FOR THE
MONTGOMERY COUNTY, PENNSYLVANIA
STONY CREEK ELEMENTARY SCHOOLEXPANSION AND RENOVATIONS
BRESLIN RIDYARD FADERO ARCHITECTS
WISSAHICKON SCHOOL DISTRICT
LIST OF DRAWINGS
D-1 GENERAL CLASSROOMS
DECEMBER 02, 2019
DESIGN DEVELOPMENT
D-2 MUSIC CLASSROOMD-3 SPECIAL EDUCATION CLASSROOMSD-4 SMALL GROUP ROOMSD-5 LIBRARY / LEARNING SUPPORTD-6a MULTI PURPOSE ROOM - STAGE
1-24 PROPOSED LAND DEVELOPMENT DRAWINGSA-1 EXISTING SITE PLANA-2 PROPOSED SITE PLANA-3 EXISTING SITE PLANA-4 PROPOSED FLOOR PLANA-5 PROPOSED MEZZANINE / ROOF PLANA-6 EXTERIOR ELEVATIONSA-7 EXTERIOR ELEVATIONSA-8 PERSPECTIVEA-9 PERSPECTIVEA-10 SCHEDULED AREA DRAWING
S-1 STRUCTURAL FRAMING PLANMEP-1 MEP FLOOR PLAN
D-6b MULTI PURPOSE ROOM - CAFETERIAD-6c MULTI PURPOSE ROOM - GYMFS1 FOOD SERVICE LAYOUT
STONYCREEKELEMENTARY-DESIGNDEVELOPMENT
BRESLIN ARCHITECTS February 25, 2020 D�HUY Engineerng, Inc.
BRESLIN ARCHITECTS D�HUY Engineerng, Inc.
STONYCREEKELEMENTARY-DESIGNDEVELOPMENT
February 25, 2020
Increases the building capacity by 177 students • The student population has grown from 408 in 2013 to 555 in the current year. Our projections
show that the 177 additional capacity will be more than adequate for the Stony Creek area
Creates a new, larger, better core space • The new multipurpose cafeteria/kitchen, gym, large space for events is a significant improvement
over the current undersized core spaces. The space is designed to be better during the school day, after school and weekends
Creates new, specifically designed special education classrooms • When complete, the autistic support program at Shady Grove will move to Stony Creek. This will
increase student capacity at Shady Grove by 66 students. Shady Grove is also a growing school
Creates a safer isolated bus loop and much longer queuing for cars • The space available for lined up cars is significantly longer.
What does this addition/renovation project accomplish for Stony Creek and the District?
BRESLIN ARCHITECTS D�HUY Engineerng, Inc.
STONYCREEKELEMENTARY-DESIGNDEVELOPMENT
February 25, 2020
Paula Sasin, Gwen & Robin Breslin, Principal – Stony Creek Breslin Ridyard Fadero Architects Gary Abbamont, Arif Fazil, Assistant Superintendent D’Huy Engineering, Inc.
Jim Crisfield, Gerry Moore, Director of Superintendent Buildings & Grounds
Kelle Heim-McCloskey, Wade Coleman, Director of Student Services Business Administrator Jen Schmidt, John McGowan, Director of Teaching & Learning Director of Technology
Teachers from Stony Creek (for their specific instructional areas)
DESIGN TEAM
BRESLIN ARCHITECTS D�HUY Engineerng, Inc.
STONYCREEKELEMENTARY-DESIGNDEVELOPMENT
February 25, 2020
BRESLIN ARCHITECTS
STONYCREEKELEMENTARY-DESIGNDEVELOPMENT
D�HUY Engineerng, Inc. February 25, 2020
BRESLIN ARCHITECTS
STONYCREEKELEMENTARY-DESIGNDEVELOPMENT
D�HUY Engineerng, Inc. February 25, 2020
BRESLIN ARCHITECTS
STONYCREEKELEMENTARY-DESIGNDEVELOPMENT
D�HUY Engineerng, Inc. February 25, 2020
BRESLIN ARCHITECTSD�HUY Engineerng, Inc.
STONYCREEKELEMENTARY-DESIGNDEVELOPMENT
February 25, 2020
BRESLIN ARCHITECTS D�HUY Engineerng, Inc.
STONYCREEKELEMENTARY-DESIGNDEVELOPMENT
February 25, 2020
BRESLIN ARCHITECTS D�HUY Engineerng, Inc.
STONYCREEKELEMENTARY-DESIGNDEVELOPMENT
February 25, 2020
BRESLIN ARCHITECTS D�HUY Engineerng, Inc.
STONYCREEKELEMENTARY-DESIGNDEVELOPMENT
February 25, 2020
BRESLIN ARCHITECTS
WISSAHICKONSTONYCREEKPHASING
Existing Building
1 of 10
WISSAHICKONSTONYCREEKPHASING
BRESLIN ARCHITECTS
Updated Phasing Plan – Early Bid Package Summer 2020June 2020 – August 2020
• Relocate Modular Buildings
• Temporary Parking Areas
• Construct Soft and Hard Play Areas Including Stormwater Management
• Install Temporary Paved Walkway to New Play Areas
• Electrical Service Modifications
• Install Temporary Electric Generator with Connection to Existing Transfer Switch
• Install Drive with Paving to Binder Course
• Install Stone Staging Area and Stone Drive to Sub-Grade.
