30
GUIDELINES FOR SAFE AND RELIABLE INSTRUMENTED PROTECTIVE SYSTEMS Center for Chemical Process Safety ccps CENTER FOR CHFMW FPOCFSS WF7y An AlChE Industry Technology Alliance @E;E&c,ENCE A JOHN WlLEY & SONS, INC., PUBLICATION

ccps - download.e-bookshelf.de · The Center for Chemical Process Safety (CCPS), an Industry Technology Alliance of AIChE, was established in . 1985 . to develop and disseminate technical

  • Upload
    others

  • View
    27

  • Download
    2

Embed Size (px)

Citation preview

  • GUIDELINES FOR SAFE AND RELIABLE INSTRUMENTED PROTECTIVE SYSTEMS

    Center for Chemical Process Safety

    ccps CENTER FOR CHFMW FPOCFSS WF7y

    An AlChE Industry Technology Alliance

    @E;E&c,ENCE A JOHN WlLEY & SONS, INC., PUBLICATION

    dcd-wgc2.jpg

  • This page intentionally left blank

  • GUIDELINES FOR SAFE AND RELIABLE INSTRUMENTED PROTECTIVE SYSTEMS

  • This book is one in a series of process safety guideline and concept books published by the Center for Chemical Process Safety (CCPS). Please go to www.wiley.com/go/ccps to see the full list of titles.

  • GUIDELINES FOR SAFE AND RELIABLE INSTRUMENTED PROTECTIVE SYSTEMS

    Center for Chemical Process Safety

    ccps CENTER FOR CHFMW FPOCFSS WF7y

    An AlChE Industry Technology Alliance

    @E;E&c,ENCE A JOHN WlLEY & SONS, INC., PUBLICATION

  • Copyright 0 2007 by American Institute of Chemical Engineers. All rights reserved

    A Joint Publication of the Center for Chemical Process Safety of the American Institute of Chemical En- gineers and John Wiley & Sons, Inc.

    Published by John Wiley & Sons, Inc., Hoboken, New Jersey Published simultaneously in Canada.

    No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means, electronic. mechanical. photocopying, recording, scanning, or otherwise, except as permitted under Section 107 or 108 of the 1976 United States Copyright Act, without either the prior written permission of the Publisher. or authorization through payment of the appropriate per-copy fee to the Copyright Clearance Center, Inc., 222 Rosewood Drive, Danvers, MA 01923, (978) 750-8400, fax (978) 750-4470, or on the web at www.copyright.com. Requests to the Publisher for permission should be addressed to the Permissions Department, John Wiley & Sons, Inc., 1 I 1 River Street, Hoboken. NJ 07030, (201) 748-601 I , fax (201) 748-6008, or online at http://www.wiley.com/go/permission.

    Limit of Liability/Disclaimer of Warranty: While the publisher and author have used their best efforts in preparing this book, they make no representations or warranties with respect to the accuracy or completeness ofthe contents of this book and specifically disclaim any implied warranties of merchantability or fitness for a particular purpose. No warranty may be created or extended by sales representatives or written sales materials. The advice and strategies contained herein may not be suitable for your situation. You should consult with a professional where appropriate. Neither the publisher nor author shall be liable for any loss of profit or any other commercial damages, including but not limited to special, incidental, consequential, or other damages.

    For general information on our other products and services or for technical support. please contact our Customer Care Department within the United States at (800) 762-2974, outside the United States at (317) 572-3993 or fax (317) 572-4002.

    Wiley also publishes its books in a variety of electronic formats. Some content that appears in print may not be available in electronic format. For information about Wiley products, visit our web site at www.wiley.com.

    Library of Congress Caralo~in~-in-Publication Data is available.

    ISBN 978-0-471-97940-1

    Printed in the United States of America

    10 9 8 7 6 5 4 3 2

    http://www.copyright.comhttp://www.wiley.com/go/permissionhttp://www.wiley.com

  • It is sincerely hoped that the information presented in this document will lead to an even more impressive safety record for the entire industry; however, neither the American Institute of Chemical Engineers, its consultants, CCPS Technical Steering Committee and Subcommittee members, their employers, their employers' officers and directors, nor SIS- Tech Solutions LP and its employees warrant or represent, expressly or by implication, the correctness or accuracy of the content of the information presented in this document. As between (1) American Institute of Chemical Engineers, its consultants, CCPS Technical Steering Committee and Subcommittee members, their employers, their employers' officers and directors, andSIS-Tech Solutions LP and its employees, and (2) the user of this document, the user accepts any legal liability or responsibility whatsoever for the consequence of its use or misuse.

