Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1
CASE NO: MG CIV 7/12
In the matter between:
NEDCOR BANK LIMITED Appellant
and
WYNAND JACOBUS VICTOR NO First Respondent
JOHANNES LODIWICUS DU PLESSIS NO Second Respondent
WILLEM HENDRIK JACOBUS CILLIERS NO Third Respondent
WYNAND JACOBUS VICTOR Fourth Respondent
MAGRIETHA JOHANNA VICTOR Fifth Respondent
GERRIT DERKSE LUTTIG Sixth Respondent
MARIA ELIZABETH LUTTIG Seventh Respondent
MARIA ELIZABETH LUTTIG NO Eighth Respondent
JOHANNES LODUWICUS DU PLESSIS NO Ninth Respondent
WILLEM HENDRIK JACOBUS CILLIERS NO Tenth Respondent
CIVIL APPEAL
HENDRICKS J; KGOELE J
DATE OF HEARING : 28 MARCH 2014
DATE OF JUDGMENT : 20 JUNE 2014
COUNSEL FOR THE APPELLANT : Adv. H J Benade
SAFLII Note: Certain personal/private details of parties or witnesses have been redacted from this
document in compliance with the law and SAFLII Policy
3
KGOELE J:
A. INTRODUCTION
[1] This is an appeal against the judgment delivered by Magistrate J.
Schmulling in the District Court, Vryburg. The appellant was the
plaintiff in the court a quo and the respondents, the defendants. The
cause of action in this matter arose from various instalment sale
agreements which the appellant and the respondents concluded with
regard to the purchase of some items.
B. FACTUAL BACKGROUND
[2] The first three respondents are the trustees of the Germi Trust. On 12
September 1997 Germi Trust and the appellant (Nedcor) concluded
twelve instalment sale agreements for the purchase of twelve items.
The fourth, fifth, sixth and seventh respondents acted as sureties for
Germi Trust. Likewise did the eighth, ninth and tenth respondents, as
trustees of the Poppiesdale Trust, acted as sureties for Germi Trust.
Bonds were also registered as securities. The terms of these
agreements were almost similar in nature.
[3] It is alleged by the appellant that at some stage, after the conclusion of
the said agreement, Germi Trust fell in arrears with payment of the
respective instalments due to the appellant. As a result, notices (in
respect of each of the twelve agreements) were sent to the fourth and
fifth respondents by a firm of Attorneys acting for and on behalf of the
appellant. These notices were dated 22 March 1999. The contents of
these notices, save for the respective amounts pertaining to the
4
different agreements, were identical. All of them are in the form of
letters of demand referring to the provisions of section 11 of The Credit
Act No. 75 of 1980. (The Act)
[4] For the sake of convenience one of the said letters is quoted and the
contents thereof read thus:-
“KENNISGEWING IN TERME VAM ARTIKEL 11 OP DIE
WET OP KREDIETOOREENKOMSTE, WET NOMMER 75
VAN 1980: NEDCOR BANK BEPERK: REK NR 2287536/0027
Ons het opdrag van ons bogenoemde kliënt ontvang om van u te eis
in terme van die bepalings van Art 11 van die Wet op
Kredietooreenkomste, Wet nommer 75 van 1980 soos gewysig, die
onmiddellike betaling van die agterstallige bedrae verskuldig op
bogenoemde rekening en wel in die bedrag van R86530.20 asook
alle verdere agterstallige rente ten opsigte daarvan en moontlike
verdere paaimente wat betaalbaar mag word, welke bedrae
betaalbaar is binne dertig dae na ontvangs hiervan by versuim
daaraan ons kliënt sal voortgaan met die uitoefening van hul regte
dienooreenkomstig die kredietooreenkoms vir hetsy die verhaal van
die volle uitstaande balans verskuldig of alternatiewelik kansellasie
van die kontrak, teruggawe van die goedere en betaling van
skadevergoeding en koste, sonder enige verdere kennisgewing van
welke aard ookal.
