30
Carlson Geotechnical 35 SE Bridgeford Boulevard, Bend, Oregon 97702 Carlson Geotechnical A division of Carlson Testing, Inc. Phone: (541) 330-9155 Fax: (541) 330-9163 Bend Office Eugene Office Salem Office Tigard Office (541) 330-9155 (541) 345-0289 (503) 589-1252 (503) 684-3460 Report G1303790 Report of Geotechnical Investigation River Vale River Rim Drive & Charleswood Lane Bend, Oregon CGT Project Number B1707933 Prepared for Pahlisch Homes Attn: Mr. Chad Bettesworth 210 SW Wilson Avenue Bend, Oregon 97702 October 25, 2017

Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

Carlson Geotechnical 35 SE Bridgeford Boulevard, Bend, Oregon 97702

Carlson Geotechnical A division of Carlson Testing, Inc. Phone: (541) 330-9155 Fax: (541) 330-9163

Bend Office Eugene Office Salem Office Tigard Office

(541) 330-9155 (541) 345-0289 (503) 589-1252 (503) 684-3460

Report G1303790 Report of Geotechnical Investigation River Vale River Rim Drive & Charleswood Lane Bend, Oregon CGT Project Number B1707933 Prepared for Pahlisch Homes Attn: Mr. Chad Bettesworth 210 SW Wilson Avenue Bend, Oregon 97702 October 25, 2017

Page 2: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th
Page 3: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 3 of 18

TABLE OF CONTENTS 1.0 INTRODUCTION ............................................................................................................................... 4

1.1 Project Description ..................................................................................................................... 4 1.2 Scope of Work ............................................................................................................................. 4

2.0 SITE DESCRIPTION ......................................................................................................................... 5 2.1 Site Geology ................................................................................................................................ 5 2.2 Site Surface Conditions .............................................................................................................. 5

3.0 FIELD INVESTIGATION ................................................................................................................... 5 4.0 LABORATORY TESTING ................................................................................................................ 6 5.0 SUBSURFACE CONDITIONS .......................................................................................................... 6

5.1 Soils & Rock ................................................................................................................................ 6 5.2 Groundwater ................................................................................................................................ 6

6.0 SEISMIC CONSIDERATIONS .......................................................................................................... 7 6.1 Seismic Design ............................................................................................................................ 7 6.2 Seismic Hazards .......................................................................................................................... 7

7.0 CONCLUSIONS ................................................................................................................................ 8 8.0 RECOMMENDATIONS ..................................................................................................................... 9

8.1 Site Preparation ........................................................................................................................... 9 8.2 Temporary Excavations ............................................................................................................ 10 8.3 Wet Weather Considerations ................................................................................................... 11 8.4 Structural Fill ............................................................................................................................. 12 8.5 Shallow Foundations ................................................................................................................ 14 8.6 Floor Slabs ................................................................................................................................. 16 8.7 Pavements ................................................................................................................................. 17 8.8 Additional Considerations ....................................................................................................... 17

9.0 RECOMMENDED ADDITIONAL SERVICES ................................................................................. 17 9.1 Design Review ........................................................................................................................... 17 9.2 Observation of Construction ................................................................................................... 17

10.0 LIMITATIONS ................................................................................................................................. 18

ATTACHMENTS Site Location ...................................................................................................................................... Figure 1 Site Plan ............................................................................................................................................. Figure 2 Soil Classification Criteria & Terminology .......................................................................................... Figure 3 ODOT Rock Classification Criteria & Terminology ............................................................................ Figure 4 Test Pit Logs .................................................................................................................. Figures 5 through 12 Doc ID: B:\GEOTECH\PROJECTS\2017 Projects\RiverVale\B1707933 Report.docx

Page 4: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 4 of 18

1.0 INTRODUCTION

Carlson Geotechnical (CGT), a division of Carlson Testing, Inc. (CTI), is pleased to submit this report summarizing the results of our limited geotechnical investigation for the proposed River Vale Subdivision project. The site is located west of the intersection of River Rim Drive and Charleswood Lane in Bend, Oregon, as shown on the attached Figure 1.

1.1 Project Description

CGT developed an understanding of the proposed project based on our correspondence and review of the provided “draft project plans” dated July 20, 2017, and prepared by DevTech Engineering Inc. Based on our review, we understand the project will include:

• Mass grading at the site to accommodate a new residential subdivision that will include 78 new residential lots. Although no grading plans have been provided, we anticipate permanent grade changes at the site will be relatively minimal, with cuts and fills generally limited to less than 3 feet in depth.

• Development within each lot is anticipated to include construction of a two-story, wood-framed, residential structure. We anticipate the living spaces of the residences will incorporate post-and-beam construction, while attached garages will incorporate slab-on-grade floors. No below-grade levels (basements) are anticipated for this site.

• Construction of new roadways and appurtenant utilities to serve the new residential lots. Pavement section design will rest with others.

• We anticipate stormwater collected from new impervious areas at the site will be collected and routed to the public stormwater system or other suitable discharge point(s). Infiltration testing was not included as part of this assignment.

1.2 Scope of Work

The purpose of our work was to explore subsurface conditions at the site in order to provide geotechnical recommendations for design and construction of the proposed development. Our scope of work consisted of the following:

• Contact the Oregon Utilities Notification Center to mark the locations of public utilities within a 30-foot radius of our explorations at the site.

• Explore subsurface conditions at the site by observing the excavation of eight test pits to practical refusal depths of up to about 7½ feet below ground surface (bgs).

• Classify the materials encountered in the explorations in general accordance with American Society for Testing and Materials (ASTM) D2488 (Visual-Manual Procedure).

• Collect representative, disturbed samples of the soils encountered within the test pits in order to perform laboratory testing and to confirm our field classifications.

• Perform laboratory testing on the soil samples obtained during site exploration to refine our field classifications. Laboratory testing included eight moisture content tests (ASTM D2216) and three fines content tests (ASTM D1140).

• Provide a technical narrative describing surface and subsurface deposits, and local geology of the site, based on the results of our explorations and published geologic mapping.

Page 5: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 5 of 18

• Provide a site vicinity map and a site plan showing the locations of the explorations relative to existing site features.

• Provide logs of the explorations, including results of laboratory testing on selected soil samples. • Provide geotechnical recommendations for site preparation, earthwork, and design and construction of

shallow foundations and floor slabs. • Provide geotechnical recommendations for pavement subgrade preparation. • Provide recommendations for the Seismic Site Class, mapped maximum considered earthquake spectral

response accelerations, and site seismic coefficients. • Provide a qualitative evaluation of seismic hazards at the site, including liquefaction potential,

earthquake-induced landsliding, and surface rupture due to faulting or lateral spread. • Provide this written report summarizing the results of our geotechnical investigation and

recommendations for the project.

2.0 SITE DESCRIPTION

2.1 Site Geology

Based on available geologic mapping1 of the area, the site is underlain by basalt of Newberry volcano (Pleistocene). This unit consists of gray porphyritic lava that locally includes minor basaltic andesite. Many exposures are columnar jointed with broad hummocky plains east of the Deschutes River. Primary flow features are characterized by pressure plateaus, pressure ridges, tumuli, and residual depressions. The flows likely erupted from vents on the north and northwest flanks of Newberry volcano, approximately 15 miles southeast of the site. The unit includes flows of different ages with some of the oldest flows offset by faulting, while the youngest have spilled over fault scarps in the older flows. Thickness of the unit ranges from about 3 to 65 feet. Based on stratigraphy exposed in the adjacent Deschutes River canyon, these basalts are underlain by older (Pleistocene and Pliocene) basalts.

2.2 Site Surface Conditions

The approximate 37-acre site is bounded by the Deschutes River to the west, existing residential development to the north and east, and undeveloped land to the south. At the time of our field investigation, the site was undeveloped and surfaced with short grasses, scattered juniper trees and small shrubs. In terms of topography, the site was relatively level to gently ascending to the east.

3.0 FIELD INVESTIGATION

CGT explored subsurface conditions at the site by observing the excavation of eight test pits (TP-1 through TP-8) on September 25, 2017, to practical refusal depths of up to about 7½ feet bgs. The test pits were excavated using a Takeuchi TB260 mini excavator, provided and operated by our subcontractor, Terry Shine Excavating of Bend, Oregon. The approximate test pit locations are shown on the attached Site Plan, Figure 2. The test pits were located in the field using approximate measurements from existing features. Upon completion, the test pits were loosely backfilled with the excavated materials.

