    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    Date: 25-06-2013

    To,

    M/s. Chandak Realtors Pvt. Ltd.,

    Mumbai

    Kind Attn: Mr. Aditya Chandak,

    Sub: - Quotation for Shell Structure works of

    PROPOSED RESIDENTIAL SPARKLING WINGS BUILDING NO. 3

    (1 Basement (Pt) + Stilt + 2 Podium + 17 Upper floors)

    Sub Structure & Super Structure Works

    (RCC, Block work, Intl. Plaster & Extnl. Plaster, Water Proofing)

    at SUB PLOT 'B' ON PLOT BEARING C.T.S. NO.2872 / 6 OF VILLAGE

    DAHISAR AT DAHISAR (EAST), MUMBAI

    Respected Sir,

    We thank you for inviting us to quote for work under subject matter above. We are pleased to submit herewith

    the quotation complete in all respect with. The rates have been quoted for in respect to the scope of works

    mentioned hereafter.

    The Construction of abovementioned building shall be carried out complete in all respect for the scope of work

    described hereunder-

    Rate excluding Piling

    Approximate Built-up Area : 1,65,406 Sq. Ft.(To be ascertained with final VFC Drawing)

    Rate per Sq. Ft. Built-up Area : Rs. 1201/-(We use H 20 Beams Doka Style as used by L & T)

    o Note:- The Built up Area are subjected to change as per final drawingso (Cement, Concrete and Steel shall be provided by the developer free of cost at site.)

    Basic rate of Steel Rs. 45,000 / M.T.

    Basic rate of Cement Rs. 260 / Bag of 50kgBasic rate of Sand Rs. 6,000 / Brass

    Basic rate of Aggregate Rs. 2,400 / Brass

    Basic rate of Block Rs. 4,000 / Cu. M.

    The total final amount shall be evaluated on basis of actual total built-up area constructed on site on the basis of

    the mode measurement describe hereunder and duly certified by the Architect. The rates shall be calculated onbasis of the mode of measurement defined hereunder to arrive at the total contract value.

  • 7/27/2019 Chandak - Dahisar - Qtn Dt. 25-06-2013

    2/7

    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    Built-up AREA Calculation

    Built up area shall be calculated on following table & before start of work & accordingly payment scheduleshall be decided.

    BUILTUP AREA STATEMENT FOR BUILDING(1 Basement (Pt) + Gr. Stilt + 2 Podium + 17 Upper floors)

    Sr. No DetailsArea

    (Sq. Mtrs.)

    Area

    (Sq. Ft.)

    1 Basement 01 (Part)

    - FIRE PUMP ROOM AT BASEMENT LEVEL

    161.58 1,739.40

    2 Basement 01 (Part)

    - STP LOCATION CAPACITY 100 KLDAREA 115 SQM HEIGHT 5.0 MTR

    217.04 2,336.43

    3 Basement 01 (Part)

    -Flush tank

    21.64 232.95

    4 Ground floor - Stilt Level - Stack Parking 933.36 10,047.58

    5 1 st floor - Podium Parking 989.20 10,648.66

    6 2 nd floor - Podium Parking 987.95 10,635.22

    7 3 rd floor 682.28 7,344.72

    8 4 th floor 682.28 7,344.72

    9 5 th floor 682.28 7,344.72

    10 6 th floor 682.28 7,344.72

    11 7 th floor 708.80 7,630.20

    12 7 th floor - Refuge Area 71.06 764.90

    13 8 th floor 682.28 7,344.72

    14 9 th floor 682.28 7,344.72

    15 10 th floor 682.28 7,344.72

    16 11 th floor 682.28 7,344.72

    17 12 th floor 682.28 7,344.72

    18 13 th floor 707.46 7,615.78

    19 13 th floor - Refuge Area 71.10 765.33

    20 14 th floor 682.28 7,344.72

    21 15 th floor 682.28 7,344.7222 16 th floor 682.28 7,344.72

    23 17 th floor 682.28 7,344.72

    24 18 th floor 682.28 7,344.72

    25 19 th floor 682.28 7,344.72

    26 19 th floor - Terrace (Pt.) 65.19 701.71

    27 Terrace Lift M/c Room & Stair Cabin 196.64 2,116.82

    Total: 15,365.00 165,406.00

    Note: - The above area is approx. Actual area for payment shall be ascertained a per final VFC drawings.

