Upload
abegaelbautista
View
227
Download
0
Embed Size (px)
Citation preview
7/28/2019 CE533 Chp4 PW Analysis
1/68
ByAssoc. Prof. Dr. Ahmet ZTA
Gaziantep University
Department of Civil Engineering
CHP IV-PRESENT WORTH ANALYSIS
CE 533 - ECONOMIC DECISIONANALYSIS IN CONSTRUCTION
7/28/2019 CE533 Chp4 PW Analysis
2/68
2 / 68CE533 - PW Analysis
TOPICS
Formulating Alternatives
PW of Equal-Life AlternativesPW of Different-Life alternatives
Future Worth Analysis
Capitalized Cost AnalysisIndependent projects
Payback Period
CHP IV-PRESENT WORTH ANALYSIS
7/28/2019 CE533 Chp4 PW Analysis
3/68
3 / 68CE533 - PW Analysis
4.1 FORMULATING MUTUALLY EXCLUSIVEALTERNATIVES
Viable firms/organizations have thecapability to generate potentialbeneficial projects for potential
investmentTwo types of investment categories
Mutually Exclusive Set
Independent Project Set
7/28/2019 CE533 Chp4 PW Analysis
4/68
4 / 68CE533 - PW Analysis
4.1 FORMULATING MUTUALLY EXCLUSIVEALTERNATIVES
Mutually Exclusive set is where acandidate set of alternatives exist(more than one)
Objective: Pick one and only one fromthe set.
Once selected, the remainingalternatives are excluded.
7/28/2019 CE533 Chp4 PW Analysis
5/68
7/28/2019 CE533 Chp4 PW Analysis
6/68
6 / 68CE533 - PW Analysis
4.1 FORMULATING MUTUALLY EXCLUSIVEALTERNATIVES
Mutually exclusive alternatives competewith each other.
Independent alternatives may or may
not compete with each otherThe independent project selectionproblem deals with constraints and mayrequire a mathematical programming orbundling technique to evaluate.
7/28/2019 CE533 Chp4 PW Analysis
7/68
7 / 68CE533 - PW Analysis
4.1 Type of Alternatives
Alternatives CF are classified asrevenue-based or cost-based
Revenue/Cost the alternatives consist
of cash inflow and cash outflows Select the alternative with the maximum
economic value
Service the alternatives consist mainlyof cost elements
Select the alternative with the minimumeconomic value (min. cost alternative)
7/28/2019 CE533 Chp4 PW Analysis
8/68
8 / 68CE533 - PW Analysis
4.1 Evaluating Alternatives
Part of Engineering Economy is theselection and execution of the bestalternative from among a set of
feasible alternatives
Alternatives must be generatedfrom within the organization
One of the roles of engineers!
7/28/2019 CE533 Chp4 PW Analysis
9/68
9 / 68CE533 - PW Analysis
4.1 Evaluating Alternatives
In part, the role of the engineer toproperly evaluate alternatives froma technical and economic view
Must generate a set of feasiblealternatives to solve a specificproblem/concern
7/28/2019 CE533 Chp4 PW Analysis
10/68
10 / 68CE533 - PW Analysis
4.1 Alternatives
Problem
DoNothing
Alt.1
Alt.2
Alt.m
Analysis
Selection
Execution
If there are m investment proposals,
we can form up to 2m mutually exclusive alternatives.This includes DN option.
7/28/2019 CE533 Chp4 PW Analysis
11/68
11 / 68CE533 - PW Analysis
4.1 Alternatives: The Selected Alternative
Problem Alt.Selected
Execution
Audit and Track
Selection is dependent upon the data, life,discount rate, and assumptions made.
7/28/2019 CE533 Chp4 PW Analysis
12/68
12 / 68CE533 - PW Analysis
4.2 Present Worth Approach Equal-Lifes
Simple Transform all of the current
and future estimated cash flow back to
a point in time (time t = 0)
Have to have a discount rate before the
analysis in started
Result is in equivalent dollars now!
7/28/2019 CE533 Chp4 PW Analysis
13/68
13 / 68CE533 - PW Analysis
4.2 THE PRESENT WORTH METHOD
At an interest rate usually equal to or
greaterthan the Organizationsestablished MARR.
