Upload
vanxuyen
View
216
Download
3
Embed Size (px)
Citation preview
223
CHAPTER - VII
SUMMARY AND FINDINGS
Ever since the dawn of civilization, man has indulged in some form
of construction activity. Modern construction areas include high- rise
buildings, dams and irrigation networks, energy conversion and
industrial plants, environmental protection works, infrastructural
facilities like roads, bridges, railways, airports and sea ports, satellite
launching stations, onshore and offshore oil terminals etc.
Construction activity contributes to the economic development of a
country. The GDP per capita and the investment in the construction per
capita generally follow a straight line relationship, that is, construction
activity increases with the increase in per capita income. In some of the
developing countries, the growth rate of construction activity outstrips
that of population and of GDP.
The construction industry is the second largest economic activity in
India. During the last ten years the total capital formation by
construction was about 44 per cent of the total investment and the
contribution of construction to GDP was 5 per cent.
Construction accelerates the economic growth of a nation . In
India, for example, during the plan period 1980-85, for every rupee of
investment, construction added 78 paise to the GDP as compared with 20
paise per rupee of investment in agriculture.
224
Construction is an employment spinner. 16 percent of the nation’s
working population depends on construction for their livelihood. In
India, during the eighties, the overall annual employment increased by 2
per cent, whereas increase of employment in the construction sector
during the same period recorded an annual growth rate of about 7 per
cent.
Construction industry plays a dominant role in providing socio-
economic stability to the nation’s economy. A change in the level of
construction industry output not only affects GDP and manufacturing but
also the general employment levels and incomes of people. It is proved
that construction and housing sectors provide the backward and forward
linkage advantages, rarely seen in any other segment of industry.
Fluctuations in construction demand affect the economy in many ways:
they affect the demand for labour and materials as well as the lag in time
taken to supply the industry’s output. Backward linkages, in particular,
can have widespread impact because much of the raw, semi-processed,
and processed materials are provided by relatively unsophisticated
labour-intensive domestic sources and by basic industries such as cement
and steel manufacturing. Forward linkages affect practically all other
sectors of the economy. In fact, construction has been ranked among the
top four out of the twenty economic sectors in terms of inter-sectoral
linkages.
The importance of construction industry as an agent of
development is enhanced by its ability to provide gainful employment
for a large number of workers. Much of the demand for labour is often
met by taking unskilled workers from rural areas, who can subsequently
be trained for more demanding jobs. Construction is often the only
225
alternative for farm labour, particularly as it can adjust to the labour
needs of harvesting seasons to a larger degree than manufacturing.
There is hardly any sector which does not have a construction
component. It varies from 10-20 percent in scientific research and
education, to 40 percent in transport and communication, 75 percent in
power, 80 percent in irrigation and flood control to 100 percent in
housing.
The economic role of the construction industry is two fold- it helps
to promote or provide new capacity needed to satisfy additional demand
and maintains or improves existing capacity needed to satisfy continuing
demand. In the process construction activity also adds to the total
demand for labour and other productive resources.
The construction industry has a special place in the process of
development and has played an important part in shaping society’s
physical environment. Construction products are dams, bridges, tunnels,
highways, ports, buildings etc. The customer, in most cases, is the
community. These products are used to make living better for the people.
Therefore, safety, quality, cost, productivity and finishes during
construction and thereafter are very important. Construction is a one time
activity. It must be performed correctly the first time. There is less scope
for correcting the defects after the construction is over. Therefore,
quality consciousness, skill and workmanship of workers are critical to
achieving quality.
Generally, the value of construction products is high in relation to
the income of the purchaser. For example, the purchase of a house will
usually entail the expenditure of several times the annual income of the
buyer. Consequently, the products of the construction industry are
purchased by the client from his/her savings. Thus, construction industry
226
thrives on the savings and investment of the economy and has linkages
with the rest of the economy in terms of generation of output and
employment.
Traditionally, the construction sector in India has been dominated
by small and medium enterprises (SMEs). Nearly 96 percent of
construction enterprises fall under the SME category.
Various central, state and municipal/ local laws are applicable to
the construction industry. The laws relating to different aspects of the
sector fall under different categories. The various industry components
are regulated by different Ministries, government departments and
organizations like the Ministry of Environment and Forests, the Labour
Department, Pollution Control Board etc.
Many issues affect the smooth functioning of the sector. These
include contracting issues, financing issues, quality and technical issues
and manpower issues.
The sector has started inducting the latest developments in
Information Technology. Project design, development, implementation
and monitoring have been computerized.
India’s project exports have shown a steady trend. These exports
are spread across three broad categories namely civil construction works,
turnkey projects and consulting services.
The biggest policy initiatives over the past two years has been the
cabinet approval for 100 percent Foreign Direct Investment (FDI) in the
construction development sector through the automatic route. This is
likely to ensure rapid improvement in infrastructure , benefit
manufacturing and generate fresh employment. However, the results of
the policy will become apparent only over three to five years.
227
Ranked 12th in the world, the Indian construction industry accounts
for 5 per cent of GDP, and is the second highest employer after
agriculture. Moreover, about 169 industries are directly or indirectly
dependent on this sector. The housing sector which is one of the fastest
growing sectors of the economy registers an annual growth rate of 25 to
30 per cent.In spite of this, the housing loan penetration is very low in
India. The mortgage to GDP ratio is only 6 per cent in India where as it
is 56 per cent in the U.S, 51 per cent in the U.K and 12 percent in other
Asian countries. The potential in the home loan market is immense if
India touches the Asian average of 12 per cent.
