Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
CBB 4023
PLANT DESIGN II
DESIGN OF
MALEIC ANHYDRIDE PRODUCTION PLANT
GROUP 6
AMIRAH RAIHANA BINTI HARIS FADZILAH 11885
MARYAM FARZANAH BINTI MOHD FAUZI 11971
MOHAMMAD ILHAM BIN MAT HUSSIN 12004
MOHAMMAD KHAIRULANAM BIN AZEMAN 12005
NUR SYAFIQAH BINTI ABDUL MANAN 12148
CHEMICAL ENGINEERING DEPARTMENT
UNIVERSITI TEKNOLOGI PETRONAS
SEPTEMBER 2012
1
CERTIFICATION OF APPROVAL
CBB 4023
PLANT DESIGN II
DESIGN OF
MALEIC ANHYDRIDE PRODUCTION PLANT
GROUP 6
AMIRAH RAIHANA BINTI HARIS FADZILAH 11885
MARYAM FARZANAH BINTI MOHD FAUZI 11971
MOHAMMAD ILHAM BIN MAT HUSSIN 12004
MOHAMMAD KHAIRULANAM BIN AZEMAN 12005
NUR SYAFIQAH BINTI ABDUL MANAN 12148
APPROVED BY:
________________________________________
DR. RISZA BINTI RUSLI (Group Supervisor)
DATE: 20TH
SEPTEMBER 2012
CHEMICAL ENGINEERING DEPARTMENT
UNIVERSITI TEKNOLOGI PETRONAS
SEPTEMBER 2012
2
EXECUTIVE SUMMARY
Maleic anhydride is a versatile chemical intermediate used to make unsaturated polyester
resins, lube oil additives, alkyd resins, and variety of other products. Maleic anhydride is
frequently shortened to MAN. In order to produce MAN, the process involved is by the
oxidation of benzene or other aromatic compounds. In this case, we would use the normal
butane (n-butane) as the main feed. Regarding to this process, it will be further explain in the
next chapter as well as the process route that has been chosen in this project.
The main objective of this project is to develop a Maleic Anhydride production plant. The
development of plant should consider all the relevant criteria required in order to make the
most optimize production plant.
Throughout this project, overall document emphasized on the details of the project
background, market survey, site feasibility study, conceptual process design, process control,
safety and loss prevention, waste treatment facility as well as economic evaluation. Location
chosen for MAN production plant is at Kidurong, Sarawak. This is due to the availability of
raw materials, utilities and transportation.
In United States, MAN production rate is estimated to be about 250,000tonnes/annum.
According to the demand, the quantity of MAN is about 223,000tonnes/annum.Thus, the
proposed plant design will be justified based on the economic potential of the process, by
comparing the price of MAN and price of raw materials needed. Hence, overall process
description of this project will be further explained in the next chapters.
3
ACKNOWLEDGEMENT
Alhamdulillah, praised to God for giving us an opportunity to complete this Plant Design
Project I and II courses after struggling with all the problems and challenges in completing
design project for the past several months.
There were about fourteen (14) weeks have been given to us in completing the design project
in Plant Design Project II (CBB4023) course under the supervision of our keen supervisor,
Dr. RiszaRusli. We as the member of this group would like to pass our highest gratitude to
Dr. RiszaRusli for all his guidance and continuous supports throughout the semester. He has
been a very supportive supervisor and willing to share his knowledge, in order to ensure that
we could learn and understand every single thing in this project. Our gratitude is also
extended to PDP 2 coordinator, Dr. Rajashekar and DrMurniMelati for their effort in
arranging and planning the course structures so that all will be run smoothly.
Last but not least, our appreciation is given to our beloved group mates, course mates and
also friends, thanks for all supports and motivations, which helps us a lot to make sure that
this project ended successfully. Not to forget to those who directly or indirectly involved in
giving us the opportunity to learn and work as a team while designing our first plant project.
4
TABLE OF CONTENTS
CERTIFICATION OF APPROVAL .................................................................................................................. 1
EXECUTIVE SUMMARY .................................................................................................................................. 2
ACKNOWLEDGEMENT ................................................................................................................................... 3
TABLE OF CONTENTS ..................................................................................................................................... 4
LIST OF FIGURES .............................................................................................................................................. 8
LIST OF TABLES ................................................................................................................................................ 9
CHAPTER 1: INTRODUCTION...................................................................................................................... 10
1.1 PROJECT BACKGROUND ...................................................................................................................... 10
1.2 PROBLEM STATEMENT ......................................................................................................................... 10
1.3 OBJECTIVES ............................................................................................................................................ 10
1.4 SCOPE OF PROJECT ................................................................................................................................ 11
CHAPTER 2: LITERATURE REVIEW ......................................................................................................... 12
2.1 BACKGROUND OF PRODUCT ............................................................................................................... 12
2.1.1 Product Overview: Maleic anhydride (MAN) ................................................................................. 12
2.1.2 History of MAN Production(Timothy R. Felthouse, 2001) ............................................................. 12
2.2 AVAILABLE & FEASIBLE PROCESS ROUTES TO MAN PRODUCTION ......................................... 14
2.2.1 Benzene partial oxidation to MAN (AP-42, CH 6.14: Maleic Anhydride) ...................................... 14
2.2.2 N-butane partial oxidation to MAN ................................................................................................ 15
2.2.3 MAN fromphthalic anhydride recovery process ............................................................................. 15
2.3 SCREENING AND SELECTION OF PROCESS ROUTES ...................................................................... 16
2.4 PHYSICAL AND CHEMICAL PROPERTIES ......................................................................................... 17
2.5 COST DATA .............................................................................................................................................. 17
2.6 SITE FEASIBILITY STUDY ..................................................................................................................... 19
2.6.1 Introduction .................................................................................................................................... 19
2.6.2 Selection Criteria ............................................................................................................................ 19
2.6.3 Summary of site Characteristic in Each Location .......................................................................... 20
2.6.4 Site Evaluation ................................................................................................................................ 21
2.7 POTENTIAL HAZARDS .......................................................................................................................... 23
2.7.1 Previous Accident On Similar Plant ............................................................................................... 23
2.7.2 Potential Hazards and Control Measures ...................................................................................... 24
2.7.3 Material Safety Data Sheet (MSDS) & Hazard .............................................................................. 26
CHAPTER 3: CONCEPTUAL PROCESS DESIGN AND SYNTHESIS ..................................................... 30
3.1 LEVEL I: PROCESS OPERATING MODE .............................................................................................. 30
5
3.2 LEVEL II: INPUT-OUTPUT STRUCTURE ............................................................................................. 31
3.3 LEVEL III: REACTOR DESIGN AND REACTOR NETWORK SYNTHESIS ....................................... 32
3.3.1 Reactor Conversion Selections ....................................................................................................... 33
3.3.2 Preliminary Reactor Mass Balance ................................................................................................ 34
3.3.3 Reactor Type Selection ................................................................................................................... 36
3.4 LEVEL IV: SEPARATION SYSTEM SYNTHESIS ................................................................................. 38
3.4.1 First Process Route ......................................................................................................................... 39
3.4.2 Second Process Route ..................................................................................................................... 40
3.4.3 Process Route Selection .................................................................................................................. 41
3.5 LEVEL V: HEAT INTEGRATION ........................................................................................................... 41
3.5.1 Introduction to Pinch Analysis........................................................................................................ 41
3.5.2 SPRINT Software ............................................................................................................................ 42
3.5.3 Stream Data Extraction .................................................................................................................. 42
3.5.4 Minimum Temperature Difference .................................................................................................. 43
3.5.5 Maximum Process Heat Recovery .................................................................................................. 43
3.5.6 Heat Exchanger Network ................................................................................................................ 46
3.5.7 Energy-Saving Evaluation .............................................................................................................. 47
CHAPTER 4: INSTRUMENTATION AND CONTROL ............................................................................... 48
4.1 INTRODUCTION ...................................................................................................................................... 48
4.2 DESIGN OF PLANT WIDE CONTROL SYSTEM ................................................................................... 48
4.2.1 Procedures ...................................................................................................................................... 48
4.2.2 Drier Control System ...................................................................................................................... 49
4.2.3 Deisobutanizer Control System....................................................................................................... 49
4.2.4 Reactor Control System .................................................................................................................. 50
4.2.5 Heat Exchanger Control System ..................................................................................................... 52
4.2.6 Absorber Control System ................................................................................................................ 53
4.2.7 Stripper Distillation Column Control System ................................................................................. 54
CHAPTER 5: SAFETY AND LOSS PREVENTION ..................................................................................... 56
5.1 HAZARD AND OPERABILITY STUDIES (HAZOP) ............................................................................. 56
5.1.1 Introduction to HAZOP .................................................................................................................. 56
5.1.2 Study Nodes Selection ..................................................................................................................... 56
5.1.3 HAZOP Analysis ............................................................................................................................. 57
5.2 PLANT LAYOUT ...................................................................................................................................... 65
5.2.1 Site Layout ...................................................................................................................................... 65
5.2.2 Non-Process Area ........................................................................................................................... 65
5.2.3 Process Area ................................................................................................................................... 66
5.2.4 Assembly point ................................................................................................................................ 68
5.2.5 Emergency Exit ............................................................................................................................... 69
5.3 PLANT LAYOUT CONSIDERATION FACTORS .................................................................................. 69
6
CHAPTER 6: WASTE TREATMENT ............................................................................................................ 72
6.1 INTRODUCTION ...................................................................................................................................... 72
6.2 WASTE MINIMIZATION ......................................................................................................................... 73
6.3 WASTE AUDIT ......................................................................................................................................... 73
6.4 EFFLUENT DISCHARGE STANDARD AND REQUIREMENTS ......................................................... 74
6.4.1 Purpose of Effluent Standards ........................................................................................................ 74
6.4.2 Liquid waste .................................................................................................................................... 75
6.4.3 Gaseous Waste ................................................................................................................................ 76
6.4.4 Solid waste ...................................................................................................................................... 76
6.5 TREATMENT STRATEGY ...................................................................................................................... 76
6.6 SCREENING PROCESS ............................................................................................................................ 80
6.6.1 Aerated Grit Removal ..................................................................................................................... 80
6.6.2 pH Stabilizer ................................................................................................................................... 80
6.6.3 Equalization Tank ........................................................................................................................... 80
6.6.4 Coagulation Tank ........................................................................................................................... 81
6.6.5 Clarifier .......................................................................................................................................... 81
6.6.6 Sludge Dewatering .......................................................................................................................... 81
6.6.7 Mechanical Sludge Thickener ......................................................................................................... 81
6.6.8 Sludge Storage ................................................................................................................................ 81
6.6.9 Disinfection ..................................................................................................................................... 82
6.6.10 Biopond ...................................................................................................................................... 82
6.7 GAS TREATMENT ................................................................................................................................... 82
6.8 SOLID HANDLING TREATMENT .......................................................................................................... 85
6.9 SCHEDULED WASTE .............................................................................................................................. 86
CHAPTER 7: PROJECT ECONOMICS AND COST ESTIMATION ......................................................... 87
7.1 INTRODUCTION ...................................................................................................................................... 87
7.1.1 Capital Investment .......................................................................................................................... 87
7.1.2 Total Equipment Cost (TEC) .......................................................................................................... 88
7.1.3 Fixed Capital Investment ................................................................................................................ 88
7.1.4 Estimation of Total Operating Cost ................................................................................................ 89
7.1.5 Gross Profit .................................................................................................................................... 89
7.2 PROFITABILITY ANALYSIS .................................................................................................................. 90
7.2.1 Start-up Period ............................................................................................................................... 90
7.2.2 Depreciation ................................................................................................................................... 90
7.2.3 Cash Flow Estimation ..................................................................................................................... 91
7.2.4 Net Present Worth ........................................................................................................................... 92
7.2.5 Internal Rate of return .................................................................................................................... 92
7.2.6 Rate of Return (ROR) Estimation ................................................................................................... 92
7.2.7 Net Present Value or Worth (NPV) Estimation............................................................................... 92
7
7.2.8 Pay Back Time ................................................................................................................................ 93
7.3 DISCUSSIONS .......................................................................................................................................... 93
CHAPTER 8: CONCLUSION & RECOMMENDATION ............................................................................. 94
8.1 CONCLUSION .......................................................................................................................................... 94
8.2 RECOMMENDATION .............................................................................................................................. 95
REFERENCES ................................................................................................................................................... 96
APPENDICES ..................................................................................................................................................... 98
8
LIST OF FIGURES
FIGURE 1: THE MAIN PROCESS TECHNOLOGY FROM SCIENTIFIC DESIGN ...................... 14
FIGURE 2: REACTIONS FOR PARTIAL OXIDATION OF N-BUTANE TO MAN ...................... 15
FIGURE 3: GLOBAL DEMAND OF MAN ACCORDING TO REGION(MALEIC ANHYDRIDE . 18
FIGURE 4: PRODUCTION CAPACITY OF MAN ACCORDING TO REGION, 2000 .................. 18
FIGURE 5: KIDURONG INDUSTRIAL AREA ........................................................................... 23
FIGURE 6: SCHEMATIC PROCESS OF AMMONIA .................................................................. 31
FIGURE 7: HEURISTIC METHOD: ONION MODEL ................................................................. 38
FIGURE 8: FIRST PROCESS ROUTE ........................................................................................ 40
FIGURE 9: SECOND PROCESS ROUTE .................................................................................... 41
FIGURE 10: COMPOSITE CURVE FOR MAXIMUM HEAT RECOVERY: ................................. 44
FIGURE 11: PROBLEM TABLE ALGORITHM BY SPRINT SOFTWARE .................................. 45
FIGURE 12: HEAT EXCHANGER NETWORK .......................................................................... 46
FIGURE 13: SELECTED STUDY NODES CONNECTED TO REACTOR .................................... 57
FIGURE 14: ISOBUTANE STORAGE TANK ............................................................................. 77
FIGURE 15: BLOCK DIAGRAM OF WASTEWATER TREATMENT PLANT ............................. 78
FIGURE 16: FLOW SHEET OF WASTEWATER TREATMENT PLANT..................................... 79
FIGURE 17: NITROGEN SEPARATOR ..................................................................................... 84
FIGURE 18: WASTE OF STREAM 18 (S18) .............................................................................. 85
FIGURE 19: CASH FLOW DIAGRAM ....................................................................................... 91
FIGURE 20: PAYBACK TIME ................................................................................................... 93
9
LIST OF TABLES
TABLE 1: WORLD MAN CAPACITY BY REACTOR TYPE (MAN WORLD SURVEY, 1992) ... 13
TABLE 2: CONTRIBUTING FACTORS TO OPERABILITY AND ECONOMY ASPECTS .......... 20
TABLE 3: WEIGHTAGE CRITERIA IN DECIDING SITE LOCATION ...................................... 21
TABLE 4: WEIGHTAGE TABLE ON SITES .............................................................................. 22
TABLE 5: ANALYSIS OF POTENTIAL HAZARDS ................................................................... 25
TABLE 6: HAZARD ANALYSIS ............................................................................................... 26
TABLE 7: GUIDELINES FOR BATCH AND CONTINUOUS PROCESS ..................................... 30
TABLE 8: PRODUCTION OF MALEIC ANHYDRIDE FROM N-BUTANE ................................. 33
TABLE 9: PRELIMINARY REACTOR MASS BALANCE .......................................................... 34
TABLE 10: MASS BALANCE WITH RECYCLE ........................................................................ 35
TABLE 11: ADVANTAGES AND DISADVANTAGES OF PACKED BED REACTOR (SMITH) . 36
TABLE 12: ADVANTAGES AND DISADVANTAGES OF FLUIDIZED BED REACTOR ........... 36
TABLE 13: STREAM DATA EXTRACTED ............................................................................... 42
TABLE 14: OPTIMUM TMIN IN DIFFERENT INDUSTRIES (PINCH ANALYSIS).................... 43
TABLE 15: UTILITIES REQUIRED BEFORE HEAT INTEGRATION ........................................ 44
TABLE 16: UTILITIES REQUIRED AFTER HEAT INTEGRATION .......................................... 45
TABLE 17: COMPARISON OF UTILITY REQUIREMENT BEFORE AND AFTER HI ............... 47
TABLE 18: DRIER CONTROL SYSTEM DETAILS ................................................................... 49
TABLE 19 : DEISOBUTANIZER CONTROL SYSTEM DETAILS .............................................. 50
TABLE 20: REACTOR CONTROL SYSTEM DETAILS ............................................................. 52
TABLE 21: COOLER CONTROL SYSTEM DETAILS ................................................................ 53
TABLE 22: HEAT EXCHANGER CONTROL SYSTEM DETAILS ............................................. 53
TABLE 23: GAS ABSORBER, C-301 CONTROL SYSTEM DETAILS ........................................ 54
TABLE 24: DISTILLATION COLUMN CONTROL SYSTEM ..................................................... 55
TABLE 25: STUDY NODES IN HAZOP ANALYSIS .................................................................. 56
TABLE 26: STUDY NODE #1 .................................................................................................... 58
TABLE 27: STUDY NODE #2 .................................................................................................... 60
TABLE 28: STUDY NODE #3 .................................................................................................... 62
TABLE 29: RECOMMENDED MINIMUM CLEARANCE ........................................................... 70
TABLE 30: WASTE STREAMS PROPERTIES ........................................................................... 74
TABLE 31: ENVIRONMENTAL QUALITY (EXTRACT) ........................................................... 75
TABLE 32: PLANT WASTEWATER AND STANDARD B VALUES OF EQA ............................ 76
TABLE 33: METHOD OF REMOVAL ACCORDING TO WASTE COMPONENT ....................... 76
TABLE 34: SUMMARY OF LIMITATIONS FOR THE GASEOUS TREATMENT STRATEGY ... 82
TABLE 35: DISPOSAL METHODS OF SOLID WASTE ............................................................. 85
TABLE 36: TOTAL EQUIPMENT COST ................................................................................... 88
TABLE 37: CAPITAL INVESTMENT FOR START-UP PERIOD ................................................ 90
TABLE 38: CUMULATIVE CASH FLOW .................................................................................. 92
10
CHAPTER 1: INTRODUCTION
1.1 PROJECT BACKGROUND
The final year design project team has been assigned to design a Maleic Anhydride
production plant using mixed butane as the raw material. For this semester, the team needs to
incorporate safety aspects, site selection, conceptual design, material and energy balance,
heat integration and preliminary economic evaluation in the early design of the plant. Each
team is also assigned a lecturer from the Chemical Department as a supervisor to guide the
students in designing the plant.
1.2 PROBLEM STATEMENT
Maleic anhydride (MAN) is used in the production of unsaturated polyester resins. These
laminating resins have a high structural strength and good dielectric properties. These
characteristics makes maleic anhydride eligible for a variety of applications in automobile
bodies, molded boats, building panels, , chemical storage tanks, lightweight pipe, machinery
housings, furniture, luggage, and bathtubs. Maleic anhydride is also used to produce other
chemicals including fumaric acid, agricultural chemicals, alkyd resins, lubricants,
copolymers, plastics, and succinic acid.
The main feed stocks for MAN industry are benzene and normal butane. However, due to its
increasing cost of benzene and chemical hazard of benzene, the industry turned to butane as
the main feed stock because of its fewer hazards compared to benzene, low cost and abundant
source availability.
The team is assigned the task of designing a Maleic Anhydride production plant using a pre-
specified composition of mixed butane as the raw material. The capacity of the plant must be
determined based on the demand and worldwide market for Maleic Anhydride.
