 65
DATESIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Blinding 7 Page 18 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
CHECKLIST FOR PLACING BLINDING 1 of 1 0 1
CHECKLIST FOR PLACING BLINDING
Date: JV Form # OHL-CL/FORM/CL/1007-REV 1
Reference to RFIT # (Only if applicable) Checklist #
Location: Sub Contractor (If app.)
S.NO. DESCRIPTION/ TOPICCOMPLIANCE
REMARKSYes No N/A
1 Is the area to recieve blinding released and conformant?
2 Is the JHA or AHA approved by KEO/ QP?
3 Is the Prequalification for Readymix Supplier approved by KEO/ QP?
4 Is the required Mix Design approved by KEO/ QP?
5 Is the Independent Testing Lab approved for testing/ sampling?
6
7 Is the anti termite treatment carried out and released?
8 Extended by Min. 10 cm at ends
9 Are forms laid out correctly? Surveyor verification10 Record RL of top of form:11 Are enough steel pegs driven into ground for controlling intermediate levels?12 Are all required box outs and inserts installed?
12 Date of Casting:
13 or approved curing compound
14 Cube IDs for samples taken Attach pour card
15 Placement by: Tower crane/ Bucket; Chute; Direct discharge; Pump
NOTES/ REMARKS:
*
** Commence curing of concrete immediately after initial setting using hessian and water spraying. Cover with polythene to prevent rapid evaporation.
*** Record method of placement - Direct discharge; Pump; Tower crane/ Bucket; Chute (Circle appropriate)*** Identify defects in concrete after stripping of forms (if any) and the approved method of repair:
AGENCY >>> OHL-CL JV SURVEYOR OHL-CL JV QC KEO
NAME
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
Are the following avaialble: Cube molds; Slump cone app.; Calibrated concrete thermometer; Thermometer; Hygrometer
Is polythene sheet laid out as specified: Thickness and taped at joints/ repaired where damaged by masking tape.
Section Manager to Verify. Raise RFIT for casting.
Curing for 7 days using hessian sheet and water + Polythene cover or use curing compound compatible to waterproofing system.
Details of supplier; DO #; volume; Concrete properties as received (Concrete slump and temperature); Location of placement; Cube Ids and reports are in the Pour Card (attached) and Cube Register(kept separately)
OHL-CL JV SECTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Blinding 7 Page 19 of 65
DATESIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/RF Concrete-Vertical 8 Page 20 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
1 of 1 0 1
CHECKLIST FOR PLACING REINFORCED CONCRETE - Columns/ Walls
Date: JV Form # OHL-CL/FORM/CL/1008-REV 1
Reference to RFIT # (Only if applicable) Checklist #
Location: Sub Contractor (If app.)
S.NO. DESCRIPTION/ TOPICCOMPLIANCE
REMARKSYes No N/A
1 Is layout in conformance with the TBM and approved shop dwgs.?2 Is the area to recive reinforced concrete released and conformant?3 Is the JHA or AHA approved by KEO/ QP?4 Is the Prequalification for Readymix Supplier approved by KEO/ QP?5 Is the required Mix Design approved by KEO/ QP?6 Is the Independent Testing Lab approved for testing/ sampling?7
8 Is reinforcinfg steel approved by KEO/ QP? Material Transmittal9
10
11 Provision for box outs and inserts? Section Manager to verify12 Is the top of concrete marked on form? Level =13 Is the steel extended enough for the next lift?14 Raise RFIT for casting15 Are enough concrete vibrators mobilized at site? Record numbers16 Spray water, if necessary, on steel/ form before concrete placement17 Placement by: Tower crane/ Bucket; Chute; Direct discharge; Pump Circle appropriate18 Date of Casting:19 Curing for 7 days using hessian sheet and water + Polythene cover or approved curing compound20 Cube IDs for samples taken Attach Pour card
NOTES/ REMARKS:
*
** Commence curing of concrete immediately after initial setting using hessian and water spraying. Cover with polythene to prevent rapid evaporation.
*** Identify defects in concrete after stripping of forms (if any) and the approved method of repair:
AGENCY >>> OHL-Contrack JV QC KEO
NAME
DATE
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
CHECKLIST FOR PLACING REINFORCED CONCRETE - Columns & Walls
Are the following avaialble: Cube molds; Slump cone app.; Calibrated concrete thermometer; Thermometer; Hygrometer
Is reinforcing steel placed conformant: Bent to shape; lapped properly; Cover as specified; Free from dust/ rust/ contaminant; Tied adequately
Lapping = 50D; If epoxy coated touch up where reqd.