Since the past few years, the construction sector in Kerala has been
witnessing amazing growth. The residential construction sector has been
very active in the state since 1980’s . One of the major contributing
factors for the increasing demand is that the mid-segment of the
population is moving into apartments in a big way. Increase in the
number of IT professionals and a general enhancement in the earning
potential among the salaried class have been behind the construction
boom.
Now Kerala has transformed into become as one of the most
sought after destinations in the country for real estate developers.
Resultantly, almost all large firms in the country have started full-
fledged operations in the state.
The study is taken up with the following objectives.
1. To assess the changing structure of construction industry with
special reference to Kerala.
2. To evaluate the economic and financial performance of
construction sector in Kerala.
3. To assess the linkages in the construction industry.
228
4. To identify the managerial and operational problems relating to the
construction sector.
5. To suggest strategies to tackle the identified problems and to equip
the units to compete in the liberalized regime.
Hypotheses
1. Increase in demand for residential and commercial buildings with
modern amenities cause large construction firms to proliferate in
urban areas.
2. Need-based construction activities cause local builders and small
contracting firms to operate in rural areas.
3. There is negative linkage with the primary sector, weak linkage
with the secondary sector and positive linkage with the service
sector.
The study is based both on primary and secondary data. As there are no
barriers either to the entry or exit of the firms in the construction industry,
no authentic data is available about their existence. There are large and
established players with long years of experience in urban areas. On the
other hand, a large number of small firms operate in the rural construction
market.
For selecting samples, the database maintained by the Kerala
Builders Forum (KBF), Kerala Builders Association (KBA) and the
Builders Association of India (BAI) has been extensively relied upon.
Since construction industry is widespread in its reach, data has
been collected from each of the main categories of participants, namely,
builders, contractors, input suppliers and workers.
On the basis of location, the construction industry in Kerala is
classified mainly into urban and rural areas. The areas are again
229
classified into three, namely, Northern, Central and Southern regions.
The Northern region comprises Kozhikkode and its suburbs. The Central
Region consists of Kochi, Thrissur and adjoining areas. The Southern
region constitutes Thiruvananthapuram, Neyyattinkara, Attingal and
suburbs.
Regarding the size of the units, no rigorous classification has been
made officially. Here, an attempt is made to classify units as follows:
1. Category A :- Units having an average annual turnover of less than
Rs. 1 crore.
2. Category B :- Units having an average annual turnover between Rs.
1 crore and Rs. 10 crore.
3. Category C :- Units having an average annual turnover of more
than Rs. 10 crores.
Data is available from 12 major builders in the state out of a total of 33,
from 9 major contracting firms out of a total of 52, from local builders
and contracting firms numbering 40 each from a total of 2,813. Data is
also available from input suppliers numbering 15 of which 9 firms have
outlets in all the three regions.
Data pertaining to construction workers numbering 200 is
available. Of these, administrative staff consisted of 30, engineers 20,
architects 8 and construction labourers 142. All these are taken from the
central region.
Samples were selected for each type using random sampling.
Construction, being one of the core activities undertaken in an economy,
requires urgent attention by planners, policy makers and those who run
and manage such units. The financial strength of the industry can have a
positive impact on the economy as a whole.
230
Construction is one of the least researched industries in the
country. It is also an industry that reports the minimal data about its
internal working. There are research works at the national level mostly
undertaken by specialized institutions and Government aided agencies.
State specific researches exploring the linkages of the industry in the
local economy are lacking.
In order to examine the working of the industry, details on capital
structure, inputs, output, workers’ emoluments etc. were required. All
these concepts are developed for large manufacturing concerns and varies
even from industry to industry. Considering the peculiar nature of the
construction industry, some of these concepts have been modified
wherever necessary and collected data were analyzed with the help of
percentages and structural ratios.
Sectoral linkages of the construction industry are examined with
other sectors ( namely, primary, secondary and tertiary)
Problems are identified from discussions with owners, managers,
engineers and other technical staff, workers and customers.
The prospects of the industry are related to the likely increase in demand
for construction products. The likely increase in the demand for housing,
apartments and commercial spaces is estimated until 2025.
Over the past two decades, the construction sector in Kerala has
been witnessing an amazing growth. The number of construction
participants has increased enormously. Over the past 10 years, the
number of major builders in the state has increased by 65 percent, of
medium and small builders, by 52.5 per cent each. During the same
period the number of major contracting firms registered an increase of
52.9 per cent, Medium (51.4 per cent) and small firms (126 per cent)
231
(See tables 4.13 and 4.14). A number of construction consultancy
organizations, equipment manufacturing and leasing companies and
construction labour recruitment agencies have sprung up in the state.
Along with this, many financial institutions that are catering exclusively
to construction financial requirements have also come up.
The thriving real estate sector has promoted numerous other allied
segments. Bathroom accessories, tiles both interior and exterior, steel,
wood , cement, furniture, paints and electrical gadgets are having high
demand in the state.
Real estate transactions in Kerala have registerd an annual increase
of 25 to 35 percent over the past five years and the prices across sectors
and cities have undergone an appreciation of 150 to 200 percent.
Construction industry in the state comprises very large number of
small firms. The number of small firms is, in fact, so large that the
construction is called a non-formal sector of the economy. In
construction, there are no licensing conditions or other regulations as they
exist in the manufacturing sector.
