34
Challenges for Balancing Area Coordination Considering High Wind Penetration Robin Broder Hytowitz & Dr. Ben Hobbs, Johns Hopkins University Dr. Ozge Ozdemir, Energy Research Centre of the Netherlands (ECN) TAIC/FERC Workshop, November 7-8 2014

Challenges for Balancing Area Coordination Considering ... Hytowitz.pdf · • Wind, load diversity reduce impact of variability • Better resource use • Reserve • Unit scheduling

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

  • Challenges for Balancing Area Coordination Considering High Wind Penetration Robin Broder Hytowitz & Dr. Ben Hobbs, Johns Hopkins University Dr. Ozge Ozdemir, Energy Research Centre of the Netherlands (ECN) TAIC/FERC Workshop, November 7-8 2014

  • Outline

    • Motivation • Background • Initial Results • Future Work

  • Motivation •  Renewables add variability to system operations •  Balancing area (BA) consolidation has been proposed •  Wind, load diversity reduce impact of variability •  Better resource use

    •  Reserve •  Unit scheduling

    •  Decrease peak generation & ramping needs

    M. Milligan, B. Kirby, and S. Beuning, “Combining Balancing Areas’ Variability  : Impacts on Wind Integration in the Western Interconnection,” in WINDPOWER Conference and Exhibition, 2010.

  • Motivation •  Tradeoffs •  System size (more nodes & variables) makes solving to

    optimality more difficult •  Increasing complexity in systems operations (ex: stochastic UC)

    •  Most dramatic results are seen in studies with large consolidation

    •  Does not address uncertainty •  What’s more valuable?

    •  Challenge of merging different policies, rules, and regulations

    B. A. Corcoran, N. Jenkins, and M. Z. Jacobson, “Effects of aggregating electric load in the United States,” Energy Policy, vol. 46, pp. 399–416, Jul. 2012.

  • Questions

    • Assuming full integration is not an option: • How can we incent efficient coordination &

    trade? • What coordination comes closest to

    integration?

  • Outline

    • Motivation • Background • Initial Results • Future Work

  • General Market Timeline

    DA HA FMM RT

    Load & renewable forecasts, generation bids, fixed schedules, updates

    Resource schedules (commitment, energy, ancillary services), prices, reliability checks

    DA = Day-Ahead, HA = Hour-Ahead, FMM = Fifteen Minute Market, RT = Real-Time

  • Hurdle Rates •  Definition •  Within models, a transaction cost that represents barrier to

    trade between BAs •  “Economic friction”[1]

    •  Parameterized to simulate actual amount of trade •  Not actual price

    •  Easy to implement in model objective:

    HR(TradeA→B +TradeB→A )

  • General US Markets

    DA

    RT

    DA

    RT

    BA 1 BA 2

  • EU Markets (non-market splitting), West Coast

    DA

    RT

    DA

    RT

    BA 1 BA 2

    Bridge Out

  • EU Market-Splitting/Coupling

    DA

    RT

    DA

    RT

    BA 1 BA 2

    Bridge Out

  • CAISO – PacifiCorp – Nevada Energy Imbalance Market (EIM)

    DA

    RT

    DA

    RT

    BA 1 BA 2

  • CAISO Energy Imbalance Market Details

    DA

    RT

    DA

    RT

    BA 1 BA 2

    HA HA

    FMM FMM

  • Market BA (ex: CAISO)

    Allocation of BA Interties

    Self-schedule

    Generation bids

    Dynamic scheduling

    Bilateral contracts

    Pseudo-tie line

    (Loop flow)

    etc.

  • General US Markets

    DA

    RT

    DA

    RT

    BA 1 BA 2

  • Actual Markets

    DA

    RT

    DA

    RT

    BA 1 BA 2

    HA HA

    FMM FMM

    Self-schedule

    Pseudo-tie line Generation bids

    Dynamic-schedule

    Bilateral contracts

  • Outline

    • Motivation • Background • Initial Results • Future Work

  • Scenarios

    Real-Time

    No Coordination Hurdle Rate Full Integration

    Day-Ahead

    No Coordination

    Hurdle Rate Old WECC,

    EU non-market splitting

    Regional authorities CAISO

    Full Integration EU market

    splitting/coupling (Nordpool, APX)

    Consolidation Single RTO

  • Scenarios

    No Coordination

    Hurdle Rate

    Integration

    No Coor- dination

    Hurdle Rate

    Integration

    Day

    -Ahe

    ad

    Hour-Ahead

  • Model

    •  Types of models •  Day-ahead scheduling: unit commitment •  Commits generation units for the next day •  MILP, binary decisions represent commitment

    •  Real-time model •  Optimizes (least cost) power flow

    •  Both models: •  Subject to transmission & generation constraints (KCL,

    KVL, capacity) •  Options to curtail wind and shed load

  • Model: Integrated Market

    min cgPg,t + cgSUvg,t + cg

    NLug,t∀g∑

    ∀t∑

    Subject to: Line limits, transmission constraints (BΘ), capacity limits, ramp rates, minimum up & down times, spin & non-spin reserve requirements

    Day-Ahead

    Real-Time

    min cgPg,t∀g∑

    ∀t∑

    Subject to: Line limits, transmission constraints (BΘ), capacity limits, ramp rates, spin reserve requirements

  • Model: Hurdle Rate

    min cgPg,t + cgSUvg,t + cg

    NLug,t( )∀g∑

    ∀t∑ +HR(StAB + StBA )