Die uwe.
HONEY & VENNOTE INC”
5
[5] On the 29th March 1999, seven (7) days after sending out the letters of
demand, the appellant approached the Magistrate Court, Vryburg and
on an ex-parte basis obtained an order against the fourth and fifth
respondents in the form of an interim interdict for the attachment of the
twelve items which form the basis of the agreement between Germi
Trust and the appellant. Paragraph 1.1 and paragraph 2 of the said
order, which in my view are important in the consideration of this
matter, reads as follows:-
“1 X GEBRUIKTE MAN 26.372 DFTC TROK MET
REEKSNOMMER V[…], ONDERSTELNOMMER F[…] EM
REGISTRASIENOMMER EN LETTERS P[…]
1.1 Asook dat die Balju van die Landroshof bemagtig en
beveel word om die goedere onverwyld uit die besit van
die Respondent of enige ander persoon in wie se besit die
gemelde item(s) mag wees te verwyder en te oorhandig
aan die eiser of n person wat hy mag aanwys ter bewaring
en ten behoewe van die eiser om dit te bewaar wie die
goedere moet bewaar hangende die uitslag van die
aansoek alternatiewelik die uitslag van ‘n aksie ingestel te
word deur die Applikant vir die kansellasie van die
skriftelike ooreenkoms en/of ooreenkomste, alternatiewelik
bekragtiging van kansellasie van die skriftelike
ooreenkoms en/of ooreenkomste, teruglewering van die
goedere sowel as die afdwinging van enige ander regte
waarop die Applikant geregtig mag wees in terme van die
skriftelike ooreenkoms en/of ooreenkomste.
6
1.2 Dat vir sover dit nodig is vir die ten uitvoering daar gestel
in paragraaf 1.1 hierbo, word die balju van die
Landdroshof gemagtig en beveel om enige deur op enige
perseel of om enige toegang tot enige perseel oop te maak,
indien geweier word om dit oop te maak of indien daar
niemand daar teenwoordig is wat die person teen wie die
ten uitvoerlegging ten uitvoer gelê moet word
verteenwoordig nie, en indien nodig, kan die balju vir die
doel geweld gebruik.
2. Dat die bevel daar gestel in paragraaf 1 hierbo sal dien as
‘n tussentydse interdik hangende die uitslag van die aksie
en dat die Respondent opgeroep word om redes, indien
enige, aan te voer om 9 00 in die voormôre op 12de dag
van Mei 1999 waarom hierdie Bevel nie bekragtig moet
word nie en waarom die Respondent nie beveel moet word
om die kostes (soos op ‘n prokureur en kliënt skaal
skriftelik ooreengekom) hiervan te betaal nie.
GETEKEN te VRYBURG hierdie 29ste dag van MAART 1999”
[6] This interim order was made final on 12 May 1999. Three months
thereafter, on 12 August 1999, these items were sold on auction.
7
D. THE SUMMONS
[7] On the 29th March 2000 summons were issued by the appellant as
plaintiff against the respondents as defendants for payment of a
balance of R2 395 178 70. In the summons the appellant prayed inter
alia for cancellation of the aforementioned twelve agreements. On 05
December 2005 default judgment was granted in favour of the
appellant against the respondents after the matter had been withdrawn
against the sixth respondent. This default judgment was successfully
appealed against by the respondents. The matter was referred back
to the Magistrate Court Vryburg (the trial court) for trial de novo before
a differently constituted court.
E. THE TRIAL COURT’S FINDINGS
[8] The following were the issues that the trial court had to grapple with
when the trial commenced:-
8.1 that the contracts were not validly cancelled;
8.2 that the defendant denies that Germi Trust failed to perform in
the terms and conditions of the contract; and
8.3 that the quantum claim is also denied.
