46
COMPETENCY-BASED LEARNING MATERIAL Sector: CONSTRUCTION Qualification Title: CARPENTRY NC III Unit of Competency: FABRICATE/INSTALL DOOR/WINDOW JAMBS AND PANELS Module Title: FABRICATING/INSTALLING DOOR/WINDOW JAMBS AND PANELS Technical Education and Skills Development Authority Jacobo Z. Gonzales Memorial School of Arts and Trades San Antonio, Biñan City JZGMSAT QA SYSTEM Carpentry NC III Fabricate/install door/window jambs and panels Date Developed: April 1, 2011 Document No. Issued by: Page 1 of 46 Developed by: Glenn F. Salandanan Revision # ____

CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

Embed Size (px)

DESCRIPTION

COMPETENCY-BASED LEARNING MATERIALSector: Qualification Title: Unit of Competency: Module Title:CONSTRUCTION CARPENTRY NC III FABRICATE/INSTALL DOOR/WINDOW JAMBS AND PANELS FABRICATING/INSTALLING DOOR/WINDOW JAMBS AND PANELSTechnical Education and Skills Development Authority Jacobo Z. Gonzales Memorial School of Arts and Trades San Antonio, Biñan CityCarpentry NC III JZGMSAT QA SYSTEM Fabricate/install door/window jambs and panelsDate Developed: April 1, 2011 Developed by: Glenn F. Sa

Citation preview

Page 1: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

COMPETENCY-BASED LEARNING MATERIAL

Sector: CONSTRUCTION

Qualification Title: CARPENTRY NC III

Unit of Competency: FABRICATE/INSTALL DOOR/WINDOW JAMBS AND PANELS

Module Title: FABRICATING/INSTALLING DOOR/WINDOW JAMBS AND PANELS

Technical Education and Skills Development AuthorityJacobo Z. Gonzales Memorial School of Arts and Trades

San Antonio, Biñan City

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 1 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 2: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

HOW TO USE THIS COMPETENCY BASED LEARNING MATERIAL

Welcome to the module in Developing Competency-Based Learning Materials. This module contains training materials and activities for you to complete.

You are required to go through a series of learning activities in order to complete each learning outcome of the module. In each learning outcome are Information Sheets, Self-Checks, Operation Sheets and Job Sheets. Follow these activities on your own. If you have questions, don't hesitate to ask your facilitator for assistance.

The goal of this course is the development of practical skills. To gain these skills, you must learn basic concepts and terminology. For the most part, you'll get this information from the Information Sheets and TESDA Website, www.tesda.gov.ph

This module was prepared to help you achieve the required competency, in "Developing Competency-Based Learning Materials".

This will be the source of information for you to acquire knowledge and skills in this particular competency independently and at your own pace, with minimum supervision or help from your instructor.Remember to:

Work through all the information and complete the activities in each section.

Read information sheets and complete the self-check. Suggested references are included to supplement the materials provided in this module.

Most probably your trainer will also be your supervisor or manager. He/she is there to support you and show you the correct way to do things.

You will be given plenty of opportunity to ask questions and practice on the job. Make sure you practice your new skills during regular work shifts. This way you will improve both your speed and memory and also your confidence.

Use the Self-checks, Operation Sheets or Job Sheets at the end of each section to test your own progress.

When you feel confident that you have had sufficient practice, ask your Trainer to evaluate you. The results of your assessment will be recorded in your Progress Chart and Accomplishment Chart.

You need to complete this module before developing the CBLM of the Learning Outcomes assigned to you.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 2 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 3: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

MODULE CONTENT

UNIT OF COMPETENCY : FABRICATE/INSTALL DOOR/WINDOW JAMBS AND PANELS

MODULE TITLE : FABRICATING/INSTALLING DOOR/WINDOW JAMBS AND PANELS

MODULE DESCRIPTOR : This module covers the competencies in selecting and preparing tools and materials, fabricating door/window, jambs and panels, fabricating jambs/panels of doors/ windows according to plans, and installing fabricated door/window jambs/panels and pre-fabricated moldings.

NOMINAL DURATION : 80 hrs.

CERTIFICATE LEVEL : NC III

PREREQUISITE :

LEARNING OUTCOMES:

Upon completion of this module, the trainee/student must be able to:

• Select and prepare power/hand tools and materials required in fabricating/installing door/window jambs and panels.

• Fabricate jambs and panels of doors/windows according to plans.

• Install fabricated door/window jambs/panels and pre-fabricated moldings.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 3 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 4: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

ASSESSMENT CRITERIA:

• Plans and details are correctly identified and interpreted according to job requirements.

