Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
WORKFLOW
CONSULTING
Case StudyLean Methods Improve ProductivityOU Medical Center creates a safer, more effective and efficient anatomic lab
1 10
1 10
2
Change Readiness Assessment
4 of 4 dimensions support a high-to-medium need for change management
How big is this change for the organization culturally and in general?
(Day-to-day Work Activities, Decision Making, Logistically)?
Minor Changes Major Changes
Not a Big Deal Very Severe
High Recognition Low Recognition
High Recognition Low Recognition
1 10
1 10
X
X
X
What is the level of severity if the change fails?
(Strategic Alignment, Lost Opportunity, Loss of Credibility)
How widely acknowledged are the risks of the status quo?
(Quality, Patient Safety, Productivity)
How much are the benefits of this change recognized by those involved in the change?
(Cost Reduction, Employee Satisfaction)
X
Errors that occur in an anatomic pathology lab can be deadly.
Slow turnaround times can cost thousands and increase
patient anxiety.
In pursuit of a safer and more efficient lab, the Board-certified
pathologists and their team at Oklahoma University (OU)
Medical Center implemented lean process modifications and
the Ventana Symphony automated staining system. The team
targeted improving quality, productivity and turnaround times
specifically in the hematoxylin and eosin (H&E) staining work
cell. Recognizing that timely and accurate lab results for patients
also means a more competitive lab for OU Medical Center, the
anatomic pathology lab teamed with Ventana Medical Systems
to streamline H&E operations in preparation for an anticipated
growth surge.
Background
The histology lab at OU Medical Center operates 24 hours
a day, six days a week and supports the histology needs for
OU Medical Center, The Children’s Hospital, OU Physicians,
Oklahoma State Health Department, OU Oral Pathology and
some on-campus research operations. With a new OU cancer
center nearing completion, lab demand was projected to surge;
however, space and capacity constraints limited the lab’s ability
to meet the climbing demand.
“Having seen the benefits of throughput improve-
ment in the operating room suites, we knew there
was an opportunity to put lean process improve-
ment to work in the pathology lab to support the
potential increase in demand.”
Figure 1.
Assessing Change
Ventana’s Workflow Consulting Solutions used lean principles to
pull the department together in such a way that the
staff saw the effects of their own actions on others, as well
as on overall turnaround times. The team engaged both senior
leadership from the hospital and physicians as the first step in
assessing change readiness (see Figure 1 on page 2).
Four dimensions of readiness were assessed to match the
level of change management required for a successful imple-
mentation of lean to OU Medical Center’s lab. The team
determined the size of the change and the level of severity
should the change fail. They also assessed the perceived risks
of no change (status quo), and the awareness of the resulting
benefits of lean.
Reaching Operational Efficiency
The team looked at before-and-after productivity comparisons
based on historical workload and quality data. They created a
visual snapshot of how the lab operated in real time by follow-
ing a specimen through the lab, measuring steps, specimen
travel distance and total turnaround time (see Figure 2).
Initially, the team grew weary believing operational efficiency
was too difficult to achieve. However, small teams across
the lab studied and implemented portions of the transforma-
tion, and with findings graphed and charted, they illuminated
nonvalue-added activities and opportunities to eliminate rework.
“Early on, operational efficiency seemed elusive as
we kept documenting wait times for equipment,
staff and pathologist decisions.“
Lean process improvement spotlighted opportunities to reduce
both time and movements from barcoding a specimen block
through processing, embedding, cutting and staining, ending
with assembled case slides.
3
Figure 2: New flow saves 357 ft per case or 2.9 miles a day.
BEFORE AFTER
New H&E Workflow Process Reduces Travel Time 42%
For example, in the H&E staining workcell, the team reduced
specimen travel distances from 92 to 53 feet, a 42 percent
improvement. Reconfigurations of workcell instrumentation and
organization was a collaborative effort involving the Ventana lean
consultants, lab team members and leadership.