Besides being a regular purveyor of direct and indirect employment
to about 20 per cent of the state’s workforce, construction sector in
Kerala is also attracting skilled, semi skilled and even unskilled workers
from states like Bihar, Orissa , West Bengal, Maharashtra and UP. There
are migrant labour settlements in almost all districts of the state and most
of them are employed mainly in the construction sector.
The sky rocketing prices of land, cement and steel are causing
concerns. The high tax rates are yet another factor that has put the sector
in a disadvantageous position.
232
Generally, the cost of house construction is higher in Kerala when
compared to other states. This is due to the fact that all construction
materials are brought here from other parts of the country.
Economic development depends on investment. Investment policy
may have a sectoral bias in view of the priority of the economy or
generating maximum linkage effect in the system.
The linkage literature in economics talks about the positive
correlation between investment in one sector with investments in large
number of allied sectors. The construction activity is one of the sectors
that has the largest number of linkages.
There is direct mention about the backward, forward and
consumption linkages. Yet another classification can be made on the
basis of permanent and temporary linkages. Permanent linkages lead to
sustainable investment in allied sectors for a long period of time. On the
other hand, temporary linkages persuades investment in allied sectors for
short periods.
The construction sector in the state has a negative linkage with the
primary sector with more paddy fields being converted into spaces for
construction coupled with labour shortage in this sector making it less
cost effective.
Generally, construction has a strong positive linkage with the
secondary sector. The construction sector consumes the products of as
much as 169 industries. Here, in our state, the linkages with the
secondary sector is positive but weak as the state continues to be
industrially backward.
Construction is a hybrid of manufacturing and service. In service
wise linkages, both forward and backward linkages are visible.
233
While explaining linkages, one more classification seems relevant
and they are centripetal and centrifugal linkages. If investment in one
sector leads to additional investments in the various sectors of the local
economy we call it centripetal linkages. On the other hand linkages that
are not likely to have a positive impact on other sectors of the local
economy are called centrifugal linkages.
A hypothetical example has been worked out in respect of
construction projects each for rural and urban areas under two
assumptions, namely, (1) when centripetal linkages are strong, and (2)
when centrifugal linkages are strong. The additional investment in
respect of a rural project under the second assumption is only 31.82 per
cent of the total additional investment under the first assumption.
Similarly, additional investment in respect of an urban project under the
second assumption is only 44.49 per cent of the additional investment
under the first assumption.
Table 7.1
Weighted contribution of sectors to GSDP growth
(1994-95 to 2001-02)
Sector Kerala All India
Primary -4.77 13.34
Secondary 21.32 25.82
Territory 83.45 60.84
Source: Calculation based on data from CSO, National accounts (2002)
Going by the available trends, the centripetal linkages of the
construction industry in the state are not profound enough to maintain
the high growth trajectory.
The weighted contribution of various sectors to the Kerala’s GSDP
growth during the post reform period is primary sector (-4.77 per cent),
234
secondary sector (21.32 per cent), and tertiary sector (83.45 per cent)
which clearly demonstrates the acceleration in the growth of service
sector ahead of industry and agriculture.
The sustainability of the growth momentum depends upon whether
the rapidly growing service sector will be able to contribute to an
enhanced output and productivity in the industrial and other sectors.
So far the developments have not been satisfactory. There is
limited inter linkages between services and commodity producing sector
in Kerala (Subrahmanian, 2006)1.
The linear growth process experienced by the U.S in 50’s and the
U.K in 60’s leading to the emergence of post industrial societies (Bell,
1976)2 there did not happen here. But the economy and social structure of
post-industrial societies are very much manifest in the state of Kerala. It
points to a transition from pre-industrial society to post-industrial society
bypassing industrialization. The reason why backward linkages of the
construction industry in the state are thinner and forward linkages are
stronger can be attributed to the non linear growth process experienced by
the state.
History seems to underline the importance of state action in
engineering and assisting the process of take-off in developing
economies. (Bhagavathi 1987)3.
The need of the hour is to strengthen the centripetal linkages of the
construction sector as much as possible for maintaining and speeding up
the growth momentum of the state economy.
235
Economic and Financial Performance of Construction Industrial
Units
1. 6 per cent of the sample units (builders and contractors taken
together) had an average annual turnover of less than Rs. 1 million
while 20 per cent had an average annual turnover of more than Rs.
60 million.
2. Typical value of the projects tendered for is less than Rs. 5 lakh in
the case of 8 per cent of the firms while it is more than Rs. 35 lakhs
for 18 per cent of the firms.
3. Tender success rate is 6-10 per cent for 43 per cent of the sample
units while it is above 30 per cent for 14 per cent of the sample
units.
4. 98 per cent of the sample units give top priority to profit earnings
per share followed by customer satisfaction and return on
investment. Technology leadership has registered the lowest rank
among 90 per cent of the firms.
5. There is inter firm inconsistency in the financial management
practices reported to by builders and contractors. Viewed from the
technical angle, there is marked difference in their composition of
fixed and working capital. Exclusive builders generally have less
investment in plant and machinery while exclusive contractors
have a very high investment. For exclusive builders, investment in
plant and machinery was negligible in the year 2008-09 whereas in
the case of exclusive contractors, 81.12 per cent of the total fixed
capital is represented by plant and machinery during the same year.