• Appropriate tools and materials are selected, checked and prepared according to specifications

• Materials are re-checked for correct specifications to ensure that they are free from defects; otherwise defects are reported to immediate supervisor for appropriate action

• Appropriate PPE is selected according to safety standards and regulations

• Plans and details are correctly identified and interpreted according to job requirements

• Stocks are planed, squared, laid-out, cut to size and shape according to the required specifications with tolerances of + 5mm in tolerance and + 3mm for squareness and evenness

• Parts are assembled according to dimensions and specifications

• Fabricated parts are positioned according to dimensions and specifications

• Fabricated jambs /panels and pre-fabricated moldings are installed according to specified measurements with + 3mm for squareness, levelness and plumbness

• Temporary bracings are removed without causing damage to frames 24 hours after pouring concrete/mortar

• Finishing hardware materials/ accessories are attached to installed door/window jambs/panels based on specifications

• Unexpected situations are dealt with according to company rules and regulations

• Housekeeping is performed according to safety regulations

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 4 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 5: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

LEARNING OUTCOME NO. 1 Select and prepare power/hand tools and materials required in fabricating/installing door/window jambs and panels.

CONTENTS:• Window and Door Symbols for Floor Plans

ASSESSMENT CRITERIAa. Plans and details are correctly identified and interpreted according

to job requirements.

b. Appropriate tools and materials are selected, checked and prepared according to specifications

c. Materials are re-checked for correct specifications to ensure that they are free from defects; otherwise defects are reported to immediate supervisor for appropriate action

d. Unexpected situations are dealt with according to company rules and regulations

e. Appropriate PPE is selected according to safety standards and regulations

CONDITIONS: You must be provided with the following:

• WORKPLACE LOCATION• TOOLS AND EQUIPMENT

HammerMarking ToolsMeasuring ToolsSteel SquareTry-square

• TRAINING MATERIALSLeaning PackagesBond paperBall pensManualsRelated References

Hand SawChalk LineWater Hose LevelPlumb BobPPECircular Saw

ASSESSMENT METHOD

Portfolio

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 5 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 6: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

Learning Experience

SELECT AND PREPARE POWER/HAND TOOLS AND MATERIALS REQUIRED IN FABRICATING/INSTALLING DOOR/WINDOW

JAMBS AND PANELS

Learning Activities Special Instructions• Read Information Sheet

No. 2.1-1 on window and door symbols for floor plans

• Answer Self-Check No. 2.1-1

Compare your answer to the answer key

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 6 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 7: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

INFORMATION SHEET NO. 2.1-1WINDOW AND DOOR SYMBOLS FOR FLOOR PLAN

Learning Objective: After reading this INFORMATION SHEET, YOU MUST be able to IDENTIFY SYMBOLS OF WINDOWS AND DOORS IN FLOOR PLANS

The symbols shown below represent the common types of windows and doors used on floor plan sketches. Knowing these symbols may help you to understand your blueprint better.

Figure 1. Examples of different common door and window symbols shown in plan form

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 7 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 8: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

SELF-CHECK NO. 2.1-1

Check your mastery in types of doors and window symbols by completing the tasks below.

MATCHING TYPE. Match the symbols in Column A to the type of doors/windows in Column B. Write the letters only on the space provided before the number.

COLUMN A COLUMN B

______1. a. Double , opening out window

b. Left sash over right

c. Double hung window

d. Double acting, single door

e. Single door, interior

f. Double door, interior

g. In and out doors

______2.

______3.

______4.

______5.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 8 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 9: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

ANSWER KEY NO. 2.1-1

Check your answer with the answer key below. If you fail to get it right, refer back to corresponding resources until you make it perfect.

1. E

2. F

3. D

4. C

5. A

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 9 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 10: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

LEARNING OUTCOME NO. 2 Fabricate jambs and panels of doors/windows according to plans

CONTENTS:• Doors and Windows• Door Jamb Construction• Window Sashes

ASSESSMENT CRITERIA1. Plans and details are correctly identified and interpreted according

to job requirements

2. Materials, tools and equipment are selected and prepared consistent with job requirements

3. Stocks are planed, squared, laid-out, cut to size and shape according to the required specifications with tolerances of + 5mm in tolerance and + 3mm for squareness and evenness

4. Parts are assembled according to dimensions and specifications

5. Unexpected situations are dealt with according to company rules and regulations

6. Housekeeping is performed according to safety regulations

CONDITIONS: You must be provided with the following:

• WORKPLACE LOCATION• TOOLS AND EQUIPMENT

HammerMarking ToolsMeasuring ToolsSteel SquareTry-square

• TRAINING MATERIALSLeaning PackagesBond paperBall pensManualsRelated References

Hand SawChalk LineWater Hose LevelPlumb BobPPECircular Saw

ASSESSMENT METHOD

Portfolio

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 10 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 11: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