Time to first available slides decreased from 12 hours to four
hours, providing more time for resident review of slides prior
to sign-out. By shifting 17 percent of total workflow from a
nighttime shift to the afternoon, the team improved the average
time at which the last case was presented to the pathologist for
diagnosis. This meant 50 percent of slides/cases arrived
on the pathologist’s desk for diagnosis one hour and four
minutes earlier. This improvement resulted in patients receiving
their results sooner, leading to a better patient experience for OU
Medical Center.
4
Figure 3: Symphony reduced nonvalue-add process steps (green) at the microtomy workbench; future state eliminates 8 steps.
Figure 4: Symphony streamlined process steps removing nonvalue-add steps (green) at the H&E staining workbench; future state now includes a fully-automated H&E staining process
Additionally, OU Medical Center removed errors at the tail end
of the histology sequence by implementing the Symphony
automated platform. Errors in assembly were common despite
meticulous care by even the most experienced histologists.
Previously, the chaos introduced between grossing, process-
ing trays, embedding stations, cutting areas and batch stainers
often meant that a case was scattered over several runs (see
Figures 3 and 4).
“Our patients receive the greatest benefits of lean.
The time and efficiency savings, coupled
by improvements in safety generated by lean,
translate into timely and accurate lab results
for our patients.”
Total Process Turnaround Time Improves in Microtomy and H&E
BEFORE AFTER
BEFORE AFTER
Receiving Accessioning 9ft 3ft 6ftCassette 32ft 16ft 16ftMarking Grossing 38ft 20ft 18ftTissue Processing 88ft 68ft 20ftCreate Slides 22ft 4ft 18ftEmbedding 18ft 5ft 13ftMicrotomy 42ft 14ft 28ftH&E Staining 32ft 20ft 12ftCase Assembly 126ft 100ft 26ftReview/Archival 270ft 120ft 150ftRecuts, SS, IHC 96ft 25ft 71ftTotal 773ft 395ft 378ft
Step Dist. Lean Op. Final
Embedding 18ft 5ft 13ft
Microtomy 42ft 14ft 28ft
H&E Staining 32ft 20ft 12ft
42% Improvement
one-touch automated H&E staining system. This system
replaced OU Medical Center’s previous installation of separate
drying oven, linear stainer and coverslipper. Today, 13 staining
steps are now automated.
Both the microtomy and H&E staining workbenches were
greatly impacted by this combination of technology and lean
workflow improvements. Based on travel time alone, which in
lean is considered pure waste, a total of 23 minutes per slide
rack of manual and semi-automated work were absorbed by
Symphony. This translates to a savings of approximately three
hours per day. Lean Six Sigma resulted in a 42 percent improve-
ment in the H&E staining workcell; overall a 51 percent improve-
ment was achieved (see Figure 5).
These significant improvements represent only the beginning
of a longer-term and broader project to break through other
bottlenecks in the anatomic pathology lab. OU Medical Center
continues to use lean principles in an iterative process to find
and sustain improvement throughout the lab.
5
Results
Implementing lean workflow, a relatively low-tech change in
process produced significant results for the histology lab at OU
Medical Center:
• Average time from gross station to completely assembled
slide cases ready for pathologist sign-out decreased 2.9
hours (12 percent).
• Total process turnaround time reduced 28 minutes per case
(4 percent).
• Mean quarterly productivity increased 8.5 percent from
2312 slides and blocks/FTE to 2509.
• Manual steps reduced from 219 to 182 (17 percent).
• Specimen travel time distance reduced 49 percent overall
to 395 ft/case and 42 percent in the H&E cell.
• The number of days in which new slides/cases arrived on
the pathologist’s desk for diagnosis after 10 a.m. was
reduced by 50 percent, more than a one-hour
improvement.
Approximately 25 percent of these improvements were a direct
result of implementing a high-tech solution: The Symphony
Lean Six Sigma Results in a 51% Improvement in Distance Traveled
Figure 5.
Ventana Medical Systems, Inc.1910 E. Innovation Park Drive Tucson, Arizona 85755USA +1 (520) 887 2155(800) 227 2155
www.ventanamed.com
© 2009