Formwork: Oiled with shutter release agent; Adequate supports; Tight at joints; True to line and level indicated
Raise RFIT after closure of three sides of form for steel inspection
Limit free fall of concrete in form to 1.5 M in one lift
Details of supplier; DO #; volume; Concrete properties as received (Concrete slump and temperature); Location of placement; Cube Ids and reports are in the Pour Card (attached) and Cube Register(kept separately)
OHL-Contrack JV SURVEYOR
OHL-Contrack JV SECTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/RF Concrete-Vertical 8 Page 21 of 65
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/RF Concrete-Slabs & Footing-9 Page 22 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
1 of 1 0
CHECKLIST FOR PLACING REINFORCED CONCRETE - Footings and Slabs
Date: JV Form # OHL-CL/FORM/CL/1009-REV 0
Reference to RFIT # (Only if applicable) Checklist #
Location: Sub Contractor (If app.)
S.NO. DESCRIPTION/ TOPICCOMPLIANCE
REMARKSYes No N/A
1 Is layout in conformance with the TBM and approved shop dwgs.?2 Is the area to recive reinforced concrete released and conformant?3 Is the JHA or AHA approved by KEO/ QP?4 Is the Prequalification for Readymix Supplier approved by KEO/ QP?5 Is the required Mix Design approved by KEO/ QP?6 Is the Independent Testing Lab approved for testing/ sampling?7
8 Is reinforcinfg steel approved by KEO/ QP? Material Transmittal9
10
11 Provision for box outs and inserts? Technical Manager to verify12 Is the top of concrete marked on form? Level =13 Is the steel extended enough for lapping in the next casting? Raise RFIT for casting14 Are enough concrete vibrators mobilized at site? Record numbers15 Spray water, if necessary, on steel/ forms prior to concrete placement16 Placement by: Tower crane/ Bucket; Chute; Direct discharge; Pump Circle appropriate17 Date of Casting:18 Curing for 7 days using hessian sheet and water + Polythene cover or approved curing compound19 Cube IDs for samples taken Attach Pour card
NOTES/ REMARKS:
*
** Commence curing of concrete immediately after initial setting using hessian and water spraying. Cover with polythene to prevent rapid evaporation.
*** Identify defects in concrete after stripping of forms (if any) and the approved method of repair:
AGENCY >>> OHL-CL JV SURVEYOR OHL-CL JV QC KEO
NAME
DATE
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
CHECKLIST FOR PLACING REINFORCED CONCRETE - Footings & Slabs
Are the following avaialble: Cube molds; Slump cone app.; Calibrated concrete thermometer; Thermometer; Hygrometer
Is reinforcing steel placed conformant: Bent to shape; lapped properly; Cover as specified; Free from dust/ rust/ contaminant; Tied adequately
Lapping = 50D; If epoxy coated touch up where reqd.
Formwork: Oiled with shutter release agent; Adequate supports; Tight at joints; True to line and level indicated
Details of supplier; DO #; volume; Concrete properties as received (Concrete slump and temperature); Location of placement; Cube Ids and reports are in the Pour Card (attached) and Cube Register(kept separately)
OHL-CL JV SECTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/RF Concrete-Slabs & Footing-9 Page 23 of 65
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Pour Card-10 Page 24 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
CONCRETE POUR LOG 1 of 1 0
Date Supplier Grids/ Location DO #Qty.
Time Concrete PropertiesRemarks
Batched Arrival Disch.Temp. Slump
mm
AGENCY >>> THIRD PARTY LABORATORY OHL-CL JV QC KEO
NAME
JV's Internal Form/ Checklist
CONCRETE POUR LOG (Form # OHL-CL/FORM/CL/1010-REV 0)
Concrete Grade
Air Temp.
oCCube
IDM3 oC
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Pour Card-10 Page 25 of 65
DATE
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Cube Register-11 Page 26 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
CONCRETE CUBES REGISTER 1 of 1 0
CUBE ID #CONCRETE CUBE RESULTS
Remarks7 DAYS RESULTS 28 DAYS RESULTSLAB REF. # STRENGTH TRL. TO KEO LAB REF. # STRENGTH TRL. TO KEO
AGENCY >>> THIRD PARTY LABORATORY OHL-CL JV QC KEO
NAME
JV's Internal Form/ Checklist
CONCRETE CUBE REGISTER (Form # OHL-CL/FORM/CL/1011-REV 0)
DATE OF CASTING
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Cube Register-11 Page 27 of 65
DATE
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/CMU-12 Page 28 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
1 of 1 0
CHECKLIST FOR CONCRETE MASONRY WORKS - CMU
Date: JV Form # OHL-CL/FORM/CL/1012-REV 0
Reference to RFIT # (Only if applicable) Checklist #
Location: Sub Contractor (If app.)
