Upload
dhiraj-sheti
View
229
Download
0
Embed Size (px)
Citation preview
8/2/2019 CDS Northern Corridor Fact Sheet
1/4
East Africa Corridor Diagnostic StudyNorthern and Central Corridors
NORTHERN CORRIDOR
EXISTING INFRASTRUCTURE
Te Northern Corridor connects the
Port o Mombasa to markets in Kenya,
Uganda, Rwanda and Burundi as well as
southern Sudan, parts o eastern Demo-
cratic Republic o Congo (DRC), and
parts o northern anzania. It also links
the East Arican Community (EAC) tostates on its periphery: South Sudan,
DRC and Ethiopia. It is strategic be-
cause o the importance o the Port o
Mombasa to the region.
Mombasa Port
As a multipurpose port, Mombasa handles container-
ized cargo, general cargo, dry bulk, and liquid bulk. In
2009 the total throughput o the port was 19.1 million
tons; ollowing an average annual growth rate o 8.8 percentrom 2002 to 2009. Te predominant trac is imports, which
represent 86.6 percent o total trac. For imports, 38.9 percent
is liquid bulk, 28.1 percent is dry bulk, 24.7 percent is contain-
erized cargo, and only 8.2 percent is general cargo. In 2009,
transit trac was around 5 million tons, o which 80 percent
was or Uganda.
Road System
Te trunk road network o the Northern Corridor main axis
that stretches rom Mombasa to Bujumbura via Malaba is
1,970 km and to Goma is 1,846 km.
Rail System
Te Northern Corridor rail system operates within Kenya and
Uganda as a narrow gauge (1,000 mm) system, compatible
with the anzania Railway Limited (RL) system on the
Central Corridor in anzania. Te line extends rom the port
o Mombasa to Nairobi, and urther to Malaba, connecting to
the Ugandan rail system serving Kampala and on to Kasese close
to the DRC border. Tere are several spurs, the most important
being the line to Kisumu on Lake Victoria, and the spur to
Magadi Soda south o Nairobi. Te rail link to anzania is
closed, because o low trac demand.
Border Crossings
Border crossings in the region are characterized by poor inra-
structure, inadequate coordination and congestion. Te busiest
and most congested border on the route is at Malaba between
Kenya and Uganda. One stop border post (OSBP) operations
are being introduced on all the Northern Corridor borders
with support rom the World Bank and Arican Development
Bank as part o the East Arica rade and ransport Facilitation
Project. Te regional OSBP legal ramework being developed
by the East Arica Community with support rom the Japanese
International Cooperation Agency (JICA) provides the legal
jurisdiction and structure, operating principles and methods o
coordination.
Cargo clearance can be done at the border, but in most cases is
done at inland clearance centers (ICDs), most in capital cities.
Where clearances are done at the ICDs, the border clearance
is generally done in a ew hours. Nevertheless, the clearance
process is not complete and the 1-3 day nal clearance at inland
centers is part o the overall process. Most o the trucks operat-
ing on the route are Kenyan-owned since it is easier or them to
arrange cargo rom the port and then seek return hauls in the
other countries. Nevertheless, the cargo is signicantly imbal-
anced in avor o imports and many return hauls are empty.
Freight orwarders are represented by national and regional as-sociations. Tese associations will be important co-drivers or
more eective transport acilitation measures on the Corridor.
8/2/2019 CDS Northern Corridor Fact Sheet
2/4
CURRENT PERFORMANCE
Te CDS analyzed the price, time and reliability o each o
the destinations rom the port o Mombasa or imports o
dierent handling types o cargo served by road. wo trans-
port alternatives were considered or the segments between
Mombasa and Nairobi, one via road and one via rail. Figure
1 shows that the rail alternative is less expensive and aster
than the road alternative. Tis is mostly due to how the
customs clearance at the port is handled. Te containers thatare transported by rail are identied when ofoaded rom the
ship and immediately transported to the rail yard or loading
into a train with the maniest. Customs is cleared at the ICD
in Nairobi given that the Kenya Revenue Authority (KRA)
allows direct bill o lading to the ICD.