Learning Experience

FABRICATE JAMBS AND PANELS OF DOORS/WINDOWS ACCORDING TO PLANS

Learning Activities Special Instructions• Read Information Sheet

No. 2.2-1 on Doors and Windows

• Answer Self-Check No. 2.2-1

Compare your answer to the answer key

• Read Information Sheet No. 2.2-2 on door jamb construction

• Answer Self-Check No. 2.2-2

Compare your answer to the answer key

• Perform Job Sheet No. 2.2-2 on Fabricating door jamb

Evaluate your own work using the Performance CriteriaPresent your work to your trainer for evaluationKeep a copy of your work for the next activities

• Read Information Sheet No. 2.2-3 on Window Sashes

• Answer Self-Check No. 2.2-3

Compare your answer to the answer key

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 11 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 12: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

INFORMATION SHEET 2.2-1DOORS AND WINDOWS

Learning Objective: After reading this INFORMATION SHEET, YOU MUST be able to identify different TYPES of DOORS AND WINDOWS

A. DOORS

Types of DoorsDoors, both exterior and interior, are classified as job-built or mill-

built. This classification is further broken down as batten, panel, and flush doors.

Figure 2. Types of doors

1. Job-Built DoorsThe batten door is the most commonly used and most easily

constructed type of job-built door.

2. Mill-Built DoorsThe usual exterior door is the panel type (Figure 2). It consists of

stiles, rails, and filler panels. Two frequently used interior doors are the flush and the panel types.

a. Panel Doors. Panel doors consist of vertical members called stiles and horizontal members called rails. Stiles and rails form the framework into which panels are inserted. Additional vertical and horizontal members called muntins are used to divide the door into any number of panels. Panels may be solid wood, plywood, particleboard or louvered or have glass inserts.

b. Flush Doors. Flush doors have flat surfaces on both sides and consist of a wood frame with thin sheets of material (plywood veneer, plastic laminates, hardboard, or metal) applied to both faces. Flush doors have either a solid or hollow core.• Solid-core doors have a solid particle board or woodblock core

which is covered with layers of veneer. They are usually used as

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 12 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 13: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

exterior doors. Solid-core doors provide better sound insulation and have less tendency to warp.

• Hollow-core doors have a lightweight core made of various materials that are covered with layers of veneer. They are usually used as interior doors and are less expensive to produce.

Figure 3. Mill-built doors

3. Specialty DoorsSpecialty doors include double doors, sliding doors, and folding

doors.

Door FramesDoor frames are made of the following parts: the head casing, the

jambs (head and two sides), and the sill (on exterior doors only. Doors and frames may be fabricated in the shop and installed separately; they may also be remanufactured (prehung), purchased ready for installation. Door-frame layout calculations begin with the size of the door (height, width, and thickness), as given on the door schedule.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 13 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 14: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

Figure 4. Principal parts of a door jamb

Construction information for door frames is usually given in detail drawings. In the type of frame shown in Figure 4, the door jambs are rabbeted to depths of 1/2 inch preventing the door from swinging through the frames.

Figure 5. Typical door-frame details

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 14 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 15: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

Exterior Door FramesExterior door frames are made up of

two side jambs, a head jamb, a sill, and a stop. They are constructed in several ways. In hasty construction (on-site prefabrication), the frames will be as shown in Figure 5. This type requires no frame construction because the studs on each side of the opening act as a frame. Studs are normally placed 16 inches apart on center. Extra studs are added at the sides of door and window openings. Headers are usually used at the top and bottom of such openings.

Figure 6. Single outside door

Interior Door FramesInterior door frames are made up of two side jambs, a head jamb,

and stop moldings which the door closes against. Interior door frames have no sill and no casing, otherwise they are the same as the exterior frames. Figure 6 shows the elevation of a single inside door.

Figure 7. Singe inside door

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 15 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 16: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

Note: SWING - The hand of a door describes the direction in which a door is to swing and from which side it is hinged. The hand is determined from the outside of the door. A standard door has the hinges on the right or left and swings away from you. A reverse door has the hinges on the right or left and swings toward you.

B. WINDOWS

Types of WindowsThe most common types of windows are double-hung and hinged

(or casement) windows. All windows consist of two parts, the frame and the sash.

Figure 8. Types of windows

1. Double-hung window Made of upper and lower sashes that slide vertically past one another. However, for full ventilation of a room, only one-half of the area of the window can be used. Any current of air passing across its face is lost to the room.

2. Casement windows (out-swinging or in-swinging)May be hinged at the sides, top, or bottom. Casements have the

advantage of catching a parallel breeze and slanting it into a room.

Window FramesWindow frames are made of four basic parts: the head, the jambs

(two), and the sill. (The sash is the framework that holds the glass in the window.)