There is also difference in the composition of physical working
capital between exclusive builders and exclusive contractors. The
capital base is poor even in the case of large firms while small
236
firms manage with very small amount of capital. This raises the
question of sustainability of construction activities undertaken by
these firms.
6. 80 per cent of the construction work in rural areas in undertaken by
small firms while 90 per cent of the work in urban areas are
undertaken by large firms. 70 – 80 per cent of the residential
construction work takes place in urban and semi-urban areas.
7. There is considerable difference in the return on networth enjoyed
with builders having a range of 5-40 per cent while contracting
firms have a range of 8-18 per cent for the period 2004-2009. The
average return on networth enjoyed by the builders for the above
period comes to 22.44 per cent while that of the contractors, it
comes to 13.47 per cent. The global economic meltdown has
affected the builders and contractors of the state with decline in
return on investment in the year 2008-09. For builders the decline
from 2007-08 was 18.1 per cent and for contractors it was 21.74
per cent.
8. The construction organizations (builders and contractors taken
together) in urban and semi-urban areas have been experiencing a
high rate of business growth measured in terms of increase in fixed
assets and annual turnover. Large players have registered average
annual growth rate of 20-40 per cent over the period 2004-09. 8
per cent of the rural and 3 per cent of the urban firms experienced
negative growth rates while 10 per cent of the rural and 40 per cent
of the urban establishments showed growth rates above 20 per cent
on an average for the period 2004-09.
9. 90 per cent of the administrative and 80 per cent of the technical
(engineering) work is given to employees recruited locally. On the
other hand, 20-60 per cent of the manual work especially low end
237
jobs are entrusted to the migrant labour force. Labour management
in the construction industry is far from satisfactory.
10. 28.5 per cent of large firms have introduced new construction
technology while only 10 per cent of the medium and small units
are ready to introduce technology upgradation.
11. Going by the sample, 90 per cent of the sample units (builders and
contractors) are not in the habit of conducting regular internal nd
external appraisals. Modern methods of strategic planning have
not found favour with a majority of the construction organizations
in the state.
12. Majority (90 per cent) of the builders and contractors follow a
“herd mentality” in their investment decisions. Construction
organizations in the state are not yet ready to experiment with
innovative product mix incorporating low cost housing, affordable
housing etc. They are yet to realize the importance of designing
multiple investment opportunities.
13. 80.9 per cent of the large construction firms have already secured
ISO 9000 certification while 60 per cent of the small and medium
firms are not even aware of it.
14. Only 9 per cent of the large firms have secured ISO 14000
certification while 92.5 per cent of the small and medium firms are
not aware of it.
Operational Efficiency of Construction Industrial Units
15. Item rate contract is found to be the most prevalent contractual
mechanism in the construction sector in Kerala. Under this
method, the owner through an appointed consultancy organization
does the engineering. Bill of quantities is furnished and the
tenderer is required to quote the price item-wise. The contractor
238
need not have large financial capacity in this case. It is practised in
subcontract packages. Due to time and cost overruns, possibilities
for disputes are more.
16. A large project will usually have a prime contractor who will
appoint sub-contractors for different work packages. A sub-
contractor, in turn, may have his own contractors for various jobs
i.e.; brick layers, concreters, painters, tile layers, electricians,
carpenters etc. The prime contractor does the co-ordination work.
Short-term employment, job tenure lasting for the project duration
only and piece rate system of payment are the major features of
contracting. 90 percent of builders in the sample followed the
above practice.
17. Analysis of the cost components of a typical building construction
project reveals that building materials constitute bulk of the
construction cost (43 per cent) followed by personnel (22.75 per
cent).
18. Structural aspects of cost components reveal that columns, beams,
walling and roofing to be the largest item of cost (31 percent)
followed by doors, windows and timber items (17 per cent) and
foundations upto plinth (14 per cent).
19. Depending upon the type of a housing project, building materials
account for 40-60 per cent of the total project construction cost.
20. Cost of cement comes to 25 per cent of the total material cost
followed by bricks / blocks (19.4 per cent) and timber cost (14.92
per cent) in the case of a representative single story house.
21. River sand which constitutes 11.94 per cent of the material cost has
become a very costly item now a days because of the restrictions
imposed by the authorities on river sand mining.
239
22. Manufactured sand or M. Sand is found to be the most suitable one
to replace river sand. However, manufacturing M. sand requires
skilled workers. Environmentalists are of the opinion that there
should be enough precautions to prevent any further pollution from
the extensive use of M-sand.
23. A movement for the use of mud in building construction is gaining
ground in Kerala. The use of mud implies the application of
traditional technology which is sure to strengthen the centripetal
linkages of the industry in the state. So far, the role of mud in
major construction projects has not been significant.
24. The use of ready mix concrete (RMC) is slowly gaining ground in
Kerala. At present, there is only 2 per cent penetration and that too
takes place mainly in urban areas.
25. It has been estimated by construction experts at the National
Institute of Construction Management and Research (2003), that
the overall potential for cost reduction of a representative housing
unit ranges from 21.5 to 37.5 per cent.
26. Productivity in construction is a very important issue. The general
method of measuring productivity i.e., )Quality(Input
)Quality(Ooutput (within a
time period, quality considered) applies to construction industry as
well. 80 per cent of large firms undertake periodic measurement of
productivity. Only 30-40 percent of small firms undertake
productivity measurements.