[9] The appellant called two witnesses namely, Mr Herbert George Meyer
and Mr Abraham Albertus Moller to testify on its behalf, who testified
mainly about quantum of the amount claimed. I am of the view that the
summary of the evidence of these two witnesses is not necessary in
view of the outcome of this matter which will become clearer later in
8
this judgment. The defendants closed their case without leading any
evidence.
[10] The finding and the judgment of the trial court was mainly based
on the questions as to whether the contracts were validly
cancelled and furthermore, whether the appellant is lawfully
entitled to claim the damages if the court finds that the contract
were not validly cancelled. This is clear from the judgment of the
trial court where it stated that:-
“Die uitspraak van die hof is gebasseer op die punt of die kontrak
regmatiglik gekanseller is en of die eiser geregtig is op
skadevergoeding as die hof bevind dat die kontrak nie regmatig
gekanselleer is nie.”
[11] The trial court dismissed the appellant’s (plaintiff’s) claim on the basis
that the contracts were not validly cancelled at the time the items were
sold on auction, and further that, the appellant cannot claim damages
as it made performance of the respondents in terms of the agreement
impossible by selling the items before cancellation.
F. THE APPEAL
[12] Dissatisfied about the outcome, the appellant lodged an appeal
against this judgment, hence this appeal. The appeal is premised on
the following grounds:-
“KENNISGEWING VAN APPèL: REëL 51
9
“NEEM KENNIS dat die Eiser in hierdie saak hiermee kennis gee
en appèl aanteken teen die vonnis en/of uitspraak deur Landros J
Schmulling gelewer op 11 Januarie 2012, en wel op die volgende
gronde:-
1. Die Agbare Landdros het met respek fouteer deur te bevind dat
Eiser nie ‘n terugname bevel (tussentydse beslaglegging en
bewaring) kon verkry het as dertig (30) dae ingevolge Artikel 11
van die Wet op Kredietooreenkomste, 1980, nog nie verstryk het
nie.
2. Die Agbare Hof het fouteer deur te bevind dat Eiser prestasie vir
die Verweerders (Eerste tot Derde Verweerder – Germi Trust)
onmoontlik gemaak het.
3. Die Agbare Hof het fouteer deur te bevind dat Eiser hulle eie
skade veroorsaak het deur die items te verkoop voordat hulle ‘n
hofbevel verkry het wat verkoping van die items gemagtig het.
4. Die Agbare Hof het fouteer deur te beslis dat Eiser, na uitreiking
van die Artikel 11 aanmanings in Maart 1999, nie aan
Verweerders die geleentheid gegee het om aan die aanmanings
te voldoen nie.
5. Die Agbare Hof het fouteer deur te beslis dat Eiser nie geregtig
is op skadevergoeding nie aangesien Eiser prestasie deur
Verweerders onmoontlik gemaak het deur die items te verkoop,
10
en/of onmoontlik gemaak het deur die items voor regmatige
kansellasie te verkoop.
6. Die Agbare Hof het fouteer deur te bevind dat Eiser prestasie vir
Verweerders onmoontlik gemaak het en Verweerders derhalwe
verskoon word van prestasie ingevolge die kontrak, en verskoon
word van enige skade wat gely word uit die Verweerders se nie-
prestasie.
7. Die Agbare Hof het fouteer deur nie te bevind dat Verweerders
reeds voordat Eiser die items verkoop het, wanpresteer het en
dat Eiser op grond van daardie vooraf wanprestasie geregtig
was om te kanselleer en/of geregtig was op ‘n bevel van
bekragtiging van kansellasie en/of geregtig was om kennis te gee
van kansellasie by wyse van dagvaarding nie.
8. Die Agbare Hof het fouteer deur te beslis dat Eiser die koste van
die geding op ‘n prokureur en kliënt skaal moet betaal.
9. Die Agbare Hof het fouteer deur ‘n prokureur en kliënt
kostebevel teen Eiser te verleen, na aanleiding van die afwysing
van die aksie.”