In hasty construction, millwork window frames are seldom used. Instead, simple openings are left in the walls with the stops all nailed to the stud. The sash may be hinged to the inside or outside of the wall or may be constructed to slide. The sliding sash with overlapping panes is

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 16 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 17: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

most common in Army construction because it requires little installation time.

Sills have a usual slope of 1 to 5 inches so that they shed water quickly. They are wider than frames, usually extending about 1 1/2 inches beyond the sheathing. They also form a base for the outside finished casing.

Window SashesA window is normally composed of an upper and a lower sash. There

are two ordinary types of wood sashes: fixed or movable. • Fixed sashes - removable only with the aid of a carpenter• Movable sashes - may slide up and down in channels in the frame (double-hung), or they may swing in or out and be hinged at the side (casement type).

Sashes are classified as single or divided, according to the number of pieces of glass (or lights). A sash may be made of 1 x 3 material with reinforced, rolled plastic material, which can be cut to any desired size.

JointsWindow sashes may be made with open mortise, four tenons, and

with rails tenoned into stiles; with half-lap corners; or with butt joints or corrugated fasteners. In either of the first two cases, the joints may be nailed or glued.

AccessoriesWindow screens - Screen sash is usually 3/4-inch stock; however, for large windows and doors 1 1/8-inch material is frequently used or 3/4-inch lumber is braced with a horizontal member.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 17 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 18: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

SELF-CHECK NO. 2.2-1

Check your mastery in types of doors and window by completing the tasks below.

IDENTIFICATION. Answer the following questions by writing the letter of your choice on the space provided before the number.

_____1. This door consists of vertical members called stiles and horizontal members called rails. Additional vertical and horizontal members called muntins and are used to divide the door into any number of panels.

a. Job-built doorsb. Panel doorsc. Flush doorsd. Specialty doors

_____2. These type of doors have flat surfaces on both sides and consist of a wood frame with thin sheets of material (plywood veneer, plastic laminates, hardboard, or metal) applied to both faces.

a. Job-built doorsb. Panel doorsc. Flush doorsd. Specialty doors

_____3. This type of window have the advantage of catching a parallel breeze and slanting it into a room.

a. Casement windowb. Double-hung windowc. Double opening out windowd. Single, opening-in window

_____4. Made of upper and lower sashes that slide vertically past one another. However, for full ventilation of a room, only one-half of the area of the window can be used. Any current of air passing across its face is lost to the room.

a. Casement windowb. Double-hung windowc. Double opening out windowd. Single, opening-in window

_____5. Window frames are made of four basic parts. Which of the following is not included?

a. Headb. Jambs (2)c. Sashd. Sill

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 18 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 19: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

ANSWER KEY NO. 2.2-1

Check your answer with the answer key below. If you fail to get it right, refer back to corresponding resources until you make it perfect.

1. B2. C3. A4. B5. C

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 19 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 20: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

INFORMATION SHEET 2.2-2DOOR JAMB CONSTRUCTION

Learning Objective: After reading this INFORMATION SHEET, YOU MUST be able to FABRICATE and INSTALL DOOR JAMB.

Door jambs are the linings of the framing in door openings. The casing and stops are nailed to the door jambs, and the door is hung from them. Door openings should allow 1/2 inch between the frame and the jamb (Figure 8-8, page 8-6) to permit plumbing and leveling of jambs. Inside jambs are made of 3/4-inch stock; outside jambs are made of 1 3/8-inch stock. The width of the stock varies with the thickness of the walls. Inside jambs are built up with 3/8- x 1 3/8-inch stops nailed to the jamb. Outside jambs are usually rabbeted to receive the door.

Jambs are made and set as follows:

Step 1. Cut the side jambs of an entrance door to the height of the door, less the depth of the head jamb rabbet (if any), plus the:• Diagonal thickness of the sill, plus the sill bevel allowance.• Thickness of the threshold, if any.• Thickness of the head jamb.• Height of the side-jamb lugs.

Step 2. Cut the head jamb to the width of the door, less the combined depths of the side-jamb rabbets (if any), plus the combined depths of the head-jamb dadoes (grooves).

Step 3. Level the floor across the opening to determine any variation in floor heights at the point where the jambs rest on the floor.

Step 4. Cut the head jamb with both ends square. Allow the width of the door plus the depth of both dadoes and a 3/16-inch door clearance.

Step 5. From the lower edge of the dado, measure a distance equal to the height of the door plus the clearance required under it. Mark it and cut it square. On the opposite jamb, do the same. Make additions or subtractions on this side for floor variations, if any.