In terms o total cost (including reight orwarding and extra
inventory costs) the rail connection to Nairobi is 19 percent lower
than road. In terms o time rail is 20 percent quicker that road.
Te combination o port and ICD costs account or 50 percent in
the road option and 34 percent in the rail option; the remaining
costs o both alternatives are related entirely to the surace trans-port cost. ime at the port and ICD or containers transported by
road is 97 percent o the total time, while via rail is 69 percent.
Tere are also two transport alternatives between Mombasa and
Kampala, one via road and one via rail. Te rail connection is
slightly less expensive considering the higher extra inventory
cost associated with the unreliability o rail service. In terms o
time, the rail alternative takes 43 percent longer than road.
In terms o distribution o cost and time, the ports share o
the total cost is reduced compared to that shown or Nairobi.
Te port now represents 14 percent o the cost or the road
connection and 14 percent or rail. With respect to time, theport represents 67 percent and the Malaba border post 8 percent
or the road connection while the port represents 47 percent or
the rail connection. Tis is due to the increased cost and time
taken up by the longer land transport component to Kampala.
Figure 2 presents the results or destinations served only by road.
When looking at the total cost, the most expensive destination is
Nimule due to higher rates to account or security risks betweenNimule and southern Sudan. Another expensive destination is
Bujumburawhere trucks are required to wait or up to a week
while the cargo is cleared. For the MombasaKigali pair, the port
only represents 8 percent o the transport cost while still taking
up most o the time with a 58 percent share. Tis cost distribu-
tion is very similar or Bujumbura, Nimule, and Kasindi. In
terms o time, the port share decreases in cases where the border
and inland clearance takes longer. Tus the port share o total
transport time to Bujumbura is 53 percent and to Nimule is
57 percent. Te delays also have signicant cost implications
because the trucks are required to remain loaded while theclearance is completed. On the graph, border represents both
the time spent at the border and at the inland clearance oce.
Kampala (Road)Nairobi (Rail) Kampala (Rail)Nairobi (Road)
ICD27%100%
RoadBorder
8%
100%
Rail31%100% 100%
ICD27%100%
RoadBorder
8%
100%
Rail31%100% 100%
ICD27%100%
RoadBorder
8%
100%
Rail31%100% 100%
ICD27%ICD42%80%
100%
Road25%
Border8%
80%
100%
Rail31%80%
100%
Rail53%80%
100%
ICD27%ICD42%80%
100%
Road25%
Border8%
80%
100%
Rail66%Rail31%
80%
100%
Rail53%80%
100%
RoadRoad3%
ICD27%ICD42%
60%
80%
100%
Road86%
Road25%
Border8%
60%
80%
100%
Rail66%Rail31%
60%
80%
100%
Rail86%Rail53%
60%
80%
100%
Road50%
Road3%
ICD27%ICD42%
40%
60%
80%
100%
Road86%
Road25%
Border8%
60%
80%
100%
Rail66%Rail31%
60%
80%
100%
Rail86%Rail53%
60%
80%
100%
Road50%
Road3%
ICD27%ICD42%
40%
60%
80%
100%
Road86%
Road25%
Border8%
60%
80%
100%
Rail66%Rail31%
