14
1 Challenges and Solutions for RES integration within the Spanish Power System. Red Eléctrica’s role Toledo, 18 June 2010 Juan Fran. Alonso Llorente RED ELÉCTRICA DE ESPAÑA Red Eléctrica de España (REE): Mission and principles. The existence of REE, world pioneer since 1985, as independent and exclusively dedicated to Transmission and System Operation, has proved fundamental for the fast and secure implementation of electricity market and integration of RES Designs, builds and maintains the transmission network. Since 2007 as exclusive transmission company Operates the system to guarantee the power supply. Since 2006 also in the extra-peninsular systems REE and the integration of RES. Toledo. 18 June 2010 FREE- FLOAT 80% SEPI: Spanish Stated Owned Holding Company SEPI 20 % SHARE CAPITAL (Closure 2009): 2 Transmission Grid Main magnitudes (SPPS) Closure 2009 REE vs. TOT Lines 400 kV [km ct] 17 977 99,8% 220 kV [km ct] 16 777 98,4% Subst. 220 & 400 kV [nº bays] 3 385 96,8% Transformers 400/X kV [MVA] 66 259 98,8%

Challenges and Solutions for RES integration within the

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Challenges and Solutions for RES integration within the

1

Challenges and Solutions for RES integration within the Spanish Power System.

Red Eléctrica’s role

Toledo, 18 June 2010 Juan Fran. Alonso Llorente

RED ELÉCTRICA DE ESPAÑA

Red Eléctrica de España (REE): Mission and principles.The existence of REE, world pioneer since 1985, as independent andexclusively dedicated to Transmission and System Operation, has provedfundamental for the fast and secure implementation of electricity market andintegration of RES

Designs, builds and maintains the transmission network.

Since 2007 as exclusive transmission company

Operates the system to guarantee the power supply.

Since 2006 also in the extra-peninsular systems

g

REE and the integration of RES. Toledo. 18 June 2010

FREE-FLOAT

80%

SEPI: Spanish Stated Owned Holding Company

SEPI 20 %

SHARE CAPITAL (Closure 2009):

2

Transmission GridMain magnitudes (SPPS)

Closure 2009

REE vs. TOT

Lines400 kV [km ct] 17 977 99,8%

≤ 220 kV [km ct] 16 777 98,4%

Subst.≤ 220 & 400 kV [nº bays] 3 385 96,8%

Transformers 400/X kV [MVA] 66 259 98,8%

Page 2: Challenges and Solutions for RES integration within the

2

ContentsOverview of the Spanish Power System

Integration of Renewable Generation (RES) in Spain

past and prospects

sensitive aspects of RES for the power system

In System Planning and Access

Defining new technical requirementsDefining new technical requirements

In System Operation: the generation control

Final Remarks and Possible trends

RED ELÉCTRICA DE ESPAÑA

251.509 GWh = 181.614 Net Ordinary Regime+ 81.785 Net Special Regime

3 770 H d t d d

Yearly Demand supply and coverage 2009

- 3.770 Hydro-pump storage demand- 8.120 International exchanges

Special Regime GenerationRenewable:Minihydro

Non Renewable:Cogeneration

Hydro‐power8.9%

Nuclear19.1%Wind

13 7%

Rest of special regime12.4%

Photovoltaic2.0%

Minihydro2.0%

REE and the integration of RES. Toledo. 18 June 2010

MinihydroBiomassWindIndustrial wasteUrban wasteSolar

CogenerationCoalFuel - Gas oilRefinery gasNatural gas

Coal12.1%

Fuel‐Gas0.7%

Combined cyclles29.0%

13.7%

Page 3: Challenges and Solutions for RES integration within the

3

RED ELÉCTRICA DE ESPAÑA

Installed capacity May 2010

Technology MW %H d RE C ti Waste Treat Hydro-power 16.657 17,85

Nuclear 7.455 7,99Coal 10.856 11,63Fuel-Gas 1.849 1,98Combined cycles 24.294 26,04Total (ordinary regime) 61.111 65,49Wind power generation 18.842 20,19Solar power 3.548 3,8Biomass 647 0,69

Hydro17,85% Nuclear

7,99%

Coal11,63%

Combined Cycle26,04%

Wind20,19%

Solar3,80%

Biomass0,69%

Hydro RE2,11%

Cogeneration6,46%

Waste Treat.1,25%

REE and the integration of RES. Toledo. 18 June 2010

Special regime hydro 1.965 2,11Cogeneration 6.027 6,46Waste treatment 1.170 1,25Total (special regime) 32.199 34,51

Total 93.310

Fuel‐Gas1,98%

26,04%

3.268 MW Solar PV280 MW Solar Thermal

RED ELÉCTRICA DE ESPAÑA

Integration of renewables: prospects and challenges

38.000 MW*

Ambitious national objectives for RES (20% of final energy in 2020) requireadditional integration within the power system (>40% in the electric energy )