1 Mimura, Koji, 1992, Reconnaissance Geologic Map of the West Half of the Bend and the East Half of the Shevlin Park 7½’

Quadrangles, Deschutes County, Oregon. U.S. Geological Survey, Map MF-2189

Page 6: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 6 of 18

A qualified member of CGT’s geotechnical staff logged the soils and rock encountered within the test pits in general accordance with the Unified Soil Classification System (USCS) and the ODOT Soil and Rock Classification Manual, respectively. Explanations of these classification criteria are provided on the attached Figures 3 and 4, respectively. Representative disturbed (grab) samples of the soils were collected as the test pits were excavated. The samples were stored in sealable plastic bags and transported to our laboratory for further examination and testing. Logs of the explorations are presented on the attached Test Pit Logs, Figures 5 through 12.

4.0 LABORATORY TESTING

Laboratory testing was performed on samples collected in the field to refine our initial field classifications and determine in-situ parameters. Laboratory testing included eight moisture content determinations (ASTM D2216) and three percentage passing the U.S. Standard No. 200 Sieve tests (ASTM D1140). Results of the laboratory tests are shown on the attached Test Pit Logs, Figures 5 through 12.

5.0 SUBSURFACE CONDITIONS

The following sections detail subsurface conditions encountered in the explorations.

5.1 Soils & Rock

Silty Sand Topsoil (OL): Silty sand topsoil was encountered at the surface of each test pit and was approximately ½-foot thick. The topsoil was generally brown, moist, fine-grained, and rooted. Silty Sand (SM): Below the silty sand topsoil, we encountered silty sand that contained varying amounts of subangular gravel to 1 inch in diameter and cobbles up to 12 inches in diameter. The silty sand was generally medium dense, brown, damp to moist, and fine-grained. The silty sand extended to depths of about 3½ to 7½ feet bgs. Basalt Bedrock (RX): Beneath the silty sand in each test pit, we encountered basalt bedrock. The basalt was typically hard (R4), gray and fresh. Practical refusal of the referenced mini excavator was encountered at about ½ foot below the surface of the basalt in each test pit.

5.2 Groundwater

Groundwater was not encountered within the depths explored in the test pits in September 2017. We researched available well logs located within Section 13, Township 18 South, Range 11 East on the Oregon Water Resources Department (OWRD)2 website. Our review indicated that groundwater levels in the area varied with surface elevations but were generally encountered at depths in excess of 100 feet bgs. It should be noted that groundwater levels vary with local topography. In addition, the groundwater levels reported on the OWRD logs often reflect the purpose of the well, so water well logs may only report deeper, confined groundwater, while geotechnical or environmental borings will often report any groundwater encountered, including shallow, unconfined groundwater. Therefore, the levels reported on the OWRD well logs referenced above are considered generally indicative of local water levels and may not reflect actual groundwater levels at the project site.

2 Oregon Water Resources Department, 2017. Well Log Records, accessed October 2017, from OWRD web site:

http://apps.wrd.state.or.us/apps/gw/well_log/.

Page 7: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 7 of 18

6.0 SEISMIC CONSIDERATIONS

6.1 Seismic Design

The 2014 Oregon Residential Specialty Code (2014 ORSC) requires the determination of seismic site class be based on subsurface data in accordance with Chapter 20 of the American Society of Civil Engineers Minimum Design Loads for Buildings and Other Structures (ASCE 7). Based on the results of our subsurface explorations and analyses, we have assigned a Site Class D for the subsurface conditions encountered. Seismic ground motion values were determined in accordance with Section R301.2.2 of the 2014 ORSC. The Seismic Design Category was determined from Table R301.2.2.1.1 of the 2014 ORSC. Earthquake ground motion parameters for the site were obtained based on the United States Geological Survey (USGS) Seismic Design Values for Buildings - Ground Motion Parameter Calculator3. The site Latitude 44.012345° North and Longitude 121.355789° West were input as the site location. The following table shows the recommended seismic design parameters for the site.

Table 1 Seismic Ground Motion Values (2014 ORSC) Parameter Value

Mapped Acceleration Parameters Spectral Acceleration, 0.2 second (Ss) 0.414g Spectral Acceleration, 1.0 second (S1) 0.212g

Coefficients (Site Class D)

Site Coefficient, 0.2 sec. (FA) 1.469 Site Coefficient, 1.0 sec. (FV) 1.977

Adjusted MCE Spectral Response Parameters

MCE Spectral Acceleration, 0.2 sec. (SMS ) 0.608g MCE Spectral Acceleration, 1.0 sec. (SM1 ) 0.418g

Design Spectral Response Accelerations Design Spectral Acceleration, 0.2 seconds (SDS ) 0.405g Design Spectral Acceleration, 1.0 second (SD1 ) 0.279g

Seismic Design Category D

6.2 Seismic Hazards

6.2.1 Liquefaction

In general, liquefaction occurs when deposits of loose/soft, saturated, cohesionless soils, generally sands and silts, are subjected to strong earthquake shaking. If these deposits cannot drain quickly enough, pore water pressures can increase, approaching the value of the overburden pressure. The shear strength of a cohesionless soil is directly proportional to the effective stress, which is equal to the difference between the overburden pressure and the pore water pressure. When the pore water pressure increases to the value of the overburden pressure, the shear strength of the soil approaches zero, and the soil can liquefy. The liquefied soils can undergo rapid consolidation or, if unconfined, can flow as a liquid. Structures supported by the liquefied soils can experience rapid, excessive settlement, shearing, or even catastrophic failure. For fine-grained soils, susceptibility to liquefaction is evaluated based on penetration resistance and plasticity, among other characteristics. Criteria for identifying non-liquefiable, fine-grained soils are

3 United States Geological Survey, 2017. Seismic Design Parameters determined using:, “U.S. Seismic Design Maps Web

Application,” accessed October 2017, from the USGS website http://earthquake.usgs.gov.

Page 8: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 8 of 18

constantly evolving. Current practice4 to identify non-liquefiable, fine-grained soils is based on plasticity characteristics of the soils, as follows: (1) liquid limit greater than 47 percent, (2) plasticity index greater than 20 percent, and (3) moisture content less than 85 percent of the liquid limit. The susceptibility of sands, gravels, and sand-gravel mixtures to liquefaction is typically assessed based on penetration resistance, as measured using SPTs, CPTs, or Becker Hammer Penetration tests (BPTs). Based on the lack of groundwater within the depths explored and the presence of shallow bedrock, we conclude there is a negligible risk of liquefaction occurring at the site.

6.2.2 Slope Instability

The majority of the site is relatively flat and has a negligible risk of slope instability, seismically induced or otherwise. The western portion of the site is situated along the crest of the eastern wall of the Deschutes River canyon. The geologic hazard mapping5 indicates a moderate to high hazard associated with landslides on these slopes. We conclude there is a commensurate risk of seismically induced landslides impacting these slopes and the areas immediately adjacent to their crest. Recommendations for minimum slope setback for residential structure foundations are presented later in this report. In the event development plans include situating residential structures within the recommended setback zone, a quantitative slope stability analysis should be performed. Such an analysis would require borings using powered drilling and rock coring capabilities, and is outside the scope of this assignment.

6.2.3 Surface Rupture

6.2.3.1 Faulting Although the site is situated in a region of the country with known active faults, none are mapped on or in the immediate vicinity of the site. Therefore, we conclude the risk of surface rupture at the site due to faulting is very low.

6.2.3.2 Lateral Spread Surface rupture due to lateral spread can occur on sites underlain by liquefiable soils that are located on or immediately adjacent to slopes steeper than about 3 degrees (20H:1V), and/or adjacent to a free face, such as a stream bank or the shore of an open body of water. During lateral spread, the materials overlying the liquefied soils are subject to lateral movement downslope or toward the free face. Based on the negligible risk of liquefaction at the site, we conclude the risk of lateral spread is similarly negligible.

7.0 CONCLUSIONS

Based on the results of our field explorations and analyses, the site may be developed as described in Section 1.1 of this report, provided the recommendations presented in this report are incorporated into the design and development. Satisfactory subgrade support for shallow foundations, floor slabs, and pavements can be obtained from the native, medium dense to better, silty sand (SM), the basalt bedrock (RX), or on structural fill that is properly placed and compacted on these materials during construction.

4 Seed, R.B. et al., 2003. Recent Advances in Soil Liquefaction Engineering: A Unified and Consistent Framework. Earthquake

Engineering Research Center Report No. EERC 2003-06. 5 Oregon Department of Geology and Mineral Industries, 2017. Oregon Statewide Geohazards Viewer, accessed October 2017,

from DOGAMI web site: http://www.oregongeology.org/sub/hazvu/index.htm.