Step 6. Nail the side jambs and jamb heads together with 8d common nails, through the dado into the head jamb.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 20 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 21: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

Figure 9. Door Jambs

Figure 10. Jamb allowanceStep 7. Set the jambs into the opening. Place small blocks on the subfloor

under each jamb. Blocks should be as thick as the finished floor

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 21 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 22: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

will be. This allows room for the finished floor to go under the door.

Step 8. Plumb the jambs and level the jamb head. Wedge the sides with shingles between the jambs and the studs, to align them. Nail them securely in place. Take care not to wedge the jamb unevenly. Use a straightedge 5 or 6 feet long inside the jambs to help prevent uneven wedging.

Step 9. Check the jambs and the head carefully. Jambs placed out of plumb will tend to swing the door open or shut, depending on the direction in which the jamb is out of plumb.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 22 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 23: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

SELF-CHECK NO. 2.2-2

Check your mastery in interpretation of plans and details by completing the tasks below.

IDENTIFICATION. Complete the sentence by choosing your answer on the phrases below. Write your answer on the space provided.

Check the jamb Measure the distanceCut the head Nail the side jambCut the head jamb Plumb the jambsCut the side jambs Set the jambsLevel the floor

1. ______________________ of an entrance door to the height of the door, less the depth of the head jamb rabbet (if any).

2. ______________________ to the width of the door, less the combined depths of the side-jamb rabbets (if any), plus the combined depths of the head-jamb dadoes (grooves).

3. ______________________across the opening to determine any variation in floor heights at the point where the jambs rest on the floor.

4. ______________________jamb with both ends square. Allow the width of the door plus the depth of both dadoes and a 3/16-inch door clearance.

5. From the lower edge of the dado, ____________________ equal to the height of the door plus the clearance required under it. Mark it and cut it square. On the opposite jamb, do the same. Make additions or subtractions on this side for floor variations, if any.

6. ______________________ and jamb heads together with 8d common nails, through the dado into the head jamb.

7. ______________________ into the opening. Place small blocks on the subfloor under each jamb. Blocks should be as thick as the finished floor will be. This allows room for the finished floor to go under the door.

8. ______________________ and level the jamb head. Wedge the sides with shingles between the jambs and the studs, to align them. Nail them securely in place. Take care not to wedge the jamb unevenly.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 23 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 24: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

Use a straightedge 5 or 6 feet long inside the jambs to help prevent uneven wedging.

9. _____________________ and the head carefully. Jambs placed out of plumb will tend to swing the door open or shut, depending on the direction in which the jamb is out of plumb.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 24 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 25: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

ANSWER KEY NO. 2.2-2

Check your answer with the answer key below. If you fail to get it right, refer back to corresponding resources until you make it perfect.

1. Cut the side jambs2. Cut the head jamb3. Level the floor4. Cut the head5. Measure the distance6. Nail the side jamb7. Set the jambs8. Plumb the jambs9. Check the jambs

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 25 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 26: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

JOB SHEET NO. 2.2-2

Title: Fabricate Door JambPerformance Objective: Given the necessary materials, you should

be able to fabricate door jambSupplies and Materials: Working Drawing/ Plan

2”x6”x39” Lumber

Tools and Equipment: • Hammer• Marking Tools• Measuring Tools• Wood chisel • Try-square

• Hand saw• Chalk Line• PPE• Circular Saw• Table saw

Steps/Procedure:

1. Plane and squaring stocks to dimension. Typically, 2”x6” of lumber is used. (Refer to Operation Sheet No. 4.2-5 on Plane and square stock to dimension)

2. Cut the side jambs to its length. The standard height of door is 2.10 meters. This means the sides of the door jamb need to be 2.20 meters to allow for the thickness of the header and for the threshold less the depth of the rabbet which is normally 5mm.

3. Rabbet the jambs and the header. The width of the rabbet should be the thickness of the door to be installed.

4. Cut the header according to the width of the door to be installed. Add the combined thickness of the two side jambs less the depths of the rabbets.

5. Use slipped miter joint to connect the three pieces together. Secure the side jambs to the header by using wood glue and 8d nails as fasteners.

6. Check the squareness of the assembles pieces using framing square. Temporarily secure the three pieces using diagonal corner braces to keep it square at the head and stretcher near the bottom to keep the jambs set apart at the correct width.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 26 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 27: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

ACTIVITY: From the given working drawing below, fabricate model door jamb.

Note: All measurements are in metric.

Assessment Method:Performance Criteria Checklist

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 27 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 28: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

PERFORMANCE CRITERIA CHECKLISTOPERATION SHEET NO. 2.2-2

Name of Trainee:_________________________________ Date: __________________

CRITERIA YES NO

1. Did plane and square stocks to dimension according to the required specifications with tolerances of + 5mm in tolerance and + 3mm for squareness and evenness?