8.367 MW* 5.079 MW*

• Grid development• Technical Requirements• Control by TSO and more

Particular features imply technical and management challenges for the powersystem and the generation:

Location far from load and gridVulnerability to incidents(voltage dips)Primary energy: Lack of firmness and control

REE and the integration of RES. Toledo. 18 June 2010

REE is working to maximise SecureIntegration of RES in Power System

* Draft of NAP to by submitted to EC in June10

… without forgetting other organisational aspects

dispatchable resourcesPrimary energy: Lack of firmness and control

Page 4: Challenges and Solutions for RES integration within the

4

RED ELÉCTRICA DE ESPAÑA

Challenges for integrating RES generation. REE’s actionsRED ELÉCTRICA works for maximizing the secure integration of RES generation in its

different functions as System Operator and Transmission company:

Development and

reinforcement of

transmission grid

Energy Prospective: access and grid planning

Generation Adequacy Studies

Management of access and planning studies and proposals. Capacity Studies

Regulatory proposals (Grid Code) identifying technical and operational requisites

M t i l ti h i

REE and the integration of RES. Toledo. 18 June 20107

Management in real-time horizons

Production forecast: Wind and recently solar

Management of Ancillary Services

Contribution to system dispatchability by the development of a specific control arquitecture for RES generation

RED ELÉCTRICA DE ESPAÑA

Managing Access and Planning the GridA good programming of new non-transmission facilities (e.g., generators) musttake into account decision and commissioning processes in transmission grid:

Decision on transmission facilities

Access to the grid• Regulated process to

assess the aceptability ofa new non-transmissionfacility

• Continuous process

Grid Planning• REE carries out the planning studies andproposals• National Goverment, with the collaboration ofRegional Administrations, approve the griddevelopment plan

• Every 4 years, new horizon (10 y)• Every year review with same horizon

REE and the integration of RES. Toledo. 18 June 20108

Continuous process• Every year, review with same horizonBinding (unlike indicative planning forgeneration)

The actual development of the grid (authorization, construction and ; from 1to more than 10 years)

Page 5: Challenges and Solutions for RES integration within the

5

RED ELÉCTRICA DE ESPAÑA

Grid development

WIND POWER: High presence intransmission (>60%, contrary toother systems with high penetration)

NºNodesRdT Today Future

220 & 400 kV 49 > 100

and expected to increase

250 MW150 MW 250 MW 22 MW

150 MW

REE and the integration of RES. Toledo. 18 June 2010 9

3.830 MW

4.293 MW 2.960 MW

Grid Applications: 14.730 MWT: 11.583 MWD: 3.147 MW

41 MW

435 MW

49 MW

22 MW

400 MW

100 MW

1.800 MW

SOLAR POWER:

TS.- Majoritary in transmission (≈ 80%)

FV.- Minoritary in transmission(≈ 5% ofexisting; few new plans)

RED ELÉCTRICA DE ESPAÑA

RES generation does not avoid distribution grid but requires transmissionexpansion, where the majority of Wind Power (>60%) and Solar Thermal (>80%) isexpected. RES is a relevant motivation in the current Plan:

new lines and reinforcements for avoiding constrains operation facilities associated to physical connection

