29
03/30/22 1 CAUSES OF CLAIMS AND AVOIDANCE N D Sharma

CAUSES OF CLAIMS AND AVOIDANCE

  • Upload
    sissy

  • View
    52

  • Download
    2

Embed Size (px)

DESCRIPTION

CAUSES OF CLAIMS AND AVOIDANCE. N D Sharma. CLAIM. A Claim is a request for reimbursement of cost and / or time from one Party to another. This may be for a progress payment or a variation, or something else - PowerPoint PPT Presentation

Citation preview

Page 1: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 1

CAUSES OF CLAIMS AND AVOIDANCE

N D Sharma

Page 2: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 2

CLAIM

A Claim is a request for reimbursement of cost and / or time from one Party to another. This may be for a progress payment or a variation, or something else

Under the Contract either party may have a claim’ (PPMO SBD does not envision Employer’s Claim)

Page 3: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 3

CLAIMS

Contract provides for procedures making contractual claims by the contractor arising out of including:

•  A response to events which the contractor was not required to anticipate

• For additional payment or additional time• The legal/contractual consequence of events

Page 4: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 4

CLAIMS

Contractual Claims include:• Additional work claims – cost & profit• Damages claims – cost only• Neutral risk claims – time only

Common Legal (outside the Contract) Claims:• Claims in tort• Ex- Gratia

Page 5: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 5

CLAIMS

Claims may be arising out of several factor including:

• Manner in which contract was secured (Low bidding )

• The Engineer and roles in designing • The level of definition of the scope of works• Political aspects• Legal / contractual

Page 6: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 6

CAUSES OF CLAIMS• Inability to recognize all the risks and failure to

deal adequately with those including their sharing amongst the contracting parties

• Risks being either ignored or dealt with arbitrarily

• Employer’s tendency to own all the rights and shift risks and obligations to the contractor

• Inadequate pre-bid investigations; developing projects hastily not knowing the potential risks

Page 7: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 7

RISKS OWNERSHIPFIDIC/PPMO Cls.

Risk Employer

Contractor

1.9/20.1 and 42©

Delayed drawings and instructions

1.9 Error in Employers requirements

√ √

2.1/21 Right of access to the site

4.7 Setting out √ √

4.12/42.1(f) Unforeseeable physical conditions

Page 8: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 8

RISKS OWNERSHIP

FIDI/PPMOCls.

Risk Employer

Contractor

4.24 Fossils √

7.4/42 and 33 Testing delays by the Employer

7.5 /35.5 Def Rejection of Materials √

7.6/34 Remedial works √

8.4(a)/27.1 Extension for time for completion - Variation

Page 9: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 9

RISKS OWNERSHIP

FIDIC/PPMO Cls

Risk Employer Contractor

8.4(b)/na Extension for time for completion – delay giving entitlement to EOT

8.4(e)/na Exceptionally adverse climatic conditions

8.4(d)/na Unforeseeable shortages and the availability of personnel or goods caused by epidemic or by government action

Page 10: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 10

RISKS OWNERSHIP

FIDIC/PPMO Cls

Risk Employer Contractor

9.4/33 Failure to pass Tests on Completion

11.4/35 Failure to remedy Defects

12.1 and 14.1/37 and 38

Increase of quantities √

Page 11: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 11

RISKS OWNERSHIP

FIDIC/PPMO Cls

Risk Employer

Contractor

12.4/na Omission of work through a Variation

12.4 Failure to pass tests after Completion

13.3/37 and 38 Variation procedure √

13.7/45 Adjustment for changes in legislation

√ √

13.8/45 Adjustment for changes in cost

√ √

Page 12: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 12

RISKS OWNERSHIP

FIDIC/PPMO Cls

Risk Employer Contractor

14.8/41 Delayed payment √

15.4/61 Payment after Termination

17.1 Indemnities √ √

17.2/na Care of the Works prior to the Taking Over Certificate

Page 13: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 13

RISKS OWNERSHIPFIDIC/PPMO Cls

Risk Employer Contractor

17.4/11 Consequences of Employer's risks

19.4/42 Consequences of force majeure

20.1/na Contractor's claims √

Page 14: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 14

CAUSES Of CLAIMS• Awards of contracts going to very low rate

bidding contractors, looking for opportunity to put in claims leading to disputes.