[13] From the judgment of the trial court, it is abundantly clear that the
learned Magistrate was of the view that the most important issue to be
decided was whether or not the contracts (agreements) were validly
cancelled by the appellants.
11
[14] The letters of demand which refers to section 11 of The Act do not
serve as a notice of cancellation of the said contracts. This is evident
from the wording thereof which stated that:-
“1. Let asseblief daarop dat u die bostaande kontrak verbreuk het insovere u
versuim het om die verskuldige paaiement/huurgeld te betaal en die
rekening is gevolglik agterstallig ten bedrae R3666.74.
2. U word hiermee kennis gegee dat tensy u binne ń periode van veertien
dae vanaf versending van hierdie kennisgewing, in terme van Artikel 11 op
die Wet van Kredietkoopooreenkomste nr 75 van 1980 die bogenoemde
verbreuking onverwyld herstel deur die rekening ten volle op datum te
bring, ons die kontrak sal kanselleer sonder verdere kennisgewing en sal
voortgaan met die nodige stappe vir terruggawe van die goedere
gefinansier onder bogenoemde kontrak sowel as met ń eis vir
skadevergoeding as gevol van u bogenoemde kontrakbreuk. [My own
emphasis]
3. U word dus versoek om hierdie saak met ons te bespreek en die persoon
wat hierdie kennisgewing onderteken het onverwyld te kontak.”
[15] At best, the letter of demand served as a notice in terms of Section 11
of The Act of default of payment and furthermore, indicated the steps
that the appellant will take if the default persisted. Amongst other
things that the appellant contemplated exercising (not that it had
elected to) was to cancel the contract and take the necessary steps for
the return of the goods and lastly, a claim for damages. Section 11 of
The Act is quite clear that upon default, the plaintiff (appellant) shall
exercise his/her choices of asking for specific performance or the
return of goods and cancellation.
12
[16] Clause 10 of the terms of the agreements signed by both parties is
also in line with Section 11 as it specifies the choices the plaintiff
(appellant) had to make in respect of a default or non-performance by
another party. It provides:-
a) should the Buyer ….. then and upon the happening of any of this event,
the seller shall be entitled in its election and without prejudice to any
other’s right to:-
i) claim immediate payment of all amounts payable hereof
irrespective of whether or not such amount are due at that
stage.
ii) cancel this agreement, take possession of the goods, retain all
payment already made in terms hereof by the Buyer and to
claim and liquidate damages payment of the difference between
the balance outstanding and the resale value of the goods
determined in accordance with clause10b.
[17] The trial court found, correct in my view, that the ex-parte interim court
order granted on 29 March 1999 which was made final on 12 May
1999, also does not amount to an order for cancellation. This is also
apparent from the wording of the said court order quoted supra.
[18] In my view the purpose of the interim order which was ultimately made
final was not for the permanent return of goods but, their attachment
for safe keeping in custody until the defendant pays and/or the
appellant brings and succeeds in his claim for the cancellation and
return of the same goods.
[19] Furthermore, the trial court found correctly in my view, that the general
requirement of cancellation of contracts is that cancellation can only
13
take place when the creditor failed to comply with the requirements of
a written notice of default within the number of days indicated therein.
It is quite clear in casu that the ex-parte application was made seven
(7) days after sending out the letter that contained the notice.
Therefore, the purpose of the ex-parte application could not have been
intended to serve as cancellation of the contract or have that effect.
The reason is that the respondents were still within the specified time
frame of 30 days provided in the letter of demand for them to comply
with the contract at that particular time.
[20] It is trite law that a decision to cancel a contract should not be vague
but must be a clear unequivocal election to do so. No doubt must
exist in the mind of the other party. Christie in the book of “The Law
of Contract in South Africa (5th edition, 2006) on page 539 states:-
“Notice of cancellation must be clear and unequivocal, but need not
correctly identify the cause of cancellation”
See also Data Colour v Intermarket 2001 (2) SA284 (SCA) of 299 E
where the following was said:-
“The innocent party to a breach of a contract justifying cancellation
exercises his right to cancel it (a) by words or conduct manifesting a clear
election to do so (b) which is communicated to the guilty party”. [My own
emphasis]
[21] From the above it is quite clear, as the trial court has found, that the
appellant never directly and unequivocally communicated to the
defendant that it is cancelling the contracts.