1.3 OBJECTIVES
The objective of this project is to develop a Maleic Anhydride production plant. The plant
must be cost-effective, considers all of the desired criteria in addition to dealing with relevant
issues. The team needs to recommend the best possible design, which will ultimately
convince panel of juries to verify the new plant. The objectives of this design project include
the following:
11
To integrate chemical engineering skills and knowledge in a detailed design of a
chemical plant.
To apply appropriate design codes in a detailed design work
To present a piping and instrumentation diagram (P&ID) and control strategy
packages
To perform detailed economic evaluation of the proposed chemical plant
To generate cost effective process options while maintaining operability, safety
and environment friendliness of the design.
1.4 SCOPE OF PROJECT
The scopes of work for FYDP II are as follows:
Making the necessary decisions, judgements and assumptions in design problems.
Performing the instrumentation and control study
Performing the process design of the major process units.
Performing the mechanical design of the major process units.
Performing the economic evaluation including capital cost estimation and
manufacturing cost estimation.
Considering the environmental and safety issues related to the plant. Material
safety data sheet (MSDS) for all the chemicals involved must be part of the safety
and environmental discussion.
Utilising the blend of hand calculations, spreadsheets, mathematical computer
packages, and process simulators to design a process
Preparing the group and individual reports as per standard format and conducting
the oral presentations.
12
CHAPTER 2: LITERATURE REVIEW
2.1 BACKGROUND OF PRODUCT
2.1.1 Product Overview: Maleic anhydride (MAN)
Maleic anhydride is a versatile molecule that is used in many applications which requires a
number of functionalities and properties (Timothy R. Felthouse, 2001). It is considered an
excellent joining and cross linking agent due to its three active sites (one double bond and
two carboxyl groups). Besides that, due to its cross linking abilities, it is widely used in the
manufacturing of unsaturated polyester resins. Maleic Anhydride is also one of the important
intermediate in the fine chemical industry, mainly in the manufacturing of agricultural
chemicals and additives for lubricating oil. In addition, it also serves as a component for
several copolymers in the polymer sectors (Lohbeck, Haferkorn, Fuhrmann, & Fedtke, 2005).
In 1928, Diels and Alder worked on a reaction between Maleic Anhydride and 1,4-butadiene
and the work was later awarded the Nobel prize in 1950. The starting of the usage of Maleic
Anhydride in the pesticide and pharmaceutical industries was because of the studied reaction.
Several examples of the specialty chemicals that can be prepared from Maleic Anhydride
includes tartaric acid, diethyl and dimethyl succinate, malic acid, glyoxylic acid,
diisobutylhexahydrophthalate (DIBE), methyl tetrahydrophthalic anhydride esters and
dodecene succinic anhydride. (Lohbeck, Haferkorn, Fuhrmann, & Fedtke, 2005)
2.1.2 History of MAN Production(Timothy R. Felthouse, 2001)
Maleic anhydride was initially commercialized in the early 1930s through the selective
oxidation of benzene. The usage of benzene as the feed for the production of maleic
anhydride was dominant until 1980s. Several processes were introduced with the common
ones that were from Scientific Design. By then, there were also small amount of maleic acid
being produced as by-product in the production of phtalic anhydride that can be oxidised into
maleic anhydride.
However, the usage of benzene started to change and was replaced by n-butane in 1974
because of its toxic effects and economic aspects. The recognition of benzene as hazardous
material and deemed carcinogen substance with the rapid increase in the benzene price
opened up the search for alternative process technology specifically in the
13
United States. Later, the first commercial production of maleic anhydride from butane was
established at Monsato’s J. F. Queeny plant in the year 1974.
After 1980s, the United States maleic anhydride industries underwent a conversion of
feedstock from benzene to butane. But, during the early years, the conversion to butane as
feedstock had its limitation whereby the early butane-based catalyst were not active and
selective enough for a better conversion of benzene-based plant without a significant loss of
capacity production.
However, further enhanced catalyst was developed by Monsanto, Denka, and Halcon which
led to the world’s first butane-to-maleic anhydride plant which was started up by Monsanto in
1983. The plant incorporated an energy efficient solvent-based product collection and
refining system. It was then the largest maleic anhydride production facility and later it
undergone debottlenecking project from a capacity of 59,000 tons per year to 105,000 tons
per year in 1999.
By mid-1980s, United States 100% of maleic anhydride production were using butane as
feedstock due to advances in catalyst technology, increased regulatory pressures, and
continuing cost advantages of butane over benzene.
Meanwhile, Europe has also converted from benzene-based to butane-based maleic anhydride
technology starting from the construction of new butane based facilities by CONDEA-
Hunstman, Pantochim and Lonza. The growth in the industry turned to the butane-to-maleic
anhydride route, usually at the expense of benzene-based production.
Table below shows the worldwide maleic production capacity broken down into fixed-bed
benzene, fixed-bed butane, fluidized-bed butane, andphthalic anhydride (PA) co-product.
TABLE 1: WORLD MAN CAPACITY BY REACTOR TYPE (MAN WORLD SURVEY, 1992)
1993 Actual 2000 Actual
Reactor (Feed) Kiloton / year, % Kiloton / year, %
Fixed Bed (butane) 369 43.0 704 51.8
Fixed Bed (benzene) 325 37.9 388 28.5
Fluid Bed (butane) 127 14.8 217 16.0
Fixed Bed (PAcoproduct) 37 4.3 50 3.7
Total 858 100.0 1359 100.0
14
It can be seen from the table that both fixed-bed and fluidized-bed butane routeshave
increased dramatically with the fixed-bed route adding 336 kiloton/year capacity compared to
90 kiloton/year for the fluid-bed process. Only a few newer benzene-based fixed-bed
processes have been built with a difference of 63 kiloton/year since the early1980s and the
reason it was built was due to limited resource of butane.
2.2 AVAILABLE & FEASIBLE PROCESS ROUTES TO MAN PRODUCTION
Generally, there are 3 routes that can be considered for the commercial production of MAN.
The 3 routes are given below together with their chemical reactions:
2.2.1 Benzene partial oxidation to MAN (AP-42, CH 6.14: Maleic Anhydride)
FIGURE 1: THE MAIN PROCESS TECHNOLOGY FROM SCIENTIFIC DESIGN
Vaporized benzene and air are mixed and heated before entering the tubular reactor. Inside
the reactor, the benzene/air mixture is reacted in the presence of a catalyst that contains
approximately 70 percent vanadium pentoxide (V2O5), with usually 25-30% molybdenum
trioxide (MoO3), forming a vapor of MA, water, and carbon dioxide. The vapor, which may
also contain oxygen, nitrogen, carbon monoxide, benzene, maleic acid, formaldehyde, formic
acid, and other compounds from side reactions, leaves the reactor and is cooled and partially
condensed so that about 40 percent of the MA is recovered in a crude liquid state.
The effluent is then passed through a separator that directs the liquid to storage and the
remaining vapor to the product recovery absorber. The absorber contacts the vapor with
water, producing a liquid of about 40% maleic acid. The 40% mixture is converted to MA,
usually by azeotropic distillation with xylene. Some processes may use a double-effect
vacuum evaporator at this point. The effluent then flows to the xylene stripping column
where the xylene is extracted. This MA is then combined in storage with that from the
separator. Themolten product is aged to allow color-forming impurities to polymerize. These
are then removed in a fractionation column, leaving the finished product.
15
2.2.2 N-butane partial oxidation to MAN
FIGURE 2: REACTIONS FOR PARTIAL OXIDATION OF N-BUTANE TO MAN
Several process technologies for butane-to-maleic anhydride was designed including
Huntsman process, Scientific Design process, Technobell Limited process, Alusuisse maleic
anhydride (ALMA) process, and Du Pont moving bed recycle based process.
Butane and compressed air are mixed and fed adiabatic reactor, where butane reacts with
oxygen to form maleic anhydride. The reaction is exothermic, therefore either a fluidized bed
reactor or a packed bed reactor with heat removal to stay close to isothermal. The reactor
effluent is cooled and sent to packed bed absorber, where it is contacted with water to remove
the light gases and all of the maleic anhydride reacts to form maleic acid. The vapor effluent,
which consists of non-condensable must be sent to an after-burner to remove any carbon
monoxide prior to venting to the atmosphere. The liquid effluent is then cooled and flashed at
101 kPa and 120°C. The vapour effluent after flashed is sent to waste treatment where else
the liquid effluent, is sent to another reactor where maleic acid is broken down to maleic
anhydride and water. The reactor effluent is then sent to distillation column where maleic
anhydride and water are separated. The distillate from the distillation column is sent to waste
treatment (Production of Maleic Anhydride).
2.2.3 MAN fromphthalic anhydride recovery process (MAN as a byproduct of the
production of phthalic anhydride)
C8H10 + 7.5O2 C4H2O3 + 4H20 +4CO2∆H = -2518.5 kJ/mole
16
The process technology involved in this process route includes LURGI - BASF Phthalic
Anhydride Process and Technobell Limited Process.
Hot air and vaporized o-xylene are mixed and sent to a packed bed reactor. Most of the o-
xylene reacts to form phthalic anhydride, but some complete combustion of o-xylene occurs
and some maleic anhydride is formed. The reactor temperature is controlled by a molten salt
loop. The reactor effluent enters a complex series of devices known as switch condensers.
The feed to the switch condensers may be no higher than 180°C; hence, the reactor effluent
must be cooled. The net result of the switch condensers is that all light gases and water leave
through the top while small amounts of both anhydrides, and the phthalic anhydride and
maleic anhydride leave in the bottom. The bottom stream is then purified to obtain maleic
anhydride. (Production of Phthalate Anhydride from O-xylene).
2.3 SCREENING AND SELECTION OF PROCESS ROUTES
Only two routes are compared which are the benzene route and the n-butane route since the
0-xylene route is only the recovery of maleic anhydride as byproduct.
N-butane route is chosen over the benzene route mainly due to benzene’s higher hazard
properties compared to n-butane and the rapid increase in benzene’s price over n-butane. In
addition, if viewed from the compound’s molecular properties, n-butane route still is a better
route. The reason is because there are four carbon atoms in product maleic anhydride per6
carbon atoms in benzene. Therefore, the atom efficiency for the carbon atom is 4/6 x 100% =
66.7%. In the n-butane route, there are four carbon atoms in n-butane per four carbon atoms
in maleic anhydride thus giving 100% atom efficiency. If mass efficiency is considered, then
the mass of the product is compared to the mass of the raw materials. The molecular weight
of maleic anhydride is 98. For the n-butane route, we need 1 mole of n-butane (molecular
weight 58) and 3.5 moles of oxygen (total mass of 3.5 x 32 = 112.) Thus the total mass of raw
materials needed is 170. The mass efficiency of the n-butane route is therefore 98/170 or
57.6%. By a similar calculation, we can show that the mass efficiency of the benzene route is
only 44.4%.
As can be seen, n-butane is favourable to benzene in comparison of both atom and mass
economy.
17
2.4 PHYSICAL AND CHEMICAL PROPERTIES
Properties
Maleic
Anhydride
(MAN)
Propane
Iso-butane N-butane Isopentane
Formula C2H2(CO)2O C3H8 C4H10 C4H10 C5H12
Chemical
structure
Molecular
weight
(g/mol)
98.06
44.1 58.12 58.12 72.15
Density
(g/ml) 1.48
0.584-42
0.6011 0.61972
Melting
point(◦C) 52.8
-188 -138 -138 -159.9
Boiling
Point(◦C) 202
-42.1 -11.7 -0.5 27.8
Flash
point(◦C) 103
-104 -87 -60 -56
Appearance
White
crystal Colourless
gas
Colourless
gas
Colourless
gas
Colourless
liquid
2.5 COST DATA
In building a production plant, initial capital investment as well as cost for operation and
maintenance needs to be considered. According to Silla (2003), there are three components
that contribute to the total production cost, which are direct costs, indirect costs and general
costs. Direct costs include feedstock supply, utilities supply and labour cost (Silla, 2003).
Indirect costs cover expenses like taxes, insurance and plant overhead costs (Silla, 2003). On
the other hand, general costs include administrative costs, marketing costs, etc. (Silla, 2003).
For the early stage of the market research, studies on the current market of the main product
(MAN) and the different feeds are performed. Research on the capital investment for existing
production plant is also presented in this paper.
MAN is mainly used as a raw material in the production of polyester resins, which are largely
used in boating, automobile and construction industries. Recently, a growing market of MAN
is observed in the production of butanediol, which is used in the synthesis of plastics and as a
18
textile additive. Apart from that, it is also been greatly used in the manufacture of alkyd
resins, a significant material in paints and coatings. Other applications that make use of MAN
include manufacturing of agricultural chemicals, lubricant additives and copolymers.
FIGURE 3: GLOBAL DEMAND OF MAN ACCORDING TO REGION(MALEIC ANHYDRIDE, 2011)
FIGURE 4: PRODUCTION CAPACITY OF MAN ACCORDING TO REGION, 2000 (TIMOTHY R.
FELTHOUSE, 2001)
In relation of the market demand and production capacity according to region, demand in
most regions is proportional to the production capacity (Maleic Anhydride, 2011). For an
instance, the highest demand of MAN comes from Asia (specifically China), and Asia also
has been the topmost producer of MAN (Maleic Anhydride, 2011). In United States, the price
of MAN is reported to be between USD 1,922 – 2,055 per tonne in 2011 (Timothy R.
Felthouse, 2001). The production capacity in US is reported to be up to 250,000tonnes/year
while their demand is 223,000 tonnes/year (Timothy R. Felthouse, 2001).
North America 23%
South & Central America
3%
West Europe 34%
East & Central Europe
4%
Asia 35%
Africa 1%
North America
South & Central America
West Europe
East & Central Europe
Asia
Africa
19
Globally, among companies that supply MAN are Bartek Ingredients Inc., BASF AG,
LANXESS Corporation and Huntsman Corporation (Jose, 2008). While in Asia, Changzhou
Yabang Chemical Co Ltd, Danyang Chemical Plant, and Thirumalai Chemicals Ltd are the
companies with MAN production (Jose, 2008). One company that produces MAN in
Malaysia is TCL Industries (Malaysia) SdnBhd (Jose, 2008). TCL Industries Malaysia is a
company under Thirumalai Chemicals Ltd that produces worldwide supply of up to 60,000
tonnes per year MAN (Maleic Anhydride, 2011).
Considering the world market outlook, China is found to be the main region for future
growth. This is due to the rise in demand of unsaturated polyester resin which requires MAN
for the production. Besides than Middle East, other countries such as Saudi Arabia and UAE
also are showing growth market and an increase in import requirements (ICIS,2002).
In a plant design study by Woril Turner Dudley (2012), to build a plant that produce about
USD 500,000 for a kmol product/hour MAN requires a capital investment of USD
18,161,381. This value can provide cost estimation in the future plant design for this project.
2.6 SITE FEASIBILITY STUDY
2.6.1 Introduction
Choosing strategic plant location is one of the most crucial decisions needs to be done. The
construction of a chemical plant requires a preliminary feasibility study to be done in order to
make certain that the proposed Kidurong Industrial Estate is feasible, economically and
environmentally. The location of the plant site takes relatively high precedence and it mainly
depends on the availability of feedstock, cost of production, marketing of the products, land
availability and also the infrastructure. The right location allows maximum profit with a
minimum operating cost and allowance for future expansion.
2.6.2 Selection Criteria
Based on the study done in the selecting strategic plant location, there are several factors that
should be taken into consideration when undertaking the process of selecting a suitable site.
There are two major factors that contribute to the operability and economic aspects of a site
location for a plant, which are the primary factor and specific factor.
20
TABLE 2: CONTRIBUTING FACTORS TO OPERABILITY AND ECONOMY ASPECTS
2.6.3 Summary of site Characteristic in Each Location
Five major locations are identified to be considered in the site selection for the construction
of Maleic Anhydride production plant. The locations are:
i) Kidurong Industrial Area
ii) Kota Kinabalu Industrial Park
iii) PasirGudang Industrial Estate
iv) PengerangIntergrated Petroleum Complex
v) Kerteh Petrochemical Complex
The characteristics of each location are listed based on the primary and specific factors which
had been justified before. Appendix 3 shows the summary of the site characteristics for each
location.
Primary Factors Specific Factors
Raw material supply for industry Availability of low cost labor
and services
Reasonable land price Safety and environmental
impacts
Source of utilities, such as electricity, water
and etc.
Incentives given by
government :
Pioneer Status
Investment Tax Allowance
(ITA)
Effluent and waste disposal
facilities
Climate status
Wind
Rainfall
Temperature
Relative Humidity
Transportation facilities
Local community
consideration
21
2.6.4 Site Evaluation
The evaluation of each location is done based on weightage system. Table 3 below shows the
range of weighted marks for each identified criteria. The site location is evaluated based on
the guidelines.
TABLE 3: WEIGHTAGE CRITERIA IN DECIDING SITE LOCATION
Factors 7-10 Marks 4-6 Marks 0-3 Marks
Supply of raw material Able to obtain large
supply locally thus
saving on import cost
Having long pipeline
networks for
transportation of raw
material
Source of raw
materials from
neighbouring states or
countries with the
distance not exceeding
80km.
Uses a pipeline system
as well.
Unable to obtain raw
material from close
sources with the
distance exceeding
80 km
Forced to import
from foreign
countries
Uses a pipeline
system as well.
Price and Area of Land Land area exceeding
60 hectares
Price of land below
RM 20 psm
Land area below 60
hectares
Price of land more
than RM 20 psm
Land area below 40
hectares
Price of land more
than RM 30 psm
Local Government
Incentives
Incentives from the
local organization of
country development
Incentives from
special company
Incentives from the
local organization of
country development
No incentives from
the local organization
of country
development
Transportation Complete network
and well maintained
highways,
expressways and
roads
International Airport
facilities access to the
main location around
the world
Location near to
international port
which import and
export activities
Reliable railway lines
to remote areas not
accessible by roads
Good federal road and
highway system
Limited railway
system access
More distant from the
ports
Airport facilities
which may not have
international flight
facilities- only
providing domestic
flight
Average road system
No highways or
expressway system in
close proximity
No railway system
Very distant from the
ports or harbours
Distant form the
nearest airport more
than 100km away
22
TABLE 4: WEIGHTAGE TABLE ON SITES
Criteria
Kidurong
Industrial
Site
Kota
Kinabalu
Industrial
Park
PasirGudang
Industrial
Estate
PengerangIntergrated
Petroleum Complex
Kerteh
Integrated
Petrochemical
Complex
Supply of Raw
Material 10 8 9 9 10
Price 8 1 9 10 4
Area of Land 10 7 4 9 4
Local
Government
Incentives
9 8 8 8 8
Transportation 9 8 6 6 10
Workers Supply 10 7 10 9 98
Utilities, water
and electricity 8 8 9 7 9
Type of industrial
and its location 10 3 5 10 10
Waste water
disposal 10 8 10 9 9
Total 84 58 70 86 73
Percent (%) 84 58 70 86 73
Based on the weight matrix, the selected location for MAN plant construction is Kidurong
Industrial site. The location is justified to be the most suitable and strategic compared to the
others based on all the criteria.
Some of the attractive information of the location is as followed:
Kidurong Industrial site is located only 20 km with approximately 15 minutes from
Bintulu Town. It is identified as the main industrial core of the whole Bintulu area
which is one of the attractions of multinationals oil and gas companies.
It consist of a few established multinational oil and gas company such as MLNG
complex, which is deemed as the world largest single gas manufacturing complex
apart from Shell and Murphy.
23
FIGURE 5: KIDURONG INDUSTRIAL AREA
Include related infrastructure such as Bintuludeepwater Port, Bintulu Airport and a
few options of power supply.
The available MLNG Complex is targeted as the main supply of raw material for
Malefic Anhydride production plant.