• Inefficient contract administration on the part of the Employer/Purchaser

• Force-Majeure conditions not recognized.• Failure on the part of the actors of the

contract to timely discharge their duties and meet contractual obligations

Page 15: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 15

CLAIM TIMELINE

• If the Contractor considers himself to be entitled to an EOT or addition payment or both, he must give notice to the Engineer as soon as practicable and “not later than28 days after the Contractor became aware, or should have become aware, of the event or circumstance” giving rise to the claim. If he fails to make claim on time he is not entitled to it.

Page 16: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 16

CAUSES OF CLAIMS AND AVOIDANCE

AVOIDANCE OF CLAIMS

Page 17: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 17

AVOIDANCE OF CLAIMS• Parties must know their contracts well; • ‘Every contract is unique’; though this

saying is somewhat diluted by the introduction of SBDs, elaborate regulations (PPR) and the PPA

• Parties must understand that they are at par as sovereign partners of the contract, to be regulated by their contract and the governing law.

Page 18: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 18

AVOIDING CLAIMSAvoidance of Claims through Contract Administration• Drawings, information and ‘Holds’• Approvals• Ground conditions• Relationships• Consultants’ performance• Access to works• Public authority / government bodies• Payment• The manner in which early problems are dealt with• Performance of nominated sub-contractors

Page 19: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 19

AVOIDING CLAIMS

Avoidance of Claim Situations by Contractor’s Actions:

• carefully review the bidding documents including drawings and specifications;

• price the job adequately to make fair profit;• manage and perform contract with due

diligence;• respect specifications and instructions;

Page 20: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 20

AVOIDING CLAIMS

Avoidance of Claim Situations by Contractor’s Actions:

• use materials, plant as specified and ensure quality;

• take care of works in progress by appropriate measures;

• comply with all applicable laws, regulations including safety related;

Page 21: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 21

AVOIDING CLAIMS

Avoidance of Claim Situations by Contractor’s Actions:

• inform the Employer in advance whenever an event occurs which is likely to increase the cost of the works and or the time of completion;

• remedy defects well before expiry of the defect liability/ defect notification or warranty period; and

• present claims, if any, in a timely manner.

Page 22: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 22

AVOIDING CLAIMS

Avoidance of Claim Situations Good documentation:

CONTRACTOR’S PROGRAM• Reflect Contract requirements• Include Contract milestones• Show sequence of works• Incorporate resource and other constraints• Supported by Method Statement

Page 23: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 23

AVOIDING CLAIMS

Employer’s Actions at. thé Procurent Stage:• inform and instruct bidders on the procedure

for preparation and submission of bids; • describe the standards required; • inform bidders of the criteria for evaluating

bids; and • also inform that the only bidder having the

experience and capacity to execute the

Page 24: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 24

AVOIDING CLAIMS

Employer’s Actions at. thé Procurent Stage:• in the case of works, provide detailed site

investigation report and other information related to the site of which the Employer is in possession

• define the conditions of contract and method of payments;

• describe procedures for acceptance of final products ;

• and for issuance of contract amendments

Page 25: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 25

AVOIDING CLAIMS

Employer’s Actions at. thé Procurent Stage:• define adequately quality control procedures• inform about the rights and duties of the parties

and the remedy against defaulter• provide for amicable settlement, adjudication and

arbitration mechanisms for settlement of disputesFIDIC- Based conditions stipulate that:– an independent Engineer, empowered with

authority to administer the contract with some pre-disclosed restrictions, will supervise the contract.

Page 26: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 26

AVOIDING CLAIMS

Employer’s Actions at. thé Procurent Stage:• the Employer has produced a design for the

work through a competent Engineer • the possession of site and access thereto will

be made available as specified in the documents or within reasonable time so that the activities as scheduled would not be adversely affected

Page 27: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 27

EMPLOYER’S CLAIM

Employer’s Claim:• Entitlement: under any Clause of the

contact or otherwise in connection with the Contract.

• No time bar for the notice (should be given as early practicable- can be given by the Employer or by the Engineer

• Engineer to refer to engineer for determination!

Page 28: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 28

Engineer's Supremacy

• Employer is denied to set off against or make any deduction from a certified amount or otherwise claim against the Contractor unless done in accordance with the contract provisions under Clause

Page 29: CAUSES OF CLAIMS AND AVOIDANCE

04/22/23 29

HANDLING OF CLAIMSEmployer and Contracor’s Joint Actions: • Keep good record systems and agree on facts• Respond to challenges / issues promptly• Monitor progress• Establish claims systems and procedure• Review resourcing• Do not assume everything will come good at

the end of the day• Settle amicably or go for adjudication