2. Did I cut the stocks to size and shape according to the required specifications with tolerances of + 5mm in tolerance and + 3mm for squareness and evenness?

3. Are all parts assembled according to specifications?

4. Did I secure the three pieces together using braces and stretcher?

5. Did I use tools and equipment consistent with job requirements?

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 28 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 29: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

INFORMATION SHEET NO. 2.2-3WINDOW SASHES

Learning Objective: After reading this INFORMATION SHEET, YOU MUST be able to Know the PARTS OF A WINDOW SASH and follow the STEPS IN CONSTRUCTING WINDOW SASH

STEPS IN CONSTRUCTING WINDOW SASHESStep 1. Make two frames with the glass substitute installed on one.Step 2. Nail the frames together. When the two frames are nailed

together, they should be turned so that the joints are not over each other. This staggers the joints and strengthens the sash. Do not make the window sash larger than the available glass substitute. If the sash is too large for the glass substitute to cover, a muntin may be placed in the sash to hold the glass substitute; this should be fastened with corrugated metal fasteners. Where long sashes are made, a muntin should be placed in the center for added strength. Figure 9, shows the window frame and sash details.

Step 3. Cut the side pieces to a length equal to the height of the sash, less the width of one piece of material.

Step 4. Cut the top and bottom pieces the same length as the window, less the width of the material.

Step 5. Fasten at the joints with corrugated metal fasteners.

Figure 11. Window frame and sash details

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 29 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 30: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

SELF-CHECK NO. 2.2-3

Check your mastery in window sash by completing the tasks below.

IDENTIFICATION: Identify the parts of the window by writing your answer on the space provided.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 30 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 31: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

ANSWER KEY NO. 2.2-3

Check your answer with the answer key below. If you fail to get it right, refer back to corresponding resources until you make it perfect.

1. DRIP CAP2. TOP RAIL3. SASH4. MULLION5. BOTTOM RAIL6. SIDE CASING7. STILE8. STOP BEAD

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 31 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 32: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

LEARNING OUTCOME NO. 3 Install fabricated door/window jambs/panels and pre-fabricated moldings.

CONTENTS:• Door Installation• Door Trim• Door Lock Installation

ASSESSMENT CRITERIA1. Fabricated parts are positioned according to dimensions and

specifications2. Fabricated jambs /panels and pre-fabricated moldings are installed

according to specified measurements with + 3mm for squareness, levelness and plumbness

3. Temporary bracings are removed without causing damage to frames 24 hours after pouring concrete/mortar

4. Finishing hardware materials/ accessories are attached to installed door/window jambs/panels based on specifications

5. Unexpected situations are dealt with according to company rules and regulations

6. Housekeeping is performed according to safety regulations7. Appropriate PPE is used according to safety standards and

regulations CONDITIONS: You must be provided with the following:

• WORKPLACE LOCATION• TOOLS AND EQUIPMENT

HammerMarking ToolsMeasuring ToolsSteel SquareTry-square

• TRAINING MATERIALSLeaning PackagesBond paperBall pensManualsRelated References

Hand SawChalk LineWater Hose LevelPlumb BobPPECircular Saw

ASSESSMENT METHOD

Portfolio

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 32 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 33: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

Learning Experience

INSTALL FABRICATED DOOR/WINDOW JAMBS/PANELS AND PRE-FABRICATED MOLDINGS

Learning Activities Special Instructions• Read Information Sheet

No. 2.3-1 on Door Installation

• Answer Self-Check No. 2.3-1

Compare your answer to the answer key

• Perform Operation Sheet No. 2.3-1 on Installing door

Evaluate your own work using the Performance CriteriaPresent your work to your trainer for evaluationKeep a copy of your work for the next activities

• Read Information Sheet No. 2.3-2 on Door trim

• Read Information Sheet No. 2.3-3 on Door lock Installation

• Perform Operation Sheet No. 2.3-3 on Door Lock Installation

Evaluate your own work using the Performance CriteriaPresent your work to your trainer for evaluationKeep a copy of your work for the next activities

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 33 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 34: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

INFORMATION SHEET NO. 2.3-1DOOR INSTALLATION

Doors, both mill-built and job-built, are installed in the finished door frames as described in the following steps:

Step 1. Cut off the stile extensions, if any.Step 2. Plane the edges of the stiles until the door fits tightly against the

hinge side and clears the lock side of the jamb by about 1/16 inch. Be sure that the top fits squarely to the rabbeted recess and that the bottom swings free of the finished floor by about 1/2 inch. The lock stile of the door must be beveled slightly (Figure 1) so that the edge of the stile will not strike the edge of the door jamb.

