10
Chapter 9: Reducing Project Duration 4KF3 Page 1 of 10 Lecture Notes Options for Accelerating Project Completion Unconstrained Resources o Adding resources o Outsourcing o Overtime o Core project team o Do it twice Crashing Crash Time vs. Normal Time Crash Cost vs. Normal Cost Crash Point

Chapter 9: Reducing Project Durations3.amazonaws.com/prealliance_oneclass_sample/xYgd2L51ve.pdfChapter 9: Reducing Project Duration 4KF3 Page 1 of 10 Lecture Notes Options for Accelerating

Embed Size (px)

Citation preview

Page 1: Chapter 9: Reducing Project Durations3.amazonaws.com/prealliance_oneclass_sample/xYgd2L51ve.pdfChapter 9: Reducing Project Duration 4KF3 Page 1 of 10 Lecture Notes Options for Accelerating

Chapter 9: Reducing Project Duration 4KF3

Page 1 of 10

Lecture Notes Options for Accelerating Project Completion

Unconstrained Resources

o Adding resources

o Outsourcing

o Overtime

o Core project team

o Do it twice

Constrained Resources

o Fast-tracking

o Critical-chain

o Reduce scope

o Compromise quality

Project Crashing

The process of accelerating a project.

PMBOK: “A specific type of project schedule compression technique performed by taking action to decrease the total project schedule duration after analyzing a number of alternatives to determine how to get the maximum schedule duration compression for the least additional cost.”

Project Cost Duration Graph

Crashing

Crash Time vs. Normal Time

Crash Cost vs. Normal Cost

Crash Point

Page 2: Chapter 9: Reducing Project Durations3.amazonaws.com/prealliance_oneclass_sample/xYgd2L51ve.pdfChapter 9: Reducing Project Duration 4KF3 Page 1 of 10 Lecture Notes Options for Accelerating

Chapter 9: Reducing Project Duration 4KF3

Page 2 of 10

Project Crashing

An Example

Page 3: Chapter 9: Reducing Project Durations3.amazonaws.com/prealliance_oneclass_sample/xYgd2L51ve.pdfChapter 9: Reducing Project Duration 4KF3 Page 1 of 10 Lecture Notes Options for Accelerating

Chapter 9: Reducing Project Duration 4KF3

Page 3 of 10

Page 4: Chapter 9: Reducing Project Durations3.amazonaws.com/prealliance_oneclass_sample/xYgd2L51ve.pdfChapter 9: Reducing Project Duration 4KF3 Page 1 of 10 Lecture Notes Options for Accelerating

Chapter 9: Reducing Project Duration 4KF3

Page 4 of 10

Page 5: Chapter 9: Reducing Project Durations3.amazonaws.com/prealliance_oneclass_sample/xYgd2L51ve.pdfChapter 9: Reducing Project Duration 4KF3 Page 1 of 10 Lecture Notes Options for Accelerating

Chapter 9: Reducing Project Duration 4KF3

Page 5 of 10

Page 6: Chapter 9: Reducing Project Durations3.amazonaws.com/prealliance_oneclass_sample/xYgd2L51ve.pdfChapter 9: Reducing Project Duration 4KF3 Page 1 of 10 Lecture Notes Options for Accelerating

Chapter 9: Reducing Project Duration 4KF3

Page 6 of 10

How Short is Short Enough?

Include contract provisions in your calculations; – Some contracts have penalties for late delivery – Other projects have bonuses for early completion

Is the cost of crashing lower than the penalty for lateness?

Is the cost of crashing lower than the bonus?

Is there a strategic benefit to early completion?

Page 7: Chapter 9: Reducing Project Durations3.amazonaws.com/prealliance_oneclass_sample/xYgd2L51ve.pdfChapter 9: Reducing Project Duration 4KF3 Page 1 of 10 Lecture Notes Options for Accelerating

Chapter 9: Reducing Project Duration 4KF3

Page 7 of 10

Finding the Optimum Point

Terminology

• All Normal ‐ a project schedule in which all durations and costs are at the normal rates.

• All Crash ‐ a project schedule in which all durations are at their lowest durations.

Considerations

Crash Time Estimates

Linearity Assumption

Choice of Activities

Network Sensitivity If Cost is the Issue, Not Time?

