THE WORLD BANK CARBON FINANCE UNIT CDM Programmes of Activities : OPPORTUNITIES TO IMPROVE IMPLEMENTATION PRESENTATION AT HCC MEETING, MAY 31, 2011 BY MONALI RANADE ([email protected] ) [WITH FELICITY SPORS AND KLAUS OPPERMANN]

CDM Programmes of Activities : Opportunities to improve implementation

  • Upload
    cybele

  • View
    36

  • Download
    0

Embed Size (px)

DESCRIPTION

CDM Programmes of Activities : Opportunities to improve implementation Presentation at HCC Meeting, May 31, 2011 by Monali Ranade ( [email protected] ) [With Felicity Spors and Klaus Oppermann ]. Current situation versus the vision?. Actual situation - PowerPoint PPT Presentation

Citation preview

Page 1: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

CDM Programmes of Activities : OPPORTUNITIES TO IMPROVE IMPLEMENTATION PRESENTATION AT HCC MEETING, MAY 31, 2011

BY MONALI RANADE ([email protected] )[WITH FELICITY SPORS AND KLAUS OPPERMANN]

Page 2: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

Current situation versus the vision?

PoA Vision:

a)Reduce transaction costs and facilitate dispersed projects. b)Small projects targeted particularly from under-represented or LDC countries to participate in CDMc)Scale-up and accelerate emission reduction activities

Actual situation

1. Limited private sector involvement in PoAs due to market and regulatory barriers.

2. Regulatory uncertainty (regulations, procedures, eligibility criteria, liability etc)

3. Complexity in applying methodologies and tools

4. PoA implementation largely with public finance and capacity building support.

Page 3: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

PoA potential – Regional distribution

Number Crunching

• 30% PoAs v/s 73% CDM projects in BIC (Brazil, India and China)

• 11% PoAs v/s 1.7% CDM projects in LDCs/SIDs

Source: UNEP Risoe CDM/JI Pipeline Analysis and Database, March 1st 2011

Page 4: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

PoA potential – supporting sustainable development by supporting small dispersed HH/SME projects

EE demand side 29

Waste 23

Solar 12

Hydro 5

EE supply side 4 Forestry & Agriculture 2 Fossil fuel switch 2 Biomass energy 2 Agriculture 1 CMM 1 Transport   1 Total PoAs   82

But PoAs have not yet achieved scale up of GHG mitigation in number of PoAs nor in size of PoAs.

Page 5: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

• 10 small scale– Household RE in Bangladesh (ASM I.A)

– Household EE in Senegal, Bangladesh (AMS II.C)

– Supply side EE in China, Yemen, India, (AMS II.A)

– Waste in Uganda, Phillipines, Thailand (AMS III.F & III.D)

– Transport in Egypt (AMS III.C)

• 4 large scale – LFG in Brazil, Phillipines, Morocco (ACM0001)

– Hydro in Vietnam (ACM0002)

• CME categories– Financial Institutions (e.g., Bangladesh, Brazil, Phillipines)

– Government agencies (e.g., Uganda, Vietnam, Senegal)

– Power companies (China, India, Yemen)

World Banks PoA Portfolio 2 registered;12 Under validation

Page 6: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

• Additionality of PoA – Justifying programs supported by public funds

– Assessing PoAs that support mandatory laws

• Defining eligibility criteria for additionality of CPA– DOEs requiring very precise criteria

– Too many criteria so restrictive that only 1st CPA may be eligible

• Setting baseline and monitoring– Survey methods

– Sample size

• Monitoring systems– Building appropriate monitoring structure and database without

over-burdening the CME and at a rational cost

– Yet unknown verification challenges

A few Challenges (among many others)

Page 7: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

• Structuring program– Upfront cost of structuring programs (seed funds)

– Building capacity of CME

– Designing programs to incorporate future sources of revenue

• Procedural issues– Start date of PoA and CPA (partly resolved by the 31 Dec 09 rule)

– Focal point designation in MOC (partly resolved)

– Other minor issues

• DOE Liability– Trustees‘ dilemma

– Buyers‘ dilemma

– CME financial capacity and credit-worthiness

A few Challenges (among many others)

Page 8: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

Challenges: Complex and varied business structures

Hands-off Hands-on

Whole-seller

PoA Coordinating entity is the CPA entity• controls all CPAs• finances all projects• prepares all CPA-DDs• covers all monitoring costsPoA retains 100% revenue

PoA Coordinating entity• can influence CPAs• finances some projectsCPA entity• leads preparation of CPA-DD• covers own monitoring costsPoA retains major part of revenue

PoA Coordinating entity• communicates with EB• Support CPA developmentCPA entity• finances project directly• leads preparation of CPA-DD • covers own monitoring costsPoA retains minor part of revenue

PoA Coordinating entity• supports identification of CPAs• part finances all projects• covers monitoring costsCPA entity• prepares own CPA-DD• covers own monitoring costsPoA shares revenue

Retailer

Page 9: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

“We can't solve problems by using the same kind of thinking we used when we created them." – Albert Einstein

• Based on experience it is possible to identify two kinds of PoAs in general: – PoA type A – individual units for each CPA (poss. different owners of

CPAs).

– PoA type B - small/micro activities or technologies e.g. lighting, cooking stoves often located in LDCs or countries with less than 10 CDM projects.

• Recommendation to increase scale up – Different procedures and regulations required to support PoA types A and B, critical for ensuring regional representation addressed, and SD projects scaled up to achieve potential GHG reductions.

Challenges are plenty – how to find a solution?

Page 10: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

Key barriers in existing rules

Page 11: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

Recommendations to address regulatory barriers facilitate larger CPAs

Page 12: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

Simplified additionality for micro RE projects

Page 13: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

Simplified additionality for micro EE projects

Page 14: CDM Programmes of Activities  :  Opportunities to improve implementation

THE WORLD BANK CARBON FINANCE UNIT

Simplified additionality for Type III projects

Page 15: CDM Programmes of Activities  :  Opportunities to improve implementation

In conclusion

General experience with CDM PoA?

•Programs are complex •CDM-specific regulatory complexities pose additional challenge

•Need highly capable coordinating agency

•Even the simplest POAs can be tough to monitor

• Each PoA is unique in its combination of national circumstances, technology, beneficiary and financing

However, rules are getting better defined and

knowledge is being generated through the experience of a wide-range of

PoA developers in different sectors and countries.