• District to Provide Temporary Walk-In Freezer
Staging Area
Temp Parking
Temp Parking
Soft Play Area
Hard Play Area
2 of 10
WISSAHICKONSTONYCREEKPHASING
BRESLIN ARCHITECTS
Updated Phasing Plan – Phase 1September 2020 – June 2021
• Mobilize on Site and Establish Staging Area
• Building Addition
• Install Temporary Water Service Serving Existing Building
• Install Temporary Gas Service Serving Existing Building
• Remove Existing Underground Oil Tank
• Remove Existing Electric Generator
• Remove Existing Electric Transformer
• Site Improvements East Side of Site (Partial Storm Water Structures and Piping, Future Water Main, Future Gas Main, …) Bus
Drop Off & Pick Up
Parent Drop Off & Pick Up
3 of 10
No Construction Deliveries: 8:00 – 8:45am and 3:00 – 3:45pm
BRESLIN ARCHITECTS
Updated Phasing Plan – Phase 2June 2021– August 2021
• Continue Building Addition
• Begin Interior M.E.P. Extensions From New Boiler Room
• Site Improvements East Side of Site
• Install Underground Basin, Storm Water Structures and Piping, Remove Storm Water Bypass System
• Install New Water Service From Street
• Install Sanitary Sewer Tie-In to New Addition
• Install New Interior Switch Gear and Connect New Electric Service to Existing Building
• Install New Emergency Generator
• Install Yost Road Access, Storm Water Improvements and 10’ Wide Stone Temporary Walkway September 2021
• Interior Renovations in Corridor Ceilings and North of Corridor to New Addition
• Remove Temporary Parking Lots
• Install New Parking Lot & Driveway Adjacent to New Gymnasium up to Binder Course
4 of 10
Reno
WISSAHICKONSTONYCREEKPHASING
Underground Basin
BRESLIN ARCHITECTS
Updated Phasing Plan – Phase 3September 2021– December 2021
• Continue Building Addition Owner to Occupy Addition December 2021
• Relocate Construction Fence
• Continue Interior M.E.P. Extensions From New Boiler Room
• Site Improvements East Side of Site
• Interior Renovations North of Corridor to New Addition Complete Prior to December 2021
Bus Drop Off & Pick Up
Parent Drop Off & Pick Up
Teacher Parking
5 of 10
WISSAHICKONSTONYCREEKPHASING
BRESLIN ARCHITECTS
Updated Phasing Plan – Phase 4December 2021 – January 2022
• Owner to Occupy New Addition December 2021
• Relocate Staging Area and Job Trailers
• Interior Renovations at Existing Gymnasium January 2022 to June 2022
• Site Improvements Southwest Side of Site
Reno
Existing Building
Bus Drop Off & Pick Up
Teacher Parking
Parent Drop Off & Pick Up
6 of 10
Staging Area
WISSAHICKONSTONYCREEKPHASING
BRESLIN ARCHITECTS
Updated Phasing Plan – Phase 5January 2022 – June 2022
• Interior Renovations at Existing Gymnasium January 2022 to June 2022
• Interior Renovations for New Gymnasium Restrooms
• Site Improvements Southwest Side of Site
• Install Stone Access for Multi Purpose Room Renovations
Reno
Existing Building
Bus Drop Off & Pick Up
Teacher Parking
Parent Drop Off & Pick Up
7 of 10
Staging Area
WISSAHICKONSTONYCREEKPHASING
Reno
BRESLIN ARCHITECTS
Updated Phasing Plan – Phase 6
Existing BuildingReno Reno
Parent Drop Off & Pick Up
Teacher Parking
June 2022 – August 2022
• Interior Renovations at Existing Multi Purpose Room to Library June 2022 to November 2022
• Site Improvements Southwest Side of Site
Bus Drop Off & Pick Up
8 of 10
Staging Area
Underground Basin
WISSAHICKONSTONYCREEKPHASING
BRESLIN ARCHITECTS
Updated Phasing Plan – Phase 7August 2022 - November 2022 Substantial Completion
• Complete Site Improvements Southwest Side of Site
• Interior Renovations at Existing Multi Purpose Room to Library June 2022 to November 2022
• Remove Modular Classrooms
• Restore Staging Area
• Final Paving and Line Striping
• Remove All Construction Equipment
• Remove E&S Controls
• Final Landscaping by October 2022Parent Drop Off & Pick Up
Teacher Parking
Bus Drop Off & Pick Up
9 of 10
Reno
Reno
WISSAHICKONSTONYCREEKPHASING
WISSAHICKONSTONYCREEKSCHEMATICDESIGN
BRESLIN ARCHITECTS
Updated Phasing Plan – CompletionNovember 2022 Final Completion
10 of 10
BRESLIN ARCHITECTS D�HUY Engineerng, Inc.
STONYCREEKELEMENTARY-DESIGNDEVELOPMENT
Milestones
Whitpain Township Land Development Approval Feb 2020
Award Bids - Phase 1 Sitework April 2020
Bids - Main Project June 2020 Phase 1 Sitework Timeline June 2020 - August 2020
Modular Relocation Timeline June 2020 - August 2020
Award Bids - Main Project July 2020 Occupy New Addition January 2022
Occupy Classroom Renovation Phase August 2022
Occupy Library Renovation Phase November 2022
February 25, 2020