Main challenges: Grid Development

N b t ti d b

VCONEJOS

RIBARROJA

LAFORTUNA

ELBROSQUIL

SABON

MA R IN A

AGUAYO

ANLLARES

APARECIDA

BOIMENTE

CARTELLE

COMPO STIL LA

ELPALO

PESOZ

GRADO

L AL OMBA

LAROBLA

L ADA

MASGALAN

MONTEARE

NARCEA

SANZO SALAS

VELILLA

VILECHA

VILLAMECA

ALMAZAN

SENGRACIA

AZPEITIA

ARRUBAL

CASTEJONELEREBRO

LAGOAÇA

CRODRIGO

GRIJOTA

HERNANI

HERRERA

HINOJOSA

ICHASO

LASERNA

MURUARTE

OLMEDOOLMEDO

SAUCELLE

VILLARIN

VIRTUS

VITORIA

ARAGON ASCO

BE GUE S

BESCANO

CCTELNOU

C. BARBA

ESPLUGA

CALDERS

ESCATRON

MEZQUITA

LLOGAIA

S. PALLARS

MEDINACELI

OSERA

MUNIESA

PENAFLOR

PEÑALBA

GARRAF

RIUDARENES

RAMIS

P IE ROL ARUEDA

SALLENTE

GRAMANE T

TERRER

MUDEJAR TERUEL

MAIALS

VANDELLO

ALMARAZ

ANCHUEL O

ROMICA

VVA ESCUDEROS

AYORAAYORA

CASTELLON

CEDILLO

COFRENTES

COLOREJA

CORTESII

FUENTES ALCARRIA

BELINCHON

GALAP AGAR

LASTRAS

L OECHE S

MORELLASALSADELLA

LAMUELA

MINGLANILLA

MORALE J A MORAT A

OLMEDILL

T VE L ASCO

REQUENA

PINOFRANQUEADO

SEGOVIA

TORRENTE

CE REAL

TRILLO

T ORRECI LL A

GAUSA

VIL LAVE RDE

VALDECABALLEROS

LINDOSO

FALAGUEIRA

ARGIA

BAIXAS

AGUAYO

AMEIXEIRAS

ACERIASA

ALBARELL

APARECIDA

ASTILLER

A. ZINC

BELESAR

ABO ÑO

DUMBRIA

EIRIS

CARRIO

CHANTADACHANTADA

CACICEDO

CARTELLE

CAMBADOS

CASTRELO

CILLAMAYOR

CONSO

CORNATEL

CTCOMPOSTIL LA

FRIEIRA

LAGRANDA

GRELA-2

L AL OMBA

LUBIAN

MATAPORQUERA

MASGALAN

MEIRAMA

MONTEARENAS

MDCARRIO

MONTOUTO

MTESL EON

ONDINAS

P.BIBEY

CANDO

PDEMOURO

PEÑADRADA

PEREDA

PRADA

P.E.SIL

PSMIGUEL

PUERTO

QUERENO

REMOLINA

RIBADELAGO

S.AGUSTIN

CAYETANOCAYETANO

S.ESTEBAN

S.MARINA

S.PEDRO

SANABRIA

SANCOMPO

SANTIAGO

SIDEGASA

SI ERO

SNIACE

SOBRADELO

SOTO RI BERA

SOUTELO

SUIDO

TABIEL LA

TELLEDO

TIBO

TRASONA

CICERO

TRIVES

UNINSA

GUARDO

VELLE

VILLABLINO

VIMIANZO

MAZARICOARISTRAIN

ALCARAMA

ALDEADAVILA

ALI

AYALA

ELCERRO

CASTRO

ELGEA

CORDOVILLA

FORJASGAMARRA

ALCOMOLAALCOMOLA

GAROÑA-BARCINA

HERNANI

HERRERA

ICHASO

IRUN

JUNDIZ

LAGUARDIALORA

LASERNA

