CASE STUDY
THE TOWN OF
LUANG REAP HOI
PHNOM PENH PLAN
The Skill and knowledge Improvement Project for
Sustainable Development in Tourism Industry
OUTLINE
EXCUTIVE SUMMARY STAKEHOLDER ANALYSIS PROBLEM TREE SOLUTION /OBJECTIVE TREE DESIGN AND MONITORING
FRAMEWORK WORK BREAKDOWN STRUCTURECRITICAL PATHMS PROJECT
Executive Summary
According to case study, There is a small city named Luang Reap Hoi where tourism industry is growing rapidly but city council has no plan to support the accumulated number of tourists that causes a lot of problems to city which can defined in 4 groups
– Human Resource– Tourism and Infrastructure– Environment– Social
• In our point of view, the problems of Human Resource is critical issue.
• The objective of the project is, to improve skill and Knowledge for employees and local people to work in tourism industry.
• The process of the project– Stakeholder Analysis– Problem tree– Objective tree– Design and Monitoring Framework– Work Breakdown Structure– Critical Path
• The expected result is, people have skill and knowledge in tourism industry consist of interpretation, hotel services and so on.
• The beneficial of this project promotes the increasing number of tourists and improve investment in tourism industry that would contribute the economic growth.
• Duration time = 96 weeks (2 years)
• Budget = 2 million dollars
Stakeholder Analysis
Stakeholder Stakeholder’ s interest PerceiveProblem
ResourceMandate
TourismGood service ( Hospitality )
Communication- No Interpretation
Willingness to pay for improved
service
The owner of Hotel & Restaurant
Good skill workersNo qualified staffs& high competition
Facilities & capital
Employee Living high standard Reduced Salaries Capacity
Local People Own business, get a job Lack of skilland knowledge , Do not have capital
Culture & Traditional
Department of Skill Development
Skill development & resource unemployment
Insufficient fund
Expertise And facilitation,
Provide Training
PROBLEM TREEPROBLEM TREELow Economic growth
Unemployment rate increasing
Decreased investment in tourism service
Number of tourism decline
Bad services
People Lack of skill & knowledge in tourism service industry
No Training Center
Inadequate of education staffs
Poor education No InterestingMotivation
No plan &policies Difficult Access to School
No sufficient from families
Insufficient school
-No money - don’t know skill
& knowledge important
BadTransportation
Gov. has no fund for
support
Cultural andTransportatio
n
High Economic Growth
More Employment
Sufficient Investment in Tourism Sector
Good Service
Sufficient Training Center
Adequate Of Education Staff Good Education
More InterestingMotivation
Good Plan and Policy
Affordable
Easy Access to School
Realize the Important of Skill and Knowledge
Family Support
Good Transportation
Sufficient School
Gov. SupportFund
SOLUTION / OBJECTIVE TREE
Design Summary Performance Target Data Source Assumptions/ RISKS
IMPACT-High economics growth-More employment-Increase investment in tourism industry
-GDP: 3% increase from 1.5 in 5 years
-Employment rate: increase 20% from 1,000 in 5 years
-the amount of
investment in tourism industry: $50 millions in 10 years (now 20 million)
-Ministry of Economics
-Ministry of Labor
-Ministry of Planning
-Political is stable
-No financial crisis
-No contagious disease
OUTCOME
-Better services to tourism sector
-The number of tourists: increase 10% from 10,000 in 2 years
-Satisfaction of tourists: increase 80% from 10,000 in 1 year
-Ministry of Tourism, Immigration Department
-Out source (survey)
-program updating
-Ministry of Tourism’s priority
OUTPUTS-training center operational
-Adequate education staff