S.NO. DESCRIPTION/ TOPICCOMPLIANCE
REMARKSYes No N/A
1 Is the area to receive CMU released and conformant?
2 Is the JHA or AHA approved by KEO/ QP?
3 Is the Prequalification for CMU Supplier approved by KEO/ QP?
4 Is the required Mortar Mix Design approved by KEO/ QP?
5 Is the Independent Testing Lab approved for testing/ sampling?
6 Are the CMU accessories approved by KEO/ QP?
7 Are the CMU and Sand tested and conformant?
8 Setting out/ Layout for CMU works - Approved and released? Raise RFIT
9 CMU Installation
i Mix mortar using machine and measuring boxes
ii True to line and level - make up difference in level in the first course
iii Leave clearance at ends/ boxouts/ inserts as indicated on app. Dwgs.
iv
v Install accessories as indicated and to Manufacturer recommendations
vi Cure CMU for 3 days using water spray thrice daily Raise RFIT for completion of CMU
10 Mortar Sampling
i Sampled on:
ii Mortar Cube ID:
NOTES/ REMARKS:* Details of Cubes maintained in the Mortar Cube Register Log
AGENCY >>> OHL-CL JV SURVEYOR OHL-CL JV QC KEO
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
CHECKLIST FOR CONCRETE MASONRY WORKS - CMU
Do not install more than 7 course in one session - Additional course may be laid using wooden wedges.
OHL-CL JV SECTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/CMU-12 Page 29 of 65
NAMEDATESIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Mortar Cube Register-13 Page 30 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
MORATR CUBE REGISTER 1 of 1 0
MORTAR CUBE ID #CONCRETE CUBE RESULTS
Remarks7 DAYS RESULTS 28 DAYS RESULTSLAB REF. # STRENGTH TRL. TO KEO LAB REF. # STRENGTH TRL. TO KEO
AGENCY >>> THIRD PARTY LABORATORY OHL-CL JV QC KEO
NAME
JV's Internal Form/ Checklist
MORTAR CUBE REGISTER (Form # OHL-CL/FORM/CL/1013-REV 0)
DATE OF CASTING
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Mortar Cube Register-13 Page 31 of 65
DATE
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Plaster-14 Page 32 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
CHECKLIST FOR PLASTERING (RENDER) WORKS 1 of 1 0
CHECKLIST FOR PLASTERING (RENDER) WORKS
Date: JV Form # OHL-CL/FORM/CL/1014-REV 0
Reference to RFIT # (Only if applicable) Checklist #
Location: Sub Contractor (If app.)
S.NO. DESCRIPTION/ TOPICCOMPLIANCE
REMARKSYes No N/A
1 Is the area to receive render released and conformant?
2 Is the JHA or AHA approved by KEO/ QP?
3 Is the required Render Mix Design and materials approved by KEO/ QP?
4 Are the render/ plaster accessories approved by KEO/ QP?
5
6 Install plaster accessories as indicated and true to line and level
7 Are level pads installed and true to line and level? Raise RFIT for commencing render
8 Plastering/ Rendering Works
i First Coat/ Scratch Coat/ Splatter dash: Cure for one day using water Spray thrice daily
ii Leave surface level and rough
iii
9 Raise RFIT for completion of render
NOTES/ REMARKS:
AGENCY >>> OHL-CL JV SURVEYOR OHL-CL JV QC KEO
NAME
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
Is the "Work Clearance Request" signed off by other trades to commence rendering activities?
Second coat/ Brown Coat: Afetr min. 24 hours of 1st coat; Surface scratched; Cure for two days with water sparayed thrice daily
Third Coat/ Skim Coat: After min. 24 hours of 2nd coat; Finsih surface smooth with steel and foam trowel
Cure 3 days with water sparyed thrice daily.
OHL-CL JV SECTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Plaster-14 Page 33 of 65
DATESIGNATURE
KEO International Consultants11/18/2015 WCR-15
QATAR FOUNDATION EDUCATION CITY
WORK CLEARANCE REQUEST Civil Mechanical Electrical Plumbing Survey
BID PACKNo. Rev.