A process of obtaining theequivalent worth of future cashflows to some point in time
called the Present Worth
7/28/2019 CE533 Chp4 PW Analysis
14/68
14 / 68CE533 - PW Analysis
4.2 THE PRESENT WORTH METHOD
P(i%) = P(+) P(-).
P(i%) = P( + cash flows) +
P( - cash flows)
OR, . . .
7/28/2019 CE533 Chp4 PW Analysis
15/68
15 / 68CE533 - PW Analysis
4.2 THE PRESENT WORTH METHOD
If P(i%) > 0 then the project isdeemed acceptable.
If P(i%) < 0 the project is usuallyrejected.
If P(i%) = 0 Present worth of costs = Presentworth of revenues Indifferent!
7/28/2019 CE533 Chp4 PW Analysis
16/68
16 / 68CE533 - PW Analysis
4.2 THE PRESENT WORTH METHOD
If the present worth of a project turns out to =0, that means the project earned exactly thediscount rate that was used to discount the cashflows!
The interest rate that causes a cash flows NPVto equal 0 is called the Rate of Return of the
cash flow!
7/28/2019 CE533 Chp4 PW Analysis
17/68
17 / 68CE533 - PW Analysis
4.2 THE PRESENT WORTH METHOD
A positive present worth is a dollaramount of "profit" over the minimumamount required by the investors(owners).
For P(i%) > 0, the following holds true:
7/28/2019 CE533 Chp4 PW Analysis
18/68
18 / 68CE533 - PW Analysis
4.2 THE PRESENT WORTH METHOD
Depends upon the Discount Rate Used
The present worth is purely a
function of the MARR (thediscount rate one uses).
If one changes the discount rate, adifferent present worth will result.
7/28/2019 CE533 Chp4 PW Analysis
19/68
19 / 68CE533 - PW Analysis
4.2 THE PRESENT WORTH METHOD
For P(i%) > 0, the followingholds true:
Acceptance or rejection of aproject is a function of the timingand magnitude of the project'scash flows, and the choice of thediscount rate.
7/28/2019 CE533 Chp4 PW Analysis
20/68
20 / 68CE533 - PW Analysis
4.2 PRESENT WORTH: SpecialApplications
Present Worth of Equal LivedAlternatives
Alternatives with unequal lives: Beware
Capitalized Cost Analysis
Require knowledge of the discount rate
before we conduct the analysis
7/28/2019 CE533 Chp4 PW Analysis
21/68
21 / 68CE533 - PW Analysis
4.2 PRESENT WORTH: Equal Lives
Present Worth of Equal LivedAlternatives straightforward
Compute the Present Worth of eachalternative and select the best, i.e.,smallest if cost and largest if profit.
7/28/2019 CE533 Chp4 PW Analysis
22/68
22 / 68CE533 - PW Analysis
4.2 Equal Lives Straightforward!
Given two or more alternatives withequal lives.
Alt. 1
Alt. 2
Alt. N
N = for allalternatives
Find PW(i%) for each alternative then compare
7/28/2019 CE533 Chp4 PW Analysis
23/68
23 / 68CE533 - PW Analysis
4.2 PRESENT WORTH: Example
Consider: Machine A Machine B
First Cost $2,500 $3,500
Annual Operating Cost 900 700
Salvage Value 200 350Life 5 years 5 years
i = 10% per year
Which alternative should we select?
7/28/2019 CE533 Chp4 PW Analysis
24/68
24 / 68CE533 - PW Analysis
4.2 PRESENT WORTH: Cash Flow Diagram
Which alternative should we select?
0 1 2 3 4 5
$2,500A = $900
F5=$200MA
0 1 2 3 4 5
$3,500
F5=$350
A = $700
MB
7/28/2019 CE533 Chp4 PW Analysis
25/68
25 / 68CE533 - PW Analysis
4.2 PRESENT WORTH: Solving
PA= 2,500 + 900 (P|A, .10, 5)200 (P|F, .01, 5)
= 2,500 + 900 (3.7908) - 200 (.6209)
= 2,500 + 3,411.72 - 124.18 = $5,788
PB = 3,500 + 700 (P|A, .10, 5)
350 (P|F, .10, 5)= 3,500 + 2,653.56 - 217.31 = $5,936
SELECT MACHINE A: Lower PW cost!