27. It has been observed that the highest site productivity i.e.,
producing the required quantity of construction within the
budgeted time and by the best and the cheapest method, is seldom
achieved due to technical, managerial and financial reasons.
240
28. In practice, the extent and quantity of wastages are not always
exactly measurable. However, a NICMAR study group headed by
Dr. K. N. Vaid observes that cement, steel and sand wastages
account for 86 percent of the total cost of wastage in construction
industry.
29. Very little efforts are made by residential construction units in
Kerala in applying scientific methods of Material Requirement
Planning (MRP), working out Economic Order Quantity (EOQ),
determination of lot size etc. in majority of the projects undertaken
by them.
30. Authoritative serial data on the size of the construction workforce
and its distribution by skill are not available except in the case of
projects executed by big contractors of repute.
31. Generally, in construction industry, labour is categorised into
skilled, semi-skilled and unskilled. Skilled workers like mason,
carpenters etc. have the responsibility of reporting to engineers and
senior level technical personnel. Semi-skilled workers have to
report to first class skilled workers (supervisors) and unskilled
workers have to report to the immediate boss under whom they are
working.
32. According to a study undertaken by NICMAR study group,
unskilled workers constitute 54.43 percent of the total labour
employed followed by masons (30.42 per cent) and carpenters
(7.94).
33. The survey results also conform to the observations of NICMAR
study group with masons topping the list of skilled workers in the
sample with 17.82 percent followed by carpenters (10.54 per cent),
painters and brick workers (7.02 per cent each).
241
34. Majority of the construction workers are males. However, with the
concept of family employment gaining ground, the number of
women workers has started rising in construction sites. 61.97
percent of the workers in the sample are males.
35. Majority of the workers in the sample are in the age group of 35-45
(40.14 per cent) followed by 45-55 (33.8 per cent)
36. Among the sample workers, 82 per cent have experience of more
than 10 years, and 5 per cent, of more than 40 years experience in
the construction sector. The number of workers in the 0-5 years
experience category is only 5.65 percent. This finding implies that
there is reluctance on the part of the new generation to enter the
field.
37. Among the 142 sample workers, 86 per cent are married, 6 per cent
unmarried, 5 per cent are widowed and 3 per cent are divorced and
separated.
38. Majority of the construction workers in the sample belonged to the
Other Backward Community (54.92 per cent) followed by
scheduled castes (25.32 per cent) and forward community (19.73
per cent).
39. In the sample selected, 10 per cent are illiterates. Majority of the
construction workers in the sample have got upper primary
education (28.87 per cent), graduates numbering 5 (3.52 per cent)
and one post graduate (0.73 per cent) are found in the study. Those
who got professional education were absent in the sample selected.
40. Among the sample workers only 38 workers (26.76 per cent) have
active membership in the political parties, 68 workers (47.88 per
cent) have passive membership while 36 workers (25.36 per cent)
have no membership in any political parties. Only 18 workers
(12.67 per cent) have active trade union activities, 112 workers
242
(78.87 per cent) have passive trade union activities and 12 workers
(8.46 per cent) have no participation in trade union activities.
Perhaps the reason for this is that construction belongs to the
unorganized sector of the economy.
41. Majority of the workers in the sample got an average of 10 to 15
days work per month. 30 per cent of the workers in the sample got
15 to 20 days of work and 21.13 per cent of the workers got 20 to
25 days of work on an average in a month.
42. In Kerala, construction workers get high wage rates. There is
difference in the wage rates between rural and urban workers. First
class carpenter tops the list with Rs. 375 per day followed by first
class brick worker (Rs. 370) and first class mason (Rs. 360) in
urban areas. The respective figures for rural areas come to Rs. 350,
Rs. 350 and Rs. 325.
43. A high wage rate compared to the rates in other states attracts
labour form other states. Migrant workers are employed in tile and
brick manufacturing units in several parts of Kerala. These
workers are brought by labour contractors. Taking the number of
migrant workers and their emoluments is a difficult task as most of
them are seasonal workers who generally return home soon after
their work. Very few stay back here. The situation in the migrant
labour colonies is far from satisfactory. Lack of basic facilities like
drinking water, washing and toilet facilities make their exclusive
settlements away from the mainstream. In Kerala also regular
deductions from the daily wages paid to the construction workers
are not uncommon. But the situation of the local workers engaged
here is far better than their counterparts in other states.
243
Problems in the Construction Sector
1. Construction sector in the state is fragmented. There is a large
number of small firms.
2. The industry follows non-uniform and outdated technical and
managerial practices.
3. There is lack of financial assistance for introducing technological
changes and modernization.
4. Knowledge management systems of the various construction
industrial units are poor. Information and retrieval system on
construction are weak.
5. There is continuance of age-old methods and traditional techniques
in the construction sector making it less competitive in the
domestic and international markets.
6. The technology and management practices of the construction
sector in Kerala are far behind the levels existing in other recently
developed countries.
7. Construction costs are higher in Kerala because most of the
construction materials are brought here from other parts of the
country. There is limited inter linkages between services and
commodity producing sectors in Kerala.
8. Standardization and quality control in construction are weak.
9. Designs are old and projects consume extra large quantities of
materials. Time and cost overturns are much frequent in the sector.
10. Scarcity of skilled labour force is another constraint experienced by
the sector. Along with this attempts to impart training among
workers have not found favour with the construction industrial
units.