Page 9: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 9 of 18

The primary geotechnical consideration for this project is the presence of near-surface, relatively fresh, hard basalt bedrock (RX). As shown on the attached Site Plan, Figure 2, and the test pit logs, we encountered basalt bedrock at depths of about 3½ to 7½ feet bgs during our field investigation. The presence of shallow bedrock should be factored when considering temporary excavations necessary to install shallow foundations and other below-grade facilities (such as utilities) at the site. We do not anticipate that excavation of the bedrock using conventional excavation equipment will be feasible. Depending on finalized elevations, we anticipate hydraulic hammering of the bedrock will likely be required to facilitate its removal. Hydraulic hammering, if required, will likely result in increased cost and should be factored in planning. Geotechnical recommendations for temporary excavations are presented in Section 8.2 of this report. The native silty sand (SM) is sensitive to small changes in moisture content. Grading of these soils during wet weather can pose challenges for earthwork. Considerations for wet weather construction are discussed in Section 8.3 of this report. Re-use of these soils as structural fill during wet times of the year will require special consideration, as discussed in Section Error! Reference source not found. of this report.

8.0 RECOMMENDATIONS

The recommendations presented in this report are based on the information provided to us, results of the field investigation, laboratory data, and professional judgment. CGT has observed only a small portion of the pertinent subsurface conditions. The recommendations are based on the assumptions that the subsurface conditions do not deviate appreciably from those found during the field investigation. CGT should be consulted for further recommendations if the design and/or location of the proposed development changes, or variations and/or undesirable geotechnical conditions are encountered during site development.

8.1 Site Preparation

8.1.1 Site Stripping

Existing vegetation and silty sand topsoil (SM) should be removed from within, and for a minimum 5-foot margin around, proposed structural fill, building pads, and pavement areas. Based on the results of the test pits, stripping depths at the site are anticipated be to about ½ foot bgs. These materials may be deeper or shallower away from the exploration locations. The geotechnical engineer or his representative should provide recommendations for actual stripping depths based on observations during site stripping. Stripped surface vegetation and topsoil should be transported off-site for disposal, or stockpiled for later use in landscaped areas.

8.1.2 Grubbing

Grubbing of trees and shrubs should include the removal of the root mass and roots greater than ½-inch in diameter. Grubbed materials should be transported off-site for disposal. Where root masses are removed, the resulting excavation should be properly backfilled with structural fill in conformance with Section 8.4 of this report.

8.1.3 Existing Utilities & Below-Grade Structures

All existing utilities at the site should be identified prior to excavation. Abandoned utility lines beneath the new residential structures and pavements should be completely removed or grouted full. Soft, loose, or otherwise unsuitable soils encountered in utility trench excavations should be removed and replaced with

Page 10: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 10 of 18

imported granular structural fill in conformance with Section 8.4.2 of this report. No below-grade structures were encountered in our explorations. Where encountered during site preparation, buried structures (i.e. footings, foundation walls, slabs-on-grade, tanks, etc.) should be completely removed and disposed of off-site. The resulting excavation should be backfilled with imported granular structural fill in conformance with Section 8.4.2 of this report.

8.1.4 Test Pit Backfills

The test pits conducted at the site were loosely backfilled during our field investigation. Where test pits are located within finalized structural fill, building pad, or pavement areas, the loose backfill materials should be re-excavated. The resulting excavations should be backfilled with structural fill placed and compacted in general accordance with Section 8.4.2 of this report.

8.1.5 Subgrade Preparation – Pavement Areas & Residential Lots to Receive Structural Fill

8.1.5.1 Dry Weather Construction After site preparation as recommended above, but prior to placement of structural fill and/or base rock, the geotechnical engineer or his representative should observe a proof roll test of the exposed subgrade soils in order to identify areas of excessive yielding. Proof rolling of subgrade soils is typically conducted during dry weather conditions using a fully-loaded, 10- to 12-cubic-yard, tire-mounted, dump truck or equivalent weighted water truck. Areas that appear too soft and wet to support proof rolling equipment should be prepared in general accordance with the recommendations for wet weather construction presented in Section 8.3 of this report. If areas of soft soil or excessive yielding are identified, the affected material should be over-excavated to firm, stable subgrade, and replaced with imported granular structural fill in conformance with Section 8.4.2 of this report.

8.1.5.2 Wet Weather Construction Preparation of residential lot and pavement subgrade soils during wet weather should be in conformance with Section 8.3 of this report. As indicated therein, increased base rock sections and a geotextile separation fabric may be required in wet conditions in order to support construction traffic and protect the subgrade. Cement amendment may also be considered to help stabilize subgrade soils during wet weather.

8.1.6 Erosion Control

Erosion and sedimentation control measures should be employed in accordance with applicable City, County, and State regulations regarding erosion control.

8.2 Temporary Excavations

8.2.1 Overview

All excavations should be in accordance with applicable OR-OSHA regulations. It is the contractor's responsibility to select the excavation methods, to monitor site excavations for safety, and to provide any shoring required to protect personnel and adjacent improvements. A “competent person”, as defined by OR-OSHA, should be on-site during construction in accordance with regulations presented by OR-OSHA. CGT’s current role on the project does not include review or oversight of excavation safety.

Page 11: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 11 of 18

8.2.2 OSHA Soil Types

8.2.2.1 Silty Sand (SM) Conventional earthmoving equipment in proper working condition should be capable of making necessary excavations into the on-site sandy soils. For use in the planning and construction of temporary excavations at the site, an OSHA soil type “C” should be used for the native, silty sand (SM). Some caving or sloughing of the sidewalls may occur in dry, cohesionless soils. In the event that caving of the sidewalls is observed, the sidewalls should be flattened or shored.

8.2.2.2 Basalt Bedrock (RX) The basalt encountered in the test pits was generally hard (R4) and fresh. An OSHA soil type “A” may be used for the native basalt (RX) during planning and construction of temporary excavations at the site extending below the bedrock. We anticipate that excavation of the basalt using conventional excavation equipment will not be feasible. Hydraulic hammering will likely be required to facilitate excavation of the basalt. Blasting of the basalt bedrock is not recommended due to the site’s proximity to offsite residential development. If the contractor proposes blasting, the geotechnical engineer should be engaged early in the design process to review pre-construction surveys, design, and monitoring plans.

8.2.3 Excavations Near Foundations

Excavations near footings should not extend within a 1H:1V (horizontal:vertical) plane projected out and down from the outside, bottom edge of the footings. In the event that excavation needs to extend below the referenced plane, temporary shoring of the excavation and/or underpinning of the subject footing may be required. The geotechnical engineer should be consulted to review proposed excavation plans for this design case to provide specific recommendations.

8.3 Wet Weather Considerations

Notwithstanding the generally arid conditions of the Bend area, soil conditions should be evaluated in the field by the geotechnical engineer or his representative at the initial stage of site preparation to determine whether the recommendations within this section should be incorporated into construction.

8.3.1 General

Trafficability of the near-surface, silty sand (SM) may be difficult, and significant damage to subgrade soils could occur, if earthwork is undertaken without proper precautions at times when the exposed soils are more than a few percentage points above optimum moisture content. For construction that occurs during wet weather, site preparation activities may need to be accomplished using track-mounted equipment, loading removed material onto trucks supported on granular haul roads, or utilizing other methods to limit soil disturbance. The geotechnical engineer or his representative should evaluate the subgrade during excavation by probing rather than proof rolling. Soils that have been disturbed during site preparation activities, or soft or loose areas identified during probing, should be over-excavated to firm, stable subgrade, and replaced with imported granular structural fill in conformance with Section 8.4.2 of this report.

8.3.2 Geotextile Separation Fabric

We recommend a geotextile separation fabric be placed to serve as a barrier between the prepared fine-grained subgrade and granular fill/base rock in areas of repeated or heavy construction traffic. The

Page 12: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 12 of 18

geotextile fabric should be in conformance with Section 02320 of the current Oregon Department of Transportation (ODOT) Standard Specification for Construction.

8.3.3 Granular Working Surfaces (Haul Roads & Staging Areas)

Haul roads subjected to repeated heavy, tire-mounted, construction traffic (e.g. dump trucks, concrete trucks, etc.) will require a minimum of 18 inches of imported granular material. For light staging areas, 12 inches of imported granular material is typically sufficient. Additional granular material, geo-grid reinforcement, or cement amendment may be recommended based on site conditions and/or loading at the time of construction. The imported granular material should be in conformance with Section 8.4.2 of this report and have less than 5 percent material passing the U.S. Standard No. 200 Sieve. The prepared subgrade should be covered with geotextile fabric prior to placement of the imported granular material. The imported granular material should be placed in a single lift (up to 24-inches deep) and compacted using a smooth-drum, non-vibratory roller until well-keyed.

8.3.4 Footing Subgrade Protection

A minimum of 3 inches of imported granular material is recommended to protect fine-grained footing subgrades from foot traffic during inclement weather. The imported granular material should be in conformance with Section 8.4.2 of this report, have less than 5 percent material passing the U.S. Standard No. 200 Sieve, and have a maximum particle size limited to 1-inch. The imported granular material should be placed in one lift over the prepared, undisturbed subgrade, and compacted using non-vibratory equipment until well keyed.