7/28/2019 CE533 Chp4 PW Analysis
26/68
26 / 68CE533 - PW Analysis
4.2 Present Worth of Bonds
Often corporations or government obtaininvestment capital for projects by sellingbonds.
A good application of PW method is theevaluation of a bond purchase alternative.
If PW < 0 at MARR, do-nothing alternativeis selected.
A bond is similar to an IOU for time periodssuch as 5, 10, 20 or more years.
7/28/2019 CE533 Chp4 PW Analysis
27/68
27 / 68CE533 - PW Analysis
4.2 Present Worth of Bonds
Each bond has a face value V of $100,$1000, $5000 or more that is fullyreturned to the purchaser when the
bond maturity is reached.
Additionaly, bond provide thepurchaser with periodic interest
payments I (bond dividends) using thebond coupon (interest) b, and c, thenumber of payment periods per year.
7/28/2019 CE533 Chp4 PW Analysis
28/68
28 / 68CE533 - PW Analysis
4.2 Bonds Notation and Example
(Bond face value)(bond coupon rate) V.b
I = ------------------------------------------ = ----
number of payments per year c
At the time of purchase, the bond may sell formore or less than face value.
Example: V = $5,000 (face value) b = 4.5% per year paid semiannually
c = 10 years
7/28/2019 CE533 Chp4 PW Analysis
29/68
29 / 68CE533 - PW Analysis
4.2 PW Bonds Example Continued
The interest the firm would pay to thecurrent bondholder is calculated as:
0.045$5,000( ) $5,000(0.0225)2
$112.50 every 6 months
I
I
The bondholder, buys the bond and will receive$112.50 every 6 months for the life of the bond
7/28/2019 CE533 Chp4 PW Analysis
30/68
30 / 68CE533 - PW Analysis
4.2 Example 4.2
Aye has some extra money, requires safeinvestment. Her employer is offering toemployees a generous 5% discount for 10-year 5000 YTL bonds tat carry a coupon rate of
6% paid semiannually.The expectation is to match her return onother safe investments, which have averaged6.7% per year compounded semiannually.(This is an effective rate of 6.81% per year).
Should Aye buy the bond?
7/28/2019 CE533 Chp4 PW Analysis
31/68
31 / 68CE533 - PW Analysis
4.2 Example 4.2 Cash-Flow Diagram
A = 150
0 1 2 3 4 . .. 19 20
P=??
$5,000
i=3.35%
Find the PW(3.35%) of the future cashflows to the potential bond buyer
7/28/2019 CE533 Chp4 PW Analysis
32/68
32 / 68CE533 - PW Analysis
4.2 Example 4.2 Solving
I = (5000)(0.06)/2 = 150 YTL every 6months for a total of n=20 dividendpayments.The semiannual MARR is 6.7/2 =
3.35%, and the purchase price now is5000(0.95)= -4750 YTL.Using PW evaluation:PW = -4750 + 150(P/A, 3.35%, 20) +
5000(P/F, 3.35%, 20) = - 2.13 YTL
7/28/2019 CE533 Chp4 PW Analysis
33/68
33 / 68CE533 - PW Analysis
4.3 Present Worth Analysis of Different-LifeAlternatives
In an analysis one cannot effectivelycompare the PW of one alternative witha study period different from another
alternative that does not have the samestudy period.
This is a basic rule!
7/28/2019 CE533 Chp4 PW Analysis
34/68
34 / 68CE533 - PW Analysis
4.3 PRESENT WORTH: Unequal Lives
If the alternatives have different lifes,there are 2 ways to use PW analysis tocompare alternatives:
A) The lowest common Multiple (LCM)
B) Study period (planning horizon)
7/28/2019 CE533 Chp4 PW Analysis
35/68
35 / 68CE533 - PW Analysis
4.3 PRESENT WORTH: Lowest CommonMultiple (LCM) of Lives
If the alternatives have different studyperiods, you find the lowest commonlife for all of the alternatives in
question.Example: {3,4, and 6} years. Thelowest common life (LCM) is 12 years.