244
11. Lack of a corporate approach in meeting the ever growing demands
of the customers. Efforts of the Kerala Builders Forum (KBF),
Kerala builders Association (KBA) and the Builders Association of
India (BAI) have not yielded the desired results.
12. Inordinate delay in getting building permits and sanctions from the
local bodies
13. Inability to take quick decisions in a terrain unfamiliar to the units.
14. Lack of serious articulation and implementation of sustainable
construction practices.
15. Housing loan penetration continues to be low.
16. Lack of adherence to safety norms.
17. Lack of a comprehensive quality management system(QMS)
18. Inability to adapt to technological changes.
19. Delay and lack of efforts in developing new building materials.
20. Lackadaisical attitude towards cost-effective and environment
friendly construction.
21. Lack of construction industry specific insurance products.
22. Less regard for the issue of housing for the economically weaker
sections and low income groups.
23. Use of harmful or potentially harmful building materials.
24. Absence of efforts to popularize environment friendly and energy
efficient management practices for the building sector.
25. Scarcity of building materials especially sand.
26. Lack of enabling tax regime.
27. Contracting issues. Cost escalations are usual in the sector. But
revision of rates not always possible.
28. Rampant reclamation of the paddy fields and wet lands leading to
ecological problems.
245
29. Inefficiency in providing basic facilities like power, drinking water
and drainage to apartment dwellers, especially, in urban areas.
30. Lack of scientific space management and infrastructure
development in cities.
31. Unauthorized constructions are on the rise. There is proliferation of
fake or special orders and the builder –politician –bureaucrat nexus
provides the culprits with safe way out.
32. At times, a total ban on land filling poses problems for genuine
construction work.
33. Lowering of Floor Area Ratio (FAR) from 4 to 1.5 inhibits vertical
growth in cities.
34. Lack of awareness and willingness on the part of the local
construction units to conform to National Building Code.
35. Very high construction costs create a situation that for many people
housing is manifestly not affordable.
36. Flow of fake currency into the real estate sector.
37. The increase in the number of migrant workers in the construction
sector and their settlement pose a problem for the authorities. At
times, it also leads to fast deteriorating quality of work.
38. Environmental Management system (EMS) is yet to acquire
popularity among the construction industrial units in Kerala.
39. No strong Research and Development base in construction
industry. Besides the linkages between R &D organization, if any,
and the industry are weak.
40. Lack of proper lending norms to construction projects.
41. Lenders are unwilling to lend to construction projects as there are
no appropriate risk assessment mechanisms.
246
42. There is acute shortage of working capital being experienced by
construction firms, especially the small ones. Moreover, the
working capital management is far from efficient.
43. Lack of an efficient Health, Safety and Environment information
system related to the construction sector.
44. Limited inter linkages between the construction sector and the
commodity producing sectors in Kerala.
45. Inability to find a viable alternative to river sand. The Mining and
Geology Department of the state is yet to develop a viable
alternative.
46. Inability on the part of units to access reasonably priced credit for
construction enterprises.
47. Infrastructure deficit, both in rural and urban areas, is posing
difficulties.
48. Inadequate investments in the construction sector. Weak
governance and out of date procedures process and processes,
vitiate the investment climate.
49. The high incidence of indirect taxation is discouraging especially
the small units from undertaking new projects.
50. Lack of professional training institutes to impart training to
construction workers.
51. Lack of provision of adequate social security and welfare to
construction workers. Only sixty percent of the construction
workers have been enrolled by the Kerala Building and Other
Construction Workers Welfare Scheme which was introduced in
1989 (John, 2004)4.
52. Many local contractors have only oral agreements with the
sub-contractors. There is widespread violation of such contracts
leading to disputes.
247
53. Employee performance appraisals, customer surveys and skills
analysis are not systematically undertaken by the construction
industrial units.
54. Lack of expertise in undertaking economic, technological, political
and social appraisals.
55. The units require more professionalism for undertaking strategic
planning practices.
56. The construction sector is yet to fully recover from the global
economic meltdown as a result of the sub prime lending muddle in
the US.
Hypotheses
1. Increase in demand for residential and commercial buildings with
modern amenities cause large construction firms to proliferate in
urban areas.
2. Need-based construction activities cause local builders and small
contracting firms to operate in rural areas.
3. There is negative linkage with the primary sector, weak linkage
with the secondary sector and positive linkage with the service
sector.
Regarding the first hypothesis the study accepts the same. There is
proliferation of large sophisticated construction units in the urban areas.
Only large firms with modern technology can satisfy the demands of
urban construction market.
The study validates the second hypothesis that in rural areas, small
and medium players dominate. The reason is that need based construction
activities constitute a major part in spite of investment based construction
in rural areas.
248
The study accepts the third hypothesis that the construction sector
has a negative linkage with the primary secotr. Expansion of construction
leads to a shrinkage in the cultivable land. It also leads to reducing the
labour availability for agricultural activities besides causing a hike in
agricultural labour rates.
Generally, construction has a strong positive linkage with the
secondary sector. The construction sector consumes the products of as
much as 169 industries. Here, in our state, the linkages with the
secondary sector is positive but weak as the state continues to be
industrially backward.
Construction is a hybrid of manufacturing and service. In service
wise linkages, both forward and backward linkages are visible.
While explaining linkages, one more classification seems relevant
and they are centripetal and centrifugal linkages. If investment in one
sector leads to additional investments in the various sectors of the local
economy we call it centripetal linkages. On the other hand linkages that
are not likely to have a positive impact on other sectors of the local
economy are called centrifugal linkages.
