Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program Request

Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

Embed Size (px)

Citation preview

Page 1: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

Carroll County Public Schools

Board of Education Work SessionAugust 27, 2014

FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program Request

Page 2: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

CCPS Capital Budget Process Educational Facilities Master Plan June Presentation/Board Work Session August Public Hearing

September Approval by Board of Education October Submission to County and State October County adoption of Budget May State approval of final CIP May

8/27/2014

Page 3: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

Focus of CIP Request New North Westminster Area K-8 School New Career & Technology Center Replacement of 14 Single Ply Roofs that are

past their useful lives Replacement of 6 Heating, Air Condition, and

Ventilating (HVAC) Systems that are past their useful lives

8/27/2014

Page 4: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

North Westminster K-8 School• Replace both Charles Carroll and William

Winchester Elementary Schools• Replace Westminster East Middle School• Total Project cost = $72,444,000• Based on 220,000 square feet• Elementary School Capacity of 979 and a Middle

School Capacity of 790• Supplants $72,000,000 million in last year’s CIP

for modernizations of Charles Carroll, East Middle, and William Winchester

8/28/2013

Page 5: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

New Career & Technology Center• Replace current Career & Technology Center• Total Project Cost = $75,972,000• Based on 200,000 square feet building

housing 29 programs• Eliminate Roof and HVAC projects if funded

8/28/2013

Page 6: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

Roofing Projects

8/28/2013

• CIP moved SCHS and WHS roofs up to FY16 based on condition

• Plan replaces 14 single ply roofs that are past their useful lives

• Plan also eliminates the need to replace Charles Carroll and East Middle roofs

• Implementation of this plan will leave six schools that still have single ply roofs

Page 7: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

HVAC Systems

8/27/2014

Plan replaces six HVAC systems that are past their useful lives

Plan also eliminates the need to replace Charles Carroll and East Middle HVAC systems

Page 8: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

Kindergarten Additions

8/28/2013

• Plan includes last four Kindergarten Additions required as part of the move to Full Day Kindergarten

• Kindergarten classes are currently being held in classrooms were not designed to meet the instructional needs of Kindergartners

Page 9: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

High School Science Rooms

8/28/2013

• Plan includes the renovation of 19 science classrooms at our oldest high schools that have not been renovated to meet today’s instructional program

• The County’s current Adopted CIP does have funding included to complete these projects

• Plan amended to align with County funding timeline

Page 10: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

Other Systemic Renovations

8/28/2013

• Plan includes the replacement of aging electrical equipment at Westminster High and Sykesville Middle

• Plan includes the replacement of existing Fire Alarm System at North Carroll High

• Plan includes the replacement of existing windows at South Carroll High and Westminster High

Page 11: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

FY16 County Request ($000) omitted

1. New North Westminster K-8(Planning) $5,5272. CCCTC Roof $2,4683. Westminster ES Roof $1,7554. South Carroll HS Roof $4,0925. Westminster HS Roof $3,8626. Francis Scott Key HS Roof (Planning) $2617. CCCTC HVAC(Planning) $8538. Westminster HS Electrical(Planning) $1009. Taneytown ES K Addition (Planning) $87

8/27/2014

Page 12: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

FY16 County Request (cont.) ($000) omitted

10. Paving $85511. Technology Improvements $1,31012. Roofing Improvements $16013. Barrier Free Modifications $5014. Relocatable Classrooms $60

County Total $15,023

8/27/2014

Page 13: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

FY17 – FY21 County Request County Share of FY17-FY21 Request = $152,631,000

3 Modernization projects10 Roof Replacement projects6 HVAC Replacement projects4 Kindergarten Addition projects4 Science Room Renovation projects2 Electrical Service projects1 Fire Alarm System projects2 Window Replacement projectsAnnual Requests (Paving, Technology, Roofing, Barrier Free Modifications, & Relocatables)

8/27/2014

Page 14: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

County CIP & BOE Request

8/27/2014

Page 15: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

FY16 State Request($000) omitted

1. New North Westminster K-8 School Planning2. CCCTC Roof Replacement $1,3703. Westminster ES Roof Replacement $9074. South Carroll HS Roof $2,1435. Westminster HS Roof $1,997 State Total $6,417

8/27/2014

Page 16: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

State Construction Funding

8/27/2014

Page 17: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

17

CIP Request Discussion

8/27/2014

Page 18: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

North Westminster Area K-8 Project

• State Approval Process• State Site Approval - Priority Funding Area Requirements• Disposition of School Facilities – State Definitions• Feasibility Study requirements• Funding participation

• Local Process• Site Search and School Location• Cost benefits analysis of William Winchester Elementary, East Middle,

and Winchester Building Properties• Level of funding commitment to complete all aspects of project• Current County CIP - Charles Carroll Modernization• Inclusion of other community needs

8/27/2014

Page 19: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

MGT Boundary Recommendations Discussion Points

• Timing of Boundary Study with Decisions on North Westminster Area School

• Avoiding the Possibility of Redistricting Twice• Future Steps and Recommendations

• Committee Report at September 10th Board Meeting• Delay study of northern boundaries until final decision

on North Westminster area• Proceed with southern elementary boundaries study in

summer of 2015

8/27/2014

Page 20: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

Career & Technology Center

• Systemic Renovations vs. Replacement School• Roof and HVAC Project are in poor condition and

are in FY16 Request• Systemic Renovation projects can be viewed as a

commitment to utilize the existing Center for another 15 years

8/27/2014

Page 21: Carroll County Public Schools Board of Education Work Session August 27, 2014 FY 2016 Capital Budget and FY 2017 – FY 2021 Capital Improvement Program

21

Systemic Renovations BOE CIP Request includes $29,500,000 in Roof Replacement

projects ($14,495,000 Local) County Adopted CIP includes $13,346,000 in Roof

Replacement projects ($5,169,000 Local) BOE CIP Request includes $39,384,000 in HVAC Replacement

projects ($19,095,000 Local) County Adopted CIP includes $6,410,000 in HVAC

Replacement projects ($3,121,000 Local)

8/27/2014