The land price is cheap and reasonable compared to the other established locations which are
around RM77.42. The available land is also huge and sufficient enough for the construction
of MAN plant.
2.7 POTENTIAL HAZARDS
2.7.1 Previous Accident On Similar Plant
The plant was located in Indonesia. The fire incident was started on 20th
January 2004. This
chemical factory was doing processing which involved ammonia and maleic anhydride. The
plant employs some 450 people and makes chemicals used in plastics.
The blasts were sparked by a fire in several tanks. The fire caused a leak of maleic anhydride
from the top of a tank, which ignited, increasing the intensity of the fire. The fire was also
threatening some ammonia tanks. Flames were 50 meter high and smoke could be seen
several kilometers away. The blaze destroyed at least 5 nearby homes and more than 50 fire
trucks were deployed at the height of the fire but only masked firefighters could approach the
blaze. The state electricity company cut power to the area. The company shut down pipeline
that supplied gas to the industrial complex. The fire was caused by an overheated machine.
Fifty-six were injured. Most of them suffered serious burns. The death toll in the devastating
fire at a chemical plant increased to three after another victim died from severe burns in
24
hospital. A 36-year-old man sustained burns to more than 90% of his body and at last died
after several days. The man was one of the 13 victims being treated in a hospital, who
suffered more severe burns in the fire. Three other victims died hours after the fire engulfed
the chemical plant. Among them were the plant and production director. Police has evacuated
hundreds residents within 1 kilometer of the plant. More than 100 firemen and police battled
to put out the blaze. There was the sound of at least five explosions before a column of black
smoke rose into the sky. The resulting fire lasted until 2330 hours while thick black smoke
covered the sky until 1800 hours. The people have complained of eye irritations from a huge
pall of smoke. Hundreds of workers are taking indefinite vacations. It has been discovered
that the communities living in the surrounding area, have complained about water
contamination in their wells. The water has a foul smell and when used for bathing the
community reports it causes itchiness.
2.7.2 Potential Hazards and Control Measures
Production of MAN from normal butane requires a process with high pressure and
temperature. In addition to that, the reactant used in this petrochemical industry is highly
flammable and reactive with oxidizing agent. These conditions made the process plant
become relatively hazardous compared to other industries like food and manufacturing
industries. Potential hazards are grouped according to its common source, and the hazards
effects and control measures are summarized in the table below.
TABLE 5: ANALYSIS OF POTENTIAL HAZARDS
Source Potential Hazards Effects Control Measures
Chemical Tank, Storage &
Transportation
Dangerous chemical reaction,
overpressure, temperature above flash
point, corrosion of storage tank, release of
toxic fume, chemical spillage
Fire
Explosion
Air pollution
Land pollution
Replace hazardous chemical with a less hazardous
alternative
Isolation of incompatible chemicals
Installation of pressure safety valve
Filtration of toxic fume
Warning signage/ label for chemicals
Store chemical in well-ventilated area
Reactor Overpressure, overheat, sudden
temperature rise Explosion
Utilize overpressure relief protection
Implement control system to prevent overheat and
overpressure condition
Installation of pressure safety valve
Distillation Column High pressure Flooding
Sequence the distillation process for a minimum flow of
non-key components
Utilize overpressure relief protection
Heat Transfer Overpressure, fouling, overflow of
cooling or heating medium
Tube rupture
Leaking
Contamination of
liquid
Thermal shock
Utilize overpressure relief protection
Substitution to a less hazardous cooling or heating
medium
Use control valve to prevent thermal shock
Utilities (Electricity, gas, water,
etc.) Short circuit, ignition Fire
Explosion
Ensure proper connections and maintenance for
electrical components
Keep flammable material away from ignition source
Layout Unsafe layout (poor arrangement, limited
space to perform safe work) Create less
conducive, accident-
prone workplace
Ensure safe and practical design of process plant,
considering safe operational sequence and future
expansion
Separate process and non-process area.
Ensure proper ventilation
Location Natural disaster, approval from local
community
High risk of disaster
Pollution affecting
community (noise,
air, etc.)
Selection of site with minimal risk of natural disaster
Keep safe distance between the plant site and the local
community
Environment Untreated waste water Water pollution Develop a treatment system for waste water
2.7.3 Material Safety Data Sheet (MSDS) & Hazard
TABLE 6: HAZARD ANALYSIS
Chemicals Flash
point
Auto-Ignition
Temperature Fire & Explosion Reactivity Symptoms / Effects
Maleic
Anhydride 102
oC 477
oC
Combustible when exposed to heat
or flame. Material in powder form,
capable of creating a dust explosion.
When heated to decomposition it
emits acrid smoke and irritating
fumes.
Reactive with oxidizing
agents, reducing agents,
acids, moisture. Slightly
reactive to reactive with
metals, alkalis.
Exposure will cause asthma,
dermatitis and pulmonary
oedema; effects may be delayed.
Tumorigen.
n-butane -
60.15oC
286.85oC
Extremely flammable in the
presence of following materials or
conditions: open flames, sparks and
static discharge and oxidizing
materials.
The product is stable.
Contact with rapidly expanding
gas may cause burns and or
frostbite. Acts as a simple
asphyxiant.
Propane -104oC 450
oC
Explosive air-vapor mixtures may
form if allowed to leak to
atmosphere.
The product is stable.
Higher concentrations may cause
dizziness and unconsciousness
due to asphyxiant. Liquid can
cause burns and frostbite if in
direct contact with skin.
27
Chemicals Flash
point
Auto-Ignition
Temperature Fire & Explosion Reactivity Symptoms / Effects
iso-butane -82.8oC 460
oC
Flammable liquid and gas
under pressure. Form
explosive mixtures with air
and oxidizing agents.
Stable. Avoid from high
temperature and incompatible
materials such as oxidizing
agents.
May be mildly irritating to
mucous membranes. At high
concentrations, may
cause drowsiness. At very high
concentrations, may act as an
asphyxiant and cause headache,
drowsiness, dizziness, excitation,
excess salivation, vomiting, and
unconsciousness. Lack of oxygen
can kill.
isobutene -76oC 465
oC Extremely flammable.
Can form explosive mixture
with air. May react violently
with oxidants.
In high concentrations may cause
asphyxiation. Symptoms may
include loss of mobility /
consciousness. Victim may not be
aware of asphyxiation. In low
concentrations may cause narcotic
effects. Symptoms may
includedizziness, headache,
nausea and loss ofco-ordination.
1-butene -80oC 384
oC
Forms explosive mixtures
with air and oxidizing agents.
Avoid exposure to
incompatible materials such
as oxidizing agents, halogens,
and acids. Avoid to elevated
temperatures, and pressures or
the presence of a catalyst.
Asphyxiant. Moderate
concentrations may cause
headache, drowsiness, dizziness,
excitation, excess salivation,
vomiting, and unconsciousness.
Lack of oxygen can kill.
28
Chemicals Flash
point
Auto-Ignition
Temperature Fire & Explosion Reactivity Symptoms / Effects
Neopentane < -7oC 450
oC
Severe fire hazard. Severe
explosion hazard. The vapor is
heavier than air. Vapors or
gases may ignite at distant
ignition sources and flash
back. Gas/air mixtures are
explosive.
Stable at normal temperatures
and pressure. Avoid heat,
flames, sparks and other
sources of ignition. Minimize
contact with material.
Containers may rupture or
explode if exposed to heat.
High concentrations can cause
eye and respiratory mucous
membrane irritation and mild
narcotic symptoms, or loss of
consciousness. Long-term
exposure can induce mild
dermatitis.
Isopentane -51oC 420
oC
Flammable in presence of
open flames and sparks.
Slightly flammable to
flammable in presence of
oxidizing materials.
The product is stable.
Hazardous in case of eye contact
(irritant), of ingestion, of
inhalation. Slightly hazardous in
case of skin contact (irritant,
permeator).
n-pentane -49oC 260
oC
Extremely flammable in
presence of open flames and
sparks, of heat. Flammable in
presence of oxidizing
materials. Nonflammable in
presence of shocks. Slightly
explosive in presence of heat,
of oxidizing materials. Non-
explosive in presence of
shocks.
Stable at room temperature in
closed containers under
normal storage and handling
conditions.
Can causes eye and skin irritation.
Ingestion may cause central
nervous system depression,
characterized by excitement,
followed by headache, dizziness,
drowsiness, and nausea.
Inhalation may cause respiratory
tract irritation.
Oxygen -52.2oC N/A
Oxidizing agent can
vigorously accelerate
combustion. Contact with
flammable materials may
cause fire or explosion.
Extremely reactive or
incompatible with the
oxidizing materials, reducing
materials and combustible
materials.
Breathing 80% or more oxygen at
atmospheric pressure for more
than a few hours may cause nasal
stuffiness, cough, sore throat,
chest pain, and breathing
difficulty.
29
Chemicals Flash
point
Auto-Ignition
Temperature Fire & Explosion Reactivity Symptoms / Effects
Water N/A N/A N/A N/A No acute and chronic health
effects.
Carbon
Dioxide None None Non-flammable.
Stable. Certain reactive
metals, hydrides, moist
cesium monoxide, or lithium
acetylene carbide diammino
may ignite. Passing carbon
dioxide over a mixture of
sodium peroxide and
aluminum or magnesium may
explode.
Moderately irritating to the eyes,
skin, and respiratory system.
Carbon
Monoxide
Not
available. 700
oC
Severe fire hazard. Vapor/air
mixtures are explosive.
Containers
Stable at normal temperatures
and pressure.
Incompatibilities
withoxidizing materials,
halogens, metal oxides,
metals, combustible materials,
lithium
Harmful if inhaled, blood
damage, and difficulty breathing.
Causing blisters, frostbite, and
blurred vision. may rupture or explode if
exposed to heat.
30
CHAPTER 3: CONCEPTUAL PROCESS DESIGN AND SYNTHESIS
3.1 LEVEL I: PROCESS OPERATING MODE
For any chemical process, there are two mode of operation that a plant can choose to operate;
batch process and continuous process. The choice of best mode of operation follows these
guidelines as in the table shown below:
TABLE 7: GUIDELINES FOR BATCH AND CONTINUOUS PROCESS
Guidelines Batch Continuous
Production rate Production less than 10 x 106 lb
per annum
Production more than 10 x 106 lb
per annum
Availability Product is a seasonal product
Raw material are limited
Product is a commodity product
Raw material are always available
Purpose Suitable for research purposes Suitable for mass production
(profit purposes)
Lifetime of
Product Short Long
Our selection for the mode of operation of our plant is discussed in detail for each
guideline point:
i. Production rate
Our targeted capacity is 50 000 metric ton per annum, which is bigger than 10
million pound per annum (4 535.9237 metric ton per year).
ii. Availability
Maleic anhydride is a commodity product, which need to be available all year
due to its extensive usage in the industry.
iii. Purpose
Our maleic anhydride plant obtains profit by its mass production of its product in
most economical process route as possible.
iv. Lifetime of the product
31
The demand for maleic anhydride is projected to increase and for that, the
lifetime for the product is long.
v. Operational problem
Maleic anhydride is usually produced in a gas state before being cooled and
stored as liquid product. With that, it has low operational problem.
From all the points discussed above, the best choice of mode of operation for our plant is
continuous process as the product is produced in large quantity, the product is a
commodity product, it has long lifetime and the process has low operational problem.
3.2 LEVEL II: INPUT-OUTPUT STRUCTURE
The process of ammonia is shown below. According to Douglas, to fix the input and
output structure, a box is drawn around the process. Then the focus is on what are the
feed for the process and what are the product and by-product that comes out from the
process:
FIGURE 6: SCHEMATIC PROCESS OF AMMONIA
To complete the input and output structure of the plant, some check question should be
answered in order to fix the structure above. The check questions are as shown below:
1. Should we purify the feed stream before they enter the process?
2. Should we remove or recycle a reversible by-product?
3. Should we use a gas recycle and purge stream?
4. Should we not bother to recover and recycle some reactants?
32
We will address each check question in detail in order to synthesize our plant’s input and
output structure.
Q1. Should we purify the feed stream before they enter the process?
By composition, our mixed butane feed consists of approximately 32% unwanted
components (such as iso-butane, propane and pentane). These chemicals, without
removing it first will affect the reactivity and selectivity of reaction in the reactor.
For that reason, the feed should be treated first before being fed into the system.
Q2. Should we remove or recycle a reversible by-product?
The by-products of MAN production are water, carbon dioxide, and carbon
monoxide. These are non-reversible product so there is no need for recycle
stream for the by-product.
Q3. Should we use a gas recycle and purge system?
The process is a high pressure process; the pressure in the MAN synthesis loop is
250kPa. Gas stream that remains after the product being recovered contain some
amount of nitrogen. Nitrogen is inert and did not take part in the MAN
conversion. They tend to accumulate in the process loop as the reaction take
place continuously. This could increase the pressure inside the loop. Therefore,
these inert should be taken out and be purged.
Q4. Should we not bother to recover and recycle some reactant?
Process air, a reactant is being used in excess in this process. Since process air is
relatively inexpensive compared to mixed butane, we are not bothered to recover
the reactant. However, water collected from the moisture separator vessel can be
reheated back to steam using the high energy transferred into the furnace, which
can be used in the system. This could save some amount of cost since steam is a
type of utility in the plant.
3.3 LEVEL III: REACTOR DESIGN AND REACTOR NETWORK
SYNTHESIS
Reactors play an important role in all plant especially chemical plant, where the chemical
reaction is taking part. As shown by onion model, reactor is said to be the heart of the
33
whole plant. In other words, reactor is the most important equipment among all in the
chemical plant. As a result, no reactor means no reaction will occur. Without any
reaction, there will be no product produced. From the reactions, mass transfer as well as
chemical kinetics and others are calculated.
3.3.1 Reactor Conversion Selections
The chemical reactions involved in the production of Maleic anhydride consist of one
main reaction and one side reaction.
C4H10 + 3.5O2 C4H2O3+ 4H2O [1]
Butane oxygen maleic anhydride water
C4H10 + 5.5O2 2CO + 2CO2 + 5H2O [2]
Butane oxygen carbon monoxide carbon dioxide water
TABLE 8: PRODUCTION OF MALEIC ANHYDRIDE FROM N-BUTANE
(BLUM & NICHOLAS, 1982)
An ideal reactor will have a high selectivity on the desired product. In evaluating reactor
performance, selectivity is more meaningful to consider than reactor yield. (Smith)
Thus, the % conversion with the highest selectivity is selected which is a % conversion
of 82.2 with a % yield of 57.6 and a % selectivity of 70. The selectivity for carbon
dioxide is 20%.(Slinkard & Baylis, 1975)
34
3.3.2 Preliminary Reactor Mass Balance
Preliminary mass balance calculation for reactor is as below.
TABLE 9: PRELIMINARY REACTOR MASS BALANCE
Component
Mass flow rate kg/hr
In Out
Isobutane 1287.80 1287.80
n-butane 6560.33 1167.74
Oxygen 39730.87 27884.01
Maleic anhydride 0.00 7158.16
Carbon monoxide 0.00 1168.42
Carbon dioxide 0.00 1835.85
Water 3195.32 10021.49
Nitrogen 130843.36 130843.36
EP1 = Product-Reactant
= (RM 6 566.43/ton x 51958tonne/yr) –
[(RM 2858.34/ton x 56693tonne/yr)
= RM 179 130 700.3/year
Assuming that the n-butane can be recycled back as feed, the opportunity to optimize the
reactor is as below.
in
Reactor
out
35
TABLE 10: MASS BALANCE WITH RECYCLE
Component
Mass flow rate kg/hr
In recycle Out
Isobutane 1287.80 0 1287.80
n-butane 5392.59 1167.74 1167.74
Oxygen 39730.87 0 27884.01
Maleic anhydride 0.00 0 7158.16
Carbon monoxide 0.00 0 1168.42
Carbon dioxide 0.00 0 1835.85
Water 3195.32 0 10021.49
Nitrogen 130843.36 0 130843.36
EP1 = Product-Reactant
= (RM 6 566.43/ton x 51958tonne/yr) –
[(RM 2858.34/ton x 42709tonne/yr)
= RM 219 101 726.9/year
The % increase in profit is = (219101726.9-179130700.3)/179130700.3 X 100
= 22,31%
The increase in profit is mainly due to the less usage of n-butane as feed. However, the
removal of low boiling point components (nitrogen, oxygen, carbon monoxide, isobutene
and carbon dioxide) besides n-butane from the recycle stream will cause the loss of most
of the n-butane unless the stream is cooled below the boiling point temperature of n-
36
butane which is typically below cooling water temperature and is not preferred as
refrigeration is required which will be costly.
3.3.3 Reactor Type Selection
The choice selection of type reactor is between two types which is the fixed bed reactor
(FBR) and the fluidized bed reactor (FBR).
The advantages and disadvantages of PBR are summarized below:
TABLE 11: ADVANTAGES AND DISADVANTAGES OF PACKED BED REACTOR (SMITH)
Advantage Disadvantage
High ratio of heat transfer area to
volume
Can be used for multiphase reaction
Use during careful control of residence
time
Have mechanical advantage at high
pressure
Difficult to control temperature due to
varying heat load in bed
Catalyst temperature can be locally
excessive giving hot spots
Off line catalyst regeneration
The advantages and disadvantages of FBR are summarized below:
TABLE 12: ADVANTAGES AND DISADVANTAGES OF FLUIDIZED BED REACTOR
Advantage Disadvantage
Good heat transfer and
temperature uniformity
Useful for frequent catalyst
regeneration (online
regeneration)
Attrition of catalyst can cause carryover
Back mixing on the kinetics in the reactor,
product destruction and by-product reactions
in the space above the fluidized bed
Vulnerability to large-scale catalyst releases
from explosion venting
Require a significant amount of space above
the catalyst level to allow the solids to
separate from the gases. This exposure of the
product to high temperatures at relatively
long residence times can lead to side
reactions and product destruction
37
The temperature of the reactor is around 400-500 0C due to the highly exothermic
reaction involved. At this temperature the components are in gas phase. The removal of
heat from the reactor is important and is the key to the reactor type selection.
The packed bed reactor (PBR) is chosen over the fluidized bed reactor (FBR) due to
several reasons.
As shown in the Tables 11 and 12 above, both reactors have a relatively good heat
transfer rate. Although the FBR have a slight advantage of good control of the
temperature uniformity, control of the hot spots and online catalyst regeneration but the
usage of the FBR is quite new in the industry and the understanding of the FBR model is
new and not complete as a whole. In addition, the disadvantages of the FBR such as back
mixing and catalyst venting also has an impact on the destruction of the product and
impact on the environment and safety point of view. Nevertheless, there are suggested
strategies to overcome the disadvantages like several proposed patents that claim can
control back mixing and also cooling the reactor effluent to prevent the catalyst
carryover to foul the heat exchangers. However, these strategies are relatively new and
not fully established.
Meanwhile, the existence of the PBR is since the production of MAN from benzene
before the usage of n-butane. Several strategies have been successfully implemented to
overcome the problem with the temperature control and hot spots. Among them are using
a small diameter and by using a profile of catalyst through the reactor to even out the
rate of reaction and achieve better control. Several reactors can be installed to overcome
the off line catalyst regeneration. In addition, the exothermic heat of reaction is removed
from the salt mixture by the production of steam in an external salt cooler. Efficient
utilization of waste heat from a maleic anhydride plant is critical to the economic
viability of the plant. The steam can be used to drive an air compressor, generate
electricity, or both. There is also the opportunity to have other equipment to operate at a
higher operating temperature giving a better performance of the equipment knowing that
there is excess waste. This can cut cost by reducing extra equipment for the separation
train.