  • This page intentionally left blank

  • ACKNOWLEDGEMENTS

    The American Institute of Chemical Engineers (AIChE) wishes to thank the Center for Chemical Process Safety (CCPS) and those involved in its operation, including its many sponsors whose funding made this project possible and the members of the Technical Steering Committee who conceived of and supported this Guidelines project. The members of the Guidelines for Safe and Reliable Instrumented Protective Systems Subcommittee deserve special recognition for their dedication and technical contributions leading to the creation of this useful addition to the CCPS process safety Guidelines series.

    The members of the Subcommittee were:

    Dave A. Deibert, Chair Arthur J. Schwartz A. Doug Cates Bob Roubion Gregory Schultz Helmut Bezecny Richard R. Dunn Jan Windhorst Dallas L. Green Randy Freeman

    Air Products and Chemicals, Inc. Bayer (retired) Celanese Degussa The Dow Chemical Company The Dow Chemical Company Dupont NOVA Chemicals, Inc. Rohm and Haas Company Safety & Property Protection

    Consulting

    Adrian L. Sepeda was the CCPS staff liaison and was responsible for overall project administration. Adrian also wrote the book preface.

    The task of preparing the text from Subcommittee input was entrusted to Dr. Angela Summers, President, SIS-TECH Solutions LP, and principal book author. She and selected members of her capable staff organized and drafted the concepts and emphasis areas requested. Dr. Michela Gentile and Susan Wiley assisted with book drafting and review. Laurie Mayes-Fisher was responsible for typesetting and graphic design.

    vii

  • Guidelines for Safe and Reliable IPS viii

    A special thanks and appreciation to Ken Bond, Shell (retired), Bernard Michaux, Total (retired), and Vic Maggioli, IEC 61 5 1 1 Chairman, for input and council during the drafting of the book.

    CCPS also gratefully acknowledges and thanks those who peer reviewed the draft and offered meaningful comments and suggestions. These peer reviewers were:

    Hal Thomas Robert Zittleman Degussa Vern Darling Richard Stougie Wayne Chastain Eastman Chemicals Robert Blanco Fibertel William Olsen Tony Thompson Monsanto Brian Smith Nova Chemicals Lisa Morrison PPG Industries, lnc. Art Dowel1 Rohm & Haas Company John Alderman RRS Engineering Bryan Zachary SIS-TECH Solutions, LP Kevin Klein Solutia

    Air Products and Chemicals, lnc.

    The Dow Chemical Company The Dow Chemical Company

    Merck & Company, Inc.

    Their insights, comments, and suggestions helped ensure a balanced perspective for the Guideline.

    Lastly, we wish to express our special appreciation for the guidance, counsel, and contributions of Dr. Arthur Schwartz, committee member, who passed away before the book was published. Art was a scholar and a gentleman.

  • PREFACE

    The American Institute of Chemical Engineers (AIChE) has a more than 50 year history of involvement with process safety as it relates to chemical processing facilities. Through its strong ties with process designers, builders, operators, safety professionals and academia, AlChE has enhanced communication and fostered improvement in the already high safety standards of the industry. AlChE publications and symposia have become a recognized valuable information resource for the engineering profession on the causes of accidents and means of prevention.

    The Center for Chemical Process Safety (CCPS), an Industry Technology Alliance of AIChE, was established in 1985 to develop and disseminate technical information for use in the prevention of major chemical accidents. CCPS is supported by a diverse group of industrial sponsors in the chemical industry and related industries who provide the necessary funding and professional guidance for its projects. The CCPS Technical Steering Committee and the technical subcommittees oversee individual projects selected by CCPS. Professional representatives of the sponsoring companies staff the subcommittees, with a member of the CCPS staff coordinating subcommittee activities.

    Since its founding, CCPS has published many volumes in its “Guidelines” series and in its smaller “Concept” series texts. These CCPS books address not only scientific techniques, practices and issues faced by engineers in plant design, operations and maintenance, they also cover the broader subject of chemical process safety management. Successful process safety programs and management systems are the products of committed and active participation of personnel at all levels who apply a systematic approach to process safety as an integral part of operations management.