8.4 Structural Fill

The geotechnical engineer should be provided the opportunity to review all materials considered for use as structural fill (prior to placement). The geotechnical engineer or his representative should be contacted to evaluate compaction of structural fill as the material is being placed. Evaluation of compaction may take the form of in-place density tests and/or proof roll tests with suitable equipment. Structural fill should be evaluated at intervals not exceeding every 2 vertical feet as the fill is being placed.

8.4.1 On-Site Materials

8.4.1.1 Silty Sand (SM) Re-use of this soil as structural fill is feasible, though it may be difficult during wet weather because it is sensitive to small changes in moisture content and difficult, if not impossible, to adequately compact during wet weather. Depending on the time of year construction occurs, moisture conditioning (drying or wetting) may be required in order to achieve adequate compaction. Processing (removal) of cobbles in excess of 4 inches in diameter will be required in some areas of the site and should be factored. If used as structural fill, this soil should be free of organic matter, debris, and particles larger than 4 inches. When used as structural fill, this soil should be placed in lifts with a maximum thickness of about 8 inches at moisture contents within –1 and +3 percent of optimum, and compacted to at least 100 percent of the material’s maximum dry density, as determined in general accordance with AASHTO T-99 (Standard Proctor).

8.4.1.2 Basalt (RX) Re-use of excavated basalt bedrock (RX) as structural fill is feasible, provided it can be processed (crushed, or blended with imported granular material) to achieve a fill that is fairly well graded between coarse and fine.

Page 13: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 13 of 18

The material should be prepared in conformance with that recommended for imported granular structural fill in Section 8.4.2 of this report. If the on-site soils cannot be properly moisture-conditioned and/or processed, we recommend using imported granular material for structural fill.

8.4.2 Imported Granular Structural Fill – General Use

Imported granular structural fill should consist of angular pit or quarry run rock, crushed rock, or crushed gravel that is fairly well graded between coarse and fine particle sizes. The granular fill should contain no organic matter, debris, or particles larger than 4 inches, and have less than 5 percent material passing the U.S. Standard No. 200 Sieve. For fine-grading purposes, the maximum particle size should be limited to 1½ inches. The percentage of fines can be increased to 12 percent of the material passing the U.S. Standard No. 200 Sieve if placed during dry weather, and provided the fill material is moisture-conditioned, as necessary, for proper compaction. Granular fill material should be placed in lifts with a maximum loose thickness of about 12 inches, and compacted to at least 100 percent of the material’s maximum dry density, as determined in general accordance with AASHTO T-99 (Standard Proctor). Proper moisture conditioning and the use of vibratory equipment will facilitate compaction of these materials. Compaction of granular fill materials with high percentages of particles in excess of 1½ inches should be evaluated by periodic proof-roll observation or continuous observation by the CGT geotechnical representative during fill placement, since it cannot be tested conventionally using a nuclear densometer. Such materials should be “capped” with a minimum of 12 inches of 1½-inch-minus (or finer) granular fill under all structural elements (footings, concrete slabs, etc.).

8.4.3 Trench Base Stabilization Material

If groundwater is present at the base of utility excavations, trench base stabilization material should be placed. Trench base stabilization material should consist of a minimum of 1-foot of well-graded granular material with a maximum particle size of 4 inches and less than 5 percent material passing the U.S. Standard No. 4 Sieve. The material should be free of organic matter and other deleterious material, placed in one lift, and compacted until well-keyed.

8.4.4 Trench Backfill Material

Trench backfill for the utility pipe base and pipe zone should consist of granular material as recommended by the utility pipe manufacturer. Trench backfill above the pipe zone should consist of well-graded granular material containing no organic matter or debris, have a maximum particle size of ¾ inch, and have less than 8 percent material passing the U.S. Standard No. 200 Sieve. As a guideline, trench backfill should be placed in maximum 12-inch-thick lifts. The earthwork contractor may elect to use alternative lift thicknesses based on their experience with specific equipment and fill material conditions during construction in order to achieve the required compaction. The following table presents recommended relative compaction percentages for utility trench backfill.

Page 14: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 14 of 18

Table 2 Utility Trench Backfill Compaction Recommendations

Backfill Zone Recommended Minimum Relative Compaction

Structural Areas1 Landscaping Areas

Pipe Bedding and Within Pipe Zone 92% AASHTO T-99 or pipe

manufacturer’s recommendation 90% AASHTO T-99 or pipe

manufacturer’s recommendation

Above Pipe Zone 95% AASHTO T-99 92% AASHTO T-99

Within 3 Feet of Design Subgrade 100% AASHTO T-99 95% AASHTO T-99

1Includes proposed structures, pavements, exterior hardscaping features, etc.

8.4.5 Controlled Low-Strength Material (CLSM)

CLSM is a self-compacting, cementitious material that is typically considered when backfilling localized areas. CLSM is sometimes referred to as “controlled density fill” or CDF. Due to its flowable characteristics, CLSM typically can be placed in restricted-access excavations where placing and compacting fill is difficult. If chosen for use at this site, we recommend the CLSM be in conformance with Section 00442 of the most recent, State of Oregon, Standard Specifications for Highway Construction. The geotechnical engineer’s representative should observe placement of the CLSM and obtain samples for compression testing in accordance with ASTM D4832. As a guideline, for each day’s placement, two compressive strength specimens from the same CLSM sample should be tested. The results of the two individual compressive strength tests should be averaged to obtain the reported 28-day compressive strength.

8.5 Shallow Foundations

8.5.1 Subgrade Preparation

Satisfactory subgrade support for shallow foundations associated with the planned residential structures can be obtained from the native medium dense, silty sand (SM), the basalt bedrock (RX), or structural fill that is properly placed and compacted on these materials during construction. The geotechnical engineer or his representative should be contacted to observe subgrade conditions prior to placement of forms, reinforcement steel, or structural fill (if required). If soft, loose, or otherwise unsuitable soils are encountered, they should be over-excavated as recommended by the geotechnical representative at the time of construction. The resulting over-excavation should be brought back to grade with imported granular structural fill in conformance with Section 8.4.2 this report. The maximum particle size of over-excavation backfill should be limited to 1½ inches. All granular pads for footings should be constructed a minimum of 6 inches wider on each side of the footing for every vertical foot of over-excavation. Where present, bedrock surfaces that will support foundations should be cut as level and as smooth as practical. Placement of foundation concrete on extremely rough bedrock surfaces is not recommended, particularly for continuous wall footings. Crushed rock in conformance with Section 8.4.2 of this report may be placed to serve as a leveling course where relatively smooth and level bedrock surfaces cannot be achieved during excavation.

Page 15: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 15 of 18

8.5.2 Minimum Footing Width & Embedment

Minimum footing widths should be in conformance with the most recent, Oregon Residential Structural Code (ORSC). As a guideline, we recommend individual spread footings have a minimum width of 24 inches. For one-story, light-framed structures, we recommend continuous wall footings have a minimum width of 12 inches. Similarly, for two- and three-story, light-framed structures, we recommend continuous wall footings have a minimum width of 15 and 18 inches, respectively. All footings should be founded at least 18 inches below the lowest, permanent adjacent grade.

8.5.3 Slope Setback (Lots 11 through 26)

In accordance with Section R403.1.9 of the 2014 ORSC, foundations constructed within or near descending slopes exhibiting gradients steeper than 3H:1V (horizontal:vertical) should be set back a distance equal to at least ⅓ the slope height from the slope surface. This distance should be measured between the face of the slope and the bottom, closest edge of the respective foundation. Organic topsoil and loose surface soils (if present) should not be included when determining this distance. The geotechnical engineer or his representative should be contacted to observe foundation subgrade conditions and confirm this recommended minimum setback is achieved, where applicable.

8.5.4 Bearing Pressure & Settlement

Footings founded as recommended above should be proportioned for a maximum allowable soil bearing pressure of 2,500 pounds per square foot (psf). This bearing pressure is a net bearing pressure, applies to the total of dead and long-term live loads, and may be increased by one-third when considering seismic or wind loads. For foundations founded as recommended above, total settlement of foundations is anticipated to be less than 1 inch. Differential settlements between adjacent columns and/or bearing walls should not exceed ½-inch.

