Chapter 10 Dealing with Uncertainty

Page 2: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

10.1 Introduction

• ---exacerbated by regulatory & environmental uncertainty

• Restructuring of the electric industry, is more complex than imagined.

• Dealing with uncertainty is crucial.

Page 3: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

10.2 Key Issues

1. How can we make economic decisions in the face of market and nonmarket uncertainties?

2. How do we measure uncertainty, especially uncertainty about nonmarket issues like global climate change?

3. How do we determine the value of new information that might help reduce uncertainty?

Page 4: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

• Uncertainty has critical impacts. (price volatility, policy compromises)

• Development and failure of IRP (integrated resource planning).

Page 5: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

10.3 Making Investment Decisions Under Uncertainty

• Sensitivity analysis &scenario analysis• Sensitivity analysis:

“base case” model, adjust inputs individually• Scenario analysis:

same “base case”, but constructs specific “scenarios” that can include multiple changes.

Problem for both:

Ignore the likelihood of different events or scenarios; fail to identify “least-cost” choices.

Page 6: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

Table 10.1 Distribution Planning Costs

Page 7: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

Table 10-2: Expected Costs of Alternative Investment Strategies

Page 8: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

Real Options

Let us consider discounted cash flow analysis & the impact of uncertainty.

Suppose: consider whether to build a new electric generating plant; output will be sold in the wholesale market.

Page 9: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

• C=$500 million. Produce $1 million MWh per year• P either $40 per MWh or $80 per MWh,

then P=0.5*$40+0.5*$80=$60

C: cost; P: price; Q: quantity of electricity produced; r: discount rate

Page 10: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

• NPV is positive, but should also consider when P is $40:

• NPV of waiting for one year is:

If P=$40, no investment ( first term 0); if P=$80, invest. Uncertainty resolved.

---This resembles a call option on a common stock.

The cost of waiting is forgone R if the future turns out well.

Page 11: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

Figure: The future Price of Electricity

Page 12: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

• First, calculate the Min. P next year for the investment to have a positive NPV if we wait:

• This means the initial price, P0, equals P1/1.5=$30. So if P0< $30, we will never wait to invest in the plant, coz there is no chance the investment will be profitable.

Page 13: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

• Next, determine when the expected NPV of investing today is greater than expected NPV if waiting:

• P0=$78. So the opportunity cost of waiting will be greater than the value of the option to wait.

Page 14: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

Figure 10-2 :Value of Option to Invest.

Page 15: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

Figure 10-3 Increased Price Uncertainty

Page 16: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

Decision Trees and the Value of Information

• Decision trees: for making good decisions and determining the value of new info.

• Ex: deciding whether to walk to work tomorrow or ride the bus.

• Consider: weather

walk Ride Bus

Rain 0 6

No Rain

10 6

Page 17: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

• Two decision “branches” and two uncertainty branches off each decision branch.

• E(walk)=0.5*10+0.5*0=5.0• E(Bus)=0.5*6+0.5*6=6.0

• So unless gamble on the weather, you should take a bus.

Page 18: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

The Role of Emotions• Traditional economics assumes rational decision-maker.

• Sometimes, the info needed to make a rational decision is not available; some decisions are emotional or political.

• But when it comes to major investment decisions and regulatory evaluations, role of emotions should be limited.

Page 19: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

Applying Decision Analysis Techniques to the Electric Industry

Ex: a coal-fired power plant, required to reduce carbon emissions by 50% starting 5 years from now.

Choices:

1. Shut down the plant

2. Purchase emissions allowances at an unknown future P

3. Invest in a new experimental technology that is designed to capture 80% of the carbon emissions and inject it deep underground.

Page 20: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

Regulatory Impacts

• This analysis is also crucial from a regulatory standpoint.

• To ensure prudent investment• To scrutinize unregulated generators bidding into POLR

auction

Page 21: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

10.4 Measuring Price Volatility

• Forecast changes in demand and supply, to ensure that enough electricity is available to avoid blackouts;

• to evaluate whether market power concerns are likely to emerge.

• But still can not account for all.

• Volatility, similar to std.dev., but normalized to a specific time period.

Page 22: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

Figure 10-7: Henry Hub Daily Average Closing Natural Gas

Prices.

Page 23: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

• Measuring volatility is critical for :

determining the value of hedging and the cost of reducing exposure to uncertain market prices;

capital investment decision.

• Easiest way to calculate historic volatility:

1. Calculate the log of day-to-day P changes for entire y

2. Calculate the std.dev. Of those P changes

3. Multiply the std.dev. By the square root of the average number of trading days per y, usually defined as 252.

Page 24: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

10.5 Nonmarket Uncertainties

• Ex: regulatory and political structures, etc.

• What can be done?

1. Ignore nonmarket uncertainties or addressing them crudely (Diff bw risk and uncertainty); determine event thresholds

2. Add uncertainty to the decision framework3. Complications: Use judgment; decide how much risk is acceptable;

weigh the risks of different investment strategies

Page 25: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

Table 10-4 Critical Event Matrix

Page 26: Chapter 10 Dealing with Uncertainty. 10.1 Introduction ---exacerbated by regulatory & environmental uncertainty Restructuring of the electric industry,

Figure 10-8 Comparing Multiple Projects