Evaluate all over 12 years for a PWanalysis.
7/28/2019 CE533 Chp4 PW Analysis
36/68
36 / 68CE533 - PW Analysis
4.3 PRESENT WORTH: Example UnequalLives
EXAMPLE
Machine A Machine B
First Cost $11,000 $18,000
Annual Operating Cost 3,500 3,100Salvage Value 1,000 2,000
Life 6 years 9 years
i = 15% per year
Note: Where costs dominate a problem it is customary to assign apositive value to cost and negative to inflows
7/28/2019 CE533 Chp4 PW Analysis
37/68
37 / 68CE533 - PW Analysis
4.3 PRESENT WORTH: Example UnequalLives
A common mistake is tocompute the present
worth of the 6-yearproject and compare it tothe present worth of the
9-year project.NO! NO! NO!
7/28/2019 CE533 Chp4 PW Analysis
38/68
38 / 68CE533 - PW Analysis
4.3 PRESENT WORTH: Unequal Lives
i = 15% per year
0 1 2 3 4 5 6
$11,000
F6=$1,000
A1-6
=$3,500
Machine A
0 1 2 3 4 5 6 7 8 9
F6=$2,000
A 1-9
=$3,100
$18,000
Machine B
LCM(6,9) = 18 year study period will apply for present worth
7/28/2019 CE533 Chp4 PW Analysis
39/68
39 / 68CE533 - PW Analysis
4.3 Unequal Lives: 2 Alternatives
i = 15% per year
Machine A
LCM(6,9) = 18 year study period will apply for present worth
Cycle 1 for A Cycle 2 for A Cycle 3 for A
6 years 6 years 6 years
Cycle 1 for B Cycle 2 for B
18 years
9 years 9 yearsMachine B
7/28/2019 CE533 Chp4 PW Analysis
40/68
40 / 68CE533 - PW Analysis
4.3 Example: Unequal Lives Solving
LCM = 18 years
Calculate the present worth of a 6-year cyclefor A
PA = 11,000 + 3,500 (P|A, .15, 6)
1,000 (P|F, .15, 6)
= 11,000 + 3,500 (3.7845) 1,000 (.4323)
= $23,813, which occurs at time 0, 6 and 12
7/28/2019 CE533 Chp4 PW Analysis
41/68
41 / 68CE533 - PW Analysis
4.3 Example: Unequal Lives
PA= 23,813+23,813 (P|F, .15, 6)+
23,813 (P|F, .15, 12)= 23,813 + 10,294 + 4,451 = 38,558
0 6 12 18
$23,813 $23,813 $23,813
Machine A
7/28/2019 CE533 Chp4 PW Analysis
42/68
42 / 68CE533 - PW Analysis
4.3 Unequal Lives Example: Machine B
Calculate the Present Worth of a 9-yearcycle for B
0 1 2 3 4 5 6 7 8 9
F6=$2,000
A 1-9
=$3,100
$18,000
7/28/2019 CE533 Chp4 PW Analysis
43/68
43 / 68CE533 - PW Analysis
4.3 9-Year Cycle for B
Calculate the Present Worth of a 9-year cyclefor B
PB = 18,000+3,100(P|A, .15, 9)
1,000(P|F, .15, 9)= 18,000 + 3,100(4.7716) - 1,000(.2843)
= $32,508 which occurs at time 0 and 9
7/28/2019 CE533 Chp4 PW Analysis
44/68
44 / 68CE533 - PW Analysis
4.3 AlternativeB 2 Cycles
PB = 32,508 + 32,508 (P|F, .15, 9)
= 32,508 + 32,508(.2843)
PB = $41,750
Choose Machine A
0 9 18
$32,508 $32,508
Machine A: PW =$38,558
7/28/2019 CE533 Chp4 PW Analysis
45/68
45 / 68CE533 - PW Analysis
4.3 Unequal Lives Assumed StudyPeriod
Study Period Approach
Assume alternative: 1 with a 5-year life
Alternative: 2 with a 7-year life
Alt-1: N = 5 yrs
Alt-2: N= 7 yrs
LCM = 35 yrs
Could assume a study period of, say, 5 years.