8.5.5 Lateral Capacity

A maximum passive (equivalent fluid) earth pressure of 150 pounds per cubic foot (pcf) is recommended for design of footings confined by the native, silty sand (SM) or imported granular structural fill that is placed during construction. The recommended earth pressure was computed using a factor of safety of 1½, which is appropriate due to the amount of movement required to develop full passive resistance. In order to develop the above capacity, the following should be understood: 1. Concrete must be poured neat in excavations or the foundations must be backfilled with imported

granular structural fill, 2. The adjacent grade must be level, 3. The static ground water level must remain below the base of the footings throughout the year. 4. Adjacent floor slabs, pavements, or the upper 12-inch-depth of adjacent, unpaved areas should not be

considered when calculating passive resistance. An ultimate coefficient of friction equal to 0.35 may be used when calculating resistance to sliding for footings founded on the native sandy soils described above. An ultimate coefficient of friction equal to 0.45 may be used when calculating resistance to sliding for footings founded on a minimum of 6 inches of imported granular structural fill (crushed rock) that is properly placed and compacted during construction.

Page 16: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 16 of 18

8.6 Floor Slabs

8.6.1 Subgrade Preparation

Satisfactory subgrade support for slabs constructed on grade, supporting up to 150 psf area loading, can be obtained from the native, medium dense, silty sand (SM), the basalt bedrock (RX), or structural fill that is properly placed and compacted on these materials during construction. The geotechnical engineer or his representative should observe floor slab subgrade soils to evaluate surface consistencies. If soft, loose, or otherwise unsuitable soils are encountered, they should be over-excavated as recommended by the geotechnical representative at the time of construction. The resulting over-excavation should be brought back to grade with imported granular structural fill as described in Section 8.4.2 of this report.

8.6.2 Crushed Rock Base

Concrete floor slabs should be supported on a minimum 6-inch-thick layer of crushed rock (base rock). The base rock should consist of well-graded granular material (crushed rock) containing no organic matter or debris, have a maximum particle size of ¾ inch, and have less than 5 percent material passing the U.S. Standard No. 200 Sieve. Base rock should be placed in one lift and compacted to at least 95 percent of the material’s maximum dry density as determined in general accordance with AASHTO T-99 (Standard Proctor). For design cases where a vapor barrier or retarder is not placed below the slab, we recommend “choking” the surface of the base rock with fine sand just prior to concrete placement. Choking means the voids between the largest aggregate particles are filled with sand, but does not provide a layer of sand above the base rock. Choking the base rock surface reduces the lateral restraint on the bottom of the concrete during curing.

8.6.3 Design Considerations

For floor slabs constructed as recommended, a modulus of subgrade reaction of 200 pounds per cubic inch (pci) is recommended for the design of the floor slab. Floor slabs constructed as recommended will likely settle less than ½-inch. For general floor slab construction, slabs should be jointed around columns and walls to permit slabs and foundations to settle differentially.

8.6.4 Subgrade Moisture Considerations

Liquid moisture and moisture vapor should be expected at the subgrade surface. The recommended crushed rock base is anticipated to provide protection against liquid moisture. Where moisture vapor emission through the slab must be minimized, e.g. impervious floor coverings, storage of moisture sensitive materials directly on the slab surface, etc., a vapor retarding membrane or vapor barrier below the slab should be considered. Factors such as cost, special considerations for construction, floor coverings, and end use suggest that the decision regarding a vapor retarding membrane or vapor barrier be made by the architect and owner. If a vapor retarder or vapor barrier is placed below the slab, its location should be based on current American Concrete Institute (ACI) guidelines, ACI 302 Guide for Concrete Floor and Slab Construction. In some cases, this indicates placement of concrete directly on the vapor retarder or barrier. Please note that the placement of concrete directly on impervious membranes increases the risk of plastic shrinkage cracking and

Page 17: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 17 of 18

slab curling in the concrete. Construction practices to reduce or eliminate such risk, as described in ACI 302, should be employed during concrete placement.

8.7 Pavements

8.7.1 Subgrade Preparation

Satisfactory subgrade support for new pavements can be obtained from the native, medium dense, silty sand (SM), the basalt bedrock (RX), or structural fill that is properly placed and compacted on these materials during construction. Subgrade preparation of pavements should be in conformance with Section 8.1.5 of this report. Pavement subgrade surfaces should be crowned (or sloped) for proper drainage in accordance with specifications provided by the project civil engineer.

8.7.2 Design Sections

Pavement section design was not included in this assignment. At the time this report was prepared, it was our understanding pavement section design will rest with others. CGT would be pleased to provide geotechnical recommendations for design pavement sections, upon request, for an additional fee.

8.8 Additional Considerations

8.8.1 Drainage

Subsurface drains, if incorporated, should be connected to the nearest storm drain or other suitable discharge point. Paved surfaces and ground near or adjacent to the residential structures should be sloped to drain away from the structures. Surface water from paved surfaces and open spaces should be collected and routed to a suitable discharge point. Surface water should not be directed into foundation drains, if incorporated, or onto site slopes.

8.8.2 Expansive Potential

The near surface native soils consist of silty sand (SM) and basalt bedrock (RX). These materials are not considered susceptible to appreciable movements from changes in moisture content. Accordingly, no special considerations are required to mitigate expansive potential of the near surface soils at the site.

9.0 RECOMMENDED ADDITIONAL SERVICES

9.1 Design Review

Geotechnical design review is of paramount importance. CGT recommends that the geotechnical design review take place prior to releasing bid packets to contractors.

9.2 Observation of Construction

Satisfactory earthwork, pavement, and foundation performance depends to a large degree on the quality of construction. Sufficient observation of the contractor’s activities is a key part of determining that the work is completed in accordance with the construction drawings and specifications. Subsurface conditions observed during construction should be compared with those encountered during subsurface explorations, and recognition of changed conditions often requires experience. We recommend that qualified personnel visit the site with sufficient frequency to detect whether subsurface conditions change significantly from those observed to date and anticipated in this report.

Page 18: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

River Vale Bend, Oregon CGT Project Number B1707933 October 25, 2017

Carlson Geotechnical Page 18 of 18

We recommend the geotechnical engineer or their representative attend a pre-construction meeting coordinated by the contractor and/or developer. The project geotechnical engineer or their representative should provide observations and/or testing of at least the following earthwork elements during construction:

• Site Stripping & Grubbing. • Subgrade Preparation for Structural Fills, Shallow Foundations, Floor Slabs, and Pavements. • Compaction of Structural Fill and Utility Trench Backfill. • Compaction of Base Rock for Floor Slabs and Pavements. • Compaction of Asphalt Concrete for Pavements. It is imperative that the owner and/or contractor request earthwork observations and testing at a frequency sufficient to allow the geotechnical engineer to provide a final letter of compliance for the earthwork activities.

10.0 LIMITATIONS

We have prepared this report for use by the owner/developer and other members of the design and construction team for the proposed development. The opinions and recommendations contained within this report are not intended to be, nor should they be construed as a warranty of subsurface conditions, but are forwarded to assist in the planning and design process. We have made observations based on our explorations that indicate the soil conditions at only those specific locations and only to the depths penetrated. These observations do not necessarily reflect soil types, strata thickness, or water level variations that may exist between or away from our explorations. If subsurface conditions vary from those encountered in our site explorations, CGT should be alerted to the change in conditions so that we may provide additional geotechnical recommendations, if necessary. Observation by experienced geotechnical personnel should be considered an integral part of the construction process. The owner/developer is responsible for ensuring that the project designers and contractors implement our recommendations. When the design has been finalized, prior to releasing bid packets to contractors, we recommend that the design drawings and specifications be reviewed by our firm to see that our recommendations have been interpreted and implemented as intended. If design changes are made, we request that we be retained to review our conclusions and recommendations and to provide a written modification or verification. Design review and construction phase testing and observation services are beyond the scope of our current assignment, but will be provided for an additional fee. The scope of our services does not include services related to construction safety precautions, and our recommendations are not intended to direct the contractor’s methods, techniques, sequences, or procedures, except as specifically described in our report for consideration in design. Geotechnical engineering and the geologic sciences are characterized by a degree of uncertainty. Professional judgments presented in this report are based on our understanding of the proposed construction, familiarity with similar projects in the area, and on general experience. Within the limitations of scope, schedule, and budget, our services have been executed in accordance with the generally accepted practices in this area at the time this report was prepared; no warranty, expressed or implied, is made. This report is subject to review and should not be relied upon after a period of 3 years.

Page 19: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

CARLSON

GEOTECHNICAL503-601-8250

1 Inch = 2,000 feet

0 2000 4000

Scale (F8) Topo!Image by 64.23%

Site LocationFIGURE 1

Map created with ESRI ArcGIS Pro and ESRI Topographic Basemap.