14
[22] Cancellation of a contract can also be effected by the issuing of a
summons. The appellant submitted before the trial court that the
contract was cancelled by the issuing of summons in this matter or by
the abovementioned confirmation by the court of the rule nisi. It is
common cause that the said items (goods) were sold almost seven (7)
months before summons was issued. With regard to this, the following
is stated in the Heads of Argument filed on behalf of the appellant:-
“4.1.1 Appellant kan nie betwis dat dagvaarding (29 Maart 2000)
sewe maande na verkoop van die items (12 Augustus 1999)
geskied het nie.
Ook nie dat op datum van die verkoop van die items (12
Augustus 1999) die kontrak nog nie gekanselleer was nie”
[My emphasis]
[23] This concession is indeed correct and well made. This is also in line
with what was said by the trial court, namely:-
“Die probleem met kansellasie deur dagvaarding is dat die aksie
eers sewe maande na die verkoop van die items ingestel is.
Die hof bevind dus dat op datum van verkoop van die items deur
die Eiser die kontrak tussen Eiser en Verweerder nog nie
gekanselleer was nie.”
This finding by the trial court cannot be faulted.
15
[24] Section 11 of the Credit Act states:-
“No credit grantor shall, by reason of the failure of the credit receiver to
comply with any obligation in terms of any credit agreement, to be
entitled to claim the return of the goods to which the credit agreement
relates the credit grantor by letter, handed over to the credit receiver
and for which an acknowledgement of receipts has been obtained or
posted by prepaid registered mail to the credit receiver at his address
stated in the credit agreement in terms of section 5(1)(b) nor the
address changed in accordance with section 5(4), has notified the
credit receiver that he so failed and has required him to comply with the
obligation in question in question within such period, being not less than
30 days after the date of such handing over or such posting, as may be
stated in the letter, and the credit receiver has failed to comply with
such requirement: Provided that should the credit receiver have failed
on two or more occasions to comply with obligations in terms of any
credit agreement and the credit grantor has given notice as aforesaid,
the said period shall be reduced to 14 days.”
[25] Applying section 11 of the The Act to the facts of this case, the trial
court found:-
“Deur die verkoping van die items het die eiser dus prestasie vir
die verweerder onmoontlik gemaak. Daar kan tog nie van die
verweerder verwag word om te presteer as die items verkoop en
vervreem is nie. Die vraag is waarop moet hy presteer?
Indien prestasie geheel en al onmoontlik word kan ‘n bevel vir
daadwerklike vervulling nie verleen word nie en is die skuldenaar
vir onmoontlike making nie geregtig op skadevergoeding nie.
16
Dit blyk dus uit die feite voor die hof dat eiser hulle eie skade
veroorsaak het deur die items te verkoop voor hulle ‘n hofbevel
verkry het wat verkoping van die items gemagtig het. En nog meer
voordat die kontrak tussen eiser en verweerder behoorlik en
regmatiglik gekanselleer is. Eiser het nooit aan verweerder na die
uitreiking van artikel 11 aanmanings die geleentheid gegee om aan
die bepalings en vereistes van die aanmanings te voldoen en
sodoende te presteer ingevolge die terme van die kontrak.”
[26] It was contended on behalf of the appellant that it was never made
impossible for the respondents to comply / perform in terms of the
contract. As at 19 March 1999, so it is further contended, was a court
order for attachment of the items obtained. In my view it is clear, as
was also found by the trial court, that the said order was for the safe
custody of the said items. It was not an order for cancellation of the
agreements nor was the appellants, in terms of the said court order,
empowered to the sell the said items on auction.
