FOR THE MONTGOMERY COUNTY, PENNSYLVANIA STONY CREEK ELEMENTARY SCHOOL EXPANSION AND RENOVATIONS BRESLIN RIDYARD FADERO ARCHITECTS WISSAHICKON SCHOOL DISTRICT LIST OF DRAWINGS D-1 GENERAL CLASSROOMS DECEMBER 02, 2019 DESIGN DEVELOPMENT D-2 MUSIC CLASSROOM D-3 SPECIAL EDUCATION CLASSROOMS D-4 SMALL GROUP ROOMS D-5 LIBRARY / LEARNING SUPPORT D-6a MULTI PURPOSE ROOM - STAGE 1-24 PROPOSED LAND DEVELOPMENT DRAWINGS A-1 EXISTING SITE PLAN A-2 PROPOSED SITE PLAN A-3 EXISTING SITE PLAN A-4 PROPOSED FLOOR PLAN A-5 PROPOSED MEZZANINE / ROOF PLAN A-6 EXTERIOR ELEVATIONS A-7 EXTERIOR ELEVATIONS A-8 PERSPECTIVE A-9 PERSPECTIVE A-10 SCHEDULED AREA DRAWING S-1 STRUCTURAL FRAMING PLAN MEP-1 MEP FLOOR PLAN D-6b MULTI PURPOSE ROOM - CAFETERIA D-6c MULTI PURPOSE ROOM - GYM FS1 FOOD SERVICE LAYOUT STONY CREEK ELEMENTARY - DESIGN DEVELOPMENT BRESLIN ARCHITECTS February 25, 2020 DHUY Engineerng, Inc.

CD StonyCreek Parents

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CD StonyCreek Parents

FOR THE

MONTGOMERY COUNTY, PENNSYLVANIA

STONY CREEK ELEMENTARY SCHOOLEXPANSION AND RENOVATIONS

BRESLIN RIDYARD FADERO ARCHITECTS

WISSAHICKON SCHOOL DISTRICT

LIST OF DRAWINGS

D-1 GENERAL CLASSROOMS

DECEMBER 02, 2019

DESIGN DEVELOPMENT

D-2 MUSIC CLASSROOMD-3 SPECIAL EDUCATION CLASSROOMSD-4 SMALL GROUP ROOMSD-5 LIBRARY / LEARNING SUPPORTD-6a MULTI PURPOSE ROOM - STAGE

1-24 PROPOSED LAND DEVELOPMENT DRAWINGSA-1 EXISTING SITE PLANA-2 PROPOSED SITE PLANA-3 EXISTING SITE PLANA-4 PROPOSED FLOOR PLANA-5 PROPOSED MEZZANINE / ROOF PLANA-6 EXTERIOR ELEVATIONSA-7 EXTERIOR ELEVATIONSA-8 PERSPECTIVEA-9 PERSPECTIVEA-10 SCHEDULED AREA DRAWING

S-1 STRUCTURAL FRAMING PLANMEP-1 MEP FLOOR PLAN

D-6b MULTI PURPOSE ROOM - CAFETERIAD-6c MULTI PURPOSE ROOM - GYMFS1 FOOD SERVICE LAYOUT

STONYCREEKELEMENTARY-DESIGNDEVELOPMENT

BRESLIN ARCHITECTS February 25, 2020 D�HUY Engineerng, Inc.

Page 2: CD StonyCreek Parents

BRESLIN ARCHITECTS D�HUY Engineerng, Inc.

STONYCREEKELEMENTARY-DESIGNDEVELOPMENT

February 25, 2020

Increases the building capacity by 177 students • The student population has grown from 408 in 2013 to 555 in the current year. Our projections

show that the 177 additional capacity will be more than adequate for the Stony Creek area

Creates a new, larger, better core space • The new multipurpose cafeteria/kitchen, gym, large space for events is a significant improvement

over the current undersized core spaces. The space is designed to be better during the school day, after school and weekends

Creates new, specifically designed special education classrooms • When complete, the autistic support program at Shady Grove will move to Stony Creek. This will

increase student capacity at Shady Grove by 66 students. Shady Grove is also a growing school

Creates a safer isolated bus loop and much longer queuing for cars • The space available for lined up cars is significantly longer.

What does this addition/renovation project accomplish for Stony Creek and the District?

Page 3: CD StonyCreek Parents

BRESLIN ARCHITECTS D�HUY Engineerng, Inc.