Figure 12. Horizontal sections showing closing edge of door

Figure 13. Hanging a door

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 34 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 35: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

Figure 14. Horizontal sections showing hanging edge of door

Step 3. After proper clearances have been made, tack the door in position in the frame and wedge it at the bottom.

Step 4. Mark hinge positions with a sharp-pointed knife on the stile and the jamb. Hinge positions on the stile must be placed slightly higher than the lower door rail and slightly lower than the upper door rail to avoid cutting out part of the door-rail tenons that are housed in the stile. Three measurements must be marked:

• location of the butt on the jamb• location of the butt on the door• thickness of the butt on both the jamb and the door

Step 5. Door butts (or hinges) are mortised into the door frames as shown in Figure 4. Use three butt hinges on all full-length exterior doors to prevent warping and sagging. Place the butts and mortise them with the utmost accuracy so that the door will open and close properly, and so that the door, when open, will not strike the casing. The butt pin must project more than half its thickness from the casing.

Figure 15. Hinge positions

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 35 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 36: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

Figure 16. Door butt (hinge)

Step 6. Using the butt as a pattern, mark the butt dimension on the door edge and face of the jamb.

Step 7. Cut the marked areas, called gains, on the door jambs and door to fit the butts. Use a 1-inch chisel and mallet.

Figure 17. Cutting the housings using the chisel-chopping method, prior to chisel-paring

Gain is the cutout or mortise made to receive a leaf of the hinge. The depth is determined by the hinge's thickness, and the width is determined by the hinge's size.

Setback is the distance that the hinge is placed away from the side of the door, usually 3/16 inch.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 36 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 37: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

Step 8. Test the gains. The butts must fit snugly and exactly flush with the edge of the door and the face of the jamb.

Step 9. Screw half of each of the butt joints on the door and the other three parts on the jamb. Place the butts so that the pins are inserted from the top when the door is hung.

Step 10. Set the door against the frame so that the two halves of the top butt engage. Insert the top pin. Engage and insert pins in the bottom and center butts.

Figure 18. Installing door butts (hinges)

Door Stopsa. When fitting doors, the stops are usually nailed in place temporarily

until the door has been hungb. Stops for doors in single-piece jambs are generally 1/2 inch thick

and 2 inches wide. They are installed with a butt joint at the junction of the side and head jambs.

c. A 45° bevel cut at the bottom of the stop, about 1 to 1 1/2 inches above the finish floor, will eliminate a dirt pocket and make cleaning or refinishing the floor easier.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 37 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 38: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

OPERATION SHEET NO. 2.3.1

Title: Install Door Performance Objective: Given the necessary materials, you should

be able to install door.Supplies and Materials: Door Jamb, Lumber, Door hinge Tools and Equipment: • Hammer

• Marking Tools• Measuring Tools• Wood chisel

• Try-square• Hand saw• PPE• Circular Saw

Steps/Procedure:

1. Plane the edges of the stiles until the door fits tightly against the hinge side and clears the lock side of the jamb by about 1/16 inch. Be sure that the top fits squarely to the rabbeted recess. The lock stile of the door must be beveled slightly so that the edge of the stile will not strike the edge of the door jamb.

2. After proper clearances have been made, tack the door in position in the frame.

3. Mark hinge positions on the stile and the jamb. Hinge positions on the stile must be placed slightly higher than the lower door rail and slightly lower than the upper door rail to avoid cutting out part of the door-rail tenons that are housed in the stile.

4. Door hinges are mortised into the door frames. Place the butts and mortise them with the utmost accuracy so that the door will open and close properly, and so that the door, when open, will not strike the casing. The butt pin must project more than half its thickness from the casing.

5. Using the butt as a pattern, mark the butt dimension on the door edge and face of the jamb.

6. Cut the marked areas, called gains, on the door jambs and door to fit the butts. Use a 1-inch chisel and mallet.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 38 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 39: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

7. Test the gains. The butts must fit snugly and exactly flush with the edge of the door and the face of the jamb.

8. Screw half of each of the butt joints on the door and the other three parts on the jamb. Place the butts so that the pins are inserted from the top when the door is hung.

9. Set the door against the frame so that the two halves of the top butt engage. Insert the top pin. Engage and insert pins in the bottom and center butts.

ACTIVITY: From the given working drawing below, install door on fabricated

door jamb on Job Sheet No. 2.2-2.Note: All measurements are in metric.

Assessment Method:Performance Criteria Checklist

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 39 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 40: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

PERFORMANCE CRITERIA CHECKLISTOPERATION SHEET NO. 2.3.1

Name of Trainee:_________________________________ Date: __________________

CRITERIA YES NO

1. Did plane and square stocks to dimension according to the required specifications with tolerances of + 5mm in tolerance and + 3mm for squareness and evenness?

