21
CEM 515 PROCESS ANALYSIS & IMPROVEMENT Presented BY: Omar Abdulrahman Srour

CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

  • Upload
    lamtram

  • View
    214

  • Download
    1

Embed Size (px)

Citation preview

Page 1: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

CEM 515PROCESS ANALYSIS & IMPROVEMENTPresented BY: Omar Abdulrahman Srour

Page 2: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Process DescriptionThis process is followed by contractors working for Saudi Aramco LSTK & LSBP contracts for the procurement of major materials and equipments . The process starts upon the award of contracts to contractors and should be strictly followed while procuring long lead materials. The main milestones of the process are the following:1. Technical acceptance Package: this package includes the proper description of the materials,

it’s proper 9Com number and category and the agreed level of inspection.2. Material requisition Package (MR): This includes the request for quotation package and the

content of this package includes the data required by the manufacturers to bid for the supply of the equipments (i.e. material description and qty, specification and related standards, Drawings and datasheets)

3. Inspection Assignment Package (IAP): The IAP is prepared for all equipments with level of inspection greater than 0 . This includes at least the MR content in addition to the Purchase Order( PO), Inspection and Test Plan (ITP), Third Party Inspector resume, pre-inspection meeting (PIM) agenda, approved none material requirements (NMR-601)

Page 3: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Process flow chart

Page 4: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Process flow chart

Page 5: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Process flow chart

Page 6: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Process flow chart

Page 7: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Process flow chart

Page 8: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Process Customers

The Customers of the described Process are:1. The Project Team2. The Client ( Saudi Aramco)

Page 9: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Customers expectations

The expectations of Process Customers are:1. Procurement of equipments per the project

standards and specifications2. On time Delivery of the project equipments

Page 10: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Process Inputs and InterfacesThe inputs of the Process are:1. The project Material Take Off sheets (MTO)2. The Project specification and design3. The client standardsThe Process Interfaces are:1. Contractor Project execution Team2. Saudi Aramco Project Management team (SAPMT)3. Vendor Inspection Department (VID), Saudi Aramco4. Contractor Procurement Department5. Equipment’s manufacturer6. Third Party Inspection Agency7. Main contractor store / Project Store

Page 11: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Process Outputs

The outputs of the Process are:1. Procurement of project equipments from regulated

vendors incompliance with project design, specification and standards

Page 12: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Process Problems

It has been noticed during the 15% external quality audit of this process hat the procurement department have placed orders to none approved vendors and an NCR have been issued.

Page 13: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

NCR Copy

Page 14: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Problem Root Cause

Ishikawa fishbone diagram tool have been utilized to illustrate the

possible causes of the problem

Page 15: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Root Cause Analysis through Fishbone Diagram for NCR # 02

Procedures/Policies

QUALITY TEAM

Project Team

PROCUREMENT

MR not followed during PO/IAP

Procurement process Not clear

Designer recommendation shall not be considered as vendor approval

PO placed on assumption and experiences

QAM Not reviewed PO

Pro. Suvr. not verified the vendor approval while technical approval

RFQ’s obtained from none approved supplies

Not discussed with VID prior to PO placement Lack of coordination with

proc.

Project Tam not aware about Approved vendors

Material technical acceptance not distributed to all relevant parties.

RVL List was not followed during RFQ

Vendor approval limit not verified & confirmed

Vendor approval conformance not obtained

MR/RVL not followed

Page 16: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Recommendations

1. Revise the Process layout for more clarity2. Insure the compliance with TA by all parties via

proper distribution of the document 3. Procurement Dept should refrain from sending

RFQ’s to none approved vendors

Page 17: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Revised Process flow chart

The Following slides shows the revised Process diagram and will be implemented on a pilot project prior to final implementation

Page 18: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of
Page 19: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of
Page 20: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of
Page 21: CEM 515 PROCESS ANALYSIS & IMPROVEMENT - KFUPMfaculty.kfupm.edu.sa/CEM/bushait/CEM_515-082/Flow-chart/Process... · it’s proper 9Com number and category and the agreed level of

Thank You