38
3.4 LEVEL IV: SEPARATION SYSTEM SYNTHESIS
Having made initial specification for the reactor, attention is turned to separation of the
reactor effluent in the process route screening. This is in line with the heuristic approach
for the separation train sequence.
FIGURE 7: HEURISTIC METHOD: ONION MODEL
However, considering that the feed is not of pure n-butane, there is a need to carry out
separation before the reactor to purify the feed. A distillation column which is the
benchmark for the separating equipment is chosen to separate out the n-butane to
increase the purity of the feed.
The procedure followed in deciding the process route using the heuristic method is as
follows:
Decide on type of separator that will be likely used for the required separation
Decide on the sequencing of the separator to achieve the process requirement
39
The golden rule for separation is to separate heterogeneous mixtures as soon as it forms.
However the reactor effluent is of homogeneous mixture.
The first choice for separating homogeneous mixture is using the distillation column.
Nevertheless, separations using distillation column have circumstances not favoring
distillation as below:
1. Separation of low molecular weight materials
2. Separation of high molecular weight heat sensitive material.
3. Separation of components with low concentration.
4. Separation of classes of components
3.4.1 First Process Route
The reactor effluent mainly consists of gases like nitrogen, oxygen, carbon monoxide
and carbon dioxide. Thus, separation of the gases which is a class of component cannot
be done using distillation column. Alternatives of separation include the creation of
another phase within the system by changing the temperature or pressure or by addition
of a mass separation agent. This can be done by using an absorber. Since changing the
operating parameters require the usage of heating or cooling and the component
interested to be separated is the gases, the mass separation agent is used to absorb MAN
from the effluent.
Water is usually used as the standard mass separation agent (MSA). Alternatively, there
are also other organic mass separation agents that can be used but for the first process
route, the standard water is used. The usage of other mass separation agent will be
discussed in the second process route.
The water exiting the absorber contains dissolved MAN and also maleic acid which is
the reaction of MAN and water. Water is the major component fraction in the stream
exiting the absorber. Another phase separation can be done easily by increasing the
temperature to remove a large amount of water. The flash drum is used to separate the
different phases after the temperature is increased.
After the flash drum, the maleic acid needs to be converted back to MAN before the
proceeding to further separate the water. For this purpose, a reactor is used to convert
back the acid into MAN at a specified temperature.
40
After the maleic acid reactor, a distillation column can be used to separate water and
MAN. However, according to UNIFAC thermodynamic package, MAN and water forms
azeotrope which makes the mixture hard to separate. To overcome the hard separation,
two distillation columns operating at different pressures are needed to separate the water.
FIGURE 8: FIRST PROCESS ROUTE
3.4.2 Second Process Route
The second process route considers the usage of other MSA in the absorber. Among the
commonly used mass separation agent for the process are dibutyl phthalate, dibutyl
terephthalate, dimethyl phthalate and diisopropyl phthalate. According to Chen (2002),
dibutyl phthalate (DBP) is best used for n-butane processes. Thus, it is chosen as the
MSA for the second route.
The DBP absorbs most of the MAN and small amounts of water. The MSA then needs to
be regenerated through the separation of DBP from MAN and water. Usually, a stripper
is used for the regenaration of the MSA. However, DBP can be separated from MAN
without using a gas stripper. Hence, a stripper distillation column which is a typical
distillation column is used to separate the DBP. Since the amount of water together with
MAN is relatively small, the purity of the MAN separated is at 99 weight %. So, further
41
purification will need two more distillation column to further separate the azeotrope
mixture which will be uneconomical.
FIGURE 9: SECOND PROCESS ROUTE
3.4.3 Process Route Selection
The second process route is selected over the first process route. This is because more
equipment is used in the first route due to the production of maleic acid when water
reacts with MAN. In addition, the usage of water as the MSA requires two distillation
columns to separate the azeotrope mixtures. On the other hand, the usage of dibutyl
phthalate as the MSA simplifies the separation train sequence. Although DBP is more
expensive than water, but according US Patent 5069687 and US Patent 4071540, the
usage of DBP is more energy efficient due to the avoidance of the evaporation of water
and effective in absorbing 99.4% of the MAN. Moreover, due the small amount of water,
the MAN exiting the stripper distillation column is already at more than 99 weight % so
further purification is not needed.
3.5 LEVEL V: HEAT INTEGRATION
3.5.1 Introduction to Pinch Analysis
Pinch analysis is a well-established tool that determines the minimum energy
requirement and the optimumdesign of heat exchanger network. This analysis enables a
plant design to reach the following goals:
Maximizing heat recovery of the system.
Minimizing heating and cooling utility consumption.
Optimizing the selection of utility sources.
42
Optimizing the trade-off between energy costs and capital cost.
3.5.2 SPRINT Software
In integrating heat network into the design, SPRINT software is used. This software may
be used to develop composite curve, problem table algorithm, and grand composite curve
based on the stream data inserted by a user. This software is also capable of detecting
infeasibility of a heat exchanger network design if there is any temperature violation. In
short, SPRINT software facilitates the necessary calculations for heat integration.
3.5.3 Stream Data Extraction
The first step in performing heat integration is to extract information of streams that
require heat duty. These are streams that require change in temperature. The streams that
are selected for heat integration will exclude streams for equipment (such as reboiler and
condenser). Stream data extracted for this project can be tabulated as follows:
TABLE 13: STREAM DATA EXTRACTED
Type Stream Ts
(°C)
Tt
(°C)
H
(kW)
CP
(kW/°C)
H1 Hot Reactor exit 500.0000 125.0000 20,619.0904 54.9842
H2 Hot Solvent feed 250.0000 35.0000 7,027.2561 32.6849
C1 Cold Feed vaporizer 25.0000 85.0000 854.8509 14.2475
C2 Cold Deisobutanizer bottom 75.8398 120.0000 320.0433 7.2473
C3 Cold Mixer output 116.7270 310.0000 10,187.2383 52.7091
Information on supply temperature (Ts), target temperature (Tt) and heat duty (H) are
generally extracted from process flow diagram (PFD) made by iCon simulation. CP is
assumed constant at any temperature and is calculated using the following equation:
The streams extracted are categorized into hot and cold streams. A stream is defined as
hot when it is surplus in heat (requires cooling) and cold stream when it is deficit in heat
(requires heating).
43
3.5.4 Minimum Temperature Difference
Temperature difference between hot stream and cold stream is the driving force for heat
transfer between the two profiles. Minimum temperature difference, Tmin, is the lowest
potential driving force, below which heat transfer is unlikely. Tmin determines the
amount of heat recovery in a system. When Tmin is lower, the potential heat recovery
from process will be higher. However, according to application experience by KBC
Energy Service, the typical Tmin value varies according to industry (Pinch Analysis).
TABLE 14: OPTIMUM TMIN IN DIFFERENT INDUSTRIES (PINCH ANALYSIS)
Industrial sector Typical
ΔTmin (°C) Remarks
Oil refining 20 – 40
Relatively low heat transfer coefficients, parallel
composite curves in many applications, fouling of
heat exchangers
Petrochemical 10 – 20 Reboiling and condensing duties provide better heat
transfer coefficients, low fouling
Chemical 10 – 20 As for petrochemicals
Low temperature
process 3 - 5
Power requirement for refrigeration system is very
expensive. ΔTmin decreases with low refrigeration T
Maleic Anhydride production plant is a petrochemical industry. Hence, the optimum
Tmin according to the table above is in range of 10°C – 20°C. For this project, Tmin of
10°C is selected so as to maximise heat recovery from the system.
3.5.5 Maximum Process Heat Recovery
Initially, the plant is designed so as all the heating and cooling requirements are satisfied
by using utilities. The table below indicates the total hot and cold utility requirement
before heat integration:
44
TABLE 15: UTILITIES REQUIRED BEFORE HEAT INTEGRATION
Type Stream H
(kW)
H1 Hot Reactor exit 20,619.0904
H2 Hot Solvent feed 7,027.2561
Total cold utility required 27,646.3465
C1 Cold Feed vaporizer 854.8509
C2 Cold Deisobutanizer bottom 320.0433
C3 Cold Mixer output 10,187.2383
Total hot utility required 11,362.1325
By applying pinch analysis, we target on maximizing energy recovery from the process
so that the utility requirement can be minimized. The maximization of process heat
recovery can be visualized using a composite curve as shown below:
FIGURE 10: COMPOSITE CURVE FOR MAXIMUM HEAT RECOVERY:
With the input of extracted stream data, SPRINT software calculates the maximum heat
recovery from process streams and the minimum utility requirement. In composite curve,
the maximum process heat recovery is represented by the range of heat load where hot
45
profile and cold profile overlap. The maximum process heat recovery, minimum cold
utility (Qcmin), and minimum hot utility (Qhmin) requirements are as follows:
TABLE 16: UTILITIES REQUIRED AFTER HEAT INTEGRATION
Utility H
(kW)
Minimum cold utility (Qcmin) 16,284.2140
Minimum hot utility (Qhmin) 0.0000
The values of pinch temperature, Qcmin, and Qhmin can also be obtained from problem
table algorithm (PTA). Figure below shows the PTA acquired using SPRINT software.
FIGURE 11: PROBLEM TABLE ALGORITHM BY SPRINT SOFTWARE
From the PTA, the pinch temperature, .
Therefore,
46
3.5.6 Heat Exchanger Network
Based on information extracted on PTA, pinch point is located at the highest shifted
temperature (495C). This means that the overall system existed below the pinch.
Therefore, only analysis of heat integration below the pinch is relevant. Prior to decision
on the best heat exchanger network, estimation of the minimum number of heat
exchanger units, Nunit, can be made using the following equation:
Where
From the equation,
During pairing of the streams, two rules must be obeyed to ensure the network is
feasible. The rules are:
The T between a pair of hot stream and cold stream must always be ≥ 10C.
CP rule (i.e. CPhot≤ CPcold for above pinch and CPhot≥ CPcold for below pinch)
must not be violated unless the pair is away from pinch.
Figure below illustrate the heat exchanger network designed for this plant.
FIGURE 12: HEAT EXCHANGER NETWORK
After creating heat exchanger network, it can be summarized that the total number of
heat exchangers for the plant is 5 units. Process heat recovery can be sum up to
Tpinch hot, 500°C
H1 500 125
H2 250 35
C1 85 25
C2 120 75.8
C3 310 116.7
Tpinch cold, 490°C
10,187 kW
320 kW
10,432 kW
5,852 kW
314.72C
855 kW
240.21 C 214.05C
47
11,362.1325kW. The amount of cold utility requirement is 16,284.2140 kW, while no
hot utility is required.
3.5.7 Energy-Saving Evaluation
Comparison of heat utility requirements before and after heat integration (HI) can be
summarized into the following table:
TABLE 17: COMPARISON OF UTILITY REQUIREMENT BEFORE AND AFTER HI
Utility
Requirement
Heat Duty (kW)
% Saving
Before HI After HI
Hot utility, Qh 11,362.1325 0.0000 100.0%
Cold utility, Qc 27,646.3465 16,284.2140 41.1%
Total 39,008.4791 16,284.2140 58.3%
Percentage saving can be calculated using the following formula:
Referring to the table above, it is observed that there is a huge reduction in utility
requirement after pinch analysis is applied. The plant can eliminate 100% of the
requirement for hot utility, while the amount of cold utility can be reduced up to 41.1%.
As an overall, heat integration implemented can minimize the plant’s operating cost by
minimizing utility requirement, as well as reducing capital cost by minimizing the
number of heat exchangers during heat exchanger network design.
48
CHAPTER 4: INSTRUMENTATION AND CONTROL
4.1 INTRODUCTION
A safe mode operating chemical plant requires a good control system around the
equipment by installation of relevant instrumentations in achieving its target production.
This is to ensure that the operation of the plant could be conducted in the most
economical way and avoid accidents that may lead to the upset value of the production.
The objectives of designing the control system strategy are:
To have a safer operation plants and avoid accidents such as explosion
To maintain the operational condition of the unit operation at their own
respective condition
To control the process that is in line with the production rate
To maintain the product purity as high as possible
To avoid excess usage of heating and cooling utilities
4.2 DESIGN OF PLANT WIDE CONTROL SYSTEM
4.2.1 Procedures
The four major steps in designing the plant wide control system are;
i. The overall specification for the plant and its control system are stated.
ii. The control system structure, which includes selecting controlled, measured and
manipulated variables, product quality, handling operating constraints, is
developed.
iii. Detailed specification of all instrumentation, cost estimation, evaluation of
alternatives and the ordering and installation of unit operation are available.
iv. Design and construction of the plant and plant tests (startup, operation at design
conditions and shutdowns) are known.
However, for this plant, the steps taken are only;
i. Identification of controlled, manipulated and disturbance variables are
developed.
49
ii. Appropriate control strategies are implemented.
The Process &Instrumentation Diagram (P&ID) for the whole plant is attached in the
Appendix 2.
4.2.2 Drier Control System
The purpose of the control system is to maintain the desired water content in the air
which is fed into the reactor. The control system consists of pressure and level
controller. The drier is a flash vessel whereby flashing of the air occur at a specified
temperature and pressure to remove water.
TABLE18: DRIER CONTROL SYSTEM DETAILS
Controlled variable Manipulated variable Type of controller Set Point
Pressure of the flash
vessel
Vapour flow rate Feedback Control
Pressure :
1480kpa
Level of the flash
drum
Air inlet flow rate Feedback Controller Level: 70%
4.2.3 Deisobutanizer Control System
The control system in the deisobutanizer column is important in order to have an
accurate separation between the components and to ensure good ratio of purity. Basically
the process is applying the distillation concept; the only different is the different take off
point at the trays. The control system must be able to cause the average sum of the
product streams to be exactly equal to the average desired stream. It must also be able to
maintain the desired concentration of products at the bottom and the top streams. Control
requirements for deisobutanizer, K-1 are:
Pressure in the column
Feedback control is used to control the operating pressure at the top of the column
to avoid overpressure.
Level of the liquid at the bottom of the column
50
The liquid level is controlled by manipulating the outlet of the bottom product flow
rate using feedback control system.
Temperature of the column
The reflux temperature is controlled by manipulating the inlet flow rate of low
pressure steam (LPS) entering the reboiler by using the feedback control.
Reflux temperature
The temperature difference must not exceed the critical temperature difference. The
temperature indicator and controller installed at the condenser outlet controls the
temperature by manipulating the cool water supply (CWS) line.
Reflux ratio
A flow indicator and controller is installed at the reflux line cascaded with flow
indicator and controller of the distillate line to control the flow of the reflux back
into the column. Ratio control will maintain the ratio of the reflux line and distillate
line at the set point.
TABLE19 : DEISOBUTANIZER CONTROL SYSTEM DETAILS
Controlled variable Manipulated variable Type of controller Set Point
Pressure in the column Top outlet vapor flow
rate
Feedback control
Pressure:
1100 kPa
Bottom liquid level Bottom liquid outlet
flow rate
Feedback control
Level: 80 %
Bottom temperature Steam inlet flow rate Feedback control
Temperature:
75.8 oC
Reflux temperature Cooling water supply
flowrate
Feedback control
Temperature:
55.4 0C
Reflux ratio Outlet gas flow rate Ratio control Reflux ratio: 1.8
4.2.4 Reactor Control System
For the control system design at the reactor, C-1, several requirements have to be made;
Feed flow rate of the two inlet streams into the reactor
The flow rate into the reactor has a certain ratio value for the ideal reaction to
occur or otherwise, accidents such as explosion may occur at any time during the
51
operation. The ratio is set at least 1.7% oxygen. Therefore, these two inlet
streams have to be adjusted at this desired value so that accident will not occur by
controlling it with a ratio controller. Both are feedforward controller and are
interconnected with a ratio controller to ensure that the desired ratio of the feed
stream can be obtained.
Temperature of the reactor
On top of that, the temperature inside the reactor is controlled by manipulating
the bypass supply stream of the refrigerant and the bypass feed flow rate to the
reactor using feedback controller. The flow rate of molten salt (MS) will
determine and change the temperature inside the reactor until it reaches the
desired set point. In addition, for further safety reason, the feed flow rate will be
decreased if the temperature goes too high.
Additional safety features includes the installation of an interlock system and
emergency shutdown system if the temperature gets extremely high. The system
is activated at the temperature of 6500C and when it is activated, the block valve
will close the flow of feed; the feed is bypassed and the blow down valve will be
opened to purge the content in the reactor to prevent contain the high
temperature.
Pressure of the reactor
The pressure of the reactor also has to be controlled just as the same priority as
the temperature in the reactor. The feed are of gaseous phase and are easily
influenced by the adjustment of the temperature as well as the pressure with
assumption that the gas is an ideal gas. Furthermore, these two parameters are
essential in the production of the maleic anhydride as the rate of the reaction is
directly dependent on the temperature and pressure of the reactor. The pressure is
controlled by regulating the outlet gas at the top of the reactor. For safety reasons,
pressure relief valve, PSV is installed should the pressure increased tremendously
in the reactor. Accidents may occur if the pressure exceeds the desired value. The
catalyst used is also being control in sense of temperature by measuring and
manipulating the pressure so that the ideal condition could be achieved.
52
TABLE20: REACTOR CONTROL SYSTEM DETAILS
Controlled Variables Manipulated Variables Type of Controller Set Point
Ratio of inlet flow rate Air flow rate Ratio Control
Flow rate ratio =
S8/S6 = 0.017
Temperature of the
reactor
Bypass MS and bypass
feed
High selector with
split range and
cascade control
Temperature: 500 0C
Total bypass feed and
open blow down valve
None (use interlock
and tripping system)
Temperature: 6500C
Temperature of the
reactor (for start-up
reactor)
Start-up heater flow
bypass
Feedback control Temperature: 4000C
Pressure of the reactor Reactor outlet flow rate Feedback Control Pressure: 250 kPa
4.2.5 Heat Exchanger Control System
The purpose of performing a control system for heat exchanger is to maintain the desired
temperature of its outlet stream either by providing heating or cooling utility. There are
two types of heat exchanger control system, depending on whether the heat exchanger
has been integrated or not.
Cooler (Single stream heat exchanger)
There is only one process stream which is experiencing heating or cooling and
the temperature of the stream is controlled by manipulating the flow rate of
utilities stream.
Double stream heat exchanger
The heat exchanger has been integrated. Therefore, there were two process
streams connected to the heat exchanger. Both process streams will experience
either heating or cooling process. Bypass stream is connected from inlet stream to
the outlet stream of the cold stream. Temperature indicator and controller are
53
installed at the outlet of the hot stream and are cascaded with the flow indicator
and controller which is installed at the bypass stream. The temperature of the cold
stream is controlled by manipulating the flow rate of bypass stream.
TABLE 21: COOLER CONTROL SYSTEM DETAILS
Cooler Controlled
Variable
Manipulated
Variable
Type of
Controller Set point
W-6 Reactor effluent
temperature
Cooling water
supply flow rate
Feedback Control Temperature:
125 0C
W-9 Solvent recycle
temperature
Cooling water
supply flow rate
Feedback Control Temperature:
35 0C
TABLE 22: HEAT EXCHANGER CONTROL SYSTEM DETAILS
Heat
Exchanger
Controlled
Variable
Manipulated
Variable
Type of
Controller Set point
W-4 Outlet temperature
of pump
Bypass flow rate Cascade Control
Temperature:
204.2 0C
W-1 Outlet temperature
of W-4
Bypass flow rate Cascade Control
Temperature:
35 0C
4.2.6 Absorber Control System
Absorber is used to absorb the maleic anhydride from other gases. The requirements for
absorber control system are as below:
Level of liquid in the column
The level of liquid at the bottom of the absorber is maintain at desired level by
controlling the outlet flow of rich solvent using feedback controller.