7/28/2019 CE533 Chp4 PW Analysis
46/68
46 / 68CE533 - PW Analysis
4.3 Unequal Lives Assumed StudyPeriod
Assume a 5-yr. Study period
Estimate a salvage value for the 7-yearproject at the end of t = 5
Truncate the 7-yr project to 5 years
Alt-1: N = 5 yrs
Alt-2: N= 7 yrs
Now, evaluate bothover 5 years using
the PW method!
7/28/2019 CE533 Chp4 PW Analysis
47/68
47 / 68CE533 - PW Analysis
FUTURE WORTH APPROACH
FW(i%) is an extension of the presentworth method
Compound all cash flows forward in
time to some specified time periodusing (F/P), (F/A), factors or,
Given P, the F = P(1+i)N
7/28/2019 CE533 Chp4 PW Analysis
48/68
48 / 68CE533 - PW Analysis
Applications of Future Worth
Projects that do not come on line untilthe end of the investment period
Commercial Buildings
Marine Vessels Power Generation Facilities
Public Works Projects
Key long time periods involving
construction activities
7/28/2019 CE533 Chp4 PW Analysis
49/68
49 / 68CE533 - PW Analysis
Life Cycle Costs (LCC)
Extension of the Present Worth method
Used for projects over their entire lifespan where cost estimates are
employedUsed for:
Buildings (new construction or purchase)
New Product Lines
Commercial aircraft
New automobile models
Defense systems
7/28/2019 CE533 Chp4 PW Analysis
50/68
50 / 68CE533 - PW Analysis
Life Cycle: Two General Phases
TIME
Cost-$
Acquisition Phase Operation Phase
Cumulative Life CycleCosts
7/28/2019 CE533 Chp4 PW Analysis
51/68
51 / 68CE533 - PW Analysis
4.4 CAPITALIZED COST ANALYSIS
CAPITALIZED COST- the present worthof a project that lasts forever.
Government Projects
Roads, Dams, Bridges (projects thatpossess perpetual life)
Infinite analysis period
7/28/2019 CE533 Chp4 PW Analysis
52/68
52 / 68CE533 - PW Analysis
4.4 Derivation for Capitalized Cost
Start with the closed form for the P/A factor
Next, let N approach infinity and divide thenumerator and denominator by (1+i)N
(1 ) 1
(1 )
N
N
iP A
i i
7/28/2019 CE533 Chp4 PW Analysis
53/68
53 / 68CE533 - PW Analysis
4.4 Derivation - Continued
Dividing by (1+i)N yields
Now, let n approach infinity and the
right hand side reduces to.
11
(1 )NiP A
i
7/28/2019 CE533 Chp4 PW Analysis
54/68
54 / 68CE533 - PW Analysis
4.4 Derivation - Continued
1 AP A
i i
Or,
CC(i%) = A/i
7/28/2019 CE533 Chp4 PW Analysis
55/68
55 / 68CE533 - PW Analysis
4.4 CAPITALIZED COST
Assume you are called on to maintain acemetery site forever if the interest rate= 4% and $50/year is required to
maintain the site.
Find the PW of an infinite annuity flow
1 2 3 4 5 .. N=inf.
A=$50/yr
P = ?
..
7/28/2019 CE533 Chp4 PW Analysis
56/68
56 / 68CE533 - PW Analysis
4.4 CAPITALIZED COST
P0 = $50[1/0.04]
P0 = $50[25] = $1,250.00
Invest $1,250 into an account thatearns 4% per year will yield $50 of
interest forever if the fund is not
touched and the i-rate stays constant.
7/28/2019 CE533 Chp4 PW Analysis
57/68
57 / 68CE533 - PW Analysis
4.4 CAPITALIZED COST: Endowments
Assume a wealthy donor wants to endow a
chair in an engineering department.
The fund should supply the department with
$200,000 per year for a deserving faculty
member.