Township 18 South, Range 11 East, Section 13 Willamette Meridian

SITE

Latitude: 44.012345° NorthLongitude: 121.355789° West

N

RIVER VALE - BEND, OREGONProject Number B1707933

Drafted by: DE

Page 20: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

270

CARLSON

GEOTECHNICAL503-601-8250

TP-1(6')

TP-2(7½‘)

TP-3(4½‘)

TP-4(5½‘)

Drafted by: DE

TP-5(5½‘)

TP-8(5½‘)

TP-6(3½‘)

TP-7(4½‘)

N

LEGEND

RIVER VALE - BEND, OREGONProject Number B1707933

Test pit exploration location anddepth to basalt bedrock

TP-1(X’)

0 200 400

1 Inch = 200 Feet

NOTES: Drawing based on observations made while onsite and site plans provided by client. All explorationlocations should be considered approximate.

FIGURE 2Site Plan

Page 21: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

Classification of Terms and Content

NAME: Group Name and SymbolRelative Density or ConsistencyColorMoisture ContentPlasticityOther ConstituentsOther: Grain Shape, Approximate GradationOrganics, Cement, Structure, Odor, etc.Geologic Name or Formation

USCS Grain Size<#200 (0.075 mm)

FineMediumCoarseFineCoarse

3 to 12 inches;scattered <15% estimatednumerous >15% estimated

Boulders

Relative Density or ConsistencyGranular Material Fine-Grained (cohesive) Materials

SPTN-Value Density SPT

N-ValueTorvane tsf

Shear StrengthPocket Pen tsf

Unconfined Consistency Manual Penetration Test

Thumb penetrates about 1 inch2 - 4 0.13 - 0.25 0.25 - 0.50 Soft

Difficult to indent by thumbnail>30 >2.00 >4.00 Hard

Moisture Content

Stratified: Alternating layers of material or color >6 mm thick

Plasticity Dry Strength Dilatancy Toughness

Visual-Manual Classification

CoarseGrained

Soils:More than

50% retainedon No. 200

sieve

Fine-GrainedSoils:

50% or morePasses No.200 Sieve

Gravels: 50% or moreretained onthe No. 4 sieve

Sands: More than50% passing theNo. 4 sieve

Silt and ClaysLow Plasticity Fines

Silt and ClaysHigh Plasticity Fines

CleanGravelsGravelswith FinesCleanSandsSandswith Fines

Highly Organic Soils

GW Well-graded gravels and gravel/sand mixtures, little or no finesGP Poorly-graded gravels and gravel/sand mixtures, little or no finesGM Silty gravels, gravel/sand/silt mixturesGC Clayey gravels, gravel/sand/clay mixturesSW Well-graded sands and gravelly sands, little or no finesSP Poorly-graded sands and gravelly sands, little or no finesSM Silty sands, sand/silt mixturesSC Clayey sands, sand/clay mixturesML Inorganic silts, rock flour, clayey siltsCL Inorganic clays of low to medium plasticity, gravelly clays, sandy clays, lean claysOL Organic silt and organic silty clays of low plasticityMH Inorganic silts, clayey siltsCH Inorganic clays of high plasticity, fat claysOH Organic clays of medium to high plasticityPT Peat, muck, and other highly organic soils

Thumb penetrates about ¼ inch4 - 8 0.25 - 0.50 0.50 - 1.00 Medium StiffThumb penetrates less than ¼ inch8 - 15 0.50 - 1.00 1.00 - 2.00 Stiff

Readily indented by thumbnail15 - 30 1.00 - 2.00 2.00 - 4.00 Very Stiff

Thumb penetrates more than 1 inch<2 <0.13 <0.25 Very Soft

#200 - #40 (0.425 mm)#40 - #10 (2 mm)#10 - #4 (4.75)

Sand

> 12 inches

Gravel #4 - 0.75 inch0.75 inch - 3 inches

Cobbles

Fines

0 - 4 Very Loose4 - 10 Loose

10 - 30 Medium Dense30 - 50 Dense

>50 Very Dense

Major Divisions GroupSymbols Typical Names

Structure

Homogeneous: Same color and appearance throughout

Lenses: Has small pockets of different soils, note thickness

Blocky: Cohesive soil that can be broken down into smallangular lumps which resist further breakdown

Slickensided: Striated, polished, or glossy fracture planes

Fissured: Breaks along definite fracture planes

Laminated: Alternating layers < 6 mm thick

MLCLMHCH

Non to LowLow to MediumMedium to HighMedium to High

Non to LowMedium to HighLow to Medium

High to Very High

Slow to RapidNone to SlowNone to Slow

None

Low, can’t rollMedium

Low to MediumHigh

Wet: Visible free water, likely from below water tableMoist: Leaves moisture on handDamp: Some moisture but leaves no moisture on handDry: Absence of moisture, dusty, dry to the touch

ASTM D2488 Standard Practice for Description and Identification of Soils (Visual-Manual Procedure)CARLSON

GEOTECHNICAL503-601-8250

FIGURE 3Soil Classification

RIVER VALE - BEND, OREGONProject Number B1707933

Page 22: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

Table 24: Stratification Terms

Table 22: Scale of Relative Rock Weathering

Table 23: Scale of Relative Rock Hardness

CARLSON

GEOTECHNICAL503-601-8250

Tables adapted from the 1987 Soil and Rock Classification Manual, Oregon Department of Transportation.

ODOTFIGURE 4RIVER VALE - BEND, OREGON

Project Number B1707933

Fresh

Slightly Weathered

Moderately Weathered

Predominantly Weathered

Decomposed

Crystals are bright. Discontinuities may show some minor surface staining. No discoloration in rockfabric.

Rock mass is generally fresh. Discontinuities are stained and may contain clay. Some discoloration inrock fabric. Decomposition extends up to 1-inch into rock.Rock mass is decomposed 50% or less. Significant portions of rock show discoloration and weatheringeffects. Crystals are dull and show visible chemical alteration. Discontinuities are stained and maycontain secondary mineral deposits.Rock mass is more than 50% decomposed. Rock can be excavated with geologist’s pick. Alldiscontinuities exhibit secondary mineralization. Complete discoloration of rock fabric. Surface of coreis friable and usually pitted due to washing out of highly altered minerals by drilling water.

Rock mass is completely decomposed. Original rock fabric may be evident. May be reduced to soilwith hand pressure.

Designation Field Identification

ExtremelySoft

Very Soft

Soft

MediumHard

Hard

Can be indented with difficulty by thumbnail. May be moldable or friablewith finger pressure.R0

R4

R1

R2

R3

R5

<100 psi

100-1000 psi

1000-4000 psi

4000-8000 psi

>16000 psi

Crumbles under firm blows with point of geology pick. Can be peeled bypocket knife. Scratched with finger nail.Can be peeled by pocket knife with difficulty. Cannot be scratched withfinger nail. Shallow indention made by firm blow of geology pick.Can be scratched by knife or pick. specimen can be fractured with a sin-gle firm blow of hammer/geology pick.Can be scratched with knife or pick only with difficulty. Several hardblows required to fracture specimen. 8000-16000 psi

Very Hard Cannot be scratched by knife or sharp pick. Specimen requires manyblows of hammer to fracture or chip. Hammer rebounds after impact.

Term Field IdentificationHardnessDesignation

Approximate UnconfinedCompressive Strength

Laminations

Fissle

Parting

Foliation

Thin beds (<1cm)

Tendency to break along laminations

Tendency to break parallel to bedding, any scale

Non-depositional, e.g., segregation and layering of mineralsin metamorphic rock

Term Characteristics

Page 23: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

GRAB1

SILTY SAND TOPSOIL WITH GRAVEL: Loose,brown, damp, fine- to medium-grained sand,subangular gravel up to 1 inch diameter.SILTY SAND WITH GRAVEL: Medium dense,brown, damp, fine- to medium-grained sand,subangular gravel up to 3 inches in diameter,some roots to ½ inch diameter.

No roots below 5 feet bgs.

BASALT: Hard (R4), gray, fresh.• Test pit terminated at 6 feet bgs due to practicalrefusal on basalt.• No groundwater or caving observed.• Test pit loosely backfilled with excavatedmaterials upon completion.

SM

SM

RX

LOGGED BY TRF

GROUND ELEVATION 3848 ft ELEVATION DATUM Mean Sea LevelDATE STARTED 9/25/17

SEEPAGE None

GROUNDWATER AT END None

GROUNDWATER AFTER EXCAVATION None

REVIEWED BY BMW

EXCAVATION METHOD 2-foot toothed bucket

EQUIPMENT Takeuchi TB 260

EXCAVATION CONTRACTOR Terry Shine Excavating

WEATHER Mostly Clear SURFACE Soil

FIGURE 5

RE

CO

VE

RY

%(R

QD

)

SA

MP

LE T

YP

EN

UM

BE

R

PO

CK

ET

PE

N.