Pressure at top of the column
Feedback control is used to control the operating pressure at the top of the
column to avoid overpressure. The pressure at the top of the absorber is
maintained at desired condition by controlling the outlet flow of off-gases. For
54
safety reasons, pressure relief valve, PSV is installed should the pressure
increased tremendously in the column.
Feed flow rate of the two inlet streams into the absorber
The purpose the control system is to ensure the feed streams is at desired flow
rate. The feed to absorber are outlet of reactor cooler, W-3 and the recycled
solvent dibutyl phthalate from the outlet of heat exchanger, W-4. The ratio for
both streams must be controlled to ensure the absorption for maleic anhydride is
effective. Ratio control is implemented to ensure that sufficient amount of dibutyl
phthalate is fed into the absorber depending on the flow rate ratio set for both
inlet streams.
TABLE 23: GAS ABSORBER, C-301 CONTROL SYSTEM DETAILS
Control
Variable
Manipulated
Variable
Type of
Controller Set Point
Liquid level at
bottom of absorber
Bottom outlet flow rate Feedback Control Level: 80 %
Pressure in the
Absorber
Off-gas outlet flow rate Feedback Control
Pressure:
200kPa
Ratio of inlet flow
Rate
Flow of dibutyl
phthalate
Ratio Control
Flow rate ratio:
S29/S16 =
5.71
4.2.7 Stripper Distillation Column Control System
The control system in the distillation column is important in order to have a sharp
separation between the components in the incoming feed. The control system of
distillation column is controlled based on three purposes:
Material balance control
- The column control system causing the average sum of the product streams
(bottom and top product) to be exactly equal to the average feed rate, keeping
the column in material balance.
- Although the plant is usually designed for a nominal production rate, a design
tolerance is always incorporated because the market condition and demand may
require an increase or decrease from the current state. The control system is then
needed to ensure a smooth and safer transition from the old production level to
the newly desired production level. Its purpose is to direct the control action in
55
such a way as to make the inflows equal to the outflows and achieve a new
steady-state material balance for the plant.
Product quality control
- To maintain the desired concentration of the products at the bottom and the top
of the column.
Satisfaction of constraints.
For safety purposes, satisfactory operation of the column, certain constraints must
be understood and followed, for example:
- The column shall not flood.
- Column pressure drop should be low enough to maintain the efficiency of the
column operation in order to prevent serious weeping or dumping.
- The temperature difference in the reboiler should not exceed the critical
temperature difference.
- Avoid shock loading to the column so that overload of reboiler or condenser
heat-transfer capacity can be avoided.
- Column pressure should not exceed a maximum permissible limit.
-
TABLE 24: DISTILLATION COLUMN CONTROL SYSTEM
Controlled Variable Manipulated Variable Type of Controller Set point
Pressure in the column Top outlet vapor flow
rate
Feedback Control Pressure:
120 kPa
Bottom liquid level Bottom liquid flow
rate
Feedback Control Level: 80 %
Bottom temperature Steam inlet flow
rate
Feedback Control Temperature:
250 0C
Reflux drum level Reflux solution flow
rate
Feedback Control Level: 50 %
Reflux temperature Cooling water
supply flow rate
Feedback Control Temperature:
85 0C
Reflux ratio Reflux flow rate &
MA product flow
rate
Ratio Control
Ratio: 1.8
56
CHAPTER 5: SAFETY AND LOSS PREVENTION
5.1 HAZARD AND OPERABILITY STUDIES (HAZOP)
5.1.1 Introduction to HAZOP
HAZOP, according to Dunn (2009), is a structured procedure intended to proactively
identify equipment modifications and/or safety devices required in order to avoid any
significant danger as a result of equipment failure.HAZOP study focuses on each
pipeline and vessel shown on the respective flow sheet or line diagram. Any possible
deviations from normal operating conditions are studied.As a result, HAZOP study
enables investigation on potential mal-operation, as well as identifies their root causes,
consequences and corrective actions.
5.1.2 Study Nodes Selection
For this HAZOP studies, the selection of study nodes is based on nodes that contain
highly hazardous materials and critical process conditions. With reference to preliminary
hazard analysis conducted in the earlier stage of plant design, it is found that reactor is
one of the high-risk equipment. Due to its high temperature application and variation in
reaction activity, reactor is classified as equipment with critical condition. Furthermore,
the stream contains mixture of gaseous n-butane and air at high temperature, which may
lead to explosion if overpressure.
Therefore, three study nodes connected to reactor (C-1) is selected to be studied in this
HAZOP analysis. The study nodes are shown in the table and figure below.
TABLE 25: STUDY NODES IN HAZOP ANALYSIS
No. Study node
1 Inlet to reactor (C-1) – Stream 11
2 Outlet to reactor (C-1) – Stream 12
3 Inlet of molten salt loop to reactor
57
Reactor
C-1
Stream 11
(Reactant: n-
butane & air)
Stream 12
(Product: MAN,
water, CO, CO2)
Boiler
(For steam
generation)
Molten
salt
inlet
Molten
salt outlet
1 2
3
Further understanding of the process flow can be done by referring to Process Flow
Diagram (PFD) or Process Instrumentation and Control Diagram (P&ID) as attached in
Appendices.
5.1.3 HAZOP Analysis
The following tables (Table 26 - Table 28) illustrate findings from HAZOP analysis.
FIGURE 13: SELECTED STUDY NODES CONNECTED TO REACTOR
58
TABLE 26: STUDY NODE #1
HAZOP STUDY RECORD SHEET PROJECT : MALEIC ANHYDRIDE PLANT
MAJOR UNIT : REACTOR
Date : 20 October 2012
System : MAN Production Study node: Inlet to reactor (C-1) – Stream 11
Item Guide word Deviation Possible consequences Possible causes Safeguard/
Action required
1A1
Flow
More Upsetting process
Uncontrolled reaction
Excessive heat
Excess air
Excess n-butane
Valve fully open
Install high flow alarm
Install dry air control valve after
compressor
Operator to continuously monitor
pipe/valve condition and manually
change valve position
1A2
No No reaction
No product
Pipe rupture
Valve fully closed
Blockage
Install feed flow meter
To be included in biweekly routine
checkup procedure by Inspection Team
1A3
Less Less pressure
Less favorable product.
Pipe leakage
Valve partially closed
Install low flow alarm
Operator to continuously monitor
pipe/valve condition and manually
change valve position
59
TABLE 26 (CONTINUED)
Item Guide word Deviation Possible consequences Possible causes Safeguard/
Action required
1B1
Pressure More High velocity of
reactant
Overpressure
High temperature
Valve failure
Overheat
Dryer failure
High pressure alarm
Installpressure safety valve (PSV)
Install high temperature alarm
1B2 Less Less reaction
Less favorable product
Leakage
Compressor failure
Insert safety valve
Install low pressure alarm
1C1 Temperature
More Uncontrolled reaction
Mechanical failure
May cause explosion
Pressure increase Install temperature sensor
1C2 Less Less pressure, less
favorable product.
Low pressure Install temperature sensor
1D1 Ignition - Fire, sparks Presence of oxidizing
substance
Temperature rise
Insulation of pipe and equipment
Temperature sensor
60
TABLE 27: STUDY NODE #2
HAZOP STUDY RECORD SHEET PROJECT : MALEIC ANHYDRIDE PLANT
MAJOR UNIT : REACTOR
Date : 20 October 2012
System : MAN Production Study node: Outlet to reactor (C-1) – Stream 12
Item Guide word Deviation Possible consequences Possible causes Safeguard/
Action required
2A1 Flow More Upsetting process
Increase demand for
solvent
Increase in temperature
Uncontrolled reaction
Install high flow alarm
Regular monitoring by Control Team
2A2
No No product Pipe rupture, valve
fully closed, blockage
No reaction
To be included in biweekly routine
checkup procedure by Inspection Team
Regular monitoring by Control Team
Operator to continuously monitor
pipe/valve condition and manually
change valve position
2A3
Less Less product form
Decrease in
temperature
Low reaction rate
Pipe leakage
Valve partially closed
Install low flow alarm
To be included in biweekly routine
checkup procedure by Inspection Team
Regular monitoring by Control Team
61
TABLE 27 (CONTINUED)
Item Guide word Deviation Possible consequences Possible causes Safeguard/
Action required
2B1 Pressure More Low absorption rate Uncontrolled reaction Install pressure safety valve (PSV)
Install high pressure alarm
2B2 Less Less flow rate to the
absorber
Agitate absorption
process
Take longer time
Low reaction rate
Pipe leakage
Install low flow alarm
Operator to monitorpipe/valve
condition
Regular monitoring by Control Team
2C1 Temperature More Increase in utility Uncontrolled reaction Install temperature sensor
Install auto-control valve for utility
2C2 Less Less pressure
Take longer time for
absorption process
Low reaction rate Install temperature sensor
62
TABLE 28: STUDY NODE #3
HAZOP STUDY RECORD SHEET PROJECT : MALEIC ANHYDRIDE PLANT
MAJOR UNIT : REACTOR
Date : 20 October 2012
System : MAN Production Study node: Inlet of molten salt loop to reactor
Item Guide word Deviation Possible consequences Possible causes Safeguard/
Action required
3A1
Flow
More More heat absorbed
Temperature in reactor
decrease
Favor undesired
reaction
Valve fully open Install high flow alarm
Operator to manually change valve
position
3A2 No Rise in reactor
temperature
Explosion
May lead to auto-
ignition
Pipe rupture
Valve fully closed
Install safety valve
Pipe/valve operation to be included in
biweekly routine checkup procedure by
Inspection Team
Operator to continuously monitor
pipe/valve condition and manually
change valve position
63
TABLE 28 (CONTINUED)
Item Guide word Deviation Possible consequences Possible causes Safeguard/
Action required
3A3
Less Rise in reactor
temperature
Explosion
May lead to auto-
ignition
Pipe leakage
Valve partially closed
Install low flow alarm
Install safety valve
To be included in biweekly routine
checkup procedure by Inspection Team
Operator to continuously monitor
pipe/valve condition and manually
change valve position
3B1 Pressure More System unit rupture
Backflow into solvent
supply
Utility (boiler) failure
Blockage due to crystal
formation
Install pressure safety valve (PSV)
Install high pressure alarm
Boiler operation to be included in
biweekly routine checkup procedure by
Inspection Team
3B2 Less Reduction in flow rate
of salt
Longer cooling time for
reactor
Large heat loss in
utility (boiler) system
Pipe leakage
Install low flow alarm
Boiler/pipe operation to be included in
biweekly routine checkup procedure by
Inspection Team
64
TABLE 28 (CONTINUED)
Item Guide word Deviation Possible consequences Possible causes Safeguard/
Action required
3C1 Temperature More Less effective in
cooling down reactor’s
temperature
Utility (boiler) failure Install temperature sensor
Boiler operation to be included in
biweekly routine checkup procedure by
Inspection Team
3C2 Less Heat capacity is higher
More heat is absorbed
Temperature in reactor
decrease
Favor undesired
reaction
Large heat loss in
utility (boiler) system
Install temperature sensor
Boiler operation to be included in
biweekly routine checkup procedure by
Inspection Team
65
5.2 PLANT LAYOUT
5.2.1 Site Layout
This Maleic Anhydride production plant will be located in Kidurong Industrial Area, Sabah.
It is planned to occupy area of 350 meter x 300 meter (105,000 m2). The overall site layout
is shown in Appendix. Several factors have been considered in laying out the site. The
process units and ancillary building should be laid out to give the most economical flow of
materials and personnel around the site. In term of safety, process area is located at enough
distance from the place where there are a lot of personnel. Basically, the site layout can be
divided into two parts:
Non-Process area
Process Area
5.2.2 Non-Process Area
As suggested by Kirk-Othmer (1997), non-process area should be located at a distance of at
least, 60 meters from processing area. This is important to avoid any undesired incident due
to explosion or fire from the process zone. Among the buildings or units in the non-process
area are: -
Guard post
Guard posts are located at the entrance of the site. The security checkpoints are important to
ensure unauthorized access into the plant. There are 3 guard posts in this site:
o Main entrance guard post – to control the flow in and out of personnel or cars
between the site and public area.
o Process area guard post – security check to ensure that there is no hazardous or
undesired materials being brought into the process area. It is a common practice in
some places where personnel should have a ‘safety-briefing’ card to be allowed to
enter the process site.
o Contractor’s entrance guard post – contractors will enter the process area at
different entrance with their heavy transport such as crane and lorry.
Administration building
66
Administration office building is sited far away from the process area to avoid any explosion
and fire hazard since this is the place where a lot of personnel involve. It is also near to the
cafeteria and ‘surau’.
Cafeteria
Cafeteria provides meals for the employees and visitors.
Clinic
The location of clinic has been chosen so that it can be reached easily either from the
process area or non-process area. It offers emergency and fast treatment to the injured
employees before being sent to the nearest hospital for further treatment.
5.2.3 Process Area
Process area is the heart of this plant. It is a hazardous area since it deals with a lot of
chemicals. Arrangement of main process site as well as other ancillary buildings was done
carefully. Below are the units and buildings in the Process Area:
Unit 1
This is where the n-butane is being separated from the feed mixture in obtaining a stream of
high content n-butane. It consists of a deisobutanizer column, compressor and mixer.
Unit 2
Oxidation process occur in vapor phase. The feed is contacted with the Vanadium
Phosphorus Oxide catalyst in a packed bed system. MAN is formed as the main product in
the process with the production of carbon monoxide and carbon dioxide as the by product.
Unit 3
MAN purification is a unit to further purify the MAN from other by-products. The main
process goes through the absober Column where MAN is absorbed from the incoming
stream followed by a stripper unit for DBP regeneration to be recycled.
Utilities
This unit will supply cooling water, low pressure steam, plant and instrument air and some
other utilities to the main process unit. Its location is perfectly suitable to give the most
economical run of pipe to and from the process unit.
67
Pump house
The pump house contains pumps used to control the material stream flow between the
process units with the storage farm.
Wastewater Treatment Unit
The wastewater effluent from the process unit will be sent to Wastewater Treatment Unit to
be treated before being released to the environment. It is located adjacent to the main
process unit so that the wastewater effluents from the process units can be channeled to it
without needing long piping to be transferred.
Storage farm
Storage farm consists of some big tanks. These tanks will store the raw material from
supplier before being processed and also stores the product before being exported. Storage
farm is located away from the major processing unit to avoid explosion hazard.
Central control building
All the control valves for the whole process area will be controlled and monitored from this
central control building. Even it is near to the main process area, it still can be considered as
a safe place since it is provided with explosion proof doors and very thick concrete walls. In
case of emergency occurs in the plant, control room will be the assembly point in the
process area.
Fire station
There are two fire stations provided in the process area. One is located near the main process
unit and the other one is placed near the storage farm. These arrangements are made so that
faster action could be taken in case of fire-emergency in these two most hazardous areas.
Operator station
Operator station is adjacent to the central control building.
Laboratory
Quality of feed and product should be taken into considerations. Laboratory is the place
where the sample (both feed and product) is tested and analyzed to determine whether it
meets the specifications or not. All the result will be sent to the control room and some
68
adjustments in controlling will be made, if needed. Thus, the distance between laboratory
and control room is not too far. Laboratory staffs will also perform an analysis regarding
waste of the process before being channeled to nearby environment.
Chemical storage
This unit stores vessels containing chemical substance, lubricants, and catalyst pellet used
for the process. Thus, it is located to the process unit.
Flare Area
Flare is used to burn all excess gas that is emitted from the process units as well as to burn
some of the waste gas from waste treatment area. In our plant, the flare stack is located at
the middle of 100m x 100m area, to give a radius of 50 meters from other sites and
buildings, and meet the statement from Kirk-Othmer (1997), which stated that the minimum
safety range from flare to unit operation and storage farm is in radius of 60 meters.
Warehouse
Warehouse stores all the equipment’s spare parts. It is placed near to the workshop to ease
the maintenance job.
Expansion Site
There are some free areas allocated for the future plant expansion. They occupy enough
space for further expansion, whether for process reaction or producing the plant’s own
utility such as cooling water and steam.
5.2.4 Assembly point
For the whole site in this vinyl chloride plant, there are a few zones that have been identified
to be as assembly area. In the site layout shown in the appendix, all the assembly areas are
represented by small triangles. These are the focal points for every personnel to gather in
case of emergency occur, and the assembly areas are located in both process area and non-
process area. For the non process area, the assembly points are determined to be in front of
the car park, administration building and warehouse. For the process area, the assembly
points are in the control room, near the process area main entrance as well as beside the fire
69
station. However, control room is the best assembly point since it is built with special safety
features with thick concrete wall and explosion-proof door.
5.2.5 Emergency Exit
It is a common practice to have some alternatives way to exit from the chemical plant. In
this site, there are three emergency exits available, two of them are provided in the process
area while the other one is near to the workshop building.
5.3 PLANT LAYOUT CONSIDERATION FACTORS
The economic construction and efficient operation of a process unit will depend on how well
the plant and equipment specified on the process flow-sheet is laid out.
Some of the factors considered are:
Cost
Minimization of construction cost is done by adopting shortest run of connecting pipe
between equipment. The cost is also reduced by having the least amount of structural steel
work. The most important thing is to have an arrangement for best operation and
maintenance.
Operation
Equipment such as valves, sample points and instruments are considered as frequently
attended equipments. They are located not far away from control room, with convenient
positions and heights, to ease the operator’s job. Also, sufficient working and headroom
space are provided to allow easy access to equipments.
Maintenance
When laying out the plant, some considerations were made regarding maintenance work.
For examples:
o Both reactors which use catalysts are located in open space for easiness of
removing or replacing the catalysts.
o Enough space is allocated for heat exchangers for withdrawing the bundles
purposes.
70
o All equipments are accessible to crane/lift truck
o Compressors and pumps are located under cover since they require dismantling
for maintenance
Safety
Among the safety consideration that we have when laying out this plant are:
o Operators have 4 escape routes if anything occurs in the main process unit.
o To minimize fire from spread, flammables handling process units are separated
from each other
o Process vessels with substantial inventories of flammable liquids are located at
grade.
o Elevated areas will have at least one stairway.
o Storage farm which stores the flammable materials are located at safe distance
from the main process area.
o Equipment subject to explosion hazard is set away from occupied buildings and
areas.
Plant expansion
Equipments are arranged by considering future plant expansion, which means it can be
conveniently connected with the new equipment.
TABLE 29: RECOMMENDED MINIMUM CLEARANCE (SOURCE: PABLO AND MARCELL, 1995)
General
1 Primary roads Width 30 ft; Headroom 22 ft; distance from
buildings and process area 10 ft
2 Secondary Roads Width 20 ft; headroom 20 ft; distance from
buildings and process area 5 ft
3 Pump Access Aisle Ways Width 12 ft; headroom 12ft
4 Process Area Main Walkways Width 10 ft; headroom 8 ft
5 Process Areas Service Walkways Width 4 ft; headroom 7 ft
6 Main Pipe Racks Headroom 22 ft
71
7 Secondary Pipe Racks Headroom 15 ft
8 Floor Elevations
The vertical distance between operating
levels must be no less than height of the
tallest process vessel plus 8 ft
Around Hazardous Areas
9 Flare 100 ft
Around Process Equipment
Tank Farms:
10 Between tanks 0.5 diameter
11 From tank to dike wall 5 ft
12 Access around diked area 10 ft
13 Dike capacity largest tank plus 10%
14 Around compressor 10 ft
Between Adjacent Vertical Vessels
15 3 ft diameter 4 ft
16 3-6 ft diameter 6 ft
17 over 6 ft diameter 10 ft
Between Adjacent horizontal Vessels
18 Up to 10 ft diameter up to 10 ft diameter
19 more than 10 ft diameter more than 10 ft diameter
20 Between Horizontal Heat Exchangers 4 ft
21 Between Vertical Heat Exchangers 2 ft
72
CHAPTER 6: WASTE TREATMENT
6.1 INTRODUCTION
Waste is a general problem in chemical plant operation especially in the developing country
where the rules and regulations are very strict regarding the waste disposal. A plant takes
few raw materials to produce products through several stages of processes for the sole
purpose of generating income. But it is not possible to convert all the raw materials into
saleable products thus generating unwanted waste or residual.