  • 7/27/2019 Chandak - Dahisar - Qtn Dt. 25-06-2013

    3/7

    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    Measurement of Construction Area shall be on the following basis:

    Sr. No Description% for

    Measurement

    1. Floor area & Staircase 100%

    3. Lift Machine Room 100%

    4. Part Terrace / Dry Yard 50%

    5. Refuge 50%

    6. Gr. Floor (if above 3Mtrs.)_ 125%

    7. Flower Bed / Niche Area 70%8. Overhead Tank Nil

    9. Terrace at Roof level Nil

    10. Basement Ht more than 3.2m up to 6.00M 150%

    Measurements:

    The site In-charge shall jointly measure all the works in progress with the contractors authorized agent. Such

    measurement shall be recorded in the measurement sheets by the contractor and shall be signed by

    representative of Site In-charge. For the purpose of taking joint measurement, the contractors representativeshall be bound to be present whenever required by the Engineer In-Charge.

    Payment Schedule to the contractor: The contractor shall be paid as per the payment schedule.

    Payment Schedule:Consider following assumptions for:

    a. Concrete - 1.5 Cu. Ft / Sq. Ft. BUA

    b. Steel - 6.0 Kg / Sq. Ft. BUA

    Running Account payments:

    All running account payments shall be regarded as payments by way of advance against the final payment only

    and not as payments for work actually done and completed.

    Sr. No Description% for

    Measurement

    1 On Completion of Plinth, UG Tank & STP 15%

    2 On Completion of 1st

    slab 4%3 On Completion of slabs 51%

    3 Waterproofing 2%

    4 On Completion of O.H Tanks, Lift Machine Room 2%

    5 On Completion of Masonry 9%

    7 On Completion of Internal Plaster (Gypsum) 8%

    8 On Completion of External Plaster 8%

    9 Hand over 1%

  • 7/27/2019 Chandak - Dahisar - Qtn Dt. 25-06-2013

    4/7

    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    SCOPE OF WORK

    (RCC, Block work, Plaster & Waterproofing)

    a) The specified work shall consist of Sub Structure & Super Structure Work (RCC,Block work, Intl. & Extl. Plaster) Contract on Sq. ft. BUA basis with Part Material

    (Only cement and Steel shall be supplied by the Developer and deducted from the

    contractors bill) in accordance with the drawings issued by the Developer to the

    Contractor with specifications and rates given in Bill of quantities appearinghereunder and as described more particularly herein.

    b) The Developer shallprovide drawings approved by Architects/ Structural consultantsto the contractor to execute the work at Site.

    1. CONCRETEProving of Beams, Columns, Slabs, Chajjas, Lifts Machines Room, Lift Well, Lintels,

    Copings, UG & OH Water Storage Tanks, R.C.C. Staircase & other Walls in Site machine

    mixed concrete complete with the grade of concrete as per detailed specifications of R.C.C.

    Consultant including all formworks, reinforcement and inserts required to carry on the said

    works. Formwork for slabs shall be 12mm ply form.

    2. MASONRYAll masonry woks shall be Block masonry as per Architectural drawings and specifications.

    External masonry shall be of block 150mm thick constructed in C:M 1:5.

    Internal partition wall and elevation masonry shall be constructed in half brick walls in C:M

    1:5.

    R.C.C. runners with required reinforcement shall be provided at mid-depth of the half brick

    walls.

    All masonry works will be carried out in proper line, level & plumb.

    3. PLASTERAll internal walls shall be applied with single coat 8-12mm thick in C.M. 1:4 .

    No plaster shall be rendered to the ceilings.

    External plaster shall be finished with 5-10mm thick plaster in C.M. 1:4 with a thickness of

    6-10mm over thebacking coat.