60%
80%
100%
Rail86%Rail53%
60%
80%
100%
Port
Road50%
Road3%
ICD27%ICD42%
40%
60%
80%
100%
Port67%
Road86%
Road25%
Border8%
40%
60%
80%
100%
Port
Rail66%Rail31%
40%
60%
80%
100%
Rail86%Rail53%
40%
60%
80%
100%
Port55%
Road50%
Road3%
ICD27%ICD42%
40%
60%
80%
100%
Port67%
Road86%
Road25%
Border8%
40%
60%
80%
100%
Port69%
Rail66%Rail31%
40%
60%
80%
100%
Port
Rail86%Rail53%
40%
60%
80%
100%
PortPort55%
Road50%
Road3%
ICD27%ICD42%
20%
40%
60%
80%
100%
Port67%
Road86%
Road25%
Border8%
20%
40%
60%
80%
100%
PortPort69%
Rail66%Rail31%
20%
40%
60%
80%
100%
Port47%
Rail86%Rail53%
20%
40%
60%
80%
100%
Port23%
Port55%
Road50%
Road3%
ICD27%ICD42%
20%
40%
60%
80%
100%
Port14%
Port67%
Road86%
Road25%
Border8%
20%
40%
60%
80%
100%
Port34%
Port69%
Rail66%Rail31%
20%
40%
60%
80%
100%
Port14%
Port47%
Rail86%Rail53%
20%
40%
60%
80%
100%
Port23%
Port55%
Road50%
Road3%
ICD27%ICD42%
0%
20%
40%
60%
80%
100%
Port14%
Port67%
Road86%
Road25%
Border8%
0%
20%
40%
60%
80%
100%
Port34%
Port69%
Rail66%Rail31%
0%
20%
40%
60%
80%
100%
Port14%
Port47%
Rail86%Rail53%
0%
20%
40%
60%
80%
100%
Port23%
Port55%
Road50%
Road3%
ICD27%ICD42%
0%
20%
40%
60%
80%
100%
CostUSD/ TEU T imeHrs.Port14%
Port67%
Road86%
Road25%
Border8%
0%
20%
40%
60%
80%
100%
CostUSD/TEU TimeHrs.
Port34%
Port69%
Rail66%Rail31%
0%
20%
40%
60%
80%
100%
CostUSD/ TEU T im eHrs.Port14%
Port47%
Rail86%Rail53%
0%
20%
40%
60%
80%
100%
CostUSD/ TEU Ti meHrs.
Port23%
Port55%
Road50%
Road3%
ICD27%ICD42%
0%
20%
40%
60%
80%
100%
CostUSD/ TEU T imeHrs.Port14%
Port67%
Road86%
Road25%
Border8%
0%
20%
40%
60%
80%
100%
CostUS D/TEU TimeHrs.
Port34%
Port69%
Rail66%Rail31%
0%
20%
40%
60%
80%
100%
CostU SD/T EU T im eHrs.Port14%
Port47%
Rail86%Rail53%
0%
20%
40%
60%
80%
100%
CostUSD/ TEU Ti meHrs.
Port23%
Port55%
Road50%
Road3%
ICD27%ICD42%
0%
20%
40%
60%
80%
100%
CostUSD/ TEU T imeHrs.Port14%
Port67%
Road86%
Road25%
Border8%
0%
20%
40%
60%
80%
100%
CostUS D/TEU TimeHrs.
Port34%
Port69%
Rail66%Rail31%
0%
20%
40%
60%
80%
100%
CostU SD/T EU T im eHrs.Port14%
Port47%
Rail86%Rail53%
0%
20%
40%
60%
80%
100%
CostUSD/ TEU Ti meHrs.Elements
Cost TimeElements
Cost TimeElements
Cost TimeElements
Cost Time
USD/TEU Hrs. USD/TL Hrs. USD/TEU Hrs. USD/TL Hrs.
Port 315 217 Port 315 217 Port 297 217 Port 297 217
Road 701 11 Road - - Road 1,801 80 Road - -
Border - - Border - - Border - 26 Border - 2
Rail - - Rail 620 99 Rail - - Rail 1,762 243,
ICD Lake - - Lake - - Lake - -- - - - - -
Transport 1,396 396 Transport 935 316 Transport 2,098 323 Transport 2,059 462
Freight Fwd. Fee 300 - Freight Fwd. Fee 300 - Freight Fwd. Fee 300 - Freight Fwd. Fee 300 -
Extra Inventory 619 - Extra Inventory 632 - Extra Inventory 621 - Extra Inventory 632 -
Total Total Total Total, , , ,
Source: Nathan Associates Inc.
FIGURE 1. Cost and Time for Destinations Served by Road and Rail Transport, 2010
(imports of light containers)
8/2/2019 CDS Northern Corridor Fact Sheet
3/4
CAUSES OF INEFFICIENCY
Te perormance o the Northern Corridor is aected by numer-
ous operational, policy, procedural, and administrative issues.