    StAB − St

    BA = Pk,tline

    ∀k∈IT∑ ∀t

    Subject to

    Line limits, transmission constraints (BΘ), capacity limits, ramp rates, minimum up & down times, spin & non-spin reserve requirements

    Day-Ahead

    Real-Time

    min cgPg,t( )∀g∑

    ∀t∑ +HR(StAB + StBA )

  • Model: No Coordination

    min cgPg,t + cgSUvg,t + cg

    NLug,t∀g∑

    ∀t∑

    Subject to

    Line limits, transmission constraints (BΘ), capacity limits, ramp rates, minimum up & down times, separate spin & non-spin reserve requirements

    Day-Ahead

    Real-Time

    min cgPg,t∀g∑

    ∀t∑

    Pk,tline

    ∀k∈IT∑ = 0 ∀t

  • System Topography •  Reliability Test System 1996 •  3 Zone (99 generators,

    73 buses) •  24 hours

    •  Each BA is similar in size •  # generators •  Type of generation •  Wind capacity

    [3]

  • Results – Real Time Costs

    Total Cost (Millions $)!

    RT!

    No Coordination! Hurdle Rate! Full Integration!

    DA!

    No Coordination!

    Hurdle Rate!

    Full Integration!

    2

    2.4

    2.8

    3.2

    RT 2

    2.4

    2.8

    3.2

    RT 2

    2.4

    2.8

    3.2

    RT

    2

    2.4

    2.8

    3.2

    RT

    200

    2

    2.4

    2.8

    3.2

    RT 2

    2.4

    2.8

    3.2

    RT

    2

    2.4

    2.8

    3.2

    RT 2

    2.4

    2.8

    3.2

    RT 2

    2.4

    2.8

    3.2

    RT

    300

  • Results – Prices

    Average LMP ($/MWh)!

    RT!

    No Coordination! Hurdle Rate! Integrated Market!

    DA!

    No Coordination!

    Hurdle Rate!

    Integrated Market!

    0

    20

    40

    60

    DA RT 0

    20

    40

    60

    DA RT 0

    20

    40

    60

    DA RT

    0

    20

    40

    60

    DA RT 0

    20

    40

    60

    DA RT 0

    20

    40

    60

    DA RT

    0

    20

    40

    60

    DA RT 0

    20

    40

    60

    DA RT 0

    20

    40

    60

    DA RT

    5000

    6000

  • Results - deterministic and stochastic wind scenarios

    $2.00

    $2.20

    $2.40

    $2.60

    $2.80

    $3.00

    $3.20

    $3.40

    0%

    1%

    2%

    3%

    4%

    5%

    6%

    7%

    No Coordination

    Integrated Hurdle Rate- $3

    Hurdle Rate- $6

    Hurdle Rate- $10

    Tota

    l Cos

    t (M

    illio

    n $)

    Trad

    e as

    a p

    erce

    nt o

    f dem

    and

    Detrm - Trade Stoch - Trade Detrm - Total Cost Stoch - Total Cost

  • Price results – single wind forecast

    11% 12% 16%

    11% 11%

    0% 2% 4% 6% 8% 10% 12% 14% 16% 18%

    13.5 14

    14.5 15

    15.5 16

    16.5 17

    17.5 18

    18.5 19

    Perc

    ent c

    hang

    e be

    twee

    n DA

    and

    RT

    LMP

    ($/M

    Wh)

    DA Mean RT Mean Percent Change

  • Results – All scenarios

    0!

    0.2!

    0.4!

    0.6!

    0.8!

    1!

    1.2!

    1.4!

    1.6!

    $2,000,000! $2,500,000! $3,000,000! $3,500,000!

    Net!Trade

    !as!a!%!of!D

    emand!

    Total!Cost!($)!

    Integration Day-Ahead

    Hurdle Rate Day-Ahead

    No Coordination Day-Ahead

    ■ DA ▲ RT Integration ♦ RT HR ● RT NC

  • Conclusions •  Integrated markets yield most gains from trade •  Barriers on interties impede efficient markets •  Going from no coordination to hurdle rates makes large

    difference •  Further lowering hurdle rates most beneficial in DA rather

    than RT •  Further work needed to determine the simplifying

    effect of hurdle rates relative to actual barriers •  Which barriers are most important to address? •  Who should be responsible for removing inefficiencies?

    •  When no RT coordination, there might not be enough generation on-line to meet demand •  Average prices more consistent DA vs RT when there is

    no coordination day-ahead

  • Outline

    • Motivation • Background • Initial Results • Future Work

  • Future Work •  Different size BAs, different generation mix •  Modeling specific barriers on the intertie line •  Self-scheduling •  Dynamic-scheduling

    •  COMPETES model – ECN •  Look at European grid

    •  Additional balancing areas •  Greatest benefits for renewables

  • Thank you! Questions?

    Email: [email protected]

  • References •  [1] Joseph H. Eto, Douglas R. Hale and Bernard C. Lesieutre,

    “Toward More Comprehensive Assessments of FERC Electricity Restructuring Policies: A Review of Recent Benefit-Cost Studies of RTOs” The Electricity Journal

    •  [2] Frank Wolack, “The Economics of Self Scheduling,” Presentation available: http://www.caiso.com/Documents/Presentation-Economics-Self-Scheduling-MSCPresentation.pdf

    •  [3] Jesús María López-Lezama, Mauricio Granada-Echeverri, and Luis A. Gallego-Pareja, “A combined pool/bilateral dispatch model for electricity markets with security constraints” Ingeniería y Ciencia, June 2011.