A hypothetical example has been worked out in respect of
construction projects each for rural and urban areas under two
assumptions, namely, (1) when centripetal linkages are strong, and (2)
when centrifugal linkages are strong. The additional investment in
respect of a rural project under the second assumption is only 31.82 per
cent of the total additional investment under the first assumption.
Similarly, additional investment in respect of an urban project under the
second assumption is only 44.49 per cent of the additional investment
under the first assumption.
249
Going by the available trends, the centripetal linkages of the
construction industry in the state are not profound enough to maintain
the high growth trajectory.
The sustainability of the growth momentum depends upon whether
the rapidly growing service sector will be able to contribute to an
enhanced output and productivity in the industrial and other sectors.
Forward Linkages
Based on the hypothetical example, the following forward linkages
have been traced.
1) Demand for furniture, 2) consumer durable, 3) desk top computers 4)
security, 5) laundry 6) gardening 7) cost of maintenance 8) cost of
decoration of the units 9) insuring the residential units and 10) marketing
the existing units for the purpose of sale.
Closely related to the forward linkages is the consumption linkage
through increased demand for goods and services especially, Fast Moving
Consumer Goods (FMCG). However, it is very difficult to trace each and
every item that becomes part of the forward linkage.
Backward Linkages
Based on the hypothetical example, the following backward
linkages are traced. They include mainly the inputs, that is, material and
non material. The main items are listed below.
1) Land, 2) sand, 3) cement, 4) steel, 5) brick 6) insulation, 7) wood, 8)
tiles 9) paint, 10) sanitary ware 11) electrical lighting and 12) fittings.
Besides the above, a number of professional services are needed
from the outset of a project till its completion. All types of labour namely,
skilled, semi skilled and unskilled are required to undertake the project. It
is estimated that a large number of manufacturing industries are
250
dependent on the construction industry for their survival, growth and
expansion. The impact of the construction industry on the commodity
market, the labour market and the financial market is phenomenal. While
assessing the linkages of the construction sector, it is found that,
backward linkages are more exactly measurable than forward linkages.
Suggestions
1. Efforts to formalize business entities in the construction sector
should be given top priority. It will make the industry more
organized. It will also help in corporatizing the entities which, in
turn, will attract venture capital in addition to professionals and the
best talent.
2. Setting up a state level agenda for construction will be a major step
in framing an integrated policy for the development of socially
responsible real estate practices.
3. Proper materials management practices are to be introduced and
efforts to reduce wastages must be implemented.
4. A construction equipment bank at the state level and the
development of equipment pool at the district level are essential for
enabling contractors and construction companies to adopt better
technology and practices. Along with this tariff burdens on
equipments should be removed for infrastructure projects to
facilitate increased use of technology in projects, boosting
contractor capacities.
5. Since the industry is labour intensive, district level knowledge
cenres should be set up to provide proper information regarding the
availability of workers of different trades in the industry. Efforts
should be made towards creating a regulatory framework for
construction labour. The industry and the government should take
251
steps for training, testing and certification of construction workers.
Institutional framework to impart training to workers must be
enhanced. Specialised courses like construction management must
be included in the curriculum so as to meet quality manpower at
the managerial level.
6. Equitable contract conditions instead of a one-size-fits-all are
required in the development perspective in order to ensure financial
stability and profitability of various projects. With this end in
view, periodic review of the prevailing contract clauses should be
made for framing standard contract clauses to minimize time and
cost over-runs on any project. The area of operation of the
Construction Industry Arbitration Association (CIAA), the benefits
of which are available now only in selected areas, should be
extended to all areas for expediting litigational matters in the
industry.
7. The stakeholders in the construction industry need to be evaluated
from time to time to enhance efficiency in this sector and for
facilitating increased credit flow into the sector. A system for
grading all entities in construction project : the contractor, the
consultant, the project owner and the project itself is to be
introduced. The aim should be to develop an objective system of
grading the agencies. An effective system to grade even small
construction companies must be developed.
8. A National Construction Productivity Centre should be set up.
Along with this, the existing national productivity organizations
should be encouraged to take more interest in construction
productivity.
9. The quality assurance system developed by Construction Industry
Development Council (CIDC) for large firms must be made
252
available to small firms by making modifications, wherever
necessary.
10. The state Government must encourage construction firms to use
local resources and local manpower wherever possible. This will
strengthen the centripetal linkages of the industry.
11. Construction firms must install knowledge management system in
their organizations to measure organization’s intellectual capital on
the one hand and to combine global view point and knowledge of
international standards in construction with specialist local
knowledge.
12. There is need to design construction specific insurance products.
The various policies should be ideally structured to cover the
technical complexities of construction projects.
13. An effective and comprehensive system of taxation exclusively for
construction sector must be instituted to encourage undertaking
new projects and for discouraging corrupt practices.
14. Construction firms have to take a proactive approach in
maintaining and improving the health of the cities. City
management should be jointly undertaken by well trained
administrators, professionals, elected representatives and people
themselves.
15. Construction participants, mainly, builders and contractors must be
encouraged to implement Environmental Management System
(EMS) as a part of the firm’s overall management system, for
developing the organisation’s environmental policy and for
ensuring compliance by the organization with the stated policy.