Reduce scope

Have owner take on responsibility

Outsource

Brainstorm for Savings

Reading Notes

Rationale for Reducing Project Duration

Time to market

o Business survival depends on adaptability

When unforeseen delays cause substantial problems

o Costs of getting back on track vs. being late

Incentive contract can make reduction of project time rewarding

Imposed deadlines

Avoid/reduce high overhead costs

When it is important to reassign key equipment and/or people to new projects

Page 8: Chapter 9: Reducing Project Durations3.amazonaws.com/prealliance_oneclass_sample/xYgd2L51ve.pdfChapter 9: Reducing Project Duration 4KF3 Page 1 of 10 Lecture Notes Options for Accelerating

Chapter 9: Reducing Project Duration 4KF3

Page 8 of 10

Options for Accelerating Project Completion

Options When Resources ARE NOT Constrained

Adding Resources

o Most common method

o Limited – not necessarily a direct correlation between resources and speed

Outsourcing Project Work

o Subcontracting an activity to a contractor who may have superior knowledge or

abilities

Scheduling Overtime

o Easiest

o Disadvantages include added fees for hourly overtime charges, productivity

losses, organizational concerns, etc.

Establish a Core Project Team

o Avoiding hidden costs of multi-tasking

Do It Twice – Fast and Correctly

o Quick and dirty short-term solutions before actual solutions

Options When Resources ARE Constrained

Fast-Tracking

o Changing activity relationships from sequential to parallel

Critical-Chain

o Recall: CCPM

Reducing Project Scope

o The most common response

o Reassess the true specifications of the project

o Calculate the savings

Compromise Quality

o Rarely acceptable or used

Project Cost-Duration Graph

Procedure for identifying the costs of reducing project time so that the comparisons can

be made with the benefits of getting the project completed sooner

Project Cost-Duration Graph: see figure 9.1

o The total cost for each duration is the sum of direct and indirect costs

Indirect costs

Supervision, administration, consultants, interest

Can vary directly with time

Direct costs

Labour, materials, equipment, subcontractors

Assigned directly to a work package and activity

Page 9: Chapter 9: Reducing Project Durations3.amazonaws.com/prealliance_oneclass_sample/xYgd2L51ve.pdfChapter 9: Reducing Project Duration 4KF3 Page 1 of 10 Lecture Notes Options for Accelerating

Chapter 9: Reducing Project Duration 4KF3

Page 9 of 10

Constructing a Project Cost-Duration Graph (3 Steps)

1) Find total direct costs for project durations

2) Find total indirect costs for project durations

3) Sum direct and indirect costs for these selected durations

Determining the Activities to Shorten:

Managers need to look for critical activities that can be shortened with the smallest

increase in cost per unit of time

Normal time for an activity represents low-cost, realistic, efficient methods for completing

the activity under normal conditions

Crashing: shortening an activity

Crash time: the shortest possible time an activity can realistically completed

Crash cost: the direct cost for completing an activity in its crash time is called crash cost

Crash point: represents the maximum time an activity can be compressed

The heavy line connecting the normal and crash points represent the slope, which

assumes the cost of reducing the time of the activity is a constant per unit of time

Assumptions of graph:

o The cost-time relationship is linear

o Normal time assumes low-cost, efficient methods to complete the activity

o Crash time represents a limit – the greatest time reduction possible under

realistic conditions

o Slope represents per unit of time

o All accelerations must occur within normal and crash times

See example on pages 316-319

Practical Considerations

Using the Project Cost-Duration Graph

o Graph is valuable to compare any proposed alternative or change with the

optimum cost and time

o Want to create graph as early as possible

Crash times

o Collecting crash times can be difficult

o Times are rough at best

Linearity Assumption

Page 10: Chapter 9: Reducing Project Durations3.amazonaws.com/prealliance_oneclass_sample/xYgd2L51ve.pdfChapter 9: Reducing Project Duration 4KF3 Page 1 of 10 Lecture Notes Options for Accelerating

Chapter 9: Reducing Project Duration 4KF3

Page 10 of 10

o Reasonable, quick comparisons can be made using the linear assumption and is

adequate for most projects

Choices of Activities to Crash Revisited

o Other factors beyond cost:

Inherent risks with crashing

Timing of activities

Overallocation of resources

Impact on morale and motivation

Time Reduction Decisions and Sensitivity

o How far to reduce the project time toward the optimum depends on the sensitivity

of the project network

o A network is sensitive if it has several critical or near-critical paths

o Slack reduction in a project with several near-critical paths increases the chances

of being late

o Large savings can result in reducing paths that are insensitive (occur in about

25% of all projects)

What if Cost, Not Time, Is the Issue?

Commonly used options for cutting costs:

o Reduce Project Scope

o Have Owner Take on More Responsibility

Identifying tasks that customer can do themselves

o Outsourcing Project Activities or Even the Entire Project

o Brainstorming Cost Savings Options