The wastewater is essentially the water supply of the community after it has been fouled by
a variety of usage. Wastewater source of generation may be define as a combination of the
liquid or water that carries wastes removed from the residences, institutions and industrial
establishments, together with such groundwater, surface water, and storm water. The
decomposition of untreated accumulation of wastewater will produce large quantities of
malodorous gases. It also contains numerous pathogenic microorganisms that inhabit the
intestinal tract or that may be present in certain industrial waste. Toxic contaminant in
wastewater may lead to fatality of all organisms including aquatic or land inhibited animals
and even human beings. Non-biodegradable waste that accumulated in the food chain is
absorbed into our body system hence leads to serious sickness such as cancer, food
poisoning and others. For these reasons, the treatment of wastewater is necessary in an
industrialized society.
The wastewater treatment involves the primary treatment for the solid removing, such as
screening and sedimentation, the secondary treatment involves biological or chemical
treatment and tertiary treatment for the nutrient removal. The increase in environmental
awareness has pushed the authority to implement strict regulations to limit the release of
proven and potentially hazardous materials by chemical plants.
73
6.2 WASTE MINIMIZATION
A waste is best solved from the source. Minimizing the waste is the most effective way to
counter the waste problem. This includes reducing or recycling the materials that contribute
to waste and resulting in a reduction of total quantity of the waste altogether.
The most preferable way of waste minimization is the prevention of the waste. But
this would also be the least economical and logical way of handling the waste
because in a process plant, to produce a product, there also will be byproducts
created. Byproduct is the main contributor to the unwanted waste.
The other major step in waste minimization is by increasing the efficiency of the
process equipment. Increasing the efficiency means less byproduct or waste will be
produce by the equipment. But for each percentage of efficiency increment, the
tradeoff is the increasing of the overall cost. The cost estimation must be done
thoroughly in order to get the optimum operating conditions for all major equipment
that contributes to producing waste such as reactor, separator and absorber.
The third option which is highly adapted in all process plant is reuse or recycle of
materials. This is the most favorable method in term of cost and the waste
minimization.
The least favorable option of waste handling is disposal of the waste. Disposal of the
waste to the environment must be under the minimum quantity as possible.
6.3 WASTE AUDIT
The discharge from the plant has been identified and there are 3 major wastes. These wastes
are divided into three categories; gaseous waste, liquid waste and solid waste.
The gaseous waste is the off gas released from Absorber (C-2). It contains nitrogen,
carbon dioxide, carbon monoxide and traces of other materials.
The liquid wastes from Deisobutanizer (C-1) contain isobutane. Besides, other
consideration likes dibutyl phthalate discharge or leakage into waste water treatment
from Absorber (C-2) and Stripper (C-3). Also from surface runoff during the raining
74
seasons in the plant area contains traces of other materials. Non-acidic waste is from
the drainage system in the plant area.
Table 30 below shows the streams and type of waste discharged.
TABLE 30: WASTE STREAMS PROPERTIES
Parameter Stream 3 Stream 15 Stream 18
Waste Isobutane Off-gas Water
Type of waste Liquid Gaseous Gaseous
Type of treatment Recycle and
storage
Recycle,
storage, and
incinerate
Recycle to stream 10
Molar flowrate( kmol/hr) 27.50 5798.74 15.27
Temperature (oC) 55.4393 85.7274 85.0
6.4 EFFLUENT DISCHARGE STANDARD AND REQUIREMENTS
In Malaysia, Environmental Quality Act 1974 is the act relating to the prevention,
abatement, control of pollution and enhancement of the environment, and purposes
connected therewith. This parent act, consist of several acts that are enacted from time to
time. This plant is subjected to the Environmental Quality (Scheduled Waste) Regulation
2005 which caters for solid waste storage and disposal and Environmental Quality (Sewage
and Industrial Effluents)Regulation 1979 which caters for the wastewater released.
6.4.1 Purpose of Effluent Standards
The sole purpose of these Effluent Standards for the discharge from wastewater treatment
plants is to control and disposal of effluent to the waters. This will protect the receiving
waters and the living aquatic ecosystems. The public health also must be taken into
75
consideration. These standards are crucial because wastewater discharges have been known
to contribute considerable amount of the biodegradable organic matter and suspended solids
into the receiving waters.
These standards stated the maximum values of waste parameters which must not be
exceeded in order to release the wastewater into the environment. After taking this into
consideration, the design parameters of all the effluent should be less than the standards
mentioned in order to ensure that the waste generated by the plant will fall within the
required degree.
6.4.2 Liquid waste
There are two standards for effluent discharge specified in the Environmental Quality Act
(EQA) 1974:
1. Standard A for discharge upstream of any raw water intake.
2. Standard B for discharge downstream of any raw water intake.
The standards are listed in the Third Schedule of the Environmental Quality Act 1974,
under the Environmental Quality (Sewage and Industrial Effluents) Regulations, 1979,
regulations 8 (1), 8 (2) and 8 (3). An extract of the standards is given below:
TABLE 31: ENVIRONMENTAL QUALITY (SEWAGE AND INDUSTRIAL EFFLUENTS)
REGULATIONS, 1979 (EXTRACT)
Parameters Standard A Standard B
Temperature 40°C 40°C
pH value 6.0-9.00 5.5-9
BOD5 20mg/l 50mg/l
COD 50mg/l 100mg/l
Phenol 0.001mg/l 1.0mg/l
Sulphide 0.50mg/l 0.50mg/l
Oil and Grease Not Detectable 10mg/l
76
TABLE 32: PLANT WASTEWATER AND STANDARD B VALUES OF EQA
Parameter Unit Standard B Plant wastewater
Temperature ˚C 40 40
PH value 5.5-9.0 5.0-9.0
BOD5 at 20˚C ppm 20 10000
COD ppm 50 5000
Phenol mg/l 1.0 >1.0
Oil mg/l 10 >10
6.4.3 Gaseous Waste
The purge gases from the plant process line include n-butane, nitrogen, oxygen, carbon
monoxide, carbon dioxide, water vapor and a little amount of maleic anhydride. The
emission of these gaseous is monitored and controlled to meet the requirements of the
Environmental Quality (Clean Air) Regulations, 1978 under the Malaysian Clean Air
Standards for Dark Smoke and Solid Particle
6.4.4 Solid waste
Under the Environmental Quality (Scheduled Wastes) Regulations 2005, solid waste is
categorized under scheduled wastes and must be treated with outmost care. The appropriate
safety procedure is required in collecting, packaging, storing and transporting the solid
waste. The solid waste is sent to Kualiti Alam Sdn. Bhd. for disposal.
6.5 TREATMENT STRATEGY
TABLE 33: METHOD OF REMOVAL ACCORDING TO WASTE COMPONENT
Wastewater Component Removal Process Level of
Treatment
Oil and Grease (components of
wastewater from other
sources)
Aerated Grit removal
Primary
Suspended Solid Screening, Aerated grit removal
77
Volatile Organic
Compounds:
Maleic anhydride, dibutyl
phthalate
Equalization tank, Clarifier
Secondary
Acid (H2SO4)and
Caustic (NaoH)(used for
pH adjustment)
Clarifier, sludge dewatering
Alum Al2(SO4)3 (used as
chemical coagulant)
Clarifier, sludge dewatering
Sludge Sludge dewatering Unit (centrifuge),
Mechanical Sludge Dewatering (filter
press). Treated sludge shall be sent to
Kualiti Alam Sdn. Bhd. for disposal.
Tertiary
Besides that, wastes of isobutane from stream 3 (S3) will be recycled and stored in the
storage tank for selling.
FIGURE 14: ISOBUTANE STORAGE TANK
78
SECONDARY TREATMENT PRIMARY TREATMENT
TERTIARY TREATMENT
1
SCREENING AND
GRIT REMOVAL
3
BIOLOGICAL
TREATMENT
2
SETTLING AND CHEMICAL
TREATMENT
TREATMENT STAGES
4
PHYSICAL
SEPARATION
6
DISINFECTION
7
NUTRIENT
REMOVAL
5
SCHEDULED
WASTE HANDLING
FIGURE 15: BLOCK DIAGRAM OF WASTEWATER TREATMENT PLANT
79
FIGURE 16: FLOW SHEET OF WASTEWATER TREATMENT PLANT
SECONDARY TREATMENT PRIMARY TREATMENT
TERTIARY TREATMENT
TERTIARY TREATMENT
Untreated
wastewater
Screening
Aerated Grit
Removal
Acid
pH
Stabilizer
Equalization Tank
Alum
Coagulation Tank
Clarifier
Disinfection
biopond
Mechanical
Sludge
Thickener
Sludge
Storage Area
For Disposal
Flowsheet of Wastewater
Treatment Plant
Sludge
dewatering
Caustic
Spent water
Two-Stage
Centrifugal
Separator
SludgeSludge Cake
sea
80
6.6 SCREENING PROCESS
This is the first stage of waste treatment which is the primary treatment stage. The screening
facility purposes are:
To protect downstream equipments and processes by removing debris and other big
particles.
To reduce interference with in plant flow
To minimize blockages in sludge handling facility
6.6.1 Aerated Grit Removal
The grit removal process is also included under the primary treatment stage. The flow
velocity is reduced to allow retention time for larger and heavier particles to settle out. The
grit removal facility purposes are:
To remove grit that will cause problem to pumps and sludge treatment and
dewatering
To remove grease that will cause problem to clarifier
Both grit and grease contain big particles that cannot be broken down by chemical
and biological treatment later.
6.6.2 pH Stabilizer
The pH stabilizer facility falls under the secondary treatment which is the chemical treatment
stage. It consists of multiple mixers to facilitate the mixing of acid and base in order to
stabilize the pH inside the equipment. The purpose of adjusting the pH:
To protect downstream process and equipment from high acidity water that is
corrosive in nature.
Non-neutral pH of wastewater is unacceptable at the biological treatment facility
because it is toxic to the microorganism
6.6.3 Equalization Tank
Secondary treatment stage also includes the equalization tank. The purposes of equalizing the
flow are:
Prevent flow variation for the downstream process
Reduce potential overflow
Reduce hydraulic loading into the downstream process
81
6.6.4 Coagulation Tank
The wastewater must undergo coagulation process before entering the tertiary treatment
which is the biological treatment. The purpose of coagulation process:
Removal of suspended and colloidal solid which cannot be removed by sedimentation.
Reduce soluble organic content in the wastewater consequently reducing the COD
and BOD values.
Removal of metals, phosphorous and colored substances
6.6.5 Clarifier
The first phase of tertiary treatment stage is the clarifier facility. It provided the
sedimentation time which reduces the velocity of wastewater that will allow organic matter in
suspended solid to settle out. The purpose of this facility:
Remove maximum amount of solids
Separate wastewater into sludge and spent water which will be treated separately for
optimum efficiency.
6.6.6 Sludge Dewatering
All treatment processes will generate significant amount of sludge containing inert and non-
biodegradable organic matter. This particular type of sludge must be dispose because it
cannot be treated anymore. Purpose of sludge dewatering facility:
Remove the water contain in the sludge.
Separate the water from sludge
Turned the sludge into sludge cake with low percentage of water.
6.6.7 Mechanical Sludge Thickener
The main purpose of this equipment is to thicken the sludge cake from 1% dry solid to about
6% dry solid content. The thickening equipment used is the gravity belt thickener. To
increase the thickening process, a chemical dosing conditioning also injected into the sludge.
6.6.8 Sludge Storage
The dried sludge cake will be stored for 30 days before disposal to allow sufficient
accumulation of the required quantity of sludge to be disposed. The storage building or
82
structure must have a roof with partly open walls to allow good ventilation. For good conduct
and safety, the storage area should be situated downwind.
6.6.9 Disinfection
The main reason for the disinfection facility is to destruct selective disease causing organism
in the wastewater. Disinfection is important for the wastewater that will be released out into
the open water system. Usage of calcium hypoclorite is the most preferable option because
the typical chlorination type of disinfection is very harmful to operator. Good mixing during
the disinfection stage is important.
6.6.10 Biopond
The biopond facility will provide the last biological treatment before releasing the wastewater
to sea. The wastewater from the disinfection phase will be exposed to microorganism that
will dissolve the remaining organic substances. But the ratio of wastewater from the
disinfection phase must be kept very low to the ratio of wastewater contained in the biopond.
This is to facilitate the dilution process where all the traces of calcium hypoclorite would not
have any affect anymore. This is crucial to prevent toxicity to microorganism in the biopond.
The holding period of treated wastewater in the biopond will range from one to two week
before releasing to receiving water. So the volume of the biopond will have to be bigger.
6.7 GAS TREATMENT
When making contact with the gaseous waste, there are few methods available for the
treatment. The methods are incineration, condensation, adsorption and flaring. All the
treatment method has been studied and the limitation of each method is taken into account
when choosing the best method to be used to treat the gaseous waste. The limitation as shown
in the table:
TABLE 34: SUMMARY OF THE LIMITATIONS FOR THE GASEOUS TREATMENT STRATEGY
Treatment
Method Limitation
Control by
flaring
More economical since the gaseous wastes is not going to be recover
or as the result of intermittent, uncertain or emergency process
operations
The combustion of VOCs will produce harmless or much less
83
harmful substances since the flare temperature will be operating
below 1000 K to avoid the formation of NOx
Flare will be injected with steam to enhance mixing so that the
combustion process will be as complete as practical
Control by
adsorption
Normally used for large VOCs content stream for recovery
Not economical for small stream
Activated carbon is a very effective adsorbent in removing VOCs,
but quite expensive
Control by
incineration
Not practical for low gas flow
The N2 presents in the gas stream may enter the atmosphere partly as
N2, NO or NO2
Incomplete combustion of gas stream can produce an exhaust gas
that is more harmful than the input gas
Additional fuel is require to burn the VOCs if the total mass fraction
of VOCs too small
If a heat exchanger is installed to lower the cost of fuel, the cost of
the heat exchanger itself is high and may lead to corrosion problem
If catalytic incinerator is applied, the fuel cost is greatly reduced and
the operating temperature is low. However, the catalyst will
significantly increase the operating cost
Control by
condensation
Normally used for large VOCs content stream for recovery purpose
This method is not economical for small stream
The temperature is low enough that ordinary one-stage refrigerators
cannot be used
Often the temperatures required for high removal efficiency are
below the freezing temperature of the material being removed so that
the material freezes on the cooling coils, requiring frequent
defrosting
If the gas being treated contains significant amounts of water vapor,
it will condense and freeze on the cooling coil, this requiring
frequent defrosting
84
After considering all the options, the flaring method has been chosen because it fulfills the
entire requirement and suitable to treat the gaseous waste discharge at the off gas line. Its
systems are the satisfactory provision in the design and operation of the basic requirements
for combustion.
These gases must be release to maintain the operating pressure of the equipment in the
process plant from daily operation and also during the emergency shutdown. The main
control that needs to be maintained along the flaring process is the control of proper steam
flow. This is because with proper steam flow, smokeless operation can be maintained at all
conditions of gas flow, which provide an almost complete combustion of gaseous. To
conform to the Environmental Quality (Clean Air) Regulations 1978, a filter should be
installed at the stack gas tip before releasing the gas. Gas quality monitoring system should
also be installed in order to ensure that the gas release is within the acceptable range.
Besides that, the nitrogen gaseous that was produced at stream 15 (S15) will be separated by
using nitrogen separator and will be used as process blanket. The other component such as
isobutane will be recycled and kept in the storage tank for selling.
FIGURE 17: NITROGEN SEPARATOR
For the gas waste from the stream 18 (S18) will also be channeled to the flare for combustion.
85
FIGURE 18: WASTE OF STREAM 18 (S18)
6.8 SOLID HANDLING TREATMENT
Solid wastes of the plant are generated from different processes, chemical handling
operations as well as from wastewater treatment, which consists of hazardous and non-
hazardous wastes. Hazardous waste is defined as any solid waste listed as hazardous or
possesses one or more hazardous characteristics as defined in federal waste regulations. Its
effect can last for very long periods of time. Major solid wastes are typically in the form of
sludge, scrap and spent process catalyst and it’s divided into three; scheduled waste, recycled
waste and domestic waste.
There are a few treatment methods in handling the solid waste and it have been summarized
in Table 35 below:
TABLE 35: DISPOSAL METHODS OF SOLID WASTE
Solid Waste Disposal/Treatment Method
Tank bottom sludge (from Wastewater
Plant)
Sent to KualitiAlam
Empty Drums Returned to supplier
Wood, metal scrap/various valuables like
empty drums
Miscellaneous (paper, plastic, domestic
waste)
Sold to contractors
Disposed off through a Contractor
86
6.9 SCHEDULED WASTE
Scheduled wastes, one of the solid wastes produced in the plant is a small percentage of
hazardous waste, which has been regarded for a long time as intractable, or difficult to safely
dispose of, without special technologies and facilities. It is also can be defined as a material
or article containing a chemical, or mixture of chemicals, exceeding the threshold
concentration and threshold quantity which are:
organic in nature
resistant to degradation by chemical, physical or biological means
toxic to humans, animals, vegetation or aquatic life
bio-accumulative in humans, flora and fauna
According to Environmental Quality (Scheduled Wastes) Regulations, 1989, solid waste is
categorized under scheduled wastes, and must be treated appropriately. It is the duty of the
plant management to adopt safety procedure in collecting, packaging, inventorying and
transporting the solid waste to suitable parties before further treatment. Sludge is turned into
sludge cake to reduce the weight and for ease of loading into plastic lined drums before being
transported.
87
CHAPTER 7: PROJECT ECONOMICS AND COST ESTIMATION
7.1 INTRODUCTION
The economic evaluation of a plant is important in determining the profitability of a
plant in generating profit. Therefore, before building any plant, the design engineer needs to
decide between alternative designs to be implemented as well as the overall plant economics.
In evaluating the project economics, estimates of investment and equipment costs are
required. Before the final process design starts, company management normally becomes
involved to decide if significant capital funds will be committed to the project or not.
7.1.1 Capital Investment
The estimation of Total Capital Investment and Total Product Cost of the project are
determined by using the methods suggested by Peters and Timmerhaus .Equipment
purchasing amount are determined by using method by Warren D.Seider, J.D Seader and
Daniel R.Lewin.
The capital needed to supply the required manufacturing and plant facilities is called fixed
capital investment (FCI) while that necessary for the operation of plant is termed the working
capital (WC). Start-up Cost (SC) is the cost required at first once the process of the plant is
started. Thus the sum of the fixed capital investment, working capital start-up cost is known
as the total capital investment (TCI). Furthermore, cash flow and discounted cash flow are
also constructed in determining the Pay-Back Period as well as Net Present Value for the
project.
Fixed capital investment can be divided into two that are manufacturing fixed capital
investment (direct cost) and non-manufacturing fixed capital investment (indirect cost).
Basically, FCI depends on the total equipments cost available in the plant multiply with a
factor that varies according to what type of cost it represents. Meanwhile, working capital is
the additional investment needed, over and above the fixed capital, to start the plant up and
operate it to the point when income is earned.