MAZORRAS

LOGROÑO

MERCBENZ

MEDINA

MIRANDA

MUDARRAI

ORCOYEN

OLITE

ORMAIZTEGUI

MURUARTE

PASAJES

POZASAL

QUEL

P.POZA

RENEDORICOBAYO

SANGUESA

SANTIZ

SAUCELLE

SENGRACIA

SEQUERO

TAFALLA

TORDESILLAS

TUBACEXTUBOS

TUDELA

MONDRAGON

LAOLMA

VALLEJERA

VALPARAISO

VILLALBILLA

VILLAMAYOR

VILLARINO

VITORIA

ZAMORA

ZUMARRAGA

ABRE RA

ADRALL

A.GURREA

ESCALDES

ASCO

ALMUDEVAR

AE NOE ST E

ATALAYA

BADALONA

ALBATARREC

LA SELVA

ANOI ABAYO

BELLICENS

BSONUEVO

BE GUE S

BESCANO

BIESCAS

CABEZO SR

CALAMOCHA

CANY E T

AENAE STEAENAE STE

CARTU JOS

GAVA

CAST E LL E T

CEL SA

CENTELLES

CSBI SBAL

E I XAMP L E

ELOL IVAR

ENTRERRIOS

SESUE

ERISTE

ESCALONA

ESCATRON

ESPARTAL

F OIX

F RANQUE SES

FUENDETODOS

GRADO

GUIXI ERE S

GURREA

JALON

JUIA

JUNEDA

L AROCA

LANZASAGUDAS

L E SCORT

VIENTOS

L.L EONES

LLAVORSI

LOSVISOSMANGRANERS

TORSEGRE

MAGALLON

MANF I GUE RE S

MARAGALL

MARIAMAT A

MEDIANO

MEQUINENZA

MEZQUITA

CE RVE L LO

MONCAYO

MONTBLANC

M ONTETORRERO

AVEZARAG

MONZON

CINCA

ELS AUBALS

MORALETS

NUDOVIAR

ONCALA

T ANGCAT A

P AL AU

PEÑAFLOR

PERAFORT

P IE ROL A

PL AZA

POLA

PUIGPELAT

R.CALDE S

REPSOL

RMART ORE L L

RUBI

RIOGALLEGO

RUBIO

CAN J ARDI

S . ANDRE U

VIL ADE CANS

S.BOIS .BOI

S .CUGAT

S.CELONI

S.JUST

S.F OST

SABADSUR

SABIÑANIGO

SE NT MENAT

SUBI RAT SSUBI RAT S

CERCS

BARO VIVE R

TARDIENTA

TABESCAN

CONSTANTI

TARRAGONATARRAGONA-G

T RINI TAT

TARRAPOWER

T RSNT BOI

EL VENTERRO

TREVAGO

VANDELLOS

URGE L L

VIC

P E NE DES

VIL LANUEVA

Z. FRANCAZAL

VI LANOVA

ACECA

ALBAL

AL GE TE

ALDAYA

ARANJUEZ

ALMARAZ

AÑOVER 2

AÑOVER

ARGANDA

AZUTAN

AL CO BE NDAS

ARR. VEGA

AZCA

BECHI

ALBURQUERQUE

ARAVACA

BOADIL L A

BOLARQUEAGUACATE

BENIFERRI

CERP L AT A

C.F RE GACC.F RE GAC

CACERES

R-C REAL

CE REAL

CANI L LE J AS

COSL ADA

CASATEJADA

CVALMANZ

SIDMED

ELGRAO

E LCOT O

EALMARAZ

EL IANA

ELEMPERADOR

EL P IL AR

ERVAL DEM

L AE STRE

F .S.LUIS

F .MUESTRAS

FORT UNA

F UENCARRAL

F T ECI LL A

G.GALAN

GALAP AGAR

GE T AF E

GUIJOG.