STONYCREEKELEMENTARY-DESIGNDEVELOPMENT

February 25, 2020

Paula Sasin, Gwen & Robin Breslin, Principal – Stony Creek Breslin Ridyard Fadero Architects Gary Abbamont, Arif Fazil, Assistant Superintendent D’Huy Engineering, Inc.

Jim Crisfield, Gerry Moore, Director of Superintendent Buildings & Grounds

Kelle Heim-McCloskey, Wade Coleman, Director of Student Services Business Administrator Jen Schmidt, John McGowan, Director of Teaching & Learning Director of Technology

Teachers from Stony Creek (for their specific instructional areas)

DESIGN TEAM

Page 4: CD StonyCreek Parents

BRESLIN ARCHITECTS D�HUY Engineerng, Inc.

STONYCREEKELEMENTARY-DESIGNDEVELOPMENT

February 25, 2020

Page 5: CD StonyCreek Parents

BRESLIN ARCHITECTS

STONYCREEKELEMENTARY-DESIGNDEVELOPMENT

D�HUY Engineerng, Inc. February 25, 2020

Page 6: CD StonyCreek Parents

BRESLIN ARCHITECTS

STONYCREEKELEMENTARY-DESIGNDEVELOPMENT

D�HUY Engineerng, Inc. February 25, 2020

Page 7: CD StonyCreek Parents

BRESLIN ARCHITECTS

STONYCREEKELEMENTARY-DESIGNDEVELOPMENT

D�HUY Engineerng, Inc. February 25, 2020

Page 8: CD StonyCreek Parents

BRESLIN ARCHITECTSD�HUY Engineerng, Inc.

STONYCREEKELEMENTARY-DESIGNDEVELOPMENT

February 25, 2020

Page 9: CD StonyCreek Parents

BRESLIN ARCHITECTS D�HUY Engineerng, Inc.

STONYCREEKELEMENTARY-DESIGNDEVELOPMENT

February 25, 2020

Page 10: CD StonyCreek Parents

BRESLIN ARCHITECTS D�HUY Engineerng, Inc.

STONYCREEKELEMENTARY-DESIGNDEVELOPMENT

February 25, 2020

Page 11: CD StonyCreek Parents

BRESLIN ARCHITECTS D�HUY Engineerng, Inc.

STONYCREEKELEMENTARY-DESIGNDEVELOPMENT

February 25, 2020

Page 12: CD StonyCreek Parents

BRESLIN ARCHITECTS

WISSAHICKONSTONYCREEKPHASING

Existing Building

1 of 10

Page 13: CD StonyCreek Parents

WISSAHICKONSTONYCREEKPHASING

BRESLIN ARCHITECTS

Updated Phasing Plan – Early Bid Package Summer 2020June 2020 – August 2020

• Relocate Modular Buildings

• Temporary Parking Areas

• Construct Soft and Hard Play Areas Including Stormwater Management

• Install Temporary Paved Walkway to New Play Areas

• Electrical Service Modifications

• Install Temporary Electric Generator with Connection to Existing Transfer Switch

• Install Drive with Paving to Binder Course

• Install Stone Staging Area and Stone Drive to Sub-Grade.

• District to Provide Temporary Walk-In Freezer

Staging Area

Temp Parking

Temp Parking

Soft Play Area

Hard Play Area

2 of 10

Page 14: CD StonyCreek Parents

WISSAHICKONSTONYCREEKPHASING

BRESLIN ARCHITECTS

Updated Phasing Plan – Phase 1September 2020 – June 2021

• Mobilize on Site and Establish Staging Area

• Building Addition

• Install Temporary Water Service Serving Existing Building

• Install Temporary Gas Service Serving Existing Building

• Remove Existing Underground Oil Tank

• Remove Existing Electric Generator

• Remove Existing Electric Transformer

• Site Improvements East Side of Site (Partial Storm Water Structures and Piping, Future Water Main, Future Gas Main, …) Bus

Drop Off & Pick Up

Parent Drop Off & Pick Up

3 of 10

No Construction Deliveries: 8:00 – 8:45am and 3:00 – 3:45pm

Page 15: CD StonyCreek Parents

BRESLIN ARCHITECTS

Updated Phasing Plan – Phase 2June 2021– August 2021

• Continue Building Addition

• Begin Interior M.E.P. Extensions From New Boiler Room

• Site Improvements East Side of Site

• Install Underground Basin, Storm Water Structures and Piping, Remove Storm Water Bypass System

• Install New Water Service From Street

• Install Sanitary Sewer Tie-In to New Addition

• Install New Interior Switch Gear and Connect New Electric Service to Existing Building