(tsf

)

DR

Y U

NIT

WT

.(p

cf)

DE

PT

H(f

t)

0

2

4

6

MC20 40 60 80

PL LL

PAGE 1 OF 1

Test Pit TP-1G

RA

PH

ICLO

G

WDCP N60 VALUE 20 40 60 80

MATERIAL DESCRIPTION

WD

CP

N60

VA

LUE

GR

OU

ND

WA

TE

R

ELE

VA

TIO

N(f

t)

3846

3844

3842

3840

3838

FINES CONTENT (%) 20 40 60 800 100G

RO

UP

SY

MB

OL

PROJECT NAME River Vale

PROJECT LOCATION River Rim Drive, Bend, Oregon

CLIENT Pahlisch Homes

PROJECT NUMBER B1707933

Carlson Geotechnical7185 SW Sandburg Street, Suite 200Tigard, Oregon 97281(503) 601-8250www.carlsontesting.com

CG

T E

XP

LOR

AT

ION

WIT

H W

DC

P B

1707

933.

GP

J 1

0/26

/17

DR

AF

TE

D B

Y: D

E

7

15

Page 24: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

GRAB1

SILTY SAND TOPSOIL WITH GRAVEL: Loose,brown, damp, fine- to medium-grained sand,subangular gravel up to 1 inch diameter.SILTY SAND WITH GRAVEL: Medium dense,brown, damp, fine- to medium-grained sand,subangular gravel up to 1 inch in diameter.

Isolated cobbles up to 12 inches in diameter.

BASALT: Hard (R4), gray, fresh.• Test pit terminated at 7½ feet bgs due to practicalrefusal on basalt.• No groundwater or caving observed.• Test pit loosely backfilled with excavatedmaterials upon completion.

SM

SM

RX

LOGGED BY TRF

GROUND ELEVATION 3849 ft ELEVATION DATUM Mean Sea LevelDATE STARTED 9/25/17

SEEPAGE None

GROUNDWATER AT END None

GROUNDWATER AFTER EXCAVATION None

REVIEWED BY BMW

EXCAVATION METHOD 2-foot toothed bucket

EQUIPMENT Takeuchi TB 260

EXCAVATION CONTRACTOR Terry Shine Excavating

WEATHER Mostly Clear SURFACE Soil

FIGURE 6

RE

CO

VE

RY

%(R

QD

)

SA

MP

LE T

YP

EN

UM

BE

R

PO

CK

ET

PE

N.

(tsf

)

DR

Y U

NIT

WT

.(p

cf)

DE

PT

H(f

t)

0

2

4

6

MC20 40 60 80

PL LL

PAGE 1 OF 1

Test Pit TP-2G

RA

PH

ICLO

G

WDCP N60 VALUE 20 40 60 80

MATERIAL DESCRIPTION

WD

CP

N60

VA

LUE

GR

OU

ND

WA

TE

R

ELE

VA

TIO

N(f

t)

3848

3846

3844

3842

3840

FINES CONTENT (%) 20 40 60 800 100G

RO

UP

SY

MB

OL

PROJECT NAME River Vale

PROJECT LOCATION River Rim Drive, Bend, Oregon

CLIENT Pahlisch Homes

PROJECT NUMBER B1707933

Carlson Geotechnical7185 SW Sandburg Street, Suite 200Tigard, Oregon 97281(503) 601-8250www.carlsontesting.com

CG

T E

XP

LOR

AT

ION

WIT

H W

DC

P B

1707

933.

GP

J 1

0/26

/17

DR

AF

TE

D B

Y: D

E

6

Page 25: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

GRAB1

SILTY SAND TOPSOIL WITH GRAVEL: Loose,brown, damp, fine- to medium-grained sand,subangular gravel up to 1 inch diameter.SILTY SAND WITH GRAVEL: Medium dense,brown, damp, fine- to medium-grained sand,subangular gravel up to 1 inch in diameter.

Isolated cobbles up to 12 inches in diameter.

BASALT: Hard (R4), gray, fresh.• Test pit terminated at 4½ feet bgs due to practicalrefusal on basalt.• No groundwater or caving observed.• Test pit loosely backfilled with excavatedmaterials upon completion.

SM

SM

RX

LOGGED BY TRF

GROUND ELEVATION 3851 ft ELEVATION DATUM Mean Sea LevelDATE STARTED 9/25/17

SEEPAGE None

GROUNDWATER AT END None

GROUNDWATER AFTER EXCAVATION None

REVIEWED BY BMW

EXCAVATION METHOD 2-foot toothed bucket

EQUIPMENT Takeuchi TB 260

EXCAVATION CONTRACTOR Terry Shine Excavating

WEATHER Mostly Clear SURFACE Soil

FIGURE 7

RE

CO

VE

RY

%(R

QD

)

SA

MP

LE T

YP

EN

UM

BE

R

PO

CK

ET

PE

N.

(tsf

)

DR

Y U

NIT

WT

.(p

cf)

DE

PT

H(f

t)

0

2

4

MC20 40 60 80

PL LL

PAGE 1 OF 1

Test Pit TP-3G

RA

PH

ICLO

G

WDCP N60 VALUE 20 40 60 80

MATERIAL DESCRIPTION

WD

CP

N60

VA

LUE

GR

OU

ND

WA

TE

R

ELE

VA

TIO

N(f

t)

3850

3848

3846

3844

3842

FINES CONTENT (%) 20 40 60 800 100G

RO

UP

SY

MB

OL

PROJECT NAME River Vale

PROJECT LOCATION River Rim Drive, Bend, Oregon

CLIENT Pahlisch Homes

PROJECT NUMBER B1707933

Carlson Geotechnical7185 SW Sandburg Street, Suite 200Tigard, Oregon 97281(503) 601-8250www.carlsontesting.com

CG

T E

XP

LOR

AT

ION

WIT

H W

DC

P B

1707

933.

GP

J 1

0/26

/17

DR

AF

TE

D B

Y: D

E

7

Page 26: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

GRAB1

SILTY SAND TOPSOIL: Loose, brown, damp,fine- to medium-grained sand.

SILTY SAND WITH GRAVEL: Medium dense,brown, damp, fine- to medium-grained sand,subangular gravel up to 2 inches in diameter.

Isolated cobbles up to 12 inches in diameter.

BASALT: Hard (R4), gray, fresh.• Test pit terminated at 5½ feet bgs due to practicalrefusal on basalt.• No groundwater or caving observed.• Test pit loosely backfilled with excavatedmaterials upon completion.

SM

SM

RX

LOGGED BY TRF

GROUND ELEVATION 3861 ft ELEVATION DATUM Mean Sea LevelDATE STARTED 9/25/17

SEEPAGE None

GROUNDWATER AT END None

GROUNDWATER AFTER EXCAVATION None

REVIEWED BY BMW

EXCAVATION METHOD 2-foot toothed bucket

EQUIPMENT Takeuchi TB 260

EXCAVATION CONTRACTOR Terry Shine Excavating

WEATHER Mostly Clear SURFACE Soil

FIGURE 8

RE

CO

VE

RY

%(R

QD

)

SA

MP

LE T

YP

EN

UM

BE

R

PO

CK

ET

PE

N.

(tsf

)

DR

Y U

NIT

WT

.(p

cf)

DE

PT

H(f

t)

0

2

4

MC20 40 60 80

PL LL

PAGE 1 OF 1

Test Pit TP-4G

RA

PH

ICLO

G

WDCP N60 VALUE 20 40 60 80

MATERIAL DESCRIPTION

WD

CP

N60

VA

LUE

GR

OU

ND

WA

TE

R

ELE

VA

TIO

N(f

t)

3860

3858

3856

3854

3852

FINES CONTENT (%) 20 40 60 800 100G

RO

UP

SY

MB

OL

PROJECT NAME River Vale

PROJECT LOCATION River Rim Drive, Bend, Oregon

CLIENT Pahlisch Homes

PROJECT NUMBER B1707933

Carlson Geotechnical7185 SW Sandburg Street, Suite 200Tigard, Oregon 97281(503) 601-8250www.carlsontesting.com

CG

T E

XP

LOR

AT

ION

WIT

H W

DC

P B

1707

933.

GP

J 1

0/26

/17

DR

AF

TE

D B

Y: D

E

8

Page 27: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

GRAB1

SILTY SAND TOPSOIL: Loose, brown, damp,fine- to medium-grained sand.

SILTY SAND WITH GRAVEL: Medium dense,brown, damp, fine- to medium-grained sand,subangular gravel up to 1 inch in diameter, someroots up to ½ inch diameter.

Isolated cobbles up to 12 inches in diameter.

BASALT: Hard (R4), gray, fresh.• Test pit terminated at 5½ feet bgs due to practicalrefusal on basalt.• No groundwater or caving observed.• Test pit loosely backfilled with excavatedmaterials upon completion.