DAGANZO

EL HORNIL LO

HUELVESINGENIO

ALAMEDA

J.CABRERA

LAPALOMA

L UCE RO

MADRIDEJOS

M AJ ADAHONDA

MBE CE RRAMBE CE RRA

ME CO

MEL ANCOL

MIRASIE RRA

MORAT A

ARDOZ

NORTE

OLMEDILLA

OTERO

P RADSANT

P ARACUE L LOS 1

PATRAIX

PE RAL ES

P OL IGONC

PICON

P ROSP E RI

P ARL A OE ST E

T VE L ASCO

P RI NCESAP RI NCESA

P SF ERNANDO

QUARTPOB

PLASENCIA

RE TAMAR

RI VAS

PRAHONAL

SAGUNTO

SEGORBE

SIMANCAS

TORREJON

TORRENTE

TORRIJOS

T 3CANT OS

VALDECANVALDECANVALDECAN

VAL DEMORO

VAL DRIVA

VALL E CAS

VALLDUXO

VENT AS

VILLARES

TRILLO

BEMPOSTA

POCINHO

ARGIA

PRAGNERES

TORRVEGA

TPALENCIA

VICAL VAR

SANTURCEZIERBENA

AL ONSOTEGUI

BASAURI

GATICA

GUEÑES

NERVACERO

ORTUEL LA

SANTURCE

SIDENOR

ACEBI ZK

BABCOCK

ABANTOEL ABRA

ZAM UDIO

AMOREBIETA

ABADIANO

ALCUESCAR

CARRIO

BENICARLO

OROPESA

COSTA VERDE

VALLDIGNA

P.TABERNES

BENICULL

CATADAU

VENDRE LL

SABON

MORA

OLMEDILLA

PUENTELA

HIJAR

SOLORZANO

BENADRES

PENAGOS

PENAGOS

LAPOBLA

L APL ANA

LOURIZAN

PAZOSBORBEN

JM.ORIOLJM.ORIOL

STAPONSA

ATIOS

TOMEZA

ALUMINIO

ESQUEDAS RAMIS

MUDARRA

OTERO

ESPLUGA

ARENALES TRUJILLO

T VE LASCO 2

P ARACUE L LOS 2

CAN RIGAL T

GRAMANE T

CDIMAGE N

CASACAMPO

CORNIDO

P.G.RODRIGUEZP.G.RODRIGUEZ

VILLAGARCIA

LARACHA

MESON VENTO

VENTORRILLO

N. VIGO

BALAIDOS

S.CL AUD IO

PIELAGOS

ABERIN

LAS LLANAS

EZCABARTE

CRODRIGO

LAGUNA

CORCOS

VILLIMAR

CARDIEL

ALCIRA

ABANTO

BUE NAVIST A

TRI GALE S

V.ARCIP RE ST E

L AS MATAS

AL CALA II

CAMARMA

ME DI ODIA

RET IRO

L IST A

ARKALE

P ARL A

CAMPOMAYORSTA. TERESA VALDEPEÑAS

CARRASES

PUZOL

PQ. CABECERANOUMOLES

VIVEROS

LA TORRE

VINAROZ

FACUL TAT

LE SSEP S

CODONY E R

CE RDA

VAL DONCEL L ES

CORNE L LA

COL LBL ANC

SERRALLO

BURRIANA

MONCOFAR

MORVEDREMORVEDRE

P.SUERT

PUJALT

ARMUÑA DE TAJUÑA

EBORA

VALMOJADO

LAS ARROYADAS

TRENEDO

VILLATOROHARO

LARDERO

MATAPORQUERA

VALLE DEL NALON

S.MARCOS

VIL ADE CANS

VIL L AVE RDEVIL L AVE RDEVI L LAVE R E STE

BRIVIESCA

VILLARREAL SUR

CAN J ARDI 2

TJ ARA2TJARA1

SOLORZANO

MOT ORS

MIRANDA

TSIDMED

ZARATAN

SORIA

VILL ALL ANA

PALENCIA

P RADOLONGO

SAGRE RA

I LL E SCAS

N.S .COL OMA

S.A . BARCA

SARRI Á

TAMON

SILVOTA

LUGO

LABARCES

PTO. LAPICE

VILLAMANIN

N. DUMBRIA

ESCUCHA

S. PALLARS

HOSP I TAL ET

SANT S

CALAMOCHA

SAMA

PQ . C ENTRA L

VERNEDA

S.COLOMA

LOSCERROS

CONGOSTO

MERCAMADRIDVDCARROS

FUENLABRADA

CARPETANIA

PINTOAYUDEN

LEGANES

PINTOMORALEJA

VILLAVICIOSA PQINGENI

COLIMPICA

CAMPONACVALDEBEBAS

LAS MERCEDES

HORTALEZA

SANCHINARROAENA

PARACUELLOS

CDEPORTI

BRUNETE

SSREYESSSREYES2

VICALVAROPALAFOXMAZARRED

ARGANZUELA

LOS PRADILLOS

S.ROQUE

TALCIRA

PIÑOR

BERROCALES

LOECHES2

ANCHUELO

VILLALCASAYAGO

TURIS

SALSADELLA

ESTEPAR

BECILLA

VAL L EGON

S.FELIU

DESVERNDESVERN

N.BARRIS

RAMBLETA

PONFERRADA

BEJAR

CAÑAVERAL

TURIS

ALFORJA

TAMON

FUENTE HITO

CANTALEJO

PLATEA

DELTEBRE

LA PUEBLANUEVA

TALAVERAARAÑUELO

SESENA

L AJARA

OLVAN

S.COSTERA

CARIÑENA

MONZON II

TABIEL LA II

PIÑUEL

SAGRAJASSAGRAJAS

TAMBRE II

MONTEDERRAMOS

TORRECILLA

TAMBRE NUEVA

MONZON II

TABIEL LA II

MORELL

ELS AUBALS

SECUITASECUITA

facilities associated to physical connection

OH Circuit [km] 12.270UG Cables [km] 386Uprating lines [km] 8.308SS [nº bays *] 3.476Transformers [MVA] 52.450Reactors [Mvar] 2.800Capacitors [Mvar] 1.100

New substations and baysSome 100 buses in 220 kV

and 50 in 400 kV

REE and the integration of RES. Toledo. 18 June 2010

CASARES

ROMICA

ALANGE

ASOMADA

NESCOMBRERAS

PEÑARRUBIA

MANZANARES

TOTANA

PALMARPALMAR

PINILLA

ROCAMORA

ARCOSFRT

BRAZATORTAS

ARCHIDONA

SIBALBOA

GBRAL TAR

GUADAME

CARTAMA

BIENVENIDA

BROVALES

BAZA

HUENEJA

CARTUJA

JORDANA

ARENAL

LITORAL

SAN SERVAN

CABRA

PINARREY

CARMONA

TARIFA

PTOCRUZ

ALQUEVA

ALARCOS

BENEJAMA

R-C.REAL

CAMPOAMOR

CANTALAR

ARGAMASILLA

NOVELDA

BAJO SEGURA

ELCHE2

ESCOMBRERAS

FAUSITA

LAPALOMA

LA NAVA

HOYAMORENA

MTEBELLO

PALMAR

PALMERAL

PETREL

PICON

ROJALES

S.VICENT

SMSALINAS S.