[27] The reasoning that the trial court erred in finding that appellants made
it impossible for the respondents to perform because they could still
have paid the instalments that were allegedly due, is flawed. The
correct procedures for cancellation and the return of items were not
followed. It can therefore not be expected of a litigant to perform
under such circumstances. Sight should not be lost of the fact that the
items sold included trucks that were probably used to earn an income.
If taken and sold unlawfully, the performance of the respondents is
rendered impossible.
17
[28] The particulars of claim attached to the summons stated that the said
contract be cancelled which is indicative of the fact that it was not
previously done. This serves as an intimation of the cancellation. This
unfortunately put a final nail on the coffin of the appellant’s case.
See: Middelburg Stadsraad v Trans Natal Steenkool Koöperasie
1970 (2) SA 244 (TPA);
Also: Shrosbree v Simen 1999 (2) SA 488 (SECLD);
Also: Win Twice Property v Binos 2004 (4) SA 436 (WLD).
[29] In Santambank Bpk v Dempers 1987 (4) SA 639 (OPA) the following
appears on page 645 I – 646 F:-
“Vir die redes wat ek reeds hierbo gegee het, het ek tot die
genoemde gevolgtrekking gekom dat die woorde ‘teruggawe te eis’
in art 11 van die Wet slaan op die beëindiging van die kontrak wat
aangegaan was tussen die kredietgewer en die kredietopnemer en
dat die kredietgewer se vordering waarmee hy tussentydse
verligting met betrekking tot die behoud van die goedere (wat sy
eiendom is) aanvra, nie besig is met ‘n eis om teruggawe soos
bedoel deur art 11 van die Wet nie omdat hy daardeur nog nie sy
aksie vir kansellasie en teruggawe afdwing nie. Die kredietgewer
se bedoelde aansoek vir bedoelde tussentydse regshulp in die vorm
van ‘n tussentydse interdik staan ook nie gelyk aan verbeuring nie
want die kredietopnemer verbeur eers dán sy reg op die gekoopte
of verhuurder goed as die aksie wat die kredietgewer teen hom
gaan instel ná afloop van die 30 dae vermeld in die gesegde
kennisgewing, met ‘n uitspraak ten gunste van die kredietgewer
18
afgesluit word waarin kansellasie en teruggawe beveel word.
Indien hy byvoorbeeld binne die tydperk wat in die kennisgewing
gestel word sy versuim herstel (deur byvoorbeeld te betaal), dan is
hy geregtig om die koopgoed of huurgoed terug te kry en is die
kredietgewer trouens verplig om dit aan hom terug te besorg.
Weliswaar word die kredietopnemer se reg om die koop- of
huurgeld te gebruik van hom ontneem, en wel terwyl die
kredietooreenkoms nog nie beëindig is nie en hy derhalwe ceteris
paribus op ongestoorde besit daarvan geregtig sou wees totdat die
kredietooreenkoms beëindig word. Deur die kredietooreenkoms te
verbreek het die kredietopnemer egter sy besitreg van die goed in
gevaar gestel want die kredietgewer is geregtig om vir hom
onmiddellik ‘n art 11-kennisgewing te gee om sy gebrek aan te
suiwer indien die kredietgewer hom vir kansellasie en teruggawe
wil dagvaar en sal die kredietopnemer die goed moet teruggee as
die kredietgewer met sy geding (wat hy na afloop van 30 dae kan
instel) suksesvol is. Dat hy intussen die gebruik van sy goed mag
verloor is, indien die tussentydse beslaglegging regtens geoorloof
is, regstreeks te wyte aan sy kontrakbreuk, maar sodanige verlies
van gebruik (indien dit deur tussentydse beslaglegging
teweeggebring word) is immers nie stricto sensu ‘n verbeuring van
die goed self nie want verbeuring behels ‘n eenmalige gebeurtenis
met permanente en finale ontneming van die kredietopnemer se
regte, en dit gebeur eers as die kredietgewer se eis vir kansellasie
en teruggawe geslaag het.”