    This Guideline explains the decision-making processes for the management of instrumented protective systems (IPS) throughout a project’s life cycle. It uses IEC and ISA standards as a basis for the work processes used to achieve safe and reliable process operation. It establishes a framework for a protective management system that can be used to design and manage those specific instrumented systems. By walking the reader through a project’s life cycle, engineering, maintenance, and operations disciplines can easily focus on their responsibilities and duties. Using this approach, the book is useful as a primer, guidelines reference and resource manual. Examples are used to provide “real-world” experience applications. This book is a companion publication to the earlier published CCPS book, “Guidelines for Safe Automation of Chemical Processes.”

    CCPS hopes that the guidance and examples provided herein will aid in promoting safer and more reliable IPSs.

    ix

  • This page intentionally left blank

  • TABLE OF CONTENTS

    ACKNOWLEDGEMENTS

    PREFACE

    TABLE OF CONTENTS

    LIST OF FIGURES

    LIST OF TABLES

    INTRODUCTION

    1.1 Purpose

    1.2 Target Audience

    1.3 Book Road Map

    1.4 Management Commitment

    PLANNING 2.1 Protective Management System Lifecycle

    2.2 Why It Makes Good Business Sense

    2.3 Documentation

    2.4 Good Engineering Practices

    2.4.1 Conformance 2.4.2 Application-Specific Practices

    2.4.3 SIS Good Engineering Practices

    2.4.4 ISA 84.0 l/IEC 6 15 1 1 Overview 2.5 Key Management System Elements

    2.5.1 Staffing 2.5.2 Responsibility and Competence

    2.5.3 Independent Review

    2.6 Special Topics

    2.6.1 Non-safety Risks 2.6.2 Lifecycle Costs

    2.6.3 Managing Organization Changes

    vii ix

    xi

    xix xxiii

    1

    3

    5

    8

    9 11

    14

    19

    20 24

    25

    26

    27

    28

    34

    34 35

    36

    43

    43 44

    44

    xi

  • xii Table of Contents

    2.6.4 IPS Classification

    2.6.5 Existing SIS

    RISK ASSESSMENT

    3.1 Intended Audience

    3.2 Input Information

    3.3 Basic Work Process

    3.4 Output Documentation

    3.5 Key Management System Elements

    3.5.1 Risk Criteria

    3.5.2 Screen Hazardous Events

    3.5.3 Evaluate Consequence Severity

    3.5.4 Evaluate initiating Event Frequency

    3.5.5 Identify Protective Functions

    3.5.6 Conceptual Allocation

    3.6 Special Topics

    3.6.1 Develop Risk Reduction Strategy

    3.6.2 Mitigated Versus Unmitigated Risk

    3.6.3 Identify Non-Protective Actions

    DESIGN

    4.1 Intended Audience

    4.2 Input Information

    4.3 Basic Work Process

    4.4 Output Documentation

    4.5 Process Requirements

    4.5.1 Operability Requirements

    4.5.2 Functionality Requirements

    4.5.3 Reliability Requirements

    4.5.4 Maintainability Requirements

    4.5.5 Classify Remaining Functions

    4.5.6 Verify Process Requirements

    45

    46

    49

    52

    52

    56

    63

    65

    65

    69

    72

    74

    75

    76

    80

    80

    82

    83

    85

    88

    89

    90

    93

    95

    97

    99

    105

    106

    107

    107

  • Guidelines for Safe and Reliable IPS xiii

    4.6 I&E Requirements

    4.6.1 Identify Good Engineering Practices

    4.6.2 Physically Allocate IPF

    4.6.3 Architecture

    4.6.4 Fault Detection Strategy

    4.6.5 Operator Interface

    4.6.6 Independence and Common Cause

    4.6.7 Cost-Benefit Analysis

    4.6.8 Risk Reduction and STR Verification

    4.6.9 Verify the I&E Requirements

    4.7 Functional Assessment

    4.8 Key Management System Elements

    4.8.1 Technical Practices

    4.8.2 Approved Equipment List

    4.9 Special Topics

    4.9.1 Independence Evaluation

    4.9.2 Continuous and Demand Mode Operation

    ENGINEERING, INSTALLATION, COMMISSIONING AND VALIDATION

    5.1 Intended Audience

    5.2 Input Information

    5.3 Basic Work Process 5.4 Output Documentation

    5.5 Hardware

    5.5.1 Application Requirements