The calculation made follows the Douglas’s approach method
The interest rate for plant operation is 10% per annum
Project life-cycle will be 15 years
Plant operates at normal annual operation period which is 330 days
88
7.1.2 Total Equipment Cost (TEC)
Capital cost estimate for chemical process plants can be based on purchase cost estimation of
the major equipment items. The equipment cost will be used along with factors for estimating
other relevant costs(Sinnott.2005).
TABLE 36: TOTAL EQUIPMENT COST
Equipments Cost Quantity Total Cost (USD) Total Cost
(RM)
Expander 1000000 1 1000000 3059039.462
Centrifugal Separator 1340000 1 1340000 4099112.879
Butane Tank 160000 1 160000 489446.3139
Cooler 1 59500 1 59500 182012.848
Cooler 2 67000 1 67000 204955.6439
Heat Exchanger 1 245000 1 245000 749464.6681
Heat Exchanger 2 116000 1 116000 354848.5775
Heat Exchanger 3 134500 1 134500 411440.8076
Absorber 1580000 1 1580000 4833282.349
Recycle Pump 13000 3 39000 119302.539
Deisobutanizer 570000 1 570000 1743652.493
Stripper 343000 1 343000 1049250.535
MAN Tank 238000 1 238000 728051.3919
Reaction Reactor (incl catalyst) 620000 1 620000 1896604.466
Mixer 160000 1 160000 489446.3139
TOTAL EQUIPMENT COST 20409911.29
In order to estimate the capital cost for chemical process plant, the factorial method of cost
estimation is used. To make a more accurate estimate, the cost factors that are compounded
into the ‘Lang factor’ are considered individually.
7.1.3 Fixed Capital Investment
The direct cost and indirect cost items incurred in the construction that are used to
calculate Fixed Capital Investment of a plant are as such :
FCI = Total Equipment Cost * Lang’s Factor
= RM 71965347.20 (in 2004)
89
Fixed Capital Investment (FCI) = FCI (2004) * (CEPCI 2012/CEPCI2004)
= 94889923.13
Total Capital Investment = Working Capital (15% FCI) + S/Up Cost (10% FCI) + FCI
= RM 118 612 403.90
7.1.4 Estimation of Total Operating Cost
All expenses directly connected with the manufacturing operation or the physical equipment
of a process plant is included in the operating costs.
Raw Material
98838109.36
Utilities Cold Utilities
25192299
Maintenance Cost 2% of FCI
1897798.463
Operating Supplies 10% of Maintenance Cost
189779.8463
Operating Labour
720000
Management Personnel 10% of Operating Labour
72000
Laboratory Charges 5% of Operating Labour
36000
Patent and Royalties 1% of Total Expenses
1269459.867
TOTAL VARIABLE COST 128215446.5
Local tax 1% of FCI
948899.2313
Insurance 0.4% of FCI
379559.6925
FIXED CHARGES 1328458.924
PLANT OVERHEAD 50% (Maintenance + Labour + Supervision) 1344899.231
TOTAL MANUFACTURING COST 130888804.7
Administrative Cost 15% (Maintenance + Labour + Supervision) 403469.7694
Distribution and Selling 10% of TMC
13088880.47
R&D 5% of TMC
6544440.235
TOTAL GENERAL EXPENSES 20036790.47
TOTAL OPERATING COST = Total Manufacturing Cost + General Expenses
= RM 150,925,595.20
7.1.5 Gross Profit
For the case of this plant, the revenue comes from solely selling of MAN as shown below:
Profit = Total Sale – Total Operating Cost
= (RM 7 944.33/ton x 50000tonne/yr) – 150,925,595.20
= RM 177,395,904.80/year
90
7.2 PROFITABILITY ANALYSIS
In determining the economic attractiveness of a project, it is important to based decision three
important economic parameters which are Investment Rate of Return (IRR), Net Present
Value (NPV) and Pay Back Period (PBP). Several assumptions are made in the economic
analysis of this maleic anhydride acid plant. The assumptions are as follows:
The plant has a project plant life of 15 years.
The plant construction period is 3 years before commencing production. Hence,
the total investment cost is distributed evenly between the 3 years.
Interest rate is 15%
Local Taxes is assumed to be at 10% annually.
7.2.1 Start-up Period
The plant will start up in year 4. The plant construction assumed to be last for 3 years.
TABLE 37: CAPITAL INVESTMENT FOR START-UP PERIOD
Start up period of 3 years
Year 0 Equipment & Design - 29602641.93
Year 1 (Direct Cost – Year 1 Cost)/2 -19895528
Year 2 As year 1 -19895528
Year 3 Indirect Cost + S/up cost -26294129.60
Total -95687827.53
7.2.2 Depreciation
When government taxing comes into place, depreciation becomes important to aid the
plant from balancing tax payment to equipment wear. In this project, depreciation per annum
can be computed as.
millionRM
RMRM
n
SVBDt
7.7
15
)394889923.103.0(9118612403.
15
)Investment Capital Fixed0.03-(B
91
life edepreciabl expected n
Investment Capital Fixed0.03x value,salvage estimated SV
investment total B
chargeon depreciati annualD
n)1,2......,(tyear t
where
t
7.2.3 Cash Flow Estimation
Here, the net cash flow in each year of the project is brought to its “present worth” at the start
of the project by discounting it at some chosen compound interest.
years projects, of life t
cent/100per rate)est rate(interdiscount r
nyear in flowcash net estimated NFW where,
11
tn
nnr)(
NFWt of projecTotal NPW
A discount rate of 15% is used
From the investment as Table 37 and also annual gross earning, cash flow diagram is as
follow, to obtain the payback period.
FIGURE 19: CASH FLOW DIAGRAM
92
7.2.4 Net Present Worth
TABLE 38: CUMULATIVE CASH FLOW
r (%) NPW (Cumulative Cash Flow at years 15) (RM)
10 630341893
20 255582162
30 102887451
40 33344914
50 -1062648
From the net present worth calculated by varying the discount rate, it will reach negative
when the rate is in between 40-50%, this is higher than MARR, thus project is feasible.
7.2.5 Internal Rate of return
7.2.6 Rate of Return (ROR) Estimation
The simplest method is to base the ROR on the average income over the life of the project
and the original investment.
%43.22%10091118612403.15
399036617
100
per centnvestmentoriginal iojectLife of pr
ctd of projeflow at en net cash CumulativeROR
Expected ROR (Rate of Return) must at least meet or exceed the MARR (Minimum
Attractive Rate of Return) of 15%. Since, the rate of return of the project is 22.43%, which is
more than 15%, the project is worth investing.
7.2.7 Net Present Value or Worth (NPV) Estimation
years projects, of life t
cent/100per return of rate flowcash discountedr
nyear in flowcash net estimated NFW
where,
11'
tn
nn)r(
NFWNPW
NPV calculated is RM 399 million
93
7.2.8 Pay Back Time
Pay Back Period the time that must elapse after startup until cumulative undiscounted cash
flow repays fixed capital investment. For this project, it is 5 years.
FIGURE 20: PAYBACK TIME
7.3 DISCUSSIONS
From the economic analysis done, the plant will need a capital investment of RM RM118.612
million. An internal rate of return (IRR) of 49 % and a net present value (NPW) of RM 399
million is attainable for a project plant life of 15 years with a payback time of 5 years after
plant startup. In addition, annual sales will generate an income of RM 177.395million
annually. In fact the return on investment is 22.43%, which is higher than MARR, hence, this
indicates that the plant is economically viable and economically attractive. The economic
evaluation conducted on the maleic anhydride plant at this stage serves only as a very crude
estimation.
Furthermore, the correlations taken from different references may give different value and
methods in estimating the plants cost. In addition, the assumptions made may also be invalid,
considering the fact that economic environment is very sensitive to the global environment
and may subject to changes from time to time. Apart from that, it is very difficult to predict
the actual annual cash flow since the reliability of the plant equipments is not known. Hence,
the actual investment cost may be larger than the predicted figure. For improvement, a
concise economic evaluation should be carry out by considering all the factors mentioned
above to obtain the best economic potential for the MAN plant.
-5E+08
0
500000000
1E+09
1.5E+09
2E+09
0 5 10 15
Cu
mu
lati
ve C
ash
Flo
w (
RM
)
Year
Payback Period
94
CHAPTER 8: CONCLUSION & RECOMMENDATION
8.1 CONCLUSION
The overall design project for the production of Maleic Anhydride meets the desired
requirements and objectives. The production of 50,000 metric tonne per year of Maleic
Anhydride has a bright future especially in the South East Asia region. From the feasibility
study carried out, the future growth of Maleic Anhydride demand in the South East Asia
market is optimistic, 4.5 % per year growth on Maleic Anhydride consumption is forecasted
until year 2009.
The proposed plant is situated at Kidurong Industrial Estate which is feasible, economically
and environmentally. Moreover, the utilities supply such as cooling water supply, deionized
water, electricity and steam supply required for the process can be easily obtained.
The process chosen for the production of Maleic Anhydride is the catalytic oxidization of n-
butane. Heuristics approach has been applied in identifying the appropriate design. For the
process synthesis and flow sheeting, base case material and energy balance together with
process simulation has been performed both by manual calculation and iCON simulator.
Detailed equipment process design and mechanical engineering design of all major
equipment has been performed. A highly integrated heat exchanger network and process
control system is also included to the proposed plant to ensure the profitability of the plant.
In responding to the environmental responsibility, the plant has been designed to achieve the
target of waste minimization and cost minimization. The unwanted side product is being
combusted and well treated to ensure the emission coming out from the plant has met the
Malaysian government Environment Quality Act, 1974. On the safety aspect, HAZOP study
has been conducted to identify the occurrence of operational problems and providing
necessary resolution. A general safety study includes personal safety, emergency
management, Standard Operation Procedures (SOP) and plant start up and shut down
procedures were documented in this report as well.
95
As for the economic evaluation of the process plant, the cost of the plant is calculated by
using detailed factorial method. The total capital investment of the plant is approximately RM
118 million. The Rate of Return (ROR) is 22.43 % which is higher than Minimum Attractive
Rate of Return (MARR) 15 %, therefore the project is worth investing. The payback period is
5 years after plant start-up which is within feasible period of time.
Finally, it can be concluded that the construction of a 50,000 metric tonne per year of Maleic
Anhydride production plant in Kidurong, Bintulu is technically feasible and economically
attractive.
8.2 RECOMMENDATION
The final year design project has been useful in cultivating and enhancing the skills and
knowledge at hand. As final year students, the experience gained throughout the process of
this project has given the opportunity to actually design a real processing plant has increase
our understanding in the chemical engineering field. Besides that, other skills were also
developed in the process such as communication skills, management skill, and team work.
However, we find that there few areas that needs improvements and perhaps a new approach
in solving some of the problems faced.
Firstly, we recommend that the PDP committee provide standardized values of key elements
such as the feeds prices. We have different values of feed because taking it from different
sources. So, a standardized value is appropriate to accommodate the student with a good
reference. Secondly, further research must be done on isomeric conversion technology in
order to convert isomers back to its normal state. This is important to reduce the amount of
byproduct produced from the process. Thirdly, we propose that students should be provided
easier access to the labs to use engineering software such as HYSYS and AutoCAD and the
department should provide a proper manual as guidance. Finally, a complete and clear
guidance should be provided to the student and without further amendment. Students are
facing difficulty to cope with sudden changes and added requirements made by the
coordinator due to the short time frame to finish it.
We hope that these recommendations will be considered and useful by the PDP committee to
improve the PDP project handled by the student in the future.
96
REFERENCES
(1992). Maleic Anhydride World Survey. London: Tecnon(U.K.) Ltd.
Maleic Anhydride. (2011, November). Retrieved June 2, 2012, from IHS Chemical:
http://www.ihs.com/products/chemical/planning/ceh/maleic-anyhydride.aspx
Maleic Anhydride. (2011). Retrieved June 4, 2012, from Thirumalai Chemicals Ltd.:
http://www.thirumalaichemicals.com/maleic.html
AP-42, CH 6.14: Maleic Anhydride. (n.d.). Retrieved June 1, 2012, from
www.epa.gov/ttnchie1/ap42/ch06/final/c06s14.pdf
BDA. (2010, April 10). Official Website of Bintulu Development Authority. Retrieved June
11, 2012, from Bintulu Development Authority Official Website:
http://www.bda.gov.my/modules/web/index.php?menu_id=0&sub_id=1
Fogler, H. S. (2006). Elements of Chemical Reaction Engineering (4th ed.). New Jersey:
Pearson Education Inc.
Ishak, M. (2011, September 1). Bintulu Analysis. The Report, SARAWAK 2011, 34-43.
Jose, S. (2008, November 3). World Maleic Anhydride Market to Reach 2.0 Million Metric
Tons by 2012, According to New Report by Global Industry Analysts. Retrieved June
4, 2012, from PRWeb:
http://www.prweb.com/releases/maleic_anhydride/butanediol/prweb1553754.htm
KKIP. (1995, November 2). Investing in KKIP. Retrieved June 12, 2012, from Kota Kinabalu
Industrial Park: http://www.sabah.com.my/kkip/inv.html
Lohbeck, K., Haferkorn, H., Fuhrmann, W., & Fedtke, N. (2005). Maleic and Fumaric Acids.
In Ullmann's Encyclopedia of Industrial Chemistry. Weinheim: Wiley-VCH.
Pinch Analysis. (n.d.). Retrieved August 25, 2012, from KBC Nextgen Performance:
http://www.kbcat.com/?id=51&fm=search&searchText=pinch%20analysis
Production of Maleic Anhydride. (n.d.). Retrieved June 6, 2012, from
www.che.cemr.wvu.edu/publications/projects/large.../maleic.PDF
Production of Phthalate Anhydride from O-xylene. (n.d.). Retrieved June 7, 2012, from
www.che.cemr.wvu.edu/publications/.../phthalic2/phthalic2-b.pdf
97
Sarawak Government. (2010, April 20). Sarawak Government Portal | Investment Incentives.
Retrieved June 11, 2012, from The Official Portal of Sarawak Government:
http://www.sarawak.gov.my/en/investors/investment-incentives
Silla, H. (2003). Chemical Process Engineering Design and Economics. USA: Marcel
Dekker.
Timbang, M. (2007, March 2). Bintulu - Wikipedia, the free encyclopedia. Retrieved June 11,
2012, from Wikipedia: http://en.wikipedia.org/wiki/Bintulu
Timothy R. Felthouse, J. C.-J. (2001, April 26). Department of Chemistry. Retrieved June 2,
2012, from University of South Alabama:
http://www.southalabama.edu/chemistry/barletta/felthouse.pdf
Tissue, B. M. (2000). The Chemistry Hypermedia Project. Retrieved August 1, 2012, from
CHP website: http://www.files.chem.vt.edu/chem-ed/sep/gc/gc.html
Town and Regional Planning Department Sabah. (2011, January 1). Land Zoned for Industry
Sabah. Retrieved June 12, 2012, from Jabatan Perancang Wilayah dan Negeri Sabah:
http://www.townplanning.sabah.gov.my/
US EPA. (2011, July 8). Oil and Gas Production Waste | Radiation Protection | US EPA.
Retrieved July 25, 2012, from US Environmental Protection Agency:
http://www.epa.gov/rpdweb00/tenorm/oilandgas.html#scale
Woril Turner Dudley, V. K. (2012, January 3). Maleic Anhydride - Process Design.
Retrieved June 2, 2012, from Scribd.: http://www.scribd.com/doc/76994917/Maleic-
Anhydride-Process-Design#
98
APPENDICES
APPENDIX 1: PROCESS FLOW DIAGRAM OF MAN PLANT .................................................I
APPENDIX 2: P&ID OF MAN PRODUCTION PLANT ............................................................ II
APPENDIX 3: CRITERIAS FOR EACH SITE PLANNED ...................................................... III
APPENDIX 4: MASS BALANCE CALCULATION (DEISOBUTANIZER) ............................... V
APPENDIX 5: MASS ENERGY BALANCE (MIXER) ............................................................. IX
APPENDIX 6: MASS ENERGY BALANCE (REACTOR) ......................................................... X
APPENDIX 7: MASS ENERGY BALANCE (ABSORBER) ..................................................... XII
APPENDIX 8: MASS ENERGY BALANCE (STRIPPER) ..................................................... XIII
APPENDIX 9: CP VALUE FOR ENERGY BALANCE CALCULATION ............................ XVII
APPENDIX 10: DRAFT OF PLANT LAYOUT ..................................................................... XIX
i
APPENDIX 1: PROCESS FLOW DIAGRAM OF MAN PLANT
ii
APPENDIX 2: P&ID OF MAN PRODUCTION PLANT
iii
APPENDIX 3: CRITERIAS FOR EACH SITE PLANNED
Selection Criteria Kidurong Industrial Area
Kota Kinabalu Industrial
Park
PasirGudang Industrial
Estate
Kertih Integrated
Petrochemical Complex
PengerangIntergrated
Petroleum Complex
Location 20 km from Bintulu Town 25 km from KK 36km from Johor Bharu 5 km from Paka and 9.6 km
from Kemaman 42km from Johor Bharu
Type of industry Light & Medium Any compatible Light, Medium & Heavy Petrochemical, Chemical and
General Petrochemical and refinery
Preferred
Petrochemical and gas Food
Petrochemical
Timber-based Timber-based
Plantation and Agro Plantation-based
Energy Intensive
Area available 97.3 hectare 7.05 acres 430 acres 100 acres 22, 500 acres
Land price(per m2) RM77.42 RM129.17 RM 86.08 – 236.72 RM20 RM64.58-RM86.11
Raw material
Optimal, Kerteh PETRONAS Gas Berhad
PETRONAS Rapid (LNG
Regasification Plant) Supplier Amoco Chemicals, Gebeng
Power Supply SESCO’S Combined Cycle
Power Plant (132MW)
KKIP Power SdnBhd Sultan Iskandar Power
Station (644 MW)
TasikKenyir Hydroelectric
Dam Sultan Iskandar Power
Station (TNB)
(300MW) (400MW)
Bakun Hydroelectricity
Power Project (2400MW)
Powertron Resources S/B IPP YTL Power Generation
Sdn. Bhd. IPP YTL (600 MW)
PasirGudang Power Station
(YTL Power International
Bhd) (120MW)
Sarawak Power Generation
Plant (220MW)
Sabah Electricity SdbBhd
Paka Power plant PETRONAS Power Plant
(future planning) (293MW)
CUF Kerteh
Water Supply
Bintulu Water Supply
Treatment Plant
Diversified Water Resources
S/B Loji Air Sungai Layang Bukit Sah SAJ Holding SdnBhd
Syarikat Air Johor Sungai Cherol
Future investment on water
supply project
Loji Air Sungai Buluh Sungai Kemasik
Port Facilities Bintulu Deepwater Port Sepanggar Bay Port PasirGudang Port Kerteh Port, TanjungBerhala
Port, Kuala Terengganu port
Pengerang Petroleum
Terminal
TanjungLangsat Petroleum
Terminal
Airport Bintulu Airport Kota Kinabalu International
Airport
Senai International Airport,
Johor and Changi
International Airport,
Singapore
Sultan Mahmud Airport,
Kuala Terengganu and Sultan
Ahmad Shah Airport,
Kuantan
Senai International Airport,
Johor and Changi
International Airport,
Singapore
Railway facilities - - Singapore and North Kuantan-Kerteh Railway KTM Singapore-North
iv
Peninsular Malaysia peninsular route
Roadways
Pan-Borneo Highway KK-Sulaman Road Main road to Singapore Kuala Terengganu-Kuantan- Second Link Expressway
KK West Coast Parkway PLUS Highway Karak Highway Senai-Desaru Expressway
Federal Route 500
North-South Highway
Incentives
Pioneer Status Pioneer Status
Infrastructure Allowance. a flat corporate tax rate of 3%
of chargeable income; 5-years 70% tax exemption
on statutory income
5-years corporate tax on 15%
of statutory income Incentive for exports
Investment Tax Allowance Investment Tax Allowance
Incentives for research
development
Five-year exemption on
import duty.