    4.WATER PROOFING

    All Toilet and terrace water proofing shall be of Brickbat / Chemical Water Proofing

  • 7/27/2019 Chandak - Dahisar - Qtn Dt. 25-06-2013

    5/7

    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    Terms and Conditions

    1) The basic rate shall include all transportation, loading VAT or any other taxes applicable.2) Services tax and Vat applicable shall be paid by the owner.3) WATER AND ELECTRICITY (Free of Cost at Site)

    a) Construction Water: Water required for construction purpose shall be arranged at one source only

    by the Developer at free of cost at Site. The Contractor shall make the arrangement for storage of the

    construction water and distribution, including the piping, pumping and its distribution up to the place ofworks.

    b) Electricity: Electricity required for construction purpose, labour hutments and general illumination

    in and around the work place shall be arranged and borne by the Developer at one source only at free of

    cost at site.

    General common area lighting arrangement to be in scope of main contractor.

    Water and Electricity as available for the work will be supplied at one point at free of cost at site.

    c) Water supply shall be provided free of cost at point for the labour hutments and drinking purpose.

    4) Bills shall be made as per the mode of the payment attached herewith. Payments against R.A. Billsshall be paid within 7-10 days from the date of submission of the R.A. Bill.

    5) Advance (5% of Contract Amount) against mobilization shall be paid to the Contractor and may berecovered from 2

    ndR.A. Bill onwards @ 5% of the bill amount.

    6) Retention @ 2% of the value of the works executed shall be deducted from R.A. Bills and 50% shall berelease on the general completion of works.

    Balance 50% shall release after the completion of defect liability period of 6 months or one monsoon

    whichever is early.

    7) Cement and Steel shall be supplied by Developer at site. RMC shall be supplied by the Developer withRs.150/- pumping charges.

    8) The period of completion of the works shall be 18 months (plus 5 months Grace Period), Subject toavailability of VFC Drawing & Front.

    9) Delay in execution of works due to a delay from our end either in terms of elements etc. shall beadmitted by us for a period of 30 days in all. A delay beyond shall be claimed as idle charges at the rate

    of Rs. 50,000/week against idle labour, equipment, machinery etc. Also in case of unexpected delay the

    rates shall be liable for a escalation.

    10) The Site In Charge or his Senior officer appointed by the Developer shall lookafter Co-ordination ofwork and shall be authorized to inspect the work of Contractor, in way and manner as may be desired

    by the Developer.

  • 7/27/2019 Chandak - Dahisar - Qtn Dt. 25-06-2013

    6/7

    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    11) In case of work for which no such specification is supplied by the Developer, such work shall becarried out in accordance to with the instructions of the Developers Site in charge and General

    Manager - Technical.

    12) Insurance by the Contractor:a) The contractor shall take the appropriate insurance policies to cover all risks involved in

    course of execution of work related to labour, personnel, Machinery or otherwise.

    b) The contractor shall be liable for any liability, loss, claim arising in respect of any damage to

    property or in respect of personal injury or death of any person appointed by the contractor or any

    sub contractor engaged by the Contractor or for any loss caused on account of any act of

    Contractor to any other Person or Property.

    b) Contractor shall cover insurance, which he may be required under any law from time to timeor otherwise to secure himself against risk of accident etc. The Developer may ask the

    Contractor to take any other specific policy provided always that Developer shall not be liable

    for any peril which can be insured or otherwise.

    The contractor shall comply with conditions and observe all acts, rules and Regulations including

    the following:-a) Employees state Insurance Act, 1948: As applicable to himself, his employees or any other

    persons engaged or employed in course of work or in work related to Contract. The Contractor

    shall maintain all cards and records as required under the act in respect of employees andpayments and the contractor shall secure the agreement of the sub-contract to maintain such

    records. Any expenses incurred for the contributions making contributions or maintainingrecords shall be in the contractors account.

    b) Workman Compensation and employees Liability Insurance: - The Contractor alone

    shall be liable for compensation payable under workman compensation Act or any other lawin force. The Contractor shall take insurance policy for all the contractors employees engaged

    in the performance of this contract to cover all risks. If any of the work is given on Sub-

    Contract, the contractor shall require the sub-contractor to provide for compensation of

    workmen and also to provide Developers liability insurance for the latters employees if such

    employees are not covered under the contractors insurance.

    c) Minimum wages Act: - Wages shall be paid as per the prevailing Government Rules and

    records must be maintained as required.