    5.5.2 Field Device Specification

    5.5.3 Logic Solver Specification

    5.5.4 Operator Interface Specification

    5.5.5 Response Time

    5.6 Software

    107

    110

    110

    116

    130

    137

    143

    144

    145

    146

    147

    148

    148

    149

    151

    151

    152

    155 157

    158

    159

    163

    164

    164

    165

    166

    169

    171

    173

  • xiv Table of Contents

    5.6.1 Software Specification

    5.6.2 Utility Software Selection

    5.6.3 Software Language Selection

    5.6.4 Application Program Development 5.6.5 Managing Changes

    5.7 Factory Acceptance Test 5.7.1 FAT Procedure

    5.7.2 Deficiency Tracking

    5.7.3 Test Documentation 5.8 Installation Plans

    5.9 Commissioning Plans

    5.9.1 Commissioning Sequence

    5.9.2 Commissioning Activity Follow-up

    5.10 Verifi Operator And External Interfaces

    5.1 1 Validation 5.1 1.1 Loop checks

    5.11.2 Site Acceptance Test

    5.1 1.3 Start-up Procedures 5.1 1.4 Hot Cutover

    5.11.5 Pre-Startup Safety Review

    5.12 Management Of Change

    OPERATIONAL AND MECHANICAL INTEGRITY

    6.1 Intended Audience 6.2 Input Information

    6.3 Basic Work Process 6.3.1 Developing IPS Procedures

    6.3.2 Auditing IPS Procedures 6.3.3 Revising IPS Procedures

    6.4 Output Documentation

    6.5 Operating Procedures

    I 74

    175

    176

    177

    180

    180

    181

    183

    183

    184

    185

    187

    189

    190

    191

    191

    192

    194

    195

    195

    196

    197

    198

    199

    199

    20 1

    204

    204

    204

    206

  • Guidelines for Safe and Reliable IPS xv

    6.5.1 Operator Response to Hazardous Events

    6.5.2 Operator Response to Failure

    6.5.3 Compensating Measures and MTTR 6.6 Bypass Management Procedure

    6.7 Maintenance Procedures

    6.8 Training 6.8.1 Operations 6.8.2 Maintenance

    6.8.3 Engineering

    6.8.4 Auditing

    6.9 Managing Changes

    6.9.1 Access Security

    6.9.2 Management of Change

    6.9.3 Hardware Configuration Management 6.9.4 Embedded Software Management 6.9.5 Application Program Management

    6.9.6 Decommissioning

    6.10 Monitoring Performance

    6.10.1 Process Demands 6.10.2 Detected Faults

    6.10.3 Dangerous Failures

    6.10.4 Spurious Operation

    6.10.5 Personnel conformance to work practices

    CONTINUOUS IMPROVEMENT

    7. I Intended Audience 7.2 Input Information

    7.3 Basic Work Process 7.3.1 Understanding History

    7.3.2 Benchmarking Current Status 7.3.3 Defining Gaps

    207

    208

    208

    209

    210

    212

    213 214

    214

    214

    215

    216

    216

    217

    218

    218

    219

    220

    220

    22 1

    22 1

    222

    223

    225

    227

    228

    23 1

    232

    233

    233

  • xvi Table of Contents

    7.4 Output Documentation

    7.5 Determining Path Forward

    DEFINITIONS

    PROTECTION LAYERS

    B. 1 Inherently Safer Design

    B.2 Control

    B.2.1 Control Function

    B.2.2 Protective Function

    B.3 Supervisory B.3.1 Operator Activities

    B.3.2 Operator Alarms with Response

    B.3.3 Instrumented Systems

    B.4 Preventive

    B.4.1 Instrumented Systems

    B.5 Mitigative

    B.5.1 Mechanical Equipment

    B.5.2 Instrumented Systems

    B.6 Barriers

    B.7 Limitation

    B.8 Response

    CORE ATTRIBUTES

    C. 1 Independence

    C.2 Functionality

    C.3 Integrity

    C.4 Reliability

    (2.5 Auditability

    C.6 Access Security C.7 Management Of Change

    UNDERSTANDING FAILURE

    D. 1 Caution-It’s A Benchmark

    235

    236

    239

    267

    269

    27 1

    272

    275

    276

    277

    279

    284

    284

    285

    287

    287

    289

    294

    295

    299

    30 1

    30 1

    303

    304

    305

    306

    306

    309

    31 1

    313

  • Guidelines for Safe and Reliable IPS xvii

    D.2 A “Bathtub” Viewpoint

    D.3 Failure Types

    D.3.1 Random failures

    D.3.2 Systematic failures