Ship waiting in Mombasa is oten three to our days. Crane
productivity at the specialized terminal is about 10 moves/
crane-hour, with berth productivity o 15 moves/berth-hour.
Berth productivity at the conventional terminal is not much
dierent than that at the specialized terminal, at 1314 moves/
berth-hour. Te reasons or the low productivity indicated by
Mombasa lines are yard congestion, trac jam inside the termi-
nal, equipment breakdown, shortage o equipment, lack o mod-
ern erminal Operating System (OS) and labor motivation.
In Kenya, vehicles licensed or transit cannot carry domestic
cargo and must use prescribed transit routes. Tis has the eect
o many return trips being empty. Similarly in anzania, the
Revenue Authority licenses trucks or transit or domestic with
the same eect.
Domestic road transport policies in all EAC states are aimed
at deregulating market access, which has had some positiveeects, but the lack o qualitative regulation has also had
several undesirable consequences. Tese include low entry
barriers leading to cutthroat competition, low saety levels
and poor service quality.
Existing overloading control strategy is aimed at achieving 100
percent inspection o all commercial vehicles. Te high intensity
o checking increases journey times and provides an added in-
centive or corruption. Dierences in national limits complicate
cross-border operations. Tere is also no regional consistency
in terms o the requency o checks as some states (Burundi,
Rwanda) have no existing weighbridge inrastructure.
Te Northern Corridor suers rom serious delays caused by
inormal stops and check points on the route. Some are ocially
sanctioned and some are created to collect payments or police,
transit authorities and local communities. Without sucient
law enorcement vehicles, stationary control points are essential
to check or driving licenses, vehicle registration, vehicle roadworthiness certicates, and to inspect vehicles or contraband
and tracking. Nevertheless, unocial stops delay transit trans-
port and add cost to transport which is passed on to the shipper.
In other cases, they are payments to avoid regulatory control,
such as payments to avoid overloading regulation.
Insucient use is made o customs tools to expedite processing.
Clearance modernization is being implemented at the national
level and the extent o implementation is varied. ools include
risk management, authorized economic operators, customs
bonds and control points and preclearance.
Failure to implement an eective transit regime impedes transit
movement in terms o cost, time and reliability. Many aspects
o a transit regime exist, but have not been ully implemented.
Common vehicle regulations have been issued, but also not ully
implemented and there are current eorts to change again. Road
worthiness standards have been promoted, but there is lack o
trust in the systems o other EAC partner states. Customs dec-
laration have been simplied and harmonized, but each country
still requires its own orm under national insignia.
FIGURE 2. Cost and Time for Destinations Served Only by Road Transport, Imports, 2010 (imports of light containers)
Kigali (Road) Nimule (Road) Kasindi (Road)Bujumbura (Road)