SM

SM

RX

LOGGED BY TRF

GROUND ELEVATION 3859 ft ELEVATION DATUM Mean Sea LevelDATE STARTED 9/25/17

SEEPAGE None

GROUNDWATER AT END None

GROUNDWATER AFTER EXCAVATION None

REVIEWED BY BMW

EXCAVATION METHOD 2-foot toothed bucket

EQUIPMENT Takeuchi TB 260

EXCAVATION CONTRACTOR Terry Shine Excavating

WEATHER Mostly Clear SURFACE Soil

FIGURE 9

RE

CO

VE

RY

%(R

QD

)

SA

MP

LE T

YP

EN

UM

BE

R

PO

CK

ET

PE

N.

(tsf

)

DR

Y U

NIT

WT

.(p

cf)

DE

PT

H(f

t)

0

2

4

MC20 40 60 80

PL LL

PAGE 1 OF 1

Test Pit TP-5G

RA

PH

ICLO

G

WDCP N60 VALUE 20 40 60 80

MATERIAL DESCRIPTION

WD

CP

N60

VA

LUE

GR

OU

ND

WA

TE

R

ELE

VA

TIO

N(f

t)

3858

3856

3854

3852

3850

FINES CONTENT (%) 20 40 60 800 100G

RO

UP

SY

MB

OL

PROJECT NAME River Vale

PROJECT LOCATION River Rim Drive, Bend, Oregon

CLIENT Pahlisch Homes

PROJECT NUMBER B1707933

Carlson Geotechnical7185 SW Sandburg Street, Suite 200Tigard, Oregon 97281(503) 601-8250www.carlsontesting.com

CG

T E

XP

LOR

AT

ION

WIT

H W

DC

P B

1707

933.

GP

J 1

0/26

/17

DR

AF

TE

D B

Y: D

E

8

18

Page 28: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

GRAB1

SILTY SAND TOPSOIL: Loose, brown, damp,fine- to medium-grained sand.

SILTY SAND WITH GRAVEL: Medium dense,brown, damp, fine- to medium-grained sand,subangular gravel up to 1 inch in diameter.

BASALT: Hard (R4), gray, fresh.• Test pit terminated at 3½ feet bgs due to practicalrefusal on basalt.• No groundwater or caving observed.• Test pit loosely backfilled with excavatedmaterials upon completion.

SM

SM

RX

LOGGED BY TRF

GROUND ELEVATION 3868 ft ELEVATION DATUM Mean Sea LevelDATE STARTED 9/25/17

SEEPAGE None

GROUNDWATER AT END None

GROUNDWATER AFTER EXCAVATION None

REVIEWED BY BMW

EXCAVATION METHOD 2-foot toothed bucket

EQUIPMENT Takeuchi TB 260

EXCAVATION CONTRACTOR Terry Shine Excavating

WEATHER Mostly Clear SURFACE Soil

FIGURE 10

RE

CO

VE

RY

%(R

QD

)

SA

MP

LE T

YP

EN

UM

BE

R

PO

CK

ET

PE

N.

(tsf

)

DR

Y U

NIT

WT

.(p

cf)

DE

PT

H(f

t)

0

2

MC20 40 60 80

PL LL

PAGE 1 OF 1

Test Pit TP-6G

RA

PH

ICLO

G

WDCP N60 VALUE 20 40 60 80

MATERIAL DESCRIPTION

WD

CP

N60

VA

LUE

GR

OU

ND

WA

TE

R

ELE

VA

TIO

N(f

t)

3866

3864

3862

3860

3858

FINES CONTENT (%) 20 40 60 800 100G

RO

UP

SY

MB

OL

PROJECT NAME River Vale

PROJECT LOCATION River Rim Drive, Bend, Oregon

CLIENT Pahlisch Homes

PROJECT NUMBER B1707933

Carlson Geotechnical7185 SW Sandburg Street, Suite 200Tigard, Oregon 97281(503) 601-8250www.carlsontesting.com

CG

T E

XP

LOR

AT

ION

WIT

H W

DC

P B

1707

933.

GP

J 1

0/26

/17

DR

AF

TE

D B

Y: D

E

9

29

Page 29: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

GRAB1

SILTY SAND TOPSOIL: Loose, brown, damp,fine- to medium-grained sand.

SILTY SAND WITH GRAVEL: Medium dense,brown, damp, fine- to medium-grained sand,subangular gravel up to 1 inch in diameter.

BASALT: Hard (R4), gray, fresh.• Test pit terminated at 4½ feet bgs due to practicalrefusal on basalt.• No groundwater or caving observed.• Test pit loosely backfilled with excavatedmaterials upon completion.

SM

SM

RX

LOGGED BY TRF

GROUND ELEVATION 3865 ft ELEVATION DATUM Mean Sea LevelDATE STARTED 9/25/17

SEEPAGE None

GROUNDWATER AT END None

GROUNDWATER AFTER EXCAVATION None

REVIEWED BY BMW

EXCAVATION METHOD 2-foot toothed bucket

EQUIPMENT Takeuchi TB 260

EXCAVATION CONTRACTOR Terry Shine Excavating

WEATHER Mostly Clear SURFACE Soil

FIGURE 11

RE

CO

VE

RY

%(R

QD

)

SA

MP

LE T

YP

EN

UM

BE

R

PO

CK

ET

PE

N.

(tsf

)

DR

Y U

NIT

WT

.(p

cf)

DE

PT

H(f

t)

0

2

4

MC20 40 60 80

PL LL

PAGE 1 OF 1

Test Pit TP-7G

RA

PH

ICLO

G

WDCP N60 VALUE 20 40 60 80

MATERIAL DESCRIPTION

WD

CP

N60

VA

LUE

GR

OU

ND

WA

TE

R

ELE

VA

TIO

N(f

t)

3864

3862

3860

3858

3856

FINES CONTENT (%) 20 40 60 800 100G

RO

UP

SY

MB

OL

PROJECT NAME River Vale

PROJECT LOCATION River Rim Drive, Bend, Oregon

CLIENT Pahlisch Homes

PROJECT NUMBER B1707933

Carlson Geotechnical7185 SW Sandburg Street, Suite 200Tigard, Oregon 97281(503) 601-8250www.carlsontesting.com

CG

T E

XP

LOR

AT

ION

WIT

H W

DC

P B

1707

933.

GP

J 1

0/26

/17

DR

AF

TE

D B

Y: D

E

9

Page 30: Carlson Geotechnical Bend Office (541) 330-9155 Eugene ...€¦ · Laboratory testing included - moisture content determinations (ASTM eight D2216) and threepercentage passing th

GRAB1

SILTY SAND TOPSOIL: Loose, brown, damp,fine- to medium-grained sand.

SILTY SAND WITH GRAVEL: Medium dense,brown, damp, fine- to medium-grained sand,subangular gravel up to 1 inch in diameter.

Isolated cobbles up to 12 inches in diameter.

BASALT: Hard (R4), gray, fresh.• Test pit terminated at 5½ feet bgs due to practicalrefusal on basalt.• No groundwater or caving observed.• Test pit loosely backfilled with excavatedmaterials upon completion.

SM

SM

RX

LOGGED BY TRF

GROUND ELEVATION 3867 ft ELEVATION DATUM Mean Sea LevelDATE STARTED 9/25/17

SEEPAGE None

GROUNDWATER AT END None

GROUNDWATER AFTER EXCAVATION None

REVIEWED BY BMW

EXCAVATION METHOD 2-foot toothed bucket

EQUIPMENT Takeuchi TB 260

EXCAVATION CONTRACTOR Terry Shine Excavating

WEATHER Mostly Clear SURFACE Soil

FIGURE 12

RE

CO

VE

RY

%(R

QD

)

SA

MP

LE T

YP

EN

UM

BE

R

PO

CK

ET

PE

N.

(tsf

)

DR

Y U

NIT

WT

.(p

cf)

DE

PT

H(f

t)

0

2

4

MC20 40 60 80

PL LL

PAGE 1 OF 1

Test Pit TP-8G

RA

PH

ICLO

G

WDCP N60 VALUE 20 40 60 80

MATERIAL DESCRIPTION

WD

CP

N60

VA

LUE

GR

OU

ND

WA

TE

R

ELE

VA

TIO

N(f

t)

3866

3864

3862

3860

3858

FINES CONTENT (%) 20 40 60 800 100G

RO

UP

SY

MB

OL

PROJECT NAME River Vale

PROJECT LOCATION River Rim Drive, Bend, Oregon

CLIENT Pahlisch Homes

PROJECT NUMBER B1707933

Carlson Geotechnical7185 SW Sandburg Street, Suite 200Tigard, Oregon 97281(503) 601-8250www.carlsontesting.com

CG

T E

XP

LOR

AT

ION

WIT

H W

DC

P B

1707

933.

GP

J 1

0/26

/17

DR

AF

TE

D B

Y: D

E

7