    D.3.3 Common Cause Failures

    D.4 Failure Classification

    D.4.1 Safe and Dangerous Failures

    D.4.2 Detected and Undetected Failures

    D.5 IPF Performance Metrics

    D.5.1 Failure Rate

    D.5.2 Instantaneous Probability of Failure

    D.5.3 Average Probability of Failure on Demand

    D.5.4 Beta Factor

    D.6 Spurious Trip Rate

    D.7 Example Application

    PROCESS EQUIPMENT RELIABILITY DATABASE

    USER APPROVED EQUIPMENT AND PRACTICES

    F. 1 User Approved F.l.l Operating environment

    F.1.2 Analysis and Testing F.1.3 Prior Use History

    F.2 Evolution Of Plant Automation

    F.2.1 Basic Process Control System F.2.2 Safety Instrumented System

    F.2.3 Future Technology

    F.3 Logic Solver Considerations

    F.3.1 Technologies

    F.3.2 Electrical Systems F.3.3 Electronic Systems

    F.3.4 Programmable Electronic System

    3 I4

    317

    318

    319

    322

    325

    326

    328

    330

    33 1

    332

    335

    338

    338

    340

    343

    347

    347

    350

    350

    352

    355

    357

    357

    359

    3 60

    360

    36 1

    362

    363

  • xviii Table of Contents

    F.3.5 Logic Solver Separation F.4 Field Device Considerations

    F.4.1 Separation

    F.4.2 Inputs

    F.4.3 Final Elements

    F.5 Utilities

    F.5.1 Instrument air

    F.5.2 Power

    F.6 Wiring Practices

    F.7 Communications And Interconnectivity

    F.8 Prescriptive Designs

    F.8.1 SIL 1 F.8.2 SIL 2 F.8.3 SIL 3

    REFERENCES

    ACRONYMS AND ABBREVIATIONS

    INDEX

    364

    3 66

    367

    368

    37 1

    373

    3 74

    375

    379

    38 1

    383

    3 84

    3 84

    385

    387

    393

    396

  • LIST OF FIGURES

    Figure 2.1. Planning Phase.

    Figure 2.2. System Relying on Personnel Training and Experience.

    Figure 2.3. System Relying on Procedures and Practices. (adapted from

    Figure 2.4. System Relying on Establishing and Monitoring

    Figure 2.5. ISA 84.01AEC 615 1 1 Lifecycle.

    Figure 2.6. Lifecycle Illustrating Functional Assessment Stages.

    Figure 2.7. Example Instrumented Safety System Classification.

    Figure 3.1. Risk Assessment Phase.

    Figure 3.2. Protection Layers.

    Figure 3.3. Risk Reduction Triangle.

    Figure 3.4. Hazard and Risk Analysis Work Process.

    Figure 3.5. Using IPLs to Close Risk Gap.

    Figure 3.6. Risk Assessment Process. Figure 3.7. Example Showing Risk Matrices Using Qualitative

    (adapted From Reason 1997)

    Reason 1997)

    Core Attributes. (adapted from Reason 1997)

    (A), Semi-Quantitative Frequency (B), and Semi-Quantitative Frequency and Severity (C).

    Figure 3.8. Example Risk Screening Process.

    Figure 3.9. Initiating Cause Challenging Four IPLs.

    Figure 3.10. Initiating Cause Challenging Four IPLs With Vulnerabilities. Figure 3.11. Control Function Fails Leading to Challenge on IPLs. Figure 3.12. Initiating Cause Due to Failure Within BPCS.

    Figure 3.13. Initiating Cause Leads to Hazardous Event due to

    Figure 4.1. Design Phase.

    Figure 4.2. Overall Work Process. Figure 4.3. Process Requirements Work Process.

    Multiple IPL Failure.

    15

    16

    17

    18

    30

    38

    45

    51

    58

    59

    60

    62

    64

    67

    72

    77

    77

    78

    79

    80

    88

    92

    97

    xix

  • xx List of Figures

    Figure 4.4. Process Condition Changes With Time. Figure 4.5. I&E Requirements Work Process.

    104

    109

    1 1 1 Figure 4.6. Separate and Independent Protection Layers.

    Figure 4.7. Supervisory Function Implemented in BPCS with

    Figure 4.8. Separate BPCS with Combined Supervisory Function and SIF. 1 13 Separate SIS. 112

    Figure 4.9. Combined Control Function, Supervisory Function and SIF.

    Figure 4.10. BPCS with Control and Supervisory Functions and SIS

    Figure 4.1 1. BPCS with Control and Supervisory Functions and Separate

    Figure 4.12. Scope of IPS.

    Figure 4.13. Impact of MTTFD on the PFDAVG of Equipment

    Figure 4.14. Common Voting Architectures.

