Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Challenges for Balancing Area Coordination Considering High Wind Penetration Robin Broder Hytowitz & Dr. Ben Hobbs, Johns Hopkins University Dr. Ozge Ozdemir, Energy Research Centre of the Netherlands (ECN) TAIC/FERC Workshop, November 7-8 2014
Outline
• Motivation • Background • Initial Results • Future Work
Motivation • Renewables add variability to system operations • Balancing area (BA) consolidation has been proposed • Wind, load diversity reduce impact of variability • Better resource use
• Reserve • Unit scheduling
• Decrease peak generation & ramping needs
M. Milligan, B. Kirby, and S. Beuning, “Combining Balancing Areas’ Variability : Impacts on Wind Integration in the Western Interconnection,” in WINDPOWER Conference and Exhibition, 2010.
Motivation • Tradeoffs • System size (more nodes & variables) makes solving to
optimality more difficult • Increasing complexity in systems operations (ex: stochastic UC)
• Most dramatic results are seen in studies with large consolidation
• Does not address uncertainty • What’s more valuable?
• Challenge of merging different policies, rules, and regulations
B. A. Corcoran, N. Jenkins, and M. Z. Jacobson, “Effects of aggregating electric load in the United States,” Energy Policy, vol. 46, pp. 399–416, Jul. 2012.
Questions
• Assuming full integration is not an option: • How can we incent efficient coordination &
trade? • What coordination comes closest to
integration?
Outline
• Motivation • Background • Initial Results • Future Work
General Market Timeline
DA HA FMM RT
Load & renewable forecasts, generation bids, fixed schedules, updates
Resource schedules (commitment, energy, ancillary services), prices, reliability checks
DA = Day-Ahead, HA = Hour-Ahead, FMM = Fifteen Minute Market, RT = Real-Time
Hurdle Rates • Definition • Within models, a transaction cost that represents barrier to
trade between BAs • “Economic friction”[1]
• Parameterized to simulate actual amount of trade • Not actual price
• Easy to implement in model objective:
HR(TradeA→B +TradeB→A )
General US Markets
DA
RT
DA
RT
BA 1 BA 2
EU Markets (non-market splitting), West Coast
DA
RT
DA
RT
BA 1 BA 2
Bridge Out
EU Market-Splitting/Coupling
DA
RT
DA
RT
BA 1 BA 2
Bridge Out
CAISO – PacifiCorp – Nevada Energy Imbalance Market (EIM)
DA
RT
DA
RT
BA 1 BA 2
CAISO Energy Imbalance Market Details
DA
RT
DA
RT
BA 1 BA 2
HA HA
FMM FMM
Market BA (ex: CAISO)
Allocation of BA Interties
Self-schedule
Generation bids
Dynamic scheduling
Bilateral contracts
Pseudo-tie line
(Loop flow)
etc.
General US Markets
DA
RT
DA
RT
BA 1 BA 2
Actual Markets
DA
RT
DA
RT
BA 1 BA 2
HA HA
FMM FMM
Self-schedule
Pseudo-tie line Generation bids
Dynamic-schedule
Bilateral contracts
Outline
• Motivation • Background • Initial Results • Future Work
Scenarios
Real-Time
No Coordination Hurdle Rate Full Integration
Day-Ahead
No Coordination
Hurdle Rate Old WECC,
EU non-market splitting
Regional authorities CAISO
Full Integration EU market
splitting/coupling (Nordpool, APX)
Consolidation Single RTO
Scenarios
No Coordination
Hurdle Rate
Integration
No Coor- dination
Hurdle Rate
Integration
Day
-Ahe
ad
Hour-Ahead
Model
• Types of models • Day-ahead scheduling: unit commitment • Commits generation units for the next day • MILP, binary decisions represent commitment
• Real-time model • Optimizes (least cost) power flow
• Both models: • Subject to transmission & generation constraints (KCL,
KVL, capacity) • Options to curtail wind and shed load
Model: Integrated Market
min cgPg,t + cgSUvg,t + cg
NLug,t∀g∑
∀t∑
Subject to: Line limits, transmission constraints (BΘ), capacity limits, ramp rates, minimum up & down times, spin & non-spin reserve requirements
Day-Ahead
Real-Time
min cgPg,t∀g∑
∀t∑
Subject to: Line limits, transmission constraints (BΘ), capacity limits, ramp rates, spin reserve requirements
Model: Hurdle Rate
min cgPg,t + cgSUvg,t + cg
NLug,t( )∀g∑
∀t∑ +HR(StAB + StBA )
StAB − St
BA = Pk,tline
∀k∈IT∑ ∀t
Subject to
Line limits, transmission constraints (BΘ), capacity limits, ramp rates, minimum up & down times, spin & non-spin reserve requirements
Day-Ahead
Real-Time
min cgPg,t( )∀g∑
∀t∑ +HR(StAB + StBA )
Model: No Coordination
min cgPg,t + cgSUvg,t + cg
NLug,t∀g∑
∀t∑
Subject to
Line limits, transmission constraints (BΘ), capacity limits, ramp rates, minimum up & down times, separate spin & non-spin reserve requirements
Day-Ahead
Real-Time
min cgPg,t∀g∑
∀t∑
Pk,tline
∀k∈IT∑ = 0 ∀t
System Topography • Reliability Test System 1996 • 3 Zone (99 generators,
73 buses) • 24 hours
• Each BA is similar in size • # generators • Type of generation • Wind capacity
[3]
Results – Real Time Costs
Total Cost (Millions $)!