S.P.PINATAR

SANTAPOLA

ACERINOX

ARROYOVALLE

AL CORES

AL GECIRA

ALHAURIN

ALMODOVAR

ALVARADO

ANDUJAR

ATARFE

BALBOA

BRAZATORTAS

CARTAMA

CADIZ

CARTUJA

CASARES

CASILLAS

SALTERAS

COSTASOL

COSTALUZ

ARENAL

DRODRIGO

ELCOGAS

ENCE

DOSHMNAS

GABIAS

FACINAS

CAPARACENA

FARGUE

SAN SERVAN

GUADAME

BENAHAVIS

GUILLENA

JORDANA

MONTEBAJO

MERIDA

VENTILLA

OLIVARESOLIVARES

ONUBA

PARRALEJO

ORGIVA

GAZULES

PINARREY

PALOS

PURMARIAPURMARIA

POLIGONO

PTOREAL

P.LLANO

ROCIO

SANTIPON

S.ELVIRA

CARMONA

SID ERAND

TAJOENCANTADA

PTOCRUZ

TORARENILLAS

UBEDA

VENTAINES

VNUEVREY

S.ROQUES.ROQUE

MANZANARES

N.CASARES

TALQUEVA

PALMAR

TCASARES

SAX

VAGUADAS

AZAHARA

QUINTOS

VILANOVA

CAMPANARIO

GANDIAP.TABERNES

VERGEL

TORREVIEJA

LANCHA

PUEBLA DE GUZMAN

JIJONA

N C.COLON

SANLUCAR

MONTEALEGRE

GIBALBIN

ALCOLEA

MAZUELOS

CORNISA

MONTIJO

RODANDAL

L.MONTES

EUROPACENTRO

TORREMOLINOS

ENSANCHE

URSO

PUENTE GENIL

GUADAIRA

PADUL

BENAHADUX

CORBONES

COSARIO

ULEA

BALSICASMURCIA

MAR MENOR

SUPERNORTEIL IPA

PAL ACIOS

VIRGENRO

ESPARTINASSTABARBARA

RANILL AS

EMPALME

CABO HUERTASALTET

RABASA

ALICANTE

TORREMENTORREMEN

MAIMONA

BERJA

VILLAJOYOSA

SMSALINAS N.

MONDAATANASIO

MANILVA

SALADAS

ANTEQUERA

RODANDAL

CENTENARN.CENTENAR

ARNEVA

LA RIBINA

NERJA

ANTEQUERA 2

JANDULA

LITORALTABERNASTABERNAS

UNIVERSIDAD

CASTALLAPETREL ESTE

JIJONA

MONTESA

GANDIA SUR

GUADAIRA

CRUZCAMPO

ATAL AYA

STAJUSTA

ENTRENUCL EOS

LOSRAMOS

CARRILPITAMO

SALADAS

ILLORA

M ARI SM AS

PAL OMARES

AL JARAFE

CASAQUEMADA

LA NAVA II

ALMADEN

SAGRAJAS

N.SALADAS

BARRIOS

Particular significance: Spain-France interconnection

Page 6: Challenges and Solutions for RES integration within the

6

RED ELÉCTRICA DE ESPAÑA

The development of Spain-France Interconnection with a2 1000 MW DC d d li

Development of the Spain-France Interconnection: A priority

Spain –and Portugal- form a peninsula, also electrically, with weak electricalinterconnections with the European Union.

new 2 x 1000 MW DC underground line-Prioritary Project with “European Coordinator”-1st step for objective of 4.000 MW of commercialcapacity-Necessary for building the IEM-Fundamental for RES integration in Spain (& Portugal)

REE and the integration of RES. Toledo. 18 June 2010 11

RED ELÉCTRICA DE ESPAÑA

The transmission grid development in EuropeThe Ten Tear Network Development Plan (TYNDP) is being elaborated byENTSO-E

RES integration is a main motivation: representing > 25% of investment

REE and the integration of RES. Toledo. 18 June 2010

Presented by ENTSO-E at Florence forum

Page 7: Challenges and Solutions for RES integration within the

7

RED ELÉCTRICA DE ESPAÑA

Access and Connection : OverviewProcedures for Access and Connection are managed by REEMain Features

Main Perspective Object - Scope

Access System Operation System behaviour

Procedures

Access ApplicationConnection to Transmission >>> SO (REE)

Connection to Distribution (> 10 MW.) > DO> SO (REE)

REE issues a report evaluating access feasibility, fulfilling system security criteria

Access System Operation System behaviour

Connection Transmission Engineering and Physical Feasibility

2m

REE and the integration of RES. Toledo. 18 June 201013

pConnection Application >>> Trans.Co.

Agent submits engineering Project and Programme

Trans.Co. elaborates Report of Technical Conditions for Connection

SO (REE) supervises and issues a report

Agent < TECHNICAL ACCESS CONTRACT> Transmission Company

1m1m

RED ELÉCTRICA DE ESPAÑA

TOPOLOGICAL SCOPE NATURE OF LIMITATION

Planning and access studies for special generationThe planning and access studies are carried out with different analysisperspectives and different time horizons, resulting in connection capacitieswhich enable location optimization:

• Transmission node (and associateddistribution)

Load flow capacityShort-circuit power (Scc)Stability

ΣCapNode > CapReg : Nodal capacities are not mutually compatible and resulting grid development needs are not coherent• Electric zones (and associated distribution)

sharing constraintLoad flow capacityShort-circuit power (Scc)Stability

Regional and Zonal Capacities are the “reference” for Regional Administrations (competent f AA f SRG) d f t

REE and the integration of RES. Toledo. 18 June 2010 14

for AA of SRG) and for access management• Power System Feasibility Balance P+jQ

Stability

This scenario validates up to the regional level and avoids persistentconstraints within this scope

However, lack of national coordination does not prevent potential constraintswhen regional plans are developed up to their limits

Page 8: Challenges and Solutions for RES integration within the

8

RED ELÉCTRICA DE ESPAÑA

Prospects for SRG. Recent regulationNew national regulation oriented to gradual control of generation to beconnected per year, securing economic and technical sustainability:

Non PV: RDL6/2009 (7may09): Register and mechanism (9 requisites, incl A&C)