    Figure 4.15. Effect of Architecture on the PFDAVG for Proof Test

    Figure 4.16.2003 Dual Voting Architecture

    Figure 4.17.2003 Voting Architecture With Single Failure in the

    Figure 4.18.2003 Voting Architecture With Single Failure Toward the

    Figure 4.19. Voting Considerations. (adapted from Englund and

    Figure 4.20. Effect of Diagnostic Coverage on the PFDAVG

    Figure 4.21. Effect of Test Interval on Average Probability of Failure

    Figure 4.22. Illustration of Control Room Display. (Nimmo 2006)

    Figure 5.1. Engineering, Installation, Commissioning, and

    Figure 5.2. Relative Cost of Making Design Changes.

    Figure 5.3. Engineering, Installation, Commissioning and

    Figure 5.4. Response Time.

    with PIF and SIF.

    SIS and PIS.

    Assuming the Simplified Equation, hDTI/2.

    Intervals Between 1 and 7 Years.

    Normal Range.

    Trip State.

    Grinwis 1992)

    on Demand.

    Validation Phase.

    Validation Work Process.

    113

    114

    115

    117

    118

    124

    125

    149

    127

    127

    128

    156

    134

    139

    156

    160

    161

    172

  • Guidelines for Safe and Reliable IPS

    Figure 5.5. Commissioning Activities. Figure 6.1. Operational and Mechanical Integrity Phase.

    Figure 6.2. Operational and Mechanical Integrity Work Process

    Figure 7.1. Iceberg Illustrating the Direct and Indirect Costs of Injuries Figure 7.2. Protective Triangle.

    Figure 7.3. Continuous Improvement Phase.

    (adapted from IEC 61 5 1 1)

    xxi

    188

    198

    200

    226

    226

    227

    Figure 7.4. Overview Illustrating the Complexity of the Decision Making Process. (adapted from Reason 1990) 232

    Figure 7.5. Lifecycle Illustrating Information Collected at Each Phase.

    Figure B.1. Protection Layers.

    Figure B.2. Ability to Cost Effectively Influence Inherent Risks.

    Figure B.3. Control Function and Supervisory Function Implemented

    Figure C.l. PIS and BPCS are Separate and Independent Figure C.2. PIS and BPCS are not Independent or Separate. Figure C.3. Cyber-security risks. (Nelson 2006)

    Figure D.l. Overall Bathtub Curve (A) and Components of the Bathtub Curve (B).

    Figure D.2. Hypothetical Device’s Random Failure Rate is Constant (A), However Other Non-Random Failure Sources Affect the Observed Failure Rate of the Device (B).

    for Their Analysis. (see Table D. 1)

    in the BPCS.

    Figure D.3. Taxonomy of Common Cause Factors (CCF) and Methods

    Figure D.4. Components of the Total Random Failure Rate.

    Figure D.5. States of a Device.

    Figure D.6. Typical Saw Tooth Shape for the PFD(t).

    Figure D.7. Effect of Partial Testing on PFD(t). Figure D.8. Example Architecture Illustrating an Independent Control

    Figure E. 1. PERD Process.

    Figure F.l. Example SIL 1 SIS. Figure F.2. Example High Reliability SIL 1 SIS.

    System and Protective Instrumented System (PIS).

    230

    267

    27 1

    275

    3 02

    303

    307

    315

    320

    323

    329

    332

    333

    334

    340

    345

    3 84

    384

  • xxi i

    Figure F.3. Example SIL 2 SIS.

    Figure F.4. Example High Reliability SIL 2 SIS. Figure F.5. Example SIL 3 SIS.

    Figure F.6. Example High Reliability SIL 3 SIS.

    List of Figures

    385

    385

    386

    3 86

  • LIST OF TABLES

    Table 1.1. Target Audience and Essential Knowledge.

    Table 1.2. Road Map by Target Audience.

    Table 2.1. Objectives, Inputs and Outputs by Lifecycle Phase.

    Table 3.1. Examples of Quantitative Targets. Table 3.2. Hazard Analysis Methods. Table 3.3. Risk Analysis Methods.

    Table 3.4. Example of Frequency (or Likelihood) Rankings.

    Table 4.1. Example Ranges of MTTFD and MTTFSP for Field

    Table 4.2. Example Ranges of MTTFD and MTTFSP for

    Table 4.3. Voting Considerations.

    Table 5.1. Example Operating Environment Conditions.