-Participants have skill & Knowledge
-More interest & motivation community
-Number of programs that completed: 10 programs per year
-The number of trained staff: 10
-Test: 80% of participants qualify
-The number of applications that apply for the program: 300
-Training center report -participation of stakeholder
-sufficient skilled trainer
-Ministry of Education conduct basic education
Feasibility Study
14 weeks & 13,300
Building Design
10weeks & 7,300
Bidding
2weeks& 500
Construction
32 weeks& 1.5 M
Training Program Preparati
on22weeks29,500
Staff Training
16 weeks11,000
Training
58 weeks101,000
Certification
4 weeks 3600
Hire consultants for feasibility study4 weeks & 3000
Hire consultant for building design 4 weeks & 3000
Bidding started
2 weeks & 500
Construction started
32 weeks &1.5 M
Hire consultant for program
4 weeks & 3000
Hire staffs
4 weeks & 3000
Selection of participants
10 weeks &1000
Examination given
2 weeks & 2000
prepare feasibility study
8 weeks & 3000
Prepare engineering design
4 weeks & 4000
Bidding completed
Construction completed
Prepare program
6 weeks & 5500
Train staffs
6 weeks & 18,000
Participants selected
0
Certificate awarded
2 weeks &1600
Work Breakdown StructureSkip
120 weeks $1,659,200
Work Breakdown StructureApproval feasibility2 weeks & 300
Approval
2weeks & 300
Program completed
0
Train staffs completed
0
Run Program48 weeks &100,000
Feasibility completed
Building design complete
Hire consultants for advertisement4 weeks & 3000
Broadcasting
0
Prepare advertise campaign4 weeks & 5000
Run advertisem
ent4 weeks
& 3000
Hire Consultant for feasibility
Study 4 weeks
StartProgram
Prepare feasibility Study
8 weeks
Approvalfor feasibility
Study 2 weeks
Feasibility Complete
Hire Consultant for Building
4 weeks
PrepareEngineering
Design4 weeks
Approval for Design2 weeks
BuildingDesign
Complete
DoBidding2 weeks
Bidding Complete
1
2 3 4 5 6 7 8 9 10 11
ConstructionStart
32 weeks
ConstructionCompleted
Training Center
Run Program48 weeks
ParticipantSelected
Selection of Participants10 weeks
Adequate Education
Staff
Training Staff
Completed
Training Staff
6 weeks
Hire Staff
4 weeks
TrainingProgramComplete
Hire Consultantfor Program
4 weeks
PrepareTrainingProgram8 weeks
12
13 14
15 1617 18 19 20 21
27 28 29
Hire Consultant for Advertisement
4 weeks
Prepare Advertisement
Campaign4 weeks
22 23
Run Advertisement
4 weeks
Broadcast andAdvertisement
done
More interestedAnd motivation
24 25 26
Examination2 weeks
30
Certificate2 weeks
31
Program Complete
Participant have skills
& knowledge
32 33 Program Complete
34
Critical Path
No. Activities Duration Predecessor
1 Start project 0 -
2 Hire consultant for feasibility study
4 1
3 Prepare feasibility 8 2
4 Approval 2 3
5 Feasibility complete 0 4
6 Hire consultant for building design
4 5
7 Prepare engineeringdesign
4 6
8 Approval 2 7
Activities
No. Activities Duration Predecessor
9 Building design Complete 0 8
10 Biding 2 9
11 Biding completed 0 10
12 Construction start 32 11
13 Construction complete 0 12
14 Training Center 0 13
15 Hire consultant for program 4 1
16 Prepare program 8 15
17 Program complete 0 16
No. Activities Duration Predecessor
18 Hire staffs 4 17
19 Train staffs 6 18
20 Training completed 0 19
21 Adequate education staffs 0 20
22 Hire consultant for advertisement
4 15
23 Prepare advertise
campaign
4 22
24 Run advertisement 4 23
25 Broadcasting 0 24
No. Activities Duration Predecessor
26 More interest 0 25
27 Selection participant 10 26
28 Participant selected 0 27
29 Run program 48 14,28
30 Examination 2 29
31 Certificate 2 30
32 Program completed 0 31
33 Participants have skill & knowledge
0 32
34 Completed project 0 33
THANK YOU