CONTRACTOR : Obrascon Huarte Lain/ Contrack Limited, JV (OHL-CL JV) Date:
TO : Form # OHL-CL/FORM/CL/1015-REV 0
CCS ACTIVITY No. : SPECIFICATION DIVISION : SECTION:
TYPE : ZONE :
AREA / LOCATION / SUBJECT:
Specific Trade : Civil/Architect Electrical Mechanical MEP Coordinator QA/QC Engineer
Sign : :
DATE&TIME CLEARANCE REQUIRED :
CONTRACTOR : DATE & TIME:
RECEIVED BY SUB CONTRACTOR AGENCY: DATE & TIME:
REPLY : A : Approved B : Approved as noted below C : Not Approved (notes below)
Initials Date
PROJECT ENGINEER DATE & TIME:
RECEIVED BY CONTRACTOR : DATE & TIME:
: BP # 9 - Design and Construction of Sidra Medical and Research Centre (SMRC)
Please review and confirm that your scope of work is completed, inspected and approved for us to proceed with the following works. Note that the access to your installation may not be possible after the following works are done.
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/DFT Record-16 Page 35 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
CHECKLIST FOR TAKING DFT OF PAINT/ COATINGS 1 of 1 0
Form # OHL-Con/FORM/CL/1016-Rev 0 CL # Date:
S.No. BLDG. LEVEL GRID ITEM DESCRIPTION
INSPECTION DETAILS/ RECORDS
REMARKSDFT READINGS IN MICRONS
AGENCY >>> OHL-Contrack JV Site Engineer/ Section Manager OHL-Contrack JV QC KEO
NAME
DATE
JV's Internal Form/ Checklist
CHECKLIST FOR TAKING DFT (Dry Film Thickness of Coatings) to STRUCTURAL STEEL(Form # OHL-Con/FORM/CL/1016, rev 0)INSTRUMENT
DETAILSDRY FILM THICKNESS GAUGEMAKE: ELCOMETER MODEL #: SERIAL #
TYPE OF COATING
AVG. DFT MICRONS
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/DFT Record-16 Page 36 of 65
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/WFT Record-17 Page 37 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
CHECKLIST FOR TAKING WFT OF PAINT/ COATINGS 1 of 1 0
Form # OHL-Con/FORM/CL/1017-Rev 0 CL # Date:CHECKLIST FOR TAKING WFT (Wet Film Thickness of Coatings)
WET FILM GAUGE - ELCOMETER, #
S.No. BLDG. LEVEL GRID ITEM DESCRIPTION
INSPECTION DETAILS/ RECORDS
REMARKSWFT READINGS IN MICRONS
AGENCY >>> OHL-Contrack JV Site Engineer/ Section Manager OHL-Contrack JV QC KEO
NAME
JV's Internal Form/ Checklist
INSTRUMENT DETAILS
THERMOMETERSR. # CALIBRATION VALID TILL:
HYGROMETERSR. # CALIBRATION VALID TILL:
TEMP. oC RELATIVEHUMIDITYTYPE OF COATING
AVG. WFT MICRONS
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/WFT Record-17 Page 38 of 65
DATE
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/CL for Dowel&Rebar Planting-18 Page 39 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
CHECKLIST FOR PLANTING DOWEL/ REBAR 1 of 1 0
Form # OHL-Con/FORM/CL/1018-Rev 0 CL # Date:Checklist for Planting Dowel/ Rebar
S.NO. DESCRIPTION OF INSTALLATION
STR. ST. FRAME DESC./ LOCATION INSPECTION DETAILS
REMARKSMARK* TYPE* GRID
NOTE: Fields with * mark are applicable only for bolts for erection of structural steel/ equipment bases/ machine foundations. Other fields are common to bolts & Rebars.
AGENCY >>> OHL-Contrack JV Site Engineer/ Section Manager OHL-Contrack JV QC KEO
NAME
JV's Internal Form/ Checklist
DATE ERECTED/
INSTALLEDBLDG. & LEVEL
HOLE CLEANING
DEPTH OF HOLE MM
BOLT INSP - FULL/ CUT*
EPOXY TYPE/ MAKE
NUTS/ WASHERS*
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/CL for Dowel&Rebar Planting-18 Page 40 of 65
DATE
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/WEEKLY cc REQMT-19 Page 41 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
WEEKLY CONCRETE REQUIREMENT 1 of 1 0
Weekly Concrete RequirementBUILDING: Form # OHL-Con/FORM/CL/1019, Rev 0
ZONE/ SECTION: Request # Date
ITEM/ DESCRIPTION SAT SUN MON TUE WED THU FRI REMARKS
LOCATION/ LEVEL
12345123451234512345
SLUMP REQUIRED
1234512345
NOTE: The table above accomodates upto five pours per day. For additional requirements use the space below.