100% exemption on director
fees paid to non-Malaysian
director;
Allowance of 100% in respect
of qualifying capital
expenditure incurred
Allowance of 85% in respect
of qualifying capital
expenditure incurred
Reinvestment Allowance Infrastructure Allowance Exemption from import duty
on direct raw
materials/components
5 % discount on monthly
electrical bills for first 2
years.
50% exemption on gross
employment income for non-
Malaysian professional
traders;
Allowance of 100% in respect
of qualifying capital
expenditure incurred
100% infrastructure
allowance on qualifying
expenditures
Incentives for High Tech
Industries
Land Incentives by State
Government
Pioneer Status and
Investment Tax Allowance
and Reinvestment Allowance.
25-38 % exemption on daily
water cost for 4545 m3 of
water for
tax exemption of stamp
duties on documentation
Rebate on industrial land Free Infrastructures Incentives for high tech
industries and for training
tariff protection
Pioneer Status and
Investment Tax Allowance
and Reinvestment Allowance.
tax exemption on dividends
received by or from the LITC
companies.
Incentives for high tech
industries
Local people 200 000 peoples 200 000 peoples 1500 000 peoples 200 000 peoples 40,000 people
(Below 40 years old)
Waste water management
KualitiAlamSdnBhd, Bukit
Nenas, Negeri Sembilan
Effluent Treatment Plant of
CUF
KualitiAlamSdnBhd, Bukit
Nenas, Negeri Sembilan KualitiAlamSdnBhd
Indah Water Konsortium
v
APPENDIX 4: MASS BALANCE CALCULATION (DEISOBUTANIZER)
Example Mass Balance Calculation for Deisobutanizer distillation column
Calculation of component distribution using Hengstebeck Method
Calculation of saturation pressure of each component using the equation below:
The operating condition of the column is 850C and 11atm.
The light key (LK) is isobutene distilled in the top at 55% and the heavy key (HK) is n-
butane distilled at the bottom at 99.9%
The feed flow rate is 9700 kg/h with the pre-specified feed composition.
Example calculation using propane:
Partial pressure, Pi = Psat(x) = 3487.14(0.02) = 69.74 kPa
Volatility, Ki = Pi/PT = 69.74/1114.575 = 0.063
Relative volatility, α = Ki/Khk = 0.063/0.7 = 0.09
Cmb
dij
i
i
loglog
vi
The calculation of other component is done below:
MW Component Mass
fraction
Mass flow rate Mole flow rate Mole Fraction Psat Pi Ki
44.096 Propane 0.0154 149.38 3.3876089 0.02023 3487.1483 70.54017 0.06328885
58.122 Isobutene 0.295 2861.5 49.232649 0.29399 1535.3106 451.35917 0.404960784
58.122 n-butane 0.677 6566.9 112.98476 0.67467 1162.3554 784.20863 0.703594309
56.106 Isobutene 0.0013 12.61 0.2247531 0.00134 1404.7017 1.8852229 0.001691428
56.106 1-butene 0.002 19.4 0.3457741 0.00206 1367.9095 2.8243767 0.002534039
72.149 Neopentane 0.0011 10.67 0.1478884 0.00088 881.58433 0.7785218 0.000698492
72.149 iso-pentane 0.0077 74.69 1.0352188 0.00618 524.91238 3.2448288 0.00291127
72.149 n-pentane 0.0008 7.76 0.1075552 0.00064 426.31218 0.2737991 0.000245653
Component Α log α
Propane 0.08995077 -1.0459951
Isobutene 0.57556006 -0.2399093
n-butane 1 0
Isobutene 0.00240398 -2.6190689
1-butene 0.00360156 -2.443509
Neopentane 0.00099275 -3.0031608
iso-pentane 0.00413771 -2.3832398
n-pentane 0.00034914 -3.4569996
vii
A graph of log d/b and log α is plotted for the LK and HK as reference for finding the
composition of the other components.
Example calculation for isobutene (LK):
d = 0.55(49.23) = 27.08
b = 0.45(49.23) = 22.15
d/b = 27.08/22.15 = 1.22
log d/b = 0.087
log α = -0.24
Component LK HK
F 49.23265 112.9847562
D 27.07796 0.112984756
B 22.15469 112.8717714
d/b 1.222222 0.001001001
lg d/b 0.08715 -2.99956549
lg α -0.23991 0
From the graph above, m = -12.866 and c = -2.9996.
The d/b for other components are calculated.
Example calculation for propane:
y = -12.866x - 2.9996
-3.5
-3
-2.5
-2
-1.5
-1
-0.5
0
0.5
-0.3 -0.25 -0.2 -0.15 -0.1 -0.05 0
log
d/b
log α
log d/b vs log α
viii
Mol fraction going to bottom from feed, xbi = 1/(d/b+1) = 0
Mol fraction going to distillate from feed, xdi = 1- xbi = 1
Mol flow rate component in bottom, L = xbi(mol flow rate component) = 0
Mol flow rate component in distillate, V = xdi(mol flow rate component) = 1(3.388) = 3.388
mol/hr
Component log α log di/bi di/bi Xbi xdi V L
propane -1.0459951 10.4581731 2.8719E+10 3.482E-11 1 3.38760885 1.1796E-10
isobutane -0.2399093 0.08707368 1.22200697 0.45004359 0.54995641 27.0758105 22.156838
n-butane 0 -2.9996 0.00100092 0.99900008 0.00099992 0.11297579 112.87178
isobutene -2.6190689 30.6973407 4.9813E+30 2.0075E-31 1 0.22475315 4.512E-32
1-butene -2.443509 28.4385868 2.7453E+28 3.6426E-29 1 0.34577407 1.2595E-29
neopentane -3.0031608 35.6390672 4.3558E+35 2.2958E-36 1 0.1478884 3.3952E-37
iso-pentane -2.3832398 27.6631637 4.6043E+27 2.1719E-28 1 1.03521878 2.2484E-28
n-pentane -3.4569996 41.4781574 3.0072E+41 3.3254E-42 1 0.1075552 3.5766E-43
ix
APPENDIX 5: MASS ENERGY BALANCE (MIXER)
Example Mass Balance Calculation for mixer
Input = output
Stream 4 + stream 6 = stream 7
Component Steam 4
(kg/h)
Steam 6
(kg/h)
Steam 7
(kg/h)
Isobutane 1287.80 0 1287.80
n-butane 6560.33 0 6560.33
Oxygen 0.00 39730.8667 39730.87
Water 0.00 3195.31948 3195.32
Nitrogen 0.00 130843.358 130843.36
Stream 6 is the air feed with a 65% humidity. Thus, from the Psychometer chart from
appendix figure 5.1
H=0.018kg water/kg dry air
=0.03 kgmol water/kgmol dry air
The oxygen feed must be below 0.0181 mol % which is below the flammability limit of n-
butane mixture.
By using excel, the required amount of oxygen is 39730 kg/h
Total Nitrogen = 39730(0.79/0.21) = 130843.358 kg/h
Total air = 42926.187 kg/h = 5912.33 kgmole/h
Total water with the air = 5912.33(0.03) = 177.37 kgmole/h = 130843.358 kg/hr
4
6
7
x
APPENDIX 6: MASS ENERGY BALANCE (REACTOR)
Example Mass Balance Calculation for Reactor
C4H10 + 3.5O2 C4H2O3 + 4H2O
C4H10 + 5.5O2 2CO + 2CO2 + 5H2O
Using extent of reaction method, with the assumption of pure n-butane feed and oxygen feed
is used for the sake of simplicity.
The actual process uses a mixture of n-butane feed with air at 65% humidity used as the
source of oxygen. The water entering together with air is calculated and the ratio of air to
feed is kept at a ratio of 0.017% which is below the flammability limit.
The following initial are used for reference:
b = n-butane, f = final, i = initial, MAN = maleic anhydride, CO = carbon monoxide, CO2 =
carbon dioxide, O2 = oxygen
Production:
No. of moles for n-butane:
No. of moles for MAN:
No. of moles for carbon monoxide:
No. of moles for carbon dioxide:
No. of moles for water:
No. of moles of oxygen:
Conversion = 0.822
Selectivity of MAN;
Selectivity of CO;
xi
Selectivity ratio of MAN/CO;
Assuming,
Conversion of n-butane:
Consumption of oxygen:
Production:
Reactor
n-butane = 8081.283 kg/h
Oxygen = 13715.04 kg/h
n-butane = 1438.52 kg/h
Maleic Anhydride = 9805.7
kg/h
Carbon Monoxide = 800.526
kg/h
Carbon Dioxide = 1257.806
kg/h
Water = 8750.606 kg/h
8
9
xii
APPENDIX 7: MASS ENERGY BALANCE (ABSORBER)
Example Mass Balance Calculation for Absorber column
According to the US patent 4118403, the dibutyl phthalate (DBP) absorbs 99.4% of the MAN
and 0.1% of the water in the stream.
The gas class components are assumed to exit as gases at the top of the absorber.
Volume feed entering absorber = 100217.558 m3/h
Amount of dibutyl phthalate needed according to US patent 4118403 is 0.2 kg DBP/ m3 feed
entering.
Amount DBP needed = 0.02(100217.558) = 20043.51 ≈ 20000kg/h
At the bottom of absorber:
Amount MAN = 0.96(7518.16) = 7086.58 kg/h
Amount water = 0.001(10021.49) = 100.21
Absorber 10
12
17
11
Isobutane = 1287.80 kg/h
n-butane =1167.74 kg/h
Oxygen =27884.01 kg/h
Maleic anhydride =7158.16 kg/h
Carbon monoxide =1168.42 kg/h
Carbon dioxide = 1835.85 kg/h
Water = 10021.49 kg/h
Nitrogen =130843.36 kg/h
Isobutane = 1287.80 kg/h
n-butane = 1167.74 kg/h
Oxygen = 27884.01 kg/h
Maleic anhydride = 71.58 kg/h
Carbon monoxide = 1168.42 kg/h
Carbon dioxide = 1835.85 kg/h
Water = 9921.27 kg/h
Nitrogen = 130843.36 kg/h
Dibutyl phthalate = 20000kg/h
Maleic anhydride = 7086.58 kg/h
Water = 100.21 kg/h
Dibutyl phthalate = 20000 kg/h
xiii
APPENDIX 8: MASS ENERGY BALANCE (STRIPPER)
Example Mass Balance Calculation for Deisobutanizer distillation column
Calculation of component distribution using Hengstebeck Method
Calculation of saturation pressure of each component using the equation below:
The operating condition of the column is 128.30C and 0.066atm. Since, the pressure of the
column is vacuum, a partial condenser is used to separate the vapor and liquid in the
distillate.
The light key (LK) is water distilled in the top at 99.9% and the heavy key (HK) is dibutyl
phthalate distilled at the bottom at 99.9%
The feed flow rate is 149.69 kgmole/h with the pre-specified feed composition at stream 12.
Example calculation using maleic anhydride:
Partial pressure, Pi = Psat(x) = 9.88(0.48) = 4.715 kPa
Volatility, Ki = Pi/PT = 4.715/6.666 = 0.71
Relative volatility, α = Ki/Khk = 0.71/0.016 = 290.02
The calculation of other component is done below:
Component Mole
flow rate
Mole
fraction
Psat Pi Ki α Log α
Maleic
anhydride
72.27 0.482809 9.765642 4.71494 0.707299 290.0234 2.462
Water 5.562857 0.037163 255.2772 9.486962 1.423161 583.5581 2.766
DBP 71.85366 0.480028 0.033867 0.016257 0.002439 1 0
A graph of log d/b and log α is plotted for the LK and HK as reference for finding the
composition of the other components.
Cmb
dij
i
i
loglog
xiv
Example calculation for water (LK):
d = 0.9999(5.56) = 5.56280
b = 0.001(5.56) = 0.00006
d/b = 5.56280/0.00006 = 99999
log d/b = 5
log α = 2.76608
Component LK HK
F 5.56286 71.85366
D 5.56280 0.00072
B 0.00006 71.85294
d/b 99999 0.00001
lg d/b 5 -5
lg α 2.76608 0
From the graph above, m = -3.6512 and c = -5.
The d/b for other components are calculated.
Example calculation for maleic anhydride:
Mol fraction going to bottom from feed, xbi = 1/(10672.46+1) = 0.0001
y = 3.6152x - 5
-6
-4
-2
0
2
4
6
0.00000 0.50000 1.00000 1.50000 2.00000 2.50000 3.00000 log
d/b
log α
log d/b vs log α
xv
Mol fraction going to distillate from feed, xdi = 1- xbi = 0.9999
Mol flow rate component in bottom, L = xbi(mol flow rate component) = 0.0001(72.27) =
0.013 kgmole/h
Mol flow rate component in distillate, V = xdi(mol flow rate component) = 0.9999(72.27) =
72.2572 kgmole/h
Component log α log di/bi di/bi xbi xdi V L
Maleic
anhydride
2.462 4.028 10672.464 0.000 1.000 72.263 0.007
Water 2.766 5.142 138538.604 0.000 1.000 5.563 0.000
DBP 0.000 -5.000 0.000 1.000 0.000 0.001 71.853
Calculation for partial condenser at the distillate:
Total moles entering flash drum at condenser = 74.69 kgmol/day
Zj=mol fraction in feed, Xj=mol fraction in liquid in outlet, Yj=mol fraction in vapour in
outlet,F
V=vapour to feed ratio, Pj=vapour pressure of component supposed, P=Total pressure
By hit and trail method
At 85 oC and V/F=0.18
Components Zj Pj
KPa P
Pj
11P
P
F
V
ZX
i
j
j j
jX
P
PYi
Maleic anhydride 0.928 1.588 0.224 1.078 0.241
Water 0.072 57.767 8.136 0.032 0.257
Dibutyl phthalate 0.000 0.001 0.000 0.000 0.000
V=0.18*F
=0.18(74.69)
=13.444kgmol/day
L=0.82*F
= 0.82(74.69)
=61.25 kgmol/day
xvi
components Liquid stream
kgmol
L*Xj
vapour stream
kgmol
V*Yj
Maleic anhydride 3.242 66.049
Water 3.462 1.938
Dibutyl phthalate 0.000 0.001
13 Maleic anhydride = 317.89 kg/h
Water = 62.36 kg/h
Deisobutanizer
column
Maleic anhydride = 7086.58 kg/h
Water = 100.21 kg/h
Dibutyl phthalate = 20000 kg/h
12
15
14
Maleic anhydride = 6476.54 kg/h
Water = 34.92 kg/h
Water = 0.000723366 kg/h
Dibutyl phthalate = 20000 kg/h
xvii
APPENDIX 9: CP VALUE FOR ENERGY BALANCE CALCULATION
Compound Phase Tbp (0C) Tc (K) Pc (bar) Hv
[J/mol] HF [J/mol]
Cp [joule/(mol K)]
A B C D
Propane
gas
-42.1 369.8 42.5 18786 -103920
28.277 1.16E-01 1.96E-04 -2.33E-07
liquid 59.642 3.28E-01 -1.54E-03 3.65E-06
solid -11.23 1.06E+00 -3.60E-03 -
Isobutane
gas
-11.7 408.05 36.48 21399 -135600
6.772 3.41E-01 -1.03E-04 -3.68E-08
liquid 71.791 4.85E-01 -2.05E-03 4.06E-06
solid 110.211 -1.87E+00 1.44E-02 -
n-butane
gas
-0.5 425.2 38 22408 -126230
20.056 2.82E-01 -1.31E-05 -9.46E-08
liquid 62.873 5.89E-01 -2.36E-03 4.23E-06
solid
Isobutene
gas
-6.9 417.85 40.01 22100 -17900
32.918 1.85E-01 7.79E-05 -1.46E-07
liquid 57.611 5.63E-01 -2.30E-03 4.18E-06
solid 34.263 6.85E-02 2.07E-03 -
1-butene
gas
-6.9 417.9 40 22131 -16910
24.915 2.06E-01 5.98E-05 -1.42E-07
liquid 74.597 3.34E-01 -1.39E-03 3.02E-06
solid -11.985 1.15E+00 -3.58E-03
Neopentane
gas
9.5 433.78 31.99 22400 -167000
-17.917 5.72E-01 -4.17E-04 2.12E-07
liquid -186.315 3.24E+00 -1.09E-02 1.34E-05
solid 105.567 -2.66E-01 1.65E-03 -
Iso-pentane
gas
28 460.43 33.81 25220 -153700
-0.881 4.75E-01 -2.48E-04 6.75E-08
liquid 91.474 4.49E-01 -1.69E-03 3.13E-06
solid -10.547 1.25E+00 -3.35E-03 -
n-pentane gas 36 469.6 33.7 25791 -146540 26.671 3.23E-01 4.28E-05 -1.66E-07
xviii
liquid 80.641 6.22E-01 -2.27E-03 3.74E-06
solid -11.568 1.21E+00 -3.24E-03
Oxygen
gas
-183 154.58 50.43 6820 0
29.526 -8.90E-03 3.81E-05 -3.26E-08
liquid 46.432 3.95E-01 -7.05E-03 3.99E-05
solid -16.683 1.59E+00 -2.99E-03 -
Maleic anhydride
gas
200.2 721 72.8 54800 -470410
-72.015 1.04E+00 -1.87E-03 1.65E-06
liquid -12.662 1.06E+00 -2.32E-03 2.05E-06
solid 32.5 2.10E-01 2.73E-04 -
Carbon
monoxide
gas
-191.37 132.92 34.99 6015.8 -110530
29.556 -6.58E-03 2.01E-05 -1.22E-08
liquid 125.595 -1.70E+00 1.07E-02 4.19E-06
solid 21.83 -4.71E-02 6.41E-03 -
Carbon dioxide
gas
-56.57 304.19 73.82 25128 -394000
27.437 4.23E-02 -1.96E-05 4.00E-09
liquid -3981.02 5.25E+01 -2.27E-01 3.29E-04
solid 41.195 3.15E-02 6.41E-05 -
Water
gas
100 647.3 220.5 40683 -242000
33.933 -8.42E-03 2.99E-05 -1.78E-08
liquid 92.053 -4.00E-02 -2.11E-04 5.35E-07
solid 9.695 7.50E-02 -1.56E-05 -
Nitrogen
gas
-156 126.1 33.94 5570 0
29.342 -3.54E-03 1.01E-05 -4.31E-05
liquid 76.452 -3.52E-01 -2.67E-03 5.01E-05
solid 24.334 2.89E-01 1.16E-03
xix
APPENDIX 10: DRAFT OF PLANT LAYOUT
Admin Building
Contro
l
Room
Main Process Area
Waste water
treatment plant
Main
tenan
ce Build
ing
Main Gate
Plan
t Gate
Main Road
Wareh
ouse
Cen
tral Lab
orato
ry
Main
sub
statio
n
Off site Utilities
Storage
tank
farm
Expansion site
Flare system
area
xx
Admin Building
Storage Tank Farm
Maintenance Building
Control
Room
Waste water treatment plant
Offsite Utilities
Main Process Plant
Main Road
Plant Gate Main Gate
Main
sub
station
Central Laboratory
Warehouse
Expansion
site