How much will the donor have to come up
with to fund this chair if the interest rate =
8%/yr.
7/28/2019 CE533 Chp4 PW Analysis
58/68
58 / 68CE533 - PW Analysis
4.4 CAPITALIZED COST: Endowed Chair
The department needs $200,000 per year.
P = $200,000/0.08 = $2,500,000
If $2,500,000 is invested at 8% then theinterest per year = $200,000
The $200,000 is transferred to the department,but the principal sum stays in the investment tocontinue to generate the required $200,000
7/28/2019 CE533 Chp4 PW Analysis
59/68
59 / 68CE533 - PW Analysis
EXAMPLE
Calculate the Capitalized Cost of aproject that has an initial cost of
$150,000. The annual operating cost is$8,000 for the first 4 years and $5000thereafter. There is an recurring$15,000 maintenance cost each 15
years. Interest is 15% per year.
4.4 Capitalized Cost Example
4 4 C h Fl Di
7/28/2019 CE533 Chp4 PW Analysis
60/68
60 / 68CE533 - PW Analysis
$4,000
0 1 2 3 4 5 6 7 15 30
$150,000
$8,000
$15,000 $15,000 $15,000 $15,000
i=15%/YR
N=
How much $$ at t = 0 is required to fund thisproject?
The capitalized cost is the total amount of $ at t
= 0, when invested at the interest rate, willprovide annual interest that covers the futureneeds of the project.
4.4 Cash Flow Diagram
7/28/2019 CE533 Chp4 PW Analysis
61/68
61 / 68CE533 - PW Analysis
4.4 CAPITALIZED COST - ExampleContinued
1. Consider $4,000 of the $8,000 costfor the first four years to be a one-timecost, leaving a $4,000 annual operating
cost forever.P0= 150,000 + 4,000 (P|A, .15, 4) =
$161,420
2.855
7/28/2019 CE533 Chp4 PW Analysis
62/68
62 / 68CE533 - PW Analysis
4.4 CAPITALIZED COST - Continued
Recurring annual cost is $4,000 plus theequivalent annual of the 15,000 end-of-cycle cost.
.0 15 30 45 60 ..
Take any 15-year period and find the equivalentannuity for that period using the F/A factor.
7/28/2019 CE533 Chp4 PW Analysis
63/68
63 / 68CE533 - PW Analysis
4.4 CAPITALIZED COST: One Cycle
Take any 15-year period and find the equivalentannuity for that period using the F/A factor
$15,000
A for a 15-year period
0 15 30 45 60 ...
7/28/2019 CE533 Chp4 PW Analysis
64/68
64 / 68
CE533 - PW Analysis
4.4 CAPITALIZED COST
2. Recurring annual cost is $4,000 plus
the equivalent annual of the 15,000
end-of-cycle cost.
A= 4,000 + 15,000 (A|F, .15, 15)
= 4,000 + 15000 (.0210) = $5,315
Recurring costs = $5,315/i =
5,315/0.15 =$3,443/yr
7/28/2019 CE533 Chp4 PW Analysis
65/68
65 / 68
CE533 - PW Analysis
4.4 CAPITALIZED COST
Capitalized Cost = 161,420 + 5315/.15
= $196,853
Thus, if one invests $196,853 at time t
= 0, then the interest at 15% willsupply the end-of-year cash flow tofund the project so long as the principalsum is not reduced or the interest rate
changes (drops).
7/28/2019 CE533 Chp4 PW Analysis
66/68
66 / 68
CE533 - PW Analysis
4.6 USING EXCEL FOR PW ANALYSIS
General format to determine the PW is;
PW = P PV (i%,n,A,F)
When different-life alternatives areevaluated using LCM; develop NPV function
PW = P +
NPV(i%,year_1_CF_cell:last_year_CF_cell)
7/28/2019 CE533 Chp4 PW Analysis
67/68
67 / 68
CE533 - PW Analysis
Summary: Present Worth
PW represents a family of methods
Annual worth
Future Worth Capitalized Cost
Life-cycle cost analysis application
Bond Problems application
7/28/2019 CE533 Chp4 PW Analysis
68/68
End of Chapter 4