Originator: OHL-Contrack JV Section Manager Received by: OHL-Contrack JV Concrete Coordinator:
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
DATE WHEN REQUIRED
TIME WHEN REQUIRED
GRADE OF CONCRETE
PUMP REQUIREMENT
WITH BOOM LENGTH
QUANTITY REQUIRED
INTERVAL BET. TRUCKS
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/WEEKLY cc REQMT-19 Page 42 of 65
Copy Issued to Lab on (Date & Time) >>>>>>>
Name, Date, Sign
Recd. On (Date/ Time)
SENT TO RMX ON (DATE/ TIME)
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/WEEKLY cc Planner-20 Page 43 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
WEEKLY CONCRETE PLANNER 1 of 1 0
Weekly Concrete PlannerForm # OHL-Con/FORM/CL/1020, Rev 0
Date: _______________ Weekly Planner #
The Plant ManagerReadymix Qatar WLL,Education City, Al Rayyan,Doha, Qatar
Dear Sir:
Enclosed please ______ sheets of concrete requirements required at various locations at the above mentioned Projectduring the week _______________________ to _______________________.
You may directly co-ordinate with the individual Section Manager for scheduling the pour.The contact details of all the Section managers are provided at the end of this sheet.Contact CC or SCM in the Office for re-scheduling pours.
Note that concrete for Project work shall be not be batched and desptached unless instructed by the QC Office.
Regards
Miguel Angel BravoSenior Construction Manager (SCM)CC: PM/SCM/ All Section Mnagers/ Independent Lab/ Safety Office/ QC OfficeContact Details
ZONE/ BUILDING NAME DESIGNATION MOBILE PHONE #HOSPITAL JONATHAN CAMACHO SECTION MANAGER 5887439To be advised BASSEL MUSSEFI SECTION MANAGER 5567483CENTRAL SERVICES BUILDING To be advised To be advised To be advisedCLINIC BUILDING To be advised To be advised To be advisedUNDERGROUND CAR PARK To be advised To be advised To be advisedSTAFF CAR PARK To be advised To be advised To be advisedMOSQUE To be advised To be advised To be advisedTUNNELS To be advised To be advised To be advisedEXTERNAL WORKS To be advised To be advised To be advisedOTHER IMPORTANT CONTACTS
SAFETY OFFICE Abhimanyu Pothal Safety Manager 5598398QC OFFICE Shakeel Ahmed QC Engineer 5004934
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
To: Total: ___________Sheets including this sheet.
Fax to:Attention: Mr.
Subject: Supply of concrete to the Sidra Medical & Research Centre for the following Week
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/WEEKLY cc Planner-20 Page 44 of 65
JV Site Management MIGUEL ANGEL BRAVO 6932293SENIOR CONSTRUCTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/TPI REq - 21 Page 45 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
1 of 1 0
REQUISITION FORM FOR THIRD PARTY INSPECTIONS/ TESTING
Date: JV Form # OHL-CL/FORM/CL/1021-REV 0
Reference to RFIT/ Lr # (If app.) Request # OHLCONJV/Sidra/
Location:
To
Please depute personnel for carrying out the following: (Check Appropriate)1
2 Sampling of
3 Testing of
Inspection/ Testing and Reporting Requirements
S# RELEVANT STANDARD/ SPECS. INSPECTION/ TESTING/ REPORTING REQUIREMENTS (Include Quantity)
NOTES/ REMARKS (IF ANY)
DATE TESTED/ INSPECTED: REPORT #
(Provide details of previous test report #/ inspection report #, if reinspected/ retested)
AGENCY >>> TP REPRESENTATIVE OHL-CL JV QC QP/ KEO
NAMEDATE
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
REQUISITION FORM FOR THIRD PARTY INSPECTION/ TESTING
Witnessing/ Inspection of
SPECIAL NOTE: TESTING AGENCY SHALL ATTACH THE FOLLOWING REQUISITION WHILE INVOICING WITH THE FIELDS FILLED IN BELOW
OHL-CL JV SECTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/TPI REq - 21 Page 46 of 65
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/LogTPIReq-22 Page 47 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
LOG OF THIRD PARTY INSPECTIONS/ TESTING 1 of 1 0
Form # OHL-Con/FORM/CL/1022-Rev 0 CL # Date:LOG OF THIRD PARTY INSPECTIONS/ TESTING
INSPECTION/ TESTING DETAILS
REMARKSPASSING FAILING
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
JV's Internal Form/ Checklist
REQUISITION #
OHLCONJV/ Sidra/
DATE INSPECTED/ TESTED
INSPECTED/ TESTED
BYDESCRIPTION OF TEST/
INSPECTIONLAB REPORT #/ INSP.