ResMin 19Nov09 (CM Agreement13nov09): Identification of generation projects withl ti t f Wi d Pl t ( 1 700 MW) d S l Th l l t ( 500 MW)annual contingents : for Wind Plants (≈ 1.700 MW) and Solar-Thermal plants (≈ 500 MW)

{in adition, ≈ 500 MW in Solar PV }

6604

6604

12115

12115

18719

18719

8792

18719

27511

7982

14734

22715

EOL_RdDp 

EOL_RdDr

EOL_RdTp 

EOL_RdTr

EOL_TOTp 

EOL_TOTr

PES

CTA pte PES (RdT)

AutCon pte PES

REE and the integration of RES. Toledo. 18 June 2010 15

81

81

250

250

331

331

903

4254

5157

752

1669

2421

0 5.000 10.000 15.000 20.000 25.000 30.000

TS_RdDp 

TS_RdDr 

TS_RdTp 

TS_RdTr

TS_TOTp

TS_TOTr 

MW

AutCon pte PES

AutAcc pte PES

Preasig pte PES RDL 6/2009 

Acumulado PES  ÷ Aut. Acceso

Acumulado PES  ÷ Aut. Preasig.

RED ELÉCTRICA DE ESPAÑA

Need to identify and regulate requirements, carried out in coordination withthe Wind power industry

Technological vulnerability (voltage dips leading to disconnections).

t t f Situations where

Main Technical Requirements

Voltage (pu)

1

0,2

0,5 1 Time (sec)

start of disturbance

0,80,95 pu

0 15

Clearance of the faultFault length

Situations where generators must

remain connected0,6

2 ph isolatedfault

The “grid code” (PO 12.3) establishes the required

level for Low Voltage Through CapabilityReal Time Risk Assesment

Minimum Requirementproposed for Solar PV

REE and the integration of RES. Toledo. 18 June 2010

g g p y

Very good response from the wind generators (adaptation except <1,000 MW)New requirements associated to the increasing need for contribution tostability: specially dynamic control of voltageOther challenges: protection equipment and philosophy

Page 9: Challenges and Solutions for RES integration within the

9

RED ELÉCTRICA DE ESPAÑA

The contribution to power supply. Records in 2009 (i)Wind generation may have a very relevant contribution to the power demandsupply

Some Maximum Records:12.948 MW 24/02/10 11:21 h11 074 MW 24/02/10 11-12 h

REE and the integration of RES. Toledo. 18 June 2010 17

11.074 MW 24/02/10 11-12 h278.507 MWh 04/05/10Maximum contribution to demand:54% 08/11/09

RED ELÉCTRICA DE ESPAÑA

The contribution to power supply . Records in 2009 (ii)… but the contribution to demand supply may also be very low

Some Minimum Records:164 MW 03/06/10 11 h

REE and the integration of RES. Toledo. 18 June 2010

In consequence, fluctuating nature of wind power is translated in a lowcontribution to power supply guarantee

Minimum contribution to demand:<1% 03/06/10

Page 10: Challenges and Solutions for RES integration within the

10

RED ELÉCTRICA DE ESPAÑA

Needs for real time operation

Dispatchable Generation is required to:supply the demand (D)compensate for nondispatchable gener. (NDisG)

System Operability depends on

managing power resources:

‐ Forecast

prevent contingencies, what implies sufficient and fast enough reserves

Disp.Gen.Requirement= (D+ЄD) ‐ (NDisG+ЄNDG) +/‐ Contingencies

40000

45000

Forecast

‐ Observability and Control

existance of resources

Demand and Requirement (Winter Week) 

2,8

3,0

3,2 Evolution of Requirement Ratio  (= Daily RequirMax/RequirMin)

REE and the integration of RES. Toledo. 18 June 2010 19

15000

20000

25000

30000

35000

Lunes Martes Miércoles Jueves Viernes Sábado Domingo

MW

1,2

1,4

1,6

1,8

2,0

2,2

2,4

2,6

0% 10% 20% 30% 40% 50% 59% 69% 79% 89% 99%

Rat

io

2004 2005 2006 2007 2008 2009 Prevision 2011 (realizada en 2006)

RED ELÉCTRICA DE ESPAÑA

Generation ForecastDespite production programs/forecasts from generators, REE must elaborateown preditions as a guarantee for security of operation, in particular for RES:

WIND: : REE has improved forecasting accuracy for wind by evolution of SIPREOLICO, although there seems to be limitations due to the difficuties of metheorologicalpredictions

REE and the integration of RES. Toledo. 18 June 2010

SOLAR: REE is using a very approximated estimation tool based in irradiationforecasts. Shortly, a specific tool using real time meteo data and real time generationmeasures

Page 11: Challenges and Solutions for RES integration within the

11

RED ELÉCTRICA DE ESPAÑA

Control Need and Actions upon Special Generation

Special Generation has to be dispatched with priority over OrdinaryGeneration.Consequently, whenever possible the SO must solve the technical

t i t b i i i t ti t O di G ticonstraints by issuing instructions to Ordinary Generation:Power Output Reduction