[30] The crux of the matter in my view is the fact that no order for
cancellation of the contract and repossession of the items has been
granted by a court of law. To reiterate, the appellant acquired
19
possession of the said items in terms of an interim court order, which
was later confirmed, for the safe custody of the said items. The
appellant then, without a due process of the law, sold the said items
on auction shortly after it had acquired possession thereof. The
actions of the appellant under these circumstances cannot be
condoned. In my view, the trial court was correct in arriving at the
conclusion already quoted in paragraph 25, supra.
[31] As far as quantum is concerned, the trial court did not in its reasons for
judgment deal with the evidence presented by the appellant as
plaintiff. The reason for this is obviously that because there was no
valid cancellation of the contract (based on the alleged breach of
contract) which is a point of law, there can be no damages flowing
therefrom.
[32] On page 629 and 630 of the book by Christie quoted above, the
relevant principles in a claim for damages were set out as follows:-
“Any investigation of damages for breach of contract must logically start with an
inquiry into whether the damages were caused by the breach. It so happens that
this inquiry has engaged the attention of the courts more frequently in the law of
delict than in the law of contract, but in both types of case the inquiry is basically
the same, and Corbett CJ’s restatement of the relevant principles in International
Shipping Co (Pty) Ltd v Bentley 1990 1 SA 680 (A) 700E-701A is as authoritative
in contract as in delict.
These principles call for a two stage inquiry, first into factual causation and then
into legal causation. To establish factual causation it must be shown that the
breach was the causa sine qua non of the loss. This quaint Latin phrase is best
understood by applying the but-for test: would the plaintiff have suffered the loss
but for the defendant’s breach? If it cannot be shown that the loss would not have
20
occurred but for the breach, the plaintiff’s claim for damages fails and the second
stage of the inquiry does not arise.”
[33] I find the words quoted above apposite in this matter and in line with
the following finding of the trial court:-
“Grobbelaar vs Bosch 1964 (3) SA 6876
As ń kontraktant nie vir die onmoontlik wording te blameer is nie, hy
van prestasie verskoon word”
“Die verweerders wat nie te blameer is vir die onmoontlik making nie
word dus verskoon van prestasie in die kontrak en dus enige skade wat
gelei kan word uit die nie prestasies wat gelewer is nie.”
Likewise, the contention that specific performance was not claimed but
damages flowing from cancellation of the agreement based on breach
thereof, cannot be sustained. The selling of the items attached before
a valid cancellation of the contract amounts to repudiation of the
contract by the appellant.
[34] The respondents did not present any evidence during the trial in the
court a quo. Much had been said by counsel of the appellant about the
quantum. In my view, the trial court was indeed correct to conclude
that there was no need to take the evidence on quantum into account
and its finding in this regard cannot be faulted. There is therefore no
need to say anything more on quantum.
[35] Much criticism has also been levelled against the trial court’s finding
for the awarding of a punitive costs order. Flowing from the reasons of
judgment, it is apparent that the trial court demonstrated its disquiet
21
about the conduct of the appellant by obtaining an order for the safe
custody of the seized items and then, without affording the
respondents the opportunity to perform and rectify their alleged
default, gave an instruction to an auctioneer to sell the said items.
Thereafter, to take it even further, instituted a claim for cancellation of
the contract and for damages. The awarding of a costs order
especially on a punitive scale is in the discretion of the trial court. A
Court of Appeal will not lightly interfere with the exercise of such
discretion, unless it is found to be totally wrong. I cannot come to such
a conclusion. In my view, there is no reason to disturb the findings of
the trial court also with regard to the costs order. In view of the fact
that the respondents are successful, there is also no plausible reason
why costs should not follow the event.
G. ORDER
[36] Consequently, the following order is made:-
36.1 The appeal is dismissed with costs.
________________ A M KGOELE JUDGE OF THE HIGH COURT