REPORT #REINSP./ RETESTING
DETAILS (IF APP.)TOTAL TESTED
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Weldinsp.-23 Page 48 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
WELD VISUAL INSPECTION REPORT 1 of 1 0
WELD VISUAL INSPECTION REPORTJV Form # OHL-CL/FORM/CL/1023-REV 0
Date Inspected: Report # Installation done by: (Subcontractor Agency Name)
S.No. BUILDING LEVEL LOCATION/ DESCRIPTION FIT UP WELDER ID WPS REMARKS
AGENCY >>> OHL-CL JV QC TPI QP/ KEO
NAME
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
WELD INSP.
OHL-CL JV SECTION MANAGER
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Weldinsp.-23 Page 49 of 65
DATESIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Punch List-24 Page 50 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
PUNCH LIST 1 of 1 0
Form # OHL-Con/FORM/CL/1024-Rev 0 CL # Date:PUNCH LIST
Building: Level: Civil Mech. Elect. Others: Specify
LEGEND: Adopt the following legend: C - Ceiling; EW - East Wall; WW - West Wall; NW - North wall; SW - South wall; F - Floor; O - Others
S.No. Room # Punch/ Defect Items Remarks
JV's Internal Form/ Checklist
Discipline (Check Appropriate)
Medical Eqpmt. and FF & E
Punched By: QC Initials
Date Punched
Date Closed
Sign off: By Construction
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Punch List-24 Page 51 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
PUNCH LIST 1 of 1 0
Form # OHL-Con/FORM/CL/1024-Rev 0 CL # Date:PUNCH LIST
Building: Level: Civil Mech. Elect. Others: Specify
LEGEND: Adopt the following legend: C - Ceiling; EW - East Wall; WW - West Wall; NW - North wall; SW - South wall; F - Floor; O - Others
JV's Internal Form/ Checklist
Discipline (Check Appropriate)
Medical Eqpmt. and FF & E
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/CMU Test Log - 25 Page 52 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
CMU TEST LOG 1 of 1 0
Form # OHL-Con/FORM/CL/1025-Rev 0 CL # Date:
SUPPLIER NAME DO # SITE ID # TPI REQ. # RFIT #TESTING DETAILS
COMP. STRENGTH WATER ABSORPTIONINDIVIDUAL AVG. INDIVIDUAL AVG.
AGENCY >>> THIRD PARTY LABORATORY OHL-CL JV QC KEO
NAME
JV's Internal Form/ Checklist
CMU TEST LOG (Compressive Strength) (Form # OHL-CL/FORM/CL/1025-REV 0)
DATE OF RECEIPT
NO. OF BLOCKS
SAMPLED
REMARKS (INCLUDING DETAILS OF TRANSMITTAL
TO KEO)LAB
REPORT #LAB
REPORT #
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/CMU Test Log - 25 Page 53 of 65
DATE
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Grout Cube Register-26 Page 54 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
GROUT CUBE REGISTER 1 of 1 0
Form # OHL-Con/FORM/CL/1026-Rev 0 CL # Date:
GROUT CUBE ID #CONCRETE CUBE RESULTS
Remarks7 DAYS RESULTS 28 DAYS RESULTSLAB REF. # STRENGTH TRL. TO KEO LAB REF. # STRENGTH TRL. TO KEO
AGENCY >>> THIRD PARTY LABORATORY OHL-CL JV QC KEO
NAME
JV's Internal Form/ Checklist
GROUT CUBE REGISTER (Form # OHL-CL/FORM/CL/1026-REV 0)
DATE OF CASTING
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Grout Cube Register-26 Page 55 of 65
DATE
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Trial Mix -27 Page 56 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
TRIAL MIX DETAILS 1 of 1 0
Trial Mix Details TPI Requisition #
1 CONCRETE DETAILS
2 Date of Trial: MIX ID
3 Time of Trial GRADE
ATTENDEES
READYMIX QATAR REPRESENTATIVE INDEPENDENT TESTING LAB REP. JV REPRESENTATIVE QP/ KEO REPRESENTATIVE
S.NO. TESTING DETAILSTESTING AGE (IN DAYS)
CUBE ID LAB REPORT # REMARKS1 DAY 3 DAYS 7 DAYS 28 DAYS 56 DAYS
1 Compressive strength 1 2 3 3 3 12
2 Rapid Chloride permeability test (RCPT) 0 0 0 3 3 6
3 Water absorption 0 0 0 3 3 6