    13) Labour Laws:-a) The contractor shall comply with all rules and regulations, obligations and restrictions imposed

    under the labour laws or any other law in force. The contractor will also ensure compliance with

    all the regulations for all his subcontractor as regards to applicable Central, State, Municipal and

    local laws. The Contractor further agrees to indemnify the Developer from any liability or penalty

    which may be imposed by the Central, State, Municipal or local authorities and also from all

    claims, suits or proceedings in respect thereof.

    b) Notwithstanding anything contained herein, the relationship between Developer and Contractor is on

    principal to principal basis and Developer shall not be liable for acts of Contractor in any way

    whatsoever and Contractor is not agent of the Developer.

    c) The Contractor further agrees and undertake as under:-

  • 7/27/2019 Chandak - Dahisar - Qtn Dt. 25-06-2013

    7/7

    Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai

    Central, Mumbai 400 008. Tel: +91 22 23012971. Email: [email protected]

    Rose Group Company

    (i)No labour below the age of eighteen years shall be employed at the site. Also no family oflabours will be allowed at site.

    (ii) Contractor shall arrange required medical facility for his workers.(iii)Wearing safety gadget/particularly glows, harness safety helmet & safety shoes are

    compulsory for all the workers, Supervisors and engineers etc. but if they do not do so, the

    Site-in charge will levy fine/penalty as deemed fit by him regularly.

    (iv)The contractor shall comply with the provision of the Apprentices act, 1961 and the rules andorders issued there under from time to time. The contractor shall also be Liable for any

    pecuniary liability arising on account of any violation by him of the Act and indemnifyDeveloper in respect thereof. The Developer may frame its own rule to levy penalties.

    14) Safety:The Contractor at his own cost shall take all safety measures to prevent accidents, mishaps etc. on siteand otherwise in course of work.

    Safety helmets, safety belts and all safety equipments as may be required and safety instructions shallbe given by the contractor to his work force and staff wherever required.

    No person either labour or staff or visitor must be present at site without helmet. Safety nets of

    Minimum of 1000 wide inside the compound or as per requirement on site to be provided by the

    contractor at the periphery of the building, at the Contractors Own cost.

    The Contractor will provide necessary safety training to all the persons employed on the premises and

    protect their health and personal safety at your own cost.

    Any injured person has to be provided proper medical aid without any loss of time.

    Rates are all inclusive and among other things include the following:-

    All the cost of material such as river sand, metal, Blocks, plasticizer, retarders (construction

    chemicals), Safety net and binding wire as required for quality construction with speed in mind.

    All shuttering material such as 12 mm ply (no plates), Beam bottom, steel props, runners, spans and the

    required tools and tackles required for the same (1 New Set of slab shuttering & 2 sets of bottoms)shall be brought by contractor at site with additional half set of slab shuttering without additional cost.

    All machinery etc. for lifting, shifting, placing, or transferring the materials for the purpose of

    construction wherever if required should be one by the Contractor. All necessary equipment for

    quality checks of material such as stilt contained, sieve analysis, cube moulds, flakiness, dust, porosity,

    as required will be brought by the contractor. Compulsory helmet, safety belt and safety shoes for the

    people (workers as well as managers).Daily cleaning the site and maintaining good housekeeping.

    Following all the laws w.r.t. to maintain records for labours such as their payment, PF, etc. workmen

    compensation insurance, working hours as per BMC rules, and following all law and order as per

    prevailing, and coming in future.

    Hope you find offer reasonable and competitive in accordance to your requirements.

    We look forward to be associated with you for the said works.

    We assure of our best services in terms of quality and timely completion of the project.

    ForPHEENIX CONSTRUCTIONS

    Partner