RT!
No Coordination! Hurdle Rate! Full Integration!
DA!
No Coordination!
Hurdle Rate!
Full Integration!
2
2.4
2.8
3.2
RT 2
2.4
2.8
3.2
RT 2
2.4
2.8
3.2
RT
2
2.4
2.8
3.2
RT
200
2
2.4
2.8
3.2
RT 2
2.4
2.8
3.2
RT
2
2.4
2.8
3.2
RT 2
2.4
2.8
3.2
RT 2
2.4
2.8
3.2
RT
300
Results – Prices
Average LMP ($/MWh)!
RT!
No Coordination! Hurdle Rate! Integrated Market!
DA!
No Coordination!
Hurdle Rate!
Integrated Market!
0
20
40
60
DA RT 0
20
40
60
DA RT 0
20
40
60
DA RT
0
20
40
60
DA RT 0
20
40
60
DA RT 0
20
40
60
DA RT
0
20
40
60
DA RT 0
20
40
60
DA RT 0
20
40
60
DA RT
5000
6000
Results - deterministic and stochastic wind scenarios
$2.00
$2.20
$2.40
$2.60
$2.80
$3.00
$3.20
$3.40
0%
1%
2%
3%
4%
5%
6%
7%
No Coordination
Integrated Hurdle Rate- $3
Hurdle Rate- $6
Hurdle Rate- $10
Tota
l Cos
t (M
illio
n $)
Trad
e as
a p
erce
nt o
f dem
and
Detrm - Trade Stoch - Trade Detrm - Total Cost Stoch - Total Cost
Price results – single wind forecast
11% 12% 16%
11% 11%
0% 2% 4% 6% 8% 10% 12% 14% 16% 18%
13.5 14
14.5 15
15.5 16
16.5 17
17.5 18
18.5 19
Perc
ent c
hang
e be
twee
n DA
and
RT
LMP
($/M
Wh)
DA Mean RT Mean Percent Change
Results – All scenarios
0!
0.2!
0.4!
0.6!
0.8!
1!
1.2!
1.4!
1.6!
$2,000,000! $2,500,000! $3,000,000! $3,500,000!
Net!Trade
!as!a!%!of!D
emand!
Total!Cost!($)!
Integration Day-Ahead
Hurdle Rate Day-Ahead
No Coordination Day-Ahead
■ DA ▲ RT Integration ♦ RT HR ● RT NC
Conclusions • Integrated markets yield most gains from trade • Barriers on interties impede efficient markets • Going from no coordination to hurdle rates makes large
difference • Further lowering hurdle rates most beneficial in DA rather
than RT • Further work needed to determine the simplifying
effect of hurdle rates relative to actual barriers • Which barriers are most important to address? • Who should be responsible for removing inefficiencies?
• When no RT coordination, there might not be enough generation on-line to meet demand • Average prices more consistent DA vs RT when there is
no coordination day-ahead
Outline
• Motivation • Background • Initial Results • Future Work
Future Work • Different size BAs, different generation mix • Modeling specific barriers on the intertie line • Self-scheduling • Dynamic-scheduling
• COMPETES model – ECN • Look at European grid
• Additional balancing areas • Greatest benefits for renewables
Thank you! Questions?
Email: [email protected]
References • [1] Joseph H. Eto, Douglas R. Hale and Bernard C. Lesieutre,
“Toward More Comprehensive Assessments of FERC Electricity Restructuring Policies: A Review of Recent Benefit-Cost Studies of RTOs” The Electricity Journal
• [2] Frank Wolack, “The Economics of Self Scheduling,” Presentation available: http://www.caiso.com/Documents/Presentation-Economics-Self-Scheduling-MSCPresentation.pdf
• [3] Jesús María López-Lezama, Mauricio Granada-Echeverri, and Luis A. Gallego-Pareja, “A combined pool/bilateral dispatch model for electricity markets with security constraints” Ingeniería y Ciencia, June 2011.