• Install New Emergency Generator

• Install Yost Road Access, Storm Water Improvements and 10’ Wide Stone Temporary Walkway September 2021

• Interior Renovations in Corridor Ceilings and North of Corridor to New Addition

• Remove Temporary Parking Lots

• Install New Parking Lot & Driveway Adjacent to New Gymnasium up to Binder Course

4 of 10

Reno

WISSAHICKONSTONYCREEKPHASING

Underground Basin

Page 16: CD StonyCreek Parents

BRESLIN ARCHITECTS

Updated Phasing Plan – Phase 3September 2021– December 2021

• Continue Building Addition Owner to Occupy Addition December 2021

• Relocate Construction Fence

• Continue Interior M.E.P. Extensions From New Boiler Room

• Site Improvements East Side of Site

• Interior Renovations North of Corridor to New Addition Complete Prior to December 2021

Bus Drop Off & Pick Up

Parent Drop Off & Pick Up

Teacher Parking

5 of 10

WISSAHICKONSTONYCREEKPHASING

Page 17: CD StonyCreek Parents

BRESLIN ARCHITECTS

Updated Phasing Plan – Phase 4December 2021 – January 2022

• Owner to Occupy New Addition December 2021

• Relocate Staging Area and Job Trailers

• Interior Renovations at Existing Gymnasium January 2022 to June 2022

• Site Improvements Southwest Side of Site

Reno

Existing Building

Bus Drop Off & Pick Up

Teacher Parking

Parent Drop Off & Pick Up

6 of 10

Staging Area

WISSAHICKONSTONYCREEKPHASING

Page 18: CD StonyCreek Parents

BRESLIN ARCHITECTS

Updated Phasing Plan – Phase 5January 2022 – June 2022

• Interior Renovations at Existing Gymnasium January 2022 to June 2022

• Interior Renovations for New Gymnasium Restrooms

• Site Improvements Southwest Side of Site

• Install Stone Access for Multi Purpose Room Renovations

Reno

Existing Building

Bus Drop Off & Pick Up

Teacher Parking

Parent Drop Off & Pick Up

7 of 10

Staging Area

WISSAHICKONSTONYCREEKPHASING

Reno

Page 19: CD StonyCreek Parents

BRESLIN ARCHITECTS

Updated Phasing Plan – Phase 6

Existing BuildingReno Reno

Parent Drop Off & Pick Up

Teacher Parking

June 2022 – August 2022

• Interior Renovations at Existing Multi Purpose Room to Library June 2022 to November 2022

• Site Improvements Southwest Side of Site

Bus Drop Off & Pick Up

8 of 10

Staging Area

Underground Basin

WISSAHICKONSTONYCREEKPHASING

Page 20: CD StonyCreek Parents

BRESLIN ARCHITECTS

Updated Phasing Plan – Phase 7August 2022 - November 2022 Substantial Completion

• Complete Site Improvements Southwest Side of Site

• Interior Renovations at Existing Multi Purpose Room to Library June 2022 to November 2022

• Remove Modular Classrooms

• Restore Staging Area

• Final Paving and Line Striping

• Remove All Construction Equipment

• Remove E&S Controls

• Final Landscaping by October 2022Parent Drop Off & Pick Up

Teacher Parking

Bus Drop Off & Pick Up

9 of 10

Reno

Reno

WISSAHICKONSTONYCREEKPHASING

Page 21: CD StonyCreek Parents

WISSAHICKONSTONYCREEKSCHEMATICDESIGN

BRESLIN ARCHITECTS

Updated Phasing Plan – CompletionNovember 2022 Final Completion

10 of 10

Page 22: CD StonyCreek Parents

BRESLIN ARCHITECTS D�HUY Engineerng, Inc.

STONYCREEKELEMENTARY-DESIGNDEVELOPMENT

Milestones 

Whitpain Township Land Development Approval Feb 2020

  Award Bids - Phase 1 Sitework April 2020

  Bids - Main Project June 2020 Phase 1 Sitework Timeline June 2020 - August 2020

Modular Relocation Timeline June 2020 - August 2020

Award Bids - Main Project July 2020 Occupy New Addition January 2022

Occupy Classroom Renovation Phase August 2022

Occupy Library Renovation Phase November 2022

February 25, 2020

Page 23: CD StonyCreek Parents

BRESLIN ARCHITECTS D�HUY Engineerng, Inc.

QUESTIONS?

STONYCREEKELEMENTARY-DESIGNDEVELOPMENT

February 25, 2020