    Table 6.1. Categories of Human Error. (Mostia 2003)

    Table B.l. Examples of Operator or Supervisory Activity RRF.

    Table B.2. Examples of Operator Response to Alarm RRF. (adapted from ISA TR84.00.04-2005 Appendix B)

    Table B.3. Integrity Level Relationships. Table B.4. Examples of Mechanical Mitigation Device RRF.

    Table B.5. Examples of Limitation System RRF.

    Table D.1. Methods Used to Address the Different Types of Common Cause Failures. (see Figure D.3)

    Table D.2. Example Failures, Modes and Effects for an Electronic Pressure Transmitter.

    Table D.3. Failure Rate Data Used in the Examples. Table D.4. Hazard Rate Results for Figure D.8 Architecture.

    Table D.5. PFDAVG Results for Figure D.8 Architecture.

    Table D.6. STR Results for Figure D.8 Architecture.

    Equipment. (SIL Solver 2006)

    Logic Solvers. (SIL Solver 2006)

    7

    9

    24

    69

    70

    70

    75

    118

    120

    123

    165

    203

    278

    28 1

    285

    288

    298

    324

    327

    34 1

    34 1

    34 1

    342

    xxiii

  • This page intentionally left blank

  • Guidelines for Safe and Reliable IPS 1

    1

    INTRODUCTION

    Instrumented Protective Systems (IPS) implement protective functions that detect abnormal or unacceptable operating conditions and take action on the process to achieve or maintain a safe state. IPSs are used to reduce the process risk associated with health and safety effects, environmental impacts, loss of property and business interruption costs.

    Safe operation cannot be achieved in isolation. The risk reduction strategy must also consider the owner/operator’s business needs. Personnel are expected to operate process units to achieve target production rates, product quality, and cost performance. Balancing safety and production goals can be challenging when the IPS design and management does not adequately address the operational needs. The following can add significantly to this challenge:

    High initiating cause frequency results in frequent loss of control and process shutdown,

    High frequency of spurious IPS operation leads to: 0

    0

    0

    Lack of trust in the IPS (leading cause of improper bypassing)

    Frequent process equipment shutdown with subsequent process unit impact

    Frequent process unit start-up which may have significant inherent risk

    High frequency of IPS equipment failure results in high operating and maintenance costs,

    Ignoring functionality requirements leads to an IPS design which does not adequately support the various process operating modes and potentially causes excessive IPS equipment bypassing, alarms, and shutdowns, and

    Ignoring maintainability requirements leads to inadequate maintenance resources and facilities and potentially failure of the mechanical integrity program.

    It is well understood that plant productivity and operability improves when quality control processes are applied to process equipment operation. Given the potential problems associated with IPS implementation, it simply makes sense to apply the same quality control processes across the IPS lifecycle.

    0

    0

  • 2 Introduction

    Quality control processes rely on the use of appropriate metrics to verify compliance with the work process expectations. For IPS design and management, these metrics are associated with core attributes that are considered essential for an instrumented safeguard to be classified as an IPS. Seven core attributes should be achieved by the IPS design and supported by appropriate management practices:

    1. Independence,

    2. Functionality,

    3. Integrity,

    4. Reliability, 5 . Auditability,

    6. Access security, and

    7. Management of change.

    These core attributes are periodically assessed to determine the degree to which they are being maintained and improved. Quality control processes, such as verification, assessment, auditing, and validation, are necessary to ensure the required attributes are achieved throughout the IPS life. The level of rigor employed in the quality control limits the performance which can be reasonably achieved by the IPS.

    IPS implementation and continuous improvement involve the effort of many stakeholders, e.g., management, process safety, process, instrumentation and electrical, operations, maintenance, and manufacturers. Projects are often iterative processes requiring carefid consideration of each discipline’s needs and the core attributes.

    This guidelines book intends to:

    Clarify the essential role of the various personnel responsible for IPSs,

    Establish a protective management system framework for IPS design and management,

    Provide the work processes to be followed for IPS development from risk assessment through its implementation and transfer to operations,

    Discuss essential on-going, day-to-day activities necessary to maintain the core attributes, and

    Challenge owner/operators to continuously evaluate opportunities for improvement.

  • Guidelines for Safe and Reliable IPS 3

    1.1 PURPOSE

    The process industry has made great strides toward improving process unit performance and safe operation. It has made and continues to make significant investment to address process risk using a variety of approaches aimed at identifying and controlling risk. These approaches often must fit within a regulatory framework, which relies on the use of recognized and generally accepted good engineering practices to define the minimum requirements.