4 Chloride and Sulfate. 0 0 0 3 0 3
5 Water permeability 0 0 0 3 3 6
6 ISAT - Initial surface absorption test 0 0 0 3 0 3
TOTAL CUBES TAKEN>>>>>> 36
AGENCY >>> THIRD PARTY LABORATORY OHL-CL JV QC KEO
NAME
DATE
JV's Internal Form/ Checklist
TRIAL MIX DETAILS (Form # OHL-CL/FORM/CL/1027-REV 0)
Location of Trial: SMRC Batching Plant at Education City, Doha, Qatar
TOTAL CUBES TAKEN
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Trial Mix -27 Page 57 of 65
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/NCR REg-28 Page 58 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
NCN/ NCR/ SQN REGISTER 1 of 1 0
Form # OHL-Con/FORM/CL/1028-Rev 0NCN/ NCR/ SQN Register
S.No. # Agency Description of NCN/ NCR/ SQN Proposed Corrective Action Remarks
JV's Internal Form/ Checklist
Type: NCN/ NCR/SQN
Date Sent to KEO
Date Recd. From KEO
Status - Open/ Closed
Root Cause of Non-Conformity
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/NCR REg-28 Page 59 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Location Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
NCN/ NCR/ SQN REGISTER 1 of 1 0
Form # OHL-Con/FORM/CL/1028-Rev 0NCN/ NCR/ SQN Register
S.No. # Agency Description of NCN/ NCR/ SQN Proposed Corrective Action Remarks
JV's Internal Form/ Checklist
Type: NCN/ NCR/SQN
Date Sent to KEO
Date Recd. From KEO
Status - Open/ Closed
Root Cause of Non-Conformity
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Trial Mix Worksheet - 29 Page 60 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
CONCRETE TRIAL MIX WORKSHEET 1 of 1 0
CONCRETE TRIAL MIX WORKSHEETDate: JV Form # OHL-CL/FORM/CL/1029-REV 0
Reference to RFIT/ Lr # (If app.) Request # OHLCONJV/Sidra/
Location:
Project: Sidra Medical and Research Centre (SMRC) Laboratory #:
Date of Trial: Concrete Grade and Mix ID: Volume:
Batch#: Truck #: D.O #: Batch Time:
Material Remarks
Cement (OPC/ SRC/ QNCC)
PFA
Microsilica
20 mm Aggregate
10 mm Aggregate
Washed Sand
Admixture
Water (Litre)
Ice (Kg)
Free water/ cement ratio:
Bleeding (Immediate):
Immediate After 30 minutes After 60 minutes After 90 minutes After 120 minutesTime: Time: Time: Time: Time:
Ambient Temp. (oC)Concrete Temp. (oC)Plastic Density (Kg/M3)Slump - mmAir Content (%)Cubes Sampled/ Details
S.NO. TESTING DETAILSTESTING AGE (IN DAYS)
1 DAY 3 DAYS 7 DAYS 28 DAYS 56 DAYS
1 Compressive strength 1 2 3 3 3 122 Rapid Chloride permeability test (RCPT) 0 0 0 3 3 63 Water absorption 0 0 0 3 3 64 Chloride and Sulfate. 0 0 0 3 0 35 Water permeability 0 0 0 3 3 66 ISAT - Initial surface absorption test 0 0 0 3 0 3
Grand Total 36Remarks/ Notes:
AGENCY >>> TP REPRESENTATIVE OHL-CL JV QC KEO QP
NAMEDATE
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
Client: Qatar Foundation Client's Representative: Qatar Petroleum (QP) Construction Manager: KEOIC Prime Contractor: OHL-Contrack JV
Air Dry Weight (Kg) / m3
Absorption (Approx) (%)
Moisture Content (%)
Air Dry Weight (Accurate) (Kg)
Weight After Correction
TOTAL CUBES TAKEN
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Trial Mix Worksheet - 29 Page 61 of 65
SIGNATURE
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Weekly mortar-30 Page 62 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
Weekly Mortar (M)/ Grout (G) Requirement 1 of 1 0
Weekly Mortar (M)/ Grout (G) RequirementBUILDING: Form # OHL-Con/FORM/CL/1030, Rev 0
ZONE/ SECTION: Request # Date
ITEM/ DESCRIPTION SAT SUN MON TUE WED THU FRI REMARKS
LOCATION/ LEVEL
12345
MIX DETAILS
123451234512345
SLUMP REQUIRED
1234512345
NOTE: The table above accomodates upto five pours per day. For additional requirements use the space below.
