Paul De Schepper Knowledge centre Energy (University Thomas More – Geel/Belgium) 25/06/2020 CASE STUDY GEOTHERMICA - CAGE 1

CASE STUDY GEOTHERMICA -CAGE · 1. InnovationParc-Office : 35.000 m²-Storage : 7.500 m²-Heat demand-40 W/m² foroffices means 1400 kW-60 W/m² forstorage means 450 kW-TOTAL HEAT

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • Paul De SchepperKnowledge centre Energy

    (University Thomas More – Geel/Belgium)25/06/2020

    CASE STUDY GEOTHERMICA - CAGE

    1

  • SITUATION

    2

    Innovation parcPhase 1

    Belgium – GEEL – University Thomas More

    Heading Degree Days : 2200 (base 16,5 °c)

    Existing building :- University Thomas More

    - Energy Demand : 4450 MWh/yr- Heat demand : 2410 kW

    - Sport location (AXION 1)- Energy demand : 379 MWh/yr- Heat demand : 210 kW

  • EXPANSION

    3

    Expansion with :

    1. Innovation Parc- Office : 35.000 m²- Storage : 7.500 m²- Heat demand

    - 40 W/m² for offices means 1400 kW- 60 W/m² for storage means 450 kW- TOTAL HEAT DEMAND : 1850 kW- Total enerygy use : 2200 MWh/yr

    2. New sport location : AXION 2 (same as AXION 1 and build next axion 1)- Energy demand : 379 MWh/yr- Heat demand : 210 kW

  • EXCERCICE

    4

    Take a look at the possibilities for using geothermal energy in combination with a heat network.

    What is the best place for location collector

    Figure : Division of InnovationPark into different zones/functions

  • 5

    Collector)

    Simulation innovation parc

  • GEOTHERMAL RESERVOIRS (REGIONKEMPEN)

    6

    Bron : VITO

  • Krijt Onder-CarboonSupply Temperature 35° C 95° CInjection Temperature 22° C 60° CProduction flow 75 m³/h 125 m³/hHeat Power 1125 kW 5100 kWHeat energy 4000 MWh (3555 h) 7050 MWhPower pump 90 kW 190 kWTotal volume 263700 m³/y 172700 m³/j

    POSSIBILITY

    7

    BRON : VITO

  • • Only Innovation Parc :− Heat demand : 1850 kW• Krijt : 2 drillings 1000 m• Onder-carboon 1 drilling

    • Innovation Parc + Thomas More + Axion (sport)− Heat demand : 4680 kW• Krijt : 4 à 5 drillings 1000 m (expensive )• Onder-carboon 1 drilling

    POSSIBILITY INNOVATION PARC + THOMAS MORE

    8

  • RESULTS USING THERMOS

    9

    Heat demand 4680 kWEnergy demand 7408 MWHPipe length 3,8 kmPipe costs 2,95 M€Operating revenu 10,12 M€NPV 7,17 M€

  • 10

    HEAT NETWORK

  • • the next step is to collect concrete prices for pipe network, connection costs, etc ...• Economic analysis – return on investment• Sitting together with different partners • See if the network can be expanded

    CONCLUSION AND NEXT STEPS (MAY BE)

    11