    Many governments (e.g., the United States of America, the European Union, the United Kingdom, Germany, The Netherlands, Korea, Taiwan, and Brazil) have regulations concerning the prevention of releases of hazardous chemicals that pose serious injury or life threatening consequences. Although each government uses unique terminology to describe such events, the concept of process safety management is well known throughout the world. It is widely supported even by governments that do not have specific regulations mandating its implementation. Most require, at a minimum, that an owner/operator demonstrate compliance with the good engineering practices applicable to the manufacturing process and its associated hazards.

    The application of control and shutdown equipment to manage hazardous events was first discussed in Guidelines for Safe Automation of Chemical Processes (CCPWAIChE 1993, referred to as Safe Automation). In particular, Safe Automation provided information for the design and implementation of the Basic Process Control System (BPCS) and the SIS. It established for the process industry many of the fundamental concepts used today, such as independent protection layer (IPL), safety integrity level (SIL), separation and diversity of the BPCS and SIS, access security, and fault tolerance.

    Sufi Automation was later referenced by the Instrumentation, Systems and Automation (ISA) society standard, ANSUSA 84.0 1 - 1996, Application of Safety Instrumented Systems (SIS) for the Process Industry. This standard provided good engineering practices for the SIS lifecycle, starting with the design phase and continuing through decommissioning.

    The globalization of the process industry resulted in demand for international practices. Numerous good engineering practices, previously considered national or regional, are being modified, updated, harmonized, and issued as international practices. One such standard is IEC 6 15 1 1, Functional Safety: Safety Instrumented Systems for the Process Industry Sector, which expanded the requirements of

    IEC 61511 is the first sector standard issued using the lifecycle framework established by IEC 6 1508, Functional Safety of Electrical/ Electronic/Programmable Electronic Safety Related Systems and covers the complete SIS lifecycle for the process sector. It was developed and is maintained

    ANSI/ISA 84.01 - 1996.

  • 4 Introduction

    by the International Electrotechnical Commission (IEC) with volunteer support from organizations worldwide, including ISA and CCPS/AIChE.

    IEC 61511 was accepted in 2004 by the European Committee for Electrotechnical Standardization (CENELEC) as EN IEC 6 15 1 1 and the American National Standards Institute (ANSI) as ANSI/ISA 84.00.0 1-2004 Parts 1-3. In 2005, ISA published, Guidelines on the Implementation of ANWISA 84.00.01- 2004, to provide guidance to owners/operators concerning the application of the SIS standard to new and existing equipment. To recognize the contribution of both ISA and IEC to the documentation of good engineering practices for SIS, this book refers to the standard as ISA 84.0 l/IEC 6 15 1 1.

    ISA 84.01/IEC 6151 1 uses the SIL concept to benchmark the integrity of the instrumentation and controls used to achieve the required performance from the SIS. The required SIL is defined during a risk assessment process, which examines the process risk and identifies IPLs. ISA 84.01/IEC 615 11 requires that the SIL be quantitatively verified using estimates of the random hardware failure rate of the SIS components in the intended operating environment.

    Since ISA 84.01/IEC 61511 is an instrumentation and controls standard, it places a great deal of emphasis on the functionality and integrity of the hardware. The assignment and verification of SIL establishes a robust relationship between hardware design and risk reduction. It also provides justification for separation, fault tolerance, and proof test intervals. However, the SIS’s capability to achieve or maintain a safe state is dependent on more than the sum of its hardware components.

    Integrity and functionality are essential performance attributes, but excess attention on these can result in a loss of focus on other core attributes. While weak links in the hardware design may be identified during a numerical analysis of the SIS equipment, the ability of the installed SIS to achieve the SIL is generally limited by human performance against practices and procedures. Independence, reliability, auditability, access security, and management of change must receive as much, if not more, attention to detail.

    The core attributes support the SIS throughout its life by ensuring appropriate focus on minimizing the potential impact of human error on the SIS performance. The absence of a rigorous management system can lead to discrepancies between the desired functionality and integrity and what is achievable in actual operation.

    As process units become increasingly automated, integrated and complex, the deliberate and intentional act of implementing IPLs becomes more important. SISs are only one IPL of many that can be used to achieve and maintain safe operation. Other IPLs, such as relief devices and protective alarms, may be identified and should be managed appropriately. The management system ensures that protective equipment are designed, inspected, maintained, tested, and operated in a safe manner. Many incidents in the process industry have been caused by poor