Border14%
80%
100%
Border19%
80%
100%
Border13%
100% Border10%
100%Border
14%
80%
100%
Border19%
80%
100%
Border13%
100% Border10%
100%Border
14%
80%
100%
Border19%
80%
100%
Border13%
100% Border10%
100%Border
14%
80%
100%
Border19%
80%
100%
Border13%
100% Border10%
100%
Road
Border14%
80%
100%
Border19%
80%
100%
Road
Border13%
80%
100%
Road
Border10%
80%
100%
Road28%
Border14%
80%
100%
Road28%
Border19%
80%
100%
Road30%
Border13%
80%
100%
Road32%
Border10%
80%
100%
RoadRoad28%
Border14%
60%
80%
100%
RoadRoad28%
Border19%
60%
80%
100%
Road
Road30%
Border13%
60%
80%
100%
Road
Road32%
Border10%
60%
80%
100%
Road92%
Road28%
Border14%
40%
60%
80%
100%
Road94%
Road28%
Border19%
40%
60%
80%
100%
Road94%
Road30%
Border13%
60%
80%
100%
Road94%
Road32%
Border10%
60%
80%
100%
Road92%
Road28%
Border14%
40%
60%
80%
100%
Road94%
Road28%
Border19%
40%
60%
80%
100%
Road94%
Road30%
Border13%
60%
80%
100%
Road94%
Road32%
Border10%
60%
80%
100%
Port
Road92%
Road28%
Border14%
40%
60%
80%
100%
Road94%
Road28%
Border19%
40%
60%
80%
100%
Road94%
Road30%
Border13%
40%
60%
80%
100%
Road94%
Road32%
Border10%
40%
60%
80%
100%
Port58%
Road92%
Road28%
Border14%
40%
60%
80%
100%
Port53%
Road94%
Road28%
Border19%
40%
60%
80%
100%
Port57%
Road94%
Road30%
Border13%
40%
60%
80%
100%
Port58%
Road94%
Road32%
Border10%
40%
60%
80%
100%
Port58%
Road92%
Road28%
Border14%
20%
40%
60%
80%
100%
Port53%
Road94%
Road28%
Border19%
20%
40%
60%
80%
100%
Port57%
Road94%
Road30%
Border13%
20%
40%
60%
80%
100%
Port58%
Road94%
Road32%
Border10%
20%
40%
60%
80%
100%
Port8%
Port58%
Road92%
Road28%
Border14%
20%
40%
60%
80%
100%
Port 6%
Port53%
Road94%
Road28%
Border19%
20%
40%
60%
80%
100%
Port57%
Road94%
Road30%
Border13%
20%
40%
60%
80%
100%
Port58%
Road94%
Road32%
Border10%
20%
40%
60%
80%
100%
Port8%
Port58%
Road92%
Road28%
Border14%
0%
20%
40%
60%
80%
100%
Port6%
Port53%
Road94%
Road28%
Border19%
0%
20%
40%
60%
80%
100%
Port6%
Port57%
Road94%
Road30%
Border13%
0%
20%
40%
60%
80%
100%
Port6%
Port58%
Road94%
Road32%
Border10%
0%
20%
40%
60%
80%
100%
Port8%
Port58%
Road92%
Road28%
Border14%
0%
20%
40%
60%
80%
100%
CostU SD/T EU Ti meHrs.Port6%
Port53%
Road94%
Road28%
Border19%
0%
20%
40%
60%
80%
100%
CostUSD/ TEU T imeHrs.Port6%
Port57%
Road94%
Road30%
Border13%
0%
20%
40%
60%
80%
100%
CostUSD/ TEU T imeHrs.Port6%
Port58%
Road94%
Road32%
Border10%
0%
20%
40%
60%
80%
100%
CostUSD/TE U TimeHrs.Port8%
Port58%
Road92%
Road28%
Border14%
0%
20%
40%
60%
80%
100%
CostU SD/T EU Ti meHrs.Port6%
Port53%
Road94%
Road28%
Border19%
0%
20%
40%
60%
80%
100%
CostUSD/ TEU T imeHrs.Port6%
Port57%
Road94%
Road30%
Border13%
0%
20%
40%
60%
80%
100%
CostUSD/T EU Ti meHrs.Port6%
Port58%
Road94%
Road32%
Border10%
0%
20%
40%
60%
80%
100%
CostUSD/TE U TimeHrs.Port8%
Port58%
Road92%
Road28%
Border14%
0%
20%
40%
60%
80%
100%
CostU SD/T EU Ti meHrs.Port6%
Port53%
Road94%
Road28%
Border19%
0%
20%
40%
60%
80%
100%
CostUSD/ TEU T imeHrs.Port6%
Port57%
Road94%
Road30%
Border13%
0%
20%
40%
60%
80%
100%
CostUSD/T EU Ti meHrs.Port6%
Port58%
Road94%
Road32%
Border10%
0%
20%
40%
60%
80%
100%
CostUSD/TE U TimeHrs.Elements
Cost meElements
Cost meElements
Cost meElements
Cost me
USD/TEU Hrs. USD/TEU Hrs. USD/TEU Hrs. USD/TEU Hrs.