Originator: OHL-Contrack JV Section Manager Received by: OHL-Contrack JV Concrete Coordinator:
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
DATE WHEN REQUIRED
TIME WHEN REQUIRED
PUMP REQUIREMENT
WITH BOOM LENGTH
QUANTITY REQUIRED
INTERVAL BET. TRUCKS
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/Weekly mortar-30 Page 63 of 65
Copy Issued to Lab on (Date & Time) >>>>>>>
Name, Date, Sign
Recd. On (Date/ Time)
SENT TO RMX ON (DATE/ TIME)
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/WEEKLY grout Planner-31 Page 64 of 65
QATAR FOUNDATIONSIDRA MEDICAL AND RESEARCH CENTRE (SMRC)
Contract No. Document No.
EDUCATION CITY - QATAR GTC/07/BP#9/QFA
Title: Page Rev No.
Weekly Mortar/ Grout Planner 1 of 1 0
Weekly Mortar/ Grout PlannerForm # OHL-Con/FORM/CL/1031, Rev 0
Date: _______________ Weekly Planner #
The Plant ManagerReadymix Qatar WLL,Education City, Al Rayyan,Doha, Qatar
Dear Sir:
Enclosed please ______ sheets of concrete requirements required at various locations at the above mentioned Projectduring the week _______________________ to _______________________.
You may directly co-ordinate with the individual Section Manager for scheduling the pour.The contact details of all the Section managers are provided at the end of this sheet.Contact CC or SCM in the Office for re-scheduling pours.
Note that concrete for Project work shall be not be batched and desptached unless instructed by the QC Office.
Regards
Miguel Angel BravoSenior Construction Manager (SCM)CC: PM/SCM/ All Section Mnagers/ Independent Lab/ Safety Office/ QC OfficeContact Details
ZONE/ BUILDING NAME DESIGNATION MOBILE PHONE #HOSPITAL JONATHAN CAMACHO SECTION MANAGER 5887439To be advised BASSEL MUSSEFI SECTION MANAGER 5567483CENTRAL SERVICES BUILDING To be advised To be advised To be advisedCLINIC BUILDING To be advised To be advised To be advisedUNDERGROUND CAR PARK To be advised To be advised To be advisedSTAFF CAR PARK To be advised To be advised To be advisedMOSQUE To be advised To be advised To be advisedTUNNELS To be advised To be advised To be advisedEXTERNAL WORKS To be advised To be advised To be advisedOTHER IMPORTANT CONTACTS
SAFETY OFFICE Abhimanyu Pothal Safety Manager 5598398QC OFFICE Shakeel Ahmed QC Engineer 5004934
LocationEDUCATION CITY - QATAR
JV's Internal Form/ Checklist
To: Total: ___________Sheets including this sheet.
Fax to:Attention: Mr.
Subject: Supply of Morat/ Grout to the Sidra Medical & Research Centre for the following Week
file:///var/www/apps/conversion/tmp/scratch_2/295326286.xls/WEEKLY grout Planner-31 Page 65 of 65
JV Site Management MIGUEL ANGEL BRAVO 6932293SENIOR CONSTRUCTION MANAGER
CL ListTemplateBM-1BM TO to Sub Con-2EW - EXC-3EW - BFL-4SP Log-5Anti Termite-6.1 of 2Anti Termite Rep6.2of2Blinding 7RF Concrete-Vertical 8RF Concrete-Slabs & Footing-9Pour Card-10Cube Register-11CMU-12Mortar Cube Register-13Plaster-14WCR-15DFT Record-16WFT Record-17CL for Dowel&Rebar Planting-18WEEKLY cc REQMT-19WEEKLY cc Planner-20TPI REq - 21LogTPIReq-22Weldinsp.-23Punch List-24CMU Test Log - 25Grout Cube Register-26Trial Mix -27NCR REg-28Trial Mix Worksheet - 29Weekly mortar-30WEEKLY grout Planner-31