2. Is the door fitted to jamb allowing for clearances according to specifications

3. Are all parts assembled according to specifications?

4. Are the hinges fitted to door and jamb in line with workplace procedures?

5. Did I use tools and equipment consistent with job requirements?

Hinges fitted to door and jamb in line with workplace procedures.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 40 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 41: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

INFORMATION SHEET 2.3-2DOOR TRIM

Door trim is nailed onto the jambs to provide a finish between the jambs and the wall to cover wedging and spaces between the frame and studs. This trim is called casing. Sizes vary from 1/2 to 3/4 inch thick and from 2 1/2 to 6 inches wide. Most trim has a concave back to fit over uneven plaster. The casing layout depends on the way the side and head casings are to be joined at the corners. The casings are usually set back about 1/4 inch from the faces of the jambs. Care must be taken to make miter joints fit properly.

Door openings are cased up as follows:

Step 1.Leave a margin of 1/4 inch from the edge of the jamb to the casing, all around. Cut one (hinge-side first) of the side casings square and even with the bottom of the jamb. Cut the top or mitered end next, allowing a 1/4-inch margin at the top.

Step 2.Nail the casing onto the jamb, even with the 1/4-inch margin line. Start at the top and work toward the bottom. Use 4d finishing nails along the jamb side and 6d or 8d case nails along the outer edge of the casings. The nails along the outer edge will need to be long enough to go through the casing and into the studs. Set all nail heads about 1/8” below the surface of the wood with a nail set.

Step 3.Apply the casing for the other side and then the head casing.

Figure 19. Door trim and stop

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 41 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 42: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

INFORMATION SHEET NO. 2.3-3DOOR LOCK INSTALLATION

Types of Locks

• Cylinder locks are sturdy, heavy-duty locks designed for installation in exterior doors. They provide high security.

• Tubular locks are light-duty locks. They are used for interior doors on bathrooms, bedrooms, passages, and closets.

Steps in Installing Door Lock (For other type of lock, use lock-set installation instructions)

Step 1. After placing the hinges in position, mark off the position of the lock on the lock stile, 36 inches from the floor level.

Step 2. Hold the case of the mortised lock on the face of the lock stile. With a sharp knife, mark off the area to be removed from the edge of the stile that is to house the entire case.

Step 3. Mark the position of the door-knob hub and the position of the key.

Step 4. Mark the position of the strike plate on the jamb.

Step 5. Bore out the wood to house the lock and the strike plate and mortises.

Step 6. Clean and install the lock set. The strike plate should be flush or slightly below the face of the door jamb. Panic hardware is another type of lock. It is also known as a paretic bar or fire-exit bolt. It is often installed on the exit doors of public buildings. Slight pressure on the touch bar will retract the latch bolts at the top and bottom. Install panic hardware according to the manufacturer's instructions.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 42 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 43: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

Figure 20. Installing lock and strike plate

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 43 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 44: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

OPERATION SHEET NO. 2.3-3

Title: Install Door Knob/ Door LockPerformance Objective: Given the necessary materials, you should

be able to install door knob/lockSupplies and Materials: Installed door frames on jamb (Job Sheet

2.2-2; Operation Sheet No. 2.3-1) Door Knob/Door Lock set

Tools and Equipment: • Hammer• Marking Tools• Measuring Tools• Screw driver

• Saw set• PPE

Steps/Procedure:1. After placing the hinges in position, mark off the position of the

lock on the lock stile, typically 36 inches from the floor level. For this project get the center of the 8” stile.

2. Hold the case of the mortised lock on the face of the lock stile. With a sharp knife, mark off the area to be removed from the edge of the stile that is to house the entire case.

3. Mark the position of the door-knob hub and the position of the key.

4. Mark the position of the strike plate on the jamb.5. Bore out the wood to house the lock and the strike plate and

mortises.

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 44 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 45: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

6. Clean and install the lock set. The strike plate should be flush or slightly below the face of the door jamb.

Assessment Method:Performance Criteria Checklist

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 45 of 46Developed by:Glenn F.

Salandanan Revision # ____

Page 46: CBLM_FABRICATE/INSTALL DOOR & WINDOW JAMBS AND PANELS

PERFORMANCE CRITERIA CHECKLISTOPERATION SHEET NO. 2.3-3

Name of Trainee:_________________________________ Date: __________________

CRITERIA YES NO

1. Did I positioned the pre-fabricated parts according to dimensions and specifications?

2. Did I marked the position of the lock set correctly using the template provided before boring the stock?

3. Did I used the proper tool for the job?

JZGMSATQA

SYSTEM

Carpentry NC III

Fabricate/install door/window

jambs and panels

Date Developed:April 1, 2011

Document No.Issued by:

Page 46 of 46Developed by:Glenn F.

Salandanan Revision # ____