Port 297 217 Port 297 217 Port 297 217 Port 297 217
Road 3,604 105 Road 4,653 114 Road 5,087 114 Road 4,522 119
Border - 54 Border - 80 Border - 50 Border 5 36
Rail - - Rail - - Rail - - Rail - -- - - - - - - -
- - - - - - - -- - - - - - - -
Transport 3,901 376 Transport 4,950 411 Transport 5,384 381 Transport 4,824 372
Freight Fwd. Fee 300 - Freight Fwd. Fee 300 - Freight Fwd. Fee 300 - Freight Fwd. Fee 300 -
Extra Inventory 622 - Extra Inventory 623 - Extra Inventory 623 - Extra Inventory 618 -
Total Total Total Total, , , ,
Source: Nathan Associates Inc.
8/2/2019 CDS Northern Corridor Fact Sheet
4/4www.t.
The easT africa corridor diagnosTic sTudy is a projecT of:
proposed projecTs
Improving the eciency and reliability o the Northern
Corridor will require the adoption and implementation o an
integrated Action Plan to simultaneously address inrastruc-
ture constraints and bottlenecks and operational ineciencies,
policies and procedures. Te CDS proposes projects that can
improve corridor perormance immediately or within the next
fve years.
Table 1. Proposed Northern Corridor
Infrastructure Projects
iMproVed perforMance
Implementation o the CDS proposed projects will have a sig-
nifcant impact on Northern Corridor perormance. Generally,
the price to serve Northern Corridor destinations by road could
decrease by 25 percent and those destinations served by rail by
11-14 percent. In terms o time, the destinations served by rail
could enjoy an average reduction o 53 percent in shipment
time, while destinations served by road could have a reduction
in time ranging rom 21-33 percent.
Te proposed road projects are concentrated on the Northern
Corridor (and not on its eeder roads) and are expected to
reduce signifcantly the price and time as well as the variation in
time (reliability). Te higher savings on road transport are due
to the implementation o projects that increase the road capacity
and rehabilitate the road surace. Tis reduces congestion and
vehicle operating costs.
Te proposed rail rehabilitation projects, as indicated by Rit
Valley Railways (RVR) representatives, are expected to mainly
have an impact on time and reliability. Te projects are ex-
pected to concentrate in reducing derailments (improve saety)
and improving reliability o locomotives. Te impact o port
improvements on road and rail alternatives is also important,although its impact is greater when considering the time due to
its larger share o it (with port accounting or about 70 percent
o the total time).
Te proposed port projects (integrated ICDs, new port termi-
nal, etc.) are expected to reduce the port costs by 24 percent and
more importantly reduce port time by 39 percent. Te proposed
projects have an even greater impact on reliability with gains in
reliability o more than 60 percent. Tis signifcant improve-
ment in the overall reliability o the road and rail transport is the
result o the reduction in variations o time caused by conges-
tion and potential accidents on the road and the improvemento rail operations and reductions in the number o derailments
and locomotive breakdowns.
Port ProjectsMombasa Short-term Container Handlin Ca acit 35.0
Mombasa New Container Terminal Ki evu West 342.5Mombasa New Petroleum Facilit 55.8Mombasa Dr Bulk and General Car o Facilities 1.7Lamu Corridor New Port and Associated Infrastructure 7.0
Subtotal 442.0
Rail ProjectsRVR Infrastructure U rade 1 - 3 ears 250.0
RVR Locomotive Rehabilitation -3 ears 20.0
RVR Infrastructure U rade 3 - 5 ears 150.0
RVR Mombasa Intermodal Yard and E ui ment 20.0RVR Kam ala ICD Develo ment 10.0Reconstruction of Tororo-Gulu- Pachwach Railwa 325.0
Subtotal 775.0
Road Pro ectsNorthern Corridor Capacity Upgrades 234.5Northern Corridor Road Rehabilitation 362.9Northern Corridor Upgrade to Paved 143.7
Subtotal 741.1
Total All Infrastructure Projects 1,958.1
Source: Prepared by Nathan Associates Inc.
NameCost
(US$ mil.)