Disconnection of Plants

However, it may be necessary to issue Control Actions on SpecialGeneration, by :a) Production Constraints (reduce or disconnect):

REE and the integration of RES. Toledo. 18 June 2010 21

Local zonal congestions (transmission or distribution)

System Stability (instruction depending on technical compliance of plants)

G-D balance in power and regulating reserve (specially off-peak and transitions)

b) Q/V Management: Set-point from SO substitutes reference for cosϕ(established RD661)

RED ELÉCTRICA DE ESPAÑA

Generation Control requirements

Control of RES Generation Plants (GP) by TSO is necessary for maintaningsystem security and to maximize RES production by reducing preventiverestrictions and delay upto real time. This involves in real time:

Observability for “all” plants: GP REAL TIME INFO TSO

(production, voltage, connectivity, …)

Operability for “all significant” plants: TSO INSTRUCTIONS GP

production control (active power)

provision of system services (reactive,regulation,)

For security and efficiency, this interlocution between TSO and GP should not beindividual (several hundreds of plants) but via Generation Dispatch Centers with

REE and the integration of RES. Toledo. 18 June 2010

individual (several hundreds of plants) but via Generation Dispatch Centers withcontrol capability over a number of plants

Human and technical resources (24 h)

Secure and redundant Connection Dispatching Centre <> REE CC(computer<>computer, telephone)

Connection Dispatching Centre <> Wind Farms-Generators

Page 12: Challenges and Solutions for RES integration within the

12

RED ELÉCTRICA DE ESPAÑA

CECRE: Created by REE in 2006, is a control centre devoted to Special Regime Generation and especially to Wind Power:

Integrated in REE’s control structure

Communication with generation Control Centres (SRGCCs) for supervision and control instructions.

REE’s Solution: CECRE

According to RD661/2007 all special regime plants >10 MW must be connected to a SRGCC.

CECRE issues generation instructions through the SCADA system to the Control Centres.

CECOEL / CECORE

CECRE

Link

Direct Link CECRE‐SRG where Setpoint Instruction 

is transmitted automatically to be converted by plant

REE and the integration of RES. Toledo. 18 June 2010 23

SRGCC: Special Regime Generation Control Centre

CCCONV: Control Centre for conventional generation

Link and telecommand

SRGCCnSRGCC1CCCONV …Link and 

telecommand 

Iccp L

Link and telecommand

686 WPP via 16 GCCs326 nonWPP via 21 GCCs

(June 2010)

in effective action, was a scenario non used

25 SRCCGs

RED ELÉCTRICA DE ESPAÑA

INTEGRATION IN CECRE OF OTHER GENERATION TECHNOLOGIESIn 2009 new information and functionalities have been incorporated

REE and the integration of RES. Toledo. 18 June 201024

Page 13: Challenges and Solutions for RES integration within the

13

RED ELÉCTRICA DE ESPAÑARisks of Insufficient Control: Observability

In Spain, an unexpected magnitude of Photo‐Voltaic generation (close to 4 GW)has been connected. However, the plant fragmentation (≤ 100 kW modules dueto retribution conditions) has avoided real time tele‐measurements and theplants are “hidden behind ” the demand.

Lack of observability involves inefficient reserve programming and may become

9D08: Mild&Cloudy

Same forecast from

generators 9D and 10D

y p g g ya serious risk for system operation

Expected

REE and the integration of RES. Toledo. 18 June 2010

10D08: Clear&Cold

No real time observabilityand unreliableprogrammes

Unavoidable errors whenprogramming RequirementNeeds

Unexpected

RED ELÉCTRICA DE ESPAÑA

Production mismatch (production vs. forecast )

REE and the integration of RES. Toledo. 18 June 2010

Page 14: Challenges and Solutions for RES integration within the

14

RED ELÉCTRICA DE ESPAÑA

The many advantages of renewable energy lead to maximize installation.

In this context, REE works in the solution of the drawbacks of RES generation(technical, organisational, regulatory) in order to preserve the security andquality of supply in the power system.

Integration of RES: Final Remarks and Possible Trends

quality of supply in the power system.

In particular, for Solar PV controllability and technical adequacy

However, still a number of challenges remains:

- Dispatchable Gen: very demanding regime and decreasing running time

RES will be submitted to operating conditions including productionconstraints; specially related to off-peak situations and transitions

REE and the integration of RES. Toledo. 18 June 2010

In the solution, a significant leap forward is needed based on:

New flexible generation and enlarging energy storage possibilities

More active participation of the demand side

Incorporation to the electric sector energy consumption currently in othersectors: Electric Vehicles

RED ELÉCTRICA DE ESPAÑA

www.ree.es

REE and the integration of RES. Toledo. 18 June 2010 28

Juan Francisco Alonso Llorente