16. Periodic review of the various policies, practices and programmes
affecting the industry should be undertaken to create greater
awareness among the stakeholders about the opportunities and
253
threats before the industry. Firms should undertake strategic
planning practices to give insight into its working so as to redesign
them to cope with the changing environment.
17. Professional ethics and business ethics in the industry must
simultaneously be observed for accomplishing organizational
goals.
18. Strict compliance with the provisions of the National Building
Code should be ensured for maintaining structural, health, fire and
public safety.
19. The Government of India, the construction industry and the various
associations/organsiations in the sector need to take immediate
steps to make the industry competitive at home and abroad to face
the challenges and opportunities arising from trade liberalization
under the General Agreement on Trade in Services (GATS).
Practical measures need to be implemented to augment capacities
in the construction sector for sustaining the country’s comparative
and competitive advantages to survive and expand in the global
arena.
20. Construction workers form part of the workers in the unorganized
sector. Majority of these workers are illiterate migrants vulnerable
to exploitation. In order to provide better living conditions to these
workers, the Government should speed up the implementation of
the Building and Other Construction Workers (Regulations of
Employment and Conditions of Service) Act, Building and Other
Construction Workers Welfare Cess Act and the Inter-State
Migrant Act.
254
Policy Implications
1. The Government should insist on certification of construction
entities. Conditions for entry into and exit from the industry are to
be stipulated.
2. The Government should draft a state level agenda for construction.
3. Tariff burdens on equipments should be removed.
4. The Government should enhance the resources for the Industrial
Training Institutes to impart training to construction workers.
5. The Government should draft standard contract clauses and the
functions of the Construction Industry Arbitration Association
(CIAA) should be extended to more areas.
6. Objective grading system for the various stakeholders of the
construction industry should be introduced. Financial institutions
should be asked to adopt common lending norms.
7. National Construction Productivity Council should be set up.
8. The State Government should encourage use of local resources and
local manpower wherever possible. Tax incentives for firms
conforming to the above arrangements should be introduced.
9. An effective and comprehensive system of taxation exclusively for
the construction sector should be introduced.
10. Construction specific insurance products should be designed after
consultations with the Actuarial Society of India.
11. City management should be given top priority.
12. Government should insist on adoption of Environmental
Management System, especially, by large firms.
13. Strict adherence to the National Building Code must be ensured.
255
14. Periodic review of various provisions of GATS should be made
and the same should be communicated to stakeholders of the
construction industry.
15. The Government must strictly implement the Inter-State Migrant
Act. It must also implement the Building and Other Construction
Workers (Regulation of Employment and Conditions of Service)
Act and Building and Other Construction Workers Welfare Cess
Act, both of 1996. Providing workers basic amenities and other
necessities should be included as a condition in the contracts
awarded for construction projects.
Contribution
Construction is one of the least researched industries in the country. It is
also an industry that reports the minimal data about its internal working. There
are research works at the national level mostly undertaken by specialized
institutions and Government aided agencies. State specific researches exploring
the linkages of the industry in the local economy are lacking. This work is a
humble attempt to bridge this gap.
Areas for Future Research
1. There is scope for further research on the sectoral linkages of the
construction industry in the state of Kerala.
2. The linkages with the primary sector needs exhaustive study.
3. Environmental impact of the construction industry and possibility
of introducing EMS by the construction firms of Kerala is yet
another area which needs a thorough exploration.
4. Technology upgradation in the construction industry is another
area of research.
5. Various legislations and its implementations in the construction
industry can be an important research topic.
256
6. City management and role of construction participants
in maintaining and improving the health of cities can be
undertaken in respect of each of the cities of Kerala namely,
Thiruvananthapuram, Kochi and Kozhikode.
7. Tax regimes applicable to construction sector and the scope for its
modification is another area of research.
8. Migrant labour settlements in Kerala and the condition prevailing
in their colonies require an exhaustive study.
9. Labour relations in Kerala construction industry and workers
participation in welfare schemes can be another area of research
that could be undertaken.
Conclusion
“Construction Industry – Explorations into Forward and Backward
Linkages” is a humble attempt to account the events pertaining to the
industry in space and time which take place within the spatial boundary
of an economic system. As the title implies, the type of research is
exploratory. Hence, it forms part of a preliminary stage of research on
this economic phenomenon. Hope that this will help formulate more
concrete theories about this phenomenon in future. With this end in view,
certain basic economic hypotheses are formulated as distributional
assumptions, which often are not themselves subject to statistical testing
from the collected data. Of course, the validity of information so obtained
is logically conditional on the validity of the statistically unverifiable
aspects of these basic hypotheses. The study is undertaken on the
assumption that, in areas where the relevant theory is far from obvious,
this type of exploratory research will help in evolving such theories in
future.
257
In construction industry, what we effectively have is a unique
blend of possibly the largest concentration of the most diverse
professional disciplines within an environment that is largely dictated by
extreme market demands and commercially driven business objectives. In
this sense, the industry offers a challenge for dealing with issues having
several dimensions, and this should allow very worthwhile scenarios for
study that could almost certainly lead research in these areas.
References
1. Op. cit.
2. Bell, D. (1976) : “The Coming of Post Industrial Society”
Heinemann, London.
3. Op. cit.
4. John C. P. (2004) “Social Security and Labour Welfare with special
reference to construction workers in Kerala” Editorial Board
Neelakantan S., Gopinathan Nair and Shaji. H. Discussion Paper No.
65 Centre for Development Studies, Thiruvananthapuram